2014 PV Distribution System Modeling Workshop: European codes & guidelines for the application of advanced grid support functions of inverters: Roland Bruendlinger, AIT Austrian Institute of Technology
2014 PV Distribution System Modeling Workshop: European codes & guidelines for the application of advanced grid support functions of inverters: Roland Bruendlinger, AIT Austrian Institute of Technology
Digital transformation for aftermarket sales service
Semelhante a 2014 PV Distribution System Modeling Workshop: European codes & guidelines for the application of advanced grid support functions of inverters: Roland Bruendlinger, AIT Austrian Institute of Technology
Semelhante a 2014 PV Distribution System Modeling Workshop: European codes & guidelines for the application of advanced grid support functions of inverters: Roland Bruendlinger, AIT Austrian Institute of Technology (20)
2014 PV Distribution System Modeling Workshop: European codes & guidelines for the application of advanced grid support functions of inverters: Roland Bruendlinger, AIT Austrian Institute of Technology
1. 123.05.2014
European codes & guidelines for the application
of advanced grid support functions of inverters
Roland Bründlinger
Senior Engineer
AIT Austrian Institute of Technology, Vienna, Austria
PV Distribution System Modeling Workshop, Santa Clara, May 6, 2014
2. Contents
Background – Development and challenges of grid connected PV in Europe
Overview of current grid codes and requirements in Europe
Outlook on the new ENTSO-E Network Code
Summary & recommendations
223.05.2014 223/05/2014
3. Contents
Background – Development and challenges of grid connected PV in Europe
Overview of current grid codes and requirements in Europe
Outlook on the new ENTSO-E Network Code
Summary & recommendations
323.05.2014 323/05/2014
4. Evolution of European cumulative installed PV capacity
Source:EPIA,”IEA-PVPSTask14,TransitionfromConsumptiontoSupplyGrids,tobepublished
For comparison:
Total installed generation capacity in
EU27 2011 approx. 850 GW (eurelectric figures)
5. Net power generation capacity added in the EU28 in 2013
Source:EPIA,ESTELA,EU-OEA,EWEA,PlattsPowerVision,PVCYCLE
MW
PV now covers 3% of the overall and 6% of the
peak electricity demand
PV has been the top newly-added generation
capacity together with wind for the 3rd year.
Within growing share of RES in the generation
mix, grid and market/system integration
challenges are becoming more and more
important for the future PV deployment.
6. Spatial distribution of installed capacity (W/per inhabitant)
Source: EPIA, ”Global Market Outlook 2017”, May 2013
Bavaria:
>800 W/inhabitant
Italy: >6% of
electricity demand
Some key facts about PV grid
connection in Europe (end
2013)
About 80 GW installed in
EU27
95% of the capacity is
connected at the
distribution levels
Numerous regions/DSOs
already coping with High
PV penetration (>100%)
PV has become a game
changer in the European
electricity market
7. The role of PV in the European national electricity systems
Key Challenges
Increased variability and
uncertainty
Increasing share of non-rotating
generation
Increasing share of distribution
system connected generation
Provision of grid support services
by RES?
Penetration levels in some regions
and countries have reached levels
where full PV grid integration
becomes critical to guarantee
operational stability
Coordinated development of Grid Code
requirements for PV and DG needed.
7
Source: EPIA 2013, Reservices Project 2014
8. Contents
Background – Development and challenges of grid connected PV in Europe
Overview of current grid codes and requirements in Europe
Outlook on the new ENTSO-E Network Code
Summary & recommendations
823.05.2014 823/05/2014
9. Framework for PV/DG interconnection in Europe
Country specific grid codes and standards
Up to now no EU wide directive on DER/PV grid
interconnection
Country specific grid codes, standards, DSO
guidelines…
Different legal and administrative levels
Fundamental differences between the countries
Generally complex, intransparent situation
Issues for manufacturers and project developers
Specific product settings for each country/market
Interpretation of the requirements and application in
practice
Increased costs and reduced competiveness
Critical issues for power system operation
Lack of coordination and compatibility
Risk of losing system security during critical events
due to undefined behavior of DER
95/23/2014
10. Current requirements for advanced grid support by PV
Connection to LV distribution grids
105/23/2014
Full set of advanced grid support
requirements mandatory for :
DE: Systems >16 A (2012)
AT: Systems >16 A (2013)
IT: Units >3 kVA (2012)
DK: Systems >16 A (2013)
Main functions:
Reactive power control (typ.
PF(P) characteristic
Frequency control P(f)
No trip at low frequency
Remote limitation of P output
(DE, AT, IT)
11. Current requirements for advanced grid support by PV
Connection to MV distribution grids
115/23/2014
Full set of advanced grid support
requirements:
DE (2008), IT (2011), AT (2013),
DK (2013), FR (2008)
Selected requirements:
ES, PT, UK, CZ, BE…
Typically for MW scale
generators
Main functions:
Reactive power control
Voltage control PF(U)
Frequency control P(f)
Remote power limitation
FRT (=LVRT)
12. Contents
Background – Development and challenges of grid connected PV in Europe
Overview of current grid codes and requirements in Europe
Outlook on the new ENTSO-E Network Code
Summary & recommendations
1223.05.2014 1223/05/2014
13. Framework for PV/DG interconnection in Europe
The new ENTSO-E Network Codes
2009: European Agency for the Cooperation of
Energy Regulators (ACER) issued an official
mandate to ENTSO-E (European Network of
Electricity TSOs) to develop draft “Network Codes”
A set of rules applying to one aspect of the
energy sector
Developed by ACER, ENTSO-E & market
participants (transparent process)
Become legally binding (comitology process)
Ultimately have the same status as a
European Regulation
Goal: Strengthen the European internal electricity
market
135/23/2014
Source:ENTSO-E
14. Framework for PV/DG interconnection in Europe
The new ENTSO-E Network Code RfG
Network Code on “Requirements for Grid Connection applicable to all
Generators (RfG)” is one of the first projects, aiming at
Establishing legally binding EU wide harmonization of grid
interconnection requirements
Ensuring and increasing the system security with a growing share of
RES and variable generation
Avoiding future regret and costly retrofits to ensure security of supply
145/23/2014
Source:ENTSO-E
15. Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
Basic approach
Applicable to all generators >0.8 kW
Balance European settings and regional specifics
Proportional approach from smallest generation to
largest plants
Application for (all) new generators in order to
ensure system security in a changing environment
accommodate evolution in the generation portfolio
reduce costs through standardization.
Application for existing generators (retrofit) only if
technically justifiable,
benefits demonstrated by Cost Benefit Analysis
approved by National Regulatory Authority
155/23/2014 https://www.entsoe.eu/major-projects/network-code-development/requirements-for-generators/
16. Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
Standardized definition of generator types and
associated functionalities/ requirements depending on
transmission grid region
connection level (voltage)
generator capacity and technology (synchronous or converter based)
165/23/2014
Type D
Type C
Type B
Type A
• Wide-scale network operation and stability
• Balancing services
• Stable and controllable dynamic response
• covering all operational network states
• Automated dynamic response and resilience to events
• System operator control
• Basic capabilities to withstand wide-scale critical events
• Limited automated response and control
17. Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
175/23/2014
18. Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
Overview of aspects and requirements addressed by the RfG
185/23/2014
Addressed system
aspect
Requirement Type
A
Type
B
Type
C/D
Frequency stability Operating frequency ranges X X X
RoCoF withstand capability X X X
Limited Frequency Sensitive Mode - Overfrequency X X X
Constant active power output regardless of changes in
Frequency
X X X
Limitation of power reduction at underfrequency X X X
Automatic connection X X X
Remote ON/OFF X X
Active power reduction remote control X
Additional requirements related to frequency control X
Provision of synthetic inertia X
19. Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
195/23/2014
Addressed system
aspect
Requirement Type
A
Type
B
Type
C/D
Robustness of
power generating
modules
Fault-ride-through X X
Post-fault active power recovery X X
System restoration Coordinated reconnection X X
General system
management
Control schemes and settings X X
Electrical protection and control schemes and settings X X
Priority ranking of protection and control X X
Information exchange X X
Additional requirements to monitoring X
Voltage stability Reactive power capability X X
Fast reacting reactive power injection X X
Additional requirements for reactive power capability
and control modes
X
Overview of aspects and requirements addressed by the RfG
20. Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
205/23/2014
Some further aspects related to the RfG
Eventually, the RfG will have the character of a EU directive Later
amendments will be very difficult
Definitions in RfG leave wide room for variation/interpretation by the local
TSOs/NRAs
After its implementation the RfG will
Define system relevant minimum requirements for all generators
Provide a basis for national codes and standards
However, the RfG will not
Provide a true harmonization of the requirements across Europe
Provide “product specifications” which can be easily be implemented by
manufacturers
Provide harmonized certification, type testing or modeling procedures
Provide requirements related to communication protocols or technologies
(e.g. IEC 61850, DNP3)
21. Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
215/23/2014
Recent steps
Jan-March 2012: Open public consultation with all stakeholders
July 2012 – March 2013: Review of RfG draft by ACER
October 2013: Implementation Guideline published
European Commission comitology procedure started in January 2014
Further implementation of the code at national level via existing processes
Definition of detailed local requirements and conditions by national
TSOs in collaboration with NRAs
Amendments/ modifications to existing national guidelines
Planned to be legally binding from 2017
22. Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
225/23/2014
Resources
RfG webpage:
https://www.entsoe.eu/major-projects/network-code-
development/requirements-for-generators/
Final version of RfG Network code:
https://www.entsoe.eu/fileadmin/user_upload/_library/resources/RfG/13
0308_Final_Version_NC_RfG.pdf
Implementation Guideline:
https://www.entsoe.eu/fileadmin/user_upload/_library/resources/RfG/13
1016_-_NC_RfG_implementation_guideline.pdf
23. Contents
Background – Development and challenges of grid connected PV in Europe
Overview of current grid codes and requirements in Europe
Outlook on the new ENTSO-E Network Code
Summary & recommendations
2323.05.2014 2323/05/2014
24. Summary and key conclusions
In Europe the role of PV has changed from a marginal technology to a
visible player in the electricity market
PV and grid parity further massive deployment in short and near term
In particular Germany acts as show-case for high-penetration PV and
provision of grid support (voltage, frequency…) by decentralised PV
Coordinated approach for integrating PV on high penetration levels is crucial
to ensure system stability and security
Addressed by upcoming ENTSO-E network code “Requirements for
Generators”
Open collaboration between TSOs, DSOs and PV industry necessary
Redefinition of the interaction between DSOs and TSOs needed
The development in some European regions and countries shows that large-
scale integration of PV is technically feasible without threatening security of
supply.
245/23/2014
25. PV&RES grid integration
A brief overview of current RTD&D projects in Europe
ECOGRID EU www.eu-ecogrid.net
metaPV www.metapv.eu
PV GRID http://www.pvgrid.eu
REserviceS www.reservices-project.eu
IGREENGrid www.igreengrid-fp7.eu
PV PARITY www.pvparity.eu
And numerous other national projects/demonstrators
2523.05.2014
26. 2623.05.2014
Thank you very much for your attention!
Roland Bründlinger
AIT Austrian Institute of Technology
Giefinggasse 2, 1210 Wien, Austria
roland.bruendlinger@ait.ac.at