Activity ID Activity Name Original
Duration
Start Finish
0 TC2A - Manifolding Topsides Modules-(baseline)0 TC2A - Manifolding Topsides Modules-(baseline) 333 13-Mar-15 08-Apr-16
0.D.26 Process System0.D.26 Process System 333 13-Mar-15 08-Apr-16
0.D.26.0000 Sub System Code Level0.D.26.0000 Sub System Code Level 333 13-Mar-15 08-Apr-16
0.D.26.0000.MM1 MM1-Manifold and Pigging0.D.26.0000.MM1 MM1-Manifold and Pigging 333 13-Mar-15 08-Apr-16
0.D.26.0000.MM1.A Milestone0.D.26.0000.MM1.A Milestone 333 13-Mar-15 08-Apr-16
MM1-10010 Effective date (LOI) 0 13-Mar-15*
MM1-101000 Commence Basic & Detail Engineering Modules MM1 0 13-Mar-15*
MM1-101040 HAZID Review Workshop 0 23-Mar-15*
MM1-101060 HAZOP Review Workshop 0 27-Apr-15*
MM1-101080 Commence Fab Modules MM1 0 17-Sep-15
MM1-101020 Completion Basic & Detail Engineering Modules MM1 0 23-Sep-15*
MM1-10070 MCD for MM1 0 24-Mar-16*
MM1-10090 Commence Load-out Modules MM1 0 26-Mar-16*
MM1-101100 Modules MM1 available at Singapore Yard 0 08-Apr-16*
0.D.26.0000.MM1.B Engineering0.D.26.0000.MM1.B Engineering 327 13-Mar-15 01-Apr-16
0.D.26.0000.MM1.B.0 General0.D.26.0000.MM1.B.0 General 321 13-Mar-15 01-Apr-16
0.D.26.0000.MM1.B.0.92 PTSC0.D.26.0000.MM1.B.0.92 PTSC 321 13-Mar-15 01-Apr-16
MM1-10130 General for PMT (Meeting, Project Management, Project Coordination, Engineering review, etc)321 13-Mar-15 01-Apr-16
MM1-1305-PT-00-A-TB-00001MM1 & MM2 - Detailed Engineering Execution Plan 40 13-Mar-15 29-Apr-15
MM1-1305-PT-00-A-TB-00001-1MM1 & MM2 - Detailed Engineering Execution Plan-IDC 8 13-Mar-15* 21-Mar-15
MM1-1305-PT-00-A-TB-00001-2MM1 & MM2 - Detailed Engineering Execution Plan-IFR 6 23-Mar-15 28-Mar-15
MM1-1305-PT-00-A-TB-00001-3MM1 & MM2 - Detailed Engineering Execution Plan-IFD 11 30-Mar-15 10-Apr-15
MM1-1305-PT-00-A-TB-00001-4MM1 & MM2 - Detailed Engineering Execution Plan-IFC 15 11-Apr-15 29-Apr-15
MM1-1305-PT-00-A-KA-00001MM1 & MM2 - Detailed Engineering Coordination Procedure 31 13-Mar-15 17-Apr-15
MM1-1305-PT-00-A-KA-00001-1MM1 & MM2 - Detailed Engineering Coordination Procedure-IDC 8 13-Mar-15* 21-Mar-15
MM1-1305-PT-00-A-KA-00001-2MM1 & MM2 - Detailed Engineering Coordination Procedure-IFR 6 23-Mar-15 28-Mar-15
MM1-1305-PT-00-A-KA-00001-3MM1 & MM2 - Detailed Engineering Coordination Procedure-IFD 0 30-Mar-15 30-Mar-15
MM1-1305-PT-00-A-KA-00001-4MM1 & MM2 - Detailed Engineering Coordination Procedure-IFC 17 30-Mar-15 17-Apr-15
0.D.26.0000.MM1.B.9 3D Modelling0.D.26.0000.MM1.B.9 3D Modelling 65 12-May-15 25-Jul-15
0.D.26.0000.MM1.B.9.92 PTSC0.D.26.0000.MM1.B.9.92 PTSC 65 12-May-15 25-Jul-15
MM1-1305-PT-00-L-RA-00001MM1 & MM2 - PDMS 30% model review report 17 12-May-15 30-May-15
MM1-1305-PT-00-L-RA-00001-1MM1 & MM2 - PDMS 30% model review report-IDC 7 12-May-15* 19-May-15
MM1-1305-PT-00-L-RA-00001-2MM1 & MM2 - PDMS 30% model review report-IFR 4 20-May-15 23-May-15
MM1-1305-PT-00-L-RA-00001-3MM1 & MM2 - PDMS 30% model review report-IFD 0 25-May-15 25-May-15
MM1-1305-PT-00-L-RA-00001-4MM1 & MM2 - PDMS 30% model review report-IFC 6 25-May-15 30-May-15
MM1-1305-PT-00-L-RA-00002MM1 & MM2 - PDMS 60% model review report 17 09-Jun-15 27-Jun-15
MM1-1305-PT-00-L-RA-00002-1MM1 & MM2 - PDMS 60% model review report-IDC 7 09-Jun-15* 16-Jun-15
MM1-1305-PT-00-L-RA-00002-2MM1 & MM2 - PDMS 60% model review report-IFR 4 17-Jun-15 20-Jun-15
MM1-1305-PT-00-L-RA-00002-3MM1 & MM2 - PDMS 60% model review report-IFD 0 22-Jun-15 22-Jun-15
MM1-1305-PT-00-L-RA-00002-4MM1 & MM2 - PDMS 60% model review report-IFC 6 22-Jun-15 27-Jun-15
MM1-1305-PT-00-L-RA-00003MM1 & MM2 - PDMS 90% model review report 17 07-Jul-15 25-Jul-15
MM1-1305-PT-00-L-RA-00003-1MM1 & MM2 - PDMS 90% model review report -IDC 7 07-Jul-15* 14-Jul-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Effective date (LOI)
Commence Basic & Detail Engineering Modules MM1
HAZID Review Workshop
HAZOP Review Workshop
Commence Fab Modules MM1
Completion Basic & Detail Engineering Modules MM1
MCD for MM1
Commence Load-out Modu
Modules MM1 available
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 1 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-00-L-RA-00003-2MM1 & MM2 - PDMS 90% model review report -IFR 4 15-Jul-15 18-Jul-15
MM1-1305-PT-00-L-RA-00003-3MM1 & MM2 - PDMS 90% model review report -IFD 0 20-Jul-15 20-Jul-15
MM1-1305-PT-00-L-RA-00003-4MM1 & MM2 - PDMS 90% model review report -IFC 6 20-Jul-15 25-Jul-15
0.D.26.0000.MM1.B.S Process & Systems0.D.26.0000.MM1.B.S Process & Systems 79 13-Mar-15 16-Jun-15
0.D.26.0000.MM1.B.S.92 PTSC0.D.26.0000.MM1.B.S.92 PTSC 79 13-Mar-15 16-Jun-15
MM1-1305-PT-30-P-FD-00001MM1 & MM2 - Basic Design Data 47 13-Mar-15 09-May-15
MM1-1305-PT-30-P-FD-00001-1MM1 & MM2 - Basic Design Data-IDC 9 13-Mar-15* 23-Mar-15
MM1-1305-PT-30-P-FD-00001-2MM1 & MM2 - Basic Design Data-IFR 7 24-Mar-15 31-Mar-15
MM1-1305-PT-30-P-FD-00001-3MM1 & MM2 - Basic Design Data-IFD 13 01-Apr-15 15-Apr-15
MM1-1305-PT-30-P-FD-00001-4MM1 & MM2 - Basic Design Data-IFC 18 16-Apr-15 09-May-15
MM1-1305-PT-30-P-RA-00001MM1 & MM2 - Report - HYSYS Simulation 48 13-Mar-15 11-May-15
MM1-1305-PT-30-P-RA-00001-1MM1 & MM2 - Report - HYSYS Simulation-IDC 1 13-Mar-15* 13-Mar-15
MM1-1305-PT-30-P-RA-00001-2MM1 & MM2 - Report - HYSYS Simulation-IFR 17 14-Mar-15 02-Apr-15
MM1-1305-PT-30-P-RA-00001-3MM1 & MM2 - Report - HYSYS Simulation-IFD 13 03-Apr-15 17-Apr-15
MM1-1305-PT-30-P-RA-00001-4MM1 & MM2 - Report - HYSYS Simulation-IFC 17 18-Apr-15 11-May-15
MM1-1305-PT-30-P-RA-00002MM1 & MM2 - Report - Line Sizing 55 03-Apr-15 09-Jun-15
MM1-1305-PT-30-P-RA-00002-1MM1 & MM2 - Report - Line Sizing-IDC 1 03-Apr-15* 03-Apr-15
MM1-1305-PT-30-P-RA-00002-2MM1 & MM2 - Report - Line Sizing-IFR 21 04-Apr-15 29-Apr-15
MM1-1305-PT-30-P-RA-00002-3MM1 & MM2 - Report - Line Sizing-IFD 13 02-May-15 16-May-15
MM1-1305-PT-30-P-RA-00002-4MM1 & MM2 - Report - Line Sizing-IFC 20 18-May-15 09-Jun-15
MM1-1305-PT-30-P-RA-00003MM1 & MM2 - Report - Utility Summary 40 22-Apr-15 10-Jun-15
MM1-1305-PT-30-P-RA-00003-1MM1 & MM2 - Report - Utility Summary-IDC 1 22-Apr-15* 22-Apr-15
MM1-1305-PT-30-P-RA-00003-2MM1 & MM2 - Report - Utility Summary-IFR 6 23-Apr-15 02-May-15
MM1-1305-PT-30-P-RA-00003-3MM1 & MM2 - Report - Utility Summary-IFD 12 04-May-15 16-May-15
MM1-1305-PT-30-P-RA-00003-4MM1 & MM2 - Report - Utility Summary-IFC 21 18-May-15 10-Jun-15
MM1-1305-PT-30-P-CA-00001MM1 & MM2 - Calculation Note - Depressuring 44 23-Mar-15 15-May-15
MM1-1305-PT-30-P-CA-00001-1MM1 & MM2 - Calculation Note - Depressuring -IDC 1 23-Mar-15* 23-Mar-15
MM1-1305-PT-30-P-CA-00001-2MM1 & MM2 - Calculation Note - Depressuring -IFR 12 24-Mar-15 06-Apr-15
MM1-1305-PT-30-P-CA-00001-3MM1 & MM2 - Calculation Note - Depressuring -IFD 13 07-Apr-15 21-Apr-15
MM1-1305-PT-30-P-CA-00001-4MM1 & MM2 - Calculation Note - Depressuring -IFC 18 22-Apr-15 15-May-15
MM1-1305-PT-30-P-CA-00002MM1 & MM2 - Calculation Note - PSV Sizing 44 07-Apr-15 30-May-15
MM1-1305-PT-30-P-CA-00002-1MM1 & MM2 - Calculation Note - PSV Sizing -IDC 1 07-Apr-15* 07-Apr-15
MM1-1305-PT-30-P-CA-00002-2MM1 & MM2 - Calculation Note - PSV Sizing -IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-CA-00002-3MM1 & MM2 - Calculation Note - PSV Sizing -IFD 10 22-Apr-15 06-May-15
MM1-1305-PT-30-P-CA-00002-4MM1 & MM2 - Calculation Note - PSV Sizing -IFC 21 07-May-15 30-May-15
MM1-1305-PT-30-P-XA-00001MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets) 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XA-00001-1MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XA-00001-2MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XA-00001-3MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XA-00001-4MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XA-00002MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets) 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XA-00002-1MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 2 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-30-P-XA-00002-2MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XA-00002-3MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XA-00002-4MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XA-00003MM1 & MM2 - Material Selection Diagrams (3 Sheets) 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XA-00003-1MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XA-00003-2MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XA-00003-3MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XA-00003-4MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00001MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00001-1MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00001-2MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00001-3MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00001-4MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00002MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00002-1MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00002-2MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00002-3MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00002-4MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00003MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00003-1MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00003-2MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00003-3MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00003-4MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00004MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00004-1MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00004-2MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00004-3MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00004-4MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00005MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00005-1MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00005-2MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00005-3MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00005-4MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00006MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00006-1MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00006-2MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00006-3MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00006-4MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00007MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00007-1MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00007-2MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00007-3MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 3 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-30-P-XB-00007-4MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00008MM1 & MM2 - P&ID HP Oil Production Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00008-1MM1 & MM2 - P&ID HP Oil Production Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00008-2MM1 & MM2 - P&ID HP Oil Production Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00008-3MM1 & MM2 - P&ID HP Oil Production Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00008-4MM1 & MM2 - P&ID HP Oil Production Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00009MM1 & MM2 - P&ID HHP Oil Production Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00009-1MM1 & MM2 - P&ID HHP Oil Production Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00009-2MM1 & MM2 - P&ID HHP Oil Production Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00009-3MM1 & MM2 - P&ID HHP Oil Production Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00009-4MM1 & MM2 - P&ID HHP Oil Production Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00010MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets) 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00010-1MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00010-2MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00010-3MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00010-4MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00011MM1 & MM2 - P&ID Test Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00011-1MM1 & MM2 - P&ID Test Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00011-2MM1 & MM2 - P&ID Test Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00011-3MM1 & MM2 - P&ID Test Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00011-4MM1 & MM2 - P&ID Test Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00012MM1 & MM2 - P&ID Gas Injection Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00012-1MM1 & MM2 - P&ID Gas Injection Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00012-2MM1 & MM2 - P&ID Gas Injection Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00012-3MM1 & MM2 - P&ID Gas Injection Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00012-4MM1 & MM2 - P&ID Gas Injection Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00013MM1 & MM2 - P&ID Water Injection Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00013-1MM1 & MM2 - P&ID Water Injection Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00013-2MM1 & MM2 - P&ID Water Injection Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00013-3MM1 & MM2 - P&ID Water Injection Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00013-4MM1 & MM2 - P&ID Water Injection Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00014MM1 & MM2 - P&ID Gas Export Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00014-1MM1 & MM2 - P&ID Gas Export Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00014-2MM1 & MM2 - P&ID Gas Export Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00014-3MM1 & MM2 - P&ID Gas Export Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00014-4MM1 & MM2 - P&ID Gas Export Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00015MM1 & MM2 - P&ID Gas Lift Manifold 69 13-Mar-15 04-Jun-15
MM1-1305-PT-30-P-XB-00015-1MM1 & MM2 - P&ID Gas Lift Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00015-2MM1 & MM2 - P&ID Gas Lift Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00015-3MM1 & MM2 - P&ID Gas Lift Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00015-4MM1 & MM2 - P&ID Gas Lift Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-XB-00016MM1 & MM2 - P&ID Diesel Manifold 69 13-Mar-15 04-Jun-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 4 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-30-P-XB-00016-1MM1 & MM2 - P&ID Diesel Manifold-IDC 22 13-Mar-15* 07-Apr-15
MM1-1305-PT-30-P-XB-00016-2MM1 & MM2 - P&ID Diesel Manifold-IFR 12 08-Apr-15 21-Apr-15
MM1-1305-PT-30-P-XB-00016-3MM1 & MM2 - P&ID Diesel Manifold-IFD 14 22-Apr-15 11-May-15
MM1-1305-PT-30-P-XB-00016-4MM1 & MM2 - P&ID Diesel Manifold-IFC 21 12-May-15 04-Jun-15
MM1-1305-PT-30-P-LA-00001MM1 & MM2 - Line List 56 09-Apr-15 16-Jun-15
MM1-1305-PT-30-P-LA-00001-1MM1 & MM2 - Line List-IDC 14 09-Apr-15* 24-Apr-15
MM1-1305-PT-30-P-LA-00001-2MM1 & MM2 - Line List-IFR 10 25-Apr-15 09-May-15
MM1-1305-PT-30-P-LA-00001-3MM1 & MM2 - Line List-IFD 14 11-May-15 26-May-15
MM1-1305-PT-30-P-LA-00001-4MM1 & MM2 - Line List-IFC 18 27-May-15 16-Jun-15
MM1-1305-PT-30-P-XM-00001MM1 & MM2 - Safe Chart 52 08-Apr-15 10-Jun-15
MM1-1305-PT-30-P-XM-00001-1MM1 & MM2 - Safe Chart-IDC 7 08-Apr-15* 15-Apr-15
MM1-1305-PT-30-P-XM-00001-2MM1 & MM2 - Safe Chart-IFR 6 16-Apr-15 22-Apr-15
MM1-1305-PT-30-P-XM-00001-3MM1 & MM2 - Safe Chart-IFD 18 23-Apr-15 16-May-15
MM1-1305-PT-30-P-XM-00001-4MM1 & MM2 - Safe Chart-IFC 21 18-May-15 10-Jun-15
MM1-1305-PT-30-P-XL-00001MM1 & MM2 - ESD Logic Diagram 52 08-Apr-15 10-Jun-15
MM1-1305-PT-30-P-XL-00001-1MM1 & MM2 - ESD Logic Diagram-IDC 7 08-Apr-15* 15-Apr-15
MM1-1305-PT-30-P-XL-00001-2MM1 & MM2 - ESD Logic Diagram-IFR 6 16-Apr-15 22-Apr-15
MM1-1305-PT-30-P-XL-00001-3MM1 & MM2 - ESD Logic Diagram-IFD 18 23-Apr-15 16-May-15
MM1-1305-PT-30-P-XL-00001-4MM1 & MM2 - ESD Logic Diagram-IFC 21 18-May-15 10-Jun-15
MM1-1305-PT-30-P-LA-00002MM1 & MM2 - Alarm / Trip Schedule 52 08-Apr-15 10-Jun-15
MM1-1305-PT-30-P-LA-00002-1MM1 & MM2 - Alarm / Trip Schedule-IDC 7 08-Apr-15* 15-Apr-15
MM1-1305-PT-30-P-LA-00002-2MM1 & MM2 - Alarm / Trip Schedule-IFR 6 16-Apr-15 22-Apr-15
MM1-1305-PT-30-P-LA-00002-3MM1 & MM2 - Alarm / Trip Schedule-IFD 18 23-Apr-15 16-May-15
MM1-1305-PT-30-P-LA-00002-4MM1 & MM2 - Alarm / Trip Schedule-IFC 21 18-May-15 10-Jun-15
MM1-1305-PT-30-X-CA-00001MM1 & MM2 - Calculation Note - Deluge System 53 08-Apr-15 11-Jun-15
MM1-1305-PT-30-X-CA-00001-1MM1 & MM2 - Calculation Note - Deluge System-IDC 1 08-Apr-15* 08-Apr-15
MM1-1305-PT-30-X-CA-00001-2MM1 & MM2 - Calculation Note - Deluge System-IFR 17 09-Apr-15 29-Apr-15
MM1-1305-PT-30-X-CA-00001-3MM1 & MM2 - Calculation Note - Deluge System-IFD 14 02-May-15 18-May-15
MM1-1305-PT-30-X-CA-00001-4MM1 & MM2 - Calculation Note - Deluge System-IFC 21 19-May-15 11-Jun-15
MM1-1305-PT-30-X-CA-00002MM1 & MM2 - Steady State Analysis for Deluge System 51 15-Apr-15 16-Jun-15
MM1-1305-PT-30-X-CA-00002-1MM1 & MM2 - Steady State Analysis for Deluge System-IDC 1 15-Apr-15* 15-Apr-15
MM1-1305-PT-30-X-CA-00002-2MM1 & MM2 - Steady State Analysis for Deluge System-IFR 15 16-Apr-15 06-May-15
MM1-1305-PT-30-X-CA-00002-3MM1 & MM2 - Steady State Analysis for Deluge System-IFD 15 07-May-15 23-May-15
MM1-1305-PT-30-X-CA-00002-4MM1 & MM2 - Steady State Analysis for Deluge System-IFC 20 25-May-15 16-Jun-15
MM1-1305-PT-30-X-XE-10001MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck Equipment Layout Plan59 26-Mar-15 05-Jun-15
MM1-1305-PT-30-X-XE-10001-1MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck Equipment Layout Plan-IDC13 26-Mar-15* 09-Apr-15
MM1-1305-PT-30-X-XE-10001-2MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck Equipment Layout Plan-IFR12 10-Apr-15 23-Apr-15
MM1-1305-PT-30-X-XE-10001-3MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck Equipment Layout Plan-IFD11 24-Apr-15 09-May-15
MM1-1305-PT-30-X-XE-10001-4MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck Equipment Layout Plan-IFC23 11-May-15 05-Jun-15
MM1-1305-PT-30-X-XE-10002MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck Equipment Layout Plan59 26-Mar-15 05-Jun-15
MM1-1305-PT-30-X-XE-10002-1MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck Equipment Layout Plan-IDC13 26-Mar-15* 09-Apr-15
MM1-1305-PT-30-X-XE-10002-2MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck Equipment Layout Plan-IFR12 10-Apr-15 23-Apr-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 5 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-30-X-XE-10002-3MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck Equipment Layout Plan-IFD11 24-Apr-15 09-May-15
MM1-1305-PT-30-X-XE-10002-4MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck Equipment Layout Plan-IFC23 11-May-15 05-Jun-15
MM1-1305-PT-30-X-XB-10001MM1 - P&ID Firewater Deluge System 56 08-Apr-15 15-Jun-15
MM1-1305-PT-30-X-XB-10001-1MM1 - P&ID Firewater Deluge System-IDC 10 08-Apr-15* 18-Apr-15
MM1-1305-PT-30-X-XB-10001-2MM1 - P&ID Firewater Deluge System-IFR 11 20-Apr-15 05-May-15
MM1-1305-PT-30-X-XB-10001-3MM1 - P&ID Firewater Deluge System-IFD 15 06-May-15 22-May-15
MM1-1305-PT-30-X-XB-10001-4MM1 - P&ID Firewater Deluge System-IFC 20 23-May-15 15-Jun-15
0.D.26.0000.MM1.B.N Structural0.D.26.0000.MM1.B.N Structural 315 16-Mar-15 21-Mar-16
0.D.26.0000.MM1.B.N.92 PTSC0.D.26.0000.MM1.B.N.92 PTSC 315 16-Mar-15 21-Mar-16
MM1-1305-PT-95-N-RA-10001MM1 - In-place Analysis Report 82 16-Mar-15 22-Jun-15
MM1-1305-PT-95-N-RA-10001-1MM1 - In-place Analysis Report-IDC 0 16-Mar-15* 16-Mar-15
MM1-1305-PT-95-N-RA-10001-2MM1 - In-place Analysis Report-IFR 55 16-Mar-15 21-May-15
MM1-1305-PT-95-N-RA-10001-3MM1 - In-place Analysis Report-IFD 12 22-May-15 04-Jun-15
MM1-1305-PT-95-N-RA-10001-4MM1 - In-place Analysis Report-IFC 15 05-Jun-15 22-Jun-15
MM1-1305-PT-95-N-RA-10002MM1 - Preservice Analysis Report 85 16-Mar-15 25-Jun-15
MM1-1305-PT-95-N-RA-10002-1MM1 - Preservice Analysis Report-IDC 0 16-Mar-15* 16-Mar-15
MM1-1305-PT-95-N-RA-10002-2MM1 - Preservice Analysis Report-IFR 57 16-Mar-15 23-May-15
MM1-1305-PT-95-N-RA-10002-3MM1 - Preservice Analysis Report-IFD 12 25-May-15 06-Jun-15
MM1-1305-PT-95-N-RA-10002-4MM1 - Preservice Analysis Report-IFC 16 08-Jun-15 25-Jun-15
MM1-1305-PT-95-N-RA-10003MM1 - Structural Miscellaneous design 45 06-Jun-15 28-Jul-15
MM1-1305-PT-95-N-RA-10003-1MM1 - Structural Miscellaneous design-IDC 1 06-Jun-15* 06-Jun-15
MM1-1305-PT-95-N-RA-10003-2MM1 - Structural Miscellaneous design-IFR 17 08-Jun-15 26-Jun-15
MM1-1305-PT-95-N-RA-10003-3MM1 - Structural Miscellaneous design-IFD 12 27-Jun-15 10-Jul-15
MM1-1305-PT-95-N-RA-10003-4MM1 - Structural Miscellaneous design-IFC 15 11-Jul-15 28-Jul-15
MM1-1305-PT-95-N-RA-10005MM1 - Weight Control Report 74 28-Mar-15 25-Jun-15
MM1-1305-PT-95-N-RA-10005-1MM1 - Weight Control Report-IDC 33 28-Mar-15* 08-May-15
MM1-1305-PT-95-N-RA-10005-2MM1 - Weight Control Report-IFR 13 09-May-15 23-May-15
MM1-1305-PT-95-N-RA-10005-3MM1 - Weight Control Report-IFD 12 25-May-15 06-Jun-15
MM1-1305-PT-95-N-RA-10005-4MM1 - Weight Control Report-IFC 16 08-Jun-15 25-Jun-15
MM1-1305-PT-95-N-RA-10006MM1 - Seafastening Report 50 30-Jun-15 26-Aug-15
MM1-1305-PT-95-N-RA-10006-1MM1 - Seafastening Report-IDC 1 30-Jun-15* 30-Jun-15
MM1-1305-PT-95-N-RA-10006-2MM1 - Seafastening Report-IFR 16 01-Jul-15 18-Jul-15
MM1-1305-PT-95-N-RA-10006-3MM1 - Seafastening Report-IFD 12 20-Jul-15 01-Aug-15
MM1-1305-PT-95-N-RA-10006-4MM1 - Seafastening Report-IFC 21 03-Aug-15 26-Aug-15
MM1-1305-PT-95-N-LA-00001MM1 & MM2 - Structural Primary & secondary steel MTOs 61 16-Mar-15 28-May-15
MM1-1305-PT-95-N-LA-00001-1MM1 & MM2 - Structural Primary & secondary steel MTOs-IDC 0 16-Mar-15* 16-Mar-15
MM1-1305-PT-95-N-LA-00001-2MM1 & MM2 - Structural Primary & secondary steel MTOs-IFR 24 16-Mar-15 11-Apr-15
MM1-1305-PT-95-N-LA-00001-3MM1 & MM2 - Structural Primary & secondary steel MTOs-IFD 0 13-Apr-15 13-Apr-15
MM1-1305-PT-95-N-LA-00001-4MM1 & MM2 - Structural Primary & secondary steel MTOs-IFC 37 13-Apr-15 28-May-15
MM1-1305-PT-95-N-LA-00002MM1 & MM2 - Structural Tertiary Steel MTOs 67 04-May-15 20-Jul-15
MM1-1305-PT-95-N-LA-00002-1MM1 & MM2 - Structural Tertiary Steel MTOs-IDC 1 04-May-15* 04-May-15
MM1-1305-PT-95-N-LA-00002-2MM1 & MM2 - Structural Tertiary Steel MTOs-IFR 25 05-May-15 02-Jun-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 6 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-95-N-LA-00002-3MM1 & MM2 - Structural Tertiary Steel MTOs-IFD 0 03-Jun-15 03-Jun-15
MM1-1305-PT-95-N-LA-00002-4MM1 & MM2 - Structural Tertiary Steel MTOs-IFC 41 03-Jun-15 20-Jul-15
MM1-1305-PT-95-N-LA-00003MM1 & MM2 - Structural Miscellaneous MTOs 68 22-Jun-15 09-Sep-15
MM1-1305-PT-95-N-LA-00003-1MM1 & MM2 - Structural Miscellaneous MTOs-IDC 0 22-Jun-15* 22-Jun-15
MM1-1305-PT-95-N-LA-00003-2MM1 & MM2 - Structural Miscellaneous MTOs-IFR 24 22-Jun-15 18-Jul-15
MM1-1305-PT-95-N-LA-00003-3MM1 & MM2 - Structural Miscellaneous MTOs-IFD 0 20-Jul-15 20-Jul-15
MM1-1305-PT-95-N-LA-00003-4MM1 & MM2 - Structural Miscellaneous MTOs-IFC 44 20-Jul-15 09-Sep-15
MM1-1305-PT-95-N-LA-00004MM1 & MM2 - Structural Grating MTOs 71 23-Jun-15 14-Sep-15
MM1-1305-PT-95-N-LA-00004-1MM1 & MM2 - Structural Grating MTOs-IDC 1 23-Jun-15* 23-Jun-15
MM1-1305-PT-95-N-LA-00004-2MM1 & MM2 - Structural Grating MTOs-IFR 25 24-Jun-15 22-Jul-15
MM1-1305-PT-95-N-LA-00004-3MM1 & MM2 - Structural Grating MTOs-IFD 0 23-Jul-15 23-Jul-15
MM1-1305-PT-95-N-LA-00004-4MM1 & MM2 - Structural Grating MTOs-IFC 45 23-Jul-15 14-Sep-15
MM1-1305-PT-95-N-XG-01001MM1 & MM2 - Structural General Notes 47 24-Mar-15 20-May-15
MM1-1305-PT-95-N-XG-01001-1MM1 & MM2 - Structural General Notes-IDC 1 24-Mar-15* 24-Mar-15
MM1-1305-PT-95-N-XG-01001-2MM1 & MM2 - Structural General Notes-IFR 18 25-Mar-15 14-Apr-15
MM1-1305-PT-95-N-XG-01001-3MM1 & MM2 - Structural General Notes-IFD 11 15-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-01001-4MM1 & MM2 - Structural General Notes-IFC 17 29-Apr-15 20-May-15
MM1-1305-PT-95-N-XG-01002MM1 & MM2 - Typical Weld Details 49 24-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01002-1MM1 & MM2 - Typical Weld Details-IDC 1 24-Mar-15* 24-Mar-15
MM1-1305-PT-95-N-XG-01002-2MM1 & MM2 - Typical Weld Details-IFR 20 25-Mar-15 16-Apr-15
MM1-1305-PT-95-N-XG-01002-3MM1 & MM2 - Typical Weld Details-IFD 10 17-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01002-4MM1 & MM2 - Typical Weld Details-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01003MM1 & MM2 - Typical Connection Details 48 02-Apr-15 30-May-15
MM1-1305-PT-95-N-XG-01003-1MM1 & MM2 - Typical Connection Details-IDC 1 02-Apr-15* 02-Apr-15
MM1-1305-PT-95-N-XG-01003-2MM1 & MM2 - Typical Connection Details-IFR 20 03-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-01003-3MM1 & MM2 - Typical Connection Details-IFD 9 27-Apr-15 09-May-15
MM1-1305-PT-95-N-XG-01003-4MM1 & MM2 - Typical Connection Details-IFC 18 11-May-15 30-May-15
MM1-1305-PT-95-N-XG-01004MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01004-1MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01004-2MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01004-3MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01004-4MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01005MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01005-1MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01005-2MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01005-3MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01005-4MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01006MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01006-1MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01006-2MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01006-3MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01006-4MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFC 18 02-May-15 22-May-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 7 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-95-N-XG-01007MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01007-1MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01007-2MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01007-3MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01007-4MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01008MM1 & MM2 - Typical Plating & Grating Arrangement & Details 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01008-1MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01008-2MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01008-3MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01008-4MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01009MM1 & MM2 - Typical Handrail Arrangement & Details 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01009-1MM1 & MM2 - Typical Handrail Arrangement & Details-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01009-2MM1 & MM2 - Typical Handrail Arrangement & Details-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01009-3MM1 & MM2 - Typical Handrail Arrangement & Details-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01009-4MM1 & MM2 - Typical Handrail Arrangement & Details-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-01010MM1 & MM2 - Typical Drain Outlet Details 45 28-Mar-15 22-May-15
MM1-1305-PT-95-N-XG-01010-1MM1 & MM2 - Typical Drain Outlet Details-IDC 1 28-Mar-15* 28-Mar-15
MM1-1305-PT-95-N-XG-01010-2MM1 & MM2 - Typical Drain Outlet Details-IFR 17 30-Mar-15 17-Apr-15
MM1-1305-PT-95-N-XG-01010-3MM1 & MM2 - Typical Drain Outlet Details-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-01010-4MM1 & MM2 - Typical Drain Outlet Details-IFC 18 02-May-15 22-May-15
MM1-1305-PT-95-N-XG-12001MM1 - Drawing Index 64 24-Mar-15 09-Jun-15
MM1-1305-PT-95-N-XG-12001-1MM1 - Drawing Index-IDC 1 24-Mar-15* 24-Mar-15
MM1-1305-PT-95-N-XG-12001-2MM1 - Drawing Index-IFR 27 25-Mar-15 24-Apr-15
MM1-1305-PT-95-N-XG-12001-3MM1 - Drawing Index-IFD 0 25-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12001-4MM1 - Drawing Index-IFC 36 25-Apr-15 09-Jun-15
MM1-1305-PT-95-N-XG-12002MM1 - Structural Perspective View 52 29-Apr-15 30-Jun-15
MM1-1305-PT-95-N-XG-12002-1MM1 - Structural Perspective View-IDC 0 29-Apr-15* 29-Apr-15
MM1-1305-PT-95-N-XG-12002-2MM1 - Structural Perspective View-IFR 24 29-Apr-15 28-May-15
MM1-1305-PT-95-N-XG-12002-3MM1 - Structural Perspective View-IFD 0 29-May-15 29-May-15
MM1-1305-PT-95-N-XG-12002-4MM1 - Structural Perspective View-IFC 28 29-May-15 30-Jun-15
MM1-1305-PT-95-N-XG-12003MM1 - Deck Load Plan 32 29-Apr-15 06-Jun-15
MM1-1305-PT-95-N-XG-12003-1MM1 - Deck Load Plan-IDC 0 29-Apr-15* 29-Apr-15
MM1-1305-PT-95-N-XG-12003-2MM1 - Deck Load Plan-IFR 20 29-Apr-15 23-May-15
MM1-1305-PT-95-N-XG-12003-3MM1 - Deck Load Plan-IFD 0 25-May-15 25-May-15
MM1-1305-PT-95-N-XG-12003-4MM1 - Deck Load Plan-IFC 12 25-May-15 06-Jun-15
MM1-1305-PT-95-N-XG-12004MM1 - Upper Deck Primary Framing Plan 36 02-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12004-1MM1 - Upper Deck Primary Framing Plan-IDC 19 02-Apr-15* 23-Apr-15
MM1-1305-PT-95-N-XG-12004-2MM1 - Upper Deck Primary Framing Plan-IFR 4 24-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-12004-3MM1 - Upper Deck Primary Framing Plan-IFD 0 02-May-15 02-May-15
MM1-1305-PT-95-N-XG-12004-4MM1 - Upper Deck Primary Framing Plan-IFC 13 02-May-15 16-May-15
MM1-1305-PT-95-N-XG-12005MM1 - Mezzanine Deck Primary Framing Plan 36 31-Mar-15 14-May-15
MM1-1305-PT-95-N-XG-12005-1MM1 - Mezzanine Deck Primary Framing Plan-IDC 19 31-Mar-15* 21-Apr-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 8 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-95-N-XG-12005-2MM1 - Mezzanine Deck Primary Framing Plan-IFR 5 22-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-12005-3MM1 - Mezzanine Deck Primary Framing Plan-IFD 0 29-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-12005-4MM1 - Mezzanine Deck Primary Framing Plan-IFC 12 29-Apr-15 14-May-15
MM1-1305-PT-95-N-XG-12006MM1 - Main Deck Primary Framing Plan 36 28-Mar-15 12-May-15
MM1-1305-PT-95-N-XG-12006-1MM1 - Main Deck Primary Framing Plan-IDC 19 28-Mar-15* 18-Apr-15
MM1-1305-PT-95-N-XG-12006-2MM1 - Main Deck Primary Framing Plan-IFR 6 20-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12006-3MM1 - Main Deck Primary Framing Plan-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-12006-4MM1 - Main Deck Primary Framing Plan-IFC 11 27-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12007MM1 - Truss Row 89 & Row 90 36 28-Mar-15 12-May-15
MM1-1305-PT-95-N-XG-12007-1MM1 - Truss Row 89 & Row 90-IDC 18 28-Mar-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12007-2MM1 - Truss Row 89 & Row 90-IFR 6 18-Apr-15 24-Apr-15
MM1-1305-PT-95-N-XG-12007-3MM1 - Truss Row 89 & Row 90-IFD 0 25-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12007-4MM1 - Truss Row 89 & Row 90-IFC 12 25-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12008MM1 - Truss Row 91 & Row 92 36 28-Mar-15 12-May-15
MM1-1305-PT-95-N-XG-12008-1MM1 - Truss Row 91 & Row 92-IDC 19 28-Mar-15* 18-Apr-15
MM1-1305-PT-95-N-XG-12008-2MM1 - Truss Row 91 & Row 92-IFR 6 20-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12008-3MM1 - Truss Row 91 & Row 92-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-12008-4MM1 - Truss Row 91 & Row 92-IFC 11 27-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12009MM1 - Truss Row 93 & Row 94 34 02-Apr-15 14-May-15
MM1-1305-PT-95-N-XG-12009-1MM1 - Truss Row 93 & Row 94-IDC 17 02-Apr-15* 21-Apr-15
MM1-1305-PT-95-N-XG-12009-2MM1 - Truss Row 93 & Row 94-IFR 6 22-Apr-15 29-Apr-15
MM1-1305-PT-95-N-XG-12009-3MM1 - Truss Row 93 & Row 94-IFD 0 02-May-15 02-May-15
MM1-1305-PT-95-N-XG-12009-4MM1 - Truss Row 93 & Row 94-IFC 11 02-May-15 14-May-15
MM1-1305-PT-95-N-XG-12010MM1 - Truss Row 1A 36 28-Mar-15 12-May-15
MM1-1305-PT-95-N-XG-12010-1MM1 - Truss Row 1A-IDC 18 28-Mar-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12010-2MM1 - Truss Row 1A-IFR 6 18-Apr-15 24-Apr-15
MM1-1305-PT-95-N-XG-12010-3MM1 - Truss Row 1A-IFD 0 25-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12010-4MM1 - Truss Row 1A-IFC 12 25-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12011MM1 - Truss Row 1B 36 28-Mar-15 12-May-15
MM1-1305-PT-95-N-XG-12011-1MM1 - Truss Row 1B-IDC 18 28-Mar-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12011-2MM1 - Truss Row 1B-IFR 7 18-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12011-3MM1 - Truss Row 1B-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-12011-4MM1 - Truss Row 1B-IFC 11 27-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12012MM1 - Truss Row 1C 35 31-Mar-15 13-May-15
MM1-1305-PT-95-N-XG-12012-1MM1 - Truss Row 1C-IDC 17 31-Mar-15* 18-Apr-15
MM1-1305-PT-95-N-XG-12012-2MM1 - Truss Row 1C-IFR 6 20-Apr-15 25-Apr-15
MM1-1305-PT-95-N-XG-12012-3MM1 - Truss Row 1C-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-95-N-XG-12012-4MM1 - Truss Row 1C-IFC 12 27-Apr-15 13-May-15
MM1-1305-PT-95-N-XG-12013MM1 - Upper Deck Joint Details Sheet 1 27 17-Apr-15 21-May-15
MM1-1305-PT-95-N-XG-12013-1MM1 - Upper Deck Joint Details Sheet 1-IDC 1 17-Apr-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12013-2MM1 - Upper Deck Joint Details Sheet 1-IFR 20 18-Apr-15 14-May-15
MM1-1305-PT-95-N-XG-12013-3MM1 - Upper Deck Joint Details Sheet 1-IFD 0 15-May-15 15-May-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 9 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-95-N-XG-12013-4MM1 - Upper Deck Joint Details Sheet 1-IFC 6 15-May-15 21-May-15
MM1-1305-PT-95-N-XG-12014MM1 - Upper Deck Joint Details Sheet 2 27 17-Apr-15 21-May-15
MM1-1305-PT-95-N-XG-12014-1MM1 - Upper Deck Joint Details Sheet 2-IDC 1 17-Apr-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12014-2MM1 - Upper Deck Joint Details Sheet 2-IFR 20 18-Apr-15 14-May-15
MM1-1305-PT-95-N-XG-12014-3MM1 - Upper Deck Joint Details Sheet 2-IFD 0 15-May-15 15-May-15
MM1-1305-PT-95-N-XG-12014-4MM1 - Upper Deck Joint Details Sheet 2-IFC 6 15-May-15 21-May-15
MM1-1305-PT-95-N-XG-12015MM1 - Upper Deck Joint Details Sheet 3 31 17-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12015-1MM1 - Upper Deck Joint Details Sheet 3-IDC 1 17-Apr-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12015-2MM1 - Upper Deck Joint Details Sheet 3-IFR 22 18-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12015-3MM1 - Upper Deck Joint Details Sheet 3-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12015-4MM1 - Upper Deck Joint Details Sheet 3-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12016MM1 - Upper Deck Joint Details sheet 4 31 17-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12016-1MM1 - Upper Deck Joint Details sheet 4-IDC 1 17-Apr-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12016-2MM1 - Upper Deck Joint Details sheet 4-IFR 22 18-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12016-3MM1 - Upper Deck Joint Details sheet 4-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12016-4MM1 - Upper Deck Joint Details sheet 4-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12017MM1 - Upper Deck Joint Details sheet 5 31 17-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12017-1MM1 - Upper Deck Joint Details sheet 5-IDC 1 17-Apr-15* 17-Apr-15
MM1-1305-PT-95-N-XG-12017-2MM1 - Upper Deck Joint Details sheet 5-IFR 22 18-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12017-3MM1 - Upper Deck Joint Details sheet 5-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12017-4MM1 - Upper Deck Joint Details sheet 5-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12018MM1 - Mezzanine Deck Joint Details sheet 1 34 14-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12018-1MM1 - Mezzanine Deck Joint Details sheet 1-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12018-2MM1 - Mezzanine Deck Joint Details sheet 1-IFR 22 15-Apr-15 13-May-15
MM1-1305-PT-95-N-XG-12018-3MM1 - Mezzanine Deck Joint Details sheet 1-IFD 0 14-May-15 14-May-15
MM1-1305-PT-95-N-XG-12018-4MM1 - Mezzanine Deck Joint Details sheet 1-IFC 11 14-May-15 26-May-15
MM1-1305-PT-95-N-XG-12019MM1 - Mezzanine Deck Joint Details sheet 2 34 14-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12019-1MM1 - Mezzanine Deck Joint Details sheet 2-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12019-2MM1 - Mezzanine Deck Joint Details sheet 2-IFR 22 15-Apr-15 13-May-15
MM1-1305-PT-95-N-XG-12019-3MM1 - Mezzanine Deck Joint Details sheet 2-IFD 0 14-May-15 14-May-15
MM1-1305-PT-95-N-XG-12019-4MM1 - Mezzanine Deck Joint Details sheet 2-IFC 11 14-May-15 26-May-15
MM1-1305-PT-95-N-XG-12020MM1 - Mezzanine Deck Joint Details sheet 3 33 15-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12020-1MM1 - Mezzanine Deck Joint Details sheet 3-IDC 1 15-Apr-15* 15-Apr-15
MM1-1305-PT-95-N-XG-12020-2MM1 - Mezzanine Deck Joint Details sheet 3-IFR 24 16-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12020-3MM1 - Mezzanine Deck Joint Details sheet 3-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12020-4MM1 - Mezzanine Deck Joint Details sheet 3-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12021MM1 - Mezzanine Deck Joint Details sheet 4 33 15-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12021-1MM1 - Mezzanine Deck Joint Details sheet 4-IDC 1 15-Apr-15* 15-Apr-15
MM1-1305-PT-95-N-XG-12021-2MM1 - Mezzanine Deck Joint Details sheet 4-IFR 24 16-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12021-3MM1 - Mezzanine Deck Joint Details sheet 4-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12021-4MM1 - Mezzanine Deck Joint Details sheet 4-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12022MM1 - Mezzanine Deck Joint Details sheet 5 33 15-Apr-15 26-May-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 10 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-95-N-XG-12022-1MM1 - Mezzanine Deck Joint Details sheet 5-IDC 1 15-Apr-15* 15-Apr-15
MM1-1305-PT-95-N-XG-12022-2MM1 - Mezzanine Deck Joint Details sheet 5-IFR 24 16-Apr-15 16-May-15
MM1-1305-PT-95-N-XG-12022-3MM1 - Mezzanine Deck Joint Details sheet 5-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12022-4MM1 - Mezzanine Deck Joint Details sheet 5-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12023MM1 - Main Deck Joint Details Sheet 1 34 14-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12023-1MM1 - Main Deck Joint Details Sheet 1-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12023-2MM1 - Main Deck Joint Details Sheet 1-IFR 19 15-Apr-15 09-May-15
MM1-1305-PT-95-N-XG-12023-3MM1 - Main Deck Joint Details Sheet 1-IFD 0 11-May-15 11-May-15
MM1-1305-PT-95-N-XG-12023-4MM1 - Main Deck Joint Details Sheet 1-IFC 14 11-May-15 26-May-15
MM1-1305-PT-95-N-XG-12024MM1 - Main Deck Joint Details Sheet 2 34 14-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12024-1MM1 - Main Deck Joint Details Sheet 2-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12024-2MM1 - Main Deck Joint Details Sheet 2-IFR 19 15-Apr-15 09-May-15
MM1-1305-PT-95-N-XG-12024-3MM1 - Main Deck Joint Details Sheet 2-IFD 0 11-May-15 11-May-15
MM1-1305-PT-95-N-XG-12024-4MM1 - Main Deck Joint Details Sheet 2-IFC 14 11-May-15 26-May-15
MM1-1305-PT-95-N-XG-12025MM1 - Main Deck Joint Details Sheet 3 37 14-Apr-15 29-May-15
MM1-1305-PT-95-N-XG-12025-1MM1 - Main Deck Joint Details Sheet 3-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12025-2MM1 - Main Deck Joint Details Sheet 3-IFR 21 15-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12025-3MM1 - Main Deck Joint Details Sheet 3-IFD 0 13-May-15 13-May-15
MM1-1305-PT-95-N-XG-12025-4MM1 - Main Deck Joint Details Sheet 3-IFC 15 13-May-15 29-May-15
MM1-1305-PT-95-N-XG-12026MM1 - Main Deck Joint Details Sheet 4 37 14-Apr-15 29-May-15
MM1-1305-PT-95-N-XG-12026-1MM1 - Main Deck Joint Details Sheet 4-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12026-2MM1 - Main Deck Joint Details Sheet 4-IFR 21 15-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12026-3MM1 - Main Deck Joint Details Sheet 4-IFD 0 13-May-15 13-May-15
MM1-1305-PT-95-N-XG-12026-4MM1 - Main Deck Joint Details Sheet 4-IFC 15 13-May-15 29-May-15
MM1-1305-PT-95-N-XG-12027MM1 - Main Deck Joint Details Sheet 5 37 14-Apr-15 29-May-15
MM1-1305-PT-95-N-XG-12027-1MM1 - Main Deck Joint Details Sheet 5-IDC 1 14-Apr-15* 14-Apr-15
MM1-1305-PT-95-N-XG-12027-2MM1 - Main Deck Joint Details Sheet 5-IFR 21 15-Apr-15 12-May-15
MM1-1305-PT-95-N-XG-12027-3MM1 - Main Deck Joint Details Sheet 5-IFD 0 13-May-15 13-May-15
MM1-1305-PT-95-N-XG-12027-4MM1 - Main Deck Joint Details Sheet 5-IFC 15 13-May-15 29-May-15
MM1-1305-PT-95-N-XG-12028MM1 - Upper Deck Secondary Framing Plan 29 20-Apr-15 26-May-15
MM1-1305-PT-95-N-XG-12028-1MM1 - Upper Deck Secondary Framing Plan-IDC 15 20-Apr-15* 09-May-15
MM1-1305-PT-95-N-XG-12028-2MM1 - Upper Deck Secondary Framing Plan-IFR 6 11-May-15 16-May-15
MM1-1305-PT-95-N-XG-12028-3MM1 - Upper Deck Secondary Framing Plan-IFD 0 18-May-15 18-May-15
MM1-1305-PT-95-N-XG-12028-4MM1 - Upper Deck Secondary Framing Plan-IFC 8 18-May-15 26-May-15
MM1-1305-PT-95-N-XG-12029MM1 - Mezzanine Deck Secondary Framing Plan 28 18-Apr-15 23-May-15
MM1-1305-PT-95-N-XG-12029-1MM1 - Mezzanine Deck Secondary Framing Plan-IDC 15 18-Apr-15* 08-May-15
MM1-1305-PT-95-N-XG-12029-2MM1 - Mezzanine Deck Secondary Framing Plan-IFR 6 09-May-15 15-May-15
MM1-1305-PT-95-N-XG-12029-3MM1 - Mezzanine Deck Secondary Framing Plan-IFD 0 16-May-15 16-May-15
MM1-1305-PT-95-N-XG-12029-4MM1 - Mezzanine Deck Secondary Framing Plan-IFC 7 16-May-15 23-May-15
MM1-1305-PT-95-N-XG-12030MM1 - Main Deck Secondary Framing plan 28 18-Apr-15 23-May-15
MM1-1305-PT-95-N-XG-12030-1MM1 - Main Deck Secondary Framing plan-IDC 15 18-Apr-15* 08-May-15
MM1-1305-PT-95-N-XG-12030-2MM1 - Main Deck Secondary Framing plan-IFR 6 09-May-15 15-May-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 11 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-95-N-XG-12030-3MM1 - Main Deck Secondary Framing plan-IFD 0 16-May-15 16-May-15
MM1-1305-PT-95-N-XG-12030-4MM1 - Main Deck Secondary Framing plan-IFC 7 16-May-15 23-May-15
MM1-1305-PT-95-N-XG-12031MM1 - Upper Deck Flooring & Handrail Layout 52 23-Apr-15 25-Jun-15
MM1-1305-PT-95-N-XG-12031-1MM1 - Upper Deck Flooring & Handrail Layout-IDC 34 23-Apr-15* 04-Jun-15
MM1-1305-PT-95-N-XG-12031-2MM1 - Upper Deck Flooring & Handrail Layout-IFR 6 05-Jun-15 11-Jun-15
MM1-1305-PT-95-N-XG-12031-3MM1 - Upper Deck Flooring & Handrail Layout-IFD 0 12-Jun-15 12-Jun-15
MM1-1305-PT-95-N-XG-12031-4MM1 - Upper Deck Flooring & Handrail Layout-IFC 12 12-Jun-15 25-Jun-15
MM1-1305-PT-95-N-XG-12032MM1 - Mezzanine Deck Flooring & Handrail Layout 53 23-Apr-15 26-Jun-15
MM1-1305-PT-95-N-XG-12032-1MM1 - Mezzanine Deck Flooring & Handrail Layout-IDC 35 23-Apr-15* 05-Jun-15
MM1-1305-PT-95-N-XG-12032-2MM1 - Mezzanine Deck Flooring & Handrail Layout-IFR 6 06-Jun-15 12-Jun-15
MM1-1305-PT-95-N-XG-12032-3MM1 - Mezzanine Deck Flooring & Handrail Layout-IFD 0 13-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12032-4MM1 - Mezzanine Deck Flooring & Handrail Layout-IFC 12 13-Jun-15 26-Jun-15
MM1-1305-PT-95-N-XG-12033MM1 - Main Deck Flooring & Handrail Layout 54 23-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12033-1MM1 - Main Deck Flooring & Handrail Layout-IDC 36 23-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12033-2MM1 - Main Deck Flooring & Handrail Layout-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12033-3MM1 - Main Deck Flooring & Handrail Layout-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12033-4MM1 - Main Deck Flooring & Handrail Layout-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12034MM1 - Upper Deck Penetration Layout 52 23-Apr-15 25-Jun-15
MM1-1305-PT-95-N-XG-12034-1MM1 - Upper Deck Penetration Layout-IDC 34 23-Apr-15* 04-Jun-15
MM1-1305-PT-95-N-XG-12034-2MM1 - Upper Deck Penetration Layout-IFR 6 05-Jun-15 11-Jun-15
MM1-1305-PT-95-N-XG-12034-3MM1 - Upper Deck Penetration Layout-IFD 0 12-Jun-15 12-Jun-15
MM1-1305-PT-95-N-XG-12034-4MM1 - Upper Deck Penetration Layout-IFC 12 12-Jun-15 25-Jun-15
MM1-1305-PT-95-N-XG-12035MM1 - Mezzanine Deck Penetration Layout 52 23-Apr-15 25-Jun-15
MM1-1305-PT-95-N-XG-12035-1MM1 - Mezzanine Deck Penetration Layout-IDC 34 23-Apr-15* 04-Jun-15
MM1-1305-PT-95-N-XG-12035-2MM1 - Mezzanine Deck Penetration Layout-IFR 6 05-Jun-15 11-Jun-15
MM1-1305-PT-95-N-XG-12035-3MM1 - Mezzanine Deck Penetration Layout-IFD 0 12-Jun-15 12-Jun-15
MM1-1305-PT-95-N-XG-12035-4MM1 - Mezzanine Deck Penetration Layout-IFC 12 12-Jun-15 25-Jun-15
MM1-1305-PT-95-N-XG-12036MM1 - Main Deck Penetration Layout 51 27-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12036-1MM1 - Main Deck Penetration Layout-IDC 33 27-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12036-2MM1 - Main Deck Penetration Layout-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12036-3MM1 - Main Deck Penetration Layout-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12036-4MM1 - Main Deck Penetration Layout-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12037MM1 - Lifting Padeye Arrangement & Details Sheet 1 47 29-Apr-15 24-Jun-15
MM1-1305-PT-95-N-XG-12037-1MM1 - Lifting Padeye Arrangement & Details Sheet 1-IDC 0 29-Apr-15* 29-Apr-15
MM1-1305-PT-95-N-XG-12037-2MM1 - Lifting Padeye Arrangement & Details Sheet 1-IFR 31 29-Apr-15 05-Jun-15
MM1-1305-PT-95-N-XG-12037-3MM1 - Lifting Padeye Arrangement & Details Sheet 1-IFD 0 06-Jun-15 06-Jun-15
MM1-1305-PT-95-N-XG-12037-4MM1 - Lifting Padeye Arrangement & Details Sheet 1-IFC 16 06-Jun-15 24-Jun-15
MM1-1305-PT-95-N-XG-12038MM1 - Lifting Padeye Arrangement & Details Sheet 2 47 29-Apr-15 24-Jun-15
MM1-1305-PT-95-N-XG-12038-1MM1 - Lifting Padeye Arrangement & Details Sheet 2-IDC 0 29-Apr-15* 29-Apr-15
MM1-1305-PT-95-N-XG-12038-2MM1 - Lifting Padeye Arrangement & Details Sheet 2-IFR 31 29-Apr-15 05-Jun-15
MM1-1305-PT-95-N-XG-12038-3MM1 - Lifting Padeye Arrangement & Details Sheet 2-IFD 0 06-Jun-15 06-Jun-15
MM1-1305-PT-95-N-XG-12038-4MM1 - Lifting Padeye Arrangement & Details Sheet 2-IFC 16 06-Jun-15 24-Jun-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 12 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-95-N-XG-12039MM1 - Stair Arrangement & Details Sheet 1 50 29-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12039-1MM1 - Stair Arrangement & Details Sheet 1-IDC 32 29-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12039-2MM1 - Stair Arrangement & Details Sheet 1-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12039-3MM1 - Stair Arrangement & Details Sheet 1-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12039-4MM1 - Stair Arrangement & Details Sheet 1-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12040MM1 - Stair Arrangement & Details Sheet 2 50 29-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12040-1MM1 - Stair Arrangement & Details Sheet 2-IDC 32 29-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12040-2MM1 - Stair Arrangement & Details Sheet 2-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12040-3MM1 - Stair Arrangement & Details Sheet 2-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12040-4MM1 - Stair Arrangement & Details Sheet 2-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12041MM1 - Ladder Arrangement & Details Sheet 1 50 29-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12041-1MM1 - Ladder Arrangement & Details Sheet 1-IDC 32 29-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12041-2MM1 - Ladder Arrangement & Details Sheet 1-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12041-3MM1 - Ladder Arrangement & Details Sheet 1-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12041-4MM1 - Ladder Arrangement & Details Sheet 1-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12042MM1 - Ladder Arrangement & Details Sheet 2 50 29-Apr-15 27-Jun-15
MM1-1305-PT-95-N-XG-12042-1MM1 - Ladder Arrangement & Details Sheet 2-IDC 32 29-Apr-15* 06-Jun-15
MM1-1305-PT-95-N-XG-12042-2MM1 - Ladder Arrangement & Details Sheet 2-IFR 6 08-Jun-15 13-Jun-15
MM1-1305-PT-95-N-XG-12042-3MM1 - Ladder Arrangement & Details Sheet 2-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-95-N-XG-12042-4MM1 - Ladder Arrangement & Details Sheet 2-IFC 12 15-Jun-15 27-Jun-15
MM1-1305-PT-95-N-XG-12043MM1 - Mechanical Handling For Main Deck Equipment - sheet 1 29 01-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12043-1MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IDC 11 01-Jun-15* 12-Jun-15
MM1-1305-PT-95-N-XG-12043-2MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IFR 6 13-Jun-15 19-Jun-15
MM1-1305-PT-95-N-XG-12043-3MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IFD 0 20-Jun-15 20-Jun-15
MM1-1305-PT-95-N-XG-12043-4MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IFC 12 20-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12044MM1 - Mechanical Handling For Main Deck Equipment - sheet 2 29 01-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12044-1MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IDC 11 01-Jun-15* 12-Jun-15
MM1-1305-PT-95-N-XG-12044-2MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IFR 6 13-Jun-15 19-Jun-15
MM1-1305-PT-95-N-XG-12044-3MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IFD 0 20-Jun-15 20-Jun-15
MM1-1305-PT-95-N-XG-12044-4MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IFC 12 20-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12045MM1 - Mechanical Handling For Main Deck Equipment - sheet 3 29 01-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12045-1MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IDC 11 01-Jun-15* 12-Jun-15
MM1-1305-PT-95-N-XG-12045-2MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IFR 6 13-Jun-15 19-Jun-15
MM1-1305-PT-95-N-XG-12045-3MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IFD 0 20-Jun-15 20-Jun-15
MM1-1305-PT-95-N-XG-12045-4MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IFC 12 20-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12046MM1 - Mechanical Handling For Main Deck Equipment - sheet 4 29 01-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12046-1MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IDC 11 01-Jun-15* 12-Jun-15
MM1-1305-PT-95-N-XG-12046-2MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IFR 6 13-Jun-15 19-Jun-15
MM1-1305-PT-95-N-XG-12046-3MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IFD 0 20-Jun-15 20-Jun-15
MM1-1305-PT-95-N-XG-12046-4MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IFC 12 20-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12047MM1 - Mechanical Handling For Main Deck Equipment - sheet 5 29 01-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12047-1MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IDC 11 01-Jun-15* 12-Jun-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 13 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-95-N-XG-12047-2MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IFR 6 13-Jun-15 19-Jun-15
MM1-1305-PT-95-N-XG-12047-3MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IFD 0 20-Jun-15 20-Jun-15
MM1-1305-PT-95-N-XG-12047-4MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IFC 12 20-Jun-15 03-Jul-15
MM1-1305-PT-95-N-XG-12048MM1 - Equipment Support- Sheet 1 29 16-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12048-1MM1 - Equipment Support- Sheet 1-IDC 11 16-Jun-15* 27-Jun-15
MM1-1305-PT-95-N-XG-12048-2MM1 - Equipment Support- Sheet 1-IFR 6 29-Jun-15 04-Jul-15
MM1-1305-PT-95-N-XG-12048-3MM1 - Equipment Support- Sheet 1-IFD 0 06-Jul-15 06-Jul-15
MM1-1305-PT-95-N-XG-12048-4MM1 - Equipment Support- Sheet 1-IFC 12 06-Jul-15 18-Jul-15
MM1-1305-PT-95-N-XG-12049MM1 - Equipment Support- Sheet 2 29 16-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12049-1MM1 - Equipment Support- Sheet 2-IDC 11 16-Jun-15* 27-Jun-15
MM1-1305-PT-95-N-XG-12049-2MM1 - Equipment Support- Sheet 2-IFR 6 29-Jun-15 04-Jul-15
MM1-1305-PT-95-N-XG-12049-3MM1 - Equipment Support- Sheet 2-IFD 0 06-Jul-15 06-Jul-15
MM1-1305-PT-95-N-XG-12049-4MM1 - Equipment Support- Sheet 2-IFC 12 06-Jul-15 18-Jul-15
MM1-1305-PT-95-N-XG-12050MM1 - Equipment Support- Sheet 3 29 16-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12050-1MM1 - Equipment Support- Sheet 3-IDC 11 16-Jun-15* 27-Jun-15
MM1-1305-PT-95-N-XG-12050-2MM1 - Equipment Support- Sheet 3-IFR 6 29-Jun-15 04-Jul-15
MM1-1305-PT-95-N-XG-12050-3MM1 - Equipment Support- Sheet 3-IFD 0 06-Jul-15 06-Jul-15
MM1-1305-PT-95-N-XG-12050-4MM1 - Equipment Support- Sheet 3-IFC 12 06-Jul-15 18-Jul-15
MM1-1305-PT-95-N-XG-12051MM1 - Seafastening On Barge Arrangment & Details - Sheet 1 30 29-Jun-15 01-Aug-15
MM1-1305-PT-95-N-XG-12051-1MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IDC 0 29-Jun-15* 29-Jun-15
MM1-1305-PT-95-N-XG-12051-2MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IFR 18 29-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12051-3MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IFD 0 20-Jul-15 20-Jul-15
MM1-1305-PT-95-N-XG-12051-4MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IFC 12 20-Jul-15 01-Aug-15
MM1-1305-PT-95-N-XG-12052MM1 - Seafastening On Barge Arrangment & Details - Sheet 2 30 29-Jun-15 01-Aug-15
MM1-1305-PT-95-N-XG-12052-1MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IDC 0 29-Jun-15* 29-Jun-15
MM1-1305-PT-95-N-XG-12052-2MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IFR 18 29-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12052-3MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IFD 0 20-Jul-15 20-Jul-15
MM1-1305-PT-95-N-XG-12052-4MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IFC 12 20-Jul-15 01-Aug-15
MM1-1305-PT-95-N-XG-12053MM1 - Seafastening On Barge Arrangment & Details - Sheet 3 30 29-Jun-15 01-Aug-15
MM1-1305-PT-95-N-XG-12053-1MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IDC 0 29-Jun-15* 29-Jun-15
MM1-1305-PT-95-N-XG-12053-2MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IFR 18 29-Jun-15 18-Jul-15
MM1-1305-PT-95-N-XG-12053-3MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IFD 0 20-Jul-15 20-Jul-15
MM1-1305-PT-95-N-XG-12053-4MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IFC 12 20-Jul-15 01-Aug-15
MM1-10150 TR/MTO for Primary & Secondary Steel 1 07-Apr-15 07-Apr-15
MM1-10170 TR/MTO for Tertiary Steel 1 09-Jun-15 09-Jun-15
MM1-10190 TR/MTO for Structural Miscellaneous 1 28-Jul-15 28-Jul-15
MM1-10210 TR/MTO for Gratings (including Hilti clip and cartridge) 1 09-Aug-15 09-Aug-15
MM1-1000 TR/MTO for SF and Grillage Material 1 10-Oct-15 10-Oct-15
MM1-1100 Prepare / Submit/ Approve Structural Shop Drawings 185 11-Aug-15 21-Mar-16
0.D.26.0000.MM1.B.L Piping0.D.26.0000.MM1.B.L Piping 312 14-Mar-15 16-Mar-16
0.D.26.0000.MM1.B.L.92 PTSC0.D.26.0000.MM1.B.L.92 PTSC 312 14-Mar-15 16-Mar-16
MM1-1305-PT-00-L-CA-00001MM1 & MM2 - Stress Analysis Report 50 01-Jun-15 28-Jul-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 14 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-00-L-CA-00001-1MM1 & MM2 - Stress Analysis Report-IDC 20 01-Jun-15* 23-Jun-15
MM1-1305-PT-00-L-CA-00001-2MM1 & MM2 - Stress Analysis Report-IFR 6 24-Jun-15 30-Jun-15
MM1-1305-PT-00-L-CA-00001-3MM1 & MM2 - Stress Analysis Report-IFD 12 01-Jul-15 14-Jul-15
MM1-1305-PT-00-L-CA-00001-4MM1 & MM2 - Stress Analysis Report-IFC 12 15-Jul-15 28-Jul-15
MM1-1305-PT-00-L-LA-00001MM1 & MM2 - Special Piping Item List 47 12-May-15 04-Jul-15
MM1-1305-PT-00-L-LA-00001-1MM1 & MM2 - Special Piping Item List-IDC 7 12-May-15* 19-May-15
MM1-1305-PT-00-L-LA-00001-2MM1 & MM2 - Special Piping Item List-IFR 4 20-May-15 23-May-15
MM1-1305-PT-00-L-LA-00001-3MM1 & MM2 - Special Piping Item List-IFD 12 25-May-15 06-Jun-15
MM1-1305-PT-00-L-LA-00001-4MM1 & MM2 - Special Piping Item List-IFC 24 08-Jun-15 04-Jul-15
MM1-1305-PT-00-L-LA-00002MM1 & MM2 - TIE-IN Schedule 56 26-May-15 29-Jul-15
MM1-1305-PT-00-L-LA-00002-1MM1 & MM2 - TIE-IN Schedule-IDC 25 26-May-15* 23-Jun-15
MM1-1305-PT-00-L-LA-00002-2MM1 & MM2 - TIE-IN Schedule-IFR 7 24-Jun-15 01-Jul-15
MM1-1305-PT-00-L-LA-00002-3MM1 & MM2 - TIE-IN Schedule-IFD 12 02-Jul-15 15-Jul-15
MM1-1305-PT-00-L-LA-00002-4MM1 & MM2 - TIE-IN Schedule-IFC 12 16-Jul-15 29-Jul-15
MM1-1305-PT-00-L-LA-00003MM1 & MM2 - Manual valve list 49 17-Apr-15 16-Jun-15
MM1-1305-PT-00-L-LA-00003-1MM1 & MM2 - Manual valve list-IDC 7 17-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-LA-00003-2MM1 & MM2 - Manual valve list-IFR 2 25-Apr-15 27-Apr-15
MM1-1305-PT-00-L-LA-00003-3MM1 & MM2 - Manual valve list-IFD 10 29-Apr-15 12-May-15
MM1-1305-PT-00-L-LA-00003-4MM1 & MM2 - Manual valve list-IFC 30 13-May-15 16-Jun-15
MM1-1305-PT-00-L-SA-00001MM1 & MM2 - Addional piping class 46 14-Mar-15 09-May-15
MM1-1305-PT-00-L-SA-00001-1MM1 & MM2 - Addional piping class -IDC 1 14-Mar-15* 14-Mar-15
MM1-1305-PT-00-L-SA-00001-2MM1 & MM2 - Addional piping class -IFR 24 16-Mar-15 11-Apr-15
MM1-1305-PT-00-L-SA-00001-3MM1 & MM2 - Addional piping class -IFD 12 13-Apr-15 25-Apr-15
MM1-1305-PT-00-L-SA-00001-4MM1 & MM2 - Addional piping class -IFC 9 27-Apr-15 09-May-15
MM1-1305-PT-00-L-SA-00002MM1 & MM2 - Pipe support standard 46 06-Apr-15 01-Jun-15
MM1-1305-PT-00-L-SA-00002-1MM1 & MM2 - Pipe support standard -IDC 1 06-Apr-15* 06-Apr-15
MM1-1305-PT-00-L-SA-00002-2MM1 & MM2 - Pipe support standard -IFR 21 07-Apr-15 04-May-15
MM1-1305-PT-00-L-SA-00002-3MM1 & MM2 - Pipe support standard -IFD 12 05-May-15 18-May-15
MM1-1305-PT-00-L-SA-00002-4MM1 & MM2 - Pipe support standard -IFC 12 19-May-15 01-Jun-15
MM1-1305-PT-00-L-DS-00001MM1 & MM2 - Ball valve Data sheets 34 03-Apr-15 15-May-15
MM1-1305-PT-00-L-DS-00001-1MM1 & MM2 - Ball valve Data sheets-IDC 1 03-Apr-15* 03-Apr-15
MM1-1305-PT-00-L-DS-00001-2MM1 & MM2 - Ball valve Data sheets-IFR 12 04-Apr-15 17-Apr-15
MM1-1305-PT-00-L-DS-00001-3MM1 & MM2 - Ball valve Data sheets-IFD 9 18-Apr-15 29-Apr-15
MM1-1305-PT-00-L-DS-00001-4MM1 & MM2 - Ball valve Data sheets-IFC 12 02-May-15 15-May-15
MM1-1305-PT-00-L-DS-00002MM1 & MM2 - Globe Valve Data sheets 33 06-Apr-15 16-May-15
MM1-1305-PT-00-L-DS-00002-1MM1 & MM2 - Globe Valve Data sheets-IDC 0 06-Apr-15* 06-Apr-15
MM1-1305-PT-00-L-DS-00002-2MM1 & MM2 - Globe Valve Data sheets-IFR 12 06-Apr-15 18-Apr-15
MM1-1305-PT-00-L-DS-00002-3MM1 & MM2 - Globe Valve Data sheets-IFD 9 20-Apr-15 02-May-15
MM1-1305-PT-00-L-DS-00002-4MM1 & MM2 - Globe Valve Data sheets-IFC 12 04-May-15 16-May-15
MM1-1305-PT-00-L-DS-00003MM1 & MM2 - Check Data sheets 34 07-Apr-15 19-May-15
MM1-1305-PT-00-L-DS-00003-1MM1 & MM2 - Check Data sheets-IDC 1 07-Apr-15* 07-Apr-15
MM1-1305-PT-00-L-DS-00003-2MM1 & MM2 - Check Data sheets-IFR 12 08-Apr-15 21-Apr-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 15 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-00-L-DS-00003-3MM1 & MM2 - Check Data sheets-IFD 9 22-Apr-15 05-May-15
MM1-1305-PT-00-L-DS-00003-4MM1 & MM2 - Check Data sheets-IFC 12 06-May-15 19-May-15
MM1-1305-PT-00-L-DS-00004MM1 & MM2 - DBB valve sheets 58 10-Apr-15 19-Jun-15
MM1-1305-PT-00-L-DS-00004-1MM1 & MM2 - DBB valve sheets-IDC 1 10-Apr-15* 10-Apr-15
MM1-1305-PT-00-L-DS-00004-2MM1 & MM2 - DBB valve sheets-IFR 12 11-Apr-15 24-Apr-15
MM1-1305-PT-00-L-DS-00004-3MM1 & MM2 - DBB valve sheets-IFD 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00004-4MM1 & MM2 - DBB valve sheets-IFC 36 09-May-15 19-Jun-15
MM1-1305-PT-00-L-DS-00005MM1 & MM2 - SP Item Data Sheet -Valve Interlock 61 12-May-15 21-Jul-15
MM1-1305-PT-00-L-DS-00005-1MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IDC 1 12-May-15* 12-May-15
MM1-1305-PT-00-L-DS-00005-2MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFR 12 13-May-15 26-May-15
MM1-1305-PT-00-L-DS-00005-3MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFD 12 27-May-15 09-Jun-15
MM1-1305-PT-00-L-DS-00005-4MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFC 36 10-Jun-15 21-Jul-15
MM1-1305-PT-00-L-DS-00006MM1 & MM2 - SP Item Data Sheet - Barred Tee 52 10-Apr-15 12-Jun-15
MM1-1305-PT-00-L-DS-00006-1MM1 & MM2 - SP Item Data Sheet - Barred Tee-IDC 1 10-Apr-15* 10-Apr-15
MM1-1305-PT-00-L-DS-00006-2MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFR 12 11-Apr-15 24-Apr-15
MM1-1305-PT-00-L-DS-00006-3MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFD 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00006-4MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFC 30 09-May-15 12-Jun-15
MM1-1305-PT-00-L-DS-00007MM1 & MM2 - SP Item Data Sheet - Bends 70 24-Apr-15 17-Jul-15
MM1-1305-PT-00-L-DS-00007-1MM1 & MM2 - SP Item Data Sheet - Bends-IDC 1 24-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-DS-00007-2MM1 & MM2 - SP Item Data Sheet - Bends-IFR 15 25-Apr-15 15-May-15
MM1-1305-PT-00-L-DS-00007-3MM1 & MM2 - SP Item Data Sheet - Bends-IFD 12 16-May-15 29-May-15
MM1-1305-PT-00-L-DS-00007-4MM1 & MM2 - SP Item Data Sheet - Bends-IFC 42 30-May-15 17-Jul-15
MM1-1305-PT-00-L-DS-00008MM1 & MM2 - SP Item Data Sheets for Sample connection 58 24-Apr-15 03-Jul-15
MM1-1305-PT-00-L-DS-00008-1MM1 & MM2 - SP Item Data Sheets for Sample connection -IDC 1 24-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-DS-00008-2MM1 & MM2 - SP Item Data Sheets for Sample connection -IFR 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00008-3MM1 & MM2 - SP Item Data Sheets for Sample connection -IFD 12 09-May-15 22-May-15
MM1-1305-PT-00-L-DS-00008-4MM1 & MM2 - SP Item Data Sheets for Sample connection -IFC 36 23-May-15 03-Jul-15
MM1-1305-PT-00-L-DS-00009MM1 & MM2 - SP Item Data Sheet - Chemcial injection 58 24-Apr-15 03-Jul-15
MM1-1305-PT-00-L-DS-00009-1MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IDC 1 24-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-DS-00009-2MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFR 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00009-3MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFD 12 09-May-15 22-May-15
MM1-1305-PT-00-L-DS-00009-4MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFC 36 23-May-15 03-Jul-15
MM1-1305-PT-00-L-DS-00010MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon 58 24-Apr-15 03-Jul-15
MM1-1305-PT-00-L-DS-00010-1MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IDC 1 24-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-DS-00010-2MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFR 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00010-3MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFD 12 09-May-15 22-May-15
MM1-1305-PT-00-L-DS-00010-4MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFC 36 23-May-15 03-Jul-15
MM1-1305-PT-00-L-DS-00011MM1 & MM2 - SP Item Data Sheet - Sand probe 58 24-Apr-15 03-Jul-15
MM1-1305-PT-00-L-DS-00011-1MM1 & MM2 - SP Item Data Sheet - Sand probe-IDC 1 24-Apr-15* 24-Apr-15
MM1-1305-PT-00-L-DS-00011-2MM1 & MM2 - SP Item Data Sheet - Sand probe-IFR 9 25-Apr-15 08-May-15
MM1-1305-PT-00-L-DS-00011-3MM1 & MM2 - SP Item Data Sheet - Sand probe-IFD 12 09-May-15 22-May-15
MM1-1305-PT-00-L-DS-00011-4MM1 & MM2 - SP Item Data Sheet - Sand probe-IFC 36 23-May-15 03-Jul-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 16 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-00-L-DS-00012MM1 & MM2 - SP Item Data Sheet - Quick coupling 70 05-Jun-15 25-Aug-15
MM1-1305-PT-00-L-DS-00012-1MM1 & MM2 - SP Item Data Sheet - Quick coupling-IDC 1 05-Jun-15* 05-Jun-15
MM1-1305-PT-00-L-DS-00012-2MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFR 12 06-Jun-15 19-Jun-15
MM1-1305-PT-00-L-DS-00012-3MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFD 12 20-Jun-15 03-Jul-15
MM1-1305-PT-00-L-DS-00012-4MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFC 45 04-Jul-15 25-Aug-15
MM1-1305-PT-00-L-DS-00013MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR 70 05-Jun-15 25-Aug-15
MM1-1305-PT-00-L-DS-00013-1MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IDC 1 05-Jun-15* 05-Jun-15
MM1-1305-PT-00-L-DS-00013-2MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFR 12 06-Jun-15 19-Jun-15
MM1-1305-PT-00-L-DS-00013-3MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFD 12 20-Jun-15 03-Jul-15
MM1-1305-PT-00-L-DS-00013-4MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFC 45 04-Jul-15 25-Aug-15
MM1-1305-PT-00-L-XE-10001MM1 - Equipment Layout 40 24-Apr-15 12-Jun-15
MM1-1305-PT-00-L-XE-10001-1MM1 - Equipment Layout-IDC 10 24-Apr-15* 08-May-15
MM1-1305-PT-00-L-XE-10001-2MM1 - Equipment Layout-IFR 6 09-May-15 15-May-15
MM1-1305-PT-00-L-XE-10001-3MM1 - Equipment Layout-IFD 12 16-May-15 29-May-15
MM1-1305-PT-00-L-XE-10001-4MM1 - Equipment Layout-IFC 12 30-May-15 12-Jun-15
MM1-1305-PT-00-L-XE-10002MM1 - Piping layout 43 30-May-15 18-Jul-15
MM1-1305-PT-00-L-XE-10002-1MM1 - Piping layout-IDC 13 30-May-15* 13-Jun-15
MM1-1305-PT-00-L-XE-10002-2MM1 - Piping layout-IFR 6 15-Jun-15 20-Jun-15
MM1-1305-PT-00-L-XE-10002-3MM1 - Piping layout-IFD 12 22-Jun-15 04-Jul-15
MM1-1305-PT-00-L-XE-10002-4MM1 - Piping layout-IFC 12 06-Jul-15 18-Jul-15
MM1-1305-PT-00-L-XF-10003MM1 - Pipe support location plan 43 20-Jun-15 08-Aug-15
MM1-1305-PT-00-L-XF-10003-1MM1 - Pipe support location plan-IDC 13 20-Jun-15* 04-Jul-15
MM1-1305-PT-00-L-XF-10003-2MM1 - Pipe support location plan-IFR 6 06-Jul-15 11-Jul-15
MM1-1305-PT-00-L-XF-10003-3MM1 - Pipe support location plan-IFD 0 13-Jul-15 13-Jul-15
MM1-1305-PT-00-L-XF-10003-4MM1 - Pipe support location plan-IFC 24 13-Jul-15 08-Aug-15
MM1-1305-PT-00-L-XN-10001MM1 - Isometric drawings (n Sheets) 59 16-May-15 23-Jul-15
MM1-1305-PT-00-L-XN-10001-1MM1 - Isometric drawings (n Sheets)-IDC 13 16-May-15* 30-May-15
MM1-1305-PT-00-L-XN-10001-2MM1 - Isometric drawings (n Sheets)-IFR 12 01-Jun-15 13-Jun-15
MM1-1305-PT-00-L-XN-10001-3MM1 - Isometric drawings (n Sheets)-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-00-L-XN-10001-4MM1 - Isometric drawings (n Sheets)-IFC 34 15-Jun-15 23-Jul-15
MM1-1305-PT-00-L-XO-10001MM1 - Pipe support detail drawings 59 16-May-15 23-Jul-15
MM1-1305-PT-00-L-XO-10001-1MM1 - Pipe support detail drawings-IDC 13 16-May-15* 30-May-15
MM1-1305-PT-00-L-XO-10001-2MM1 - Pipe support detail drawings-IFR 12 01-Jun-15 13-Jun-15
MM1-1305-PT-00-L-XO-10001-3MM1 - Pipe support detail drawings-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-00-L-XO-10001-4MM1 - Pipe support detail drawings-IFC 34 15-Jun-15 23-Jul-15
MM1-1305-PT-00-L-LA-00004MM1 & MM2 - Material take-off for Manual Valves 45 23-Apr-15 17-Jun-15
MM1-1305-PT-00-L-LA-00004-1MM1 & MM2 - Material take-off for Manual Valves-IDC 1 23-Apr-15* 23-Apr-15
MM1-1305-PT-00-L-LA-00004-2MM1 & MM2 - Material take-off for Manual Valves-IFR 4 24-Apr-15 29-Apr-15
MM1-1305-PT-00-L-LA-00004-3MM1 & MM2 - Material take-off for Manual Valves-IFD 0 02-May-15 02-May-15
MM1-1305-PT-00-L-LA-00004-4MM1 & MM2 - Material take-off for Manual Valves-IFC 40 02-May-15 17-Jun-15
MM1-1305-PT-00-L-LA-00005MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket 54 26-Jun-15 27-Aug-15
MM1-1305-PT-00-L-LA-00005-1MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IDC 1 26-Jun-15* 26-Jun-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 17 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-00-L-LA-00005-2MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFR 5 27-Jun-15 02-Jul-15
MM1-1305-PT-00-L-LA-00005-3MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFD 0 03-Jul-15 03-Jul-15
MM1-1305-PT-00-L-LA-00005-4MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFC 48 03-Jul-15 27-Aug-15
MM1-1305-PT-00-L-LA-00006MM1 & MM2 - Material take-off for Pipe Support (Raw Material) 53 30-May-15 30-Jul-15
MM1-1305-PT-00-L-LA-00006-1MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IDC 1 30-May-15* 30-May-15
MM1-1305-PT-00-L-LA-00006-2MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFR 6 01-Jun-15 06-Jun-15
MM1-1305-PT-00-L-LA-00006-3MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFD 0 08-Jun-15 08-Jun-15
MM1-1305-PT-00-L-LA-00006-4MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFC 46 08-Jun-15 30-Jul-15
MM1-1305-PT-00-L-LA-00007MM1 & MM2 - Material take-off - Hub Connector 70 11-Jun-15 31-Aug-15
MM1-1305-PT-00-L-LA-00007-1MM1 & MM2 - Material take-off - Hub Connector-IDC 1 11-Jun-15* 11-Jun-15
MM1-1305-PT-00-L-LA-00007-2MM1 & MM2 - Material take-off - Hub Connector-IFR 12 12-Jun-15 25-Jun-15
MM1-1305-PT-00-L-LA-00007-3MM1 & MM2 - Material take-off - Hub Connector-IFD 0 26-Jun-15 26-Jun-15
MM1-1305-PT-00-L-LA-00007-4MM1 & MM2 - Material take-off - Hub Connector-IFC 57 26-Jun-15 31-Aug-15
MM1-10250 TR/MTO for Piping Bulk 1 10-Apr-15 10-Apr-15
MM1-10270 TR/MTO for Manual valves 1 29-Apr-15 29-Apr-15
MM1-10290 TR/MTO for Barred Tee 1 29-Apr-15 29-Apr-15
MM1-10310 TR/MTO for Cuni fittings 1 08-May-15 08-May-15
MM1-10330 TR/MTO for Corrosion, sand probe, sample connection, chemical connection 1 18-May-15 18-May-15
MM1-10350 TR/MTO for 3D Bend (free bare pipe to bending contractor) 1 30-May-15 30-May-15
MM1-10370 TR/MTO for Pipe Supports 1 06-Jun-15 06-Jun-15
MM1-10410 TR/MTO for Piping insulation 1 04-Jul-15 04-Jul-15
MM1-10430 TR/MTO for Bolt nut, gasket and other 1 06-Jul-15 06-Jul-15
MM1-10390 TR/MTO for Quick Coupling 1 09-Jul-15 09-Jul-15
MM1-10450 TR/MTO for Valve Inter-locks 1 16-Sep-15 16-Sep-15
MM1-10470 Prepare / Submit/ Approve Piping Shop Drawings 151 16-Sep-15 16-Mar-16
0.D.26.0000.MM1.B.1 E&I0.D.26.0000.MM1.B.1 E&I 313 13-Mar-15 16-Mar-16
0.D.26.0000.MM1.B.1.92 PTSC0.D.26.0000.MM1.B.1.92 PTSC 313 13-Mar-15 16-Mar-16
MM1-1305-PT-82-E-CA-00001MM1 & MM2 - Electrical Load List 57 04-May-15 08-Jul-15
MM1-1305-PT-82-E-CA-00001-1MM1 & MM2 - Electrical Load List-IDC 10 04-May-15* 14-May-15
MM1-1305-PT-82-E-CA-00001-2MM1 & MM2 - Electrical Load List-IFR 13 15-May-15 29-May-15
MM1-1305-PT-82-E-CA-00001-3MM1 & MM2 - Electrical Load List-IFD 13 30-May-15 13-Jun-15
MM1-1305-PT-82-E-CA-00001-4MM1 & MM2 - Electrical Load List-IFC 21 15-Jun-15 08-Jul-15
MM1-1305-PT-82-E-CA-00002MM1 & MM2 - Electrical Lighting Calculation 32 20-Mar-15 25-Apr-15
MM1-1305-PT-82-E-CA-00002-1MM1 & MM2 - Electrical Lighting Calculation-IDC 9 20-Mar-15* 30-Mar-15
MM1-1305-PT-82-E-CA-00002-2MM1 & MM2 - Electrical Lighting Calculation-IFR 6 31-Mar-15 06-Apr-15
MM1-1305-PT-82-E-CA-00002-3MM1 & MM2 - Electrical Lighting Calculation-IFD 13 07-Apr-15 21-Apr-15
MM1-1305-PT-82-E-CA-00002-4MM1 & MM2 - Electrical Lighting Calculation-IFC 4 22-Apr-15 25-Apr-15
MM1-1305-PT-82-E-XX-00001MM1 & MM2 - Electrical General Drawing and Document Index 36 23-Mar-15 06-May-15
MM1-1305-PT-82-E-XX-00001-1MM1 & MM2 - Electrical General Drawing and Document Index-IDC 9 23-Mar-15* 01-Apr-15
MM1-1305-PT-82-E-XX-00001-2MM1 & MM2 - Electrical General Drawing and Document Index-IFR 13 02-Apr-15 16-Apr-15
MM1-1305-PT-82-E-XX-00001-3MM1 & MM2 - Electrical General Drawing and Document Index-IFD 0 17-Apr-15 17-Apr-15
MM1-1305-PT-82-E-XX-00001-4MM1 & MM2 - Electrical General Drawing and Document Index-IFC 14 17-Apr-15 06-May-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 18 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-82-E-XX-00002MM1 & MM2 - Electrical Typical Installation Details 48 13-Mar-15 11-May-15
MM1-1305-PT-82-E-XX-00002-1MM1 & MM2 - Electrical Typical Installation Details-IDC 9 13-Mar-15* 23-Mar-15
MM1-1305-PT-82-E-XX-00002-2MM1 & MM2 - Electrical Typical Installation Details-IFR 13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XX-00002-3MM1 & MM2 - Electrical Typical Installation Details-IFD 13 08-Apr-15 22-Apr-15
MM1-1305-PT-82-E-XX-00002-4MM1 & MM2 - Electrical Typical Installation Details-IFC 13 23-Apr-15 11-May-15
MM1-1305-PT-82-E-DS-00001MM1 & MM2 - Electrical Datasheet 30 02-Apr-15 09-May-15
MM1-1305-PT-82-E-DS-00001-1MM1 & MM2 - Electrical Datasheet-IDC 9 02-Apr-15* 11-Apr-15
MM1-1305-PT-82-E-DS-00001-2MM1 & MM2 - Electrical Datasheet-IFR 6 13-Apr-15 18-Apr-15
MM1-1305-PT-82-E-DS-00001-3MM1 & MM2 - Electrical Datasheet-IFD 10 20-Apr-15 04-May-15
MM1-1305-PT-82-E-DS-00001-4MM1 & MM2 - Electrical Datasheet-IFC 5 05-May-15 09-May-15
MM1-1305-PT-82-E-XX-10001MM1 - Electrical Drawing Index 37 23-Mar-15 07-May-15
MM1-1305-PT-82-E-XX-10001-1MM1 - Electrical Drawing Index -IDC 10 23-Mar-15* 02-Apr-15
MM1-1305-PT-82-E-XX-10001-2MM1 - Electrical Drawing Index -IFR 13 03-Apr-15 17-Apr-15
MM1-1305-PT-82-E-XX-10001-3MM1 - Electrical Drawing Index -IFD 0 18-Apr-15 18-Apr-15
MM1-1305-PT-82-E-XX-10001-4MM1 - Electrical Drawing Index -IFC 14 18-Apr-15 07-May-15
MM1-1305-PT-82-E-XX-10002MM1 - Electrical Cable Ladder Support 39 08-May-15 22-Jun-15
MM1-1305-PT-82-E-XX-10002-1MM1 - Electrical Cable Ladder Support-IDC 9 08-May-15* 18-May-15
MM1-1305-PT-82-E-XX-10002-2MM1 - Electrical Cable Ladder Support-IFR 13 19-May-15 02-Jun-15
MM1-1305-PT-82-E-XX-10002-3MM1 - Electrical Cable Ladder Support-IFD 0 03-Jun-15 03-Jun-15
MM1-1305-PT-82-E-XX-10002-4MM1 - Electrical Cable Ladder Support-IFC 17 03-Jun-15 22-Jun-15
MM1-1305-PT-82-E-XJ-10001MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001 39 13-Mar-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10001-1MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IDC 9 13-Mar-15* 23-Mar-15
MM1-1305-PT-82-E-XJ-10001-2MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IFR 13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XJ-10001-3MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IFD 0 08-Apr-15 08-Apr-15
MM1-1305-PT-82-E-XJ-10001-4MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IFC 17 08-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10002MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL00239 13-Mar-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10002-1MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IDC9 13-Mar-15* 23-Mar-15
MM1-1305-PT-82-E-XJ-10002-2MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IFR13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XJ-10002-3MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IFD0 08-Apr-15 08-Apr-15
MM1-1305-PT-82-E-XJ-10002-4MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IFC17 08-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10003MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL00339 13-Mar-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10003-1MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IDC9 13-Mar-15* 23-Mar-15
MM1-1305-PT-82-E-XJ-10003-2MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IFR13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XJ-10003-3MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IFD0 08-Apr-15 08-Apr-15
MM1-1305-PT-82-E-XJ-10003-4MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IFC17 08-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10004MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL00439 13-Mar-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10004-1MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL004-IDC9 13-Mar-15* 23-Mar-15
MM1-1305-PT-82-E-XJ-10004-2MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL004-IFR13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XJ-10004-3MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL004-IFD0 08-Apr-15 08-Apr-15
MM1-1305-PT-82-E-XJ-10004-4MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL004-IFC17 08-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10005MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL00539 13-Mar-15 27-Apr-15
MM1-1305-PT-82-E-XJ-10005-1MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IDC9 13-Mar-15* 23-Mar-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 19 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-82-E-XJ-10005-2MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IFR13 24-Mar-15 07-Apr-15
MM1-1305-PT-82-E-XJ-10005-3MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IFD0 08-Apr-15 08-Apr-15
MM1-1305-PT-82-E-XJ-10005-4MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IFC17 08-Apr-15 27-Apr-15
MM1-1305-PT-82-E-TA-10001MM1 - Electrical Cable Schedule 51 10-Apr-15 11-Jun-15
MM1-1305-PT-82-E-TA-10001-1MM1 - Electrical Cable Schedule -IDC 13 10-Apr-15* 24-Apr-15
MM1-1305-PT-82-E-TA-10001-2MM1 - Electrical Cable Schedule -IFR 9 25-Apr-15 08-May-15
MM1-1305-PT-82-E-TA-10001-3MM1 - Electrical Cable Schedule -IFD 13 09-May-15 23-May-15
MM1-1305-PT-82-E-TA-10001-4MM1 - Electrical Cable Schedule -IFC 16 25-May-15 11-Jun-15
MM1-1305-PT-82-E-XT-10001MM1 - Electrical Heat Tracing Interconnection Diagram 39 21-May-15 04-Jul-15
MM1-1305-PT-82-E-XT-10001-1MM1 - Electrical Heat Tracing Interconnection Diagram-IDC 9 21-May-15* 30-May-15
MM1-1305-PT-82-E-XT-10001-2MM1 - Electrical Heat Tracing Interconnection Diagram-IFR 13 01-Jun-15 15-Jun-15
MM1-1305-PT-82-E-XT-10001-3MM1 - Electrical Heat Tracing Interconnection Diagram-IFD 0 16-Jun-15 16-Jun-15
MM1-1305-PT-82-E-XT-10001-4MM1 - Electrical Heat Tracing Interconnection Diagram-IFC 17 16-Jun-15 04-Jul-15
MM1-1305-PT-82-E-XI-10001MM1 - Electrical Heat Tracing Block Diagram 58 25-Apr-15 04-Jul-15
MM1-1305-PT-82-E-XI-10001-1MM1 - Electrical Heat Tracing Block Diagram-IDC 6 25-Apr-15* 05-May-15
MM1-1305-PT-82-E-XI-10001-2MM1 - Electrical Heat Tracing Block Diagram-IFR 13 06-May-15 20-May-15
MM1-1305-PT-82-E-XI-10001-3MM1 - Electrical Heat Tracing Block Diagram-IFD 0 21-May-15 21-May-15
MM1-1305-PT-82-E-XI-10001-4MM1 - Electrical Heat Tracing Block Diagram-IFC 39 21-May-15 04-Jul-15
MM1-1305-PT-82-E-XI-10002MM1 - Electrical Lighting Interconnection Diagram 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XI-10002-1MM1 - Electrical Lighting Interconnection Diagram-IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XI-10002-2MM1 - Electrical Lighting Interconnection Diagram-IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XI-10002-3MM1 - Electrical Lighting Interconnection Diagram-IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XI-10002-4MM1 - Electrical Lighting Interconnection Diagram-IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-10001MM1 - Electrical Lighting And Small Power Layout - Main Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-10001-1MM1 - Electrical Lighting And Small Power Layout - Main Deck -IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-10001-2MM1 - Electrical Lighting And Small Power Layout - Main Deck -IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-10001-3MM1 - Electrical Lighting And Small Power Layout - Main Deck -IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-10001-4MM1 - Electrical Lighting And Small Power Layout - Main Deck -IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-10002MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-10002-1MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-10002-2MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-10002-3MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-10002-4MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-10003MM1 - Electrical Lighting And Small Power Layout - Upper Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-10003-1MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-10003-2MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-10003-3MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-10003-4MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-11001MM1 - Electrical Earthing Layout - Main Deck 35 02-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-11001-1MM1 - Electrical Earthing Layout - Main Deck -IDC 8 02-Apr-15* 10-Apr-15
MM1-1305-PT-82-E-XE-11001-2MM1 - Electrical Earthing Layout - Main Deck -IFR 13 11-Apr-15 25-Apr-15
MM1-1305-PT-82-E-XE-11001-3MM1 - Electrical Earthing Layout - Main Deck -IFD 0 27-Apr-15 27-Apr-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 20 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-82-E-XE-11001-4MM1 - Electrical Earthing Layout - Main Deck -IFC 14 27-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-11002MM1 - Electrical Earthing Layout - Mezzanine Deck 35 02-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-11002-1MM1 - Electrical Earthing Layout - Mezzanine Deck-IDC 8 02-Apr-15* 10-Apr-15
MM1-1305-PT-82-E-XE-11002-2MM1 - Electrical Earthing Layout - Mezzanine Deck-IFR 13 11-Apr-15 25-Apr-15
MM1-1305-PT-82-E-XE-11002-3MM1 - Electrical Earthing Layout - Mezzanine Deck-IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XE-11002-4MM1 - Electrical Earthing Layout - Mezzanine Deck-IFC 14 27-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-11003MM1 - Electrical Earthing Layout - Upper Deck 35 02-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-11003-1MM1 - Electrical Earthing Layout - Upper Deck -IDC 8 02-Apr-15* 10-Apr-15
MM1-1305-PT-82-E-XE-11003-2MM1 - Electrical Earthing Layout - Upper Deck -IFR 13 11-Apr-15 25-Apr-15
MM1-1305-PT-82-E-XE-11003-3MM1 - Electrical Earthing Layout - Upper Deck -IFD 0 27-Apr-15 27-Apr-15
MM1-1305-PT-82-E-XE-11003-4MM1 - Electrical Earthing Layout - Upper Deck -IFC 14 27-Apr-15 15-May-15
MM1-1305-PT-82-E-XE-12001MM1 - Electrical Cable Ladder And Support Layout - Main Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-12001-1MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-12001-2MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-12001-3MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-12001-4MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-12002MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-12002-1MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-12002-2MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-12002-3MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-12002-4MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-12003MM1 - Electrical Cable Ladder And Support Layout - Upper Deck 36 24-Apr-15 08-Jun-15
MM1-1305-PT-82-E-XE-12003-1MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IDC 6 24-Apr-15* 04-May-15
MM1-1305-PT-82-E-XE-12003-2MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IFR 13 05-May-15 19-May-15
MM1-1305-PT-82-E-XE-12003-3MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IFD 0 20-May-15 20-May-15
MM1-1305-PT-82-E-XE-12003-4MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IFC 17 20-May-15 08-Jun-15
MM1-1305-PT-82-E-XE-13001MM1 - Electrical Cable Routing Layout - Main Deck 39 09-May-15 23-Jun-15
MM1-1305-PT-82-E-XE-13001-1MM1 - Electrical Cable Routing Layout - Main Deck-IDC 9 09-May-15* 19-May-15
MM1-1305-PT-82-E-XE-13001-2MM1 - Electrical Cable Routing Layout - Main Deck-IFR 13 20-May-15 03-Jun-15
MM1-1305-PT-82-E-XE-13001-3MM1 - Electrical Cable Routing Layout - Main Deck-IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-82-E-XE-13001-4MM1 - Electrical Cable Routing Layout - Main Deck-IFC 17 04-Jun-15 23-Jun-15
MM1-1305-PT-82-E-XE-13002MM1 - Electrical Cable Routing Layout - Mezzanine Deck 39 09-May-15 23-Jun-15
MM1-1305-PT-82-E-XE-13002-1MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IDC 9 09-May-15* 19-May-15
MM1-1305-PT-82-E-XE-13002-2MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IFR 13 20-May-15 03-Jun-15
MM1-1305-PT-82-E-XE-13002-3MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-82-E-XE-13002-4MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IFC 17 04-Jun-15 23-Jun-15
MM1-1305-PT-82-E-XE-13003MM1 - Electrical Cable Routing Layout - Upper Deck 39 09-May-15 23-Jun-15
MM1-1305-PT-82-E-XE-13003-1MM1 - Electrical Cable Routing Layout - Upper Deck-IDC 9 09-May-15* 19-May-15
MM1-1305-PT-82-E-XE-13003-2MM1 - Electrical Cable Routing Layout - Upper Deck-IFR 13 20-May-15 03-Jun-15
MM1-1305-PT-82-E-XE-13003-3MM1 - Electrical Cable Routing Layout - Upper Deck-IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-82-E-XE-13003-4MM1 - Electrical Cable Routing Layout - Upper Deck-IFC 17 04-Jun-15 23-Jun-15
MM1-1305-PT-82-E-LA-00001MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures 80 05-May-15 05-Aug-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 21 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Activity ID Activity Name Original
Duration
Start Finish
MM1-1305-PT-82-E-LA-00001-1MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IDC 7 05-May-15* 12-May-15
MM1-1305-PT-82-E-LA-00001-2MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFR 24 13-May-15 09-Jun-15
MM1-1305-PT-82-E-LA-00001-3MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFD 0 10-Jun-15 10-Jun-15
MM1-1305-PT-82-E-LA-00001-4MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFC 49 10-Jun-15 05-Aug-15
MM1-1305-PT-82-E-LA-00002MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories77 11-May-15 07-Aug-15
MM1-1305-PT-82-E-LA-00002-1MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IDC7 11-May-15* 18-May-15
MM1-1305-PT-82-E-LA-00002-2MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFR23 19-May-15 13-Jun-15
MM1-1305-PT-82-E-LA-00002-3MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFD0 15-Jun-15 15-Jun-15
MM1-1305-PT-82-E-LA-00002-4MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFC47 15-Jun-15 07-Aug-15
MM1-1305-PT-82-E-LA-00003MM1 & MM2 - Electrical Material Take-Off - Cables 62 18-May-15 28-Jul-15
MM1-1305-PT-82-E-LA-00003-1MM1 & MM2 - Electrical Material Take-Off - Cables-IDC 7 18-May-15* 25-May-15
MM1-1305-PT-82-E-LA-00003-2MM1 & MM2 - Electrical Material Take-Off - Cables-IFR 8 26-May-15 03-Jun-15
MM1-1305-PT-82-E-LA-00003-3MM1 & MM2 - Electrical Material Take-Off - Cables-IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-82-E-LA-00003-4MM1 & MM2 - Electrical Material Take-Off - Cables-IFC 47 04-Jun-15 28-Jul-15
MM1-1305-PT-82-E-LA-00004MM1 & MM2 - Electrical Material Take-Off - Cable Glands 77 21-May-15 18-Aug-15
MM1-1305-PT-82-E-LA-00004-1MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IDC 7 21-May-15* 28-May-15
MM1-1305-PT-82-E-LA-00004-2MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFR 22 29-May-15 23-Jun-15
MM1-1305-PT-82-E-LA-00004-3MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFD 0 24-Jun-15 24-Jun-15
MM1-1305-PT-82-E-LA-00004-4MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFC 48 24-Jun-15 18-Aug-15
MM1-1305-PT-82-E-LA-00005MM1 & MM2 - Electrical Material Take-Off - Junction Boxes 83 02-May-15 06-Aug-15
MM1-1305-PT-82-E-LA-00005-1MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IDC 6 02-May-15* 08-May-15
MM1-1305-PT-82-E-LA-00005-2MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFR 31 09-May-15 13-Jun-15
MM1-1305-PT-82-E-LA-00005-3MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFD 0 15-Jun-15 15-Jun-15
MM1-1305-PT-82-E-LA-00005-4MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFC 46 15-Jun-15 06-Aug-15
MM1-1305-PT-82-E-LA-00006MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials 94 21-May-15 08-Sep-15
MM1-1305-PT-82-E-LA-00006-1MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IDC 7 21-May-15* 28-May-15
MM1-1305-PT-82-E-LA-00006-2MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFR 38 29-May-15 11-Jul-15
MM1-1305-PT-82-E-LA-00006-3MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFD 0 13-Jul-15 13-Jul-15
MM1-1305-PT-82-E-LA-00006-4MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFC 49 13-Jul-15 08-Sep-15
MM1-1305-PT-82-E-LA-00007MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials 52 15-May-15 14-Jul-15
MM1-1305-PT-82-E-LA-00007-1MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IDC 7 15-May-15* 22-May-15
MM1-1305-PT-82-E-LA-00007-2MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFR 10 23-May-15 03-Jun-15
MM1-1305-PT-82-E-LA-00007-3MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFD 0 04-Jun-15 04-Jun-15
MM1-1305-PT-82-E-LA-00007-4MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFC 35 04-Jun-15 14-Jul-15
MM1-1305-PT-00-I-LA-00009MM1 & MM2 - Ex Equipment Register 68 11-Jun-15 28-Aug-15
MM1-1305-PT-00-I-LA-00009-1MM1 & MM2 - Ex Equipment Register-IDC 27 11-Jun-15* 11-Jul-15
MM1-1305-PT-00-I-LA-00009-2MM1 & MM2 - Ex Equipment Register-IFR 12 13-Jul-15 25-Jul-15
MM1-1305-PT-00-I-LA-00009-3MM1 & MM2 - Ex Equipment Register-IFD 12 27-Jul-15 08-Aug-15
MM1-1305-PT-00-I-LA-00009-4MM1 & MM2 - Ex Equipment Register-IFC 17 10-Aug-15 28-Aug-15
MM1-1305-PT-00-I-SA-00001MM1 & MM2 - Instrument Control and Shutdown Philosophy 64 10-Jun-15 22-Aug-15
MM1-1305-PT-00-I-SA-00001-1MM1 & MM2 - Instrument Control and Shutdown Philosophy-IDC 27 10-Jun-15* 10-Jul-15
MM1-1305-PT-00-I-SA-00001-2MM1 & MM2 - Instrument Control and Shutdown Philosophy-IFR 8 11-Jul-15 20-Jul-15
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2015 2016
Ghana OCTP Development Project, FPSO
EPC for Module MM1 & MM2
Remaining Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Schedule Level 3
Page 22 of 72
Date Revision Checked Approved
28-Mar-15 Baseline Schedule Level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3

Mais conteúdo relacionado

Mais procurados

Amol Sawant (Piping Engineer with 10 years experience) docx
Amol Sawant (Piping Engineer with 10 years experience) docxAmol Sawant (Piping Engineer with 10 years experience) docx
Amol Sawant (Piping Engineer with 10 years experience) docx
Amol Sawant
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
TW Carl
 
Resume_Mechanical(Static Equipments Engineer) SRP 9.5 yrs experience
Resume_Mechanical(Static  Equipments Engineer) SRP 9.5 yrs experienceResume_Mechanical(Static  Equipments Engineer) SRP 9.5 yrs experience
Resume_Mechanical(Static Equipments Engineer) SRP 9.5 yrs experience
Sachin Patil
 
Planning & Scheduling - Training
Planning & Scheduling - TrainingPlanning & Scheduling - Training
Planning & Scheduling - Training
Mohammed Feroze
 
CV-Mechanical Engineer.
CV-Mechanical Engineer.CV-Mechanical Engineer.
CV-Mechanical Engineer.
AZHAR QAZI
 
Saurabh Shah Piping Engineer CV
Saurabh Shah Piping Engineer CVSaurabh Shah Piping Engineer CV
Saurabh Shah Piping Engineer CV
Saurabh Shah
 
QA- QC INSPECTOR AJITH CV - Copy
QA- QC INSPECTOR AJITH CV - CopyQA- QC INSPECTOR AJITH CV - Copy
QA- QC INSPECTOR AJITH CV - Copy
Ajith Puthoor
 

Mais procurados (20)

Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Planning For Engineering
Planning For EngineeringPlanning For Engineering
Planning For Engineering
 
CV of Mohammad Mujeebuddin - PMO QA Manager
CV of Mohammad Mujeebuddin - PMO QA ManagerCV of Mohammad Mujeebuddin - PMO QA Manager
CV of Mohammad Mujeebuddin - PMO QA Manager
 
Senior Pipeline/ Piping Mechanical Engineer Construction & Commissioning
Senior Pipeline/ Piping Mechanical Engineer Construction & CommissioningSenior Pipeline/ Piping Mechanical Engineer Construction & Commissioning
Senior Pipeline/ Piping Mechanical Engineer Construction & Commissioning
 
Amol Sawant (Piping Engineer with 10 years experience) docx
Amol Sawant (Piping Engineer with 10 years experience) docxAmol Sawant (Piping Engineer with 10 years experience) docx
Amol Sawant (Piping Engineer with 10 years experience) docx
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
 
QA QC Inspector.doc 1
QA QC Inspector.doc 1QA QC Inspector.doc 1
QA QC Inspector.doc 1
 
Resume_Mechanical(Static Equipments Engineer) SRP 9.5 yrs experience
Resume_Mechanical(Static  Equipments Engineer) SRP 9.5 yrs experienceResume_Mechanical(Static  Equipments Engineer) SRP 9.5 yrs experience
Resume_Mechanical(Static Equipments Engineer) SRP 9.5 yrs experience
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
Planning & Scheduling - Training
Planning & Scheduling - TrainingPlanning & Scheduling - Training
Planning & Scheduling - Training
 
Cv Piping Engineer
Cv Piping EngineerCv Piping Engineer
Cv Piping Engineer
 
CV-Mechanical Engineer.
CV-Mechanical Engineer.CV-Mechanical Engineer.
CV-Mechanical Engineer.
 
CV- Piping Engineer (EPC)
CV- Piping  Engineer (EPC)CV- Piping  Engineer (EPC)
CV- Piping Engineer (EPC)
 
Saurabh Shah Piping Engineer CV
Saurabh Shah Piping Engineer CVSaurabh Shah Piping Engineer CV
Saurabh Shah Piping Engineer CV
 
QA- QC INSPECTOR AJITH CV - Copy
QA- QC INSPECTOR AJITH CV - CopyQA- QC INSPECTOR AJITH CV - Copy
QA- QC INSPECTOR AJITH CV - Copy
 

Destaque

111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
PM SOLUTION PRO| Risk-based Management and Services Inc.
 
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Gary Hayes
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classification
guest81e1c7
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
Natalie Reid
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
Bt Lee
 

Destaque (16)

111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
 
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
 
EPC Project 3 - Mural Art
EPC Project 3 - Mural ArtEPC Project 3 - Mural Art
EPC Project 3 - Mural Art
 
Schedule 3 of Companies act 2013
Schedule 3 of Companies act 2013Schedule 3 of Companies act 2013
Schedule 3 of Companies act 2013
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Hazardous Area Classification
Hazardous Area ClassificationHazardous Area Classification
Hazardous Area Classification
 
Bill Of Quantities
Bill Of QuantitiesBill Of Quantities
Bill Of Quantities
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 

Semelhante a Epc for module mm1 mm2 baseline schedule level 3

Reekie_David_ITP (1)
Reekie_David_ITP (1)Reekie_David_ITP (1)
Reekie_David_ITP (1)
David Reekie
 
GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015
William Irving
 
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
jjskekkepl
 
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
ujfjjskekmemm
 
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
fhjsekkemm
 
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
fusjejfskekemm
 
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
ufjjskekkmed
 
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manualJcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
udjjsjekkmme
 
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manualJcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
fjkskedmme
 
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manualJcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
fujjsefkskemm
 
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
jfkekd9d8di
 

Semelhante a Epc for module mm1 mm2 baseline schedule level 3 (20)

Manish Engineering Works
Manish Engineering WorksManish Engineering Works
Manish Engineering Works
 
Reekie_David_ITP (1)
Reekie_David_ITP (1)Reekie_David_ITP (1)
Reekie_David_ITP (1)
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015
 
Be siemens price list 03 02-2012
Be siemens price list 03 02-2012Be siemens price list 03 02-2012
Be siemens price list 03 02-2012
 
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
 
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
 
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
 
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
 
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
Caterpillar cat 305.5 mini hydraulic excavator (prefix dck) service repair ma...
 
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
 
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
 
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
 
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
 
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
 
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manualJcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
 
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manualJcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
 
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manualJcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
Jcb js370 (tier 2 jcb diesel max engine) tracked excavator service repair manual
 
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
 
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
Caterpillar Cat 305.5 Mini Hydraulic Excavator (Prefix DCK) Service Repair Ma...
 

Último

B. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdfB. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdf
University of Wisconsin-Milwaukee
 
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceCALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
anilsa9823
 
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
kumaririma588
 
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
amitlee9823
 
infant assessment fdbbdbdddinal ppt.pptx
infant assessment fdbbdbdddinal ppt.pptxinfant assessment fdbbdbdddinal ppt.pptx
infant assessment fdbbdbdddinal ppt.pptx
suhanimunjal27
 
Stark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptxStark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptx
jeswinjees
 
Peaches App development presentation deck
Peaches App development presentation deckPeaches App development presentation deck
Peaches App development presentation deck
tbatkhuu1
 
Government polytechnic college-1.pptxabcd
Government polytechnic college-1.pptxabcdGovernment polytechnic college-1.pptxabcd
Government polytechnic college-1.pptxabcd
shivubhavv
 
Design Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptxDesign Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptx
TusharBahuguna2
 
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
soniya singh
 
2-tool presenthdbdbdbdbddhdhddation.pptx
2-tool presenthdbdbdbdbddhdhddation.pptx2-tool presenthdbdbdbdbddhdhddation.pptx
2-tool presenthdbdbdbdbddhdhddation.pptx
suhanimunjal27
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
home
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 

Último (20)

Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Hy...
 
SD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptxSD_The MATATAG Curriculum Training Design.pptx
SD_The MATATAG Curriculum Training Design.pptx
 
B. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdfB. Smith. (Architectural Portfolio.).pdf
B. Smith. (Architectural Portfolio.).pdf
 
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun serviceCALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
CALL ON ➥8923113531 🔝Call Girls Aminabad Lucknow best Night Fun service
 
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...Verified Trusted Call Girls Adugodi💘 9352852248  Good Looking standard Profil...
Verified Trusted Call Girls Adugodi💘 9352852248 Good Looking standard Profil...
 
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdfThe_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
The_Canvas_of_Creative_Mastery_Newsletter_April_2024_Version.pdf
 
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Jigani Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
 
infant assessment fdbbdbdddinal ppt.pptx
infant assessment fdbbdbdddinal ppt.pptxinfant assessment fdbbdbdddinal ppt.pptx
infant assessment fdbbdbdddinal ppt.pptx
 
Stark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptxStark Industries Marketing Plan (1).pptx
Stark Industries Marketing Plan (1).pptx
 
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Koregaon Park ⟟ 6297143586 ⟟ Call Me For Genuine S...
 
Peaches App development presentation deck
Peaches App development presentation deckPeaches App development presentation deck
Peaches App development presentation deck
 
Government polytechnic college-1.pptxabcd
Government polytechnic college-1.pptxabcdGovernment polytechnic college-1.pptxabcd
Government polytechnic college-1.pptxabcd
 
Design Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptxDesign Inspiration for College by Slidesgo.pptx
Design Inspiration for College by Slidesgo.pptx
 
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
Call Girls in Kalkaji Delhi 8264348440 call girls ❤️
 
2-tool presenthdbdbdbdbddhdhddation.pptx
2-tool presenthdbdbdbdbddhdhddation.pptx2-tool presenthdbdbdbdbddhdhddation.pptx
2-tool presenthdbdbdbdbddhdhddation.pptx
 
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
Recommendable # 971589162217 # philippine Young Call Girls in Dubai By Marina...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Booking open Available Pune Call Girls Kirkatwadi 6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Kirkatwadi  6297143586 Call Hot Indian...Booking open Available Pune Call Girls Kirkatwadi  6297143586 Call Hot Indian...
Booking open Available Pune Call Girls Kirkatwadi 6297143586 Call Hot Indian...
 
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
Pooja 9892124323, Call girls Services and Mumbai Escort Service Near Hotel Gi...
 
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
VVIP Pune Call Girls Hadapsar (7001035870) Pune Escorts Nearby with Complete ...
 

Epc for module mm1 mm2 baseline schedule level 3

  • 1. Activity ID Activity Name Original Duration Start Finish 0 TC2A - Manifolding Topsides Modules-(baseline)0 TC2A - Manifolding Topsides Modules-(baseline) 333 13-Mar-15 08-Apr-16 0.D.26 Process System0.D.26 Process System 333 13-Mar-15 08-Apr-16 0.D.26.0000 Sub System Code Level0.D.26.0000 Sub System Code Level 333 13-Mar-15 08-Apr-16 0.D.26.0000.MM1 MM1-Manifold and Pigging0.D.26.0000.MM1 MM1-Manifold and Pigging 333 13-Mar-15 08-Apr-16 0.D.26.0000.MM1.A Milestone0.D.26.0000.MM1.A Milestone 333 13-Mar-15 08-Apr-16 MM1-10010 Effective date (LOI) 0 13-Mar-15* MM1-101000 Commence Basic & Detail Engineering Modules MM1 0 13-Mar-15* MM1-101040 HAZID Review Workshop 0 23-Mar-15* MM1-101060 HAZOP Review Workshop 0 27-Apr-15* MM1-101080 Commence Fab Modules MM1 0 17-Sep-15 MM1-101020 Completion Basic & Detail Engineering Modules MM1 0 23-Sep-15* MM1-10070 MCD for MM1 0 24-Mar-16* MM1-10090 Commence Load-out Modules MM1 0 26-Mar-16* MM1-101100 Modules MM1 available at Singapore Yard 0 08-Apr-16* 0.D.26.0000.MM1.B Engineering0.D.26.0000.MM1.B Engineering 327 13-Mar-15 01-Apr-16 0.D.26.0000.MM1.B.0 General0.D.26.0000.MM1.B.0 General 321 13-Mar-15 01-Apr-16 0.D.26.0000.MM1.B.0.92 PTSC0.D.26.0000.MM1.B.0.92 PTSC 321 13-Mar-15 01-Apr-16 MM1-10130 General for PMT (Meeting, Project Management, Project Coordination, Engineering review, etc)321 13-Mar-15 01-Apr-16 MM1-1305-PT-00-A-TB-00001MM1 & MM2 - Detailed Engineering Execution Plan 40 13-Mar-15 29-Apr-15 MM1-1305-PT-00-A-TB-00001-1MM1 & MM2 - Detailed Engineering Execution Plan-IDC 8 13-Mar-15* 21-Mar-15 MM1-1305-PT-00-A-TB-00001-2MM1 & MM2 - Detailed Engineering Execution Plan-IFR 6 23-Mar-15 28-Mar-15 MM1-1305-PT-00-A-TB-00001-3MM1 & MM2 - Detailed Engineering Execution Plan-IFD 11 30-Mar-15 10-Apr-15 MM1-1305-PT-00-A-TB-00001-4MM1 & MM2 - Detailed Engineering Execution Plan-IFC 15 11-Apr-15 29-Apr-15 MM1-1305-PT-00-A-KA-00001MM1 & MM2 - Detailed Engineering Coordination Procedure 31 13-Mar-15 17-Apr-15 MM1-1305-PT-00-A-KA-00001-1MM1 & MM2 - Detailed Engineering Coordination Procedure-IDC 8 13-Mar-15* 21-Mar-15 MM1-1305-PT-00-A-KA-00001-2MM1 & MM2 - Detailed Engineering Coordination Procedure-IFR 6 23-Mar-15 28-Mar-15 MM1-1305-PT-00-A-KA-00001-3MM1 & MM2 - Detailed Engineering Coordination Procedure-IFD 0 30-Mar-15 30-Mar-15 MM1-1305-PT-00-A-KA-00001-4MM1 & MM2 - Detailed Engineering Coordination Procedure-IFC 17 30-Mar-15 17-Apr-15 0.D.26.0000.MM1.B.9 3D Modelling0.D.26.0000.MM1.B.9 3D Modelling 65 12-May-15 25-Jul-15 0.D.26.0000.MM1.B.9.92 PTSC0.D.26.0000.MM1.B.9.92 PTSC 65 12-May-15 25-Jul-15 MM1-1305-PT-00-L-RA-00001MM1 & MM2 - PDMS 30% model review report 17 12-May-15 30-May-15 MM1-1305-PT-00-L-RA-00001-1MM1 & MM2 - PDMS 30% model review report-IDC 7 12-May-15* 19-May-15 MM1-1305-PT-00-L-RA-00001-2MM1 & MM2 - PDMS 30% model review report-IFR 4 20-May-15 23-May-15 MM1-1305-PT-00-L-RA-00001-3MM1 & MM2 - PDMS 30% model review report-IFD 0 25-May-15 25-May-15 MM1-1305-PT-00-L-RA-00001-4MM1 & MM2 - PDMS 30% model review report-IFC 6 25-May-15 30-May-15 MM1-1305-PT-00-L-RA-00002MM1 & MM2 - PDMS 60% model review report 17 09-Jun-15 27-Jun-15 MM1-1305-PT-00-L-RA-00002-1MM1 & MM2 - PDMS 60% model review report-IDC 7 09-Jun-15* 16-Jun-15 MM1-1305-PT-00-L-RA-00002-2MM1 & MM2 - PDMS 60% model review report-IFR 4 17-Jun-15 20-Jun-15 MM1-1305-PT-00-L-RA-00002-3MM1 & MM2 - PDMS 60% model review report-IFD 0 22-Jun-15 22-Jun-15 MM1-1305-PT-00-L-RA-00002-4MM1 & MM2 - PDMS 60% model review report-IFC 6 22-Jun-15 27-Jun-15 MM1-1305-PT-00-L-RA-00003MM1 & MM2 - PDMS 90% model review report 17 07-Jul-15 25-Jul-15 MM1-1305-PT-00-L-RA-00003-1MM1 & MM2 - PDMS 90% model review report -IDC 7 07-Jul-15* 14-Jul-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Effective date (LOI) Commence Basic & Detail Engineering Modules MM1 HAZID Review Workshop HAZOP Review Workshop Commence Fab Modules MM1 Completion Basic & Detail Engineering Modules MM1 MCD for MM1 Commence Load-out Modu Modules MM1 available Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 1 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 2. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-00-L-RA-00003-2MM1 & MM2 - PDMS 90% model review report -IFR 4 15-Jul-15 18-Jul-15 MM1-1305-PT-00-L-RA-00003-3MM1 & MM2 - PDMS 90% model review report -IFD 0 20-Jul-15 20-Jul-15 MM1-1305-PT-00-L-RA-00003-4MM1 & MM2 - PDMS 90% model review report -IFC 6 20-Jul-15 25-Jul-15 0.D.26.0000.MM1.B.S Process & Systems0.D.26.0000.MM1.B.S Process & Systems 79 13-Mar-15 16-Jun-15 0.D.26.0000.MM1.B.S.92 PTSC0.D.26.0000.MM1.B.S.92 PTSC 79 13-Mar-15 16-Jun-15 MM1-1305-PT-30-P-FD-00001MM1 & MM2 - Basic Design Data 47 13-Mar-15 09-May-15 MM1-1305-PT-30-P-FD-00001-1MM1 & MM2 - Basic Design Data-IDC 9 13-Mar-15* 23-Mar-15 MM1-1305-PT-30-P-FD-00001-2MM1 & MM2 - Basic Design Data-IFR 7 24-Mar-15 31-Mar-15 MM1-1305-PT-30-P-FD-00001-3MM1 & MM2 - Basic Design Data-IFD 13 01-Apr-15 15-Apr-15 MM1-1305-PT-30-P-FD-00001-4MM1 & MM2 - Basic Design Data-IFC 18 16-Apr-15 09-May-15 MM1-1305-PT-30-P-RA-00001MM1 & MM2 - Report - HYSYS Simulation 48 13-Mar-15 11-May-15 MM1-1305-PT-30-P-RA-00001-1MM1 & MM2 - Report - HYSYS Simulation-IDC 1 13-Mar-15* 13-Mar-15 MM1-1305-PT-30-P-RA-00001-2MM1 & MM2 - Report - HYSYS Simulation-IFR 17 14-Mar-15 02-Apr-15 MM1-1305-PT-30-P-RA-00001-3MM1 & MM2 - Report - HYSYS Simulation-IFD 13 03-Apr-15 17-Apr-15 MM1-1305-PT-30-P-RA-00001-4MM1 & MM2 - Report - HYSYS Simulation-IFC 17 18-Apr-15 11-May-15 MM1-1305-PT-30-P-RA-00002MM1 & MM2 - Report - Line Sizing 55 03-Apr-15 09-Jun-15 MM1-1305-PT-30-P-RA-00002-1MM1 & MM2 - Report - Line Sizing-IDC 1 03-Apr-15* 03-Apr-15 MM1-1305-PT-30-P-RA-00002-2MM1 & MM2 - Report - Line Sizing-IFR 21 04-Apr-15 29-Apr-15 MM1-1305-PT-30-P-RA-00002-3MM1 & MM2 - Report - Line Sizing-IFD 13 02-May-15 16-May-15 MM1-1305-PT-30-P-RA-00002-4MM1 & MM2 - Report - Line Sizing-IFC 20 18-May-15 09-Jun-15 MM1-1305-PT-30-P-RA-00003MM1 & MM2 - Report - Utility Summary 40 22-Apr-15 10-Jun-15 MM1-1305-PT-30-P-RA-00003-1MM1 & MM2 - Report - Utility Summary-IDC 1 22-Apr-15* 22-Apr-15 MM1-1305-PT-30-P-RA-00003-2MM1 & MM2 - Report - Utility Summary-IFR 6 23-Apr-15 02-May-15 MM1-1305-PT-30-P-RA-00003-3MM1 & MM2 - Report - Utility Summary-IFD 12 04-May-15 16-May-15 MM1-1305-PT-30-P-RA-00003-4MM1 & MM2 - Report - Utility Summary-IFC 21 18-May-15 10-Jun-15 MM1-1305-PT-30-P-CA-00001MM1 & MM2 - Calculation Note - Depressuring 44 23-Mar-15 15-May-15 MM1-1305-PT-30-P-CA-00001-1MM1 & MM2 - Calculation Note - Depressuring -IDC 1 23-Mar-15* 23-Mar-15 MM1-1305-PT-30-P-CA-00001-2MM1 & MM2 - Calculation Note - Depressuring -IFR 12 24-Mar-15 06-Apr-15 MM1-1305-PT-30-P-CA-00001-3MM1 & MM2 - Calculation Note - Depressuring -IFD 13 07-Apr-15 21-Apr-15 MM1-1305-PT-30-P-CA-00001-4MM1 & MM2 - Calculation Note - Depressuring -IFC 18 22-Apr-15 15-May-15 MM1-1305-PT-30-P-CA-00002MM1 & MM2 - Calculation Note - PSV Sizing 44 07-Apr-15 30-May-15 MM1-1305-PT-30-P-CA-00002-1MM1 & MM2 - Calculation Note - PSV Sizing -IDC 1 07-Apr-15* 07-Apr-15 MM1-1305-PT-30-P-CA-00002-2MM1 & MM2 - Calculation Note - PSV Sizing -IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-CA-00002-3MM1 & MM2 - Calculation Note - PSV Sizing -IFD 10 22-Apr-15 06-May-15 MM1-1305-PT-30-P-CA-00002-4MM1 & MM2 - Calculation Note - PSV Sizing -IFC 21 07-May-15 30-May-15 MM1-1305-PT-30-P-XA-00001MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets) 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XA-00001-1MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XA-00001-2MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XA-00001-3MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XA-00001-4MM1 & MM2 - Process Flow Diagram (PFD) (4 Sheets)-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XA-00002MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets) 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XA-00002-1MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IDC 22 13-Mar-15* 07-Apr-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 2 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 3. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-30-P-XA-00002-2MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XA-00002-3MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XA-00002-4MM1 & MM2 - Utility Flow Diagram (UFD) (2 Sheets)-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XA-00003MM1 & MM2 - Material Selection Diagrams (3 Sheets) 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XA-00003-1MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XA-00003-2MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XA-00003-3MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XA-00003-4MM1 & MM2 - Material Selection Diagrams (3 Sheets)-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00001MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00001-1MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00001-2MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00001-3MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00001-4MM1 & MM2 - P&ID Riser Oil Production 1 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00002MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00002-1MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00002-2MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00002-3MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00002-4MM1 & MM2 - P&ID Riser Oil Production 2 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00003MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00003-1MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00003-2MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00003-3MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00003-4MM1 & MM2 - P&ID Riser Oil Production 3 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00004MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00004-1MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IDC22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00004-2MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFR12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00004-3MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFD14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00004-4MM1 & MM2 - P&ID Riser Oil Production 4 - Pig Launcher And Reciever -IFC21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00005MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00005-1MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00005-2MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00005-3MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00005-4MM1 & MM2 - P&ID Riser Oil Production 5 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00006MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00006-1MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00006-2MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00006-3MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00006-4MM1 & MM2 - P&ID Riser Oil Production 6 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00007MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00007-1MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00007-2MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00007-3MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFD 14 22-Apr-15 11-May-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 3 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 4. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-30-P-XB-00007-4MM1 & MM2 - P&ID Riser Oil Production 7 - Pig Launcher And Reciever-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00008MM1 & MM2 - P&ID HP Oil Production Manifold 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00008-1MM1 & MM2 - P&ID HP Oil Production Manifold-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00008-2MM1 & MM2 - P&ID HP Oil Production Manifold-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00008-3MM1 & MM2 - P&ID HP Oil Production Manifold-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00008-4MM1 & MM2 - P&ID HP Oil Production Manifold-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00009MM1 & MM2 - P&ID HHP Oil Production Manifold 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00009-1MM1 & MM2 - P&ID HHP Oil Production Manifold-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00009-2MM1 & MM2 - P&ID HHP Oil Production Manifold-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00009-3MM1 & MM2 - P&ID HHP Oil Production Manifold-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00009-4MM1 & MM2 - P&ID HHP Oil Production Manifold-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00010MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets) 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00010-1MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00010-2MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00010-3MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00010-4MM1 & MM2 - P&ID Gas Production Manifold (2 Sheets)-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00011MM1 & MM2 - P&ID Test Manifold 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00011-1MM1 & MM2 - P&ID Test Manifold-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00011-2MM1 & MM2 - P&ID Test Manifold-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00011-3MM1 & MM2 - P&ID Test Manifold-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00011-4MM1 & MM2 - P&ID Test Manifold-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00012MM1 & MM2 - P&ID Gas Injection Manifold 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00012-1MM1 & MM2 - P&ID Gas Injection Manifold-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00012-2MM1 & MM2 - P&ID Gas Injection Manifold-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00012-3MM1 & MM2 - P&ID Gas Injection Manifold-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00012-4MM1 & MM2 - P&ID Gas Injection Manifold-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00013MM1 & MM2 - P&ID Water Injection Manifold 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00013-1MM1 & MM2 - P&ID Water Injection Manifold-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00013-2MM1 & MM2 - P&ID Water Injection Manifold-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00013-3MM1 & MM2 - P&ID Water Injection Manifold-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00013-4MM1 & MM2 - P&ID Water Injection Manifold-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00014MM1 & MM2 - P&ID Gas Export Manifold 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00014-1MM1 & MM2 - P&ID Gas Export Manifold-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00014-2MM1 & MM2 - P&ID Gas Export Manifold-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00014-3MM1 & MM2 - P&ID Gas Export Manifold-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00014-4MM1 & MM2 - P&ID Gas Export Manifold-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00015MM1 & MM2 - P&ID Gas Lift Manifold 69 13-Mar-15 04-Jun-15 MM1-1305-PT-30-P-XB-00015-1MM1 & MM2 - P&ID Gas Lift Manifold-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00015-2MM1 & MM2 - P&ID Gas Lift Manifold-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00015-3MM1 & MM2 - P&ID Gas Lift Manifold-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00015-4MM1 & MM2 - P&ID Gas Lift Manifold-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-XB-00016MM1 & MM2 - P&ID Diesel Manifold 69 13-Mar-15 04-Jun-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 4 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 5. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-30-P-XB-00016-1MM1 & MM2 - P&ID Diesel Manifold-IDC 22 13-Mar-15* 07-Apr-15 MM1-1305-PT-30-P-XB-00016-2MM1 & MM2 - P&ID Diesel Manifold-IFR 12 08-Apr-15 21-Apr-15 MM1-1305-PT-30-P-XB-00016-3MM1 & MM2 - P&ID Diesel Manifold-IFD 14 22-Apr-15 11-May-15 MM1-1305-PT-30-P-XB-00016-4MM1 & MM2 - P&ID Diesel Manifold-IFC 21 12-May-15 04-Jun-15 MM1-1305-PT-30-P-LA-00001MM1 & MM2 - Line List 56 09-Apr-15 16-Jun-15 MM1-1305-PT-30-P-LA-00001-1MM1 & MM2 - Line List-IDC 14 09-Apr-15* 24-Apr-15 MM1-1305-PT-30-P-LA-00001-2MM1 & MM2 - Line List-IFR 10 25-Apr-15 09-May-15 MM1-1305-PT-30-P-LA-00001-3MM1 & MM2 - Line List-IFD 14 11-May-15 26-May-15 MM1-1305-PT-30-P-LA-00001-4MM1 & MM2 - Line List-IFC 18 27-May-15 16-Jun-15 MM1-1305-PT-30-P-XM-00001MM1 & MM2 - Safe Chart 52 08-Apr-15 10-Jun-15 MM1-1305-PT-30-P-XM-00001-1MM1 & MM2 - Safe Chart-IDC 7 08-Apr-15* 15-Apr-15 MM1-1305-PT-30-P-XM-00001-2MM1 & MM2 - Safe Chart-IFR 6 16-Apr-15 22-Apr-15 MM1-1305-PT-30-P-XM-00001-3MM1 & MM2 - Safe Chart-IFD 18 23-Apr-15 16-May-15 MM1-1305-PT-30-P-XM-00001-4MM1 & MM2 - Safe Chart-IFC 21 18-May-15 10-Jun-15 MM1-1305-PT-30-P-XL-00001MM1 & MM2 - ESD Logic Diagram 52 08-Apr-15 10-Jun-15 MM1-1305-PT-30-P-XL-00001-1MM1 & MM2 - ESD Logic Diagram-IDC 7 08-Apr-15* 15-Apr-15 MM1-1305-PT-30-P-XL-00001-2MM1 & MM2 - ESD Logic Diagram-IFR 6 16-Apr-15 22-Apr-15 MM1-1305-PT-30-P-XL-00001-3MM1 & MM2 - ESD Logic Diagram-IFD 18 23-Apr-15 16-May-15 MM1-1305-PT-30-P-XL-00001-4MM1 & MM2 - ESD Logic Diagram-IFC 21 18-May-15 10-Jun-15 MM1-1305-PT-30-P-LA-00002MM1 & MM2 - Alarm / Trip Schedule 52 08-Apr-15 10-Jun-15 MM1-1305-PT-30-P-LA-00002-1MM1 & MM2 - Alarm / Trip Schedule-IDC 7 08-Apr-15* 15-Apr-15 MM1-1305-PT-30-P-LA-00002-2MM1 & MM2 - Alarm / Trip Schedule-IFR 6 16-Apr-15 22-Apr-15 MM1-1305-PT-30-P-LA-00002-3MM1 & MM2 - Alarm / Trip Schedule-IFD 18 23-Apr-15 16-May-15 MM1-1305-PT-30-P-LA-00002-4MM1 & MM2 - Alarm / Trip Schedule-IFC 21 18-May-15 10-Jun-15 MM1-1305-PT-30-X-CA-00001MM1 & MM2 - Calculation Note - Deluge System 53 08-Apr-15 11-Jun-15 MM1-1305-PT-30-X-CA-00001-1MM1 & MM2 - Calculation Note - Deluge System-IDC 1 08-Apr-15* 08-Apr-15 MM1-1305-PT-30-X-CA-00001-2MM1 & MM2 - Calculation Note - Deluge System-IFR 17 09-Apr-15 29-Apr-15 MM1-1305-PT-30-X-CA-00001-3MM1 & MM2 - Calculation Note - Deluge System-IFD 14 02-May-15 18-May-15 MM1-1305-PT-30-X-CA-00001-4MM1 & MM2 - Calculation Note - Deluge System-IFC 21 19-May-15 11-Jun-15 MM1-1305-PT-30-X-CA-00002MM1 & MM2 - Steady State Analysis for Deluge System 51 15-Apr-15 16-Jun-15 MM1-1305-PT-30-X-CA-00002-1MM1 & MM2 - Steady State Analysis for Deluge System-IDC 1 15-Apr-15* 15-Apr-15 MM1-1305-PT-30-X-CA-00002-2MM1 & MM2 - Steady State Analysis for Deluge System-IFR 15 16-Apr-15 06-May-15 MM1-1305-PT-30-X-CA-00002-3MM1 & MM2 - Steady State Analysis for Deluge System-IFD 15 07-May-15 23-May-15 MM1-1305-PT-30-X-CA-00002-4MM1 & MM2 - Steady State Analysis for Deluge System-IFC 20 25-May-15 16-Jun-15 MM1-1305-PT-30-X-XE-10001MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck Equipment Layout Plan59 26-Mar-15 05-Jun-15 MM1-1305-PT-30-X-XE-10001-1MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck Equipment Layout Plan-IDC13 26-Mar-15* 09-Apr-15 MM1-1305-PT-30-X-XE-10001-2MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck Equipment Layout Plan-IFR12 10-Apr-15 23-Apr-15 MM1-1305-PT-30-X-XE-10001-3MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck Equipment Layout Plan-IFD11 24-Apr-15 09-May-15 MM1-1305-PT-30-X-XE-10001-4MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Upper Deck Equipment Layout Plan-IFC23 11-May-15 05-Jun-15 MM1-1305-PT-30-X-XE-10002MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck Equipment Layout Plan59 26-Mar-15 05-Jun-15 MM1-1305-PT-30-X-XE-10002-1MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck Equipment Layout Plan-IDC13 26-Mar-15* 09-Apr-15 MM1-1305-PT-30-X-XE-10002-2MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck Equipment Layout Plan-IFR12 10-Apr-15 23-Apr-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 5 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 6. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-30-X-XE-10002-3MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck Equipment Layout Plan-IFD11 24-Apr-15 09-May-15 MM1-1305-PT-30-X-XE-10002-4MM1 - Hazardous Area Classification - Manifold &Pigging Facilities - Main Deck Equipment Layout Plan-IFC23 11-May-15 05-Jun-15 MM1-1305-PT-30-X-XB-10001MM1 - P&ID Firewater Deluge System 56 08-Apr-15 15-Jun-15 MM1-1305-PT-30-X-XB-10001-1MM1 - P&ID Firewater Deluge System-IDC 10 08-Apr-15* 18-Apr-15 MM1-1305-PT-30-X-XB-10001-2MM1 - P&ID Firewater Deluge System-IFR 11 20-Apr-15 05-May-15 MM1-1305-PT-30-X-XB-10001-3MM1 - P&ID Firewater Deluge System-IFD 15 06-May-15 22-May-15 MM1-1305-PT-30-X-XB-10001-4MM1 - P&ID Firewater Deluge System-IFC 20 23-May-15 15-Jun-15 0.D.26.0000.MM1.B.N Structural0.D.26.0000.MM1.B.N Structural 315 16-Mar-15 21-Mar-16 0.D.26.0000.MM1.B.N.92 PTSC0.D.26.0000.MM1.B.N.92 PTSC 315 16-Mar-15 21-Mar-16 MM1-1305-PT-95-N-RA-10001MM1 - In-place Analysis Report 82 16-Mar-15 22-Jun-15 MM1-1305-PT-95-N-RA-10001-1MM1 - In-place Analysis Report-IDC 0 16-Mar-15* 16-Mar-15 MM1-1305-PT-95-N-RA-10001-2MM1 - In-place Analysis Report-IFR 55 16-Mar-15 21-May-15 MM1-1305-PT-95-N-RA-10001-3MM1 - In-place Analysis Report-IFD 12 22-May-15 04-Jun-15 MM1-1305-PT-95-N-RA-10001-4MM1 - In-place Analysis Report-IFC 15 05-Jun-15 22-Jun-15 MM1-1305-PT-95-N-RA-10002MM1 - Preservice Analysis Report 85 16-Mar-15 25-Jun-15 MM1-1305-PT-95-N-RA-10002-1MM1 - Preservice Analysis Report-IDC 0 16-Mar-15* 16-Mar-15 MM1-1305-PT-95-N-RA-10002-2MM1 - Preservice Analysis Report-IFR 57 16-Mar-15 23-May-15 MM1-1305-PT-95-N-RA-10002-3MM1 - Preservice Analysis Report-IFD 12 25-May-15 06-Jun-15 MM1-1305-PT-95-N-RA-10002-4MM1 - Preservice Analysis Report-IFC 16 08-Jun-15 25-Jun-15 MM1-1305-PT-95-N-RA-10003MM1 - Structural Miscellaneous design 45 06-Jun-15 28-Jul-15 MM1-1305-PT-95-N-RA-10003-1MM1 - Structural Miscellaneous design-IDC 1 06-Jun-15* 06-Jun-15 MM1-1305-PT-95-N-RA-10003-2MM1 - Structural Miscellaneous design-IFR 17 08-Jun-15 26-Jun-15 MM1-1305-PT-95-N-RA-10003-3MM1 - Structural Miscellaneous design-IFD 12 27-Jun-15 10-Jul-15 MM1-1305-PT-95-N-RA-10003-4MM1 - Structural Miscellaneous design-IFC 15 11-Jul-15 28-Jul-15 MM1-1305-PT-95-N-RA-10005MM1 - Weight Control Report 74 28-Mar-15 25-Jun-15 MM1-1305-PT-95-N-RA-10005-1MM1 - Weight Control Report-IDC 33 28-Mar-15* 08-May-15 MM1-1305-PT-95-N-RA-10005-2MM1 - Weight Control Report-IFR 13 09-May-15 23-May-15 MM1-1305-PT-95-N-RA-10005-3MM1 - Weight Control Report-IFD 12 25-May-15 06-Jun-15 MM1-1305-PT-95-N-RA-10005-4MM1 - Weight Control Report-IFC 16 08-Jun-15 25-Jun-15 MM1-1305-PT-95-N-RA-10006MM1 - Seafastening Report 50 30-Jun-15 26-Aug-15 MM1-1305-PT-95-N-RA-10006-1MM1 - Seafastening Report-IDC 1 30-Jun-15* 30-Jun-15 MM1-1305-PT-95-N-RA-10006-2MM1 - Seafastening Report-IFR 16 01-Jul-15 18-Jul-15 MM1-1305-PT-95-N-RA-10006-3MM1 - Seafastening Report-IFD 12 20-Jul-15 01-Aug-15 MM1-1305-PT-95-N-RA-10006-4MM1 - Seafastening Report-IFC 21 03-Aug-15 26-Aug-15 MM1-1305-PT-95-N-LA-00001MM1 & MM2 - Structural Primary & secondary steel MTOs 61 16-Mar-15 28-May-15 MM1-1305-PT-95-N-LA-00001-1MM1 & MM2 - Structural Primary & secondary steel MTOs-IDC 0 16-Mar-15* 16-Mar-15 MM1-1305-PT-95-N-LA-00001-2MM1 & MM2 - Structural Primary & secondary steel MTOs-IFR 24 16-Mar-15 11-Apr-15 MM1-1305-PT-95-N-LA-00001-3MM1 & MM2 - Structural Primary & secondary steel MTOs-IFD 0 13-Apr-15 13-Apr-15 MM1-1305-PT-95-N-LA-00001-4MM1 & MM2 - Structural Primary & secondary steel MTOs-IFC 37 13-Apr-15 28-May-15 MM1-1305-PT-95-N-LA-00002MM1 & MM2 - Structural Tertiary Steel MTOs 67 04-May-15 20-Jul-15 MM1-1305-PT-95-N-LA-00002-1MM1 & MM2 - Structural Tertiary Steel MTOs-IDC 1 04-May-15* 04-May-15 MM1-1305-PT-95-N-LA-00002-2MM1 & MM2 - Structural Tertiary Steel MTOs-IFR 25 05-May-15 02-Jun-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 6 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 7. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-95-N-LA-00002-3MM1 & MM2 - Structural Tertiary Steel MTOs-IFD 0 03-Jun-15 03-Jun-15 MM1-1305-PT-95-N-LA-00002-4MM1 & MM2 - Structural Tertiary Steel MTOs-IFC 41 03-Jun-15 20-Jul-15 MM1-1305-PT-95-N-LA-00003MM1 & MM2 - Structural Miscellaneous MTOs 68 22-Jun-15 09-Sep-15 MM1-1305-PT-95-N-LA-00003-1MM1 & MM2 - Structural Miscellaneous MTOs-IDC 0 22-Jun-15* 22-Jun-15 MM1-1305-PT-95-N-LA-00003-2MM1 & MM2 - Structural Miscellaneous MTOs-IFR 24 22-Jun-15 18-Jul-15 MM1-1305-PT-95-N-LA-00003-3MM1 & MM2 - Structural Miscellaneous MTOs-IFD 0 20-Jul-15 20-Jul-15 MM1-1305-PT-95-N-LA-00003-4MM1 & MM2 - Structural Miscellaneous MTOs-IFC 44 20-Jul-15 09-Sep-15 MM1-1305-PT-95-N-LA-00004MM1 & MM2 - Structural Grating MTOs 71 23-Jun-15 14-Sep-15 MM1-1305-PT-95-N-LA-00004-1MM1 & MM2 - Structural Grating MTOs-IDC 1 23-Jun-15* 23-Jun-15 MM1-1305-PT-95-N-LA-00004-2MM1 & MM2 - Structural Grating MTOs-IFR 25 24-Jun-15 22-Jul-15 MM1-1305-PT-95-N-LA-00004-3MM1 & MM2 - Structural Grating MTOs-IFD 0 23-Jul-15 23-Jul-15 MM1-1305-PT-95-N-LA-00004-4MM1 & MM2 - Structural Grating MTOs-IFC 45 23-Jul-15 14-Sep-15 MM1-1305-PT-95-N-XG-01001MM1 & MM2 - Structural General Notes 47 24-Mar-15 20-May-15 MM1-1305-PT-95-N-XG-01001-1MM1 & MM2 - Structural General Notes-IDC 1 24-Mar-15* 24-Mar-15 MM1-1305-PT-95-N-XG-01001-2MM1 & MM2 - Structural General Notes-IFR 18 25-Mar-15 14-Apr-15 MM1-1305-PT-95-N-XG-01001-3MM1 & MM2 - Structural General Notes-IFD 11 15-Apr-15 27-Apr-15 MM1-1305-PT-95-N-XG-01001-4MM1 & MM2 - Structural General Notes-IFC 17 29-Apr-15 20-May-15 MM1-1305-PT-95-N-XG-01002MM1 & MM2 - Typical Weld Details 49 24-Mar-15 22-May-15 MM1-1305-PT-95-N-XG-01002-1MM1 & MM2 - Typical Weld Details-IDC 1 24-Mar-15* 24-Mar-15 MM1-1305-PT-95-N-XG-01002-2MM1 & MM2 - Typical Weld Details-IFR 20 25-Mar-15 16-Apr-15 MM1-1305-PT-95-N-XG-01002-3MM1 & MM2 - Typical Weld Details-IFD 10 17-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-01002-4MM1 & MM2 - Typical Weld Details-IFC 18 02-May-15 22-May-15 MM1-1305-PT-95-N-XG-01003MM1 & MM2 - Typical Connection Details 48 02-Apr-15 30-May-15 MM1-1305-PT-95-N-XG-01003-1MM1 & MM2 - Typical Connection Details-IDC 1 02-Apr-15* 02-Apr-15 MM1-1305-PT-95-N-XG-01003-2MM1 & MM2 - Typical Connection Details-IFR 20 03-Apr-15 25-Apr-15 MM1-1305-PT-95-N-XG-01003-3MM1 & MM2 - Typical Connection Details-IFD 9 27-Apr-15 09-May-15 MM1-1305-PT-95-N-XG-01003-4MM1 & MM2 - Typical Connection Details-IFC 18 11-May-15 30-May-15 MM1-1305-PT-95-N-XG-01004MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1 45 28-Mar-15 22-May-15 MM1-1305-PT-95-N-XG-01004-1MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IDC 1 28-Mar-15* 28-Mar-15 MM1-1305-PT-95-N-XG-01004-2MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFR 17 30-Mar-15 17-Apr-15 MM1-1305-PT-95-N-XG-01004-3MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFD 9 18-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-01004-4MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 1-IFC 18 02-May-15 22-May-15 MM1-1305-PT-95-N-XG-01005MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2 45 28-Mar-15 22-May-15 MM1-1305-PT-95-N-XG-01005-1MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IDC 1 28-Mar-15* 28-Mar-15 MM1-1305-PT-95-N-XG-01005-2MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFR 17 30-Mar-15 17-Apr-15 MM1-1305-PT-95-N-XG-01005-3MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFD 9 18-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-01005-4MM1 & MM2 - Typical Ladder Arrangement & Details - sheet 2-IFC 18 02-May-15 22-May-15 MM1-1305-PT-95-N-XG-01006MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1 45 28-Mar-15 22-May-15 MM1-1305-PT-95-N-XG-01006-1MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IDC 1 28-Mar-15* 28-Mar-15 MM1-1305-PT-95-N-XG-01006-2MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFR 17 30-Mar-15 17-Apr-15 MM1-1305-PT-95-N-XG-01006-3MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFD 9 18-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-01006-4MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 1-IFC 18 02-May-15 22-May-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 7 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 8. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-95-N-XG-01007MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2 45 28-Mar-15 22-May-15 MM1-1305-PT-95-N-XG-01007-1MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IDC 1 28-Mar-15* 28-Mar-15 MM1-1305-PT-95-N-XG-01007-2MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFR 17 30-Mar-15 17-Apr-15 MM1-1305-PT-95-N-XG-01007-3MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFD 9 18-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-01007-4MM1 & MM2 - Typical Stair Arrangement & Details - Sheet 2-IFC 18 02-May-15 22-May-15 MM1-1305-PT-95-N-XG-01008MM1 & MM2 - Typical Plating & Grating Arrangement & Details 45 28-Mar-15 22-May-15 MM1-1305-PT-95-N-XG-01008-1MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IDC 1 28-Mar-15* 28-Mar-15 MM1-1305-PT-95-N-XG-01008-2MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFR 17 30-Mar-15 17-Apr-15 MM1-1305-PT-95-N-XG-01008-3MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFD 9 18-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-01008-4MM1 & MM2 - Typical Plating & Grating Arrangement & Details-IFC 18 02-May-15 22-May-15 MM1-1305-PT-95-N-XG-01009MM1 & MM2 - Typical Handrail Arrangement & Details 45 28-Mar-15 22-May-15 MM1-1305-PT-95-N-XG-01009-1MM1 & MM2 - Typical Handrail Arrangement & Details-IDC 1 28-Mar-15* 28-Mar-15 MM1-1305-PT-95-N-XG-01009-2MM1 & MM2 - Typical Handrail Arrangement & Details-IFR 17 30-Mar-15 17-Apr-15 MM1-1305-PT-95-N-XG-01009-3MM1 & MM2 - Typical Handrail Arrangement & Details-IFD 9 18-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-01009-4MM1 & MM2 - Typical Handrail Arrangement & Details-IFC 18 02-May-15 22-May-15 MM1-1305-PT-95-N-XG-01010MM1 & MM2 - Typical Drain Outlet Details 45 28-Mar-15 22-May-15 MM1-1305-PT-95-N-XG-01010-1MM1 & MM2 - Typical Drain Outlet Details-IDC 1 28-Mar-15* 28-Mar-15 MM1-1305-PT-95-N-XG-01010-2MM1 & MM2 - Typical Drain Outlet Details-IFR 17 30-Mar-15 17-Apr-15 MM1-1305-PT-95-N-XG-01010-3MM1 & MM2 - Typical Drain Outlet Details-IFD 9 18-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-01010-4MM1 & MM2 - Typical Drain Outlet Details-IFC 18 02-May-15 22-May-15 MM1-1305-PT-95-N-XG-12001MM1 - Drawing Index 64 24-Mar-15 09-Jun-15 MM1-1305-PT-95-N-XG-12001-1MM1 - Drawing Index-IDC 1 24-Mar-15* 24-Mar-15 MM1-1305-PT-95-N-XG-12001-2MM1 - Drawing Index-IFR 27 25-Mar-15 24-Apr-15 MM1-1305-PT-95-N-XG-12001-3MM1 - Drawing Index-IFD 0 25-Apr-15 25-Apr-15 MM1-1305-PT-95-N-XG-12001-4MM1 - Drawing Index-IFC 36 25-Apr-15 09-Jun-15 MM1-1305-PT-95-N-XG-12002MM1 - Structural Perspective View 52 29-Apr-15 30-Jun-15 MM1-1305-PT-95-N-XG-12002-1MM1 - Structural Perspective View-IDC 0 29-Apr-15* 29-Apr-15 MM1-1305-PT-95-N-XG-12002-2MM1 - Structural Perspective View-IFR 24 29-Apr-15 28-May-15 MM1-1305-PT-95-N-XG-12002-3MM1 - Structural Perspective View-IFD 0 29-May-15 29-May-15 MM1-1305-PT-95-N-XG-12002-4MM1 - Structural Perspective View-IFC 28 29-May-15 30-Jun-15 MM1-1305-PT-95-N-XG-12003MM1 - Deck Load Plan 32 29-Apr-15 06-Jun-15 MM1-1305-PT-95-N-XG-12003-1MM1 - Deck Load Plan-IDC 0 29-Apr-15* 29-Apr-15 MM1-1305-PT-95-N-XG-12003-2MM1 - Deck Load Plan-IFR 20 29-Apr-15 23-May-15 MM1-1305-PT-95-N-XG-12003-3MM1 - Deck Load Plan-IFD 0 25-May-15 25-May-15 MM1-1305-PT-95-N-XG-12003-4MM1 - Deck Load Plan-IFC 12 25-May-15 06-Jun-15 MM1-1305-PT-95-N-XG-12004MM1 - Upper Deck Primary Framing Plan 36 02-Apr-15 16-May-15 MM1-1305-PT-95-N-XG-12004-1MM1 - Upper Deck Primary Framing Plan-IDC 19 02-Apr-15* 23-Apr-15 MM1-1305-PT-95-N-XG-12004-2MM1 - Upper Deck Primary Framing Plan-IFR 4 24-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-12004-3MM1 - Upper Deck Primary Framing Plan-IFD 0 02-May-15 02-May-15 MM1-1305-PT-95-N-XG-12004-4MM1 - Upper Deck Primary Framing Plan-IFC 13 02-May-15 16-May-15 MM1-1305-PT-95-N-XG-12005MM1 - Mezzanine Deck Primary Framing Plan 36 31-Mar-15 14-May-15 MM1-1305-PT-95-N-XG-12005-1MM1 - Mezzanine Deck Primary Framing Plan-IDC 19 31-Mar-15* 21-Apr-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 8 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 9. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-95-N-XG-12005-2MM1 - Mezzanine Deck Primary Framing Plan-IFR 5 22-Apr-15 27-Apr-15 MM1-1305-PT-95-N-XG-12005-3MM1 - Mezzanine Deck Primary Framing Plan-IFD 0 29-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-12005-4MM1 - Mezzanine Deck Primary Framing Plan-IFC 12 29-Apr-15 14-May-15 MM1-1305-PT-95-N-XG-12006MM1 - Main Deck Primary Framing Plan 36 28-Mar-15 12-May-15 MM1-1305-PT-95-N-XG-12006-1MM1 - Main Deck Primary Framing Plan-IDC 19 28-Mar-15* 18-Apr-15 MM1-1305-PT-95-N-XG-12006-2MM1 - Main Deck Primary Framing Plan-IFR 6 20-Apr-15 25-Apr-15 MM1-1305-PT-95-N-XG-12006-3MM1 - Main Deck Primary Framing Plan-IFD 0 27-Apr-15 27-Apr-15 MM1-1305-PT-95-N-XG-12006-4MM1 - Main Deck Primary Framing Plan-IFC 11 27-Apr-15 12-May-15 MM1-1305-PT-95-N-XG-12007MM1 - Truss Row 89 & Row 90 36 28-Mar-15 12-May-15 MM1-1305-PT-95-N-XG-12007-1MM1 - Truss Row 89 & Row 90-IDC 18 28-Mar-15* 17-Apr-15 MM1-1305-PT-95-N-XG-12007-2MM1 - Truss Row 89 & Row 90-IFR 6 18-Apr-15 24-Apr-15 MM1-1305-PT-95-N-XG-12007-3MM1 - Truss Row 89 & Row 90-IFD 0 25-Apr-15 25-Apr-15 MM1-1305-PT-95-N-XG-12007-4MM1 - Truss Row 89 & Row 90-IFC 12 25-Apr-15 12-May-15 MM1-1305-PT-95-N-XG-12008MM1 - Truss Row 91 & Row 92 36 28-Mar-15 12-May-15 MM1-1305-PT-95-N-XG-12008-1MM1 - Truss Row 91 & Row 92-IDC 19 28-Mar-15* 18-Apr-15 MM1-1305-PT-95-N-XG-12008-2MM1 - Truss Row 91 & Row 92-IFR 6 20-Apr-15 25-Apr-15 MM1-1305-PT-95-N-XG-12008-3MM1 - Truss Row 91 & Row 92-IFD 0 27-Apr-15 27-Apr-15 MM1-1305-PT-95-N-XG-12008-4MM1 - Truss Row 91 & Row 92-IFC 11 27-Apr-15 12-May-15 MM1-1305-PT-95-N-XG-12009MM1 - Truss Row 93 & Row 94 34 02-Apr-15 14-May-15 MM1-1305-PT-95-N-XG-12009-1MM1 - Truss Row 93 & Row 94-IDC 17 02-Apr-15* 21-Apr-15 MM1-1305-PT-95-N-XG-12009-2MM1 - Truss Row 93 & Row 94-IFR 6 22-Apr-15 29-Apr-15 MM1-1305-PT-95-N-XG-12009-3MM1 - Truss Row 93 & Row 94-IFD 0 02-May-15 02-May-15 MM1-1305-PT-95-N-XG-12009-4MM1 - Truss Row 93 & Row 94-IFC 11 02-May-15 14-May-15 MM1-1305-PT-95-N-XG-12010MM1 - Truss Row 1A 36 28-Mar-15 12-May-15 MM1-1305-PT-95-N-XG-12010-1MM1 - Truss Row 1A-IDC 18 28-Mar-15* 17-Apr-15 MM1-1305-PT-95-N-XG-12010-2MM1 - Truss Row 1A-IFR 6 18-Apr-15 24-Apr-15 MM1-1305-PT-95-N-XG-12010-3MM1 - Truss Row 1A-IFD 0 25-Apr-15 25-Apr-15 MM1-1305-PT-95-N-XG-12010-4MM1 - Truss Row 1A-IFC 12 25-Apr-15 12-May-15 MM1-1305-PT-95-N-XG-12011MM1 - Truss Row 1B 36 28-Mar-15 12-May-15 MM1-1305-PT-95-N-XG-12011-1MM1 - Truss Row 1B-IDC 18 28-Mar-15* 17-Apr-15 MM1-1305-PT-95-N-XG-12011-2MM1 - Truss Row 1B-IFR 7 18-Apr-15 25-Apr-15 MM1-1305-PT-95-N-XG-12011-3MM1 - Truss Row 1B-IFD 0 27-Apr-15 27-Apr-15 MM1-1305-PT-95-N-XG-12011-4MM1 - Truss Row 1B-IFC 11 27-Apr-15 12-May-15 MM1-1305-PT-95-N-XG-12012MM1 - Truss Row 1C 35 31-Mar-15 13-May-15 MM1-1305-PT-95-N-XG-12012-1MM1 - Truss Row 1C-IDC 17 31-Mar-15* 18-Apr-15 MM1-1305-PT-95-N-XG-12012-2MM1 - Truss Row 1C-IFR 6 20-Apr-15 25-Apr-15 MM1-1305-PT-95-N-XG-12012-3MM1 - Truss Row 1C-IFD 0 27-Apr-15 27-Apr-15 MM1-1305-PT-95-N-XG-12012-4MM1 - Truss Row 1C-IFC 12 27-Apr-15 13-May-15 MM1-1305-PT-95-N-XG-12013MM1 - Upper Deck Joint Details Sheet 1 27 17-Apr-15 21-May-15 MM1-1305-PT-95-N-XG-12013-1MM1 - Upper Deck Joint Details Sheet 1-IDC 1 17-Apr-15* 17-Apr-15 MM1-1305-PT-95-N-XG-12013-2MM1 - Upper Deck Joint Details Sheet 1-IFR 20 18-Apr-15 14-May-15 MM1-1305-PT-95-N-XG-12013-3MM1 - Upper Deck Joint Details Sheet 1-IFD 0 15-May-15 15-May-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 9 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 10. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-95-N-XG-12013-4MM1 - Upper Deck Joint Details Sheet 1-IFC 6 15-May-15 21-May-15 MM1-1305-PT-95-N-XG-12014MM1 - Upper Deck Joint Details Sheet 2 27 17-Apr-15 21-May-15 MM1-1305-PT-95-N-XG-12014-1MM1 - Upper Deck Joint Details Sheet 2-IDC 1 17-Apr-15* 17-Apr-15 MM1-1305-PT-95-N-XG-12014-2MM1 - Upper Deck Joint Details Sheet 2-IFR 20 18-Apr-15 14-May-15 MM1-1305-PT-95-N-XG-12014-3MM1 - Upper Deck Joint Details Sheet 2-IFD 0 15-May-15 15-May-15 MM1-1305-PT-95-N-XG-12014-4MM1 - Upper Deck Joint Details Sheet 2-IFC 6 15-May-15 21-May-15 MM1-1305-PT-95-N-XG-12015MM1 - Upper Deck Joint Details Sheet 3 31 17-Apr-15 26-May-15 MM1-1305-PT-95-N-XG-12015-1MM1 - Upper Deck Joint Details Sheet 3-IDC 1 17-Apr-15* 17-Apr-15 MM1-1305-PT-95-N-XG-12015-2MM1 - Upper Deck Joint Details Sheet 3-IFR 22 18-Apr-15 16-May-15 MM1-1305-PT-95-N-XG-12015-3MM1 - Upper Deck Joint Details Sheet 3-IFD 0 18-May-15 18-May-15 MM1-1305-PT-95-N-XG-12015-4MM1 - Upper Deck Joint Details Sheet 3-IFC 8 18-May-15 26-May-15 MM1-1305-PT-95-N-XG-12016MM1 - Upper Deck Joint Details sheet 4 31 17-Apr-15 26-May-15 MM1-1305-PT-95-N-XG-12016-1MM1 - Upper Deck Joint Details sheet 4-IDC 1 17-Apr-15* 17-Apr-15 MM1-1305-PT-95-N-XG-12016-2MM1 - Upper Deck Joint Details sheet 4-IFR 22 18-Apr-15 16-May-15 MM1-1305-PT-95-N-XG-12016-3MM1 - Upper Deck Joint Details sheet 4-IFD 0 18-May-15 18-May-15 MM1-1305-PT-95-N-XG-12016-4MM1 - Upper Deck Joint Details sheet 4-IFC 8 18-May-15 26-May-15 MM1-1305-PT-95-N-XG-12017MM1 - Upper Deck Joint Details sheet 5 31 17-Apr-15 26-May-15 MM1-1305-PT-95-N-XG-12017-1MM1 - Upper Deck Joint Details sheet 5-IDC 1 17-Apr-15* 17-Apr-15 MM1-1305-PT-95-N-XG-12017-2MM1 - Upper Deck Joint Details sheet 5-IFR 22 18-Apr-15 16-May-15 MM1-1305-PT-95-N-XG-12017-3MM1 - Upper Deck Joint Details sheet 5-IFD 0 18-May-15 18-May-15 MM1-1305-PT-95-N-XG-12017-4MM1 - Upper Deck Joint Details sheet 5-IFC 8 18-May-15 26-May-15 MM1-1305-PT-95-N-XG-12018MM1 - Mezzanine Deck Joint Details sheet 1 34 14-Apr-15 26-May-15 MM1-1305-PT-95-N-XG-12018-1MM1 - Mezzanine Deck Joint Details sheet 1-IDC 1 14-Apr-15* 14-Apr-15 MM1-1305-PT-95-N-XG-12018-2MM1 - Mezzanine Deck Joint Details sheet 1-IFR 22 15-Apr-15 13-May-15 MM1-1305-PT-95-N-XG-12018-3MM1 - Mezzanine Deck Joint Details sheet 1-IFD 0 14-May-15 14-May-15 MM1-1305-PT-95-N-XG-12018-4MM1 - Mezzanine Deck Joint Details sheet 1-IFC 11 14-May-15 26-May-15 MM1-1305-PT-95-N-XG-12019MM1 - Mezzanine Deck Joint Details sheet 2 34 14-Apr-15 26-May-15 MM1-1305-PT-95-N-XG-12019-1MM1 - Mezzanine Deck Joint Details sheet 2-IDC 1 14-Apr-15* 14-Apr-15 MM1-1305-PT-95-N-XG-12019-2MM1 - Mezzanine Deck Joint Details sheet 2-IFR 22 15-Apr-15 13-May-15 MM1-1305-PT-95-N-XG-12019-3MM1 - Mezzanine Deck Joint Details sheet 2-IFD 0 14-May-15 14-May-15 MM1-1305-PT-95-N-XG-12019-4MM1 - Mezzanine Deck Joint Details sheet 2-IFC 11 14-May-15 26-May-15 MM1-1305-PT-95-N-XG-12020MM1 - Mezzanine Deck Joint Details sheet 3 33 15-Apr-15 26-May-15 MM1-1305-PT-95-N-XG-12020-1MM1 - Mezzanine Deck Joint Details sheet 3-IDC 1 15-Apr-15* 15-Apr-15 MM1-1305-PT-95-N-XG-12020-2MM1 - Mezzanine Deck Joint Details sheet 3-IFR 24 16-Apr-15 16-May-15 MM1-1305-PT-95-N-XG-12020-3MM1 - Mezzanine Deck Joint Details sheet 3-IFD 0 18-May-15 18-May-15 MM1-1305-PT-95-N-XG-12020-4MM1 - Mezzanine Deck Joint Details sheet 3-IFC 8 18-May-15 26-May-15 MM1-1305-PT-95-N-XG-12021MM1 - Mezzanine Deck Joint Details sheet 4 33 15-Apr-15 26-May-15 MM1-1305-PT-95-N-XG-12021-1MM1 - Mezzanine Deck Joint Details sheet 4-IDC 1 15-Apr-15* 15-Apr-15 MM1-1305-PT-95-N-XG-12021-2MM1 - Mezzanine Deck Joint Details sheet 4-IFR 24 16-Apr-15 16-May-15 MM1-1305-PT-95-N-XG-12021-3MM1 - Mezzanine Deck Joint Details sheet 4-IFD 0 18-May-15 18-May-15 MM1-1305-PT-95-N-XG-12021-4MM1 - Mezzanine Deck Joint Details sheet 4-IFC 8 18-May-15 26-May-15 MM1-1305-PT-95-N-XG-12022MM1 - Mezzanine Deck Joint Details sheet 5 33 15-Apr-15 26-May-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 10 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 11. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-95-N-XG-12022-1MM1 - Mezzanine Deck Joint Details sheet 5-IDC 1 15-Apr-15* 15-Apr-15 MM1-1305-PT-95-N-XG-12022-2MM1 - Mezzanine Deck Joint Details sheet 5-IFR 24 16-Apr-15 16-May-15 MM1-1305-PT-95-N-XG-12022-3MM1 - Mezzanine Deck Joint Details sheet 5-IFD 0 18-May-15 18-May-15 MM1-1305-PT-95-N-XG-12022-4MM1 - Mezzanine Deck Joint Details sheet 5-IFC 8 18-May-15 26-May-15 MM1-1305-PT-95-N-XG-12023MM1 - Main Deck Joint Details Sheet 1 34 14-Apr-15 26-May-15 MM1-1305-PT-95-N-XG-12023-1MM1 - Main Deck Joint Details Sheet 1-IDC 1 14-Apr-15* 14-Apr-15 MM1-1305-PT-95-N-XG-12023-2MM1 - Main Deck Joint Details Sheet 1-IFR 19 15-Apr-15 09-May-15 MM1-1305-PT-95-N-XG-12023-3MM1 - Main Deck Joint Details Sheet 1-IFD 0 11-May-15 11-May-15 MM1-1305-PT-95-N-XG-12023-4MM1 - Main Deck Joint Details Sheet 1-IFC 14 11-May-15 26-May-15 MM1-1305-PT-95-N-XG-12024MM1 - Main Deck Joint Details Sheet 2 34 14-Apr-15 26-May-15 MM1-1305-PT-95-N-XG-12024-1MM1 - Main Deck Joint Details Sheet 2-IDC 1 14-Apr-15* 14-Apr-15 MM1-1305-PT-95-N-XG-12024-2MM1 - Main Deck Joint Details Sheet 2-IFR 19 15-Apr-15 09-May-15 MM1-1305-PT-95-N-XG-12024-3MM1 - Main Deck Joint Details Sheet 2-IFD 0 11-May-15 11-May-15 MM1-1305-PT-95-N-XG-12024-4MM1 - Main Deck Joint Details Sheet 2-IFC 14 11-May-15 26-May-15 MM1-1305-PT-95-N-XG-12025MM1 - Main Deck Joint Details Sheet 3 37 14-Apr-15 29-May-15 MM1-1305-PT-95-N-XG-12025-1MM1 - Main Deck Joint Details Sheet 3-IDC 1 14-Apr-15* 14-Apr-15 MM1-1305-PT-95-N-XG-12025-2MM1 - Main Deck Joint Details Sheet 3-IFR 21 15-Apr-15 12-May-15 MM1-1305-PT-95-N-XG-12025-3MM1 - Main Deck Joint Details Sheet 3-IFD 0 13-May-15 13-May-15 MM1-1305-PT-95-N-XG-12025-4MM1 - Main Deck Joint Details Sheet 3-IFC 15 13-May-15 29-May-15 MM1-1305-PT-95-N-XG-12026MM1 - Main Deck Joint Details Sheet 4 37 14-Apr-15 29-May-15 MM1-1305-PT-95-N-XG-12026-1MM1 - Main Deck Joint Details Sheet 4-IDC 1 14-Apr-15* 14-Apr-15 MM1-1305-PT-95-N-XG-12026-2MM1 - Main Deck Joint Details Sheet 4-IFR 21 15-Apr-15 12-May-15 MM1-1305-PT-95-N-XG-12026-3MM1 - Main Deck Joint Details Sheet 4-IFD 0 13-May-15 13-May-15 MM1-1305-PT-95-N-XG-12026-4MM1 - Main Deck Joint Details Sheet 4-IFC 15 13-May-15 29-May-15 MM1-1305-PT-95-N-XG-12027MM1 - Main Deck Joint Details Sheet 5 37 14-Apr-15 29-May-15 MM1-1305-PT-95-N-XG-12027-1MM1 - Main Deck Joint Details Sheet 5-IDC 1 14-Apr-15* 14-Apr-15 MM1-1305-PT-95-N-XG-12027-2MM1 - Main Deck Joint Details Sheet 5-IFR 21 15-Apr-15 12-May-15 MM1-1305-PT-95-N-XG-12027-3MM1 - Main Deck Joint Details Sheet 5-IFD 0 13-May-15 13-May-15 MM1-1305-PT-95-N-XG-12027-4MM1 - Main Deck Joint Details Sheet 5-IFC 15 13-May-15 29-May-15 MM1-1305-PT-95-N-XG-12028MM1 - Upper Deck Secondary Framing Plan 29 20-Apr-15 26-May-15 MM1-1305-PT-95-N-XG-12028-1MM1 - Upper Deck Secondary Framing Plan-IDC 15 20-Apr-15* 09-May-15 MM1-1305-PT-95-N-XG-12028-2MM1 - Upper Deck Secondary Framing Plan-IFR 6 11-May-15 16-May-15 MM1-1305-PT-95-N-XG-12028-3MM1 - Upper Deck Secondary Framing Plan-IFD 0 18-May-15 18-May-15 MM1-1305-PT-95-N-XG-12028-4MM1 - Upper Deck Secondary Framing Plan-IFC 8 18-May-15 26-May-15 MM1-1305-PT-95-N-XG-12029MM1 - Mezzanine Deck Secondary Framing Plan 28 18-Apr-15 23-May-15 MM1-1305-PT-95-N-XG-12029-1MM1 - Mezzanine Deck Secondary Framing Plan-IDC 15 18-Apr-15* 08-May-15 MM1-1305-PT-95-N-XG-12029-2MM1 - Mezzanine Deck Secondary Framing Plan-IFR 6 09-May-15 15-May-15 MM1-1305-PT-95-N-XG-12029-3MM1 - Mezzanine Deck Secondary Framing Plan-IFD 0 16-May-15 16-May-15 MM1-1305-PT-95-N-XG-12029-4MM1 - Mezzanine Deck Secondary Framing Plan-IFC 7 16-May-15 23-May-15 MM1-1305-PT-95-N-XG-12030MM1 - Main Deck Secondary Framing plan 28 18-Apr-15 23-May-15 MM1-1305-PT-95-N-XG-12030-1MM1 - Main Deck Secondary Framing plan-IDC 15 18-Apr-15* 08-May-15 MM1-1305-PT-95-N-XG-12030-2MM1 - Main Deck Secondary Framing plan-IFR 6 09-May-15 15-May-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 11 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 12. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-95-N-XG-12030-3MM1 - Main Deck Secondary Framing plan-IFD 0 16-May-15 16-May-15 MM1-1305-PT-95-N-XG-12030-4MM1 - Main Deck Secondary Framing plan-IFC 7 16-May-15 23-May-15 MM1-1305-PT-95-N-XG-12031MM1 - Upper Deck Flooring & Handrail Layout 52 23-Apr-15 25-Jun-15 MM1-1305-PT-95-N-XG-12031-1MM1 - Upper Deck Flooring & Handrail Layout-IDC 34 23-Apr-15* 04-Jun-15 MM1-1305-PT-95-N-XG-12031-2MM1 - Upper Deck Flooring & Handrail Layout-IFR 6 05-Jun-15 11-Jun-15 MM1-1305-PT-95-N-XG-12031-3MM1 - Upper Deck Flooring & Handrail Layout-IFD 0 12-Jun-15 12-Jun-15 MM1-1305-PT-95-N-XG-12031-4MM1 - Upper Deck Flooring & Handrail Layout-IFC 12 12-Jun-15 25-Jun-15 MM1-1305-PT-95-N-XG-12032MM1 - Mezzanine Deck Flooring & Handrail Layout 53 23-Apr-15 26-Jun-15 MM1-1305-PT-95-N-XG-12032-1MM1 - Mezzanine Deck Flooring & Handrail Layout-IDC 35 23-Apr-15* 05-Jun-15 MM1-1305-PT-95-N-XG-12032-2MM1 - Mezzanine Deck Flooring & Handrail Layout-IFR 6 06-Jun-15 12-Jun-15 MM1-1305-PT-95-N-XG-12032-3MM1 - Mezzanine Deck Flooring & Handrail Layout-IFD 0 13-Jun-15 13-Jun-15 MM1-1305-PT-95-N-XG-12032-4MM1 - Mezzanine Deck Flooring & Handrail Layout-IFC 12 13-Jun-15 26-Jun-15 MM1-1305-PT-95-N-XG-12033MM1 - Main Deck Flooring & Handrail Layout 54 23-Apr-15 27-Jun-15 MM1-1305-PT-95-N-XG-12033-1MM1 - Main Deck Flooring & Handrail Layout-IDC 36 23-Apr-15* 06-Jun-15 MM1-1305-PT-95-N-XG-12033-2MM1 - Main Deck Flooring & Handrail Layout-IFR 6 08-Jun-15 13-Jun-15 MM1-1305-PT-95-N-XG-12033-3MM1 - Main Deck Flooring & Handrail Layout-IFD 0 15-Jun-15 15-Jun-15 MM1-1305-PT-95-N-XG-12033-4MM1 - Main Deck Flooring & Handrail Layout-IFC 12 15-Jun-15 27-Jun-15 MM1-1305-PT-95-N-XG-12034MM1 - Upper Deck Penetration Layout 52 23-Apr-15 25-Jun-15 MM1-1305-PT-95-N-XG-12034-1MM1 - Upper Deck Penetration Layout-IDC 34 23-Apr-15* 04-Jun-15 MM1-1305-PT-95-N-XG-12034-2MM1 - Upper Deck Penetration Layout-IFR 6 05-Jun-15 11-Jun-15 MM1-1305-PT-95-N-XG-12034-3MM1 - Upper Deck Penetration Layout-IFD 0 12-Jun-15 12-Jun-15 MM1-1305-PT-95-N-XG-12034-4MM1 - Upper Deck Penetration Layout-IFC 12 12-Jun-15 25-Jun-15 MM1-1305-PT-95-N-XG-12035MM1 - Mezzanine Deck Penetration Layout 52 23-Apr-15 25-Jun-15 MM1-1305-PT-95-N-XG-12035-1MM1 - Mezzanine Deck Penetration Layout-IDC 34 23-Apr-15* 04-Jun-15 MM1-1305-PT-95-N-XG-12035-2MM1 - Mezzanine Deck Penetration Layout-IFR 6 05-Jun-15 11-Jun-15 MM1-1305-PT-95-N-XG-12035-3MM1 - Mezzanine Deck Penetration Layout-IFD 0 12-Jun-15 12-Jun-15 MM1-1305-PT-95-N-XG-12035-4MM1 - Mezzanine Deck Penetration Layout-IFC 12 12-Jun-15 25-Jun-15 MM1-1305-PT-95-N-XG-12036MM1 - Main Deck Penetration Layout 51 27-Apr-15 27-Jun-15 MM1-1305-PT-95-N-XG-12036-1MM1 - Main Deck Penetration Layout-IDC 33 27-Apr-15* 06-Jun-15 MM1-1305-PT-95-N-XG-12036-2MM1 - Main Deck Penetration Layout-IFR 6 08-Jun-15 13-Jun-15 MM1-1305-PT-95-N-XG-12036-3MM1 - Main Deck Penetration Layout-IFD 0 15-Jun-15 15-Jun-15 MM1-1305-PT-95-N-XG-12036-4MM1 - Main Deck Penetration Layout-IFC 12 15-Jun-15 27-Jun-15 MM1-1305-PT-95-N-XG-12037MM1 - Lifting Padeye Arrangement & Details Sheet 1 47 29-Apr-15 24-Jun-15 MM1-1305-PT-95-N-XG-12037-1MM1 - Lifting Padeye Arrangement & Details Sheet 1-IDC 0 29-Apr-15* 29-Apr-15 MM1-1305-PT-95-N-XG-12037-2MM1 - Lifting Padeye Arrangement & Details Sheet 1-IFR 31 29-Apr-15 05-Jun-15 MM1-1305-PT-95-N-XG-12037-3MM1 - Lifting Padeye Arrangement & Details Sheet 1-IFD 0 06-Jun-15 06-Jun-15 MM1-1305-PT-95-N-XG-12037-4MM1 - Lifting Padeye Arrangement & Details Sheet 1-IFC 16 06-Jun-15 24-Jun-15 MM1-1305-PT-95-N-XG-12038MM1 - Lifting Padeye Arrangement & Details Sheet 2 47 29-Apr-15 24-Jun-15 MM1-1305-PT-95-N-XG-12038-1MM1 - Lifting Padeye Arrangement & Details Sheet 2-IDC 0 29-Apr-15* 29-Apr-15 MM1-1305-PT-95-N-XG-12038-2MM1 - Lifting Padeye Arrangement & Details Sheet 2-IFR 31 29-Apr-15 05-Jun-15 MM1-1305-PT-95-N-XG-12038-3MM1 - Lifting Padeye Arrangement & Details Sheet 2-IFD 0 06-Jun-15 06-Jun-15 MM1-1305-PT-95-N-XG-12038-4MM1 - Lifting Padeye Arrangement & Details Sheet 2-IFC 16 06-Jun-15 24-Jun-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 12 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 13. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-95-N-XG-12039MM1 - Stair Arrangement & Details Sheet 1 50 29-Apr-15 27-Jun-15 MM1-1305-PT-95-N-XG-12039-1MM1 - Stair Arrangement & Details Sheet 1-IDC 32 29-Apr-15* 06-Jun-15 MM1-1305-PT-95-N-XG-12039-2MM1 - Stair Arrangement & Details Sheet 1-IFR 6 08-Jun-15 13-Jun-15 MM1-1305-PT-95-N-XG-12039-3MM1 - Stair Arrangement & Details Sheet 1-IFD 0 15-Jun-15 15-Jun-15 MM1-1305-PT-95-N-XG-12039-4MM1 - Stair Arrangement & Details Sheet 1-IFC 12 15-Jun-15 27-Jun-15 MM1-1305-PT-95-N-XG-12040MM1 - Stair Arrangement & Details Sheet 2 50 29-Apr-15 27-Jun-15 MM1-1305-PT-95-N-XG-12040-1MM1 - Stair Arrangement & Details Sheet 2-IDC 32 29-Apr-15* 06-Jun-15 MM1-1305-PT-95-N-XG-12040-2MM1 - Stair Arrangement & Details Sheet 2-IFR 6 08-Jun-15 13-Jun-15 MM1-1305-PT-95-N-XG-12040-3MM1 - Stair Arrangement & Details Sheet 2-IFD 0 15-Jun-15 15-Jun-15 MM1-1305-PT-95-N-XG-12040-4MM1 - Stair Arrangement & Details Sheet 2-IFC 12 15-Jun-15 27-Jun-15 MM1-1305-PT-95-N-XG-12041MM1 - Ladder Arrangement & Details Sheet 1 50 29-Apr-15 27-Jun-15 MM1-1305-PT-95-N-XG-12041-1MM1 - Ladder Arrangement & Details Sheet 1-IDC 32 29-Apr-15* 06-Jun-15 MM1-1305-PT-95-N-XG-12041-2MM1 - Ladder Arrangement & Details Sheet 1-IFR 6 08-Jun-15 13-Jun-15 MM1-1305-PT-95-N-XG-12041-3MM1 - Ladder Arrangement & Details Sheet 1-IFD 0 15-Jun-15 15-Jun-15 MM1-1305-PT-95-N-XG-12041-4MM1 - Ladder Arrangement & Details Sheet 1-IFC 12 15-Jun-15 27-Jun-15 MM1-1305-PT-95-N-XG-12042MM1 - Ladder Arrangement & Details Sheet 2 50 29-Apr-15 27-Jun-15 MM1-1305-PT-95-N-XG-12042-1MM1 - Ladder Arrangement & Details Sheet 2-IDC 32 29-Apr-15* 06-Jun-15 MM1-1305-PT-95-N-XG-12042-2MM1 - Ladder Arrangement & Details Sheet 2-IFR 6 08-Jun-15 13-Jun-15 MM1-1305-PT-95-N-XG-12042-3MM1 - Ladder Arrangement & Details Sheet 2-IFD 0 15-Jun-15 15-Jun-15 MM1-1305-PT-95-N-XG-12042-4MM1 - Ladder Arrangement & Details Sheet 2-IFC 12 15-Jun-15 27-Jun-15 MM1-1305-PT-95-N-XG-12043MM1 - Mechanical Handling For Main Deck Equipment - sheet 1 29 01-Jun-15 03-Jul-15 MM1-1305-PT-95-N-XG-12043-1MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IDC 11 01-Jun-15* 12-Jun-15 MM1-1305-PT-95-N-XG-12043-2MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IFR 6 13-Jun-15 19-Jun-15 MM1-1305-PT-95-N-XG-12043-3MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IFD 0 20-Jun-15 20-Jun-15 MM1-1305-PT-95-N-XG-12043-4MM1 - Mechanical Handling For Main Deck Equipment - sheet 1-IFC 12 20-Jun-15 03-Jul-15 MM1-1305-PT-95-N-XG-12044MM1 - Mechanical Handling For Main Deck Equipment - sheet 2 29 01-Jun-15 03-Jul-15 MM1-1305-PT-95-N-XG-12044-1MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IDC 11 01-Jun-15* 12-Jun-15 MM1-1305-PT-95-N-XG-12044-2MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IFR 6 13-Jun-15 19-Jun-15 MM1-1305-PT-95-N-XG-12044-3MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IFD 0 20-Jun-15 20-Jun-15 MM1-1305-PT-95-N-XG-12044-4MM1 - Mechanical Handling For Main Deck Equipment - sheet 2-IFC 12 20-Jun-15 03-Jul-15 MM1-1305-PT-95-N-XG-12045MM1 - Mechanical Handling For Main Deck Equipment - sheet 3 29 01-Jun-15 03-Jul-15 MM1-1305-PT-95-N-XG-12045-1MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IDC 11 01-Jun-15* 12-Jun-15 MM1-1305-PT-95-N-XG-12045-2MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IFR 6 13-Jun-15 19-Jun-15 MM1-1305-PT-95-N-XG-12045-3MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IFD 0 20-Jun-15 20-Jun-15 MM1-1305-PT-95-N-XG-12045-4MM1 - Mechanical Handling For Main Deck Equipment - sheet 3-IFC 12 20-Jun-15 03-Jul-15 MM1-1305-PT-95-N-XG-12046MM1 - Mechanical Handling For Main Deck Equipment - sheet 4 29 01-Jun-15 03-Jul-15 MM1-1305-PT-95-N-XG-12046-1MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IDC 11 01-Jun-15* 12-Jun-15 MM1-1305-PT-95-N-XG-12046-2MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IFR 6 13-Jun-15 19-Jun-15 MM1-1305-PT-95-N-XG-12046-3MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IFD 0 20-Jun-15 20-Jun-15 MM1-1305-PT-95-N-XG-12046-4MM1 - Mechanical Handling For Main Deck Equipment - sheet 4-IFC 12 20-Jun-15 03-Jul-15 MM1-1305-PT-95-N-XG-12047MM1 - Mechanical Handling For Main Deck Equipment - sheet 5 29 01-Jun-15 03-Jul-15 MM1-1305-PT-95-N-XG-12047-1MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IDC 11 01-Jun-15* 12-Jun-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 13 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 14. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-95-N-XG-12047-2MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IFR 6 13-Jun-15 19-Jun-15 MM1-1305-PT-95-N-XG-12047-3MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IFD 0 20-Jun-15 20-Jun-15 MM1-1305-PT-95-N-XG-12047-4MM1 - Mechanical Handling For Main Deck Equipment - sheet 5-IFC 12 20-Jun-15 03-Jul-15 MM1-1305-PT-95-N-XG-12048MM1 - Equipment Support- Sheet 1 29 16-Jun-15 18-Jul-15 MM1-1305-PT-95-N-XG-12048-1MM1 - Equipment Support- Sheet 1-IDC 11 16-Jun-15* 27-Jun-15 MM1-1305-PT-95-N-XG-12048-2MM1 - Equipment Support- Sheet 1-IFR 6 29-Jun-15 04-Jul-15 MM1-1305-PT-95-N-XG-12048-3MM1 - Equipment Support- Sheet 1-IFD 0 06-Jul-15 06-Jul-15 MM1-1305-PT-95-N-XG-12048-4MM1 - Equipment Support- Sheet 1-IFC 12 06-Jul-15 18-Jul-15 MM1-1305-PT-95-N-XG-12049MM1 - Equipment Support- Sheet 2 29 16-Jun-15 18-Jul-15 MM1-1305-PT-95-N-XG-12049-1MM1 - Equipment Support- Sheet 2-IDC 11 16-Jun-15* 27-Jun-15 MM1-1305-PT-95-N-XG-12049-2MM1 - Equipment Support- Sheet 2-IFR 6 29-Jun-15 04-Jul-15 MM1-1305-PT-95-N-XG-12049-3MM1 - Equipment Support- Sheet 2-IFD 0 06-Jul-15 06-Jul-15 MM1-1305-PT-95-N-XG-12049-4MM1 - Equipment Support- Sheet 2-IFC 12 06-Jul-15 18-Jul-15 MM1-1305-PT-95-N-XG-12050MM1 - Equipment Support- Sheet 3 29 16-Jun-15 18-Jul-15 MM1-1305-PT-95-N-XG-12050-1MM1 - Equipment Support- Sheet 3-IDC 11 16-Jun-15* 27-Jun-15 MM1-1305-PT-95-N-XG-12050-2MM1 - Equipment Support- Sheet 3-IFR 6 29-Jun-15 04-Jul-15 MM1-1305-PT-95-N-XG-12050-3MM1 - Equipment Support- Sheet 3-IFD 0 06-Jul-15 06-Jul-15 MM1-1305-PT-95-N-XG-12050-4MM1 - Equipment Support- Sheet 3-IFC 12 06-Jul-15 18-Jul-15 MM1-1305-PT-95-N-XG-12051MM1 - Seafastening On Barge Arrangment & Details - Sheet 1 30 29-Jun-15 01-Aug-15 MM1-1305-PT-95-N-XG-12051-1MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IDC 0 29-Jun-15* 29-Jun-15 MM1-1305-PT-95-N-XG-12051-2MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IFR 18 29-Jun-15 18-Jul-15 MM1-1305-PT-95-N-XG-12051-3MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IFD 0 20-Jul-15 20-Jul-15 MM1-1305-PT-95-N-XG-12051-4MM1 - Seafastening On Barge Arrangment & Details - Sheet 1-IFC 12 20-Jul-15 01-Aug-15 MM1-1305-PT-95-N-XG-12052MM1 - Seafastening On Barge Arrangment & Details - Sheet 2 30 29-Jun-15 01-Aug-15 MM1-1305-PT-95-N-XG-12052-1MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IDC 0 29-Jun-15* 29-Jun-15 MM1-1305-PT-95-N-XG-12052-2MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IFR 18 29-Jun-15 18-Jul-15 MM1-1305-PT-95-N-XG-12052-3MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IFD 0 20-Jul-15 20-Jul-15 MM1-1305-PT-95-N-XG-12052-4MM1 - Seafastening On Barge Arrangment & Details - Sheet 2-IFC 12 20-Jul-15 01-Aug-15 MM1-1305-PT-95-N-XG-12053MM1 - Seafastening On Barge Arrangment & Details - Sheet 3 30 29-Jun-15 01-Aug-15 MM1-1305-PT-95-N-XG-12053-1MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IDC 0 29-Jun-15* 29-Jun-15 MM1-1305-PT-95-N-XG-12053-2MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IFR 18 29-Jun-15 18-Jul-15 MM1-1305-PT-95-N-XG-12053-3MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IFD 0 20-Jul-15 20-Jul-15 MM1-1305-PT-95-N-XG-12053-4MM1 - Seafastening On Barge Arrangment & Details - Sheet 3-IFC 12 20-Jul-15 01-Aug-15 MM1-10150 TR/MTO for Primary & Secondary Steel 1 07-Apr-15 07-Apr-15 MM1-10170 TR/MTO for Tertiary Steel 1 09-Jun-15 09-Jun-15 MM1-10190 TR/MTO for Structural Miscellaneous 1 28-Jul-15 28-Jul-15 MM1-10210 TR/MTO for Gratings (including Hilti clip and cartridge) 1 09-Aug-15 09-Aug-15 MM1-1000 TR/MTO for SF and Grillage Material 1 10-Oct-15 10-Oct-15 MM1-1100 Prepare / Submit/ Approve Structural Shop Drawings 185 11-Aug-15 21-Mar-16 0.D.26.0000.MM1.B.L Piping0.D.26.0000.MM1.B.L Piping 312 14-Mar-15 16-Mar-16 0.D.26.0000.MM1.B.L.92 PTSC0.D.26.0000.MM1.B.L.92 PTSC 312 14-Mar-15 16-Mar-16 MM1-1305-PT-00-L-CA-00001MM1 & MM2 - Stress Analysis Report 50 01-Jun-15 28-Jul-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 14 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 15. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-00-L-CA-00001-1MM1 & MM2 - Stress Analysis Report-IDC 20 01-Jun-15* 23-Jun-15 MM1-1305-PT-00-L-CA-00001-2MM1 & MM2 - Stress Analysis Report-IFR 6 24-Jun-15 30-Jun-15 MM1-1305-PT-00-L-CA-00001-3MM1 & MM2 - Stress Analysis Report-IFD 12 01-Jul-15 14-Jul-15 MM1-1305-PT-00-L-CA-00001-4MM1 & MM2 - Stress Analysis Report-IFC 12 15-Jul-15 28-Jul-15 MM1-1305-PT-00-L-LA-00001MM1 & MM2 - Special Piping Item List 47 12-May-15 04-Jul-15 MM1-1305-PT-00-L-LA-00001-1MM1 & MM2 - Special Piping Item List-IDC 7 12-May-15* 19-May-15 MM1-1305-PT-00-L-LA-00001-2MM1 & MM2 - Special Piping Item List-IFR 4 20-May-15 23-May-15 MM1-1305-PT-00-L-LA-00001-3MM1 & MM2 - Special Piping Item List-IFD 12 25-May-15 06-Jun-15 MM1-1305-PT-00-L-LA-00001-4MM1 & MM2 - Special Piping Item List-IFC 24 08-Jun-15 04-Jul-15 MM1-1305-PT-00-L-LA-00002MM1 & MM2 - TIE-IN Schedule 56 26-May-15 29-Jul-15 MM1-1305-PT-00-L-LA-00002-1MM1 & MM2 - TIE-IN Schedule-IDC 25 26-May-15* 23-Jun-15 MM1-1305-PT-00-L-LA-00002-2MM1 & MM2 - TIE-IN Schedule-IFR 7 24-Jun-15 01-Jul-15 MM1-1305-PT-00-L-LA-00002-3MM1 & MM2 - TIE-IN Schedule-IFD 12 02-Jul-15 15-Jul-15 MM1-1305-PT-00-L-LA-00002-4MM1 & MM2 - TIE-IN Schedule-IFC 12 16-Jul-15 29-Jul-15 MM1-1305-PT-00-L-LA-00003MM1 & MM2 - Manual valve list 49 17-Apr-15 16-Jun-15 MM1-1305-PT-00-L-LA-00003-1MM1 & MM2 - Manual valve list-IDC 7 17-Apr-15* 24-Apr-15 MM1-1305-PT-00-L-LA-00003-2MM1 & MM2 - Manual valve list-IFR 2 25-Apr-15 27-Apr-15 MM1-1305-PT-00-L-LA-00003-3MM1 & MM2 - Manual valve list-IFD 10 29-Apr-15 12-May-15 MM1-1305-PT-00-L-LA-00003-4MM1 & MM2 - Manual valve list-IFC 30 13-May-15 16-Jun-15 MM1-1305-PT-00-L-SA-00001MM1 & MM2 - Addional piping class 46 14-Mar-15 09-May-15 MM1-1305-PT-00-L-SA-00001-1MM1 & MM2 - Addional piping class -IDC 1 14-Mar-15* 14-Mar-15 MM1-1305-PT-00-L-SA-00001-2MM1 & MM2 - Addional piping class -IFR 24 16-Mar-15 11-Apr-15 MM1-1305-PT-00-L-SA-00001-3MM1 & MM2 - Addional piping class -IFD 12 13-Apr-15 25-Apr-15 MM1-1305-PT-00-L-SA-00001-4MM1 & MM2 - Addional piping class -IFC 9 27-Apr-15 09-May-15 MM1-1305-PT-00-L-SA-00002MM1 & MM2 - Pipe support standard 46 06-Apr-15 01-Jun-15 MM1-1305-PT-00-L-SA-00002-1MM1 & MM2 - Pipe support standard -IDC 1 06-Apr-15* 06-Apr-15 MM1-1305-PT-00-L-SA-00002-2MM1 & MM2 - Pipe support standard -IFR 21 07-Apr-15 04-May-15 MM1-1305-PT-00-L-SA-00002-3MM1 & MM2 - Pipe support standard -IFD 12 05-May-15 18-May-15 MM1-1305-PT-00-L-SA-00002-4MM1 & MM2 - Pipe support standard -IFC 12 19-May-15 01-Jun-15 MM1-1305-PT-00-L-DS-00001MM1 & MM2 - Ball valve Data sheets 34 03-Apr-15 15-May-15 MM1-1305-PT-00-L-DS-00001-1MM1 & MM2 - Ball valve Data sheets-IDC 1 03-Apr-15* 03-Apr-15 MM1-1305-PT-00-L-DS-00001-2MM1 & MM2 - Ball valve Data sheets-IFR 12 04-Apr-15 17-Apr-15 MM1-1305-PT-00-L-DS-00001-3MM1 & MM2 - Ball valve Data sheets-IFD 9 18-Apr-15 29-Apr-15 MM1-1305-PT-00-L-DS-00001-4MM1 & MM2 - Ball valve Data sheets-IFC 12 02-May-15 15-May-15 MM1-1305-PT-00-L-DS-00002MM1 & MM2 - Globe Valve Data sheets 33 06-Apr-15 16-May-15 MM1-1305-PT-00-L-DS-00002-1MM1 & MM2 - Globe Valve Data sheets-IDC 0 06-Apr-15* 06-Apr-15 MM1-1305-PT-00-L-DS-00002-2MM1 & MM2 - Globe Valve Data sheets-IFR 12 06-Apr-15 18-Apr-15 MM1-1305-PT-00-L-DS-00002-3MM1 & MM2 - Globe Valve Data sheets-IFD 9 20-Apr-15 02-May-15 MM1-1305-PT-00-L-DS-00002-4MM1 & MM2 - Globe Valve Data sheets-IFC 12 04-May-15 16-May-15 MM1-1305-PT-00-L-DS-00003MM1 & MM2 - Check Data sheets 34 07-Apr-15 19-May-15 MM1-1305-PT-00-L-DS-00003-1MM1 & MM2 - Check Data sheets-IDC 1 07-Apr-15* 07-Apr-15 MM1-1305-PT-00-L-DS-00003-2MM1 & MM2 - Check Data sheets-IFR 12 08-Apr-15 21-Apr-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 15 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 16. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-00-L-DS-00003-3MM1 & MM2 - Check Data sheets-IFD 9 22-Apr-15 05-May-15 MM1-1305-PT-00-L-DS-00003-4MM1 & MM2 - Check Data sheets-IFC 12 06-May-15 19-May-15 MM1-1305-PT-00-L-DS-00004MM1 & MM2 - DBB valve sheets 58 10-Apr-15 19-Jun-15 MM1-1305-PT-00-L-DS-00004-1MM1 & MM2 - DBB valve sheets-IDC 1 10-Apr-15* 10-Apr-15 MM1-1305-PT-00-L-DS-00004-2MM1 & MM2 - DBB valve sheets-IFR 12 11-Apr-15 24-Apr-15 MM1-1305-PT-00-L-DS-00004-3MM1 & MM2 - DBB valve sheets-IFD 9 25-Apr-15 08-May-15 MM1-1305-PT-00-L-DS-00004-4MM1 & MM2 - DBB valve sheets-IFC 36 09-May-15 19-Jun-15 MM1-1305-PT-00-L-DS-00005MM1 & MM2 - SP Item Data Sheet -Valve Interlock 61 12-May-15 21-Jul-15 MM1-1305-PT-00-L-DS-00005-1MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IDC 1 12-May-15* 12-May-15 MM1-1305-PT-00-L-DS-00005-2MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFR 12 13-May-15 26-May-15 MM1-1305-PT-00-L-DS-00005-3MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFD 12 27-May-15 09-Jun-15 MM1-1305-PT-00-L-DS-00005-4MM1 & MM2 - SP Item Data Sheet -Valve Interlock -IFC 36 10-Jun-15 21-Jul-15 MM1-1305-PT-00-L-DS-00006MM1 & MM2 - SP Item Data Sheet - Barred Tee 52 10-Apr-15 12-Jun-15 MM1-1305-PT-00-L-DS-00006-1MM1 & MM2 - SP Item Data Sheet - Barred Tee-IDC 1 10-Apr-15* 10-Apr-15 MM1-1305-PT-00-L-DS-00006-2MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFR 12 11-Apr-15 24-Apr-15 MM1-1305-PT-00-L-DS-00006-3MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFD 9 25-Apr-15 08-May-15 MM1-1305-PT-00-L-DS-00006-4MM1 & MM2 - SP Item Data Sheet - Barred Tee-IFC 30 09-May-15 12-Jun-15 MM1-1305-PT-00-L-DS-00007MM1 & MM2 - SP Item Data Sheet - Bends 70 24-Apr-15 17-Jul-15 MM1-1305-PT-00-L-DS-00007-1MM1 & MM2 - SP Item Data Sheet - Bends-IDC 1 24-Apr-15* 24-Apr-15 MM1-1305-PT-00-L-DS-00007-2MM1 & MM2 - SP Item Data Sheet - Bends-IFR 15 25-Apr-15 15-May-15 MM1-1305-PT-00-L-DS-00007-3MM1 & MM2 - SP Item Data Sheet - Bends-IFD 12 16-May-15 29-May-15 MM1-1305-PT-00-L-DS-00007-4MM1 & MM2 - SP Item Data Sheet - Bends-IFC 42 30-May-15 17-Jul-15 MM1-1305-PT-00-L-DS-00008MM1 & MM2 - SP Item Data Sheets for Sample connection 58 24-Apr-15 03-Jul-15 MM1-1305-PT-00-L-DS-00008-1MM1 & MM2 - SP Item Data Sheets for Sample connection -IDC 1 24-Apr-15* 24-Apr-15 MM1-1305-PT-00-L-DS-00008-2MM1 & MM2 - SP Item Data Sheets for Sample connection -IFR 9 25-Apr-15 08-May-15 MM1-1305-PT-00-L-DS-00008-3MM1 & MM2 - SP Item Data Sheets for Sample connection -IFD 12 09-May-15 22-May-15 MM1-1305-PT-00-L-DS-00008-4MM1 & MM2 - SP Item Data Sheets for Sample connection -IFC 36 23-May-15 03-Jul-15 MM1-1305-PT-00-L-DS-00009MM1 & MM2 - SP Item Data Sheet - Chemcial injection 58 24-Apr-15 03-Jul-15 MM1-1305-PT-00-L-DS-00009-1MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IDC 1 24-Apr-15* 24-Apr-15 MM1-1305-PT-00-L-DS-00009-2MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFR 9 25-Apr-15 08-May-15 MM1-1305-PT-00-L-DS-00009-3MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFD 12 09-May-15 22-May-15 MM1-1305-PT-00-L-DS-00009-4MM1 & MM2 - SP Item Data Sheet - Chemcial injection-IFC 36 23-May-15 03-Jul-15 MM1-1305-PT-00-L-DS-00010MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon 58 24-Apr-15 03-Jul-15 MM1-1305-PT-00-L-DS-00010-1MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IDC 1 24-Apr-15* 24-Apr-15 MM1-1305-PT-00-L-DS-00010-2MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFR 9 25-Apr-15 08-May-15 MM1-1305-PT-00-L-DS-00010-3MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFD 12 09-May-15 22-May-15 MM1-1305-PT-00-L-DS-00010-4MM1 & MM2 - SP Item Data Sheet - Corrosion probe/coupon-IFC 36 23-May-15 03-Jul-15 MM1-1305-PT-00-L-DS-00011MM1 & MM2 - SP Item Data Sheet - Sand probe 58 24-Apr-15 03-Jul-15 MM1-1305-PT-00-L-DS-00011-1MM1 & MM2 - SP Item Data Sheet - Sand probe-IDC 1 24-Apr-15* 24-Apr-15 MM1-1305-PT-00-L-DS-00011-2MM1 & MM2 - SP Item Data Sheet - Sand probe-IFR 9 25-Apr-15 08-May-15 MM1-1305-PT-00-L-DS-00011-3MM1 & MM2 - SP Item Data Sheet - Sand probe-IFD 12 09-May-15 22-May-15 MM1-1305-PT-00-L-DS-00011-4MM1 & MM2 - SP Item Data Sheet - Sand probe-IFC 36 23-May-15 03-Jul-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 16 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 17. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-00-L-DS-00012MM1 & MM2 - SP Item Data Sheet - Quick coupling 70 05-Jun-15 25-Aug-15 MM1-1305-PT-00-L-DS-00012-1MM1 & MM2 - SP Item Data Sheet - Quick coupling-IDC 1 05-Jun-15* 05-Jun-15 MM1-1305-PT-00-L-DS-00012-2MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFR 12 06-Jun-15 19-Jun-15 MM1-1305-PT-00-L-DS-00012-3MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFD 12 20-Jun-15 03-Jul-15 MM1-1305-PT-00-L-DS-00012-4MM1 & MM2 - SP Item Data Sheet - Quick coupling-IFC 45 04-Jul-15 25-Aug-15 MM1-1305-PT-00-L-DS-00013MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR 70 05-Jun-15 25-Aug-15 MM1-1305-PT-00-L-DS-00013-1MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IDC 1 05-Jun-15* 05-Jun-15 MM1-1305-PT-00-L-DS-00013-2MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFR 12 06-Jun-15 19-Jun-15 MM1-1305-PT-00-L-DS-00013-3MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFD 12 20-Jun-15 03-Jul-15 MM1-1305-PT-00-L-DS-00013-4MM1 & MM2 - SP Item Data Sheet - HUB CONNECTOR-IFC 45 04-Jul-15 25-Aug-15 MM1-1305-PT-00-L-XE-10001MM1 - Equipment Layout 40 24-Apr-15 12-Jun-15 MM1-1305-PT-00-L-XE-10001-1MM1 - Equipment Layout-IDC 10 24-Apr-15* 08-May-15 MM1-1305-PT-00-L-XE-10001-2MM1 - Equipment Layout-IFR 6 09-May-15 15-May-15 MM1-1305-PT-00-L-XE-10001-3MM1 - Equipment Layout-IFD 12 16-May-15 29-May-15 MM1-1305-PT-00-L-XE-10001-4MM1 - Equipment Layout-IFC 12 30-May-15 12-Jun-15 MM1-1305-PT-00-L-XE-10002MM1 - Piping layout 43 30-May-15 18-Jul-15 MM1-1305-PT-00-L-XE-10002-1MM1 - Piping layout-IDC 13 30-May-15* 13-Jun-15 MM1-1305-PT-00-L-XE-10002-2MM1 - Piping layout-IFR 6 15-Jun-15 20-Jun-15 MM1-1305-PT-00-L-XE-10002-3MM1 - Piping layout-IFD 12 22-Jun-15 04-Jul-15 MM1-1305-PT-00-L-XE-10002-4MM1 - Piping layout-IFC 12 06-Jul-15 18-Jul-15 MM1-1305-PT-00-L-XF-10003MM1 - Pipe support location plan 43 20-Jun-15 08-Aug-15 MM1-1305-PT-00-L-XF-10003-1MM1 - Pipe support location plan-IDC 13 20-Jun-15* 04-Jul-15 MM1-1305-PT-00-L-XF-10003-2MM1 - Pipe support location plan-IFR 6 06-Jul-15 11-Jul-15 MM1-1305-PT-00-L-XF-10003-3MM1 - Pipe support location plan-IFD 0 13-Jul-15 13-Jul-15 MM1-1305-PT-00-L-XF-10003-4MM1 - Pipe support location plan-IFC 24 13-Jul-15 08-Aug-15 MM1-1305-PT-00-L-XN-10001MM1 - Isometric drawings (n Sheets) 59 16-May-15 23-Jul-15 MM1-1305-PT-00-L-XN-10001-1MM1 - Isometric drawings (n Sheets)-IDC 13 16-May-15* 30-May-15 MM1-1305-PT-00-L-XN-10001-2MM1 - Isometric drawings (n Sheets)-IFR 12 01-Jun-15 13-Jun-15 MM1-1305-PT-00-L-XN-10001-3MM1 - Isometric drawings (n Sheets)-IFD 0 15-Jun-15 15-Jun-15 MM1-1305-PT-00-L-XN-10001-4MM1 - Isometric drawings (n Sheets)-IFC 34 15-Jun-15 23-Jul-15 MM1-1305-PT-00-L-XO-10001MM1 - Pipe support detail drawings 59 16-May-15 23-Jul-15 MM1-1305-PT-00-L-XO-10001-1MM1 - Pipe support detail drawings-IDC 13 16-May-15* 30-May-15 MM1-1305-PT-00-L-XO-10001-2MM1 - Pipe support detail drawings-IFR 12 01-Jun-15 13-Jun-15 MM1-1305-PT-00-L-XO-10001-3MM1 - Pipe support detail drawings-IFD 0 15-Jun-15 15-Jun-15 MM1-1305-PT-00-L-XO-10001-4MM1 - Pipe support detail drawings-IFC 34 15-Jun-15 23-Jul-15 MM1-1305-PT-00-L-LA-00004MM1 & MM2 - Material take-off for Manual Valves 45 23-Apr-15 17-Jun-15 MM1-1305-PT-00-L-LA-00004-1MM1 & MM2 - Material take-off for Manual Valves-IDC 1 23-Apr-15* 23-Apr-15 MM1-1305-PT-00-L-LA-00004-2MM1 & MM2 - Material take-off for Manual Valves-IFR 4 24-Apr-15 29-Apr-15 MM1-1305-PT-00-L-LA-00004-3MM1 & MM2 - Material take-off for Manual Valves-IFD 0 02-May-15 02-May-15 MM1-1305-PT-00-L-LA-00004-4MM1 & MM2 - Material take-off for Manual Valves-IFC 40 02-May-15 17-Jun-15 MM1-1305-PT-00-L-LA-00005MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket 54 26-Jun-15 27-Aug-15 MM1-1305-PT-00-L-LA-00005-1MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IDC 1 26-Jun-15* 26-Jun-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 17 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 18. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-00-L-LA-00005-2MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFR 5 27-Jun-15 02-Jul-15 MM1-1305-PT-00-L-LA-00005-3MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFD 0 03-Jul-15 03-Jul-15 MM1-1305-PT-00-L-LA-00005-4MM1 & MM2 - Material take-off for Stub bolts, nuts and gasket-IFC 48 03-Jul-15 27-Aug-15 MM1-1305-PT-00-L-LA-00006MM1 & MM2 - Material take-off for Pipe Support (Raw Material) 53 30-May-15 30-Jul-15 MM1-1305-PT-00-L-LA-00006-1MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IDC 1 30-May-15* 30-May-15 MM1-1305-PT-00-L-LA-00006-2MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFR 6 01-Jun-15 06-Jun-15 MM1-1305-PT-00-L-LA-00006-3MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFD 0 08-Jun-15 08-Jun-15 MM1-1305-PT-00-L-LA-00006-4MM1 & MM2 - Material take-off for Pipe Support (Raw Material)-IFC 46 08-Jun-15 30-Jul-15 MM1-1305-PT-00-L-LA-00007MM1 & MM2 - Material take-off - Hub Connector 70 11-Jun-15 31-Aug-15 MM1-1305-PT-00-L-LA-00007-1MM1 & MM2 - Material take-off - Hub Connector-IDC 1 11-Jun-15* 11-Jun-15 MM1-1305-PT-00-L-LA-00007-2MM1 & MM2 - Material take-off - Hub Connector-IFR 12 12-Jun-15 25-Jun-15 MM1-1305-PT-00-L-LA-00007-3MM1 & MM2 - Material take-off - Hub Connector-IFD 0 26-Jun-15 26-Jun-15 MM1-1305-PT-00-L-LA-00007-4MM1 & MM2 - Material take-off - Hub Connector-IFC 57 26-Jun-15 31-Aug-15 MM1-10250 TR/MTO for Piping Bulk 1 10-Apr-15 10-Apr-15 MM1-10270 TR/MTO for Manual valves 1 29-Apr-15 29-Apr-15 MM1-10290 TR/MTO for Barred Tee 1 29-Apr-15 29-Apr-15 MM1-10310 TR/MTO for Cuni fittings 1 08-May-15 08-May-15 MM1-10330 TR/MTO for Corrosion, sand probe, sample connection, chemical connection 1 18-May-15 18-May-15 MM1-10350 TR/MTO for 3D Bend (free bare pipe to bending contractor) 1 30-May-15 30-May-15 MM1-10370 TR/MTO for Pipe Supports 1 06-Jun-15 06-Jun-15 MM1-10410 TR/MTO for Piping insulation 1 04-Jul-15 04-Jul-15 MM1-10430 TR/MTO for Bolt nut, gasket and other 1 06-Jul-15 06-Jul-15 MM1-10390 TR/MTO for Quick Coupling 1 09-Jul-15 09-Jul-15 MM1-10450 TR/MTO for Valve Inter-locks 1 16-Sep-15 16-Sep-15 MM1-10470 Prepare / Submit/ Approve Piping Shop Drawings 151 16-Sep-15 16-Mar-16 0.D.26.0000.MM1.B.1 E&I0.D.26.0000.MM1.B.1 E&I 313 13-Mar-15 16-Mar-16 0.D.26.0000.MM1.B.1.92 PTSC0.D.26.0000.MM1.B.1.92 PTSC 313 13-Mar-15 16-Mar-16 MM1-1305-PT-82-E-CA-00001MM1 & MM2 - Electrical Load List 57 04-May-15 08-Jul-15 MM1-1305-PT-82-E-CA-00001-1MM1 & MM2 - Electrical Load List-IDC 10 04-May-15* 14-May-15 MM1-1305-PT-82-E-CA-00001-2MM1 & MM2 - Electrical Load List-IFR 13 15-May-15 29-May-15 MM1-1305-PT-82-E-CA-00001-3MM1 & MM2 - Electrical Load List-IFD 13 30-May-15 13-Jun-15 MM1-1305-PT-82-E-CA-00001-4MM1 & MM2 - Electrical Load List-IFC 21 15-Jun-15 08-Jul-15 MM1-1305-PT-82-E-CA-00002MM1 & MM2 - Electrical Lighting Calculation 32 20-Mar-15 25-Apr-15 MM1-1305-PT-82-E-CA-00002-1MM1 & MM2 - Electrical Lighting Calculation-IDC 9 20-Mar-15* 30-Mar-15 MM1-1305-PT-82-E-CA-00002-2MM1 & MM2 - Electrical Lighting Calculation-IFR 6 31-Mar-15 06-Apr-15 MM1-1305-PT-82-E-CA-00002-3MM1 & MM2 - Electrical Lighting Calculation-IFD 13 07-Apr-15 21-Apr-15 MM1-1305-PT-82-E-CA-00002-4MM1 & MM2 - Electrical Lighting Calculation-IFC 4 22-Apr-15 25-Apr-15 MM1-1305-PT-82-E-XX-00001MM1 & MM2 - Electrical General Drawing and Document Index 36 23-Mar-15 06-May-15 MM1-1305-PT-82-E-XX-00001-1MM1 & MM2 - Electrical General Drawing and Document Index-IDC 9 23-Mar-15* 01-Apr-15 MM1-1305-PT-82-E-XX-00001-2MM1 & MM2 - Electrical General Drawing and Document Index-IFR 13 02-Apr-15 16-Apr-15 MM1-1305-PT-82-E-XX-00001-3MM1 & MM2 - Electrical General Drawing and Document Index-IFD 0 17-Apr-15 17-Apr-15 MM1-1305-PT-82-E-XX-00001-4MM1 & MM2 - Electrical General Drawing and Document Index-IFC 14 17-Apr-15 06-May-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 18 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 19. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-82-E-XX-00002MM1 & MM2 - Electrical Typical Installation Details 48 13-Mar-15 11-May-15 MM1-1305-PT-82-E-XX-00002-1MM1 & MM2 - Electrical Typical Installation Details-IDC 9 13-Mar-15* 23-Mar-15 MM1-1305-PT-82-E-XX-00002-2MM1 & MM2 - Electrical Typical Installation Details-IFR 13 24-Mar-15 07-Apr-15 MM1-1305-PT-82-E-XX-00002-3MM1 & MM2 - Electrical Typical Installation Details-IFD 13 08-Apr-15 22-Apr-15 MM1-1305-PT-82-E-XX-00002-4MM1 & MM2 - Electrical Typical Installation Details-IFC 13 23-Apr-15 11-May-15 MM1-1305-PT-82-E-DS-00001MM1 & MM2 - Electrical Datasheet 30 02-Apr-15 09-May-15 MM1-1305-PT-82-E-DS-00001-1MM1 & MM2 - Electrical Datasheet-IDC 9 02-Apr-15* 11-Apr-15 MM1-1305-PT-82-E-DS-00001-2MM1 & MM2 - Electrical Datasheet-IFR 6 13-Apr-15 18-Apr-15 MM1-1305-PT-82-E-DS-00001-3MM1 & MM2 - Electrical Datasheet-IFD 10 20-Apr-15 04-May-15 MM1-1305-PT-82-E-DS-00001-4MM1 & MM2 - Electrical Datasheet-IFC 5 05-May-15 09-May-15 MM1-1305-PT-82-E-XX-10001MM1 - Electrical Drawing Index 37 23-Mar-15 07-May-15 MM1-1305-PT-82-E-XX-10001-1MM1 - Electrical Drawing Index -IDC 10 23-Mar-15* 02-Apr-15 MM1-1305-PT-82-E-XX-10001-2MM1 - Electrical Drawing Index -IFR 13 03-Apr-15 17-Apr-15 MM1-1305-PT-82-E-XX-10001-3MM1 - Electrical Drawing Index -IFD 0 18-Apr-15 18-Apr-15 MM1-1305-PT-82-E-XX-10001-4MM1 - Electrical Drawing Index -IFC 14 18-Apr-15 07-May-15 MM1-1305-PT-82-E-XX-10002MM1 - Electrical Cable Ladder Support 39 08-May-15 22-Jun-15 MM1-1305-PT-82-E-XX-10002-1MM1 - Electrical Cable Ladder Support-IDC 9 08-May-15* 18-May-15 MM1-1305-PT-82-E-XX-10002-2MM1 - Electrical Cable Ladder Support-IFR 13 19-May-15 02-Jun-15 MM1-1305-PT-82-E-XX-10002-3MM1 - Electrical Cable Ladder Support-IFD 0 03-Jun-15 03-Jun-15 MM1-1305-PT-82-E-XX-10002-4MM1 - Electrical Cable Ladder Support-IFC 17 03-Jun-15 22-Jun-15 MM1-1305-PT-82-E-XJ-10001MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001 39 13-Mar-15 27-Apr-15 MM1-1305-PT-82-E-XJ-10001-1MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IDC 9 13-Mar-15* 23-Mar-15 MM1-1305-PT-82-E-XJ-10001-2MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IFR 13 24-Mar-15 07-Apr-15 MM1-1305-PT-82-E-XJ-10001-3MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IFD 0 08-Apr-15 08-Apr-15 MM1-1305-PT-82-E-XJ-10001-4MM1 - Electrical Single Line Diagram - MOV Distribution Panel 82EL001-IFC 17 08-Apr-15 27-Apr-15 MM1-1305-PT-82-E-XJ-10002MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL00239 13-Mar-15 27-Apr-15 MM1-1305-PT-82-E-XJ-10002-1MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IDC9 13-Mar-15* 23-Mar-15 MM1-1305-PT-82-E-XJ-10002-2MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IFR13 24-Mar-15 07-Apr-15 MM1-1305-PT-82-E-XJ-10002-3MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IFD0 08-Apr-15 08-Apr-15 MM1-1305-PT-82-E-XJ-10002-4MM1 - Electrical Single Line Diagram - Heat Tracing Distribution Panel 82EL002-IFC17 08-Apr-15 27-Apr-15 MM1-1305-PT-82-E-XJ-10003MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL00339 13-Mar-15 27-Apr-15 MM1-1305-PT-82-E-XJ-10003-1MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IDC9 13-Mar-15* 23-Mar-15 MM1-1305-PT-82-E-XJ-10003-2MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IFR13 24-Mar-15 07-Apr-15 MM1-1305-PT-82-E-XJ-10003-3MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IFD0 08-Apr-15 08-Apr-15 MM1-1305-PT-82-E-XJ-10003-4MM1 - Electrical Single Line Diagram - Normal Lighting Distribution Panel 82EL003-IFC17 08-Apr-15 27-Apr-15 MM1-1305-PT-82-E-XJ-10004MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL00439 13-Mar-15 27-Apr-15 MM1-1305-PT-82-E-XJ-10004-1MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL004-IDC9 13-Mar-15* 23-Mar-15 MM1-1305-PT-82-E-XJ-10004-2MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL004-IFR13 24-Mar-15 07-Apr-15 MM1-1305-PT-82-E-XJ-10004-3MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL004-IFD0 08-Apr-15 08-Apr-15 MM1-1305-PT-82-E-XJ-10004-4MM1 - Electrical Single Line Diagram - Emergency Lighting Distribution Panel 82EL004-IFC17 08-Apr-15 27-Apr-15 MM1-1305-PT-82-E-XJ-10005MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL00539 13-Mar-15 27-Apr-15 MM1-1305-PT-82-E-XJ-10005-1MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IDC9 13-Mar-15* 23-Mar-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 19 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 20. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-82-E-XJ-10005-2MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IFR13 24-Mar-15 07-Apr-15 MM1-1305-PT-82-E-XJ-10005-3MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IFD0 08-Apr-15 08-Apr-15 MM1-1305-PT-82-E-XJ-10005-4MM1 - Electrical Single Line Diagram - Escape Lighting Distribution Panel 82EL005-IFC17 08-Apr-15 27-Apr-15 MM1-1305-PT-82-E-TA-10001MM1 - Electrical Cable Schedule 51 10-Apr-15 11-Jun-15 MM1-1305-PT-82-E-TA-10001-1MM1 - Electrical Cable Schedule -IDC 13 10-Apr-15* 24-Apr-15 MM1-1305-PT-82-E-TA-10001-2MM1 - Electrical Cable Schedule -IFR 9 25-Apr-15 08-May-15 MM1-1305-PT-82-E-TA-10001-3MM1 - Electrical Cable Schedule -IFD 13 09-May-15 23-May-15 MM1-1305-PT-82-E-TA-10001-4MM1 - Electrical Cable Schedule -IFC 16 25-May-15 11-Jun-15 MM1-1305-PT-82-E-XT-10001MM1 - Electrical Heat Tracing Interconnection Diagram 39 21-May-15 04-Jul-15 MM1-1305-PT-82-E-XT-10001-1MM1 - Electrical Heat Tracing Interconnection Diagram-IDC 9 21-May-15* 30-May-15 MM1-1305-PT-82-E-XT-10001-2MM1 - Electrical Heat Tracing Interconnection Diagram-IFR 13 01-Jun-15 15-Jun-15 MM1-1305-PT-82-E-XT-10001-3MM1 - Electrical Heat Tracing Interconnection Diagram-IFD 0 16-Jun-15 16-Jun-15 MM1-1305-PT-82-E-XT-10001-4MM1 - Electrical Heat Tracing Interconnection Diagram-IFC 17 16-Jun-15 04-Jul-15 MM1-1305-PT-82-E-XI-10001MM1 - Electrical Heat Tracing Block Diagram 58 25-Apr-15 04-Jul-15 MM1-1305-PT-82-E-XI-10001-1MM1 - Electrical Heat Tracing Block Diagram-IDC 6 25-Apr-15* 05-May-15 MM1-1305-PT-82-E-XI-10001-2MM1 - Electrical Heat Tracing Block Diagram-IFR 13 06-May-15 20-May-15 MM1-1305-PT-82-E-XI-10001-3MM1 - Electrical Heat Tracing Block Diagram-IFD 0 21-May-15 21-May-15 MM1-1305-PT-82-E-XI-10001-4MM1 - Electrical Heat Tracing Block Diagram-IFC 39 21-May-15 04-Jul-15 MM1-1305-PT-82-E-XI-10002MM1 - Electrical Lighting Interconnection Diagram 36 24-Apr-15 08-Jun-15 MM1-1305-PT-82-E-XI-10002-1MM1 - Electrical Lighting Interconnection Diagram-IDC 6 24-Apr-15* 04-May-15 MM1-1305-PT-82-E-XI-10002-2MM1 - Electrical Lighting Interconnection Diagram-IFR 13 05-May-15 19-May-15 MM1-1305-PT-82-E-XI-10002-3MM1 - Electrical Lighting Interconnection Diagram-IFD 0 20-May-15 20-May-15 MM1-1305-PT-82-E-XI-10002-4MM1 - Electrical Lighting Interconnection Diagram-IFC 17 20-May-15 08-Jun-15 MM1-1305-PT-82-E-XE-10001MM1 - Electrical Lighting And Small Power Layout - Main Deck 36 24-Apr-15 08-Jun-15 MM1-1305-PT-82-E-XE-10001-1MM1 - Electrical Lighting And Small Power Layout - Main Deck -IDC 6 24-Apr-15* 04-May-15 MM1-1305-PT-82-E-XE-10001-2MM1 - Electrical Lighting And Small Power Layout - Main Deck -IFR 13 05-May-15 19-May-15 MM1-1305-PT-82-E-XE-10001-3MM1 - Electrical Lighting And Small Power Layout - Main Deck -IFD 0 20-May-15 20-May-15 MM1-1305-PT-82-E-XE-10001-4MM1 - Electrical Lighting And Small Power Layout - Main Deck -IFC 17 20-May-15 08-Jun-15 MM1-1305-PT-82-E-XE-10002MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck 36 24-Apr-15 08-Jun-15 MM1-1305-PT-82-E-XE-10002-1MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IDC 6 24-Apr-15* 04-May-15 MM1-1305-PT-82-E-XE-10002-2MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IFR 13 05-May-15 19-May-15 MM1-1305-PT-82-E-XE-10002-3MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IFD 0 20-May-15 20-May-15 MM1-1305-PT-82-E-XE-10002-4MM1 - Electrical Lighting And Small Power Layout - Mezzanine Deck -IFC 17 20-May-15 08-Jun-15 MM1-1305-PT-82-E-XE-10003MM1 - Electrical Lighting And Small Power Layout - Upper Deck 36 24-Apr-15 08-Jun-15 MM1-1305-PT-82-E-XE-10003-1MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IDC 6 24-Apr-15* 04-May-15 MM1-1305-PT-82-E-XE-10003-2MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IFR 13 05-May-15 19-May-15 MM1-1305-PT-82-E-XE-10003-3MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IFD 0 20-May-15 20-May-15 MM1-1305-PT-82-E-XE-10003-4MM1 - Electrical Lighting And Small Power Layout - Upper Deck -IFC 17 20-May-15 08-Jun-15 MM1-1305-PT-82-E-XE-11001MM1 - Electrical Earthing Layout - Main Deck 35 02-Apr-15 15-May-15 MM1-1305-PT-82-E-XE-11001-1MM1 - Electrical Earthing Layout - Main Deck -IDC 8 02-Apr-15* 10-Apr-15 MM1-1305-PT-82-E-XE-11001-2MM1 - Electrical Earthing Layout - Main Deck -IFR 13 11-Apr-15 25-Apr-15 MM1-1305-PT-82-E-XE-11001-3MM1 - Electrical Earthing Layout - Main Deck -IFD 0 27-Apr-15 27-Apr-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 20 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 21. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-82-E-XE-11001-4MM1 - Electrical Earthing Layout - Main Deck -IFC 14 27-Apr-15 15-May-15 MM1-1305-PT-82-E-XE-11002MM1 - Electrical Earthing Layout - Mezzanine Deck 35 02-Apr-15 15-May-15 MM1-1305-PT-82-E-XE-11002-1MM1 - Electrical Earthing Layout - Mezzanine Deck-IDC 8 02-Apr-15* 10-Apr-15 MM1-1305-PT-82-E-XE-11002-2MM1 - Electrical Earthing Layout - Mezzanine Deck-IFR 13 11-Apr-15 25-Apr-15 MM1-1305-PT-82-E-XE-11002-3MM1 - Electrical Earthing Layout - Mezzanine Deck-IFD 0 27-Apr-15 27-Apr-15 MM1-1305-PT-82-E-XE-11002-4MM1 - Electrical Earthing Layout - Mezzanine Deck-IFC 14 27-Apr-15 15-May-15 MM1-1305-PT-82-E-XE-11003MM1 - Electrical Earthing Layout - Upper Deck 35 02-Apr-15 15-May-15 MM1-1305-PT-82-E-XE-11003-1MM1 - Electrical Earthing Layout - Upper Deck -IDC 8 02-Apr-15* 10-Apr-15 MM1-1305-PT-82-E-XE-11003-2MM1 - Electrical Earthing Layout - Upper Deck -IFR 13 11-Apr-15 25-Apr-15 MM1-1305-PT-82-E-XE-11003-3MM1 - Electrical Earthing Layout - Upper Deck -IFD 0 27-Apr-15 27-Apr-15 MM1-1305-PT-82-E-XE-11003-4MM1 - Electrical Earthing Layout - Upper Deck -IFC 14 27-Apr-15 15-May-15 MM1-1305-PT-82-E-XE-12001MM1 - Electrical Cable Ladder And Support Layout - Main Deck 36 24-Apr-15 08-Jun-15 MM1-1305-PT-82-E-XE-12001-1MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IDC 6 24-Apr-15* 04-May-15 MM1-1305-PT-82-E-XE-12001-2MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IFR 13 05-May-15 19-May-15 MM1-1305-PT-82-E-XE-12001-3MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IFD 0 20-May-15 20-May-15 MM1-1305-PT-82-E-XE-12001-4MM1 - Electrical Cable Ladder And Support Layout - Main Deck -IFC 17 20-May-15 08-Jun-15 MM1-1305-PT-82-E-XE-12002MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck 36 24-Apr-15 08-Jun-15 MM1-1305-PT-82-E-XE-12002-1MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IDC 6 24-Apr-15* 04-May-15 MM1-1305-PT-82-E-XE-12002-2MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IFR 13 05-May-15 19-May-15 MM1-1305-PT-82-E-XE-12002-3MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IFD 0 20-May-15 20-May-15 MM1-1305-PT-82-E-XE-12002-4MM1 - Electrical Cable Ladder And Support Layout - Mezzanine Deck -IFC 17 20-May-15 08-Jun-15 MM1-1305-PT-82-E-XE-12003MM1 - Electrical Cable Ladder And Support Layout - Upper Deck 36 24-Apr-15 08-Jun-15 MM1-1305-PT-82-E-XE-12003-1MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IDC 6 24-Apr-15* 04-May-15 MM1-1305-PT-82-E-XE-12003-2MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IFR 13 05-May-15 19-May-15 MM1-1305-PT-82-E-XE-12003-3MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IFD 0 20-May-15 20-May-15 MM1-1305-PT-82-E-XE-12003-4MM1 - Electrical Cable Ladder And Support Layout - Upper Deck-IFC 17 20-May-15 08-Jun-15 MM1-1305-PT-82-E-XE-13001MM1 - Electrical Cable Routing Layout - Main Deck 39 09-May-15 23-Jun-15 MM1-1305-PT-82-E-XE-13001-1MM1 - Electrical Cable Routing Layout - Main Deck-IDC 9 09-May-15* 19-May-15 MM1-1305-PT-82-E-XE-13001-2MM1 - Electrical Cable Routing Layout - Main Deck-IFR 13 20-May-15 03-Jun-15 MM1-1305-PT-82-E-XE-13001-3MM1 - Electrical Cable Routing Layout - Main Deck-IFD 0 04-Jun-15 04-Jun-15 MM1-1305-PT-82-E-XE-13001-4MM1 - Electrical Cable Routing Layout - Main Deck-IFC 17 04-Jun-15 23-Jun-15 MM1-1305-PT-82-E-XE-13002MM1 - Electrical Cable Routing Layout - Mezzanine Deck 39 09-May-15 23-Jun-15 MM1-1305-PT-82-E-XE-13002-1MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IDC 9 09-May-15* 19-May-15 MM1-1305-PT-82-E-XE-13002-2MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IFR 13 20-May-15 03-Jun-15 MM1-1305-PT-82-E-XE-13002-3MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IFD 0 04-Jun-15 04-Jun-15 MM1-1305-PT-82-E-XE-13002-4MM1 - Electrical Cable Routing Layout - Mezzanine Deck -IFC 17 04-Jun-15 23-Jun-15 MM1-1305-PT-82-E-XE-13003MM1 - Electrical Cable Routing Layout - Upper Deck 39 09-May-15 23-Jun-15 MM1-1305-PT-82-E-XE-13003-1MM1 - Electrical Cable Routing Layout - Upper Deck-IDC 9 09-May-15* 19-May-15 MM1-1305-PT-82-E-XE-13003-2MM1 - Electrical Cable Routing Layout - Upper Deck-IFR 13 20-May-15 03-Jun-15 MM1-1305-PT-82-E-XE-13003-3MM1 - Electrical Cable Routing Layout - Upper Deck-IFD 0 04-Jun-15 04-Jun-15 MM1-1305-PT-82-E-XE-13003-4MM1 - Electrical Cable Routing Layout - Upper Deck-IFC 17 04-Jun-15 23-Jun-15 MM1-1305-PT-82-E-LA-00001MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures 80 05-May-15 05-Aug-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 21 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3
  • 22. Activity ID Activity Name Original Duration Start Finish MM1-1305-PT-82-E-LA-00001-1MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IDC 7 05-May-15* 12-May-15 MM1-1305-PT-82-E-LA-00001-2MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFR 24 13-May-15 09-Jun-15 MM1-1305-PT-82-E-LA-00001-3MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFD 0 10-Jun-15 10-Jun-15 MM1-1305-PT-82-E-LA-00001-4MM1 & MM2 - Electrical Material Take-Off - Lighting Fixtures-IFC 49 10-Jun-15 05-Aug-15 MM1-1305-PT-82-E-LA-00002MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories77 11-May-15 07-Aug-15 MM1-1305-PT-82-E-LA-00002-1MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IDC7 11-May-15* 18-May-15 MM1-1305-PT-82-E-LA-00002-2MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFR23 19-May-15 13-Jun-15 MM1-1305-PT-82-E-LA-00002-3MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFD0 15-Jun-15 15-Jun-15 MM1-1305-PT-82-E-LA-00002-4MM1 & MM2 - Electrical Material Take-Off - Cable Ladder/Tray And Accessories-IFC47 15-Jun-15 07-Aug-15 MM1-1305-PT-82-E-LA-00003MM1 & MM2 - Electrical Material Take-Off - Cables 62 18-May-15 28-Jul-15 MM1-1305-PT-82-E-LA-00003-1MM1 & MM2 - Electrical Material Take-Off - Cables-IDC 7 18-May-15* 25-May-15 MM1-1305-PT-82-E-LA-00003-2MM1 & MM2 - Electrical Material Take-Off - Cables-IFR 8 26-May-15 03-Jun-15 MM1-1305-PT-82-E-LA-00003-3MM1 & MM2 - Electrical Material Take-Off - Cables-IFD 0 04-Jun-15 04-Jun-15 MM1-1305-PT-82-E-LA-00003-4MM1 & MM2 - Electrical Material Take-Off - Cables-IFC 47 04-Jun-15 28-Jul-15 MM1-1305-PT-82-E-LA-00004MM1 & MM2 - Electrical Material Take-Off - Cable Glands 77 21-May-15 18-Aug-15 MM1-1305-PT-82-E-LA-00004-1MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IDC 7 21-May-15* 28-May-15 MM1-1305-PT-82-E-LA-00004-2MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFR 22 29-May-15 23-Jun-15 MM1-1305-PT-82-E-LA-00004-3MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFD 0 24-Jun-15 24-Jun-15 MM1-1305-PT-82-E-LA-00004-4MM1 & MM2 - Electrical Material Take-Off - Cable Glands-IFC 48 24-Jun-15 18-Aug-15 MM1-1305-PT-82-E-LA-00005MM1 & MM2 - Electrical Material Take-Off - Junction Boxes 83 02-May-15 06-Aug-15 MM1-1305-PT-82-E-LA-00005-1MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IDC 6 02-May-15* 08-May-15 MM1-1305-PT-82-E-LA-00005-2MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFR 31 09-May-15 13-Jun-15 MM1-1305-PT-82-E-LA-00005-3MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFD 0 15-Jun-15 15-Jun-15 MM1-1305-PT-82-E-LA-00005-4MM1 & MM2 - Electrical Material Take-Off - Junction Boxes-IFC 46 15-Jun-15 06-Aug-15 MM1-1305-PT-82-E-LA-00006MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials 94 21-May-15 08-Sep-15 MM1-1305-PT-82-E-LA-00006-1MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IDC 7 21-May-15* 28-May-15 MM1-1305-PT-82-E-LA-00006-2MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFR 38 29-May-15 11-Jul-15 MM1-1305-PT-82-E-LA-00006-3MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFD 0 13-Jul-15 13-Jul-15 MM1-1305-PT-82-E-LA-00006-4MM1 & MM2 - Electrical Material Take-Off - Miscellaneous Materials-IFC 49 13-Jul-15 08-Sep-15 MM1-1305-PT-82-E-LA-00007MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials 52 15-May-15 14-Jul-15 MM1-1305-PT-82-E-LA-00007-1MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IDC 7 15-May-15* 22-May-15 MM1-1305-PT-82-E-LA-00007-2MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFR 10 23-May-15 03-Jun-15 MM1-1305-PT-82-E-LA-00007-3MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFD 0 04-Jun-15 04-Jun-15 MM1-1305-PT-82-E-LA-00007-4MM1 & MM2 - Electrical Material Take-Off - Steel Support Materials-IFC 35 04-Jun-15 14-Jul-15 MM1-1305-PT-00-I-LA-00009MM1 & MM2 - Ex Equipment Register 68 11-Jun-15 28-Aug-15 MM1-1305-PT-00-I-LA-00009-1MM1 & MM2 - Ex Equipment Register-IDC 27 11-Jun-15* 11-Jul-15 MM1-1305-PT-00-I-LA-00009-2MM1 & MM2 - Ex Equipment Register-IFR 12 13-Jul-15 25-Jul-15 MM1-1305-PT-00-I-LA-00009-3MM1 & MM2 - Ex Equipment Register-IFD 12 27-Jul-15 08-Aug-15 MM1-1305-PT-00-I-LA-00009-4MM1 & MM2 - Ex Equipment Register-IFC 17 10-Aug-15 28-Aug-15 MM1-1305-PT-00-I-SA-00001MM1 & MM2 - Instrument Control and Shutdown Philosophy 64 10-Jun-15 22-Aug-15 MM1-1305-PT-00-I-SA-00001-1MM1 & MM2 - Instrument Control and Shutdown Philosophy-IDC 27 10-Jun-15* 10-Jul-15 MM1-1305-PT-00-I-SA-00001-2MM1 & MM2 - Instrument Control and Shutdown Philosophy-IFR 8 11-Jul-15 20-Jul-15 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2015 2016 Ghana OCTP Development Project, FPSO EPC for Module MM1 & MM2 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Summary Schedule Level 3 Page 22 of 72 Date Revision Checked Approved 28-Mar-15 Baseline Schedule Level 3