Alice Project - Report 4 (Sep. 2016)
1. ALICE PROJECT REPORT N°4 – SEPTEMBRE 2016
Attn : SHINING HOPE FOUNDATION
SARNATH SCHOOL
Extension of the school
The work of the extension of the school is still going on. The rooms are being plastered
from inside and the work of fixing the water pipes in the walls for the water supply is
going on there. As well as they are fixing the pipes for the electricity. The toilets for two
floors ready now they are making the toilets for the third floor. The floors are still to be
prepared. The painters are doing the painting work of the doors and windows frames.
Here we are sending you some of the images of the work going on there.
Image of the room ready with the plastered walls and the pipes for the electricity
2. The rooms with floors not ready. Workers painting the frames of the
windows
Toilets being ready on each floor of the new building. Ready blocks for the toilets
New guest rooms are under construction
The classrooms which were behind the stupa, now they are being converted in the
guest houses. The two classrooms are going to me be modified in 4 guestrooms with
the attach bathrooms. Here we are sending you some of the images of the work going
on there.
The image of rooms being divided in the guestrooms. Opening of the guest rooms
3. Interior view of the guestrooms Interior view of the guestrooms
The library is being repainted
The library is also being repainted. The workers are painting the building and the
furniture with different colors suggested by Grazeilla ji.
! !
Upper part of the library Lower part of the library
4. ! !
Steps leading to the upper part The cupboards painted with new colors
BODHGAYA SCHOOL
New Junior Bodhagaya High School
Construction has been delayed a lot (finances, weather…) but is
almost finished! They are beginning to work with the inside set-up.