SlideShare uma empresa Scribd logo
1 de 25
SATHYAN S
CIVIL ENGINEERING
KIOT,SALEM.
The water supply system made by pipes of different
lengths which are connected to form a one continuous
length of pipe line. Such connections are called as pipe
joints.
The design of these joints mainly depends on the condition
of the pipe, internal water pressure and the condition of
the support.
Spigot and socket
joint
Expansion joint
Flanged joint
Mechanical joint
Flexible joint
Screwed joint
Collar joint
A.C pipe joint
 Bell and spigot joint
 Used for cast iron pipes
 Enlarged end – socket
 Normal end - spigot
 A few strands of jute is wrapped
around the spigot .
 Remaining space b/w socket
and spigot is finally filled with
molten lead .
 Quantity of lead needed per
joint
- 3.5 to 4 kg for 15cm dia pipe,
- 45 to 50 kg for 1.2m dia pipe.
 Used at places where the
pipes expand or contract
due to change in
atmospheric temperature
and thus setting of thermal
stresses in pipes.
 Socket end is cast flanged
 Spigot end is plain
 On expansion, socket end
moves forward, the gap just
closed.
 On contraction, the socket
end moves backward
creating gap.
 Rigid and strong
 Expensive and mostly
used for indoor works
– pumping stations,
filter plants.
 They are fixed by
means of nuts and
bolts.
 It can be disjointed if
needed .
 Used to join the
plain ends of CI
pipes
 Strong and rigid
 Can withstand
vibrations - useful
for pipes to be
carried over
bridges or below
bridges in
hangers.
 Used where large
scale flexibilities
are required.
 Ex: River with
uneven beds, on
curves.
 Socket – spherical
 Spigot – plain end
having bead.
 Used for connecting
smaller dia of cast iron
, wrought iron
,galvanised pipe .
 It has internal
threads.
 The joint zinc paint or
hemp yarn should be
placed on pipe .
Used to joint big dia. Concrete and
asbestos cement pipe.
1:1 cement mortar is filled in space .
Used for small diameter pipes
1. Detailed map preparation.
2. Centre line marking.
3. Unloading.
4. Storing.
5. Cutting.
6. Trenches.
7. Laying
8. Back filling and tamping.
 Map showing all roads, cable lines, lanes etc., is prepared.
 Pipe line with size and length is marked.
 The position of existing pipe lines, curb lines, sewer lines will also be marked .
 Transformation from map to site.
 Stakes driven at 30m interval on straight line .
 stakes will be 7-15m on curves.
 Up to 60kg – 2persons .
 Above 60 kg – wagon/truck by holding it in rope and slides over
planks set not steeper than 45°.
 One pipe at a time.
 It may use carriers or be dragged or rolled along hard surfaces.
 To avoid damage.
 It should be stored horizontaly .
 It should be stored in layer
 Mark with a chalk at the point o cut.
 Cut with carpenter’s saw or hack saw .
 It must be a proper uniform cut.
It may be done either hand or
machine.
It must be done with required
gradient and depth.
When it is under a road way min.
cover of 1m is recommended.
Width at the base not less than
200mm on both side of the pipe.
Width may extend for joints .
 Pipes shall be lowered into the trenches by
means of suitable pulley blocks , shear legs,
chains, ropes .
 in no case the pipe shall be rolled and
dropped into the trench.
 Spigot of one pipe is carefully centred into
the socket of other pipe.
 In some clay soil (black cotton soil ) envelope
of 10 cm minimum tamped sand shall be
made around the pipe line.
Back filling must be done carefully to
avoid damages in pipe form falling of
boulders, lifting of pipes from sudden
floods.
Soil under and around the pipe line is
tamped to give continuous supports to
the pipe.
It may be done by tamping rod or
water consolidation.
The initial backfill done for 10 cm
thick.
 Step 1: From section to section. One section at a time.
 Step 2:Downstram valve is closed , upstream valve is opened to fill the water. Air
valves must be properly operated during filling.
 Step 3:Boththe sluice gates are closed .
 Step 4:Pressure gauge is fitted along the length of the pipes at holes which is left
for this purpose.
 Step 5:Section is connected to the delivery side of the pump through a small by-
pass valve to develop pressure in the section.
 Step 6:By-pass valve is closed.
 Step 7: It kept under pressure for 24 hours and inspected for possible defects
,leakages and joints.
 Step 8: Pipe line is disinfected . Add chlorine 50mg/l for 12 hours and the pipe is
emptied and flushed with treated water.
 HEAD LOSS DUE TO FRICTION .(major)
Manning’s formula
Darcy weisbach formula.
Hazen William’s formula.
Modified Hazen William’s formula.
 HEAD LOSS DUE TO BENDS AND CONSTRUCTION(MINOR)
 Internal water pressure
 External water pressure
 Temperature stress
 Water hammer.
 f=pd/zt.
 Above undisrubted soil(cohesion less soil)
 w=C
 Sluice valves / gates .
 Scour valves or blow of valves.
 Air valves.
 Pressure relief valves.
 Check valves
 Automatic shut of valves.
 Manholes.
 Insulation joints.
 Expansion joints.
 Anchorages.

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

Service Reservoirs 111001110634-phpapp02
Service Reservoirs 111001110634-phpapp02Service Reservoirs 111001110634-phpapp02
Service Reservoirs 111001110634-phpapp02
 
Canal alignment
Canal alignmentCanal alignment
Canal alignment
 
Estimation of storm sewage
Estimation of storm sewageEstimation of storm sewage
Estimation of storm sewage
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Collection and estimation of sewage
Collection and estimation of sewageCollection and estimation of sewage
Collection and estimation of sewage
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Storm water drainage
Storm water drainageStorm water drainage
Storm water drainage
 
Collection of sewage & estimation of its discharge
Collection of sewage & estimation of its dischargeCollection of sewage & estimation of its discharge
Collection of sewage & estimation of its discharge
 
Storm drainage design
Storm drainage designStorm drainage design
Storm drainage design
 
Chapter 7 conveyance of water
Chapter 7 conveyance of waterChapter 7 conveyance of water
Chapter 7 conveyance of water
 
Diversion headwork
Diversion headwork Diversion headwork
Diversion headwork
 
Design of sewers
Design of sewersDesign of sewers
Design of sewers
 
Well foundation
Well foundationWell foundation
Well foundation
 
Collection and Conveyance of Water
Collection and Conveyance of WaterCollection and Conveyance of Water
Collection and Conveyance of Water
 
Intake structures
Intake structures Intake structures
Intake structures
 
05 water supply system
05 water supply system05 water supply system
05 water supply system
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Pumping Stations
Pumping StationsPumping Stations
Pumping Stations
 
Reservoir Planning
Reservoir PlanningReservoir Planning
Reservoir Planning
 
river training work
river training workriver training work
river training work
 

Semelhante a Laying, jointing and testing of pipes

7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERINGVATSAL PATEL
 
study\source\ppt\Water control and diversion structures.ppt
study\source\ppt\Water control and diversion structures.pptstudy\source\ppt\Water control and diversion structures.ppt
study\source\ppt\Water control and diversion structures.pptpavik13
 
Unit ii introduction to water supply scheme
Unit  ii introduction to water supply schemeUnit  ii introduction to water supply scheme
Unit ii introduction to water supply schemeMadhukarJadhav8
 
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptxSewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptxPriyaTalwar8
 
Sanitary-chapter-4-Rashna-Pandit.pdf
Sanitary-chapter-4-Rashna-Pandit.pdfSanitary-chapter-4-Rashna-Pandit.pdf
Sanitary-chapter-4-Rashna-Pandit.pdfSatishMishra222706
 
Pipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and appliancePipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and applianceHarsha Singh
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTUVATSAL PATEL
 
Fit a toilet and bidet
Fit a toilet and bidetFit a toilet and bidet
Fit a toilet and bidetZulaiha Amaria
 
Raod side ditches
Raod side ditchesRaod side ditches
Raod side ditchesamanullahk
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling explorationjamali husain
 
Intake and Pipes joining
Intake and Pipes joiningIntake and Pipes joining
Intake and Pipes joiningLobsang Jampa
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsKHUSHBU SHAH
 
MEASURING, CUTTING, AND JOINING PIPES
MEASURING, CUTTING, AND JOINING PIPESMEASURING, CUTTING, AND JOINING PIPES
MEASURING, CUTTING, AND JOINING PIPESCrislyn Monterde
 
Design, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDesign, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDr. M. Kumaresan Hort.
 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point systemAnshuman Tyagi
 

Semelhante a Laying, jointing and testing of pipes (20)

PIPE LAYING
PIPE LAYINGPIPE LAYING
PIPE LAYING
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
Sewer appertunces
Sewer appertuncesSewer appertunces
Sewer appertunces
 
study\source\ppt\Water control and diversion structures.ppt
study\source\ppt\Water control and diversion structures.pptstudy\source\ppt\Water control and diversion structures.ppt
study\source\ppt\Water control and diversion structures.ppt
 
Unit ii introduction to water supply scheme
Unit  ii introduction to water supply schemeUnit  ii introduction to water supply scheme
Unit ii introduction to water supply scheme
 
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptxSewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
 
sewage layy out lec
sewage layy out lecsewage layy out lec
sewage layy out lec
 
Hydraulicdesignofsewer
HydraulicdesignofsewerHydraulicdesignofsewer
Hydraulicdesignofsewer
 
Sanitary-chapter-4-Rashna-Pandit.pdf
Sanitary-chapter-4-Rashna-Pandit.pdfSanitary-chapter-4-Rashna-Pandit.pdf
Sanitary-chapter-4-Rashna-Pandit.pdf
 
Sewer Appurtenances
Sewer AppurtenancesSewer Appurtenances
Sewer Appurtenances
 
Pipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and appliancePipes, fittings-fixtures and appliance
Pipes, fittings-fixtures and appliance
 
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
 
Fit a toilet and bidet
Fit a toilet and bidetFit a toilet and bidet
Fit a toilet and bidet
 
Raod side ditches
Raod side ditchesRaod side ditches
Raod side ditches
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
Intake and Pipes joining
Intake and Pipes joiningIntake and Pipes joining
Intake and Pipes joining
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
MEASURING, CUTTING, AND JOINING PIPES
MEASURING, CUTTING, AND JOINING PIPESMEASURING, CUTTING, AND JOINING PIPES
MEASURING, CUTTING, AND JOINING PIPES
 
Design, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDesign, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farming
 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point system
 

Mais de sathyan s

ADVANCED WATER TREATMENT PROCESS
ADVANCED WATER TREATMENT PROCESSADVANCED WATER TREATMENT PROCESS
ADVANCED WATER TREATMENT PROCESSsathyan s
 
Disposal of sewage and sludge management
Disposal of sewage and sludge managementDisposal of sewage and sludge management
Disposal of sewage and sludge managementsathyan s
 
Disaster management
Disaster managementDisaster management
Disaster managementsathyan s
 
Chain surveying
Chain surveyingChain surveying
Chain surveyingsathyan s
 
Geosynthetics and fibre textile
Geosynthetics and fibre textileGeosynthetics and fibre textile
Geosynthetics and fibre textilesathyan s
 
elements of seismology
elements of seismologyelements of seismology
elements of seismologysathyan s
 
Top 6 hardest languages to learn
Top 6 hardest languages to learnTop 6 hardest languages to learn
Top 6 hardest languages to learnsathyan s
 

Mais de sathyan s (7)

ADVANCED WATER TREATMENT PROCESS
ADVANCED WATER TREATMENT PROCESSADVANCED WATER TREATMENT PROCESS
ADVANCED WATER TREATMENT PROCESS
 
Disposal of sewage and sludge management
Disposal of sewage and sludge managementDisposal of sewage and sludge management
Disposal of sewage and sludge management
 
Disaster management
Disaster managementDisaster management
Disaster management
 
Chain surveying
Chain surveyingChain surveying
Chain surveying
 
Geosynthetics and fibre textile
Geosynthetics and fibre textileGeosynthetics and fibre textile
Geosynthetics and fibre textile
 
elements of seismology
elements of seismologyelements of seismology
elements of seismology
 
Top 6 hardest languages to learn
Top 6 hardest languages to learnTop 6 hardest languages to learn
Top 6 hardest languages to learn
 

Último

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 

Último (20)

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 

Laying, jointing and testing of pipes

  • 2. The water supply system made by pipes of different lengths which are connected to form a one continuous length of pipe line. Such connections are called as pipe joints. The design of these joints mainly depends on the condition of the pipe, internal water pressure and the condition of the support.
  • 3. Spigot and socket joint Expansion joint Flanged joint Mechanical joint Flexible joint Screwed joint Collar joint A.C pipe joint
  • 4.  Bell and spigot joint  Used for cast iron pipes  Enlarged end – socket  Normal end - spigot  A few strands of jute is wrapped around the spigot .  Remaining space b/w socket and spigot is finally filled with molten lead .  Quantity of lead needed per joint - 3.5 to 4 kg for 15cm dia pipe, - 45 to 50 kg for 1.2m dia pipe.
  • 5.  Used at places where the pipes expand or contract due to change in atmospheric temperature and thus setting of thermal stresses in pipes.  Socket end is cast flanged  Spigot end is plain  On expansion, socket end moves forward, the gap just closed.  On contraction, the socket end moves backward creating gap.
  • 6.  Rigid and strong  Expensive and mostly used for indoor works – pumping stations, filter plants.  They are fixed by means of nuts and bolts.  It can be disjointed if needed .
  • 7.  Used to join the plain ends of CI pipes  Strong and rigid  Can withstand vibrations - useful for pipes to be carried over bridges or below bridges in hangers.
  • 8.  Used where large scale flexibilities are required.  Ex: River with uneven beds, on curves.  Socket – spherical  Spigot – plain end having bead.
  • 9.  Used for connecting smaller dia of cast iron , wrought iron ,galvanised pipe .  It has internal threads.  The joint zinc paint or hemp yarn should be placed on pipe .
  • 10. Used to joint big dia. Concrete and asbestos cement pipe. 1:1 cement mortar is filled in space .
  • 11. Used for small diameter pipes
  • 12.
  • 13. 1. Detailed map preparation. 2. Centre line marking. 3. Unloading. 4. Storing. 5. Cutting. 6. Trenches. 7. Laying 8. Back filling and tamping.
  • 14.  Map showing all roads, cable lines, lanes etc., is prepared.  Pipe line with size and length is marked.  The position of existing pipe lines, curb lines, sewer lines will also be marked .
  • 15.  Transformation from map to site.  Stakes driven at 30m interval on straight line .  stakes will be 7-15m on curves.
  • 16.  Up to 60kg – 2persons .  Above 60 kg – wagon/truck by holding it in rope and slides over planks set not steeper than 45°.  One pipe at a time.  It may use carriers or be dragged or rolled along hard surfaces.
  • 17.  To avoid damage.  It should be stored horizontaly .  It should be stored in layer  Mark with a chalk at the point o cut.  Cut with carpenter’s saw or hack saw .  It must be a proper uniform cut.
  • 18. It may be done either hand or machine. It must be done with required gradient and depth. When it is under a road way min. cover of 1m is recommended. Width at the base not less than 200mm on both side of the pipe. Width may extend for joints .
  • 19.  Pipes shall be lowered into the trenches by means of suitable pulley blocks , shear legs, chains, ropes .  in no case the pipe shall be rolled and dropped into the trench.  Spigot of one pipe is carefully centred into the socket of other pipe.  In some clay soil (black cotton soil ) envelope of 10 cm minimum tamped sand shall be made around the pipe line.
  • 20. Back filling must be done carefully to avoid damages in pipe form falling of boulders, lifting of pipes from sudden floods. Soil under and around the pipe line is tamped to give continuous supports to the pipe. It may be done by tamping rod or water consolidation. The initial backfill done for 10 cm thick.
  • 21.  Step 1: From section to section. One section at a time.  Step 2:Downstram valve is closed , upstream valve is opened to fill the water. Air valves must be properly operated during filling.  Step 3:Boththe sluice gates are closed .  Step 4:Pressure gauge is fitted along the length of the pipes at holes which is left for this purpose.  Step 5:Section is connected to the delivery side of the pump through a small by- pass valve to develop pressure in the section.  Step 6:By-pass valve is closed.  Step 7: It kept under pressure for 24 hours and inspected for possible defects ,leakages and joints.  Step 8: Pipe line is disinfected . Add chlorine 50mg/l for 12 hours and the pipe is emptied and flushed with treated water.
  • 22.  HEAD LOSS DUE TO FRICTION .(major) Manning’s formula Darcy weisbach formula. Hazen William’s formula. Modified Hazen William’s formula.  HEAD LOSS DUE TO BENDS AND CONSTRUCTION(MINOR)
  • 23.  Internal water pressure  External water pressure  Temperature stress  Water hammer.
  • 24.  f=pd/zt.  Above undisrubted soil(cohesion less soil)  w=C
  • 25.  Sluice valves / gates .  Scour valves or blow of valves.  Air valves.  Pressure relief valves.  Check valves  Automatic shut of valves.  Manholes.  Insulation joints.  Expansion joints.  Anchorages.