SlideShare uma empresa Scribd logo
1 de 16
––––––AMITY UNIVERSITY RAJASTHAN––––––––
WORKSHOP PRACTISE &
SITE EXPOSURE
REPORT ON
SITE VISIT: NIMS
SUBMITTED TO :
AR. ABBHISHEK SHRIVASTAV
SUBMITTED BY:
SHOURYA PURI
S SAI GOTHAM
SOURABH SHARM
B.ARCH , 5 SEM
OBJECTIVES
The objective of the case study is to explore and observe the different
activities and techniques carried out on site. To explore the various types of
building materials and machinery on site. To have experience of an architectural
site visit and the practices going out there as an architect which will be very
useful in future and help us a lot.
INTRODUCTION
A Site visit is an official visit or approval visit to a site to examine the site and
to observe its environment & to determine its suitability for its enterprice.
A site visit for the construction of a hospital building was organised by
Col. Krishna Pal Singh on 27 july 2015 . The location of site visit was at NIMS
hospital and university near chandwaji Jaipur Rajasthan. A total of 38 students
attended the site visit. Then base on the plan, all student gathered at university
around 9:00am and we reached to the site after half an hour journey by bus.
After arrival to the site and meeting with the people in charge of guiding us, a
short brief about the project was given by Col. Krishna Pal Singh to start the
tour around the site.
After briefing the students were guided to the ground floor level and
awhile observing through , works such as flooring and some basic works were
going on. Next they guided us to the upper floors and during walking students
were able to see different types of materials, such as packets of Portland cement
or ducts before instillation for air conditioning purposes. After reaching to the
further floors , different things attracted students’attention such as beams
columns, pipes, scaffoldings and many others, plus watching workers working
on concrete stair by bending reinforcement bars. After that we had chance to
experience moving down by using scaffolding and once we reached the ground
level workers were preparing timber formworks which was quite interesting.
All this was a part of site visit of NIMS Jaipur Rajasthan for the exposure
of architecture students of Amity School of Architecture and Planning.
.
BEAMS AND COLUMNS STRUCTURE
Beams and columns are frequently used for a building's structure as a
replacement for steel. They are commonly used for precast building
solution, when combined with precast walling and flooring. The structural
precast columns are reinforced and can be used as a part of a
total precast concrete structure. A variation of finishes can be applied
according to the building type once the beams and columns are done.
Beams are commonly used as ledges for other forms of precast flooring to
rest on, but can also be used as a flooring option on their own. They are
manufactured to suit each particular building design. Some of the beams
included are Tee-Beams, L-Beams, Rectangular Beams, U-Beams and
Beam shells.
Reinforced concrete frame of the building including columns, beams, and slabs.
SCAFFOLDNG
Scaffolding, also called scaffold or staging, is a temporary structure used to
support a work crew and materials to aid in the construction, maintenance
and repair of buildings, bridges and all other man made structures. Scaffolding
is also used in adapted forms for formwork and shoring, grandstand seating,
concert stages, access/viewing towers, exhibition stands, ski ramps, half pipes
and art projects.
SCAFFOLDING
Scaffolding which is a temprary platform for workers to access to a place of work at
construction sites and also to support them as well as materials.
Concrete transfer machine
CONCRETE MIXER MACHINE
A concrete mixer (also commonly called a cement mixer) is a device that homogeneously
combines cement, aggregate such as sand or gravel, and water to form concrete. A typical
concrete mixer uses a revolving drum to mix the components. For smaller volume works portable
concrete mixers are often used so that the concrete can be made at the construction site, giving
the workers ample time to use the concrete before it hardens.
Concrete mixer machine to lift and lower materials and also to move them horizontally.
SHUTTERING
A temporary structure of wood in planks or strips used as a temporary structure
to contain setting concrete, to support the sides of trenches, or similar.
ALUMINIUM PARTITION
Reinforced concrete beams intersects.
STAIRS
A stairway, staircase, stairwell, flight of stairs, or simply stairs is a construction
designed to bridge a large vertical distance by dividing it into smaller vertical
distances, called steps. Stairs may be straight, round, or may consist of two or
more straight pieces connected at angles.
This is the construction details of a staircase
.
FOUNDATION
A foundation (or more commonly, foundations) is the element of
an architectural structure which connects it to the ground, and
transfers load from the structure to the ground. Foundations are generally
considered either shallow or deep.
STIRRUPS
A machine for armature bending and making stirrups. Angle defining is done
over metal trunnions, at the same time three independent angles can
be defined on the left or right side. A special part with limit stops can be added
for bending stirrups.
CONCLUSION
At the end of the visit and experiencing real working space and the environment
of construction and Architecture . I realized that working at a construction site is
much more different than studying in studios , classroom and books. This site
visit gave me a chance to experience and learn what cannot be gained during
lectures and in studios. Finally , this site visit helped for better understanding
what I am going to face in future and also , giving me better understanding about
construction to help me in my studying . In overall , it was a great fun and
experience for me.

Mais conteúdo relacionado

Mais procurados

Suzlon One Earth Case Study by Ameya Gumaste
Suzlon One Earth Case Study by Ameya GumasteSuzlon One Earth Case Study by Ameya Gumaste
Suzlon One Earth Case Study by Ameya Gumaste
TechGigDotCom
 
Bus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt showBus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt show
kiranightly
 

Mais procurados (20)

Charles correa
Charles correaCharles correa
Charles correa
 
Kohinoor square
Kohinoor squareKohinoor square
Kohinoor square
 
high rise buildings case study
high rise buildings case studyhigh rise buildings case study
high rise buildings case study
 
Architect as a project manager
Architect as a project managerArchitect as a project manager
Architect as a project manager
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
 
Case Study: High Rise Buildings
Case Study: High Rise BuildingsCase Study: High Rise Buildings
Case Study: High Rise Buildings
 
Charles correa
Charles correa Charles correa
Charles correa
 
Suzlon One Earth Case Study by Ameya Gumaste
Suzlon One Earth Case Study by Ameya GumasteSuzlon One Earth Case Study by Ameya Gumaste
Suzlon One Earth Case Study by Ameya Gumaste
 
CEPT UNIVERSITY PPT
CEPT UNIVERSITY PPTCEPT UNIVERSITY PPT
CEPT UNIVERSITY PPT
 
Building Economics
Building Economics Building Economics
Building Economics
 
Presentation case study convention center
Presentation case study convention centerPresentation case study convention center
Presentation case study convention center
 
Bus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt showBus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt show
 
Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)
Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)
Long span structures case study (LINK IN DESCRIPTION FOR DOWNLOAD)
 
City center kolkata
City center kolkataCity center kolkata
City center kolkata
 
dome and vault
dome and vaultdome and vault
dome and vault
 
Uttam chand jain
Uttam chand jainUttam chand jain
Uttam chand jain
 
World one (Lodha Tower)
World one (Lodha Tower)World one (Lodha Tower)
World one (Lodha Tower)
 
High Rise Building Research Document
High Rise Building Research DocumentHigh Rise Building Research Document
High Rise Building Research Document
 
Parking final
Parking finalParking final
Parking final
 
Site visit report
Site visit reportSite visit report
Site visit report
 

Destaque

Assignment 1 Site Visit Report
Assignment 1 Site Visit ReportAssignment 1 Site Visit Report
Assignment 1 Site Visit Report
armada7000
 
Site report
Site reportSite report
Site report
Yunshi94
 
Itinerary for site visit
Itinerary for site visitItinerary for site visit
Itinerary for site visit
Est
 
Employee Grievances
Employee GrievancesEmployee Grievances
Employee Grievances
simply_coool
 
Site Visit Report
Site Visit ReportSite Visit Report
Site Visit Report
ZIyeeTan
 

Destaque (20)

Site visit report
Site visit reportSite visit report
Site visit report
 
Assignment 1 Site Visit Report
Assignment 1 Site Visit ReportAssignment 1 Site Visit Report
Assignment 1 Site Visit Report
 
Objective of site visit
Objective of site visitObjective of site visit
Objective of site visit
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction site
 
Site report
Site reportSite report
Site report
 
Best Tooling presentation 2015 研安
Best Tooling presentation 2015 研安Best Tooling presentation 2015 研安
Best Tooling presentation 2015 研安
 
Itinerary for site visit
Itinerary for site visitItinerary for site visit
Itinerary for site visit
 
Daily routines
Daily routines Daily routines
Daily routines
 
Benezon: Healthcare Advocacy
Benezon: Healthcare AdvocacyBenezon: Healthcare Advocacy
Benezon: Healthcare Advocacy
 
Construction Materials site visit report
Construction Materials site visit report Construction Materials site visit report
Construction Materials site visit report
 
RAC Appeals Webinar for healthcare execs
RAC Appeals Webinar for healthcare execsRAC Appeals Webinar for healthcare execs
RAC Appeals Webinar for healthcare execs
 
Construction Site Visit
Construction Site VisitConstruction Site Visit
Construction Site Visit
 
Customer Visits
Customer VisitsCustomer Visits
Customer Visits
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
 
Employee Grievances
Employee GrievancesEmployee Grievances
Employee Grievances
 
Dell Healthcare Services Grievance and Appeals Management
Dell Healthcare Services Grievance and Appeals ManagementDell Healthcare Services Grievance and Appeals Management
Dell Healthcare Services Grievance and Appeals Management
 
Site Visit Report
Site Visit ReportSite Visit Report
Site Visit Report
 
Welcome presentation for slideshare
Welcome presentation for slideshareWelcome presentation for slideshare
Welcome presentation for slideshare
 
Project Execution
Project ExecutionProject Execution
Project Execution
 

Semelhante a SITE VISIT ARCHITECTRE (20)

Site visit report
Site visit reportSite visit report
Site visit report
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
Site Report
Site ReportSite Report
Site Report
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
 
INDL PPT 1.pptx
INDL PPT 1.pptxINDL PPT 1.pptx
INDL PPT 1.pptx
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visit
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShare
 
Construction Site Report
Construction Site ReportConstruction Site Report
Construction Site Report
 
Site report
Site reportSite report
Site report
 
Jump Formwork
Jump FormworkJump Formwork
Jump Formwork
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017
 
Integrated assignment site report
Integrated assignment site reportIntegrated assignment site report
Integrated assignment site report
 
Site report
Site reportSite report
Site report
 
Site report
Site reportSite report
Site report
 
Ez
EzEz
Ez
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)
 
Site visitation
Site visitationSite visitation
Site visitation
 
Site report
Site reportSite report
Site report
 

Mais de Shourya Puri

Mais de Shourya Puri (20)

Smo(social media optimisation)
Smo(social media optimisation)Smo(social media optimisation)
Smo(social media optimisation)
 
SMO (social media optimization)
SMO (social media optimization)SMO (social media optimization)
SMO (social media optimization)
 
Seo digital marketing
Seo digital marketingSeo digital marketing
Seo digital marketing
 
report of dance, drama and music academy and auditorium
report of dance, drama and music academy and auditoriumreport of dance, drama and music academy and auditorium
report of dance, drama and music academy and auditorium
 
Synopsis Of cultural complex
Synopsis Of cultural complexSynopsis Of cultural complex
Synopsis Of cultural complex
 
Wildcraft marketing
Wildcraft marketingWildcraft marketing
Wildcraft marketing
 
Wagah border
Wagah border Wagah border
Wagah border
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedure
 
History of jammu & kashmir
History  of jammu & kashmirHistory  of jammu & kashmir
History of jammu & kashmir
 
Town plan auroville
Town plan aurovilleTown plan auroville
Town plan auroville
 
Hybrid trusses
Hybrid trussesHybrid trusses
Hybrid trusses
 
Xeriscaping landscape and bioswale
Xeriscaping  landscape and bioswaleXeriscaping  landscape and bioswale
Xeriscaping landscape and bioswale
 
Glass Report
Glass ReportGlass Report
Glass Report
 
Fiberglass
FiberglassFiberglass
Fiberglass
 
MODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSMODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODS
 
Sustainable Waste Management
Sustainable Waste ManagementSustainable Waste Management
Sustainable Waste Management
 
Improve communication skills
Improve communication skillsImprove communication skills
Improve communication skills
 
Office case study
Office case studyOffice case study
Office case study
 
Convention hall interior acoustics
Convention hall  interior acoustics Convention hall  interior acoustics
Convention hall interior acoustics
 
Glass presentation
Glass presentationGlass presentation
Glass presentation
 

Último

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Último (20)

On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
NO1 Top Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 

SITE VISIT ARCHITECTRE

  • 1. ––––––AMITY UNIVERSITY RAJASTHAN–––––––– WORKSHOP PRACTISE & SITE EXPOSURE REPORT ON SITE VISIT: NIMS SUBMITTED TO : AR. ABBHISHEK SHRIVASTAV SUBMITTED BY: SHOURYA PURI S SAI GOTHAM SOURABH SHARM B.ARCH , 5 SEM
  • 2. OBJECTIVES The objective of the case study is to explore and observe the different activities and techniques carried out on site. To explore the various types of building materials and machinery on site. To have experience of an architectural site visit and the practices going out there as an architect which will be very useful in future and help us a lot.
  • 3. INTRODUCTION A Site visit is an official visit or approval visit to a site to examine the site and to observe its environment & to determine its suitability for its enterprice. A site visit for the construction of a hospital building was organised by Col. Krishna Pal Singh on 27 july 2015 . The location of site visit was at NIMS hospital and university near chandwaji Jaipur Rajasthan. A total of 38 students attended the site visit. Then base on the plan, all student gathered at university around 9:00am and we reached to the site after half an hour journey by bus. After arrival to the site and meeting with the people in charge of guiding us, a short brief about the project was given by Col. Krishna Pal Singh to start the tour around the site. After briefing the students were guided to the ground floor level and awhile observing through , works such as flooring and some basic works were going on. Next they guided us to the upper floors and during walking students were able to see different types of materials, such as packets of Portland cement or ducts before instillation for air conditioning purposes. After reaching to the further floors , different things attracted students’attention such as beams columns, pipes, scaffoldings and many others, plus watching workers working on concrete stair by bending reinforcement bars. After that we had chance to experience moving down by using scaffolding and once we reached the ground level workers were preparing timber formworks which was quite interesting. All this was a part of site visit of NIMS Jaipur Rajasthan for the exposure of architecture students of Amity School of Architecture and Planning. .
  • 4. BEAMS AND COLUMNS STRUCTURE Beams and columns are frequently used for a building's structure as a replacement for steel. They are commonly used for precast building solution, when combined with precast walling and flooring. The structural precast columns are reinforced and can be used as a part of a total precast concrete structure. A variation of finishes can be applied according to the building type once the beams and columns are done. Beams are commonly used as ledges for other forms of precast flooring to rest on, but can also be used as a flooring option on their own. They are manufactured to suit each particular building design. Some of the beams included are Tee-Beams, L-Beams, Rectangular Beams, U-Beams and Beam shells. Reinforced concrete frame of the building including columns, beams, and slabs.
  • 5. SCAFFOLDNG Scaffolding, also called scaffold or staging, is a temporary structure used to support a work crew and materials to aid in the construction, maintenance and repair of buildings, bridges and all other man made structures. Scaffolding is also used in adapted forms for formwork and shoring, grandstand seating, concert stages, access/viewing towers, exhibition stands, ski ramps, half pipes and art projects.
  • 6. SCAFFOLDING Scaffolding which is a temprary platform for workers to access to a place of work at construction sites and also to support them as well as materials.
  • 8. CONCRETE MIXER MACHINE A concrete mixer (also commonly called a cement mixer) is a device that homogeneously combines cement, aggregate such as sand or gravel, and water to form concrete. A typical concrete mixer uses a revolving drum to mix the components. For smaller volume works portable concrete mixers are often used so that the concrete can be made at the construction site, giving the workers ample time to use the concrete before it hardens. Concrete mixer machine to lift and lower materials and also to move them horizontally.
  • 9. SHUTTERING A temporary structure of wood in planks or strips used as a temporary structure to contain setting concrete, to support the sides of trenches, or similar.
  • 11.
  • 13. STAIRS A stairway, staircase, stairwell, flight of stairs, or simply stairs is a construction designed to bridge a large vertical distance by dividing it into smaller vertical distances, called steps. Stairs may be straight, round, or may consist of two or more straight pieces connected at angles. This is the construction details of a staircase .
  • 14. FOUNDATION A foundation (or more commonly, foundations) is the element of an architectural structure which connects it to the ground, and transfers load from the structure to the ground. Foundations are generally considered either shallow or deep.
  • 15. STIRRUPS A machine for armature bending and making stirrups. Angle defining is done over metal trunnions, at the same time three independent angles can be defined on the left or right side. A special part with limit stops can be added for bending stirrups.
  • 16. CONCLUSION At the end of the visit and experiencing real working space and the environment of construction and Architecture . I realized that working at a construction site is much more different than studying in studios , classroom and books. This site visit gave me a chance to experience and learn what cannot be gained during lectures and in studios. Finally , this site visit helped for better understanding what I am going to face in future and also , giving me better understanding about construction to help me in my studying . In overall , it was a great fun and experience for me.