2. Why-
Needs of our Children
Needs of our Schools
Needs of our Teachers
Needs of our Community
How-
Board members, design teams, site councils,
community representatives reviewing the needs
of USD 263
2 year effort with community survey input
3. Munson Primary School
◦ Safety –Secure entrance/Traffic Flow improvements
◦ Additional Special Education Classrooms
◦ Energy Efficiencies
◦ Storm shelters
Grade school
◦ Safety-Storm Shelters/Traffic flow improvements
◦ Increased classroom space
◦ Dedicated cafeteria/gymnasium
Lyle Couch Stadium
◦ Safety
◦ Stadium improvements
◦ Reduced Maintenance Costs/Community Improvements
Central Operations Center
◦ Consolidate Transportation/Grounds maintenance
◦ Increase Usable Maintenance Area
4. Improve student entrance for safety
Enhanced Storm Shelter
Greatly improve traffic congestion
Increase classroom space for Special Education
Additional classrooms
All weather area for physical education and
recess activities
Modernize building
◦ Update heating and cooling systems
◦ Asbestos Removal
◦ Replace insufficient lighting
◦ Energy efficiencies (insulation and windows)
8. Additional classrooms
Enhanced Storm Shelter
Greatly improve traffic congestion
Dedicated Cafeteria Space
New Multipurpose Building
◦ Dedicated physical education facility for students
◦ New classrooms dedicated to music and art
◦ Collaborate with Mulvane Recreation Center to
share gym/walking track
12. Improve safety and track conditions
◦ Replace outdated track to improve safety and community/school usage
◦ New lighting to improve security and extend school/community usage
Increase seating capacity
◦ Move ―Home‖ seating from East to West side of field
◦ Double seating capacity
Add all-weather field surface to enhance safety and usage for
students and student athletes
Add Locker Rooms
Additional wrestling facility
Improve parking
◦ Pave and mark spaces
Reduce Maintenance costs
◦ All Weather field surface eliminates grounds expenses
◦ Increase availability for other community youth sports and activities
◦ Remove current aging maintenance building
◦ Enhance appearance in the community
16. Increase size of maintenance facility
◦ Additional space required to service larger buses
◦ Improved traffic flow with separate entrances/exits
◦ Increased lighting for security after hours access
Consolidate Transportation/Building and
Grounds Maintenance
◦ Cost Savings
◦ Improved logistics
Improve Community Appearance with storage
and buildings
17. Separate No Space to work on
buildings/locations buses
18.
19. Proposed bond will cost an estimated $1.44 per month for
each $100,000 of a home’s fair market value.
The total bond issue amount is not-to-exceed $13.415
million.
Under current law, State will pay 20-25% of both project
and interest costs—a projected benefit of $3.8 million.
Governor has proposed an end to this state aid program
effective June 30th, so now may be a last chance
opportunity.
The USD 263 total mill rate is one of the lowest in south
central Kansas.
Today’s bond interest rates, estimated at 3.5% for the 13-
year bond, are near 50-year low levels.
Bond approval will require an estimated mill levy increase
of only 1.5 mills.
20. Sedgwick County, Kansas
Unified School District No. 263
Mulvane Schools
May 8, 2012 Bond Issue Election
$13.415 Million Bond Issue
Estimated Effect of a 1.50 Mill Net Increase
Assessed Monthly Tax Yearly Tax
Type of Property Valuation Increase Increase
$75,000 Home* $ 8,625 $ 1.08 $ 12.94
$100,000 Home* $ 11,500 $ 1.44 $ 17.25
$150,000 Home* $ 17,250 $ 2.16 $ 25.88
$200,000 Home* $ 23,000 $ 2.88 $ 34.50
$50,000 Comm. Property** $ 12,500 $ 1.56 $ 18.75
$100,000 Comm. Property** $ 25,000 $ 3.13 $ 37.50
$200,000 Comm. Property** $ 50,000 $ 6.25 $ 75.00
Yearly Tax Tax Increase
Increase Per Acre
160 Acres Dry Cropland*** $ 8,160 $ 12.24 $ 0.08
160 Acres Native Pasture*** $ 3,120 $ 4.68 $ 0.03
160 Acres Irrigated*** $ 11,232 $ 16.85 $ 0.11
* For taxing purposes, residential properties are assessed at 11.5% of fair market value.
**For taxing purposes, commercial properties are assessed at 25% of fair market value.
***For taxing purposes, agricultural properties are assessed at 30% of use or
productivity value (not fair market value).
21. What about the other projects previously identified by the community?
◦ After carefully considering feedback from the community, the Board of Education is
placing the most urgent projects before voters.
What is the state aid?
◦ The current state finance formula allows additional state aid to pay a portion of the
project and interest cost on the proposed bonds. The percentage of state aid
(currently 51%) is based on our district's wealth per pupil. With the anticipated
significant increase in our district's assessed valuation due to the casino
development, we are anticipating a drop in our bond & interest state aid to 20% by
2015. The total state aid benefit (both principal and interest) is an estimated
$3,805,000. These are tax monies that can be brought back from Topeka to the
benefit of our children and the Mulvane community. The Governor has proposed an
end to the offer of this state aid for bond issues effective June 30, 2012, so now may
be a last chance opportunity to take advantage of this program.
What will happen if the bond issue doesn’t pass?
◦ A no vote will not make our immediate needs magically disappear and slows down
progress. To address our needs with capital outlay dollars would take far more mills
and an even longer time period than the bond issue proposal.