SlideShare uma empresa Scribd logo
1 de 26
Baixar para ler offline
123.05.2014
European codes & guidelines for the application
of advanced grid support functions of inverters
Roland Bründlinger
Senior Engineer
AIT Austrian Institute of Technology, Vienna, Austria
PV Distribution System Modeling Workshop, Santa Clara, May 6, 2014
Contents
 Background – Development and challenges of grid connected PV in Europe
 Overview of current grid codes and requirements in Europe
 Outlook on the new ENTSO-E Network Code
 Summary & recommendations
223.05.2014 223/05/2014
Contents
 Background – Development and challenges of grid connected PV in Europe
 Overview of current grid codes and requirements in Europe
 Outlook on the new ENTSO-E Network Code
 Summary & recommendations
323.05.2014 323/05/2014
Evolution of European cumulative installed PV capacity
Source:EPIA,”IEA-PVPSTask14,TransitionfromConsumptiontoSupplyGrids,tobepublished
For comparison:
Total installed generation capacity in
EU27 2011 approx. 850 GW (eurelectric figures)
Net power generation capacity added in the EU28 in 2013
Source:EPIA,ESTELA,EU-OEA,EWEA,PlattsPowerVision,PVCYCLE
MW
 PV now covers 3% of the overall and 6% of the
peak electricity demand
 PV has been the top newly-added generation
capacity together with wind for the 3rd year.
 Within growing share of RES in the generation
mix, grid and market/system integration
challenges are becoming more and more
important for the future PV deployment.
Spatial distribution of installed capacity (W/per inhabitant)
Source: EPIA, ”Global Market Outlook 2017”, May 2013
Bavaria:
>800 W/inhabitant
Italy: >6% of
electricity demand
 Some key facts about PV grid
connection in Europe (end
2013)
 About 80 GW installed in
EU27
 95% of the capacity is
connected at the
distribution levels
 Numerous regions/DSOs
already coping with High
PV penetration (>100%)
 PV has become a game
changer in the European
electricity market
The role of PV in the European national electricity systems
 Key Challenges
 Increased variability and
uncertainty
 Increasing share of non-rotating
generation
 Increasing share of distribution
system connected generation
 Provision of grid support services
by RES?
 Penetration levels in some regions
and countries have reached levels
where full PV grid integration
becomes critical to guarantee
operational stability
 Coordinated development of Grid Code
requirements for PV and DG needed.
7
Source: EPIA 2013, Reservices Project 2014
Contents
 Background – Development and challenges of grid connected PV in Europe
 Overview of current grid codes and requirements in Europe
 Outlook on the new ENTSO-E Network Code
 Summary & recommendations
823.05.2014 823/05/2014
Framework for PV/DG interconnection in Europe
Country specific grid codes and standards
 Up to now no EU wide directive on DER/PV grid
interconnection
 Country specific grid codes, standards, DSO
guidelines…
 Different legal and administrative levels
 Fundamental differences between the countries
 Generally complex, intransparent situation
 Issues for manufacturers and project developers
 Specific product settings for each country/market
 Interpretation of the requirements and application in
practice
 Increased costs and reduced competiveness
 Critical issues for power system operation
 Lack of coordination and compatibility
 Risk of losing system security during critical events
due to undefined behavior of DER
95/23/2014
Current requirements for advanced grid support by PV
Connection to LV distribution grids
105/23/2014
 Full set of advanced grid support
requirements mandatory for :
 DE: Systems >16 A (2012)
 AT: Systems >16 A (2013)
 IT: Units >3 kVA (2012)
 DK: Systems >16 A (2013)
 Main functions:
 Reactive power control (typ.
PF(P) characteristic
 Frequency control P(f)
 No trip at low frequency
 Remote limitation of P output
(DE, AT, IT)
Current requirements for advanced grid support by PV
Connection to MV distribution grids
115/23/2014
Full set of advanced grid support
requirements:
 DE (2008), IT (2011), AT (2013),
DK (2013), FR (2008)
Selected requirements:
 ES, PT, UK, CZ, BE…
 Typically for MW scale
generators
Main functions:
 Reactive power control
 Voltage control PF(U)
 Frequency control P(f)
 Remote power limitation
 FRT (=LVRT)
Contents
 Background – Development and challenges of grid connected PV in Europe
 Overview of current grid codes and requirements in Europe
 Outlook on the new ENTSO-E Network Code
 Summary & recommendations
1223.05.2014 1223/05/2014
Framework for PV/DG interconnection in Europe
The new ENTSO-E Network Codes
 2009: European Agency for the Cooperation of
Energy Regulators (ACER) issued an official
mandate to ENTSO-E (European Network of
Electricity TSOs) to develop draft “Network Codes”
 A set of rules applying to one aspect of the
energy sector
 Developed by ACER, ENTSO-E & market
participants (transparent process)
 Become legally binding (comitology process)
 Ultimately have the same status as a
European Regulation
 Goal: Strengthen the European internal electricity
market
135/23/2014
Source:ENTSO-E
Framework for PV/DG interconnection in Europe
The new ENTSO-E Network Code RfG
 Network Code on “Requirements for Grid Connection applicable to all
Generators (RfG)” is one of the first projects, aiming at
 Establishing legally binding EU wide harmonization of grid
interconnection requirements
 Ensuring and increasing the system security with a growing share of
RES and variable generation
 Avoiding future regret and costly retrofits to ensure security of supply
145/23/2014
Source:ENTSO-E
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
 Basic approach
 Applicable to all generators >0.8 kW
 Balance European settings and regional specifics
 Proportional approach from smallest generation to
largest plants
 Application for (all) new generators in order to
 ensure system security in a changing environment
 accommodate evolution in the generation portfolio
 reduce costs through standardization.
 Application for existing generators (retrofit) only if
 technically justifiable,
 benefits demonstrated by Cost Benefit Analysis
 approved by National Regulatory Authority
155/23/2014 https://www.entsoe.eu/major-projects/network-code-development/requirements-for-generators/
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
 Standardized definition of generator types and
associated functionalities/ requirements depending on
 transmission grid region
 connection level (voltage)
 generator capacity and technology (synchronous or converter based)
165/23/2014
Type D
Type C
Type B
Type A
• Wide-scale network operation and stability
• Balancing services
• Stable and controllable dynamic response
• covering all operational network states
• Automated dynamic response and resilience to events
• System operator control
• Basic capabilities to withstand wide-scale critical events
• Limited automated response and control
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
175/23/2014
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
 Overview of aspects and requirements addressed by the RfG
185/23/2014
Addressed system
aspect
Requirement Type
A
Type
B
Type
C/D
Frequency stability Operating frequency ranges X X X
RoCoF withstand capability X X X
Limited Frequency Sensitive Mode - Overfrequency X X X
Constant active power output regardless of changes in
Frequency
X X X
Limitation of power reduction at underfrequency X X X
Automatic connection X X X
Remote ON/OFF X X
Active power reduction remote control X
Additional requirements related to frequency control X
Provision of synthetic inertia X
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
195/23/2014
Addressed system
aspect
Requirement Type
A
Type
B
Type
C/D
Robustness of
power generating
modules
Fault-ride-through X X
Post-fault active power recovery X X
System restoration Coordinated reconnection X X
General system
management
Control schemes and settings X X
Electrical protection and control schemes and settings X X
Priority ranking of protection and control X X
Information exchange X X
Additional requirements to monitoring X
Voltage stability Reactive power capability X X
Fast reacting reactive power injection X X
Additional requirements for reactive power capability
and control modes
X
 Overview of aspects and requirements addressed by the RfG
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
205/23/2014
 Some further aspects related to the RfG
 Eventually, the RfG will have the character of a EU directive  Later
amendments will be very difficult
 Definitions in RfG leave wide room for variation/interpretation by the local
TSOs/NRAs
 After its implementation the RfG will
 Define system relevant minimum requirements for all generators
 Provide a basis for national codes and standards
 However, the RfG will not
 Provide a true harmonization of the requirements across Europe
 Provide “product specifications” which can be easily be implemented by
manufacturers
 Provide harmonized certification, type testing or modeling procedures
 Provide requirements related to communication protocols or technologies
(e.g. IEC 61850, DNP3)
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
215/23/2014
 Recent steps
 Jan-March 2012: Open public consultation with all stakeholders
 July 2012 – March 2013: Review of RfG draft by ACER
 October 2013: Implementation Guideline published
 European Commission comitology procedure started in January 2014
 Further implementation of the code at national level via existing processes
 Definition of detailed local requirements and conditions by national
TSOs in collaboration with NRAs
 Amendments/ modifications to existing national guidelines
 Planned to be legally binding from 2017
Framework for PV/DG interconnection in Europe
ENTSO-E RfG Network Code
225/23/2014
 Resources
 RfG webpage:
https://www.entsoe.eu/major-projects/network-code-
development/requirements-for-generators/
 Final version of RfG Network code:
https://www.entsoe.eu/fileadmin/user_upload/_library/resources/RfG/13
0308_Final_Version_NC_RfG.pdf
 Implementation Guideline:
https://www.entsoe.eu/fileadmin/user_upload/_library/resources/RfG/13
1016_-_NC_RfG_implementation_guideline.pdf
Contents
 Background – Development and challenges of grid connected PV in Europe
 Overview of current grid codes and requirements in Europe
 Outlook on the new ENTSO-E Network Code
 Summary & recommendations
2323.05.2014 2323/05/2014
Summary and key conclusions
 In Europe the role of PV has changed from a marginal technology to a
visible player in the electricity market
 PV and grid parity  further massive deployment in short and near term
 In particular Germany acts as show-case for high-penetration PV and
provision of grid support (voltage, frequency…) by decentralised PV
 Coordinated approach for integrating PV on high penetration levels is crucial
to ensure system stability and security
 Addressed by upcoming ENTSO-E network code “Requirements for
Generators”
 Open collaboration between TSOs, DSOs and PV industry necessary
 Redefinition of the interaction between DSOs and TSOs needed
 The development in some European regions and countries shows that large-
scale integration of PV is technically feasible without threatening security of
supply.
245/23/2014
PV&RES grid integration
A brief overview of current RTD&D projects in Europe
 ECOGRID EU www.eu-ecogrid.net
 metaPV www.metapv.eu
 PV GRID http://www.pvgrid.eu
 REserviceS www.reservices-project.eu
 IGREENGrid www.igreengrid-fp7.eu
 PV PARITY www.pvparity.eu
 And numerous other national projects/demonstrators
2523.05.2014
2623.05.2014
Thank you very much for your attention!
Roland Bründlinger
AIT Austrian Institute of Technology
Giefinggasse 2, 1210 Wien, Austria
roland.bruendlinger@ait.ac.at

Mais conteúdo relacionado

Mais procurados

Indian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyIndian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyMahesh Chandra Manav
 
powerline communication system
powerline communication systempowerline communication system
powerline communication systemAhmed Hassan
 
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...Mahesh Chandra Manav
 
Power line communication
Power line communicationPower line communication
Power line communicationAhmad AL CHAMI
 
Metro rail project in india year 2017
Metro rail project in india year 2017Metro rail project in india year 2017
Metro rail project in india year 2017Mahesh Chandra Manav
 
On-chip ultra low power optical wake-up receiver for wireless sensor nodes ta...
On-chip ultra low power optical wake-up receiver for wireless sensor nodes ta...On-chip ultra low power optical wake-up receiver for wireless sensor nodes ta...
On-chip ultra low power optical wake-up receiver for wireless sensor nodes ta...TELKOMNIKA JOURNAL
 
Link vue system and solar pv power plant protection
Link vue system and solar pv power plant protectionLink vue system and solar pv power plant protection
Link vue system and solar pv power plant protectionMahesh Chandra Manav
 
Power Distribution Overview
Power Distribution OverviewPower Distribution Overview
Power Distribution OverviewHIMADRI BANERJI
 
IRJET- Power Line Carrier Communication
IRJET- Power Line Carrier CommunicationIRJET- Power Line Carrier Communication
IRJET- Power Line Carrier CommunicationIRJET Journal
 
Project paper
Project paperProject paper
Project paperchigongo
 
A solution to remote detection of illegal electricity.
A solution to remote detection of illegal electricity.A solution to remote detection of illegal electricity.
A solution to remote detection of illegal electricity.Praveen Kumar
 
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...IRJET Journal
 
CDMA Based Secure Cellular Communication via Satellite Link
CDMA Based Secure Cellular Communication via Satellite LinkCDMA Based Secure Cellular Communication via Satellite Link
CDMA Based Secure Cellular Communication via Satellite LinkIRJET Journal
 
Telecom Pole Sites Solutions
Telecom Pole Sites SolutionsTelecom Pole Sites Solutions
Telecom Pole Sites Solutionslokeshgupta80
 

Mais procurados (20)

Indian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periortyIndian railway&metro rail,others electrical safety first periorty
Indian railway&metro rail,others electrical safety first periorty
 
powerline communication system
powerline communication systempowerline communication system
powerline communication system
 
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
JMV LPS Ltd Make in India Product for SolarPv,High Energy Storage and Electri...
 
Power line communication
Power line communicationPower line communication
Power line communication
 
Metro rail project in india year 2017
Metro rail project in india year 2017Metro rail project in india year 2017
Metro rail project in india year 2017
 
Power Line communication
Power Line communicationPower Line communication
Power Line communication
 
On-chip ultra low power optical wake-up receiver for wireless sensor nodes ta...
On-chip ultra low power optical wake-up receiver for wireless sensor nodes ta...On-chip ultra low power optical wake-up receiver for wireless sensor nodes ta...
On-chip ultra low power optical wake-up receiver for wireless sensor nodes ta...
 
Wireless Meter Bus
Wireless Meter BusWireless Meter Bus
Wireless Meter Bus
 
Link vue system and solar pv power plant protection
Link vue system and solar pv power plant protectionLink vue system and solar pv power plant protection
Link vue system and solar pv power plant protection
 
Phasor Measurement Unit (PMU)
 Phasor Measurement Unit (PMU) Phasor Measurement Unit (PMU)
Phasor Measurement Unit (PMU)
 
E011123541
E011123541E011123541
E011123541
 
Wireless charging scheme for medium power range application systems
Wireless charging scheme for medium power range application systemsWireless charging scheme for medium power range application systems
Wireless charging scheme for medium power range application systems
 
Power Distribution Overview
Power Distribution OverviewPower Distribution Overview
Power Distribution Overview
 
Oliver Spink
Oliver SpinkOliver Spink
Oliver Spink
 
IRJET- Power Line Carrier Communication
IRJET- Power Line Carrier CommunicationIRJET- Power Line Carrier Communication
IRJET- Power Line Carrier Communication
 
Project paper
Project paperProject paper
Project paper
 
A solution to remote detection of illegal electricity.
A solution to remote detection of illegal electricity.A solution to remote detection of illegal electricity.
A solution to remote detection of illegal electricity.
 
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
IRJET- Comparative Analysis of Different Converter Topologies Employed for Tr...
 
CDMA Based Secure Cellular Communication via Satellite Link
CDMA Based Secure Cellular Communication via Satellite LinkCDMA Based Secure Cellular Communication via Satellite Link
CDMA Based Secure Cellular Communication via Satellite Link
 
Telecom Pole Sites Solutions
Telecom Pole Sites SolutionsTelecom Pole Sites Solutions
Telecom Pole Sites Solutions
 

Destaque

Day-Ahead LMP Forecasting with AURORAxmp
Day-Ahead LMP Forecasting with AURORAxmpDay-Ahead LMP Forecasting with AURORAxmp
Day-Ahead LMP Forecasting with AURORAxmpEPIS Inc
 
Geographically Distributed Multi-Master MySQL Clusters
Geographically Distributed Multi-Master MySQL ClustersGeographically Distributed Multi-Master MySQL Clusters
Geographically Distributed Multi-Master MySQL ClustersContinuent
 
Formacion experto on line coaching familia
Formacion experto on line coaching familiaFormacion experto on line coaching familia
Formacion experto on line coaching familiaAECOFAM
 
Councillors and social media: winning friends and staying out of trouble online
Councillors and social media: winning friends and staying out of trouble onlineCouncillors and social media: winning friends and staying out of trouble online
Councillors and social media: winning friends and staying out of trouble onlineIngrid Koehler
 
Grand design winarsih
Grand design winarsihGrand design winarsih
Grand design winarsihwina arsih
 
Nodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmpNodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmpEPIS Inc
 
Grid 20/20 Public Policy and Wholesale Energy Markets
Grid 20/20 Public Policy and Wholesale Energy Markets Grid 20/20 Public Policy and Wholesale Energy Markets
Grid 20/20 Public Policy and Wholesale Energy Markets Daymark Energy Advisors
 
ArcLink - IIPC GA 2013
ArcLink - IIPC GA 2013ArcLink - IIPC GA 2013
ArcLink - IIPC GA 2013Ahmed AlSum
 
Coloring of asphalt
Coloring of asphaltColoring of asphalt
Coloring of asphaltLANXESS
 
Psicoterapia Integradora Humanista Ana Gimeno-Bayón y Ramón Rosal
Psicoterapia Integradora Humanista   Ana Gimeno-Bayón y Ramón RosalPsicoterapia Integradora Humanista   Ana Gimeno-Bayón y Ramón Rosal
Psicoterapia Integradora Humanista Ana Gimeno-Bayón y Ramón RosalSergioMontoya
 
3Gender and Energy Resource Management Projects
3Gender and Energy Resource Management Projects3Gender and Energy Resource Management Projects
3Gender and Energy Resource Management ProjectsNancy Drost
 
Realidad Virtual Nuevos Mundos Para La Psicoterapia Mackay
Realidad Virtual Nuevos Mundos Para La Psicoterapia MackayRealidad Virtual Nuevos Mundos Para La Psicoterapia Mackay
Realidad Virtual Nuevos Mundos Para La Psicoterapia Mackaymackayunah
 
Digital transformation for aftermarket sales service
Digital transformation for aftermarket sales serviceDigital transformation for aftermarket sales service
Digital transformation for aftermarket sales serviceJohn Mertl
 

Destaque (20)

8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
8.2_IEEE 1547 and Microgrids_Key_EPRI/SNL Microgrid Symposium
 
2014 PV Performance Modeling Workshop: Optimizing PV Designs with HelioScope:...
2014 PV Performance Modeling Workshop: Optimizing PV Designs with HelioScope:...2014 PV Performance Modeling Workshop: Optimizing PV Designs with HelioScope:...
2014 PV Performance Modeling Workshop: Optimizing PV Designs with HelioScope:...
 
2014 PV Distribution System Modeling Workshop: Interconnection Standards in C...
2014 PV Distribution System Modeling Workshop: Interconnection Standards in C...2014 PV Distribution System Modeling Workshop: Interconnection Standards in C...
2014 PV Distribution System Modeling Workshop: Interconnection Standards in C...
 
2014 PV Reliability, Operations & Maintenance Workshop: Unlocking Opportuniti...
2014 PV Reliability, Operations & Maintenance Workshop: Unlocking Opportuniti...2014 PV Reliability, Operations & Maintenance Workshop: Unlocking Opportuniti...
2014 PV Reliability, Operations & Maintenance Workshop: Unlocking Opportuniti...
 
Day-Ahead LMP Forecasting with AURORAxmp
Day-Ahead LMP Forecasting with AURORAxmpDay-Ahead LMP Forecasting with AURORAxmp
Day-Ahead LMP Forecasting with AURORAxmp
 
2014 PV Reliability, Operations & Maintenance Workshop: O&M with SCADA, AlsoE...
2014 PV Reliability, Operations & Maintenance Workshop: O&M with SCADA, AlsoE...2014 PV Reliability, Operations & Maintenance Workshop: O&M with SCADA, AlsoE...
2014 PV Reliability, Operations & Maintenance Workshop: O&M with SCADA, AlsoE...
 
Geographically Distributed Multi-Master MySQL Clusters
Geographically Distributed Multi-Master MySQL ClustersGeographically Distributed Multi-Master MySQL Clusters
Geographically Distributed Multi-Master MySQL Clusters
 
Formacion experto on line coaching familia
Formacion experto on line coaching familiaFormacion experto on line coaching familia
Formacion experto on line coaching familia
 
Councillors and social media: winning friends and staying out of trouble online
Councillors and social media: winning friends and staying out of trouble onlineCouncillors and social media: winning friends and staying out of trouble online
Councillors and social media: winning friends and staying out of trouble online
 
Grand design winarsih
Grand design winarsihGrand design winarsih
Grand design winarsih
 
Nodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmpNodal Insights for Generation Owners and Modeling with AURORAxmp
Nodal Insights for Generation Owners and Modeling with AURORAxmp
 
Grid 20/20 Public Policy and Wholesale Energy Markets
Grid 20/20 Public Policy and Wholesale Energy Markets Grid 20/20 Public Policy and Wholesale Energy Markets
Grid 20/20 Public Policy and Wholesale Energy Markets
 
ArcLink - IIPC GA 2013
ArcLink - IIPC GA 2013ArcLink - IIPC GA 2013
ArcLink - IIPC GA 2013
 
Coloring of asphalt
Coloring of asphaltColoring of asphalt
Coloring of asphalt
 
2014 PV Distribution System Modeling Workshop: CA Rule 21 Update: Tom Bialek,...
2014 PV Distribution System Modeling Workshop: CA Rule 21 Update: Tom Bialek,...2014 PV Distribution System Modeling Workshop: CA Rule 21 Update: Tom Bialek,...
2014 PV Distribution System Modeling Workshop: CA Rule 21 Update: Tom Bialek,...
 
Psicoterapia Integradora Humanista Ana Gimeno-Bayón y Ramón Rosal
Psicoterapia Integradora Humanista   Ana Gimeno-Bayón y Ramón RosalPsicoterapia Integradora Humanista   Ana Gimeno-Bayón y Ramón Rosal
Psicoterapia Integradora Humanista Ana Gimeno-Bayón y Ramón Rosal
 
3Gender and Energy Resource Management Projects
3Gender and Energy Resource Management Projects3Gender and Energy Resource Management Projects
3Gender and Energy Resource Management Projects
 
2014 PV Distribution System Modeling Workshop: Capabilities of Advanced Inver...
2014 PV Distribution System Modeling Workshop: Capabilities of Advanced Inver...2014 PV Distribution System Modeling Workshop: Capabilities of Advanced Inver...
2014 PV Distribution System Modeling Workshop: Capabilities of Advanced Inver...
 
Realidad Virtual Nuevos Mundos Para La Psicoterapia Mackay
Realidad Virtual Nuevos Mundos Para La Psicoterapia MackayRealidad Virtual Nuevos Mundos Para La Psicoterapia Mackay
Realidad Virtual Nuevos Mundos Para La Psicoterapia Mackay
 
Digital transformation for aftermarket sales service
Digital transformation for aftermarket sales serviceDigital transformation for aftermarket sales service
Digital transformation for aftermarket sales service
 

Semelhante a 2014 PV Distribution System Modeling Workshop: European codes & guidelines for the application of advanced grid support functions of inverters: Roland Bruendlinger, AIT Austrian Institute of Technology

30 11-2011 mart grid Jani Valtari Cleen Finpro seminar
30 11-2011 mart grid Jani Valtari Cleen Finpro seminar30 11-2011 mart grid Jani Valtari Cleen Finpro seminar
30 11-2011 mart grid Jani Valtari Cleen Finpro seminarBusiness Finland
 
The European long term vision and the Elia Group challenges
The European long term vision and the Elia Group challengesThe European long term vision and the Elia Group challenges
The European long term vision and the Elia Group challengesElia
 
The european energy policy the role of ENTSO-E and of TSOs
The european energy policy the role of ENTSO-E and of TSOsThe european energy policy the role of ENTSO-E and of TSOs
The european energy policy the role of ENTSO-E and of TSOsENTSO-E
 
IEA-RETD RE-INTEGRATION 20150311
IEA-RETD RE-INTEGRATION 20150311IEA-RETD RE-INTEGRATION 20150311
IEA-RETD RE-INTEGRATION 20150311IEA_RETD
 
An Introduction to Network Codes (April 2014)
An Introduction to Network Codes (April 2014)An Introduction to Network Codes (April 2014)
An Introduction to Network Codes (April 2014)ENTSO-E
 
Flavio Cucchietti - Energy Efficiency and ICT: short term needs long term opp...
Flavio Cucchietti - Energy Efficiency and ICT: short term needs long term opp...Flavio Cucchietti - Energy Efficiency and ICT: short term needs long term opp...
Flavio Cucchietti - Energy Efficiency and ICT: short term needs long term opp...iMinds conference
 
System Integration of Renewables
System Integration of RenewablesSystem Integration of Renewables
System Integration of RenewablesMirzo Ibragimov
 
Ensuring European Energy Transition: key research and innovation actions need...
Ensuring European Energy Transition: key research and innovation actions need...Ensuring European Energy Transition: key research and innovation actions need...
Ensuring European Energy Transition: key research and innovation actions need...Leonardo ENERGY
 
Application for phasor measurement unit
Application for phasor measurement unitApplication for phasor measurement unit
Application for phasor measurement unitPower System Operation
 
Evaluation of Utility Advanced Distribution Management System (ADMS) and Prot...
Evaluation of Utility Advanced Distribution Management System (ADMS) and Prot...Evaluation of Utility Advanced Distribution Management System (ADMS) and Prot...
Evaluation of Utility Advanced Distribution Management System (ADMS) and Prot...Power System Operation
 
Miro Zeman - Department of Electrical Sustainable Energy
Miro Zeman - Department of Electrical Sustainable EnergyMiro Zeman - Department of Electrical Sustainable Energy
Miro Zeman - Department of Electrical Sustainable EnergyDutch Power
 
Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transitionNarinporn Malasri
 
Industry outlook_ ABB.pdf
Industry outlook_ ABB.pdfIndustry outlook_ ABB.pdf
Industry outlook_ ABB.pdfssuser8073a0
 
B5 g2 enhanced+protection+functionality+with+iec+61850+and+goose
B5 g2 enhanced+protection+functionality+with+iec+61850+and+gooseB5 g2 enhanced+protection+functionality+with+iec+61850+and+goose
B5 g2 enhanced+protection+functionality+with+iec+61850+and+gooseOmeal Ahmed
 
Evs16 h13 [jp]act06 experinece of inducive charging
Evs16 h13 [jp]act06 experinece of inducive chargingEvs16 h13 [jp]act06 experinece of inducive charging
Evs16 h13 [jp]act06 experinece of inducive chargingchgada
 
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Implementing Agreement (IA)
 
Smartness Indicator
Smartness IndicatorSmartness Indicator
Smartness IndicatorDutch Power
 

Semelhante a 2014 PV Distribution System Modeling Workshop: European codes & guidelines for the application of advanced grid support functions of inverters: Roland Bruendlinger, AIT Austrian Institute of Technology (20)

30 11-2011 mart grid Jani Valtari Cleen Finpro seminar
30 11-2011 mart grid Jani Valtari Cleen Finpro seminar30 11-2011 mart grid Jani Valtari Cleen Finpro seminar
30 11-2011 mart grid Jani Valtari Cleen Finpro seminar
 
The European long term vision and the Elia Group challenges
The European long term vision and the Elia Group challengesThe European long term vision and the Elia Group challenges
The European long term vision and the Elia Group challenges
 
The european energy policy the role of ENTSO-E and of TSOs
The european energy policy the role of ENTSO-E and of TSOsThe european energy policy the role of ENTSO-E and of TSOs
The european energy policy the role of ENTSO-E and of TSOs
 
IEA-RETD RE-INTEGRATION 20150311
IEA-RETD RE-INTEGRATION 20150311IEA-RETD RE-INTEGRATION 20150311
IEA-RETD RE-INTEGRATION 20150311
 
An Introduction to Network Codes (April 2014)
An Introduction to Network Codes (April 2014)An Introduction to Network Codes (April 2014)
An Introduction to Network Codes (April 2014)
 
Power related issues requiring SmartGrids solutions
Power related issues requiring SmartGrids solutionsPower related issues requiring SmartGrids solutions
Power related issues requiring SmartGrids solutions
 
Flavio Cucchietti - Energy Efficiency and ICT: short term needs long term opp...
Flavio Cucchietti - Energy Efficiency and ICT: short term needs long term opp...Flavio Cucchietti - Energy Efficiency and ICT: short term needs long term opp...
Flavio Cucchietti - Energy Efficiency and ICT: short term needs long term opp...
 
System Integration of Renewables
System Integration of RenewablesSystem Integration of Renewables
System Integration of Renewables
 
Ensuring European Energy Transition: key research and innovation actions need...
Ensuring European Energy Transition: key research and innovation actions need...Ensuring European Energy Transition: key research and innovation actions need...
Ensuring European Energy Transition: key research and innovation actions need...
 
Application for phasor measurement unit
Application for phasor measurement unitApplication for phasor measurement unit
Application for phasor measurement unit
 
Sgcp13ansell
Sgcp13ansellSgcp13ansell
Sgcp13ansell
 
Evaluation of Utility Advanced Distribution Management System (ADMS) and Prot...
Evaluation of Utility Advanced Distribution Management System (ADMS) and Prot...Evaluation of Utility Advanced Distribution Management System (ADMS) and Prot...
Evaluation of Utility Advanced Distribution Management System (ADMS) and Prot...
 
Miro Zeman - Department of Electrical Sustainable Energy
Miro Zeman - Department of Electrical Sustainable EnergyMiro Zeman - Department of Electrical Sustainable Energy
Miro Zeman - Department of Electrical Sustainable Energy
 
Sgcp12 dickerson-cal
Sgcp12 dickerson-calSgcp12 dickerson-cal
Sgcp12 dickerson-cal
 
Renewable energy and grid integration energy transition
Renewable energy and grid integration   energy transitionRenewable energy and grid integration   energy transition
Renewable energy and grid integration energy transition
 
Industry outlook_ ABB.pdf
Industry outlook_ ABB.pdfIndustry outlook_ ABB.pdf
Industry outlook_ ABB.pdf
 
B5 g2 enhanced+protection+functionality+with+iec+61850+and+goose
B5 g2 enhanced+protection+functionality+with+iec+61850+and+gooseB5 g2 enhanced+protection+functionality+with+iec+61850+and+goose
B5 g2 enhanced+protection+functionality+with+iec+61850+and+goose
 
Evs16 h13 [jp]act06 experinece of inducive charging
Evs16 h13 [jp]act06 experinece of inducive chargingEvs16 h13 [jp]act06 experinece of inducive charging
Evs16 h13 [jp]act06 experinece of inducive charging
 
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
IEA DSM Task 17: Integration of DSM, DG, RES and ES – Outcome of Phase 1 and ...
 
Smartness Indicator
Smartness IndicatorSmartness Indicator
Smartness Indicator
 

Mais de Sandia National Laboratories: Energy & Climate: Renewables

Mais de Sandia National Laboratories: Energy & Climate: Renewables (20)

M4 sf 18sn010303061 8th us german 020918 lac reduced sand2018-1339r
M4 sf 18sn010303061 8th us german 020918 lac reduced sand2018-1339rM4 sf 18sn010303061 8th us german 020918 lac reduced sand2018-1339r
M4 sf 18sn010303061 8th us german 020918 lac reduced sand2018-1339r
 
Sand2018 0581 o metadata for presentations 011918 lac
Sand2018 0581 o metadata for presentations 011918 lacSand2018 0581 o metadata for presentations 011918 lac
Sand2018 0581 o metadata for presentations 011918 lac
 
11 Testing Shear Strength and Deformation along Discontinuities in Salt
11 Testing Shear Strength and Deformation along Discontinuities in Salt11 Testing Shear Strength and Deformation along Discontinuities in Salt
11 Testing Shear Strength and Deformation along Discontinuities in Salt
 
10 Current status of research in the Joint Project WEIMOS
10 Current status of research in the Joint Project WEIMOS10 Current status of research in the Joint Project WEIMOS
10 Current status of research in the Joint Project WEIMOS
 
26 Current research on deep borehole disposal of nuclear spent fuel and high-...
26 Current research on deep borehole disposal of nuclear spent fuel and high-...26 Current research on deep borehole disposal of nuclear spent fuel and high-...
26 Current research on deep borehole disposal of nuclear spent fuel and high-...
 
25 Basin-Scale Density-Dependent Groundwater Flow Near a Salt Repository
25 Basin-Scale Density-Dependent  Groundwater Flow Near a Salt Repository25 Basin-Scale Density-Dependent  Groundwater Flow Near a Salt Repository
25 Basin-Scale Density-Dependent Groundwater Flow Near a Salt Repository
 
24 Actinide and brine chemistry in salt repositories: Updates from ABC Salt (V)
24 Actinide and brine chemistry in salt repositories: Updates from ABC Salt (V)24 Actinide and brine chemistry in salt repositories: Updates from ABC Salt (V)
24 Actinide and brine chemistry in salt repositories: Updates from ABC Salt (V)
 
23 Sandia’s Salt Design Concept for High Level Waste and Defense Spent Nuclea...
23 Sandia’s Salt Design Concept for High Level Waste and Defense Spent Nuclea...23 Sandia’s Salt Design Concept for High Level Waste and Defense Spent Nuclea...
23 Sandia’s Salt Design Concept for High Level Waste and Defense Spent Nuclea...
 
22 WIPP Future Advancements and Operational Safety
22 WIPP Future Advancements and Operational Safety22 WIPP Future Advancements and Operational Safety
22 WIPP Future Advancements and Operational Safety
 
21 WIPP recovery and Operational Safety
21 WIPP recovery and Operational Safety21 WIPP recovery and Operational Safety
21 WIPP recovery and Operational Safety
 
20 EPA Review of DOE’s 2014 Compliance Recertification Application for WIPP
20 EPA Review of DOE’s 2014 Compliance Recertification Application for WIPP20 EPA Review of DOE’s 2014 Compliance Recertification Application for WIPP
20 EPA Review of DOE’s 2014 Compliance Recertification Application for WIPP
 
19 Repository designs in bedded salt, the KOSINA-Project
19 Repository designs in bedded salt, the KOSINA-Project19 Repository designs in bedded salt, the KOSINA-Project
19 Repository designs in bedded salt, the KOSINA-Project
 
18 Interaction between Operational Safety and Long-Term Safety (Project BASEL)
18 Interaction between Operational Safety and Long-Term Safety (Project BASEL)18 Interaction between Operational Safety and Long-Term Safety (Project BASEL)
18 Interaction between Operational Safety and Long-Term Safety (Project BASEL)
 
17 Salt Reconsolidation
17 Salt Reconsolidation17 Salt Reconsolidation
17 Salt Reconsolidation
 
16 Reconsolidation of granular salt (DAEF report)
16 Reconsolidation of granular salt (DAEF report)16 Reconsolidation of granular salt (DAEF report)
16 Reconsolidation of granular salt (DAEF report)
 
15 Outcome of the Repoperm Project
15 Outcome of the Repoperm Project15 Outcome of the Repoperm Project
15 Outcome of the Repoperm Project
 
14 Radiological Consequences Analysis for a HLW Repository in Bedded Salt in ...
14 Radiological Consequences Analysis for a HLW Repository in Bedded Salt in ...14 Radiological Consequences Analysis for a HLW Repository in Bedded Salt in ...
14 Radiological Consequences Analysis for a HLW Repository in Bedded Salt in ...
 
13 "New results of the KOSINA project - Generic geological models / Integrity...
13 "New results of the KOSINA project - Generic geological models / Integrity...13 "New results of the KOSINA project - Generic geological models / Integrity...
13 "New results of the KOSINA project - Generic geological models / Integrity...
 
12 Salt testing: Low deviatoric stress data
12 Salt testing: Low deviatoric stress data12 Salt testing: Low deviatoric stress data
12 Salt testing: Low deviatoric stress data
 
09 Invited Lecture: Salt Creep at Low Deviatoric Stress
09 Invited Lecture: Salt Creep at Low Deviatoric Stress09 Invited Lecture: Salt Creep at Low Deviatoric Stress
09 Invited Lecture: Salt Creep at Low Deviatoric Stress
 

Último

Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...tanu pandey
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escortsaditipandeya
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Call Girls in Nagpur High Profile
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxSwastiRanjanNayak
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.Christina Parmionova
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Call Girls in Nagpur High Profile
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...Hemant Purohit
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxaaryamanorathofficia
 
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...MOHANI PANDEY
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Christina Parmionova
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCongressional Budget Office
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 

Último (20)

Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...Human-AI Collaborationfor Virtual Capacity in Emergency Operation Centers (E...
Human-AI Collaboration for Virtual Capacity in Emergency Operation Centers (E...
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
EDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptxEDUROOT SME_ Performance upto March-2024.pptx
EDUROOT SME_ Performance upto March-2024.pptx
 
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.
 
CBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related TopicsCBO’s Recent Appeals for New Research on Health-Related Topics
CBO’s Recent Appeals for New Research on Health-Related Topics
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
 

2014 PV Distribution System Modeling Workshop: European codes & guidelines for the application of advanced grid support functions of inverters: Roland Bruendlinger, AIT Austrian Institute of Technology

  • 1. 123.05.2014 European codes & guidelines for the application of advanced grid support functions of inverters Roland Bründlinger Senior Engineer AIT Austrian Institute of Technology, Vienna, Austria PV Distribution System Modeling Workshop, Santa Clara, May 6, 2014
  • 2. Contents  Background – Development and challenges of grid connected PV in Europe  Overview of current grid codes and requirements in Europe  Outlook on the new ENTSO-E Network Code  Summary & recommendations 223.05.2014 223/05/2014
  • 3. Contents  Background – Development and challenges of grid connected PV in Europe  Overview of current grid codes and requirements in Europe  Outlook on the new ENTSO-E Network Code  Summary & recommendations 323.05.2014 323/05/2014
  • 4. Evolution of European cumulative installed PV capacity Source:EPIA,”IEA-PVPSTask14,TransitionfromConsumptiontoSupplyGrids,tobepublished For comparison: Total installed generation capacity in EU27 2011 approx. 850 GW (eurelectric figures)
  • 5. Net power generation capacity added in the EU28 in 2013 Source:EPIA,ESTELA,EU-OEA,EWEA,PlattsPowerVision,PVCYCLE MW  PV now covers 3% of the overall and 6% of the peak electricity demand  PV has been the top newly-added generation capacity together with wind for the 3rd year.  Within growing share of RES in the generation mix, grid and market/system integration challenges are becoming more and more important for the future PV deployment.
  • 6. Spatial distribution of installed capacity (W/per inhabitant) Source: EPIA, ”Global Market Outlook 2017”, May 2013 Bavaria: >800 W/inhabitant Italy: >6% of electricity demand  Some key facts about PV grid connection in Europe (end 2013)  About 80 GW installed in EU27  95% of the capacity is connected at the distribution levels  Numerous regions/DSOs already coping with High PV penetration (>100%)  PV has become a game changer in the European electricity market
  • 7. The role of PV in the European national electricity systems  Key Challenges  Increased variability and uncertainty  Increasing share of non-rotating generation  Increasing share of distribution system connected generation  Provision of grid support services by RES?  Penetration levels in some regions and countries have reached levels where full PV grid integration becomes critical to guarantee operational stability  Coordinated development of Grid Code requirements for PV and DG needed. 7 Source: EPIA 2013, Reservices Project 2014
  • 8. Contents  Background – Development and challenges of grid connected PV in Europe  Overview of current grid codes and requirements in Europe  Outlook on the new ENTSO-E Network Code  Summary & recommendations 823.05.2014 823/05/2014
  • 9. Framework for PV/DG interconnection in Europe Country specific grid codes and standards  Up to now no EU wide directive on DER/PV grid interconnection  Country specific grid codes, standards, DSO guidelines…  Different legal and administrative levels  Fundamental differences between the countries  Generally complex, intransparent situation  Issues for manufacturers and project developers  Specific product settings for each country/market  Interpretation of the requirements and application in practice  Increased costs and reduced competiveness  Critical issues for power system operation  Lack of coordination and compatibility  Risk of losing system security during critical events due to undefined behavior of DER 95/23/2014
  • 10. Current requirements for advanced grid support by PV Connection to LV distribution grids 105/23/2014  Full set of advanced grid support requirements mandatory for :  DE: Systems >16 A (2012)  AT: Systems >16 A (2013)  IT: Units >3 kVA (2012)  DK: Systems >16 A (2013)  Main functions:  Reactive power control (typ. PF(P) characteristic  Frequency control P(f)  No trip at low frequency  Remote limitation of P output (DE, AT, IT)
  • 11. Current requirements for advanced grid support by PV Connection to MV distribution grids 115/23/2014 Full set of advanced grid support requirements:  DE (2008), IT (2011), AT (2013), DK (2013), FR (2008) Selected requirements:  ES, PT, UK, CZ, BE…  Typically for MW scale generators Main functions:  Reactive power control  Voltage control PF(U)  Frequency control P(f)  Remote power limitation  FRT (=LVRT)
  • 12. Contents  Background – Development and challenges of grid connected PV in Europe  Overview of current grid codes and requirements in Europe  Outlook on the new ENTSO-E Network Code  Summary & recommendations 1223.05.2014 1223/05/2014
  • 13. Framework for PV/DG interconnection in Europe The new ENTSO-E Network Codes  2009: European Agency for the Cooperation of Energy Regulators (ACER) issued an official mandate to ENTSO-E (European Network of Electricity TSOs) to develop draft “Network Codes”  A set of rules applying to one aspect of the energy sector  Developed by ACER, ENTSO-E & market participants (transparent process)  Become legally binding (comitology process)  Ultimately have the same status as a European Regulation  Goal: Strengthen the European internal electricity market 135/23/2014 Source:ENTSO-E
  • 14. Framework for PV/DG interconnection in Europe The new ENTSO-E Network Code RfG  Network Code on “Requirements for Grid Connection applicable to all Generators (RfG)” is one of the first projects, aiming at  Establishing legally binding EU wide harmonization of grid interconnection requirements  Ensuring and increasing the system security with a growing share of RES and variable generation  Avoiding future regret and costly retrofits to ensure security of supply 145/23/2014 Source:ENTSO-E
  • 15. Framework for PV/DG interconnection in Europe ENTSO-E RfG Network Code  Basic approach  Applicable to all generators >0.8 kW  Balance European settings and regional specifics  Proportional approach from smallest generation to largest plants  Application for (all) new generators in order to  ensure system security in a changing environment  accommodate evolution in the generation portfolio  reduce costs through standardization.  Application for existing generators (retrofit) only if  technically justifiable,  benefits demonstrated by Cost Benefit Analysis  approved by National Regulatory Authority 155/23/2014 https://www.entsoe.eu/major-projects/network-code-development/requirements-for-generators/
  • 16. Framework for PV/DG interconnection in Europe ENTSO-E RfG Network Code  Standardized definition of generator types and associated functionalities/ requirements depending on  transmission grid region  connection level (voltage)  generator capacity and technology (synchronous or converter based) 165/23/2014 Type D Type C Type B Type A • Wide-scale network operation and stability • Balancing services • Stable and controllable dynamic response • covering all operational network states • Automated dynamic response and resilience to events • System operator control • Basic capabilities to withstand wide-scale critical events • Limited automated response and control
  • 17. Framework for PV/DG interconnection in Europe ENTSO-E RfG Network Code 175/23/2014
  • 18. Framework for PV/DG interconnection in Europe ENTSO-E RfG Network Code  Overview of aspects and requirements addressed by the RfG 185/23/2014 Addressed system aspect Requirement Type A Type B Type C/D Frequency stability Operating frequency ranges X X X RoCoF withstand capability X X X Limited Frequency Sensitive Mode - Overfrequency X X X Constant active power output regardless of changes in Frequency X X X Limitation of power reduction at underfrequency X X X Automatic connection X X X Remote ON/OFF X X Active power reduction remote control X Additional requirements related to frequency control X Provision of synthetic inertia X
  • 19. Framework for PV/DG interconnection in Europe ENTSO-E RfG Network Code 195/23/2014 Addressed system aspect Requirement Type A Type B Type C/D Robustness of power generating modules Fault-ride-through X X Post-fault active power recovery X X System restoration Coordinated reconnection X X General system management Control schemes and settings X X Electrical protection and control schemes and settings X X Priority ranking of protection and control X X Information exchange X X Additional requirements to monitoring X Voltage stability Reactive power capability X X Fast reacting reactive power injection X X Additional requirements for reactive power capability and control modes X  Overview of aspects and requirements addressed by the RfG
  • 20. Framework for PV/DG interconnection in Europe ENTSO-E RfG Network Code 205/23/2014  Some further aspects related to the RfG  Eventually, the RfG will have the character of a EU directive  Later amendments will be very difficult  Definitions in RfG leave wide room for variation/interpretation by the local TSOs/NRAs  After its implementation the RfG will  Define system relevant minimum requirements for all generators  Provide a basis for national codes and standards  However, the RfG will not  Provide a true harmonization of the requirements across Europe  Provide “product specifications” which can be easily be implemented by manufacturers  Provide harmonized certification, type testing or modeling procedures  Provide requirements related to communication protocols or technologies (e.g. IEC 61850, DNP3)
  • 21. Framework for PV/DG interconnection in Europe ENTSO-E RfG Network Code 215/23/2014  Recent steps  Jan-March 2012: Open public consultation with all stakeholders  July 2012 – March 2013: Review of RfG draft by ACER  October 2013: Implementation Guideline published  European Commission comitology procedure started in January 2014  Further implementation of the code at national level via existing processes  Definition of detailed local requirements and conditions by national TSOs in collaboration with NRAs  Amendments/ modifications to existing national guidelines  Planned to be legally binding from 2017
  • 22. Framework for PV/DG interconnection in Europe ENTSO-E RfG Network Code 225/23/2014  Resources  RfG webpage: https://www.entsoe.eu/major-projects/network-code- development/requirements-for-generators/  Final version of RfG Network code: https://www.entsoe.eu/fileadmin/user_upload/_library/resources/RfG/13 0308_Final_Version_NC_RfG.pdf  Implementation Guideline: https://www.entsoe.eu/fileadmin/user_upload/_library/resources/RfG/13 1016_-_NC_RfG_implementation_guideline.pdf
  • 23. Contents  Background – Development and challenges of grid connected PV in Europe  Overview of current grid codes and requirements in Europe  Outlook on the new ENTSO-E Network Code  Summary & recommendations 2323.05.2014 2323/05/2014
  • 24. Summary and key conclusions  In Europe the role of PV has changed from a marginal technology to a visible player in the electricity market  PV and grid parity  further massive deployment in short and near term  In particular Germany acts as show-case for high-penetration PV and provision of grid support (voltage, frequency…) by decentralised PV  Coordinated approach for integrating PV on high penetration levels is crucial to ensure system stability and security  Addressed by upcoming ENTSO-E network code “Requirements for Generators”  Open collaboration between TSOs, DSOs and PV industry necessary  Redefinition of the interaction between DSOs and TSOs needed  The development in some European regions and countries shows that large- scale integration of PV is technically feasible without threatening security of supply. 245/23/2014
  • 25. PV&RES grid integration A brief overview of current RTD&D projects in Europe  ECOGRID EU www.eu-ecogrid.net  metaPV www.metapv.eu  PV GRID http://www.pvgrid.eu  REserviceS www.reservices-project.eu  IGREENGrid www.igreengrid-fp7.eu  PV PARITY www.pvparity.eu  And numerous other national projects/demonstrators 2523.05.2014
  • 26. 2623.05.2014 Thank you very much for your attention! Roland Bründlinger AIT Austrian Institute of Technology Giefinggasse 2, 1210 Wien, Austria roland.bruendlinger@ait.ac.at