SlideShare uma empresa Scribd logo
1 de 6
TOP DOWN CONSTRUCTION
ADVANTAGES
By
Sai Towers P Ltd.
Why Top Down Construction
Required
• Distance between Boundary wall of Adjacent Existing Building and
Building Line for New Building is too close and the depth of
excavation is more than 6 meter and possibility of collapse the soil
is higher during excavation.
• Using Top Down Construction more Building and Basement Area
can use. Suitable for two or more basement.
• The first base slab level slab will act in such area as a strut member
and the Retaining wall panels will not allow collapse of soil.
• Water table is too high and difficult to cast Retaining wall,
Diaphragm wall or Continuous Pile can use as a Retaining wall.
METHODOLOGY OF TOP DOWN
CONSTRUCTION
• Setting out for alignment of bore cast in situ of piles .
• Bore Cast in Situ Piles to be cast and dowels bar to be kept for
Retaining wall panels. The center of piles and Retaining wall panels
center line to be kept in same line. The Diameter of Piles preferred
600 mm, distance between two piles center to center preferred
3.33 meters (Suit for C/C distance of Columns), Depth of Piles to be
confirmed by Structural Consultants.
• Touching Piles can use as a Retaining wall with supporting
arrangement during Excavation.
• Water table is too high and difficult to cast Retaining wall, Diaphragm
wall or Continuous Pile can use as a Retaining wall.
• Instead of Column C1 to Column C8,Bore cast in Situ piles to be cast with
dowel bars for different level slab and connecting Beams, The Diameter of
Piles (suit as per Columns size), Reinforcement details (with dowels for
Retaining wall and different level slabs and Beam), Depth of Piles to be
confirmed by Structural Consultants.
• Excavation to be done around 2 meter depth and retaining wall panels to
be cast in stages with dowels bars with adjacent piles and dowel bars for
next Retaining wall panel to be kept .if soil between piles collapsed soil
nails with wire mesh to be kept on earth side to retain the same. Retaining
wall panels to be cast with dowels up to the first base slab bottom.
• Dressing and compaction of soil to be done for PCC bed for casting
of first base slab. 50mm PCC (M15 Grade) to be done, the top levels
of PCC to be keep the base slab level bottom. For beams excavation
to be done in same alignment and dimensions as required and PCC
or brick work to be done as per beam dimensions in Vertical face.
• After PCC 3mm ply to be laid on PCC Surface and PVC sheet to be
nailed with PCC surface so surface of PCC and Surface of Slab
Concrete will separate. 7. Reinforcement to be completed as per
drawings, for beams dowel bar to be used from Cast in Situ Piles.
Dowel bars to be keep for adjacent slabs for Bottom Up
Construction.
• Concreting of Slab and Beam to be completed.
• After 14 days of Concreting, PCC below slab to be break/removed
excavation to be continued and retaining wall panels to be cast. Till
final level of excavation.
• Waterproofing to be done and base slab to be cast with dowels
from Cast in Situ Piles.
• Jacketing of Columns to be done if required
If any query please mail – saitowers2000@gmail.com
or visit - sai-towers.com

Mais conteúdo relacionado

Mais procurados

earth support
earth supportearth support
earth supportjuwes
 
Top down construction
Top down constructionTop down construction
Top down constructionAmulya Kansal
 
Bored pile-retaining-walls
Bored pile-retaining-wallsBored pile-retaining-walls
Bored pile-retaining-wallsDr. Naveen BP
 
Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation Davis Ciprikis
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstructionvietcgxd
 
Anchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationAnchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationKyle Beaudry, P.Eng
 
basement excavation, underpinning
basement excavation, underpinningbasement excavation, underpinning
basement excavation, underpinningOkwera David
 
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلSecant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلDr.youssef hamida
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Mat foundation
Mat foundationMat foundation
Mat foundationshuvo293
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNeha Vivek
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructureguasiya
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakambaJohn Chakamba
 
Shoring system and Dewatering
Shoring system and DewateringShoring system and Dewatering
Shoring system and DewateringSALEM MOHAMMED
 

Mais procurados (20)

earth support
earth supportearth support
earth support
 
Top down construction
Top down constructionTop down construction
Top down construction
 
Bored pile-retaining-walls
Bored pile-retaining-wallsBored pile-retaining-walls
Bored pile-retaining-walls
 
Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation
 
2 1 excavation_basementconstruction
2 1 excavation_basementconstruction2 1 excavation_basementconstruction
2 1 excavation_basementconstruction
 
pile wall
pile wallpile wall
pile wall
 
Anchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationAnchored Secant Pile Wall Presentation
Anchored Secant Pile Wall Presentation
 
Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
basement excavation, underpinning
basement excavation, underpinningbasement excavation, underpinning
basement excavation, underpinning
 
Shoring and underpinning
Shoring and underpinningShoring and underpinning
Shoring and underpinning
 
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلSecant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Mat foundation
Mat foundationMat foundation
Mat foundation
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakamba
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Shoring system and Dewatering
Shoring system and DewateringShoring system and Dewatering
Shoring system and Dewatering
 

Semelhante a Top down construction by Sai Towers P Ltd.

Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTUVATSAL PATEL
 
Indian Standard
Indian StandardIndian Standard
Indian Standardaman kumar
 
Ann vii -structure repairs bihar
Ann vii -structure repairs biharAnn vii -structure repairs bihar
Ann vii -structure repairs biharVaishnav Mishra
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptxssuser480182
 
How to build a besser block wall
How to build a besser block wallHow to build a besser block wall
How to build a besser block wallkristenjames
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptxHimanshumangal12
 
Construction of well foundation
Construction of well foundation Construction of well foundation
Construction of well foundation dilip patidar
 
Aim for quality in construction
Aim for quality in constructionAim for quality in construction
Aim for quality in constructionpracticalanswerssl
 
How to build a besser block wall - APC
How to build a besser block wall - APCHow to build a besser block wall - APC
How to build a besser block wall - APCkristenjames
 
Brickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfBrickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfAbhinavSahu45
 
house construction
house constructionhouse construction
house constructionAbhinav Saha
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle SlabAkshay Gawade
 
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Deepak Verma
 
Concrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabConcrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabDivineGraceFernando
 

Semelhante a Top down construction by Sai Towers P Ltd. (20)

Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 
Indian Standard
Indian StandardIndian Standard
Indian Standard
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
Ann vii -structure repairs bihar
Ann vii -structure repairs biharAnn vii -structure repairs bihar
Ann vii -structure repairs bihar
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
How to build a besser block wall
How to build a besser block wallHow to build a besser block wall
How to build a besser block wall
 
Form Work
Form Work Form Work
Form Work
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
Construction of well foundation
Construction of well foundation Construction of well foundation
Construction of well foundation
 
Aim for quality in construction
Aim for quality in constructionAim for quality in construction
Aim for quality in construction
 
How to build a besser block wall - APC
How to build a besser block wall - APCHow to build a besser block wall - APC
How to build a besser block wall - APC
 
Brickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdfBrickwork & Plaster 26.02.22.pdf
Brickwork & Plaster 26.02.22.pdf
 
house construction
house constructionhouse construction
house construction
 
Work check list
Work check listWork check list
Work check list
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
 
Concrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabConcrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slab
 
Cracks in concrete
Cracks in concreteCracks in concrete
Cracks in concrete
 

Último

Kalpataru Exquisite Wakad Pune E-Brochure.pdf
Kalpataru Exquisite Wakad Pune  E-Brochure.pdfKalpataru Exquisite Wakad Pune  E-Brochure.pdf
Kalpataru Exquisite Wakad Pune E-Brochure.pdfManishSaxena95
 
Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...asmaqueen5
 
Nyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdfNyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdfabbu831446
 
Prestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdfPrestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdfkishor21012022
 
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...asmaqueen5
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)delhi24hrs1
 
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdfThe Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdfPrachiRudram
 
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...ApartmentWala1
 
ACE Terra Yamuna Expressway | 8929888700
ACE Terra Yamuna Expressway | 8929888700ACE Terra Yamuna Expressway | 8929888700
ACE Terra Yamuna Expressway | 8929888700Truhomes
 
MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor PresentationMEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor PresentationMEQ - Mainstreet Equity Corp.
 
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & RequirementsExplore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirementsmarketingkingdomofku
 
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...ApartmentWala1
 
SVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property BroadcastSVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property BroadcastSVN International Corp.
 
Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024VickyAulakh1
 
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...asmaqueen5
 
Vanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdfVanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdfkratirudram
 
Eldeco Dwarka Project In Delhi-brochure.pdf.pdf
Eldeco Dwarka Project In Delhi-brochure.pdf.pdfEldeco Dwarka Project In Delhi-brochure.pdf.pdf
Eldeco Dwarka Project In Delhi-brochure.pdf.pdfkratirudram
 
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhiasmaqueen5
 
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)delhi24hrs1
 
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...ApartmentWala1
 

Último (20)

Kalpataru Exquisite Wakad Pune E-Brochure.pdf
Kalpataru Exquisite Wakad Pune  E-Brochure.pdfKalpataru Exquisite Wakad Pune  E-Brochure.pdf
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
 
Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
Call Girls in Maurice Nagar (Delhi) ꧁8447779280꧂ Female Escorts Service in De...
 
Nyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdfNyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdf
 
Prestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdfPrestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdf
 
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...
Low Rate Call girls in Sant Nagar{Delhi }8447779280} Service Escorts In South...
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
 
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdfThe Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
The Gale at Godrej Park World Hinjewadi Pune Brochure.pdf
 
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
 
ACE Terra Yamuna Expressway | 8929888700
ACE Terra Yamuna Expressway | 8929888700ACE Terra Yamuna Expressway | 8929888700
ACE Terra Yamuna Expressway | 8929888700
 
MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor PresentationMEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
MEQ Mainstreet Equity Corp Q2 2024 Investor Presentation
 
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & RequirementsExplore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
 
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
 
SVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property BroadcastSVN Live 5.6.24 Weekly Property Broadcast
SVN Live 5.6.24 Weekly Property Broadcast
 
Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024
 
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
 
Vanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdfVanam At Purva Soukhyam Guduvanchery.pdf.pdf
Vanam At Purva Soukhyam Guduvanchery.pdf.pdf
 
Eldeco Dwarka Project In Delhi-brochure.pdf.pdf
Eldeco Dwarka Project In Delhi-brochure.pdf.pdfEldeco Dwarka Project In Delhi-brochure.pdf.pdf
Eldeco Dwarka Project In Delhi-brochure.pdf.pdf
 
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
 
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
 
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
 

Top down construction by Sai Towers P Ltd.

  • 2. Why Top Down Construction Required • Distance between Boundary wall of Adjacent Existing Building and Building Line for New Building is too close and the depth of excavation is more than 6 meter and possibility of collapse the soil is higher during excavation. • Using Top Down Construction more Building and Basement Area can use. Suitable for two or more basement. • The first base slab level slab will act in such area as a strut member and the Retaining wall panels will not allow collapse of soil. • Water table is too high and difficult to cast Retaining wall, Diaphragm wall or Continuous Pile can use as a Retaining wall.
  • 3. METHODOLOGY OF TOP DOWN CONSTRUCTION • Setting out for alignment of bore cast in situ of piles . • Bore Cast in Situ Piles to be cast and dowels bar to be kept for Retaining wall panels. The center of piles and Retaining wall panels center line to be kept in same line. The Diameter of Piles preferred 600 mm, distance between two piles center to center preferred 3.33 meters (Suit for C/C distance of Columns), Depth of Piles to be confirmed by Structural Consultants. • Touching Piles can use as a Retaining wall with supporting arrangement during Excavation.
  • 4. • Water table is too high and difficult to cast Retaining wall, Diaphragm wall or Continuous Pile can use as a Retaining wall. • Instead of Column C1 to Column C8,Bore cast in Situ piles to be cast with dowel bars for different level slab and connecting Beams, The Diameter of Piles (suit as per Columns size), Reinforcement details (with dowels for Retaining wall and different level slabs and Beam), Depth of Piles to be confirmed by Structural Consultants. • Excavation to be done around 2 meter depth and retaining wall panels to be cast in stages with dowels bars with adjacent piles and dowel bars for next Retaining wall panel to be kept .if soil between piles collapsed soil nails with wire mesh to be kept on earth side to retain the same. Retaining wall panels to be cast with dowels up to the first base slab bottom.
  • 5. • Dressing and compaction of soil to be done for PCC bed for casting of first base slab. 50mm PCC (M15 Grade) to be done, the top levels of PCC to be keep the base slab level bottom. For beams excavation to be done in same alignment and dimensions as required and PCC or brick work to be done as per beam dimensions in Vertical face. • After PCC 3mm ply to be laid on PCC Surface and PVC sheet to be nailed with PCC surface so surface of PCC and Surface of Slab Concrete will separate. 7. Reinforcement to be completed as per drawings, for beams dowel bar to be used from Cast in Situ Piles. Dowel bars to be keep for adjacent slabs for Bottom Up Construction.
  • 6. • Concreting of Slab and Beam to be completed. • After 14 days of Concreting, PCC below slab to be break/removed excavation to be continued and retaining wall panels to be cast. Till final level of excavation. • Waterproofing to be done and base slab to be cast with dowels from Cast in Situ Piles. • Jacketing of Columns to be done if required If any query please mail – saitowers2000@gmail.com or visit - sai-towers.com