SlideShare uma empresa Scribd logo
1 de 27
QUALITY CONTROL
AND INSPECTION
OF TYRES
SAI ANJANEYA
CONTENTS
• Structure of Tyres
• Manufacturing Processes Involved
• Inspection Processes
• Pre-Production Inspection
• Materials Inspection
• Production Inspection
• Visual Inspection
• Weight and Measurement Inspection
• Final Inspection
• Parameters of Testing
• Machines Used
• ISO Standards
• References and Gallery
STRUCTURE OF A TYRE
Different parts of the Tyre are:
• Tread: The part of the tire in contact with the ground. It must provide traction,
long wear and cut resistance. The tread depth and design vary based on site and
application.
• Carcass: Contains the inflation medium. The greater its strength, the greater the
pressure it can hold.
• Breakers (Belts): These are placed between the tread and carcass. They help to
join these parts. They also distribute road shock to protect the carcass. In
bias/belted and radial constructions, they control the diameter of the tire.
• Bead: Bundles of high tensile steel wire. They anchor the tire to the rim.
• Sidewalls: The protective rubber covers on the side of a tire.
• Inner liner: A specially formulated rubber compound inside the tire that
minimizes permeation. It works with the rim and O-ring to contain the inflation
medium in tubeless designs.
MANUFACTURING PROCESSES
Manufacturing Processes Involved:
• Compounding and mixing:
Compounding is the operation of bringing together all the ingredients
required to mix a batch of rubber compound. Each component has a
different mix of ingredients according to the properties required for that
component.
Mixing is the process of applying mechanical work to the ingredients in
order to blend them into a homogeneous substance. The mixing is done in
three or four stages to incorporate the ingredients in the desired order.
The ideal compound at this point would have a highly uniform material
dispersion; however in practice there is considerable non-uniformity to the
dispersion
• Component Separation:
Components fall into three classes based on manufacturing process:
calendaring, extrusion, and bead building. The extruder machine consists of
a screw and barrel, screw driver, heaters, and a die.
The extruder applies two conditions pressure. The extruder screw also
provides for additional mixing of the compound through the shearing action
of the screw.
The calendar is a set of multiple large-diameter rolls that squeeze rubber
compound into a thin sheet, usually of the order of 2 metres wide.
• Tire building:
Building is the process of assembling all the components onto a tire building
drum.
Typical TBM operations include the first-stage operation, where inner liner,
body plies, and sidewalls are wrapped around the drum, the beads are
placed, and the assembly turned up over the bead. In the second stage
operation the belt package and tread are applied and the green tire is
inflated and shaped.
• Curing:
Curing is the process of applying pressure to the green tire in a mould in
order to give it its final shape, and applying heat energy to stimulate the
chemical reaction between the rubber and other materials.
• Final Finish:
After the tire has been cured, there are several additional
operations. Tire measurement is a test where the tire is automatically
mounted on wheel halves, inflated, run against a simulated road surface,
and measured for force variation. Tire balance measurement is a test where
the tire is automatically placed on wheel halves, rotated at a high speed and
measured for imbalance.
Large commercial truck/bus tires, as well as some passenger and light truck
tires, are inspected by X-ray or magnetic induction based inspection
machines that can penetrate the rubber to analyze the steel cord structure.
In the final step, tires are inspected by human eyes for numerous visual
defects such as incomplete mould fill, exposed cords, blisters, blemishes,
and others.
TYRE INSPECTION PROCESSES
• Pre-Production Inspection:
As per SAE J 332, each machine to be used for composition and
manufacturing of different tire types will be thoroughly inspected for any
damage or defects and any other potential damaging factors detected.
The purpose of this inspection process is to verify that all of the equipment
and devices to be used for tire production is in working order to ensure
quality products.
Machines that show damage and/or defects should not be used for
production to ensure that no production anomalies will take place as much
as possible.
TYRE CODE
• Materials Inspection
All of the materials to be used for tire construction will be thoroughly
inspected for any imperfections to avoid defective products the soonest it
has been detected. The purpose of this inspection process is to ensure that
all of the materials to be used are free from damage and/or defects.
Materials that show signs of damage or defects will be automatically
rejected and will not be used throughout the entire production process.
• Production Inspection:
All of the materials that pass the inspection process will be then transferred
to the assembly line where the entire tire manufacturing process is initiated.
Throughout the duration of the manufacturing process, each material will
undergo different departments before getting the final product.
These departments are:
• Mixing and Compounding – rubber materials to be used will be mixed with
different agents to form a rubber compound to be used for tires.
• Calendar, Extrusion and Bead Building – all of the needed components for
tire manufacturing will be prepared during this production queue to ensure
all of the materials are complete prior to the next production process.
• Tire Assembly – after, all of the materials have been prepared and gathered,
tire building will be performed and will be inspected on a regular basis until
all of the components are properly coated.
• Curing – all of the tires that are halfway finished will undergo curing process
where immense pressure will be applied in a mould in order to create the
suitable shape of the tire. By using a machine to assist with the roundness,
the success rate of curing items is above 80 percent.
TYRES IN
ASSEMBLY LINE
CURING
• Visual Inspection:
After the production process, all of the finished products will undergo a
thorough inspection regarding the condition and overall quality and design
of each tire. The purpose of this inspection process is to verify that all of the
tires out of production show no signs of damage or defects to ensure
product reliability and durability as per quality control standards.
It is important that each surface area of the tire on queue must be visually
inspected and machine tested to ensure that no hidden damage is detected.
• Tread Depth – the surface area of each tire will be inspected thoroughly to
ensure that there are no cracks, moulds or bubbles detected.
• X-RAY inspection – the internal parts of the tire will be inspected for any
underlying defects that could take place during initial use to ensure that all
of the tires are structurally sound and reliable right out of production.
• Weight and Measurement Inspection:
Each tire will be measured will deflated and once again once inflated to
properly specify the gross and net weight of each tire according to its
category.
• Tire Uniformity Analysis – tires under the same category will be measured
and weighed according to its product specification to ensure durability,
reliability and strict quality control standards.
• Tire balance – tires, regardless of type, will be attached to a machine that
emulates the vehicle will be used in order to properly measure the
specifications of each tire assembly. Tires that are out of balance will be
checked for air pressure and overall build to ensure proper size and weight
on all tires.
Items that fail the weight and measurement inspection protocol will be
evaluated for alternative repairs and reconstruction (depending on the
damage) to save overall production time if applicable. Items that are beyond
repair will be automatically marked as “DEFECTIVE
• Final Inspection:
The purpose of this inspection process is to verify that all of the tires under
the production process will undergo a series of performance and battery
tests while maintaining a defect-free product at the end of the testing and
inspection phase. The common tests involved for this inspection process are:
• Tire Balance and Performance Analysis – all of the tires will be placed on
mechanisms to emulate the vehicle specified to check tire balance and if
tires are structurally sound and round.
• Tire rotation analysis – each tire will be put into spinning action to evaluate
and analyze the behaviour of the tire being inspected while in operation to
properly assess the condition of the tire and its overall composition.
• High-Speed Test – all of the tires will be tested on a road-like area where
tires will be tested under high speeds to check tire balance and roundness at
high speeds of at least 70 miles per hour.
• Damage-Rate Inspection – tires that have finished the entire inspection
process will be re-analyzed for any incomplete mould fill and will be checked
for damages like blemishes, blisters, exposed cords and other post-
production anomalies that have taken place.
PARAMETERS OF TESTING
• Outdoor
• Braking on a dry surface (also for motorcycles, trucks and buses)
• Handling on a dry surface (also for motorcycles)
• Handling on a wet surface
• Braking on a wet surface ECE R 117 / EC 1222/2009 (also for trucks and
buses)
• Longitudinal aquaplaning
• Lateral aquaplaning
• Steady-state circular test on a wet surface (also for trucks and buses)
• Indoor
• Rolling resistance
• Measurement of force and torque
• Temperature (online measurement of the temperature inside the tyre, on
the inner liner and at the tyre surface)
AQUAPLANING
• Aquaplaning or Hydroplaning by tyres of a road vehicle occurs when a layer
of water builds between the wheels of the vehicle and the road surface,
leading to a loss of traction that prevents the vehicle from responding to
control inputs.
• Aquaplaning is different phenomenon from water on the roadway merely
acting as a lubricant.
MACHINES USED
• Tire Component Profilometer
• Tire Colour Inspection Tire Length Inspection
• Tire Component Offline Profilometer Tire Component Profilometer
• Tire Piece Weight Inspection
• Tire Component Profilometer
STANDARDS
REFERENCES
• http://www.intouch-quality.com/blog/tire-inspection-qc-china/
• http://www.issia.cnr.it/wp/?portfolio=ndt-quality-control-of-tyres
• http://www.micro-epsilon.com/download/products/cat--systems--rubber-tire--en.pdf
• https://www.iso.org/obp/ui/#iso:std:63769:en
• http://www.iso.org/iso/home/store/catalogue_tc/catalogue_tc_browse.htm?commid=47686
• http://optotechnik.zeiss.com/en/products/tire-testing-intact/intact-otr
• http://www.tuv-sud.com/industry/automotive-transportation/automotive-
solutions/automotive-component-testing/tyre-testing#tab_1427765935891907481211
• http://www.dunlop.eu/dunlop_ie/what-makes-dunlop-different/tire-tests/
• http://www.michelinman.com/US/en/safe-driving/tire-safety/inspection.html
• https://www.researchgate.net/publication/258807136_Identification_and_quality_control_of_
marks_on_tires_through_artificial_vision
GALLERY
An opened tire mould being cleaned. The
deflated rubber bladder is on the central post
Structure of a Tyre
Inspection in process
Inspection in process
Tyre Balance Inspection
Quality control and inspection of tyres

Mais conteúdo relacionado

Mais procurados

Manufacturing process of tyre
Manufacturing process of tyreManufacturing process of tyre
Manufacturing process of tyreHarsh Shrimali
 
Manufacturing Process of Tyre
Manufacturing Process of TyreManufacturing Process of Tyre
Manufacturing Process of TyreAHMADQAYYUMHAFIEZ
 
Extruders - Special Supplement From Rubber & Tyre Machinery World
Extruders - Special Supplement From Rubber & Tyre Machinery WorldExtruders - Special Supplement From Rubber & Tyre Machinery World
Extruders - Special Supplement From Rubber & Tyre Machinery WorldRubber & Tyre Machinery World
 
Tyre cross section measurement
Tyre cross section measurement Tyre cross section measurement
Tyre cross section measurement Dr. Hartwig Suhr
 
Different types of suspension system
Different types of suspension systemDifferent types of suspension system
Different types of suspension systemHOME
 
steering system ppt
steering system ppt steering system ppt
steering system ppt hiten patel
 
UNIT IV STEERING, BRAKES AND SUSPENSION SYSTEMS
UNIT IV    STEERING, BRAKES AND SUSPENSION SYSTEMS	UNIT IV    STEERING, BRAKES AND SUSPENSION SYSTEMS
UNIT IV STEERING, BRAKES AND SUSPENSION SYSTEMS karthi keyan
 
Manufacturing Processes - Tyre
Manufacturing Processes - TyreManufacturing Processes - Tyre
Manufacturing Processes - TyreSateesh Kumar
 
Wheels and tyres for automobile
Wheels and tyres for automobileWheels and tyres for automobile
Wheels and tyres for automobilesgrsoni45
 
Wheel & Tyre-Service,Repair & Overhaul
Wheel & Tyre-Service,Repair & OverhaulWheel & Tyre-Service,Repair & Overhaul
Wheel & Tyre-Service,Repair & OverhaulYash Lad
 
4 independed suspension system
4 independed suspension system4 independed suspension system
4 independed suspension systemshaikusmanshag
 
Advantages of tubeless tire as compared to tube
Advantages of tubeless tire as compared to tubeAdvantages of tubeless tire as compared to tube
Advantages of tubeless tire as compared to tubeHITEC University, Taxila
 
Automobile chassis frame
Automobile chassis frameAutomobile chassis frame
Automobile chassis framejjHF47
 

Mais procurados (20)

Tyre
TyreTyre
Tyre
 
Manufacturing process of tyre
Manufacturing process of tyreManufacturing process of tyre
Manufacturing process of tyre
 
Tires
TiresTires
Tires
 
Tires
TiresTires
Tires
 
Manufacturing Process of Tyre
Manufacturing Process of TyreManufacturing Process of Tyre
Manufacturing Process of Tyre
 
Tyres
TyresTyres
Tyres
 
Extruders - Special Supplement From Rubber & Tyre Machinery World
Extruders - Special Supplement From Rubber & Tyre Machinery WorldExtruders - Special Supplement From Rubber & Tyre Machinery World
Extruders - Special Supplement From Rubber & Tyre Machinery World
 
Mc tyre
Mc tyreMc tyre
Mc tyre
 
Tyre cross section measurement
Tyre cross section measurement Tyre cross section measurement
Tyre cross section measurement
 
Different types of suspension system
Different types of suspension systemDifferent types of suspension system
Different types of suspension system
 
steering system ppt
steering system ppt steering system ppt
steering system ppt
 
UNIT IV STEERING, BRAKES AND SUSPENSION SYSTEMS
UNIT IV    STEERING, BRAKES AND SUSPENSION SYSTEMS	UNIT IV    STEERING, BRAKES AND SUSPENSION SYSTEMS
UNIT IV STEERING, BRAKES AND SUSPENSION SYSTEMS
 
GENERAL TYRE INTERNSHIP REPORT
GENERAL TYRE INTERNSHIP REPORTGENERAL TYRE INTERNSHIP REPORT
GENERAL TYRE INTERNSHIP REPORT
 
Manufacturing Processes - Tyre
Manufacturing Processes - TyreManufacturing Processes - Tyre
Manufacturing Processes - Tyre
 
Wheels and tyres for automobile
Wheels and tyres for automobileWheels and tyres for automobile
Wheels and tyres for automobile
 
Wheel & Tyre-Service,Repair & Overhaul
Wheel & Tyre-Service,Repair & OverhaulWheel & Tyre-Service,Repair & Overhaul
Wheel & Tyre-Service,Repair & Overhaul
 
4 independed suspension system
4 independed suspension system4 independed suspension system
4 independed suspension system
 
Wheel And tyres
Wheel And tyresWheel And tyres
Wheel And tyres
 
Advantages of tubeless tire as compared to tube
Advantages of tubeless tire as compared to tubeAdvantages of tubeless tire as compared to tube
Advantages of tubeless tire as compared to tube
 
Automobile chassis frame
Automobile chassis frameAutomobile chassis frame
Automobile chassis frame
 

Destaque

Quality Control
Quality ControlQuality Control
Quality Controlvishakeb
 
Quality control and inspection
Quality control and inspectionQuality control and inspection
Quality control and inspectionSamiksha Sawant
 
Mobile apps for_old_people
Mobile apps for_old_peopleMobile apps for_old_people
Mobile apps for_old_peopleAdrianaChereji
 
Poly vinyl chloride(polymers)
Poly vinyl chloride(polymers)Poly vinyl chloride(polymers)
Poly vinyl chloride(polymers)sai anjaneya
 
Automation Technology for the Steel Industry
Automation Technology for the Steel IndustryAutomation Technology for the Steel Industry
Automation Technology for the Steel Industryifm electronic gmbh
 
Iso 10474 steel and steel products - inspection documents
Iso 10474   steel and steel products - inspection documentsIso 10474   steel and steel products - inspection documents
Iso 10474 steel and steel products - inspection documentslgnguyen4444
 
Press-on Tyres by Royal Tyres Private Limited Chennai
Press-on Tyres by Royal Tyres Private Limited ChennaiPress-on Tyres by Royal Tyres Private Limited Chennai
Press-on Tyres by Royal Tyres Private Limited ChennaiIndiaMART InterMESH Limited
 
Japanese industrial standard
Japanese industrial standardJapanese industrial standard
Japanese industrial standardAlbert Candor
 
Mktg Strats Tyre Industry
Mktg Strats   Tyre IndustryMktg Strats   Tyre Industry
Mktg Strats Tyre Industryalvareena
 
Wheels and tyres pages 8 and 9
Wheels and tyres pages 8 and 9Wheels and tyres pages 8 and 9
Wheels and tyres pages 8 and 9Rob Ansell
 
Tyre Management Services / Fleet Management Services
Tyre Management Services / Fleet Management ServicesTyre Management Services / Fleet Management Services
Tyre Management Services / Fleet Management ServicesShabbir Ahmed Khan
 
Quality Assurance vs. Quality Control in Manufacturing
Quality Assurance vs. Quality Control in ManufacturingQuality Assurance vs. Quality Control in Manufacturing
Quality Assurance vs. Quality Control in ManufacturingMonarch Metal
 
Basics of automobile
Basics of automobileBasics of automobile
Basics of automobileVivek Sheel
 
Steel plant presentation
Steel plant presentationSteel plant presentation
Steel plant presentationjoycecm
 
Quality control and inspection
Quality control and inspectionQuality control and inspection
Quality control and inspectionSujal Topno
 

Destaque (20)

Tyres and tubes
Tyres and tubesTyres and tubes
Tyres and tubes
 
Quality Control
Quality ControlQuality Control
Quality Control
 
Quality control and inspection
Quality control and inspectionQuality control and inspection
Quality control and inspection
 
Mobile apps for_old_people
Mobile apps for_old_peopleMobile apps for_old_people
Mobile apps for_old_people
 
Chapter 6
Chapter 6Chapter 6
Chapter 6
 
Poly vinyl chloride(polymers)
Poly vinyl chloride(polymers)Poly vinyl chloride(polymers)
Poly vinyl chloride(polymers)
 
Automation Technology for the Steel Industry
Automation Technology for the Steel IndustryAutomation Technology for the Steel Industry
Automation Technology for the Steel Industry
 
Jis g 3106
Jis g 3106Jis g 3106
Jis g 3106
 
Iso 10474 steel and steel products - inspection documents
Iso 10474   steel and steel products - inspection documentsIso 10474   steel and steel products - inspection documents
Iso 10474 steel and steel products - inspection documents
 
Press-on Tyres by Royal Tyres Private Limited Chennai
Press-on Tyres by Royal Tyres Private Limited ChennaiPress-on Tyres by Royal Tyres Private Limited Chennai
Press-on Tyres by Royal Tyres Private Limited Chennai
 
Japanese industrial standard
Japanese industrial standardJapanese industrial standard
Japanese industrial standard
 
Mktg Strats Tyre Industry
Mktg Strats   Tyre IndustryMktg Strats   Tyre Industry
Mktg Strats Tyre Industry
 
Wheels and tyres pages 8 and 9
Wheels and tyres pages 8 and 9Wheels and tyres pages 8 and 9
Wheels and tyres pages 8 and 9
 
Tyre Management Services / Fleet Management Services
Tyre Management Services / Fleet Management ServicesTyre Management Services / Fleet Management Services
Tyre Management Services / Fleet Management Services
 
Mobility aids
Mobility aidsMobility aids
Mobility aids
 
Airless tyres 3430
Airless tyres 3430Airless tyres 3430
Airless tyres 3430
 
Quality Assurance vs. Quality Control in Manufacturing
Quality Assurance vs. Quality Control in ManufacturingQuality Assurance vs. Quality Control in Manufacturing
Quality Assurance vs. Quality Control in Manufacturing
 
Basics of automobile
Basics of automobileBasics of automobile
Basics of automobile
 
Steel plant presentation
Steel plant presentationSteel plant presentation
Steel plant presentation
 
Quality control and inspection
Quality control and inspectionQuality control and inspection
Quality control and inspection
 

Semelhante a Quality control and inspection of tyres

Non-Pnuematic (Airless tyres) seminar presentation
Non-Pnuematic (Airless tyres) seminar presentationNon-Pnuematic (Airless tyres) seminar presentation
Non-Pnuematic (Airless tyres) seminar presentationMONISHRAZZA
 
Report of General Tyre ltd
Report of General Tyre ltdReport of General Tyre ltd
Report of General Tyre ltdMuhammad Ahmed
 
Safety of forklift.ppt
Safety of forklift.pptSafety of forklift.ppt
Safety of forklift.pptSanLwinAung2
 
Tyre Manufacturing Process at J K Tyre
Tyre Manufacturing Process at J K TyreTyre Manufacturing Process at J K Tyre
Tyre Manufacturing Process at J K TyreMayank Verma
 
14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx
14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx
14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptxPrasadPatil480241
 
Otr Wheel Engineering - Wheel inspection program 2012
Otr Wheel Engineering - Wheel inspection program 2012Otr Wheel Engineering - Wheel inspection program 2012
Otr Wheel Engineering - Wheel inspection program 2012OTR Wheel Engineering, Inc
 
Report on General Tyre Limited
Report on General Tyre LimitedReport on General Tyre Limited
Report on General Tyre LimitedMuhammad Ahmed
 
ASTM D7718 Sampling Standard (topic presented at OilDoc2015)
ASTM D7718 Sampling Standard (topic presented at OilDoc2015)ASTM D7718 Sampling Standard (topic presented at OilDoc2015)
ASTM D7718 Sampling Standard (topic presented at OilDoc2015)Rich Wurzbach
 
Autoassemblyplantlayout and ohs cathywalker-2011.5.28 2003 power point
Autoassemblyplantlayout and ohs cathywalker-2011.5.28 2003 power pointAutoassemblyplantlayout and ohs cathywalker-2011.5.28 2003 power point
Autoassemblyplantlayout and ohs cathywalker-2011.5.28 2003 power pointCathy Walker
 
Tyre retreading tqm
Tyre retreading tqmTyre retreading tqm
Tyre retreading tqmshrund
 
Manufacturing Process of Steering wheel
Manufacturing Process of Steering wheel Manufacturing Process of Steering wheel
Manufacturing Process of Steering wheel OmkarGend
 
Tire Testing.pptx
Tire Testing.pptxTire Testing.pptx
Tire Testing.pptxSnehaa82
 
Hyundai-Project Intern
Hyundai-Project InternHyundai-Project Intern
Hyundai-Project InternPrasanth Nalam
 
BAJA Presentation (1)-1.pptx
BAJA Presentation (1)-1.pptxBAJA Presentation (1)-1.pptx
BAJA Presentation (1)-1.pptxEshwarKarthik4
 
A literature review on life cycle analysis of tyre retreading
A literature review on life cycle analysis of tyre retreadingA literature review on life cycle analysis of tyre retreading
A literature review on life cycle analysis of tyre retreadingijsrd.com
 
Gear failure analysis
Gear failure analysisGear failure analysis
Gear failure analysisDavalsab M.L
 
Allison training report
Allison training reportAllison training report
Allison training reportInfosys
 

Semelhante a Quality control and inspection of tyres (20)

Non-Pnuematic (Airless tyres) seminar presentation
Non-Pnuematic (Airless tyres) seminar presentationNon-Pnuematic (Airless tyres) seminar presentation
Non-Pnuematic (Airless tyres) seminar presentation
 
Internship Report
Internship ReportInternship Report
Internship Report
 
Report of General Tyre ltd
Report of General Tyre ltdReport of General Tyre ltd
Report of General Tyre ltd
 
Safety of forklift.ppt
Safety of forklift.pptSafety of forklift.ppt
Safety of forklift.ppt
 
Tyre Manufacturing Process at J K Tyre
Tyre Manufacturing Process at J K TyreTyre Manufacturing Process at J K Tyre
Tyre Manufacturing Process at J K Tyre
 
14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx
14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx
14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx14Tyres-.pptx
 
Otr Wheel Engineering - Wheel inspection program 2012
Otr Wheel Engineering - Wheel inspection program 2012Otr Wheel Engineering - Wheel inspection program 2012
Otr Wheel Engineering - Wheel inspection program 2012
 
Report on General Tyre Limited
Report on General Tyre LimitedReport on General Tyre Limited
Report on General Tyre Limited
 
ASTM D7718 Sampling Standard (topic presented at OilDoc2015)
ASTM D7718 Sampling Standard (topic presented at OilDoc2015)ASTM D7718 Sampling Standard (topic presented at OilDoc2015)
ASTM D7718 Sampling Standard (topic presented at OilDoc2015)
 
Autoassemblyplantlayout and ohs cathywalker-2011.5.28 2003 power point
Autoassemblyplantlayout and ohs cathywalker-2011.5.28 2003 power pointAutoassemblyplantlayout and ohs cathywalker-2011.5.28 2003 power point
Autoassemblyplantlayout and ohs cathywalker-2011.5.28 2003 power point
 
Tyre retreading tqm
Tyre retreading tqmTyre retreading tqm
Tyre retreading tqm
 
Manufacturing Process of Steering wheel
Manufacturing Process of Steering wheel Manufacturing Process of Steering wheel
Manufacturing Process of Steering wheel
 
Tire Testing.pptx
Tire Testing.pptxTire Testing.pptx
Tire Testing.pptx
 
Hyundai-Project Intern
Hyundai-Project InternHyundai-Project Intern
Hyundai-Project Intern
 
BAJA Presentation (1)-1.pptx
BAJA Presentation (1)-1.pptxBAJA Presentation (1)-1.pptx
BAJA Presentation (1)-1.pptx
 
A literature review on life cycle analysis of tyre retreading
A literature review on life cycle analysis of tyre retreadingA literature review on life cycle analysis of tyre retreading
A literature review on life cycle analysis of tyre retreading
 
Gear failure analysis
Gear failure analysisGear failure analysis
Gear failure analysis
 
training report
training report training report
training report
 
Allison training report
Allison training reportAllison training report
Allison training report
 
Automobiles
AutomobilesAutomobiles
Automobiles
 

Mais de sai anjaneya

Welding — arc stud welding of metallic
Welding — arc stud welding of metallicWelding — arc stud welding of metallic
Welding — arc stud welding of metallicsai anjaneya
 
Artificial neural networks (2)
Artificial neural networks (2)Artificial neural networks (2)
Artificial neural networks (2)sai anjaneya
 
Basic concepts in manufacturing
Basic concepts in manufacturingBasic concepts in manufacturing
Basic concepts in manufacturingsai anjaneya
 
Lenoir cycle(pulse jet engine)
Lenoir cycle(pulse jet engine)Lenoir cycle(pulse jet engine)
Lenoir cycle(pulse jet engine)sai anjaneya
 
Human computer interaction
Human computer interactionHuman computer interaction
Human computer interactionsai anjaneya
 
industrial automation history
industrial automation historyindustrial automation history
industrial automation historysai anjaneya
 
Bulk to micro optics
Bulk to micro opticsBulk to micro optics
Bulk to micro opticssai anjaneya
 
Silicon(ceramics) carbide
Silicon(ceramics)  carbideSilicon(ceramics)  carbide
Silicon(ceramics) carbidesai anjaneya
 
Poly vinyl chloride
Poly vinyl chloridePoly vinyl chloride
Poly vinyl chloridesai anjaneya
 
Kevalar(composite)
Kevalar(composite)Kevalar(composite)
Kevalar(composite)sai anjaneya
 

Mais de sai anjaneya (20)

Fuel level sensor
Fuel level sensorFuel level sensor
Fuel level sensor
 
Welding — arc stud welding of metallic
Welding — arc stud welding of metallicWelding — arc stud welding of metallic
Welding — arc stud welding of metallic
 
Artificial neural networks (2)
Artificial neural networks (2)Artificial neural networks (2)
Artificial neural networks (2)
 
Basic concepts in manufacturing
Basic concepts in manufacturingBasic concepts in manufacturing
Basic concepts in manufacturing
 
Lenoir cycle(pulse jet engine)
Lenoir cycle(pulse jet engine)Lenoir cycle(pulse jet engine)
Lenoir cycle(pulse jet engine)
 
Human computer interaction
Human computer interactionHuman computer interaction
Human computer interaction
 
industrial automation history
industrial automation historyindustrial automation history
industrial automation history
 
Bulk to micro optics
Bulk to micro opticsBulk to micro optics
Bulk to micro optics
 
Ceramics
CeramicsCeramics
Ceramics
 
Silicon(ceramics) carbide
Silicon(ceramics)  carbideSilicon(ceramics)  carbide
Silicon(ceramics) carbide
 
Silicon carbide
Silicon carbideSilicon carbide
Silicon carbide
 
Poly vinyl chloride
Poly vinyl chloridePoly vinyl chloride
Poly vinyl chloride
 
Porcelain
PorcelainPorcelain
Porcelain
 
Polyurethane
PolyurethanePolyurethane
Polyurethane
 
Polystyrene
PolystyrenePolystyrene
Polystyrene
 
Nickel(metal)
Nickel(metal)Nickel(metal)
Nickel(metal)
 
Graphene
GrapheneGraphene
Graphene
 
Neoprene
NeopreneNeoprene
Neoprene
 
Kevalar(composite)
Kevalar(composite)Kevalar(composite)
Kevalar(composite)
 
Level sensor
Level sensorLevel sensor
Level sensor
 

Último

Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 

Último (20)

TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 

Quality control and inspection of tyres

  • 2. CONTENTS • Structure of Tyres • Manufacturing Processes Involved • Inspection Processes • Pre-Production Inspection • Materials Inspection • Production Inspection • Visual Inspection • Weight and Measurement Inspection • Final Inspection • Parameters of Testing • Machines Used • ISO Standards • References and Gallery
  • 3. STRUCTURE OF A TYRE Different parts of the Tyre are: • Tread: The part of the tire in contact with the ground. It must provide traction, long wear and cut resistance. The tread depth and design vary based on site and application. • Carcass: Contains the inflation medium. The greater its strength, the greater the pressure it can hold. • Breakers (Belts): These are placed between the tread and carcass. They help to join these parts. They also distribute road shock to protect the carcass. In bias/belted and radial constructions, they control the diameter of the tire. • Bead: Bundles of high tensile steel wire. They anchor the tire to the rim. • Sidewalls: The protective rubber covers on the side of a tire. • Inner liner: A specially formulated rubber compound inside the tire that minimizes permeation. It works with the rim and O-ring to contain the inflation medium in tubeless designs.
  • 4.
  • 5. MANUFACTURING PROCESSES Manufacturing Processes Involved: • Compounding and mixing: Compounding is the operation of bringing together all the ingredients required to mix a batch of rubber compound. Each component has a different mix of ingredients according to the properties required for that component. Mixing is the process of applying mechanical work to the ingredients in order to blend them into a homogeneous substance. The mixing is done in three or four stages to incorporate the ingredients in the desired order. The ideal compound at this point would have a highly uniform material dispersion; however in practice there is considerable non-uniformity to the dispersion
  • 6. • Component Separation: Components fall into three classes based on manufacturing process: calendaring, extrusion, and bead building. The extruder machine consists of a screw and barrel, screw driver, heaters, and a die. The extruder applies two conditions pressure. The extruder screw also provides for additional mixing of the compound through the shearing action of the screw. The calendar is a set of multiple large-diameter rolls that squeeze rubber compound into a thin sheet, usually of the order of 2 metres wide. • Tire building: Building is the process of assembling all the components onto a tire building drum. Typical TBM operations include the first-stage operation, where inner liner, body plies, and sidewalls are wrapped around the drum, the beads are placed, and the assembly turned up over the bead. In the second stage operation the belt package and tread are applied and the green tire is inflated and shaped.
  • 7. • Curing: Curing is the process of applying pressure to the green tire in a mould in order to give it its final shape, and applying heat energy to stimulate the chemical reaction between the rubber and other materials. • Final Finish: After the tire has been cured, there are several additional operations. Tire measurement is a test where the tire is automatically mounted on wheel halves, inflated, run against a simulated road surface, and measured for force variation. Tire balance measurement is a test where the tire is automatically placed on wheel halves, rotated at a high speed and measured for imbalance. Large commercial truck/bus tires, as well as some passenger and light truck tires, are inspected by X-ray or magnetic induction based inspection machines that can penetrate the rubber to analyze the steel cord structure. In the final step, tires are inspected by human eyes for numerous visual defects such as incomplete mould fill, exposed cords, blisters, blemishes, and others.
  • 8. TYRE INSPECTION PROCESSES • Pre-Production Inspection: As per SAE J 332, each machine to be used for composition and manufacturing of different tire types will be thoroughly inspected for any damage or defects and any other potential damaging factors detected. The purpose of this inspection process is to verify that all of the equipment and devices to be used for tire production is in working order to ensure quality products. Machines that show damage and/or defects should not be used for production to ensure that no production anomalies will take place as much as possible.
  • 10. • Materials Inspection All of the materials to be used for tire construction will be thoroughly inspected for any imperfections to avoid defective products the soonest it has been detected. The purpose of this inspection process is to ensure that all of the materials to be used are free from damage and/or defects. Materials that show signs of damage or defects will be automatically rejected and will not be used throughout the entire production process.
  • 11. • Production Inspection: All of the materials that pass the inspection process will be then transferred to the assembly line where the entire tire manufacturing process is initiated. Throughout the duration of the manufacturing process, each material will undergo different departments before getting the final product. These departments are: • Mixing and Compounding – rubber materials to be used will be mixed with different agents to form a rubber compound to be used for tires. • Calendar, Extrusion and Bead Building – all of the needed components for tire manufacturing will be prepared during this production queue to ensure all of the materials are complete prior to the next production process. • Tire Assembly – after, all of the materials have been prepared and gathered, tire building will be performed and will be inspected on a regular basis until all of the components are properly coated. • Curing – all of the tires that are halfway finished will undergo curing process where immense pressure will be applied in a mould in order to create the suitable shape of the tire. By using a machine to assist with the roundness, the success rate of curing items is above 80 percent.
  • 13. • Visual Inspection: After the production process, all of the finished products will undergo a thorough inspection regarding the condition and overall quality and design of each tire. The purpose of this inspection process is to verify that all of the tires out of production show no signs of damage or defects to ensure product reliability and durability as per quality control standards. It is important that each surface area of the tire on queue must be visually inspected and machine tested to ensure that no hidden damage is detected. • Tread Depth – the surface area of each tire will be inspected thoroughly to ensure that there are no cracks, moulds or bubbles detected. • X-RAY inspection – the internal parts of the tire will be inspected for any underlying defects that could take place during initial use to ensure that all of the tires are structurally sound and reliable right out of production.
  • 14. • Weight and Measurement Inspection: Each tire will be measured will deflated and once again once inflated to properly specify the gross and net weight of each tire according to its category. • Tire Uniformity Analysis – tires under the same category will be measured and weighed according to its product specification to ensure durability, reliability and strict quality control standards. • Tire balance – tires, regardless of type, will be attached to a machine that emulates the vehicle will be used in order to properly measure the specifications of each tire assembly. Tires that are out of balance will be checked for air pressure and overall build to ensure proper size and weight on all tires. Items that fail the weight and measurement inspection protocol will be evaluated for alternative repairs and reconstruction (depending on the damage) to save overall production time if applicable. Items that are beyond repair will be automatically marked as “DEFECTIVE
  • 15. • Final Inspection: The purpose of this inspection process is to verify that all of the tires under the production process will undergo a series of performance and battery tests while maintaining a defect-free product at the end of the testing and inspection phase. The common tests involved for this inspection process are: • Tire Balance and Performance Analysis – all of the tires will be placed on mechanisms to emulate the vehicle specified to check tire balance and if tires are structurally sound and round. • Tire rotation analysis – each tire will be put into spinning action to evaluate and analyze the behaviour of the tire being inspected while in operation to properly assess the condition of the tire and its overall composition. • High-Speed Test – all of the tires will be tested on a road-like area where tires will be tested under high speeds to check tire balance and roundness at high speeds of at least 70 miles per hour. • Damage-Rate Inspection – tires that have finished the entire inspection process will be re-analyzed for any incomplete mould fill and will be checked for damages like blemishes, blisters, exposed cords and other post- production anomalies that have taken place.
  • 16.
  • 17. PARAMETERS OF TESTING • Outdoor • Braking on a dry surface (also for motorcycles, trucks and buses) • Handling on a dry surface (also for motorcycles) • Handling on a wet surface • Braking on a wet surface ECE R 117 / EC 1222/2009 (also for trucks and buses) • Longitudinal aquaplaning • Lateral aquaplaning • Steady-state circular test on a wet surface (also for trucks and buses) • Indoor • Rolling resistance • Measurement of force and torque • Temperature (online measurement of the temperature inside the tyre, on the inner liner and at the tyre surface)
  • 18. AQUAPLANING • Aquaplaning or Hydroplaning by tyres of a road vehicle occurs when a layer of water builds between the wheels of the vehicle and the road surface, leading to a loss of traction that prevents the vehicle from responding to control inputs. • Aquaplaning is different phenomenon from water on the roadway merely acting as a lubricant.
  • 19. MACHINES USED • Tire Component Profilometer
  • 20. • Tire Colour Inspection Tire Length Inspection • Tire Component Offline Profilometer Tire Component Profilometer
  • 21. • Tire Piece Weight Inspection • Tire Component Profilometer
  • 23. REFERENCES • http://www.intouch-quality.com/blog/tire-inspection-qc-china/ • http://www.issia.cnr.it/wp/?portfolio=ndt-quality-control-of-tyres • http://www.micro-epsilon.com/download/products/cat--systems--rubber-tire--en.pdf • https://www.iso.org/obp/ui/#iso:std:63769:en • http://www.iso.org/iso/home/store/catalogue_tc/catalogue_tc_browse.htm?commid=47686 • http://optotechnik.zeiss.com/en/products/tire-testing-intact/intact-otr • http://www.tuv-sud.com/industry/automotive-transportation/automotive- solutions/automotive-component-testing/tyre-testing#tab_1427765935891907481211 • http://www.dunlop.eu/dunlop_ie/what-makes-dunlop-different/tire-tests/ • http://www.michelinman.com/US/en/safe-driving/tire-safety/inspection.html • https://www.researchgate.net/publication/258807136_Identification_and_quality_control_of_ marks_on_tires_through_artificial_vision
  • 24. GALLERY An opened tire mould being cleaned. The deflated rubber bladder is on the central post
  • 25. Structure of a Tyre Inspection in process
  • 26. Inspection in process Tyre Balance Inspection