7. Planned & Ongoing EE Measures
2011-2013
Sector EE Measure Remarks
Commercial Thermal Insulation in Government
Comm Buildings Order 2000
Residential Thermal Insulation in Government
Resid. Buildings Order 2011
Residential Improve EE in Lighting Cabinet
Approval
2012-2013
8. Planned & Ongoing EE Measures
2011-2013
Sector 1: Commercial
Electricity
Title and description of Implementation savings for
the EE measure period the years
2011-2013
Thermal Insulation 2000 - Present 200 GWhr
Bylaw in Commercial /year
Buildings
9. Planned & Ongoing EE Measures
2011-2013
Details of the Measure
Title of the measure Thermal Insulation Bylaw in Commercial Buildings
Objective To reduce Cooling Load requirements for new buildings
Description of the measure Enforce Bylaw and associated technical regulations
Implementing agency Electricity & Water Authority - Bahrain
Stakeholders involved Municipalities, Eng offices, Contractors, Building owners
Target group Commercial Sector
Program cost Negligible admin fees
Total resource cost NONE
Cost / kWh saved 0
Reduction of subsidies (22-16)/1000*200000*1000 = B.D. 1,200,000 per year
Source of funding NONE
Financial instruments NONE
Awareness Booklets, brochures, press releases, video clips, interviews, etc
Monitoring and quantification of impact Historical Data + Assessing Sector’s growth rate
10. Planned & Ongoing EE Measures
2011-2013
Sector 2: Residential
Electricity
Title and description of Implementation savings for
the EE measure period the years
2011-2013
Thermal Insulation 2011 - 215 GWhr
Bylaw in Residential /year
Buildings
11. Planned & Ongoing EE Measures
2011-2013
Details of the Measure
Title of the measure Thermal Insulation Bylaw in Residential Buildings
Objective To reduce Cooling Load requirements for new buildings
Description of the measure Enforce Bylaw and associated technical regulations
Implementing agency Electricity & Water Authority - Bahrain
Stakeholders involved Municipalities, Eng offices, Contractors, Building owners
Target group Residential Sector
Program cost Negligible admin fees
Total resource cost B.D. 122000 Per Year
Cost / kWh saved = 122000/(215000*1000) =B.D. 0.000567
Reduction of subsidies (22-6)/1000*215000*1000 = B.D. 3,440,000 per year
Source of funding Government
Financial instruments NONE
Awareness Booklets, brochures, press releases, video clips, interviews, etc
Monitoring and quantification of impact Historical Data + Assessing Sector’s growth rate
15. Planned & Ongoing EE Measures
2011-2013
Sector 2: Residential
Electricity
Title and description of Implementation savings for
the EE measure period the years
2011-2013
Improve Energy 2012 - 510 GWhr
Efficiency in Lighting: /year
Replace all Inc. Lamps
with CFL Lamps
16. Improve E.E. in Res Lighting
•To Replace Incandescent
Lamps with CFL Lamps
•Residential sector
•2012-2013
•Ban Incandescent Lamps
•Approved by Cabinet
17. Planned & Ongoing EE Measures
2011-2013
Details of the Measure
Title of the measure Improve Energy Efficiency in Residential Lighting
Objective To improve the lighting efficiency in Residential Sector
Description of the measure To replace inc. lamps with CFL in Residential sector & ban Inc.
Implementing agency Electricity & Water Authority - Bahrain
Stakeholders involved MOF, WB, Consumers’ Protection Society
Target group Residential Sector
Program cost B.D. 3,000,000
Total resource cost NONE
Cost / kWh saved = 3,000,000/(510*1000*1000) =B.D. 0.00588
Reduction of subsidies (22-6)/1000*510*1000*1000 = B.D. 8,160,000 per year
Source of funding Government
Financial instruments CDM may be considered later
Awareness Booklets, brochures, press releases, video clips, interviews, etc
Monitoring and quantification of impact Historical Data + Other studies
18. Summary of EE Measures
Sector EE Implementation Annual
Measure Period Saving
Commercial Thermal 2000 - present 200 GWH
Insulation in 20-30
Commercial MW Peak
Buildings
Residential Thermal 2011- 215 GWH
Insulation in 20-30
Residential MW Peak
Buildings
Residential Improve EE 2012-2014 510 GWH
in Lighting ~ 70 MW