SlideShare uma empresa Scribd logo
1 de 25
Professional ProjectProfessional Project
Approach & ProcessApproach & Process
By Ryan MifsudBy Ryan Mifsud
Manage the end to end delivery of
Application & IT Solutions
helping customers to realise their
Infrastructure Optimisation Strategies
My Qualities & PrinciplesMy Qualities & Principles
Process
Personality
Innovation
People
Relationship with
different types of
people is key to
project success ..
People
Relationship with
different types of
people is key to
project success ..
Customers
demand quality
assurance
through delivery
by due process..
Customers
demand quality
assurance
through delivery
by due process..
The ability to
suggest solutions
and alternatives
where appropriate,
demonstrates
competence and
added value to the
customer …
The ability to
suggest solutions
and alternatives
where appropriate,
demonstrates
competence and
added value to the
customer …
Typical Solutions …Typical Solutions …
• Apps Packaging & Configuration
• Apps Development / Migrations
• AD & Exchange Migrations
• Server Upgrades and Moves
• SAN/NAS Storage Solutions
• Setting up DC & DR sites
• Mobile Communications
• Consolidation/Virtualisation
……and they may compriseand they may comprise
• User Profiling, Audits and Asset Tagging
• Data Rationalisation
• Migration (Data, Apps, Users, Mail Boxes)
• Application Development or Modifications
• Legacy Equipment/System integration
• Refurbishment & Disposal
• Testing and Acceptance
• Contingency Planning and/or Roll Back
• Education/Training/Skills Transfer
• Documentation
• Support & Transition to BAU
Project DeliveryProject Delivery
• Methodologies Used
• Approach – Phased
• Financials
• Benefits
The primary challenge of project management is to achieve all of the project goals and objectives
while adhering to classic project constraints — usually scope, quality, time and budget.
The secondary and more ambitious challenge is to optimize the allocation and integration of inputs
necessary to meet pre-defined objectives. A project is a carefully defined set of activities that use
resources (money, people, materials, energy, space, provisions, communication, motivation, etc.) to
achieve the project goals and objectives.
Methodologies UsedMethodologies Used
• PRINCE II, PMI, ISO, CMMi, BSS, Waterfall, SDLC, Agile or
Combination off
– Process
– Documentation
– Quality Management
• ITIL / ISO
– Change Control
– Configuration Management
– Problem Management
– Contingency
– Release
– Capacity
– Continuity (COB)
– Availability
– Service level
• P&L Finance
– Cost Tracker - Spreadsheet
– Purchasing & Account Polices
PRINCE 2PRINCE 2
IP1 Planning Quality
IP2 Planning a Project
IP3 Refining the Business Case and Risks
IP4 Setting up Project Controls
IP5 Setting up Project Files
IP6 Assembling a Project Initiation Document
DP1 Authorising Initiation
DP2 Authorising a Project
DP3 Authorising a Stage or Exception Plan
DP4 Giving Ad Hoc Direction
DP5 Confirming Project Closure
CS1 Authorising Work Package
CS2 Assessing Progress
CS3 Capturing Project Issues
CS4 Examining Project Issues
CS5 Reviewing Stage Status
CS6 Reporting Highlights
CS7 Taking Corrective Action
CS8 Escalating Project Issues
CS9 Receiving Completed Work Package
MP1 Accepting a Work Package
MP2 Executing a Work Package
MP3 Delivering a Work Package
SB1 Planning a Stage
SB2 Updating a Project Plan
SB3 Updating a Project Business Case
SB4 Updating the Risk Log
SB5 Reporting Stage End
SB6 Producing an Exception Plan Closing a project (CP)
Initiating a project (IP)
Controlling a stage (CS)
Managing product
Delivery (MP)
Managing stage
boundaries (SB)
SU1 Appointing a Project Board Exec and Project
Manager
SU2 Designing a Project Management Team
SU3 Appointing a Project Management Team
SU4 Preparing a Project Brief
SU5 Defining Project Approach
SU6 Planning an Initiation Stage
Starting up a project (SU)
PL1 Designing a Plan
PL2 Defining and Analysing Products
PL3 Identifying Activities and Dependencies
PL4 Estimating
PL5 Scheduling
PL6 Analysing Risks
PL7 Completing a Plan
Planning (PL)
Directing a project (DP)
Product Based Planning
Change Control
Quality Reviews
The five process groups are:
• Initiating,
• Planning,
• Executing,
• Controlling and Monitoring, and
• Closing.
PMI
IEEE Std 1490™-2003
The nine knowledge areas are:
•Project Integration Management
•Project Scope Management
•Project Time Management
•Project Cost Management
•Project Quality Management
•Project Human Resource Management
•Project Communications Management
•Project Risk Management
•Project Procurement Management
WaterfallWaterfall• Requirements
specification (AKA
Verification)
• Design
• Construction (AKA
implementation or
coding)
• Integration
• Testing and debugging
(AKA validation)
• Installation (AKA
deployment)
• Maintenance
SDLCSDLC
• Project Selection
• Initiating
• Planning
• Requirements
Definition
• Functional Design
• System Design
• Programming and
Development
• Integration and
Testing
• Installation and
Acceptance
• Closing
• Maintenance
• Training
• Retirement
• Model
• Implementation
• Test
• Deployment
• Configuration
Management
• Project management
• Environment
AGILEAGILE
Process Software
Development
Phased Solutions DeliveryPhased Solutions Delivery
Approach SimplifiedApproach Simplified
Engagement
Phase 1
Design
Phase 2a
POC & Pilot
Phase 2b
Deployment
Phase 3a
Close
Phase 3b
Engagement – PDWEngagement – PDW
(Project Definition Workshop)(Project Definition Workshop)
INPUT - Customer
• Project objectives & scope
• Any known exclusions,
constraints, assumptions &
dependencies
• Any known risks & issues
• Key stakeholders
INPUT – Templates
• Statements of work
• Rules of engagement, terms
& conditions
OUTPUT – Joint
• Approach, deliverables &
high level plan
• Likely resource requirements
• Project environment and
requirements
OUTPUT
• The costs for the Design and
POC & Pilot phase and
other indicative costs
Design - PIDDesign - PID
(Project Initiation Document)(Project Initiation Document)
• Undertake the design workshops
• Create the scope of works
• Agree the solutions design
• Spec the deployment plan, deliverables, resources
and schedule
• Spec the POC & Pilot plan, deliverables, resources,
schedule and success criteria
• Create the PID
• Provide costs for the POC & Pilot, and other
indicative costs
POC & PilotPOC & Pilot
(Validate)(Validate)
• Undertake the POC & Pilot and any revision
• Agree the final POC & Pilot solution
• Confirm the scope of works, solution design,
deployment plan, deliverables, resources, schedule
and Build
• Update the risks and issues log
• Provide costs for Deployment and Closure
DeploymentDeployment
(Build)(Build)
• Execute and progress the project plan
• Initiate work packages and schedule project
resources
• Deliver, test and accept the agreed deliverables
• Manage regular progress review meetings and
attend project board reviews
• Produce weekly highlight and progress reports, and
action lists
• Track costs incurred
• Update the risk and issues logs; manage mitigation
and resolution; process change requests
• Update the lessons learned log
CloseClose
• Create the initial project closure document
• Hold the initial project closure project
management review meeting
• Agree the project closure document
• Attend the project closure project board
review meeting
• Agree any follow up actions
• Decommission the project environment
• Project sign off
RAG Reporting MadeRAG Reporting Made
SimpleSimple
Red, Amber, Green Reporting on one A3 Sheet containing;
Escalation Matrix
Resource Calendar
Key Milestones
Key Deliverables
Actions Log
Risk log
Issues Log
Lessoned Learned
Dependencies
Assumptions
Application Status
Contingency Planner
Out of scope
Each section RAG reported incorporation with estimated date
… with in Change
Management …
… with in Change
Management …
… Project is part of
ITIL Framework …
… Project is part of
ITIL Framework …
… Effecting and
impacting on service
delivery …
… Effecting and
impacting on service
delivery …
P&L Financial TrackingP&L Financial Tracking
• Keeping Project Finances on track
– COST Tracker + Spreadsheets
• Managing Purchasing and 3rd
Party Resources
• Ensuring that both Customers and Companies
Accounting/Finance Polices are adhered too
Tabs for various
worksheets, used to
enter summarised
data shown here …
Tabs for various
worksheets, used to
enter summarised
data shown here …
You can enter Multiple PO’s. The
first value shown is the sum of
all the PO values …
You can enter Multiple PO’s. The
first value shown is the sum of
all the PO values …
Summary
values by
resource …
Summary
values by
resource …
Summary
values by
Month …
Summary
values by
Month …
BH=Bank Holiday
FoC= Free of Charge
H=Holiday
MF=Managed Fund
S= Sick
Tr=Training
BH=Bank Holiday
FoC= Free of Charge
H=Holiday
MF=Managed Fund
S= Sick
Tr=Training
Resource worksheet
allows you to enter:
•Resources types,
•Rates,
•Number of days allocated
•Etc
Resource worksheet
allows you to enter:
•Resources types,
•Rates,
•Number of days allocated
•Etc
Here we see information
being entered against the
actual resource …
Here we see information
being entered against the
actual resource …
…and
summarised
here …
…and
summarised
here …
…These must be entered
in “Resource”
“Resource Type” first
…These must be entered
in “Resource”
“Resource Type” first
… the ability to record
expenses …
… the ability to record
expenses …
… Actual vs Forecast
graphs …
… Actual vs Forecast
graphs …
… Resource
Utilisation Charts …
… Resource
Utilisation Charts …
Solution BenefitsSolution Benefits
Delivery Management approach provides:
• A structured step by step approach
• A Value Add deliverable after each Phase
• Smaller sign off authorisation required
• Rapid take on of a fully managed Solution Delivery
• Continuous Quality Assurance
• Flexibility and Scalability
• Continuous Communication & Transparency
• Reduced Risk
Questions ?Questions ?

Mais conteúdo relacionado

Mais procurados

Project management
Project managementProject management
Project managementtwilight89
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
L05 time management
L05 time managementL05 time management
L05 time managementAsa Chan
 
Bechtel project planning example
Bechtel project planning exampleBechtel project planning example
Bechtel project planning exampleasfandiyar
 
Project Management
Project ManagementProject Management
Project Managementguest4408ddc
 
Price.rick
Price.rickPrice.rick
Price.rickNASAPMC
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
2018 Project Management Workshop Schedule - Project Management Training - Dco...
2018 Project Management Workshop Schedule - Project Management Training - Dco...2018 Project Management Workshop Schedule - Project Management Training - Dco...
2018 Project Management Workshop Schedule - Project Management Training - Dco...Dcolearning
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaEdureka!
 
Project management planning
Project management planningProject management planning
Project management planningAlvin Niere
 
Project-Planning
Project-PlanningProject-Planning
Project-PlanningRon Drew
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryMichael Pink
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 

Mais procurados (20)

Schedule Review
Schedule ReviewSchedule Review
Schedule Review
 
Project management
Project managementProject management
Project management
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
L05 time management
L05 time managementL05 time management
L05 time management
 
Bechtel project planning example
Bechtel project planning exampleBechtel project planning example
Bechtel project planning example
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Project Management
Project ManagementProject Management
Project Management
 
Price.rick
Price.rickPrice.rick
Price.rick
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
2018 Project Management Workshop Schedule - Project Management Training - Dco...
2018 Project Management Workshop Schedule - Project Management Training - Dco...2018 Project Management Workshop Schedule - Project Management Training - Dco...
2018 Project Management Workshop Schedule - Project Management Training - Dco...
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
 
Project management planning
Project management planningProject management planning
Project management planning
 
Project-Planning
Project-PlanningProject-Planning
Project-Planning
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
06 project time management
06  project time management06  project time management
06 project time management
 

Semelhante a Project Management_c

Training on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.pptTraining on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.pptAshwaniKumar207236
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01petch phanpha
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
Training on ASAP Methodology.ppt
Training on ASAP Methodology.pptTraining on ASAP Methodology.ppt
Training on ASAP Methodology.pptAshwaniKumar207236
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1Toe Myint Naing
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
PmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit PayalPmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit PayalAMIT PAYAL
 
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docxRAJU852744
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxChandrasen Sharma
 
Solve It Labs Offshore Project Management
Solve It Labs Offshore Project ManagementSolve It Labs Offshore Project Management
Solve It Labs Offshore Project ManagementRafael Sultanov
 
Tough projects keeping them on course -1- mike mellin 02-18-16
Tough projects   keeping them on course -1- mike mellin 02-18-16Tough projects   keeping them on course -1- mike mellin 02-18-16
Tough projects keeping them on course -1- mike mellin 02-18-16Mike Mellin, BSEE/MS
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptxProfDrAnbalaganChinn
 
Essentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev AEssentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev ASteve Kiester
 

Semelhante a Project Management_c (20)

Training on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.pptTraining on ASAP Methodology_11.10.2020.ppt
Training on ASAP Methodology_11.10.2020.ppt
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Project management
Project managementProject management
Project management
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Training on ASAP Methodology.ppt
Training on ASAP Methodology.pptTraining on ASAP Methodology.ppt
Training on ASAP Methodology.ppt
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
PmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit PayalPmiprojectmanagementprinciplesAmit Payal
PmiprojectmanagementprinciplesAmit Payal
 
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
122 Part 1 - GuideFigure 4-15. Close Project or Phase Dat.docx
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptx
 
Solve It Labs Offshore Project Management
Solve It Labs Offshore Project ManagementSolve It Labs Offshore Project Management
Solve It Labs Offshore Project Management
 
bingsusu.pptx
bingsusu.pptxbingsusu.pptx
bingsusu.pptx
 
PMP Prep Handout_Integration
PMP Prep Handout_IntegrationPMP Prep Handout_Integration
PMP Prep Handout_Integration
 
Benefits of EPM
Benefits of EPMBenefits of EPM
Benefits of EPM
 
Tough projects keeping them on course -1- mike mellin 02-18-16
Tough projects   keeping them on course -1- mike mellin 02-18-16Tough projects   keeping them on course -1- mike mellin 02-18-16
Tough projects keeping them on course -1- mike mellin 02-18-16
 
2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx2. PAE AcFn621 Ch-2 Principle ppt.pptx
2. PAE AcFn621 Ch-2 Principle ppt.pptx
 
Essentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev AEssentials of Entry Level Project Management - Rev A
Essentials of Entry Level Project Management - Rev A
 

Project Management_c

  • 1. Professional ProjectProfessional Project Approach & ProcessApproach & Process By Ryan MifsudBy Ryan Mifsud Manage the end to end delivery of Application & IT Solutions helping customers to realise their Infrastructure Optimisation Strategies
  • 2. My Qualities & PrinciplesMy Qualities & Principles Process Personality Innovation People Relationship with different types of people is key to project success .. People Relationship with different types of people is key to project success .. Customers demand quality assurance through delivery by due process.. Customers demand quality assurance through delivery by due process.. The ability to suggest solutions and alternatives where appropriate, demonstrates competence and added value to the customer … The ability to suggest solutions and alternatives where appropriate, demonstrates competence and added value to the customer …
  • 3. Typical Solutions …Typical Solutions … • Apps Packaging & Configuration • Apps Development / Migrations • AD & Exchange Migrations • Server Upgrades and Moves • SAN/NAS Storage Solutions • Setting up DC & DR sites • Mobile Communications • Consolidation/Virtualisation
  • 4. ……and they may compriseand they may comprise • User Profiling, Audits and Asset Tagging • Data Rationalisation • Migration (Data, Apps, Users, Mail Boxes) • Application Development or Modifications • Legacy Equipment/System integration • Refurbishment & Disposal • Testing and Acceptance • Contingency Planning and/or Roll Back • Education/Training/Skills Transfer • Documentation • Support & Transition to BAU
  • 5. Project DeliveryProject Delivery • Methodologies Used • Approach – Phased • Financials • Benefits The primary challenge of project management is to achieve all of the project goals and objectives while adhering to classic project constraints — usually scope, quality, time and budget. The secondary and more ambitious challenge is to optimize the allocation and integration of inputs necessary to meet pre-defined objectives. A project is a carefully defined set of activities that use resources (money, people, materials, energy, space, provisions, communication, motivation, etc.) to achieve the project goals and objectives.
  • 6. Methodologies UsedMethodologies Used • PRINCE II, PMI, ISO, CMMi, BSS, Waterfall, SDLC, Agile or Combination off – Process – Documentation – Quality Management • ITIL / ISO – Change Control – Configuration Management – Problem Management – Contingency – Release – Capacity – Continuity (COB) – Availability – Service level • P&L Finance – Cost Tracker - Spreadsheet – Purchasing & Account Polices
  • 7. PRINCE 2PRINCE 2 IP1 Planning Quality IP2 Planning a Project IP3 Refining the Business Case and Risks IP4 Setting up Project Controls IP5 Setting up Project Files IP6 Assembling a Project Initiation Document DP1 Authorising Initiation DP2 Authorising a Project DP3 Authorising a Stage or Exception Plan DP4 Giving Ad Hoc Direction DP5 Confirming Project Closure CS1 Authorising Work Package CS2 Assessing Progress CS3 Capturing Project Issues CS4 Examining Project Issues CS5 Reviewing Stage Status CS6 Reporting Highlights CS7 Taking Corrective Action CS8 Escalating Project Issues CS9 Receiving Completed Work Package MP1 Accepting a Work Package MP2 Executing a Work Package MP3 Delivering a Work Package SB1 Planning a Stage SB2 Updating a Project Plan SB3 Updating a Project Business Case SB4 Updating the Risk Log SB5 Reporting Stage End SB6 Producing an Exception Plan Closing a project (CP) Initiating a project (IP) Controlling a stage (CS) Managing product Delivery (MP) Managing stage boundaries (SB) SU1 Appointing a Project Board Exec and Project Manager SU2 Designing a Project Management Team SU3 Appointing a Project Management Team SU4 Preparing a Project Brief SU5 Defining Project Approach SU6 Planning an Initiation Stage Starting up a project (SU) PL1 Designing a Plan PL2 Defining and Analysing Products PL3 Identifying Activities and Dependencies PL4 Estimating PL5 Scheduling PL6 Analysing Risks PL7 Completing a Plan Planning (PL) Directing a project (DP) Product Based Planning Change Control Quality Reviews
  • 8. The five process groups are: • Initiating, • Planning, • Executing, • Controlling and Monitoring, and • Closing. PMI IEEE Std 1490™-2003 The nine knowledge areas are: •Project Integration Management •Project Scope Management •Project Time Management •Project Cost Management •Project Quality Management •Project Human Resource Management •Project Communications Management •Project Risk Management •Project Procurement Management
  • 9. WaterfallWaterfall• Requirements specification (AKA Verification) • Design • Construction (AKA implementation or coding) • Integration • Testing and debugging (AKA validation) • Installation (AKA deployment) • Maintenance SDLCSDLC • Project Selection • Initiating • Planning • Requirements Definition • Functional Design • System Design • Programming and Development • Integration and Testing • Installation and Acceptance • Closing • Maintenance • Training • Retirement • Model • Implementation • Test • Deployment • Configuration Management • Project management • Environment AGILEAGILE Process Software Development
  • 10. Phased Solutions DeliveryPhased Solutions Delivery Approach SimplifiedApproach Simplified Engagement Phase 1 Design Phase 2a POC & Pilot Phase 2b Deployment Phase 3a Close Phase 3b
  • 11. Engagement – PDWEngagement – PDW (Project Definition Workshop)(Project Definition Workshop) INPUT - Customer • Project objectives & scope • Any known exclusions, constraints, assumptions & dependencies • Any known risks & issues • Key stakeholders INPUT – Templates • Statements of work • Rules of engagement, terms & conditions OUTPUT – Joint • Approach, deliverables & high level plan • Likely resource requirements • Project environment and requirements OUTPUT • The costs for the Design and POC & Pilot phase and other indicative costs
  • 12. Design - PIDDesign - PID (Project Initiation Document)(Project Initiation Document) • Undertake the design workshops • Create the scope of works • Agree the solutions design • Spec the deployment plan, deliverables, resources and schedule • Spec the POC & Pilot plan, deliverables, resources, schedule and success criteria • Create the PID • Provide costs for the POC & Pilot, and other indicative costs
  • 13. POC & PilotPOC & Pilot (Validate)(Validate) • Undertake the POC & Pilot and any revision • Agree the final POC & Pilot solution • Confirm the scope of works, solution design, deployment plan, deliverables, resources, schedule and Build • Update the risks and issues log • Provide costs for Deployment and Closure
  • 14. DeploymentDeployment (Build)(Build) • Execute and progress the project plan • Initiate work packages and schedule project resources • Deliver, test and accept the agreed deliverables • Manage regular progress review meetings and attend project board reviews • Produce weekly highlight and progress reports, and action lists • Track costs incurred • Update the risk and issues logs; manage mitigation and resolution; process change requests • Update the lessons learned log
  • 15. CloseClose • Create the initial project closure document • Hold the initial project closure project management review meeting • Agree the project closure document • Attend the project closure project board review meeting • Agree any follow up actions • Decommission the project environment • Project sign off
  • 16. RAG Reporting MadeRAG Reporting Made SimpleSimple Red, Amber, Green Reporting on one A3 Sheet containing; Escalation Matrix Resource Calendar Key Milestones Key Deliverables Actions Log Risk log Issues Log Lessoned Learned Dependencies Assumptions Application Status Contingency Planner Out of scope Each section RAG reported incorporation with estimated date
  • 17. … with in Change Management … … with in Change Management … … Project is part of ITIL Framework … … Project is part of ITIL Framework … … Effecting and impacting on service delivery … … Effecting and impacting on service delivery …
  • 18. P&L Financial TrackingP&L Financial Tracking • Keeping Project Finances on track – COST Tracker + Spreadsheets • Managing Purchasing and 3rd Party Resources • Ensuring that both Customers and Companies Accounting/Finance Polices are adhered too
  • 19. Tabs for various worksheets, used to enter summarised data shown here … Tabs for various worksheets, used to enter summarised data shown here … You can enter Multiple PO’s. The first value shown is the sum of all the PO values … You can enter Multiple PO’s. The first value shown is the sum of all the PO values … Summary values by resource … Summary values by resource … Summary values by Month … Summary values by Month …
  • 20. BH=Bank Holiday FoC= Free of Charge H=Holiday MF=Managed Fund S= Sick Tr=Training BH=Bank Holiday FoC= Free of Charge H=Holiday MF=Managed Fund S= Sick Tr=Training Resource worksheet allows you to enter: •Resources types, •Rates, •Number of days allocated •Etc Resource worksheet allows you to enter: •Resources types, •Rates, •Number of days allocated •Etc
  • 21. Here we see information being entered against the actual resource … Here we see information being entered against the actual resource … …and summarised here … …and summarised here … …These must be entered in “Resource” “Resource Type” first …These must be entered in “Resource” “Resource Type” first
  • 22. … the ability to record expenses … … the ability to record expenses …
  • 23. … Actual vs Forecast graphs … … Actual vs Forecast graphs … … Resource Utilisation Charts … … Resource Utilisation Charts …
  • 24. Solution BenefitsSolution Benefits Delivery Management approach provides: • A structured step by step approach • A Value Add deliverable after each Phase • Smaller sign off authorisation required • Rapid take on of a fully managed Solution Delivery • Continuous Quality Assurance • Flexibility and Scalability • Continuous Communication & Transparency • Reduced Risk