2. Which of the following is not considered a leadership action?
A. Influencing the performance of the team and the project
B. Monitoring the performance of the team and the project
C. Controlling the performance of the team and the project
D. Prioritizing efforts
HINT: The key is understanding the difference between managing and leading a project.
QUESTION:
3. The correct answer is C.
Throughout the project, the project team leaders are responsible for influencing, mentoring, monitoring,
and evaluating the performance of the team and the project. Controlling the performance of the team
and the project is not a specific leadership activity of project team leaders and is actually considered more
of a managing activity than a leading activity. Remember, leadership is about self-direction, while
management is about control.
ANSWER:
4. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.