FORMWORK
Introduction:
The term ‘formwork’ includes the actual material contact with the concrete, known as form
face, and all the necessary associated supporting structure.
Formwork is a die or a mould including all supporting structures, used to shape and support the
concrete until it attains sufficient strength to carry its own weight. It should be capable of
carrying all imposed dead and live loads apart from its own weight.
Formwork can be made out of a large variety of materials. Depending upon on the different
materials it can be divided into the following categories. Such as –
1. Timber formwork
2. Plywood formwork
3. Steel formwork
4. Aluminium formwork
5. Plastics
The material most commonly being used to date is timber. However, due to the depleting forest
reserves and increasing cost of timber the use of alternate materials such as plywood and steel
has become prominent. More recently, materials such as plastics and fiberglass are also being
used for pre-fabricating formwork. The type of material to be used depends on the nature of
construction as well as availability and cost of material.
There are different types of formwork available for different purposes. Generally, the formworks
for vertical concreting are called wall forms and those for horizontal concreting are called slab or
floor forms. The various types of formwork are available today. Such as-
a. Climbing formwork
b. Sliding formwork
c. Permanent formwork
d. Special formwork etc.
Scope:
 Formwork is used to give different shapes and sizes as needed in the construction.
 It is needed to contain the concrete with the reinforcement to adjust with it.
 It is also being treated as a support for all our required construction.
 For rounded wall , formwork is constructed.

Procedure:
The construction of formwork generally involves the following operations.
i. Propping and Centering
ii. Shuttering
iii. Provision of chamber
iv. Cleaning and surface treatment
In a building construction formworks are done generally for :-
 stairs
 column
 beam and slab
For the stairs, at first the timber as a flight is placed from the floor level to the ‘landing’ for stair
bottom. Then the landing as well as another flight is placed one landing to another. These all
timbers are supported by the bamboo pieces and and small pieces of timber to connect with the
flight and the landing. Then the sides are being attached. Now the reinforcement bars are laid
down as the design is made. Afterwards, for the shape of the steps , the risers are jointed between
the timber sides keeping a distance from the riser’s bottom to the flight surface.
Fig: Formwork of stair including riser,sides,flight
For the column, steel shutter is used covering the reinforcement. Timber is also can be used for
shuttering. These shutters are supported by the steel props as well as with some steel rods which
are connected with ‘Turn’ . The shutterings are attached with bolt but if timber is used for
shuttering, it is connected with wood pieces.
Fig: Steel shutter,steel props,hooked rod
For floor slab, shuttering for slab and beam is combinedly formed. To fit the shuttering of bottom
of the beam timber is used but at first the level is measured with the water level. Dasha is used to
support the bottom shutter of the beam which is fitted on the column and on the center steel
props are used to support it. Beam’s side shutter is fitted, keeping the thickness of slab accurate.
It is made leak proof.
Fig: Beam bottom,side,supported bamboo Fig: Runner,steel props,plywood
Then, for the slab shuttering, pieces of timber is used which is jointed from on end of the slab to
the other end It is known as runner. On it steel grill and plain sheet are placed to complete the
formwork of the slab. Instead of steel grill and plain sheet , plywood is also can be used. The
whole shuttering should be leak proof. In case of steel shutter, glue can be used to fill the pores.
The whole shuttering is supported on the steel props or bamboo. These should be placed
verticallly. In case of bamboo its dia should be 3 inches and matured one is used. Incase of 1st
floor, the sand is being compacted a piece of timber is placed under each bamboo. Commonly,
the gap between props is maintained 2 - 2.5 feet. If we use the pieco beam under the steel shutter
as a support then for a long span, we can reduce the quantity of steel props, which is placed
keeping 3 meter gaps from one another.
Again as previous, the level is measured of the slab and beam shutter with the water level. If the
level is not maintained, then with the level instrument it is levelled accurately.
After the shuttering, the formwork should be cleaned of all rubbish particularly the sawdust
shaving and chippings etc. The surface should be wetted with water as the concrete should come
to well contact.
Removing the formwork is also an important part of formwork.It should be done in the
following order of sequence-
 Shuttering forming vertical faces of walls, beams, and columns sides should be
removed first.
 Shuttering forming soffit to beams, girders or other heavily loaded member
should be removed in the end.
DURATION TAKEN FOR REMOVAL OF FORMWORK:
1 WALLS COLUMNS & VERTICAL SIDES
OF BEAMS 1-2 DAY
2 SLABS 3 DAYS
3 BEAM SOFFIT 7 DAYS
4 REMOVAL OF PROPS TO SLABS
A) SLAB SPANNINIG UPTO 4.5M 7 DAYS
B) SLAB SPANNINIG OVER 4.5M 14 DAYS
5 REMOVAL OF PROPS TO BEAMS
AND ARCHES
A) SPANNING UPTO 6 MTS 14 DAYS
B) SPANNING OVER 6 MTS 21 DAYS
Limitations:
 In practical sites, leak proof is not maintained perfectly.
 Sometimes the chamber shapes are deflected from the actual position. Therefore, the
placement sometimes changes of beam or other.
 Distance between steel props are not maintained. Therefore, bending of shuttering is
occured .
Conclusion:
The formwork should be made with good quality material and constructed properly. The type of
material to be used for formwork depends upon the nature of construction as well as the
availability and cost of material. In constructing floor slab, we can use plywood as shuttering
instead of timber planks. This type of shuttering ensures quality surface finish that is necessary
for floors.
The material of the formwork should be cheap, easily available and should be suitable for re-use
several times.
Nowadays , steel formwork is widely used in construction as it can be re-used because it is not
easily get damaged. But for the small construction and no need of re-use ,in that type of
construction timber formwork is cheaper than others.
References:
1. 30, East tejturi bazar
Tejgaon,Dhaka.
2. A construction site of a hospital
opposite to AUST
Love road,Dhaka.

Mais conteúdo relacionado

Mais procurados (20)

Beams and columns
Beams and columns Beams and columns
Beams and columns
 
Reinforced Concrete
Reinforced ConcreteReinforced Concrete
Reinforced Concrete
 
Formwork
FormworkFormwork
Formwork
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
Formwork
FormworkFormwork
Formwork
 
Scaffolding and formwork ppt
Scaffolding and  formwork pptScaffolding and  formwork ppt
Scaffolding and formwork ppt
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
blockwork
 blockwork blockwork
blockwork
 
Presentation on Slab, Beam & Column
Presentation on Slab, Beam & ColumnPresentation on Slab, Beam & Column
Presentation on Slab, Beam & Column
 
Blockwork
BlockworkBlockwork
Blockwork
 
Brick Masonry and Stone Masonry
Brick Masonry and Stone MasonryBrick Masonry and Stone Masonry
Brick Masonry and Stone Masonry
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
Damp Proof Course
Damp Proof Course Damp Proof Course
Damp Proof Course
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Form Work
Form Work Form Work
Form Work
 
Presentation of precast concrete
Presentation of precast concretePresentation of precast concrete
Presentation of precast concrete
 
Shuttering (Formwork)
Shuttering (Formwork)Shuttering (Formwork)
Shuttering (Formwork)
 
Stairs
StairsStairs
Stairs
 

Destaque

Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
balloon concrete formwork
balloon concrete formworkballoon concrete formwork
balloon concrete formwork08191289661
 
Application & Comparison of different Formwork System used within Ind...
Application  &  Comparison  of  different  Formwork System  used  within  Ind...Application  &  Comparison  of  different  Formwork System  used  within  Ind...
Application & Comparison of different Formwork System used within Ind...Abhishek Shah
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineeringFazal-E- Jalal
 
A collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and constructionA collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and constructionByron Smith
 
formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid shaikh khalid
 
Formwork design vs falsework design key differences
Formwork design vs falsework design  key differencesFormwork design vs falsework design  key differences
Formwork design vs falsework design key differencesscaffolddesign
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryAbhishek Shah
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyI'mMiss Lily
 

Destaque (15)

Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
balloon concrete formwork
balloon concrete formworkballoon concrete formwork
balloon concrete formwork
 
Site report
Site reportSite report
Site report
 
Application & Comparison of different Formwork System used within Ind...
Application  &  Comparison  of  different  Formwork System  used  within  Ind...Application  &  Comparison  of  different  Formwork System  used  within  Ind...
Application & Comparison of different Formwork System used within Ind...
 
Formwork
FormworkFormwork
Formwork
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineering
 
Report
ReportReport
Report
 
A collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and constructionA collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and construction
 
Formwork
FormworkFormwork
Formwork
 
formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid
 
Bab 5
Bab 5Bab 5
Bab 5
 
Mivan tech
Mivan techMivan tech
Mivan tech
 
Formwork design vs falsework design key differences
Formwork design vs falsework design  key differencesFormwork design vs falsework design  key differences
Formwork design vs falsework design key differences
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 

Semelhante a Formwork

8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdfFaizanSolanki
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.Puneet Chhonker
 
8. formworks and scaffoldings
8. formworks and scaffoldings8. formworks and scaffoldings
8. formworks and scaffoldingsHamdija Velagic
 
Place and Fix Reinforcement Materials Intro (2023 Edit).pptx
Place and Fix Reinforcement Materials Intro (2023 Edit).pptxPlace and Fix Reinforcement Materials Intro (2023 Edit).pptx
Place and Fix Reinforcement Materials Intro (2023 Edit).pptxCanberra Institute of technology
 
What Is A Slab? And What Are The Different Types Of Slab?
What Is A Slab? And What Are The Different Types Of Slab?What Is A Slab? And What Are The Different Types Of Slab?
What Is A Slab? And What Are The Different Types Of Slab?PoojaGurnule
 
various types of scffolding and formwork with underpining
various types of scffolding and formwork with underpiningvarious types of scffolding and formwork with underpining
various types of scffolding and formwork with underpiningkuldeep361335
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017bee_by
 
Formwork
FormworkFormwork
FormworkRahul
 
Mini project report on pile foundation
Mini project report on pile foundationMini project report on pile foundation
Mini project report on pile foundationjgbs123
 
REINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEREINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEBrijesh Alig
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTUVATSAL PATEL
 
Building construction 4- steel connection, Trusses, Joints, Foundations
Building construction 4- steel connection, Trusses, Joints, FoundationsBuilding construction 4- steel connection, Trusses, Joints, Foundations
Building construction 4- steel connection, Trusses, Joints, Foundationsaayush koolwal
 
Prefabricated wall panel
Prefabricated wall panelPrefabricated wall panel
Prefabricated wall panelSAHIL KUMAR
 
From work & shuttering
From work & shutteringFrom work & shuttering
From work & shutteringhamidgujjar
 

Semelhante a Formwork (20)

8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
 
formwork.pdf
formwork.pdfformwork.pdf
formwork.pdf
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
 
Temporary Works (Form Work)
Temporary Works (Form Work)Temporary Works (Form Work)
Temporary Works (Form Work)
 
8. formworks and scaffoldings
8. formworks and scaffoldings8. formworks and scaffoldings
8. formworks and scaffoldings
 
Place and Fix Reinforcement Materials Intro (2023 Edit).pptx
Place and Fix Reinforcement Materials Intro (2023 Edit).pptxPlace and Fix Reinforcement Materials Intro (2023 Edit).pptx
Place and Fix Reinforcement Materials Intro (2023 Edit).pptx
 
FormWork
FormWork FormWork
FormWork
 
What Is A Slab? And What Are The Different Types Of Slab?
What Is A Slab? And What Are The Different Types Of Slab?What Is A Slab? And What Are The Different Types Of Slab?
What Is A Slab? And What Are The Different Types Of Slab?
 
Roof truss
Roof trussRoof truss
Roof truss
 
various types of scffolding and formwork with underpining
various types of scffolding and formwork with underpiningvarious types of scffolding and formwork with underpining
various types of scffolding and formwork with underpining
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017
 
Formwork
FormworkFormwork
Formwork
 
Formwork
FormworkFormwork
Formwork
 
Mini project report on pile foundation
Mini project report on pile foundationMini project report on pile foundation
Mini project report on pile foundation
 
REINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEREINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETE
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 
Building construction 4- steel connection, Trusses, Joints, Foundations
Building construction 4- steel connection, Trusses, Joints, FoundationsBuilding construction 4- steel connection, Trusses, Joints, Foundations
Building construction 4- steel connection, Trusses, Joints, Foundations
 
Prefabricated wall panel
Prefabricated wall panelPrefabricated wall panel
Prefabricated wall panel
 
From work & shuttering
From work & shutteringFrom work & shuttering
From work & shuttering
 
TRUSS 2020.pptx
TRUSS 2020.pptxTRUSS 2020.pptx
TRUSS 2020.pptx
 

Mais de Md. Shahadat Hossain

Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Md. Shahadat Hossain
 
Ssb04 detailed design of portal frames
Ssb04 detailed design of portal framesSsb04 detailed design of portal frames
Ssb04 detailed design of portal framesMd. Shahadat Hossain
 
Skills m08 e_portalframes_singlestoreybuildings
Skills m08 e_portalframes_singlestoreybuildingsSkills m08 e_portalframes_singlestoreybuildings
Skills m08 e_portalframes_singlestoreybuildingsMd. Shahadat Hossain
 
Cantilever retaining wall design example
Cantilever retaining wall design exampleCantilever retaining wall design example
Cantilever retaining wall design exampleMd. Shahadat Hossain
 
Steel building design worked example
Steel building design worked exampleSteel building design worked example
Steel building design worked exampleMd. Shahadat Hossain
 
Optimized modeling and design of steel structures using etabs
Optimized modeling and design of steel structures using etabsOptimized modeling and design of steel structures using etabs
Optimized modeling and design of steel structures using etabsMd. Shahadat Hossain
 
FINITE ELEMENT MODELING, ANALYSIS AND VALIDATION OF THE SHEAR CAPACITY OF RC ...
FINITE ELEMENT MODELING, ANALYSIS AND VALIDATION OF THE SHEAR CAPACITY OF RC ...FINITE ELEMENT MODELING, ANALYSIS AND VALIDATION OF THE SHEAR CAPACITY OF RC ...
FINITE ELEMENT MODELING, ANALYSIS AND VALIDATION OF THE SHEAR CAPACITY OF RC ...Md. Shahadat Hossain
 
Rectangular beam design by WSD method (singly & doubly reinforcement)
Rectangular beam design by WSD method (singly & doubly reinforcement)Rectangular beam design by WSD method (singly & doubly reinforcement)
Rectangular beam design by WSD method (singly & doubly reinforcement)Md. Shahadat Hossain
 

Mais de Md. Shahadat Hossain (17)

Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)
 
Ssb04 detailed design of portal frames
Ssb04 detailed design of portal framesSsb04 detailed design of portal frames
Ssb04 detailed design of portal frames
 
Skills m08 e_portalframes_singlestoreybuildings
Skills m08 e_portalframes_singlestoreybuildingsSkills m08 e_portalframes_singlestoreybuildings
Skills m08 e_portalframes_singlestoreybuildings
 
Setting out a building
Setting out a buildingSetting out a building
Setting out a building
 
Etabs multistory-steel
Etabs multistory-steelEtabs multistory-steel
Etabs multistory-steel
 
Cantilever retaining wall design example
Cantilever retaining wall design exampleCantilever retaining wall design example
Cantilever retaining wall design example
 
Bridge facts
Bridge factsBridge facts
Bridge facts
 
Steel building design worked example
Steel building design worked exampleSteel building design worked example
Steel building design worked example
 
Optimized modeling and design of steel structures using etabs
Optimized modeling and design of steel structures using etabsOptimized modeling and design of steel structures using etabs
Optimized modeling and design of steel structures using etabs
 
Pile design guide (Collected)
Pile design guide (Collected)Pile design guide (Collected)
Pile design guide (Collected)
 
Pile design guide (Collected)
Pile design guide (Collected)Pile design guide (Collected)
Pile design guide (Collected)
 
Rebar Sizes
Rebar SizesRebar Sizes
Rebar Sizes
 
Shallow Foundation
Shallow FoundationShallow Foundation
Shallow Foundation
 
Cast in situ Pile
Cast in situ PileCast in situ Pile
Cast in situ Pile
 
FINITE ELEMENT MODELING, ANALYSIS AND VALIDATION OF THE SHEAR CAPACITY OF RC ...
FINITE ELEMENT MODELING, ANALYSIS AND VALIDATION OF THE SHEAR CAPACITY OF RC ...FINITE ELEMENT MODELING, ANALYSIS AND VALIDATION OF THE SHEAR CAPACITY OF RC ...
FINITE ELEMENT MODELING, ANALYSIS AND VALIDATION OF THE SHEAR CAPACITY OF RC ...
 
Paint-Quantity surveying report
Paint-Quantity surveying reportPaint-Quantity surveying report
Paint-Quantity surveying report
 
Rectangular beam design by WSD method (singly & doubly reinforcement)
Rectangular beam design by WSD method (singly & doubly reinforcement)Rectangular beam design by WSD method (singly & doubly reinforcement)
Rectangular beam design by WSD method (singly & doubly reinforcement)
 

Último

Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"mphochane1998
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxnuruddin69
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...Health
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 

Último (20)

Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
+97470301568>> buy weed in qatar,buy thc oil qatar,buy weed and vape oil in d...
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 

Formwork

  • 1. FORMWORK Introduction: The term ‘formwork’ includes the actual material contact with the concrete, known as form face, and all the necessary associated supporting structure. Formwork is a die or a mould including all supporting structures, used to shape and support the concrete until it attains sufficient strength to carry its own weight. It should be capable of carrying all imposed dead and live loads apart from its own weight. Formwork can be made out of a large variety of materials. Depending upon on the different materials it can be divided into the following categories. Such as – 1. Timber formwork 2. Plywood formwork 3. Steel formwork 4. Aluminium formwork 5. Plastics The material most commonly being used to date is timber. However, due to the depleting forest reserves and increasing cost of timber the use of alternate materials such as plywood and steel has become prominent. More recently, materials such as plastics and fiberglass are also being used for pre-fabricating formwork. The type of material to be used depends on the nature of construction as well as availability and cost of material.
  • 2. There are different types of formwork available for different purposes. Generally, the formworks for vertical concreting are called wall forms and those for horizontal concreting are called slab or floor forms. The various types of formwork are available today. Such as- a. Climbing formwork b. Sliding formwork c. Permanent formwork d. Special formwork etc. Scope:  Formwork is used to give different shapes and sizes as needed in the construction.  It is needed to contain the concrete with the reinforcement to adjust with it.  It is also being treated as a support for all our required construction.  For rounded wall , formwork is constructed.  Procedure: The construction of formwork generally involves the following operations. i. Propping and Centering ii. Shuttering iii. Provision of chamber iv. Cleaning and surface treatment In a building construction formworks are done generally for :-  stairs
  • 3.  column  beam and slab For the stairs, at first the timber as a flight is placed from the floor level to the ‘landing’ for stair bottom. Then the landing as well as another flight is placed one landing to another. These all timbers are supported by the bamboo pieces and and small pieces of timber to connect with the flight and the landing. Then the sides are being attached. Now the reinforcement bars are laid down as the design is made. Afterwards, for the shape of the steps , the risers are jointed between the timber sides keeping a distance from the riser’s bottom to the flight surface. Fig: Formwork of stair including riser,sides,flight For the column, steel shutter is used covering the reinforcement. Timber is also can be used for shuttering. These shutters are supported by the steel props as well as with some steel rods which are connected with ‘Turn’ . The shutterings are attached with bolt but if timber is used for shuttering, it is connected with wood pieces.
  • 4. Fig: Steel shutter,steel props,hooked rod For floor slab, shuttering for slab and beam is combinedly formed. To fit the shuttering of bottom of the beam timber is used but at first the level is measured with the water level. Dasha is used to support the bottom shutter of the beam which is fitted on the column and on the center steel props are used to support it. Beam’s side shutter is fitted, keeping the thickness of slab accurate. It is made leak proof. Fig: Beam bottom,side,supported bamboo Fig: Runner,steel props,plywood Then, for the slab shuttering, pieces of timber is used which is jointed from on end of the slab to the other end It is known as runner. On it steel grill and plain sheet are placed to complete the
  • 5. formwork of the slab. Instead of steel grill and plain sheet , plywood is also can be used. The whole shuttering should be leak proof. In case of steel shutter, glue can be used to fill the pores. The whole shuttering is supported on the steel props or bamboo. These should be placed verticallly. In case of bamboo its dia should be 3 inches and matured one is used. Incase of 1st floor, the sand is being compacted a piece of timber is placed under each bamboo. Commonly, the gap between props is maintained 2 - 2.5 feet. If we use the pieco beam under the steel shutter as a support then for a long span, we can reduce the quantity of steel props, which is placed keeping 3 meter gaps from one another. Again as previous, the level is measured of the slab and beam shutter with the water level. If the level is not maintained, then with the level instrument it is levelled accurately. After the shuttering, the formwork should be cleaned of all rubbish particularly the sawdust shaving and chippings etc. The surface should be wetted with water as the concrete should come to well contact. Removing the formwork is also an important part of formwork.It should be done in the following order of sequence-  Shuttering forming vertical faces of walls, beams, and columns sides should be removed first.  Shuttering forming soffit to beams, girders or other heavily loaded member should be removed in the end.
  • 6. DURATION TAKEN FOR REMOVAL OF FORMWORK: 1 WALLS COLUMNS & VERTICAL SIDES OF BEAMS 1-2 DAY 2 SLABS 3 DAYS 3 BEAM SOFFIT 7 DAYS 4 REMOVAL OF PROPS TO SLABS A) SLAB SPANNINIG UPTO 4.5M 7 DAYS B) SLAB SPANNINIG OVER 4.5M 14 DAYS 5 REMOVAL OF PROPS TO BEAMS AND ARCHES A) SPANNING UPTO 6 MTS 14 DAYS B) SPANNING OVER 6 MTS 21 DAYS Limitations:  In practical sites, leak proof is not maintained perfectly.  Sometimes the chamber shapes are deflected from the actual position. Therefore, the placement sometimes changes of beam or other.  Distance between steel props are not maintained. Therefore, bending of shuttering is occured .
  • 7. Conclusion: The formwork should be made with good quality material and constructed properly. The type of material to be used for formwork depends upon the nature of construction as well as the availability and cost of material. In constructing floor slab, we can use plywood as shuttering instead of timber planks. This type of shuttering ensures quality surface finish that is necessary for floors. The material of the formwork should be cheap, easily available and should be suitable for re-use several times. Nowadays , steel formwork is widely used in construction as it can be re-used because it is not easily get damaged. But for the small construction and no need of re-use ,in that type of construction timber formwork is cheaper than others. References: 1. 30, East tejturi bazar Tejgaon,Dhaka. 2. A construction site of a hospital opposite to AUST Love road,Dhaka.