Presentation on Procurement of
1) IFMIS
2) RMS &
3) PM Consultancy
Key
Parameters
RMS IFMIS
Project
Duration
4.5 Years
Implementation -1.5 Yr,
Support Extension 3 Yrs.)
5 Years
Implementation -2 Yrs,
Support Extension 3 Yrs.
Geographical
Coverage
20-25 Locations
(Kathmandu and nearby)
All offices of NEA
Functional
Coverage
IFMIS
• Financial Management
• Asset Management
• Inventory Management
• Payroll
• Project Accounting
• Employee Claims &
Retirement Benefits
IFMIS and RMS
• Financial Management
• Asset Management
• Inventory Management
• Payroll
• Human Resource
Management System
• Project Accounting
• Metering
• Billing and Collection
• Energy Audit
2
Scope of Work (RMS & IFMIS)
3
RMS: Scope of Work
 Supply, delivery, design, customization, integration,
implementation, testing, commissioning of Hardware/ software of
the RMS with FMS, including Data Migration & Change
Management and Capacity Building.
 COTS database, Middleware, Network and customer care
equipment and other software in conformance to Industry
standards and installation & maintenance of necessary
infrastructure (at DC &DR).
 Total period of contract is 4.5 years (1.5yrs for Implementation &
FMS and 3yrs for support.) During the FMS period, the SI shall
provide manpower &technical support services.
4
RMS: Key Considerations
 Software License for 6 million consumers. (5.08m, 8%,3%,3%,3%)
 Annual Technical Services (ATS) are computed @ 22% of the RMS
License Cost per year.
 Hardware Infrastructure requirements for DC and DRC
 Annual Maintenance Cost (AMC) @ 10% of HW Cost per year.
 Capacity Building : 700 RMS Users, 14 Executive Users (Abroad).
 FMS: Man-month Rate : Same till Go-Live, 10% Y-o-Y thereafter.
5
RMS: Modules
Major Modules FRS Count
1. Metering 21
2. Billing 55
3. Collection 18
4. New Connection, Disconnection & Reconnection 50
5. Energy Audit 7
Supporting Modules
6 Management information System (MIS) 12
7. Document Management System (DMS) 13
8. Customer Relationship Management (CRM) 48
9. Web Portal and Mobile Application 19
10. Customer Care Centre (CCC)
6
RMS: Project Timeline
Project Activities M01 M02 M03 M04 M05 M06 M07 M08 M09 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19
Project Initiation
Business Blueprinting
Design & Customization
Data Migration
IT infra setup for DC , DRC & CCC
Pilot Rollout
Training and Change Management
Enterprise wide roll out
Stabilization Support
FMS 3 Yrs
7
RMS: Eligibility Qualification Criteria
Scoring Matrix
SI’s Strength Product OEM’s Strength
RMS Implementation 60 15
Team Composition 10
Approach and Methodology 15
Totals 85 15
Technical Qualifying Score = 60%
Weight for the Bid Price as specified in BDS = 40%
Weight of the Bid Technical score = 60%
Compliance to the Functional Requirement Specifications (FRS) mentioned in the RFP for major modules as
standard is 85% . Less than 85% shall be termed as non-responsive.
8
IFMIS: Scope of work
 Supply, delivery, design, customization, integration,
implementation, testing, commissioning of Hardware/ software of
the IFMIS with FMS, including Data Migration & Change
Management and Capacity Building.
 COTS database, Middleware, Network and customer care
equipment and other software in conformance to Industry
standards and installation & maintenance of necessary
infrastructure (at DC &DR).
 Total period of contract is 5 years (2yrs for Implementation &
FMS and 3yrs for support.) During the FMS period, the SI shall
provide manpower & technical support services.
9
IFMIS: Key Considerations
 Software License for 1600 full enterprise users. Additional 400.
 Annual Technical Services (ATS) are computed @ 22% of the
IFMIS License Cost per year.
 Hardware Infrastructure requirements for DC and DRC
 Annual Maintenance Cost (AMC) @ 10% of HW Cost per year.
 Capacity Building : 2000 Users, 15 Executive Users (Abroad).
 FMS: Man-month Rate : Same till Go-Live, 10% Y-o-Y thereafter.
10
IFMIS: Project Timeline
Project Activities M01 M02 M03 M04 M05 M06 M07 M08 M09 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25
Project Initiation
Business Blueprinting
Design & Customization
Data Migration
IT infra setup for DC , DRC & CCC
Pilot Rollout
Training and Change Management
Enterprise wide roll out
Stabilization Support
FMS 3 Yrs
11
Recommendation
• The extension cost initial quoted, Final
revised and EY estimated = 1.66
• Recommendation from EY to float the RFP
with 3 years extension.
• Extension of 3 years has been considered
with a perception to take over the FMS by
NEA IT team.
12
IFMIS: Modules
Major Modules FRS Count
1. Financial Management 697
2. Material Management 259
3. Human Resource Management 496
4. Project Management 227
5. Maintenance Management 515
6. Production Planning 96
Supporting Modules
6 Linear Asset Management 11
7. Document and File Management 90
8. BI & BW 35
9. Mobile Application 80
10.
Employee Self Services (ESS) & Manager Self Services
(MSS)
87
13
IFMIS: Eligibility Qualification Criteria
Scoring Matrix
SI’s Strength Product OEM’s Strength
IFMIS Implementation 55 Product’s Credentials 15
Team Composition 10 Proof of the Strength of the Product 5
Approach and Methodology 15
Totals 80 20
Technical Qualifying Score = 60%
Weight for the Bid Price as specified in BDS = 40%
Weight of the Bid Technical score = 60%
Compliance to the Functional Requirement Specifications (FRS) mentioned in the RFP for major modules as
standard is 85% . Less than 85% shall be termed as non-responsive.
14
Project Management Consultant
 Expression of Interest (EoI) and Terms of Reference (ToR)
published
 Fourteen International Firms submitted the EoI
 Committee Shortlisted 6 Firms
 RFP to be finalized and submitted to ADB
 Budget approved was 1 million USD and approved was 0.8
million USD excluding applicable taxes and VAT in Nepal.
15
Recommendations Expected–1
 Team Composition:
RMS: Provincial Managers - Bachelor Degree in Electrical/ Electronics/ IT/
Computer Science or related fields and 5 years of experience on RMS
implementation.
IFMIS: Assistant Project Manager - Bachelor Degree in Electrical/ Electronics/ IT/
Computer Science or related fields and 5 years of experience on IFMIS
implementation.
Provincial Managers and Assistant Project Managers are to be deputed from in-
house.
 Evaluation of CVs
RMS: Evaluation of CVs of Project Manager and Provincial Managers only.
IFMIS: Evaluation of Project Manager and Assistant Project Managers only.
CVs of the Key Experts are to be evaluated.
 PQ: The proposed product should be of latest version and the OEM should have a future
Roadmap - for IFMIS required for the next 10 (ten) years and for RMS required for the
16
Recommendations Expected–2
 Technical Score QCBS Requirement :
Minimum Technical Score Required: 60% (IFMIS and RMS)
IFMIS: 60% –30%
RMS: 70% –30%
 ERP Professional User License Requirement
NEA’s License Requirement = 1600
Requirement in PQ/TQ: 300
Bring Down it in PQ/TQ to 200
 Confirmation on Extension period to be considered
17
Recommendations Expected–3
 Potential bidders pool is same for all the three procurements.
 Bidders from the Consultants category such as PwC, Deloitte
and KPMG also fulfill the PQ and TQ criteria set for SIs of
both the procurements.
 All the bidders will be allowed to participate in all the three
tenders.
 Selection of the top three PMC consultants will be done.
 If the bidder selected for consultant also gets selected as SI in
either or both of the procurements, then the bidder has to
work as the SI for NEA.
 This condition is to be included in the RFP for PMC.
18
Recommendations Expected–4
 ToR clearly stating the Scope of Work of the Consultant EY
 Deputed by ADB upon request from NEA
 Need the support from the consultant in bid process
management
 Approach and Methodology evaluation required expert
recommendation
19
Thank You

Mais conteúdo relacionado

Semelhante a ERP Scope, Procurement and Implementation

MRM-16 (2020).pptx
MRM-16 (2020).pptxMRM-16 (2020).pptx
MRM-16 (2020).pptx
xego1
 
T. Kiran
T. KiranT. Kiran
Making the Business Case for Remote Service Capabilities
Making the Business Case for Remote Service CapabilitiesMaking the Business Case for Remote Service Capabilities
Making the Business Case for Remote Service Capabilities
PTC
 
Manufacturing Competitiveness Enhancement Program
Manufacturing Competitiveness Enhancement ProgramManufacturing Competitiveness Enhancement Program
Manufacturing Competitiveness Enhancement Program
Durban Chamber of Commerce and Industry
 
Edcil Techncial PPT_V1.0.pptx
Edcil Techncial PPT_V1.0.pptxEdcil Techncial PPT_V1.0.pptx
Edcil Techncial PPT_V1.0.pptx
AshokKumar705948
 
SIAM Study - Comparing the Introduction of New IT Services via Simple and Com...
SIAM Study - Comparing the Introduction of New IT Services via Simple and Com...SIAM Study - Comparing the Introduction of New IT Services via Simple and Com...
SIAM Study - Comparing the Introduction of New IT Services via Simple and Com...
Ken Blunt
 
Ayan Kar
Ayan KarAyan Kar
Ayan Kar
Ayan Kar
 
Career Snapshot
Career SnapshotCareer Snapshot
Career Snapshot
Ayan Kar
 
Strategic Partnership for Rail IT Engagement
Strategic Partnership for Rail IT EngagementStrategic Partnership for Rail IT Engagement
Strategic Partnership for Rail IT Engagement
Tim Groenwals
 
Experience Snap Shot Presentation (Design 3)
Experience Snap Shot Presentation (Design 3)Experience Snap Shot Presentation (Design 3)
Experience Snap Shot Presentation (Design 3)
rdebgupta
 
Whole life performance lecture south bank university
Whole life performance lecture   south bank universityWhole life performance lecture   south bank university
Whole life performance lecture south bank university
Kim Newman
 
Sanjeev Thakur_April'16
Sanjeev Thakur_April'16Sanjeev Thakur_April'16
Sanjeev Thakur_April'16
Sanjeev Thakur
 
Rajeswaran_CV_04042016
Rajeswaran_CV_04042016Rajeswaran_CV_04042016
Rajeswaran_CV_04042016
Rajeswaran Rajendran
 
Warehouse1.pptx
Warehouse1.pptxWarehouse1.pptx
Warehouse1.pptx
SPANDANPATIL1
 
John Resume latest
John Resume latestJohn Resume latest
John Resume latest
John Jubilee
 
CGI Legacy Application Transformation
CGI Legacy Application TransformationCGI Legacy Application Transformation
CGI Legacy Application Transformation
mgrahlman
 
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery CenterFundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
ScottMadden, Inc.
 
Is On-Demand SPM Right For Your Company?
Is On-Demand SPM Right For Your Company?Is On-Demand SPM Right For Your Company?
Is On-Demand SPM Right For Your Company?
Callidus Software
 
FINAL TRAFOS
FINAL TRAFOSFINAL TRAFOS
FINAL TRAFOS
ankitbisht1992
 
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
Cisco Canada
 

Semelhante a ERP Scope, Procurement and Implementation (20)

MRM-16 (2020).pptx
MRM-16 (2020).pptxMRM-16 (2020).pptx
MRM-16 (2020).pptx
 
T. Kiran
T. KiranT. Kiran
T. Kiran
 
Making the Business Case for Remote Service Capabilities
Making the Business Case for Remote Service CapabilitiesMaking the Business Case for Remote Service Capabilities
Making the Business Case for Remote Service Capabilities
 
Manufacturing Competitiveness Enhancement Program
Manufacturing Competitiveness Enhancement ProgramManufacturing Competitiveness Enhancement Program
Manufacturing Competitiveness Enhancement Program
 
Edcil Techncial PPT_V1.0.pptx
Edcil Techncial PPT_V1.0.pptxEdcil Techncial PPT_V1.0.pptx
Edcil Techncial PPT_V1.0.pptx
 
SIAM Study - Comparing the Introduction of New IT Services via Simple and Com...
SIAM Study - Comparing the Introduction of New IT Services via Simple and Com...SIAM Study - Comparing the Introduction of New IT Services via Simple and Com...
SIAM Study - Comparing the Introduction of New IT Services via Simple and Com...
 
Ayan Kar
Ayan KarAyan Kar
Ayan Kar
 
Career Snapshot
Career SnapshotCareer Snapshot
Career Snapshot
 
Strategic Partnership for Rail IT Engagement
Strategic Partnership for Rail IT EngagementStrategic Partnership for Rail IT Engagement
Strategic Partnership for Rail IT Engagement
 
Experience Snap Shot Presentation (Design 3)
Experience Snap Shot Presentation (Design 3)Experience Snap Shot Presentation (Design 3)
Experience Snap Shot Presentation (Design 3)
 
Whole life performance lecture south bank university
Whole life performance lecture   south bank universityWhole life performance lecture   south bank university
Whole life performance lecture south bank university
 
Sanjeev Thakur_April'16
Sanjeev Thakur_April'16Sanjeev Thakur_April'16
Sanjeev Thakur_April'16
 
Rajeswaran_CV_04042016
Rajeswaran_CV_04042016Rajeswaran_CV_04042016
Rajeswaran_CV_04042016
 
Warehouse1.pptx
Warehouse1.pptxWarehouse1.pptx
Warehouse1.pptx
 
John Resume latest
John Resume latestJohn Resume latest
John Resume latest
 
CGI Legacy Application Transformation
CGI Legacy Application TransformationCGI Legacy Application Transformation
CGI Legacy Application Transformation
 
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery CenterFundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
 
Is On-Demand SPM Right For Your Company?
Is On-Demand SPM Right For Your Company?Is On-Demand SPM Right For Your Company?
Is On-Demand SPM Right For Your Company?
 
FINAL TRAFOS
FINAL TRAFOSFINAL TRAFOS
FINAL TRAFOS
 
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
An Oversight or a New Customer Phenomenon, Getting the Most of your Contact C...
 

Mais de Roshni814224

Ecommerce concepts and uses in Business.pptx
Ecommerce concepts and uses in Business.pptxEcommerce concepts and uses in Business.pptx
Ecommerce concepts and uses in Business.pptx
Roshni814224
 
Emerging Global Trends in Internet of Things.pptx
Emerging Global Trends in Internet of Things.pptxEmerging Global Trends in Internet of Things.pptx
Emerging Global Trends in Internet of Things.pptx
Roshni814224
 
Emerging IT Trends and Innovation Concepts.pptx
Emerging IT Trends and Innovation Concepts.pptxEmerging IT Trends and Innovation Concepts.pptx
Emerging IT Trends and Innovation Concepts.pptx
Roshni814224
 
Introduction to E-Commerce and Components.pptx
Introduction to E-Commerce and Components.pptxIntroduction to E-Commerce and Components.pptx
Introduction to E-Commerce and Components.pptx
Roshni814224
 
Business Information Systems in firms.pptx
Business Information Systems in firms.pptxBusiness Information Systems in firms.pptx
Business Information Systems in firms.pptx
Roshni814224
 
Strategic Information System in Business Firm.ppt
Strategic Information System in Business Firm.pptStrategic Information System in Business Firm.ppt
Strategic Information System in Business Firm.ppt
Roshni814224
 
Management Information System Applications.pptx
Management Information System Applications.pptxManagement Information System Applications.pptx
Management Information System Applications.pptx
Roshni814224
 
The Concepts of Internet and Networking.pptx
The Concepts of Internet and Networking.pptxThe Concepts of Internet and Networking.pptx
The Concepts of Internet and Networking.pptx
Roshni814224
 
Integrity Constraints in Database Management System.ppt
Integrity Constraints in Database Management System.pptIntegrity Constraints in Database Management System.ppt
Integrity Constraints in Database Management System.ppt
Roshni814224
 
Data models in Database Management Systems.ppt
Data models in Database Management Systems.pptData models in Database Management Systems.ppt
Data models in Database Management Systems.ppt
Roshni814224
 
Transaction Management, Recovery and Query Processing.pptx
Transaction Management, Recovery and Query Processing.pptxTransaction Management, Recovery and Query Processing.pptx
Transaction Management, Recovery and Query Processing.pptx
Roshni814224
 
Computer System Software Component Details.pptx
Computer System Software Component Details.pptxComputer System Software Component Details.pptx
Computer System Software Component Details.pptx
Roshni814224
 
Social Engineering and Identity Theft.pptx
Social Engineering and Identity Theft.pptxSocial Engineering and Identity Theft.pptx
Social Engineering and Identity Theft.pptx
Roshni814224
 
Cyber Security and Data Privacy in Information Systems.pptx
Cyber Security and Data Privacy in Information Systems.pptxCyber Security and Data Privacy in Information Systems.pptx
Cyber Security and Data Privacy in Information Systems.pptx
Roshni814224
 
Information Systems, Organizations and Strategy.pptx
Information Systems, Organizations and Strategy.pptxInformation Systems, Organizations and Strategy.pptx
Information Systems, Organizations and Strategy.pptx
Roshni814224
 
Information Systems in Global Business Today.pptx
Information Systems in Global Business Today.pptxInformation Systems in Global Business Today.pptx
Information Systems in Global Business Today.pptx
Roshni814224
 
Applications of Management Information System.pptx
Applications of Management Information System.pptxApplications of Management Information System.pptx
Applications of Management Information System.pptx
Roshni814224
 
Securing Management Information Systems.ppt
Securing Management Information Systems.pptSecuring Management Information Systems.ppt
Securing Management Information Systems.ppt
Roshni814224
 
relational model in Database Management.ppt.ppt
relational model in Database Management.ppt.pptrelational model in Database Management.ppt.ppt
relational model in Database Management.ppt.ppt
Roshni814224
 
Database Management System Security.pptx
Database Management System  Security.pptxDatabase Management System  Security.pptx
Database Management System Security.pptx
Roshni814224
 

Mais de Roshni814224 (20)

Ecommerce concepts and uses in Business.pptx
Ecommerce concepts and uses in Business.pptxEcommerce concepts and uses in Business.pptx
Ecommerce concepts and uses in Business.pptx
 
Emerging Global Trends in Internet of Things.pptx
Emerging Global Trends in Internet of Things.pptxEmerging Global Trends in Internet of Things.pptx
Emerging Global Trends in Internet of Things.pptx
 
Emerging IT Trends and Innovation Concepts.pptx
Emerging IT Trends and Innovation Concepts.pptxEmerging IT Trends and Innovation Concepts.pptx
Emerging IT Trends and Innovation Concepts.pptx
 
Introduction to E-Commerce and Components.pptx
Introduction to E-Commerce and Components.pptxIntroduction to E-Commerce and Components.pptx
Introduction to E-Commerce and Components.pptx
 
Business Information Systems in firms.pptx
Business Information Systems in firms.pptxBusiness Information Systems in firms.pptx
Business Information Systems in firms.pptx
 
Strategic Information System in Business Firm.ppt
Strategic Information System in Business Firm.pptStrategic Information System in Business Firm.ppt
Strategic Information System in Business Firm.ppt
 
Management Information System Applications.pptx
Management Information System Applications.pptxManagement Information System Applications.pptx
Management Information System Applications.pptx
 
The Concepts of Internet and Networking.pptx
The Concepts of Internet and Networking.pptxThe Concepts of Internet and Networking.pptx
The Concepts of Internet and Networking.pptx
 
Integrity Constraints in Database Management System.ppt
Integrity Constraints in Database Management System.pptIntegrity Constraints in Database Management System.ppt
Integrity Constraints in Database Management System.ppt
 
Data models in Database Management Systems.ppt
Data models in Database Management Systems.pptData models in Database Management Systems.ppt
Data models in Database Management Systems.ppt
 
Transaction Management, Recovery and Query Processing.pptx
Transaction Management, Recovery and Query Processing.pptxTransaction Management, Recovery and Query Processing.pptx
Transaction Management, Recovery and Query Processing.pptx
 
Computer System Software Component Details.pptx
Computer System Software Component Details.pptxComputer System Software Component Details.pptx
Computer System Software Component Details.pptx
 
Social Engineering and Identity Theft.pptx
Social Engineering and Identity Theft.pptxSocial Engineering and Identity Theft.pptx
Social Engineering and Identity Theft.pptx
 
Cyber Security and Data Privacy in Information Systems.pptx
Cyber Security and Data Privacy in Information Systems.pptxCyber Security and Data Privacy in Information Systems.pptx
Cyber Security and Data Privacy in Information Systems.pptx
 
Information Systems, Organizations and Strategy.pptx
Information Systems, Organizations and Strategy.pptxInformation Systems, Organizations and Strategy.pptx
Information Systems, Organizations and Strategy.pptx
 
Information Systems in Global Business Today.pptx
Information Systems in Global Business Today.pptxInformation Systems in Global Business Today.pptx
Information Systems in Global Business Today.pptx
 
Applications of Management Information System.pptx
Applications of Management Information System.pptxApplications of Management Information System.pptx
Applications of Management Information System.pptx
 
Securing Management Information Systems.ppt
Securing Management Information Systems.pptSecuring Management Information Systems.ppt
Securing Management Information Systems.ppt
 
relational model in Database Management.ppt.ppt
relational model in Database Management.ppt.pptrelational model in Database Management.ppt.ppt
relational model in Database Management.ppt.ppt
 
Database Management System Security.pptx
Database Management System  Security.pptxDatabase Management System  Security.pptx
Database Management System Security.pptx
 

Último

Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
Dr. Shivangi Singh Parihar
 
Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
NgcHiNguyn25
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
Academy of Science of South Africa
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
IreneSebastianRueco1
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
chanes7
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
eBook.com.bd (প্রয়োজনীয় বাংলা বই)
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
amberjdewit93
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
simonomuemu
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
National Information Standards Organization (NISO)
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
RitikBhardwaj56
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
Dr. Mulla Adam Ali
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
Scholarhat
 
Assessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptxAssessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptx
Kavitha Krishnan
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
AyyanKhan40
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
heathfieldcps1
 

Último (20)

Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.Types of Herbal Cosmetics its standardization.
Types of Herbal Cosmetics its standardization.
 
PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.PCOS corelations and management through Ayurveda.
PCOS corelations and management through Ayurveda.
 
Life upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for studentLife upper-Intermediate B2 Workbook for student
Life upper-Intermediate B2 Workbook for student
 
South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)South African Journal of Science: Writing with integrity workshop (2024)
South African Journal of Science: Writing with integrity workshop (2024)
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
RPMS TEMPLATE FOR SCHOOL YEAR 2023-2024 FOR TEACHER 1 TO TEACHER 3
 
Digital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments UnitDigital Artifact 1 - 10VCD Environments Unit
Digital Artifact 1 - 10VCD Environments Unit
 
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdfবাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
বাংলাদেশ অর্থনৈতিক সমীক্ষা (Economic Review) ২০২৪ UJS App.pdf
 
Digital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental DesignDigital Artefact 1 - Tiny Home Environmental Design
Digital Artefact 1 - Tiny Home Environmental Design
 
Smart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICTSmart-Money for SMC traders good time and ICT
Smart-Money for SMC traders good time and ICT
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
Pollock and Snow "DEIA in the Scholarly Landscape, Session One: Setting Expec...
 
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...The simplified electron and muon model, Oscillating Spacetime: The Foundation...
The simplified electron and muon model, Oscillating Spacetime: The Foundation...
 
Hindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdfHindi varnamala | hindi alphabet PPT.pdf
Hindi varnamala | hindi alphabet PPT.pdf
 
Azure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHatAzure Interview Questions and Answers PDF By ScholarHat
Azure Interview Questions and Answers PDF By ScholarHat
 
Assessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptxAssessment and Planning in Educational technology.pptx
Assessment and Planning in Educational technology.pptx
 
PIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf IslamabadPIMS Job Advertisement 2024.pdf Islamabad
PIMS Job Advertisement 2024.pdf Islamabad
 
The basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptxThe basics of sentences session 6pptx.pptx
The basics of sentences session 6pptx.pptx
 

ERP Scope, Procurement and Implementation

  • 1. 1 My Organisation November 18, 2021 Presentation on Procurement of 1) IFMIS 2) RMS & 3) PM Consultancy
  • 2. Key Parameters RMS IFMIS Project Duration 4.5 Years Implementation -1.5 Yr, Support Extension 3 Yrs.) 5 Years Implementation -2 Yrs, Support Extension 3 Yrs. Geographical Coverage 20-25 Locations (Kathmandu and nearby) All offices of NEA Functional Coverage IFMIS • Financial Management • Asset Management • Inventory Management • Payroll • Project Accounting • Employee Claims & Retirement Benefits IFMIS and RMS • Financial Management • Asset Management • Inventory Management • Payroll • Human Resource Management System • Project Accounting • Metering • Billing and Collection • Energy Audit 2 Scope of Work (RMS & IFMIS)
  • 3. 3 RMS: Scope of Work  Supply, delivery, design, customization, integration, implementation, testing, commissioning of Hardware/ software of the RMS with FMS, including Data Migration & Change Management and Capacity Building.  COTS database, Middleware, Network and customer care equipment and other software in conformance to Industry standards and installation & maintenance of necessary infrastructure (at DC &DR).  Total period of contract is 4.5 years (1.5yrs for Implementation & FMS and 3yrs for support.) During the FMS period, the SI shall provide manpower &technical support services.
  • 4. 4 RMS: Key Considerations  Software License for 6 million consumers. (5.08m, 8%,3%,3%,3%)  Annual Technical Services (ATS) are computed @ 22% of the RMS License Cost per year.  Hardware Infrastructure requirements for DC and DRC  Annual Maintenance Cost (AMC) @ 10% of HW Cost per year.  Capacity Building : 700 RMS Users, 14 Executive Users (Abroad).  FMS: Man-month Rate : Same till Go-Live, 10% Y-o-Y thereafter.
  • 5. 5 RMS: Modules Major Modules FRS Count 1. Metering 21 2. Billing 55 3. Collection 18 4. New Connection, Disconnection & Reconnection 50 5. Energy Audit 7 Supporting Modules 6 Management information System (MIS) 12 7. Document Management System (DMS) 13 8. Customer Relationship Management (CRM) 48 9. Web Portal and Mobile Application 19 10. Customer Care Centre (CCC)
  • 6. 6 RMS: Project Timeline Project Activities M01 M02 M03 M04 M05 M06 M07 M08 M09 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 Project Initiation Business Blueprinting Design & Customization Data Migration IT infra setup for DC , DRC & CCC Pilot Rollout Training and Change Management Enterprise wide roll out Stabilization Support FMS 3 Yrs
  • 7. 7 RMS: Eligibility Qualification Criteria Scoring Matrix SI’s Strength Product OEM’s Strength RMS Implementation 60 15 Team Composition 10 Approach and Methodology 15 Totals 85 15 Technical Qualifying Score = 60% Weight for the Bid Price as specified in BDS = 40% Weight of the Bid Technical score = 60% Compliance to the Functional Requirement Specifications (FRS) mentioned in the RFP for major modules as standard is 85% . Less than 85% shall be termed as non-responsive.
  • 8. 8 IFMIS: Scope of work  Supply, delivery, design, customization, integration, implementation, testing, commissioning of Hardware/ software of the IFMIS with FMS, including Data Migration & Change Management and Capacity Building.  COTS database, Middleware, Network and customer care equipment and other software in conformance to Industry standards and installation & maintenance of necessary infrastructure (at DC &DR).  Total period of contract is 5 years (2yrs for Implementation & FMS and 3yrs for support.) During the FMS period, the SI shall provide manpower & technical support services.
  • 9. 9 IFMIS: Key Considerations  Software License for 1600 full enterprise users. Additional 400.  Annual Technical Services (ATS) are computed @ 22% of the IFMIS License Cost per year.  Hardware Infrastructure requirements for DC and DRC  Annual Maintenance Cost (AMC) @ 10% of HW Cost per year.  Capacity Building : 2000 Users, 15 Executive Users (Abroad).  FMS: Man-month Rate : Same till Go-Live, 10% Y-o-Y thereafter.
  • 10. 10 IFMIS: Project Timeline Project Activities M01 M02 M03 M04 M05 M06 M07 M08 M09 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 Project Initiation Business Blueprinting Design & Customization Data Migration IT infra setup for DC , DRC & CCC Pilot Rollout Training and Change Management Enterprise wide roll out Stabilization Support FMS 3 Yrs
  • 11. 11 Recommendation • The extension cost initial quoted, Final revised and EY estimated = 1.66 • Recommendation from EY to float the RFP with 3 years extension. • Extension of 3 years has been considered with a perception to take over the FMS by NEA IT team.
  • 12. 12 IFMIS: Modules Major Modules FRS Count 1. Financial Management 697 2. Material Management 259 3. Human Resource Management 496 4. Project Management 227 5. Maintenance Management 515 6. Production Planning 96 Supporting Modules 6 Linear Asset Management 11 7. Document and File Management 90 8. BI & BW 35 9. Mobile Application 80 10. Employee Self Services (ESS) & Manager Self Services (MSS) 87
  • 13. 13 IFMIS: Eligibility Qualification Criteria Scoring Matrix SI’s Strength Product OEM’s Strength IFMIS Implementation 55 Product’s Credentials 15 Team Composition 10 Proof of the Strength of the Product 5 Approach and Methodology 15 Totals 80 20 Technical Qualifying Score = 60% Weight for the Bid Price as specified in BDS = 40% Weight of the Bid Technical score = 60% Compliance to the Functional Requirement Specifications (FRS) mentioned in the RFP for major modules as standard is 85% . Less than 85% shall be termed as non-responsive.
  • 14. 14 Project Management Consultant  Expression of Interest (EoI) and Terms of Reference (ToR) published  Fourteen International Firms submitted the EoI  Committee Shortlisted 6 Firms  RFP to be finalized and submitted to ADB  Budget approved was 1 million USD and approved was 0.8 million USD excluding applicable taxes and VAT in Nepal.
  • 15. 15 Recommendations Expected–1  Team Composition: RMS: Provincial Managers - Bachelor Degree in Electrical/ Electronics/ IT/ Computer Science or related fields and 5 years of experience on RMS implementation. IFMIS: Assistant Project Manager - Bachelor Degree in Electrical/ Electronics/ IT/ Computer Science or related fields and 5 years of experience on IFMIS implementation. Provincial Managers and Assistant Project Managers are to be deputed from in- house.  Evaluation of CVs RMS: Evaluation of CVs of Project Manager and Provincial Managers only. IFMIS: Evaluation of Project Manager and Assistant Project Managers only. CVs of the Key Experts are to be evaluated.  PQ: The proposed product should be of latest version and the OEM should have a future Roadmap - for IFMIS required for the next 10 (ten) years and for RMS required for the
  • 16. 16 Recommendations Expected–2  Technical Score QCBS Requirement : Minimum Technical Score Required: 60% (IFMIS and RMS) IFMIS: 60% –30% RMS: 70% –30%  ERP Professional User License Requirement NEA’s License Requirement = 1600 Requirement in PQ/TQ: 300 Bring Down it in PQ/TQ to 200  Confirmation on Extension period to be considered
  • 17. 17 Recommendations Expected–3  Potential bidders pool is same for all the three procurements.  Bidders from the Consultants category such as PwC, Deloitte and KPMG also fulfill the PQ and TQ criteria set for SIs of both the procurements.  All the bidders will be allowed to participate in all the three tenders.  Selection of the top three PMC consultants will be done.  If the bidder selected for consultant also gets selected as SI in either or both of the procurements, then the bidder has to work as the SI for NEA.  This condition is to be included in the RFP for PMC.
  • 18. 18 Recommendations Expected–4  ToR clearly stating the Scope of Work of the Consultant EY  Deputed by ADB upon request from NEA  Need the support from the consultant in bid process management  Approach and Methodology evaluation required expert recommendation