This project report provides an update on the Kabugao-Pudtol-Luna-Cagayan Boundary Road project in Apayao Province. The 95.7 km road connects the municipalities of Kabugao, Pudtol and Luna before turning east to Abulog, Cagayan. Construction of bridges across the Maton and Nagan Rivers has been completed. The target is to construct 2.873 km of road by October 2012. Current implementation is on target with 5% of work completed in the first quarter. The road will improve access to agricultural areas and the new Apayao provincial capital located in Luna.
1. PROJECT PROGRESS REPORT
As of EO March 2012
Project Title: Kabugao-Pudtol-Luna-Cagayan Boundary Road
Implementing Agency: Department of Public Works and Highways - CAR
Donor: (x) GOP Loan/Grant Proceeds:
( ) Loan Peso Counterpart:
( ) Grant Total Project Cost: P 58.827 M
Location/Area Apayao Province
Coverage:
Description:
The road is a major component of the Cordillera Roads Improvement Project (CRIP)
as the northern tip of the regional backbone. It traverses the municipalities of
Kabugao, Pudtol and Luna in Apayao and turns east to Abulog in Cagayan.
The Kabugao-Pudtol-Luna-Abulug Road (95.7 km) directly links the capital town
Kabugao to lower Apayao. The road starts at junction Lenneng along the Kabugao-
Conner-Abbut Road and going north-east traverses municipalities of Kabugao, Pudtol
and Luna and ends at Junction Luna in Abulug, Cagayan along the Pan-Philippine
Highway. The Pan-Philippine Highway connects Laoag, Ilocos Norte and
Tuguegarao, Cagayan.
The bridge construction across Maton and Nagan Rivers has been completed. These
rivers are major tributaries of Apayao River.
The gap at the Kabugao side (19.359 km.), traverses a rugged mountainous terrain,
then slowly goes down to the Paco Valley, which was then proposed as government
center. The road will also traverse the Mataguisi Valley in Pudtol. The valleys have
vast potential for agricultural production. While, Luna, is the location of the new
provincial capitol.
The specific project output is road construction of 2.873 kms.
Project Duration: Start: February 20, 2012 End: October 16, 2012
PROJECT PROGRESS
For CY 2012 AO 1 Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter
st
Target 5%
Seedling
Production
Actual 5%
Slippage
Cumulative Status: Status Physical Financial
(Since start of Target 5%
project) Actual (slippage)
2. Current
Implementation
Issues and/or
Problems
Encountered (if any):
Actions Taken/
Recommendations:
Remarks: Memo (Nov. 3, 2011) from Secretary Singson:
Approved for upgrading from Secondary to Arterial Road
Agency Contact DIR. EDILBERTO P. CARABBACAN
Person: Regional Director, DPWH – CAR
Engineer’s Hill
2600 Baguio City
Tel. 444-8838
3. Project Location
Kabugao-Pudtol-Luna
Cagayan Bdry Road
New Apayao Provincial
Capitol in Luna
Landmarks