1. Republic of the Philippines
Cordillera Administrative Region
Regional Project Monitoring Committee
Third Quarter
CY 2012
RPMES REPORT
Prepared by the
National Economic and Development Authority
Cordillera Administrative Region
RPMC Secretariat
2. CY 2012 Major Programs and Projects --------- 1
Project Implementation Status --------- 2
CY 2012 Priority Sectoral Programs/ Projects --------- 4
RPMC Project Site Inspections --------- 5
Annexes:
A List of Major Programs/Projects --------- A-1
B Eight Priority Sectoral Programs/Projects
Second Cordillera Highland Agricultural Resource --------- B-1
Management Program (CHARMP 2)
4 Pantawid Pamilyang Pilipino Program (4Ps) --------- B-5
Agrarian Reform Infrastructure Support Program --------- B-10
(ARISP)
Kabugao, Apayao – Solsona, Ilocos Norte Road --------- B-13
Kabugao-Pudtol-Luna-Cagayan Boundary --------- B-17
Cordillera-wide Strengthening of Local Systems --------- B-20
for Effective and Efficient Delivery of Maternal
and Child Health Services
National Greening Program (NGP) --------- B-21
Red and Black School Building Program --------- B-24
C Inspection Reports
Kabugao-Pudtol-Luna- Cagayan Boundary Road --------- C-1
Kabugao, Apayao – Solsona, Ilocos Norte Road --------- C-4
3. Third Quarter CY 2012 RPMES Report
The Regional Project Monitoring and Evaluation System (RPMES) report is prepared on a
quarterly basis to provide an overall view on the status of major program/project (P/Ps)
implementation in the region. The report is based on the submission of eleven regional line
agencies (RLAs).
I. CY 2012 Major Programs/Projects
For CY 2012, there are 46 major P/Ps with an aggregate cost of Php 10.633 Billion of which
about Php 5.9 billion or 55.52 percent are new P/Ps, Php 3.9 billion or 37.52 percent are
multi-year projects, and Php 0.740 billion or 6.96 percent are carryover projects.
In terms of cost, the economic development sector has the highest at 51.21 percent or Php
5,445 billion, followed by the infrastructure sector at 27 percent or Php 2,794 billion, and the
social sector having the least at 18.68 percent or Php 1,985.883 billion. Also included are
rehabilitation and reconstruction projects under the Strategic Action Plan (SAP) on areas
affected by typhoons “Pedring” and “Quiel” in 2011 amounting to 4 percent or Php 407 million.
1
Third Quarter CY 2012 RPMES Report
4. In terms of funding source, 67 percent is locally funded while 32 percent is foreign assisted.
The foreign- assisted projects are: (a) Second Cordillera Highland Agriculture Resource
Management Program (CHARMP II), Php 3.2 Billion, (b) Agrarian Reform Infrastructure Support
Program (ARISP), Php 903 Million; and (c) Rural Micro-Enterprises Promotion Program
(RuMEPP), Php 1.8 Million.
II. Project Implementation Status
For the third quarter, the overall status of project implementation is 43 percent, a 10 percent
increase from the second quarter. The SAP projects posted the highest accomplishment
followed the social sector, then the infrastructure sector. The economic sector’s low
performance is the due to the delayed implementation of its banner project, the CHARMP 2.
(Please refer to Annex A for the detailed status of the 46 projects)
Projects identified under the SAP of areas affected by typhoons Pedring, Quiel and Juan posted
an accomplishment of 96.41 percent, most of which are roads and school building projects.
The Social Sector obtained an overall accomplishment of 52.82 percent. The projects
reported under the sector are DSWD’s Pantawid Pamilyang Pilipino Program (4Ps), DepEd’s Red
and Black Schoolbuilding Program, Rehabilitation of School Building including Water Sanitation
Facilites and Philippines’ Response to Indigenous and Muslim Education (PRIME), DOH’s Health
Facilities and Water System Projects and foreign-assisted Cordillera-wide Strengthening of Local
2
Third Quarter CY 2012 RPMES Report
5. Health System for Effective and Efficient Delivery of Maternal and child Health Service.
The Infrastructure Sector had an overall accomplishment of 47.09 percent, composed of
DPWH’s priority roads and bridge projects. These priority roads are mainly laterals that link
CAR to Regions I and II.
The Economic Sector posted an overall accomplishment of 45.57 percent. The sector’s
accomplishment is relatively the lowest due to the negative slippages incurred by two of its
major projects, these are: DA’s foreign-assisted project Second Phase of Cordillera Highland
Agricultural Resource Management Project or CHARMP 2 costing about Php 3 Billion, and
DENR’s National Government Priority, National Greening Program (NGP) costing about Php 124
Million. The other projects under the sector are DAR’s Agrarian Reform Infrastructure Support
Project (ARISP III), DA’s Farm-to-Market Roads, NIA’s Irrigation Projects, DTI’s One Town One
Product Program (OTOP) and Shared Service Facilities SSF, and DOST’s completed Small
Enterprises Technology Program (SETUP), and Packaging and Labeling Project.
Implementation Status (as Sept. 2012)
100.00% 96.41%
80.00%
52.82%
60.00% 45.57% 47.09%
49.27 %
40.00%
20.00%
0.00%
3
Third Quarter CY 2012 RPMES Report
6. The overall performance during the quarter translates to four (4) P/P completed – the SETUP of
DOST, two (2) sections of the Abra-Kalinga Road, and Gurel-Bokod-Kabayan-Buguias-Abatan
Road, eight (8) P/P are ahead of schedule, 20 are on track, and 14 behind schedule.
Of the 14 projects reported behind schedule, 11 projects incurred negative slippages less than
negative 15 percent. The common reason reported was due to inclement weather/typhoons
in the project area. Agencies have adopted catch-up plans to put the projects on track. The
DA implemented CHARMP 2 had a negative 26 percent slippage because it underwent another
NEDA ICC process for project reconfiguration to address the issue on LGU counterpart.
CHARMP will have to retarget its work schedule once reconfiguration has been in effect. The
National Greening Program (NGP) also experienced a big slippage of negative 19.63 percent due
to change in procurement process. The NGP also adopted a catch-up plan to put the project
on track. The Philippine Response to Indigenous and Muslim Education (PRIME) of DepEd, is the
most problematic project that has a negative 51 percent slippage. DepEd acknowledges the
delay and has undertaken actions to put the project on track.
III. CY 2012 Priority Sectoral Programs/ Projects
From the 46 programs/projects, eight (8) were identified as priority sectoral programs/projects
by the sectoral committees and tagged as their banner projects. These programs/projects
with an aggregate cost of Php 5.3 billion are being closely monitored by the RPMC. These
were selected based on the criteria set during the RPMES national forum: (a) foreign- assisted
projects (FAP/ODA), (b) interprovincial, (c) large scale cost, (d) national priority, critical projects
by the Office of the President (OP), and (e) regional priority. These programs/projects are as
follows:
1. Second Cordillera Highland Agricultural Resource Management Project (CHARMP 2)
2. Pantawid Pamilyang Pilipino Program (4Ps)
3. Agrarian Reform Infrastructure Support Project, Phase III
4. Kabugao-Solsona, Apayao-Ilocos Norte Road
5. Kabugao-Pudtol- Luna- Cagayan Boundary Road
6. Cordillera-wide Strengthening of Local health System for Effective and Efficient Delivery of
Maternal and Child Health Services
7. National Greening Program
8. Red and Black School Building Program
Of the eight (8) priority P/Ps, five (5) have been inspected/validated, while the remaining three
(3) are scheduled for inspection by the RPMC before the year ends, these are CHARMP, 4Ps and
the Cordillera-wide Strengthening of Local Health Systems for Effective and Efficient Delivery of
Maternal and Child Health Services. The JICA-assisted Cordillera-wide Strengthening of Local
Health Systems launched in the first quarter has accordingly procured medical equipment for
the provinces of Abra and Apayao. (Please refer to Annex B for the details of the eight priority
sectoral programs/projects)
4
Third Quarter CY 2012 RPMES Report
7. IV. RPMC Project Site Inspections
An inspection/validation of the Kabugao-Pudtol-Luna-Cagayan Boundary Road and the Road
Opening of Kabugao, Apayao-Solsona, Ilocos Norte Road (Apayao Side) was conducted by the
RPMC Inspectorate Team on October 9 - 10, 2012. These are regional priority projects and
major components of the Cordillera Roads Improvement Project (CRIP). The roads are among
Apayao national roads upgraded from secondary to arterial classification through DPWH
Memorandum dated November 2, 2011 by DPWH Secretary Rogelio Singson. This
memorandum was a result of an RDC-CAR dialogue with the DPWH Secretary held August 5,
2011 in Baguio City.
During the site inspection, the Kabugao-Pudtol-Luna-Cagayan Boundary Road is proceeding
smoothly having a status of 64.79 percent. The other project, the Kabugao, Apayao – Solsona,
Ilocos Norte Road, 0.50 percent status, was recently issued a resume order after a suspension
due to recent typhoons. It has been observed that the construction of several bridges in both
projects have to be programmed to make them passable. (Please refer to Annex C for
Inspection Reports)
5
Third Quarter CY 2012 RPMES Report
9. Third Quarter RPMES Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of September 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
SOCIAL SECTOR
1. Pantawid Pamilyang Pilipino DSWD 888.889 Loan 63.06%
Program (4Ps)
Slippage:
-3.62%
2. Red and Black School Building DepEd CY 2011: GOP CY 2011
Program 166.944 95.94%
209 Classrooms
CY 2012: CY 2012
115.200 34.16%
143 Classrooms
3. Cordillera-wide Strengthening of DOH & LGUs 43.00 JICA 5%
Local Health System for Effective Abra Apayao
and Efficient Delivery of Maternal Benguet
and Child Health Services
4. National Household Targeting DSWD 41.025 GOP, 59.41%
System for Poverty Reduction Loan
Program
5. Rehabilitation of School Building DepEd School Building GOP
including Water Sanitation CY 2011: CY 2011 Fund:
Facilities 15.468 88.92%
WATSAN
CY 2011: CY 2011 Fund:
15.861 96.48%
School Building
CY 2012: CY 2012 Fund:
28.633 Waiting for
SARO
WATSAN
CY 2012:
29.340
6. Philippine Response to Indigenous DepEd 3.978 AusAid 31%
People’s (IP) and Muslim
Education (PRIME) Slippage:
-51%
A-1
10. Third Quarter RPMES Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of September 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
7. Construction of Various Health DOH CY 2011: GOP CY 2011 fund:
Facility 117.867 58.55%
CY 2012: CY 2012 fund:
335.179 6.49%
8. Water Supply System DOH 184.500 GOP 76.64%
Sub-Total 1,985.883 52.82%
ECONOMIC SECTOR
9. Second Cordillera Highland DA 3,081.862 IFAD, 34.25%
Agricultural Resource ADB.
Management Project (CHARMP2) OFID Slippage:
-26.61%
10. Agrarian Reform Infrastructure DAR Total Project Loan 72.26%
Support Project Phase III Cost: GOP
(Abra, Apayao, Benguet, Ifugao, 903.863 Slippage:
Kalinga and Mt. Province) +22.25%
CY 2011:
(2 projects)
16.718
CY 2012:
(12 projects)
176.027
11. National Greening Program (NGP) DENR 124.339 GOP 73.44%
Slippage:
-19.63%
12. Farm-to-Market Roads DA CY 2011: Grant CY 2011:
(CY 2011 Fund: Abra, Kalinga and 53.00 85.66%
Mt. Province)
(CY 2012 Fund: Abra, Baguio City, CY 2012: CY 2012:
Benguet, Ifugao, Kalinga and Mt. 161.803 18.58%
Province)
A-2
11. Third Quarter RPMES Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of September 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
13. Irrigation Projects NIA 1,078.046 GOP 53.13%
(432 projects)
14. One Town One Product Program DTI 2.747 GOP 84.68%
(OTOP)
15. Rural Micro Enterprise Promotion DTI 1.800 IFAD with 90%
Programme (RuMEPP) GOP
Counter
Part
16. Shared Service Facilities Project DTI 8.388 NEDAC Awarding of
(SSF) Fund bidding
(National suppliers
Export
Develop-
ment and
Competi-
tiveness)
17. Small Enterprise Technology DOST 28.673 GOP 100%
Upgrading Program (SETUP)
Core and Non-Core Funded
Projects
18. Packaging and Labeling DOST 0.688 GOP 76%
Sub-Total 5,445.208 45.57%
INFRASTRUCTURE SECTOR
Abra
19. Abra-Ilocos Sur Road DPWH 106.195 GOP 55.25%
Slippage:
-8.68%
20. Abra-Kalinga Road, K0467+000- DPWH 147.691 GOP 14%
K0474+305
Slippage:
+2.67%
A-3
14. Third Quarter RPMES Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of September 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
36. Nueva Vizcaya-Ifugao-Mt. DPWH 54.163 GOP 65%
Province Road
Slippage:
-6.64%
Kalinga
37. Kalinga-Abra Road, K0470+000- DPWH 53.057 GOP 39.98%
K0472+267
Slippage:
-4.95%
38. Kalinga-Abra Road, K0476+000- DPWH 135.27 GOP 8.75%
K0480+1000, K0480+1000-
K0482+700 (with exceptions) Slippage:
+1.44%
39. Balbalan-Pinukpuk Road DPWH 100.00 GOP 87%
K0485+000-K0489+000 Slippage:
-9.40%
40. Balbalan-Pinukpuk Road DPWH 245.00 GOP 62%
K0560+1061-K0520+449 Slippage:
-10%
41. Mt. Province Bdry. –Calanan- DPWH 209.00 GOP 49.37%
Pinukpuk –Abbut Road (Pinukpuk)
(P209.0 M) K0499+674- Slippage:
K0509+294 (I.S.) -50.63%
42. Balbalan-Pinukpuk Road, Abut A DPWH 183.239 GOP Notice of
of Baay Bridge+(-18502) to Abut A award issued
of Baay Bridge+0 September 6,
2012. Contract
papers on
process.
A-6
15. Third Quarter RPMES Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of September 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
Mountain Province
43. Mt. Province –Ilocos Sur via Tue DPWH 81.815 GOP 31.17%
Road
Slippage:
-6.28%
44. Mt. Province-Ilocos Sur via Kayan DPWH 92.00 GOP 54.40%
Slippage:
-4.66%
Sub-Total 2,794.801 47.09%
STRATEGIC ACTION PLAN (SAP)
(Rehabilitation and Recovery of Areas Affected by Disasters)
45. Disaster Related Rehabilitation DPWH DRRP
Project (DRRP) Calamity
Fund
CY 2011
a. Apayao 1st District Engineering 74,550.0 87.73%
Office (16 projects)
b. Apayao 2nd District 14,000.0 100%
Engineering Office (5 projects)
c. Benguet 1st District 45,469.0 100%
Engineering Office (15
projects)
d. Benguet 2nd District 39,279.1 100%
Engineering Office (6 projects)
e. Baguio City District 600.0 100%
Engineering
Office (1 project)
f. Ifugao 1st District Engineering 8,580.0 100%
Office (2 projects)
g. Ifugao 2nd District Engineering 25,850.0 100%
Office (4 projects)
h. Kalinga District Engineering 85,910.5 95.93%
Office (9 projects)
i. Mt. Province District Office 102,459.4 100%
(28 projects)
A-7
16. Third Quarter RPMES Report
CY 2012 MAJOR PROGRAMS/PROJECTS
Cordillera Administrative Region
As of September 2012
IMPLEMENTING PROJECT COST FUNDING STATUS/
PROGRAM/PROJECT
AGENCY (PhP M) SOURCE REMARKS
Sub-Total 396.697 96.81%
46. Quick Response Fund (QRF) DepEd GOP
a. Cabaroan ES Dolores, Abra 1.202 56%
(Construction of 1 unit-2
classroom in Bldg.1)
b. Cabaroan ES Dolores, Abra 1.202 100%
(Construction of 1 unit-2
classroom in Bldg.2)
c. Cabaroan ES Dolores, Abra 318.0 79%
(Construction of 3 Seater
Toilet – type III with
handwashing)
d. Cabaroan ES Dolores, Abra 219.0 71%
(1 classroom repair)
e. Tonglo Carino PS, Buguias, 1.202 15%
Benguet
f. Talubin NHS, Bontoc Mt. 1.143 85%
Province
(Construction of 2cl /
Replacement of Burned Bldg.)
g. Tumog Es, Luna, Apayao 1.942 95%
(Construction of 1stry 3
Classroom 7x9 type I)
h. Lagawe CS, Lagawe, Ifugao 1.200 100%
(Construction of 2cl /
Replacement of Burned Bldg.)
i. Bañacao ES, Bangued West, 1.600 100%
Abra
(Repair of Classrooms /
Construction of Slope
Protection /Water System)
Sub-Total 10.027 80.56%
SAP Sub-Total 406.724 96.41%
CAR Total 10,632.616 49.27%
Sources: RLAs RPMES PMC Form I-1 and RPMES PMC Form I-2 as of September 2012.
A-8
18. Second Cordillera Highland Agricultural Resource Management Project
(CHARMP 2)
PROJECT PROFILE
Implementing Agency: Department of Agriculture-CAR
Fund Sources:
GOP: Department of Agriculture
Loan: IFAD, OFID, ADB
Grant: IFAD
Total Project Cost: Php 3,081,862,000
Location/Area Coverage: 6 provinces, 37 municipalities, 170 barangays
Abra: Lacub, Licuan-baay, Malibcong, Luba, Tubo, Sallapadan, Bucloc, Boliney
Apayao: Calanasan, Kabugao, Conner
Benguet: Bokod, Kabayan, Bakun, Kibungan,Buguias,Kapangan, Atok, Sablan,
Mountain Province: Barlig, Besao, Sadanga, Sagada, Bontoc, Tadian, Bauko, Sabangan
Kalinga: Balbalan, Pasil, Lubuagan, Tanudan, Tinglayan
Ifugao: Hingyon, Hungduan, Tinoc, Asipulo, Mayoyao
Description:
The project goal is to reduce the poverty and improve the livelihood of poor rural women and men in
indigenous communities in the upland areas of the Cordillera Administrative Region. The objectives are
to (1) increase the household income of poor farmers through sustainable agricultural development;
and (2) enhance the quality of life of targeted communities by improving land tenure security, food
security and watershed conservation.
The project has five components: (1) community mobilization, participatory planning of investments,
and land titling; (2) community watershed conservation (including forest management and agro forestry
development); (3) agricultural and agribusiness development, and promotion of income-generating
activities; (4) rural infrastructure development; and (5) project management and coordination.
Farm to market access Agro-forestry plots
B-1
Third Quarter CY 2012 RPMES Report
19. Second Cordillera Highland Agricultural Resource Management Project
Meeting with the beneficiaries& Project field assessment
PROJECT PROGRESS REPORT
As of September 2012
Project Duration:
Start: January 1, 2009 End: December 31, 2015
CY2009- CY2015
For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter
Target 49.72% 53.43% 57.15% 60.86%
Actual 18.45% 20.65% 34.25%
Slippage -31.27% -32.78% -22.90%
Cumulative Status: Status Physical Financial
(Since start of
Target 60.86% FOA+ Grant:
project)
Php 2,417.48
Actual 34.25% * Php 870.93 (36% of
FOA+Grant)
* (57.03% of the total
allotment released)
Php 1,527.073
from CY 2009-CY2012
Slippage -26.61%
B-2
Third Quarter CY 2012 RPMES Report
20. Current 1. Delayed implementation of infra subprojects due to difficulty of LGUs
Implementation in providing cash counterpart required as indicated in the NG-LGU
Issues and/or cost sharing policy.
Problems
Encountered 2. Approval of the proposed rural finance scheme/Livelihood Assistance
(if any): Finance (LAF) in place of the credit subcomponent.
3. Extension of OFID Loan Agreement which will close in July 2013
Actions Taken/ 1. The project is waiting for the approval of the proposed NG-LGU cost
Recommendations: sharing mix of 60%-40% for 1st-2nd class LGUs, 70%-30% for 3rd-6th
class LGUs from the NEDA Board. While waiting for its approval, the
Project recommended LGUs regardless of their classification to opt for
the cost-sharing arrangement included in the Project Financing
Agreement, where the CHARMP2 will shoulder 60% and LGUs will
provide 40% equity in order to proceed with the implementation of
proposed subprojects. However, only a few LGUs were able to provide
counterpart based on this scheme.
To initiate implementation of 25 submitted infra subproject proposals
from LGUs that could not afford said NG-LGU cost sharing scheme,
fund assistance from the DA-OSEC was sought to cover 30% of the
total cost of subprojects. The Project and the concerned LGUs are now
waiting for the release of CFA in the amount of Php 50 million from
the DA-OSEC.
As of June 2012, another batch of 71 subproject proposals was
submitted to DA-OSEC for fund support in the amount of Php 89
million.
2. Since the credit scheme as a subcomponent of the original Project
Design is not feasible for poor target beneficiaries in CAR, the Project
proposed for the Livelihood Fund Assistance (LAF) that would assist
livelihood and income generating activities of target groups. This
proposal is part of the revised Project Design which is now for
approval by the ICC/Government.
3. The Project requested for an extension of the loan validity to coincide
with the loan closing of the IFAD loan (June 2016). Request was
reiterated to DA-CO for submission to Department of Finance mid of
October 2012.
Remarks: The project is waiting for the final approval of the Revised Project Design
by NEDA ICC Board/ National Government.
B-3
Third Quarter CY 2012 RPMES Report
21. Agency Contact DIR. MARILYN V. STA. CATALINA, CESO IV
Person: Regional Executive Director, DA-RFU-CAR &
Project Director, CHARMP2
CAMERON P. ODSEY
Project Manager, CHARMP2
Address: PROJECT SUPPORT OFFICE
Baguio Stock Farm Compound, Marcos Highway corner Sto. Tomas Road,
2600 Baguio City
Telefax: +63.74.444.8329/ Tel No. +63. 74. 444.7991
Email: charm@mozcom.com
B-4
Third Quarter CY 2012 RPMES Report
22. Agrarian Reform Infrastructure Support (ARISP III)
PROJECT PROFILE
Implementing Agency: DAR-CAR / DPWH-CAR / NIA-CAR / LGUs
Fund Sources:
GOP:
Loan: JICA
Total Project Cost: Php 903,863,055.00
Project Cost (2011): Php 16.718 M
Loan/Grant Proceeds: Php 677,897,291.25
Peso Counterpart: Php 225,965,763.75
Project Cost (2012): Php 176.027 M
Location/Area Coverage:
Abra: Daguioman, Lacub and Luba ARCs
Apayao: Sta. Marcela, Flora and Pudtol ARCs
Benguet: Bakun, Kapangan and Kibungan ARCs
Ifugao: Asipulo, Hingyon and Tinoc ARCs
Kalinga: Tinglayan, Rizal and Pasil ARCs
Mt. Province: Sadanga, Bauko and Bontoc ARCs
Description:
The Agrarian Reform Infrastructure Support Project (ARISP) Phase III is a foreign-assisted
project of DAR, designed to provide basic support services to help develop Agrarian Reform
Communities (ARCs). It is funded from a concessional loan from the Government of Japan with
counterpart financing from the DAR, Local Government Units and the beneficiaries. The project
timetable is from CY 2008 to CY 2014.
The project espouses the concept of integrated area development in the ARCs wherein basic
infrastructure, organization / institutional, agricultural and enterprise development support are
combined to produce incremental growth in productivity and income among farmers.
Specifically, the project considers the provision of farm-to-market roads (FMR) and bridges,
irrigation projects, post-harvest facilities, and potable water supply system under its
infrastructure component.
For institutional development component, this entails the organizing and strengthening of
various organizations in the ARCs to build their capabilities to operate and manage the
infrastructure facilities and agri-business in a sustainable basis. The project also supports the
B-10
Third Quarter CY 2012 RPMES Report
23. development of viable agribusiness in the ARCs to harness the agricultural potentials, add value
to agricultural products, and make them more competitive in the market.
In CAR, actual project implementation commenced in CY 2011. From CY 2008 to 2010, the pre-
implementation activities conducted are indicative development planning, site validation,
project prioritization and individual project designs. There are 61 projects confirmed with an
aggregate cost of Php 903.86 M.
For CY 2011, two (2) projects (irrigation project and water system) were implemented and
recently completed with an aggregate cost of Php 16.72 M. These are located in the provinces
of Abra and Benguet.
DAR and NIA ARISP III Project Management Office representatives conducted Final Project
Inspection and Test Run of the newly rehabilitated Daguioman Communal Irrigation System ,
Daguioman, Abra with a service area of 89 hectares.
Completed Dalingoan Potable Water Supply System, Kapangan, Benguet. The project costing
P 2,094,916.00 will benefit around 89 Agrarian Reform Beneficiary Households.
B-11
Third Quarter CY 2012 RPMES Report
24. For CY 2012, 12 projects (10 irrigation projects and 2 FMRs) are programmed for
implementation with a total cost of Php 167.44 M. These are located in the provinces of
Apayao, Benguet, Ifugao, Kalinga and Mountain Province.
PROJECT PROGRESS REPORT
As of September 2012
Project Duration: Start: April 2008 End: April 2014
For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter
Target 29.16 % 48.87 % 45.26%
Actual 23.88 % 36.87 % 69.62%
Slippage (5.28%) (12.00 %) (24.36%)
Cumulative Status: Status Physical Financial
(Since start of project)
Target 50.01%
Actual 72.26%
Slippage 22.25%
Current 1. Undue project delay due to lack of equipment and manpower
Implementation Issues 2. Absence of DPWH QAU representative during inspection.
and/or Problems
Encountered (if any): 3. Inclement weather
Actions Taken/ 1. Conducted Strategy Planning and monthly Area Implementation
Recommendations: Team (AIT) meetings participated by representatives from DAR
Provincial / Municipal Office, DPWH, LGU and the Contractor to
draw catch-up plan.
Remarks:
Agency Contact DIR. FRANKLIN E. COCOY
Person: OIC-Regional Director, DAR-CAR
#39 m. Roxas St., Brgy. Tabora, Baguio City
ENGR. WILLIE GARCIA
445-4497
B-12
Third Quarter CY 2012 RPMES Report
25. Kabugao (Apayao)-Solsona (Ilocos Norte) Road
PROJECT PROFILE
Implementing Agency: Department of Public Works and Highways – CAR
Fund Source: GOP
Total Project Cost: Php 100 M.
Contract Cost: Php 89.089 M.
Location/Area Coverage: Barangay Madatag, Kabugao, Apayao
Description:
The road is a major component of the
Cordillera Roads Improvement Project
(CRIP) as lateral road; it connects Ilocos
Region and the Northern Cordilleras. It Kabugao-Apayao-
traverses the municipalities of Kabugao Solsona-Ilocos
and Calanasan in Apayao and turns west Norte Rd
to Solsona in Ilocos Norte.
The 76.48 km road stretch is a segment of
the San Nicolas-Solsona-Kabugao-Conner-
Abbut Lateral Road as Apayao’s direct
access to Laoag International Airport. The
road starts at PoblacionKabugao and ends
in Solsona. At the Ilocos Norte side,
concrete paving is being completed up to
the regional boundary. Approximately 10
km. is for opening at the Kabugao side.
Likewise, seven (7) major bridges are to be
constructed with a total length of 445 lm.
crossing several tributaries of the Apayao
River. However, the whole stretch
remains a gap (unpaved) even after the
project. PROJECT LOCATION
The road is among the Apayao national roads recently upgraded from secondary classification
to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson.
This memorandum was an immediate result of the RDC-CAR dialogue with Sec. Singson held at
the DPWH-CAR office on August 5, 2011.
The specific project output is road opening and gravelling of 9.56 kms.
B-13
Third Quarter CY 2012 RPMES Report
26. PROJECT PROGRESS REPORT
As of September 2012
Project Duration: Start: June 27, 2012 End: July 21, 2013
For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter
Target 0.50% 1.53%
Actual 0.50% 0.7%
Slippage -0.83%
Cumulative Status: Status Physical Financial
(Since start of
project) Target 2.03%
Actual 0.05% 8.88%
Slippage -1.98%
Current Project Suspension was issued on July 1, 2012 since the contractor
Implementation cannot mobilize due to series of slides and road cut along the 21 km
Issues and/or road leading to the project site.
Problems
Encountered (if any):
Actions Taken/ To address this, the DPWH-CAR requested DPWH-CO to utilize
Recommendations: savings for the removal of slides and restoration of road cuts costing
Php 2.38 M. This was eventually approved and the contractor was
advised to resume effective September 30, 2012.
Remarks:
Agency Contact DIR. EDILBERTO P. CARABBACAN
Person: Regional Director, DPWH– CAR
Engineer’s Hill
2600 Baguio City
Tel. 444-8838
B-14
Third Quarter CY 2012 RPMES Report
29. Kabugao-Pudtol-Luna Cagayan Boundary Road
PROJECT PROFILE
Implementing Agency: Department of Public Works and Highways – CAR
Fund Source: GOP
Total Project Cost: Php58.827 M.
Contract Cost : Php 49.574 M.
Location/Area Coverage: Barangays Swan and Mataguisi, Pudtol, Apayao
Description:
The road is a major component of the
Cordillera Roads Improvement Project
(CRIP) as the northern tip of the regional
backbone. The 95.7 km. road stretch Kabugao-Pudtol-
directly links the capital town Kabugao to Luna Cagayan
Lower Apayao, the seat of provincial Bdry Road
government and business growth center
in the Municipality of Luna.
The road starts at junction Lenneng along
the Kabugao-Conner-Abbut Road and
going north-east traverses municipalities
of Kabugao, Pudtol and Luna and ends at
Junction Luna in Abulug, Cagayan along
the Pan-Philippine Highway. The Pan-
Philippine Highway connects Laoag,
Ilocos Norte and Tuguegarao, Cagayan.
The gap at the Kabugao side (19.359
km.), traverses a rugged mountainous
terrain, then slowly goes down to the
Paco Valley, which was then proposed as
government center. The road will also
traverse the Mataguisi Valley in Pudtol. PROJECT LOCATION
The valleys have vast potential for
agricultural production.
The road is among the Apayao national roads recently upgraded from secondary classification
to arterial through DPWH Memorandum dated November 2, 2011 by Sec. Rogelio L. Singson.
This memorandum was an immediate result of the RDC-CAR dialogue with Sec. Singson held at
the DPWH-CAR office on August 5, 2011.
B-17
Third Quarter CY 2012 RPMES Report
30. The bridges across Apayao River (Babulayan Bridge) and tributaries Maton and Nagan Rivers
have been completed. However, two (2) more major bridges across Malilibag River (60 lm) and
Paco River (36 lm) are yet to be constructed to finally complete the road link. On top of this,
there are six (6) temporary bridges to be replaced with permanent bridge structures with a
total length of 90 lm.
The specific project output is road construction of 2.4 km. After the project, the road has still a
gap (unpaved) of 16.959 km.
PROJECT PROGRESS REPORT
As of September 2012
Project Duration: Start: February 20, 2012 End: December 12, 2012
For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter
Target 5% 50% 17.41%
Actual 5% 35.7% 26.81%
Slippage
Cumulative Status: Status Physical Financial
(Since start of project)
Target 67.41%
Actual 62.51% 69.49%
Slippage (4.90%)
Current Implementation The 4.9 % negative slippage is attributed to the work
Issues and/or Problems interruption during the past months due to inclement weather
Encountered (if any): caused by Typhoons Gener, Helen, and Igme.
Actions Taken/ To address this, the DPWH advised the contractor to provide
Recommendations: additional manpower and equipment to fast track
implementation.
Remarks:
Agency Contact Person: DIR. EDILBERTO P. CARABBACAN
Regional Director, DPWH– CAR
Engineer’s Hill
2600 Baguio City
Tel. 444-8838
B-18
Third Quarter CY 2012 RPMES Report
31. Mataguisi Valley
Babulayan Bridge across Apayao River
Junction Lenneng (Kabugao) Paco Valley
B-19
Third Quarter CY 2012 RPMES Report
32. National Greening Program (NGP)
PROJECT PROFILE
Implementing Agency: DENR–CAR
Fund Source: GOP
Total Project Cost: P124,339,000.00
Location/Area Coverage: Region wide
The locations are spread out all over the
six provinces of CAR including Baguio City
with a total area of 15,258 hectares to be
planted through social mobilization.
Description:
An administration priority program (Executive Order No. 26) that seeks to attain asustainable
Human development, economic and ecological security through the planting of 1.5 billion trees
in around 1.5 million hectares of public land within six years from year 2011 to 2016.
The NGP also aims to ensure food security, biodiversity conservation and address climate
change.
In the Cordillera, the target for CY 2012 is 7.5 million trees covering 15,000 hectares with a
project cost of Php 103.663 M. The project components are: (a) seedling production, Php
62.382 M; plantation site preparation; Php 17.469 M; and maintenance and protection, Php
23,812 M.
Seedling production (gmelina) of one of the
Seedling production (mahogany) of one
People’s Organization (PO) – Baroña Family
of the POs in Conner, Apayao
Association (BFA) in Poblacion, Lacub, Abra.
B-21
Third Quarter CY 2012 RPMES Report
33. Seedling production (mahogany) of one of
Seedling production (Benguet pine) of one the POs – Federation of Responsive
of the POs in Benguet Association for Magat Ecology Inc. in Ifugao
Seedling production (mahogany,
Seedling production (gmelina) of one of the narra&gmelina) of one of the POs in Natonin,
POs in Tabuk, Kalinga Mountain Province
Benguet Pine
B-22
Third Quarter CY 2012 RPMES Report
34. PROJECT PROGRESS REPORT
As of September 2012
Project Duration: Start: January 2012 End: December 2012
For CY 2012 AO 1st Quarter AO 2nd Quarter AO 3rd Quarter AO 4th Quarter
Target 11.16% 60.50% 21.41% 6.92%
Actual 14.49% 34.49% 24.46%
Slippage (3.33%) (26.01%) (3.05%)
Cumulative Status: Status Physical Financial
(Since start of project) Target 93.07% 95.71%
Actual 73.44% 95.71%
Slippage (19.62%) (0%)
Current 1. For the second year, project was delayed due the difficulty of
Implementation Issues following the prescribed procurement procedure. Seedlings
and/or Problems should be produced by the beneficiaries themselves, unlike
Encountered (if any): during the first year that these may be acquired from outside of
the project area.
2. Critical areas for tree planting due to climatic condition are: Abra,
Benguet and western Mountain Province. In these areas, tree
planting should be done only during rainy season.
Actions Taken/ 1. Procurement guideline was issued by DENR-CO to facilitate
Recommendations: implementation.
2. Adopted catch-up plan
Remarks:
Agency Contact Person: DIR. CLARENCE L. BAGUILAT
Regional Executive Director, DENR-CAR
No. 80 Diego Silang St., 2600 Baguio City, (442-4531, RD/F)
Mr. JOSEPH MAUTING
PMD, DENR-CAR (443-94-06)
B-23
Third Quarter CY 2012 RPMES Report
35. Red and Black School Building Program
PROJECT PROFILE
Implementing Agency: Department of Education-CAR
Fund Source: GOP
Total Project Cost:
(CY 2011) P166.944 M
(CY 2012) P115.200M
Location/Area Coverage: Region wide
Description:
The Regular School Building Program specifically targets schools which are categorized under
the Red Zone or those which have a ratio of 56 or more students to one classroom: and the
Black Zone, or schools which make use of makeshift classrooms and facilities.
The standard DepEd design is 7m x 9m classroom for rural areas with a classroom-student ratio
of 1:45. This standard also applies to all public secondary schools, regardless of location and
class size.
In CAR, the carry-over CY 2011projectshas a total project cost of Php166.944 M. covering 147
school sites for new 209 classrooms. The table below shows the details per province/city:
No. of No. of Status
Province/City sites(CY 2011) Project Cost
Classrooms (AO Sept. 2012)
Abra 18 16 18,427,000 90.43%
Apayao 21 26 15,812,000 96.57%
Benguet 18 28 25,793,000 100%
Ifugao 13 21 28,493,000 98.69%
Kalinga 41 65 44,636,000 95.12%
Mt. Province 30 34 20,042,000 90.45%
Baguio 6 10 13,740,000 100%
CAR 147 209 166,943,500 95.94%
B-24
Third Quarter CY 2012 RPMES Report
36. Mankayan Central School – On going construction (May 28, 2012)
Bulalacao National High School
Bangao National High School
B-25
Third Quarter CY 2012 RPMES Report
37. For CY 2012 projects, construction started during the second quarter. There are 147 school sites
to have 207 new classrooms with a total project cost of Php 115.2 M. The next table shows the
details per province/city:
No. of sites No. of Status
Province/City Classrooms Project Cost (AO Sept. 2012)
(CY 2012)
Abra 18 26 7,920,000 89.49%
Apayao 21 26 10,080,000 0%
Benguet 18 28 15,840,000 90.57%
Ifugao 13 21 10,800,000 27.24%
Kalinga 41 65 29,520,000 18.53%
Mt. Province 30 31 23,760,000 27.69%
Baguio 6 10 17,280,000 16.91%
CAR 147 207 115,200,000 34.16%
PROJECT PROGRESS REPORT
As of September 2012
Project Duration: Start: January End: December
st nd rd
For CY 2012 AO 1 Quarter AO 2 Quarter AO 3 Quarter AO 4th Quarter
Target
Actual (CY 2011) 8.44% 0.78% 6.72%
(CY 2012) 7.69% 26.47%
Slippage
Cumulative Status: Status Physical Financial
(Since start of project) Target
Actual (CY 2011) 95.94%
(CY 2012) 34.16%
Current Implementation
Issues and/or Problems
Encountered (if any):
Actions Taken/
Recommendations:
Remarks: Implementation of CY 2012 projects comments during this quarter.
Agency Contact Person: DIR. ELLEN B. DONATO
Regional Director
Wangal, La Trinidad, 2601 Benguet
B-26
Third Quarter CY 2012 RPMES Report
39. RPMC-CAR Inspection Report on the
Road Upgrading (Gravel to Concrete) along
Kabugao-Pudtol-Luna-Cagayan Boundary Road
conducted on 09 October 2012
1. The RPMC Inspectorate Team
The Regional Project Monitoring Committee (RPMC-CAR) Inspectorate Team conducted on
09 October 2012 a project-site inspection on the Kabugao- Pudtol-Luna- Cagayan Boundary
Road. This is a regional priority sectoral project implemented by the DPWH-CAR regional
office.
The RPMC member-agency representatives were the following:
Rene V. Valera, DILG-CAR Jerome B. Agaloos, NEDA-CAR
James M. Degsi, DBM-CAR Manilyn S. Dulay, NEDA-CAR
The Team was assisted by the following DPWH Apayao 2nd Engineering District and
Contractor’s representative:
ADE Rustom Martinez, DPWH Apayao II Galo Aplod, OCDC
Jerry Ragojos, DPWH Apayao II
Before the field inspection, the group paid courtesy to the Apayao Provincial Government
officials at the Provincial Capitol in Luna, Apayao. The Team met with the Provincial
Administrator Vincent Talattad and Chief Executive Atty. Xandred Claveria.
2. Project Profile
The road is a major component of the Cordillera Roads Improvement Project (CRIP) as the
northern tip of the regional backbone. It traverses the municipalities of Kabugao, Pudtol
and Luna in Apayao and turns east to Abulog in Cagayan. The 95.7 km. road stretch directly
links the capital town Kabugao to Lower Apayao, the seat of provincial government and
business growth center.
The road is among the Apayao national roads recently upgraded from secondary
classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec.
Rogelio L. Singson. This memorandum was an immediate result of the RDC-CAR dialogue
with Sec. Singson held at the DPWH-CAR office on August 5, 2011.
The bridges across Apayao River (Babulayan Bridge) and tributaries Maton and Nagan Rivers
have been completed. However, two (2) more major bridges across Malilibag River (60 lm)
C-1
40. and Paco River (36 lm) are yet to be constructed to finally complete the road link. On top of
this, there are six (6) temporary bridges to be replaced with permanent bridge structures
with a total length of 90 lm.
3. Project Basic Information
Specific Location Barangays Swan & Mataguisi, Pudtol,
Apayao
Station Limits KO 661+000 – KO 661+321 &
KO 643+520- KO646+080
Length of Road Project 2.4 km
Project Cost Php 58.827 M.
Contract Cost Php 49.574 M.
Source of Fund CY 2012 DPWH Regular Infra Program
Project Schedule Feb. 20, 2012 to Dec. 12, 2012
Contractor OCDC
Major Work Items PCCP (2.4 km), RCPC, stone masonry,
concrete curb & gutter and road signs
Project Status 64.79 %, slippage (2.62 %)
4. Findings
The road construction is smoothly on progress. The mere 2.62 % negative slippage is
attributed to the work interruption during the past months due to inclement weather
caused by Typhoons Gener, Helen, and Igme. To address this, the DPWH advised the
contractor to provide additional manpower and equipment to fast track implementation.
5. Comment(s)/ Recommendation(s)
The work progress is commendable. It is however recommended that the DPWH should
also prioritize the programming for the construction of the bridges across Paco River
(District I) and Malilibag River (District 2) to finally open the road up to Kabugao.
C-2
41. PHOTO DOCUMENTATION
On-going concreting of Kabugao-Pudtol-Luna-Cagayan Boundary Road
(2.4 km along Barangays Swan & Mataguisi section)
Completed Babulayan Bridge Concrete approach of Babulayan Recently completed road
across Bridge concreting project
Apayao River
EXIT CONFERENCE
The RPMC Inspectorate Team
Courtesy call on Apayao Provincial Administrator Vincent Talattad meets ADE Rustom Martinez,
and Chief of Staff Atty. Xandred Claveria DPWH Apayao II (L)
C-3
42. RPMC-CAR Inspection Report on the
Road Opening of Kabugao, Apayao- Solsona-Ilocos Norte Road (Apayao Side)
conducted on 10 October 2012
1. The RPMC Inspectorate Team
The Regional Project Monitoring Committee (RPMC-CAR) Inspectorate Team conducted on
10 October 2012 a project-site inspection on the Kabugao, Apayao- Solsona-Ilocos Norte
Road. This is a regional priority sectoral project implemented by the DPWH-CAR regional
office.
The RPMC member-agency representatives were the following:
Rene V. Valera, DILG-CAR Jerome B. Agaloos, NEDA-CAR
James M. Degsi, DBM-CAR Manilyn S. Dulay, NEDA-CAR
The Team was assisted by the following DPWH Apayao 1st Engineering District and LGU
Kabugao staff:
Antonio Baguec (PE), DPWH Apayao I Arne Paul Ligwang, LGU Kabugao
Domingo Enciso, DPWH Apayao I Harold Aboran, LGU Kabugao
The group paid courtesy and held separate exit conferences with DPWH Apayao 1st District
ADE Edward P. Magno and LGU Kabugao Municipal Administrator Romeo B. Tamot.
2. Project Profile
The road is a major component of the Cordillera Roads Improvement Project (CRIP) as a
lateral road. It directly connects Apayao Province to Ilocos Region. It traverses the
municipalities of Kabugao and Calanasan in Apayao and turns west to Solsona in Ilocos
Norte. The 76.48 km road stretch is a segment of the San Nicolas-Solsona-Kabugao-
Conner-Abbut Lateral Road as Apayao’s direct access to Laoag International Airport. At the
Ilocos Norte side, concrete paving is being completed up to the regional boundary.
The road is among the Apayao national roads recently upgraded from secondary
classification to arterial through DPWH Memorandum dated November 2, 2011 by Sec.
Rogelio L. Singson. This memorandum was an immediate result of the RDC dialogue with
Sec. Singson held at the DPWH-CAR office on August 5, 2011.
It was noted that even after the project, the whole stretch remains a gap until concreted.
Likewise, seven (7) major bridges are to be constructed with a total length of 445 lm.
crossing several tributaries of the Apayao River.
C-4
43. 3. Project Basic Information
Specific Location Barangays Madatag, Kabugao, Apayao
Station Limits KO 627+840 – KO 637+400
Length of Road Project 9.56 km
Project Cost Php 100 M.
Contract Cost Php 89.089 M.
Source of Fund CY 2012 DPWH Infra Program
Original Project Schedule June 27, 2012 to April 22, 2013
Suspension Order No.1 July 1, 2012
Resume Order No 1 September 30, 2012
Expected Completion July 21, 2013
Contractor PBO Construction
Major Work Items Roadway & drainage excavation, gravelling, stone
masonry & installation of cross drainages, catch
basins, common earth & solid rock excavation
Project Status 0.50 %
4. Findings
Project Suspension was issued on July 1, 2012 since the contractor cannot mobilize due to
series of slides and road cut along the 21 km section leading to the project site. To address
this, the DPWH-CAR requested DPWH-CO to utilize savings for the removal of slides and
restoration of road cuts costing Php 2.38 M. This was eventually approved and the
contractor was advised to resume effective September 30, 2012. Due to the slides and road
cuts, the group had to cruise Apayao River for two (2) hours using a motor-banca and hike
for an hour to reach the project site.
It was found out that the road alignment follows an old logging road of which some portions
were later widened by the AFP Engineering Brigade. Accordingly, the AFP had a military
camp at Barangay Madatag. The area has a vast potential for agriculture, water recreation
and Philippine eagle watching. The forest area along the river and within the Apayao-Ilocos
Norte boundary is a perfect eagle’s habitat.
5. Comment(s)/ Recommendation(s)
The leadership of Apayao Province and MLGU Kabugao in cooperation with the DPWH
Apayao I are commended for the swift conduct of a parcellary survey on August 2011 along
the road line to delineate private properties from road right-of-way (RROW). This was
among the conditions set by Secretary Singson prior to the issuance of the memorandum
and funding release.
For FY 2013-2016, the DPWH should program the construction of the seven (7) major
bridges with a total length of 445 lm. crossing several tributaries of the Apayao River.
Meanwhile, the contractor should immediately resume construction work.
C-5
44. PROJECT PHOTO-DOCUMENTATION
Actual Project Site at Barangay Madatag
Location: KO627+840-KO637+400
On July 1, 2012 the suspension order was issued since the contractor cannot mobilize due to series of
massive slides and road cuts along the 21 km section leading to the project site.
C-6
45. The DPWH-CO recently approved to utilized savings for the removal of slides and restoration of road
cuts costing Php 2.38 M. Consequently, the contractor was advised to resume effective Sept. 30, 2012
Location: KO627+840-KO637+400
The area has a vast
potential for
agriculture,
water recreation and
Philippine eagle
watching
C-7
46. Junction Kabugao, Apayao Kabugao section
Junction San Nicolas, Ilocos Norte
Solsona Welcome Arch
C-8
47. Ongoing concreting work, near regional boundary
COURTESY CALL and EXIT CONFERENCE
Exit conference with Kabugao Municipal
Administrator Romeo Tamot (2nd R)
With Engr. Domingo Enciso (R) and Exit conference with DPWH Apayao I
Kabugao Local Officials ADE Edward P. Magno (R) and Engr. Domigo Enciso
(L) and PE Antonio Banguec (2nd L)
C-9