Practical Training Report On
"Construction site of GIRLS HOSTEL MNIT JAIPUR”
Taken at
(CENTRAL PUBLIC WORKS DEPARTMENT)
Submitted to the
Rajasthan Technical University, Kota
in partial fulfillment of the Requirement for the
Award of degree of
BACHELOR OF TECHNOLOGY
BY
RAHUL JANGID
14CE39
DEPARTMENT OF CIVIL ENGINEERING
GOVT.ENGINEERING COLLEGE AJMER
Session 2017-18
2
TABLE OF CONTENT
TITLE PAGE NO
1. CERTIFICATE
2. ACKNOWLEDGEMENT
3. ABSTRACT
4. INTRODUCTION
4.1 ABOUT
4.2 LOCATION OF SITE
5 PROJECTDETAILS
5.1 FOUNDATION
5.2 FORM WORK
5.3 PALCING OF REINFORCEMENT IN A COLUMN
5.4 REINFORCEMENT PLACEMENT AND CASTING OF SLAB
5.5 TECHNOLOGY USED
6. QUALITY CONTROL
7. SAFETY
8. DAILY WORKREPORT ON SITE
9. conclusion
3
4
5
6
7
17
18
20
31
3
CERTIFICATE
4
ACKNOWLEDGEMENT
it is indeed a great pleasure and privilege to present this training report at GECA AJMER.
I am extremely grateful to my training and placement office for issuing a training letter,
which mode my training possible at CPWD, JAIPUR
I would like to express my gratitude to Er. MANU MITTLE for his invaluable suggestions
motivation, guidance and support through out the training. His methodology to start from
simple ant then deepen through mode me to bring out this project report without anxiety.
Thanks to all other CPWD officials, operator and all other members of CPWD, yet uncounted
for their help in completing the report and see the light of success.
I am thankful to friends, colleagues and all other persons who rendered their assistance
directly to complete this project work successfully.
I extended my due thanks to Er. AKASH GARG who gave me valuable time and
suggestions and guide me a lot at various stages of my Summer Training
DATE :AUG 2017 RAHUL JANGID
5
ASTRACT
Structural design is the primary aspect of civil engineering. The very basis of construction of
any building, residential house or dams, bridges, culverts, canals etc.is designing.
The foremost basic in structural engineering is the design of simple basic components and
members of a building viz. slabs, beam, columns and footings for their design, an
architectural design is prepared using the auto CAD . in order to design them it is important to
first obtain the plan of the particular building that is positioning of the particular rooms such
that they serve their respective purpose and suitability. Plan layout of beam and the position
of columns are fixed. Thereafter, the vertical loads are calculated namely the dead load and
live load from IS: 875
In this project the design of G+5 floors hostel building is done according to the Indian
standards IS456 has been used for the reinforcement design IS 875 has been used for the
estimation of all the loads on the structure viz. dead load, live load, and wind load, once the
loads are obtained, the slabs are designing of slabs depends upon whether it is one way or
two way slab the end conditions and the loading the analysis and designing of beam &
columns are done by the “STAAD PRO” software tool. The footing are designed manually
after completion of designing estimation has to be carried out.
6
INTRODUCTION
ABOUT:
The Central Public Works Department of India is a Central Government owned authority
that is in charge of public sector works in the country. Central Public Works Department
(CPWD) under Ministry of Urban Development is entrusted with construction and
maintenance of buildings for most of the Central Government Departments, Public
undertakings and autonomous bodies.
In the Indian History both pre and post independence - CPWD has a glorious era of more
than 150 year with dedicated, energetic and committed corps of Engineers and Architects.
Before being re-structured to its present form in 1930 “Central Public Works Department”
originated in July 1854 when the Governor General of India decided to set up a Central
Agency:
“to exercise universal control over public works in India with best of scientific
knowledge with authority & system”.
Central Public Works Department, delhi is the premier agency of Govt. of India engaged in
planning, designing, construction and maintenance of Government assets in the field of built
environment and infrastructure development. Assets in built environment include Hospital
Schools, Colleges, Technical Institutes, Police Buildings, Prisons, Courts,hostels etc;
assets in infrastructure development include Roads, Bridges, Flyovers, Footpaths, Subways
etc. CPWD Delhi also sustains and preserves these assets through a well developed system of
maintenance which includes amongst others specialized services like rehabilitation works,
roads signage and aesthetic treatments like interiors, monument lighting, landscaping.
Page 7
PROJECT OVERVIEW
SITE LOCATION
MNIT, JAIPUR AT NEAR CPWD DEPARTMENT ,GANGA GIRLS HOSTEL BUILDING
Advantages of this site
: Land : Store
: Parking space : Health unit
: Transportation facilities
Image 1 Foundation stone
Image 2: of construction site
Page 8
Construction of “Ganga Girls Hostel MNIT Jaipur,at JLN Marg,Malviya Nagar
Jaipur(Raj.) (SH: C/o Girls hostel Building, Electric sub Station & External
Development Work i.e. Internal Electrical Installations)
884 seatedgirls hostel.
single seatedrooms- 454
triple seatedrooms-141
Rooms physically challenged students-7
LETTER NO. : F8(63)/Vmnit/E/v2014-15/v532
NAME OF CONTRACTOR: BCC Pvt. Ltd. Building Better Future
SIZE PLOT 110m*90m
ESTIMATED COST:
Civil Work- Rs 68,38,2017 /-
Electric-Work- Rs 11,63,9120/-
Total Cost- Rs 80,02,11037/-
DATE OF START: oct 2015
Page 9
FOUNDATION
Footings are strips of concrete or filled concrete blocks placed under foundation wall. Gravel
or crushed stone footings may also be used. The purpose of footing is to transfer the loads
safely in the ground.
1.IsolatedFooting-
An isolated footing is used to support the load on a single column. It is usually either square
or rectangular in plan. It represents the simplest, most economical type and most widely used
footing. Whenever possible, square footings are provided so as to reduce the bending
moments and shearing forces at their critical sections. Isolated footings are used in case of
light column loads, when columns are not closely spaced.
Image3: of isolated column
2.combinedfooting:-
A footing which has more than one column is called as combined footing. This kind of
footing is adopted when there is a limited space. Due to lack of space we cannot cast
individual footing, Therefore footings are combined in one footing.
Page 10
Image 4: of combined footing
foundation and plinth-
• RCC M25 Grade Concrete in strip/isolated footing with grade/plinth beam.
• 230 mm thick fly ash brick masonry work from grade beam to plinth level.
• M25 grade RCC slab at ground floor/plinth level.
Image 5: plinth beam
Super structure-
RCC frame structure having M25 grade, beam column and slab.
 All external walls shell be with 230 mm thick with fly ash bricks and all partition
walls shall be with half brick thickness fly ash in cement mortar 1:4
Page 11
Flooring and dado work-
 Ceramic wall and floor tiles in all toilets.
 Mirror polished Kota stone flooring rooms, corridors and stairs with marble pattern.
 Rubbed sandstone flooring in courtyard.
 Vitrified tiles in food court, visitors room etc.
Roofing:-
 Brick bat coba for water proofing on roof top and heat resistant tiles over coba
treatment.
 UPVC pipes for rain water drainage
Image 6: thermal tiles
Brick masonry-
The common materials of masonry construction are brick, building stone such
as marble, granite, travertine, and limestone, cast stone, concrete block, glass block, and cob.
Masonry is generally a highly durable form of construction.
Image 7: brick masonry at construction site
Page 12
FORM WORK
Formwork is a mould or die used to support or shape the concrete until it attains sufficient
strength to carry its self-weight. Formwork holds the concrete until it hardens to required
shape & size.
Significance of formwork-
A-Formwork constitutes 30% of cost & 60% of time in concrete construction.
B-Quality of concrete finish and soundness of concrete depends very much on type of
formwork system.
C-Desired shape of concrete is not possible if formwork is not done properly.
D-Formwork should be properly designed fabricated and erected to receive concrete.
E-Accident happen because of faulty formwork and scaffolding or staging.
Safety in using formwork-
-Components are light in weight for manual holding.
-Appropriate use of tools.
-Loose or hanging components are minimal.
Image 8: formwork of a column
Page 13
PALCING OF REINFORCEMENT IN A COLUMN
Lateral ties 8mm dia provided@150mm c/c in a column
Image 9 : Longitudinal steel bars of 20mm dia provided in a column
LATERAL TIES WITH 135* BEND
Page 14
REINFORCEMENT PLACEMENT AND CASTING OF SLAB
At there I was involved while placement of reinforcement bar for monolithic construction of
concrete slab with beam.
Reinforcement in the slab with alternate bent up bars provided at supports in order to provide
negative reinforcement at support in two way slab In concreting, concrete pump, needle
vibrator etc. were used
Page 15
Image 10: in next day of slab casting
Technology used
Generally at site survey is carried out by following two instruments
: Auto level
: Total station
Other instruments are use in casting
: Mixer
: niddle vibretor
: pumping machine
A-Total Station A total station is an electronic/optical instrument used in modern Surveying
and building construction. The total station is an electronic theodolite (Transit) integrated
with an electronic distance meter (EDM) to read slope Distances from the instrument to a
particular point. By this instrument we can Measure Angle, Distance, Coordinate and also
Data Processing.
Page 16
Advantages: The following are some of the major advantages of using total station over the
conventional surveying instruments
1. Field work is carried out very fast.
2. Accuracy of measurement is high.
3. Manual errors involved in reading and recording are eliminated.
B-Auto level- It is a leveling instrument which was on site checking the elevations of various
points.
Auto level is a modified form of dumpy level. We used auto level to transfer the level of
ground to retaining wall and setting thickness of slab in which first of all marking was made
to fix the level of particular elevations then casting of slab was performed
Transferring of surface level to retaining wall
1 – Set the auto level at the building floor level.
2 – level the instrument
3 – Take the staff reading at point also on floor level surface.
4 – Locate the staff on the formwork of retaining wall and adjust the staff in such a way so
that reading of staff is same as staff reading in step 3.
Image 11: transfer the concrete and use of niddle vibrator
Page 17
Grinding machine-
This the power mechanically operated machine which is used to mix the concrete.it consist of
a hollow cylindrical part with wing inside it.in which cement, sand, aggregate and water is
mixed
Transportation-
The Process of carrying the concrete mixture from the place of its mixing to
final position of deposition is transportation.
Method of transportation -
1. transport of concrete by pan
2. transport of concrete by wheel barrow
3. transport of concrete by T.M.
4. transport of concrete by tipping lorries
5. transport of concrete by pumps
6. transport of concrete by belt conveyors
At this site transit mixture(T.M.) are using
Image 12 : transit mixture at site
Page 18
Batching Plant-
concrete plant, also known as a batch plant or batching plant or a concrete batching plant, is
equipment that combines various ingredients to form concrete. Some of these inputs
include water, air, admixtures, sand, aggregate (rocks, gravel, etc.), fly ash, silica fume, slag,
and cement
Image 13 : batching plant and machine
Tower Crane- The tower cranes belong to essential building machines which are widely
used for transport of the construction products from storage area or vehicle to their final
positions in process of building-up of the constructions. Their positioning affects a fluency,
costs and total consumed time of building-up.
Image 14 : Tower crane at site
Page 19
QUALITY:-
The technical audit of works done by CPWD used to be done in-house right from its
inception. The functions of Quality Assurance and Technical Audit of works were shifted to
CVC in the year 1964. On the recommendation of Ranganathan Committee, the Quality
Assurance functions were again shifted to CPWD in the year 1979.
The implementation of Quality Assurance in the field will require close co-operation among
the three agencies, namely
(a) field engineers
(b) the construction agency
(c) the Quality Assurance team at Circle level for strict compliance of Quality Assurance
Procedure forming part of agreement.
Quality Control team at Circle Level
To keep a watch on the effectiveness/adequacy of Quality Assurance measures at site, a
Quality Assurance team with SE of the circle as its head and comprising of one AE.
The functions of the Quality Assurance team at Circle level are to check the compliance of
Quality Assurance system by the field units, to locate the lapse/deficiency in the
implementation of the Quality Assurance Plan, and to guide the field engineers in quality
related aspects of the work
Quality Assurance units in the Regions
Quality Assurance works in various Regions are being looked after by the Regional QA units
headed by the Superintending Engineer (TLQA) or Director Works of the Region
Page 20
SAFETY INDUCTION
Safety is very important part of any work. An induction video was showed which highlighted
the need and importance of safety at construction site. Most accidents can be prevented by
taking simple measures or adopting proper working procedures. It is very important to
discuss issues on safety and health that should be paid attention to on construction sites for
easy reference by the workers. If we work carefully and take appropriate safety measures,
there will definitely be fewer work injury cases, and our sites will become a safe and secure
place to work in. It is important to educate everyone in the site regarding safety for following
purposes.
 Workers safety
 Construction progress
 Standard procedure
 Legal cases
 Working efficiency
Precautions at site for safety-
 Wear protective equipment.
 Do not drink or take drugs while working
 Pay attention to personal hygiene
 Do not play in the workplace
 Report to your supervisor immediately if you notice any unsafe condition.
Equipment used for safety at construction site-
NETS
DAILY WORK
Page 21
WEEK 1
1st
Day
Training Location:- MNIT (Jaipur)
Today’s Duties:- To Visit training location
Working On:- visiting (analysis entire site)
Technology:- NO technology used at first day
Key learning:- pumping station ,batching plant, plastering, reinforcement determination
2nd
Day
Training Location:- MNIT , Jaipur (block No:5A) floor No:04
Today’s Duties:- To learn how to distribute Reinforcement on floor
Working On:- distribution of Reinforcement on floor(slab)
Technology:- grinder machine, inch tape etc.
Key learning:- cutting of Reinforcement ,leveling of slab
3rd
DAY
Training Location:- MNIT ,Jaipur (block No:5A)
Today’s Duties:- To learning of reinforcement distribution of slab
Working On:- cross check the pervious spreading of reinforcement
Technology:- auto level ,inch tap (including withdrawing)
Key learning:- To operate auto level
4th
DAY
Training Location:- MNIT ,Jaipur (block No:5A) floor nub:04
Today’s Duties:- To about slab casting
Working On:- slab casting, concrete mixture
Technology:- continuous batching ,mixture, pumping station, mechanical vibrator
Key learning:- slab casting
Page 22
5th
DAY
Training Location:- MNIT (Jaipur) block nub 5A
Today’s Duties:- To learn about finishing work
Working On:- plastering
Technology:- plumb bob, threat, trowel, platter
Key learning:- how to check plastering is in level
6th
DAY
Training Location:- MNIT (Jaipur) block nub 5A
Today’s Duties:- To learn about the finishing work
Working On:- finishing work (walls)
Technology:- plumb bob, trowel, platter etc.
Key learning:- straightness of walls
2nd
WEEK
1st
DAY
Training Location:- MNIT (Jaipur) block Nub 5 upper most floor
Today’s Duties:- To learn about the casting of the tank
Working On:-reinforcement distribution for tank casting finishing work on casting of the tank
Technology:- grinder, cutter, machine crane, plates pumping stations etc.
Key learning:- measurement of the tank
2nd
DAY
Training Location:- MNIT (Jaipur) block nub 5 upper most floor
Today’s Duties:- To learning about the casting of the tank
Working On:- to cross check the reinforcement distribution of tank, shuttering work on tank
and finishing work
Technology:- inch tape, etc.
Key learning:- shuttering work
Page 23
3rd
DAY
Training Location:- MNIT (Jaipur) block nub 5 upper most floor
Today’s Duties:- To learn about the finishing work
Working On:- finishing work on roof (to give slope) placing on heat resisting tiles on roof
Technology:- inch tape, trowel, platter etc.
Key learning:- to take a slope
4th
DAY
Training Location:- MNIT (Jaipur) block nub 5 upper most floor
Today’s Duties:- To learn about the casting of the tank
Working On:- casting of the tank.
Technology:- vibrator, pumping station
Key learning:- use of vibrator
5th
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- To learn about the auto level
Working On:- auto level ( leveling of field),excavation work
Technology:- JCB, plumb bob, auto level, trowel, platter ,stone cutter etc.
Key learning:- excavation
6th
DAY
Training Location:- MNIT (Jaipur) all blocks
Today’s Duties:- To visiting all blocks
Working On:- just impactions (to see all work)
Technology:- auto level etc.
Key learning:- cross check of plastering, leveling of shuttering
3rd
WEEK
Page 24
1st
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- excavation , measurement
Working On:- excavation , measurement of the field
Technology:- JCB, inch tape etc.
Key learning:- measurement
2nd
DAY
Training Location:- MNIT (Jaipur) block nub 5A
Today’s Duties:- cladding stone work
Working On:- cladding work on block 5A
Technology:- stone ,iron frame, nut bolt etc.
3rd
DAY
Today’s Duties:- see cladding stone work
Working On:- cladding stone work on 5A block & area calculate of cladding
Technology:- stone , nut bolts, steel frame etc.
Key learning:- providing cladding
4th
DAY
Today’s Duties:- calculate the area of cladding stone work
Working On:- calculate area of open space and calculate area of cladding work
Technology:- inch tape ,scaffolding etc.
Key learning:- calculate
5th
DAY
Training Location:- MNIT (Jaipur) block nub 5A & 04
Today’s Duties:- to see the plastering work
Working On:- plaster work on their blocks
Technology:- plumb bob, trowel, thread etc.
Page 25
6th
DAY
Training Location:- MNIT (Jaipur) block nub 5A & 05
Today’s Duties:- to see the plastering work and cladding stone work
Working On:- plaster work on their blocks
Technology:- plumb bob, trowel, thread etc.
Key learning:- to find mistakes in cladding stone work
4TH
WEEK
1st
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- to see the working on T.S layout
Working On:- To see the T.S. to find the coordinate of column (footing)
Technology:- T.S. , marker, thread etc.
Key learning:- working on T.S
2nd
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- to see the P.C.C. work
Working On:- P.C.C. work
Technology:- concrete mixture ( transits Batching mixture)
Key learning:- how to do P.C.C. work
3rd
DAY
Training Location:- MNIT (Jaipur) block nub 01
Today’s Duties:- to see the masonary work
Working On:- masonary work
Technology:- platter trowel, plumb bob etc.
Key learning:- masonary work
Page 26
4th
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- to cross check leveling of P.C.C. work& to providing slope
Working On:- leveling of the footing
Technology:- auto level, cross staff, inch tape etc.
Key learning:- providing slope
5th
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- footing work & column reinforcement
Working On:- footing work & column reinforcement
Technology:- plumb bob , binding wire, concrete mixture etc.
Key learning:- footing work
6th
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- calculate quantity of concrete for footing work
Working On:- calculate quantity of concrete
Technology:- inch tape
Key learning:- calculate quantity of concrete for footing only
6th
WEEK
1st
DAY
Training Location:- MNIT (Jaipur) block nub 6A
Today’s Duties:- To learn about the finishing work
Working On:- plastering, partitions work
Technology:- plumb bob, threat, etc.
Key learning:- flow to check , plastering is in level or not
Page 27
2nd
DAY
Training Location:- MNIT (Jaipur) block nub 5 upper most floor
Today’s Duties:- To learn about the casting of tank
Working On:- casting of the tank
Technology:- needle vibrator, batching mixture plant.
Key learning:-use of vibrator
3rd
DAY
Training Location:- MNIT (Jaipur) block nub 6A
Today’s Duties:- To learn about the finishing work
Working On:- finishing work (walls)
Technology:- plumb bob, threat, etc.
Key learning:- strength of walls
4th
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- To learn about the auto level finishing work
Working On:- auto level machine, plumb bob, stone cutter
Technology:- plumb bob, auto level
Key learning:- auto level work
5th
DAY
Training Location:- MNIT (Jaipur) block nub 8
Today’s Duties:- cladding of stone work
WorkingOn:- claddingof stone workon blocks
Technology:- stone ,steel frame ,nutbolt
Keylearning:- providingof claddingstone work
6th
DAY
Training Location:- MNIT (Jaipur) all block
Page 28
Today’s Duties:- visiting all blocks
Working On:- to see all works on site
Technology:- all technological equipment
Key learning:- finishing , casting, concreting
7th
WEEK
1st
DAY
Training Location:- MNIT (Jaipur) block nub 2A
Today’s Duties:- finishing work
Working On:- partition works ,masonary work
Technology:- thread, plumb bob, trowel, platter etc.
Key learning:- finishing work
2nd
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- footing work & column reinforcement
Working On:- footing work, column reinforcement.
Technology:- plumb bob, binding wire, concrete mixture etc.
Key learning:- footing work
3rd
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:-to see P.C.C work
Working On:- P.C.C. work
Technology:-concrete mixture
Key learning:- learn about P.C.C. work
4th
DAY
Training Location:- MNIT (Jaipur) block nub 7
Today’s Duties:- to see masonary work
Page 29
Working On:- masonary work
Technology:-thread , plumb bob, trowel, platter etc.
Key learning:- mesonary work
5th
DAY
Training Location:- MNIT (Jaipur) block nub 8
Today’s Duties:- to know how to provide ramp
Working On:- reinforcement detailing of ramp, slope of ramp
Technology:-drawing
Key learning:- ramp providing , slope providing
6th
DAY
Training Location:- MNIT (Jaipur) block nub 8
Today’s Duties:- to cross check reinforcement detailing for slab
Working On:- cross check reinforcement detailing on slab
Technology:- drawing , inch tape etc.
Key learning:- to read drawing
8th
WEEK
1st
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- to see working on T.S. layout
Working On:- to see T.S. to final the co-ordinate of the column
Technology:- T.S , marker, thread etc.
Key learning:- working on T.S.
2nd
DAY
Training Location:- MNIT (Jaipur) all block
Today’s Duties:- visiting all blocks
Working On:- to see all works on site
Page 30
Technology:- all technological equipment
Key learning:- finishing , casting, concreting
3rd
DAY
Training Location:- MNIT (Jaipur) block nub 7A
Today’s Duties:-to know how to provide roof
Working On:- reinforcement detailing of ramp, slope of ramp
Technology:-drawing, inch tape etc.
Key learning:-slope providing
4th
DAY
Training Location:- MNIT (Jaipur) block nub 8A
Today’s Duties:- to check the beam
Working On:- cross checking , beam using drawing
Technology:- inch tape , drawing
Key learning:- read drawing
5th
DAY
Training Location:- MNIT (Jaipur) block 8A
Today’s Duties:- to cross check reinforcement detailing for slab.
Working On:- cross checking reinforcement detailing on slab (floor)
Technology:- drawing , inch tape etc.
Key learning:- to read the drawing.
6th
DAY
Training Location:- MNIT (Jaipur) all block
Today’s Duties:- to cross check the construction block with site engineer
Working On:- error found on chamber ,reconstruction of chamber
Technology:- thread , inch tape, plumb bob
Key learning:- masonary work &joining of sewer, finishing work
Page 31
CONCLUSION
The provision of summer training as the curriculum of undergraduate technical courses is a
very appreciable step which I consider as a great opportunity to see real life application of
materials which we have already studied and seen in our textbooks or our day to day life.
The opportunity to work at a location with such an organization was really a great experience
and fun .
There were several things to learn and experience. Learning to apply the studied concepts and
phenomena was really enjoyable .
Various things which couldn’t have been possible theoretically were possible to be learnt .
Interaction with workers and and local public was also a great experience.
All over the whole process was a memorable one and quite informative .

Mais conteúdo relacionado

Mais procurados

Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCCRakshita Raghunath
 
Central Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportCentral Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportAman Gupta
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineeringalok0025
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION L&W BUILDING SOLUTIONS PVT. LMT.
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential buildingSumit Singh
 
Multistorey residential building construction training report
Multistorey residential building construction training  reportMultistorey residential building construction training  report
Multistorey residential building construction training reportBeing Deepak
 
training report civil engg. 7th sem
training report civil engg. 7th semtraining report civil engg. 7th sem
training report civil engg. 7th semRajat kashv
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanAnis Rahman Khokan
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge ConstructionMAHAVIR MEENA
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONVed Jangid
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship reportMd Mohsin Mohsin
 
Industrial trainning project report for Civil Engineering
Industrial trainning project report for Civil EngineeringIndustrial trainning project report for Civil Engineering
Industrial trainning project report for Civil EngineeringPrakash Kumar Jha
 
training report on commercial building
training report on commercial buildingtraining report on commercial building
training report on commercial buildingSumit Saini
 
Civil enginerring internship report
Civil enginerring internship reportCivil enginerring internship report
Civil enginerring internship reportZahid Khan
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training pptSumit Singh
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORTFresher Thinking
 
Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Ram1239
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGAmritpal Singh
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTIONMd Shadab
 

Mais procurados (20)

Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCC
 
Central Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportCentral Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training report
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineering
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential building
 
Multistorey residential building construction training report
Multistorey residential building construction training  reportMultistorey residential building construction training  report
Multistorey residential building construction training report
 
training report civil engg. 7th sem
training report civil engg. 7th semtraining report civil engg. 7th sem
training report civil engg. 7th sem
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman Khokan
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
Bridge report
Bridge reportBridge report
Bridge report
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship report
 
Industrial trainning project report for Civil Engineering
Industrial trainning project report for Civil EngineeringIndustrial trainning project report for Civil Engineering
Industrial trainning project report for Civil Engineering
 
training report on commercial building
training report on commercial buildingtraining report on commercial building
training report on commercial building
 
Civil enginerring internship report
Civil enginerring internship reportCivil enginerring internship report
Civil enginerring internship report
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
 
Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTION
 

Semelhante a Construction Site Report of Girls Hostel at MNIT Jaipur

Report sheet on u boot beton
Report sheet on u boot betonReport sheet on u boot beton
Report sheet on u boot betonAmish Raj
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxNaveenVerma126
 
ANALYSIS AND DESIGN OF BRIDGE FOUNDATION
ANALYSIS AND DESIGN OF BRIDGE FOUNDATIONANALYSIS AND DESIGN OF BRIDGE FOUNDATION
ANALYSIS AND DESIGN OF BRIDGE FOUNDATIONScott Donald
 
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET Journal
 
IRJET- Analysis and Design of Flyover by using Staad Pro
IRJET- Analysis and Design of Flyover by using Staad ProIRJET- Analysis and Design of Flyover by using Staad Pro
IRJET- Analysis and Design of Flyover by using Staad ProIRJET Journal
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...Firdaurs Abdullah
 
CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGEAnkit Gautam
 
Site report assignment
Site report assignmentSite report assignment
Site report assignmentSze Ting Kuek
 
IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)IRJET Journal
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report finalShubham Parab
 
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...IAEME Publication
 
IRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump HouseIRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump HouseIRJET Journal
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiJaspreet singh
 
Summer training report
Summer training reportSummer training report
Summer training reportaki8872233
 
Internship report with background
Internship report  with backgroundInternship report  with background
Internship report with backgroundKazim sultani
 
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET Journal
 

Semelhante a Construction Site Report of Girls Hostel at MNIT Jaipur (20)

JEEVA.pptx
JEEVA.pptxJEEVA.pptx
JEEVA.pptx
 
Final report 85,91,109
Final report 85,91,109Final report 85,91,109
Final report 85,91,109
 
Report sheet on u boot beton
Report sheet on u boot betonReport sheet on u boot beton
Report sheet on u boot beton
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
 
Ayush
AyushAyush
Ayush
 
ANALYSIS AND DESIGN OF BRIDGE FOUNDATION
ANALYSIS AND DESIGN OF BRIDGE FOUNDATIONANALYSIS AND DESIGN OF BRIDGE FOUNDATION
ANALYSIS AND DESIGN OF BRIDGE FOUNDATION
 
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete BridgeIRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
IRJET - Repair and Rehabilitation of Reinforced Concrete Bridge
 
IRJET- Analysis and Design of Flyover by using Staad Pro
IRJET- Analysis and Design of Flyover by using Staad ProIRJET- Analysis and Design of Flyover by using Staad Pro
IRJET- Analysis and Design of Flyover by using Staad Pro
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
 
CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGE
 
Site report assignment
Site report assignmentSite report assignment
Site report assignment
 
induarial trainin report
induarial trainin reportinduarial trainin report
induarial trainin report
 
IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)IRJET- Design of Railway Foot Over Bridge (Shelu)
IRJET- Design of Railway Foot Over Bridge (Shelu)
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
USE OF PARTIAL PREFABRICATION AND NONTRADITIONAL TECHNOLOGY IN CONSTRUCTION O...
 
IRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump HouseIRJET- Structural Analysis and Design of Pump House
IRJET- Structural Analysis and Design of Pump House
 
Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Internship report with background
Internship report  with backgroundInternship report  with background
Internship report with background
 
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
 

Último

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Último (20)

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Construction Site Report of Girls Hostel at MNIT Jaipur

  • 1. 1 A Practical Training Report On "Construction site of GIRLS HOSTEL MNIT JAIPUR” Taken at (CENTRAL PUBLIC WORKS DEPARTMENT) Submitted to the Rajasthan Technical University, Kota in partial fulfillment of the Requirement for the Award of degree of BACHELOR OF TECHNOLOGY BY RAHUL JANGID 14CE39 DEPARTMENT OF CIVIL ENGINEERING GOVT.ENGINEERING COLLEGE AJMER Session 2017-18
  • 2. 2 TABLE OF CONTENT TITLE PAGE NO 1. CERTIFICATE 2. ACKNOWLEDGEMENT 3. ABSTRACT 4. INTRODUCTION 4.1 ABOUT 4.2 LOCATION OF SITE 5 PROJECTDETAILS 5.1 FOUNDATION 5.2 FORM WORK 5.3 PALCING OF REINFORCEMENT IN A COLUMN 5.4 REINFORCEMENT PLACEMENT AND CASTING OF SLAB 5.5 TECHNOLOGY USED 6. QUALITY CONTROL 7. SAFETY 8. DAILY WORKREPORT ON SITE 9. conclusion 3 4 5 6 7 17 18 20 31
  • 4. 4 ACKNOWLEDGEMENT it is indeed a great pleasure and privilege to present this training report at GECA AJMER. I am extremely grateful to my training and placement office for issuing a training letter, which mode my training possible at CPWD, JAIPUR I would like to express my gratitude to Er. MANU MITTLE for his invaluable suggestions motivation, guidance and support through out the training. His methodology to start from simple ant then deepen through mode me to bring out this project report without anxiety. Thanks to all other CPWD officials, operator and all other members of CPWD, yet uncounted for their help in completing the report and see the light of success. I am thankful to friends, colleagues and all other persons who rendered their assistance directly to complete this project work successfully. I extended my due thanks to Er. AKASH GARG who gave me valuable time and suggestions and guide me a lot at various stages of my Summer Training DATE :AUG 2017 RAHUL JANGID
  • 5. 5 ASTRACT Structural design is the primary aspect of civil engineering. The very basis of construction of any building, residential house or dams, bridges, culverts, canals etc.is designing. The foremost basic in structural engineering is the design of simple basic components and members of a building viz. slabs, beam, columns and footings for their design, an architectural design is prepared using the auto CAD . in order to design them it is important to first obtain the plan of the particular building that is positioning of the particular rooms such that they serve their respective purpose and suitability. Plan layout of beam and the position of columns are fixed. Thereafter, the vertical loads are calculated namely the dead load and live load from IS: 875 In this project the design of G+5 floors hostel building is done according to the Indian standards IS456 has been used for the reinforcement design IS 875 has been used for the estimation of all the loads on the structure viz. dead load, live load, and wind load, once the loads are obtained, the slabs are designing of slabs depends upon whether it is one way or two way slab the end conditions and the loading the analysis and designing of beam & columns are done by the “STAAD PRO” software tool. The footing are designed manually after completion of designing estimation has to be carried out.
  • 6. 6 INTRODUCTION ABOUT: The Central Public Works Department of India is a Central Government owned authority that is in charge of public sector works in the country. Central Public Works Department (CPWD) under Ministry of Urban Development is entrusted with construction and maintenance of buildings for most of the Central Government Departments, Public undertakings and autonomous bodies. In the Indian History both pre and post independence - CPWD has a glorious era of more than 150 year with dedicated, energetic and committed corps of Engineers and Architects. Before being re-structured to its present form in 1930 “Central Public Works Department” originated in July 1854 when the Governor General of India decided to set up a Central Agency: “to exercise universal control over public works in India with best of scientific knowledge with authority & system”. Central Public Works Department, delhi is the premier agency of Govt. of India engaged in planning, designing, construction and maintenance of Government assets in the field of built environment and infrastructure development. Assets in built environment include Hospital Schools, Colleges, Technical Institutes, Police Buildings, Prisons, Courts,hostels etc; assets in infrastructure development include Roads, Bridges, Flyovers, Footpaths, Subways etc. CPWD Delhi also sustains and preserves these assets through a well developed system of maintenance which includes amongst others specialized services like rehabilitation works, roads signage and aesthetic treatments like interiors, monument lighting, landscaping.
  • 7. Page 7 PROJECT OVERVIEW SITE LOCATION MNIT, JAIPUR AT NEAR CPWD DEPARTMENT ,GANGA GIRLS HOSTEL BUILDING Advantages of this site : Land : Store : Parking space : Health unit : Transportation facilities Image 1 Foundation stone Image 2: of construction site
  • 8. Page 8 Construction of “Ganga Girls Hostel MNIT Jaipur,at JLN Marg,Malviya Nagar Jaipur(Raj.) (SH: C/o Girls hostel Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations) 884 seatedgirls hostel. single seatedrooms- 454 triple seatedrooms-141 Rooms physically challenged students-7 LETTER NO. : F8(63)/Vmnit/E/v2014-15/v532 NAME OF CONTRACTOR: BCC Pvt. Ltd. Building Better Future SIZE PLOT 110m*90m ESTIMATED COST: Civil Work- Rs 68,38,2017 /- Electric-Work- Rs 11,63,9120/- Total Cost- Rs 80,02,11037/- DATE OF START: oct 2015
  • 9. Page 9 FOUNDATION Footings are strips of concrete or filled concrete blocks placed under foundation wall. Gravel or crushed stone footings may also be used. The purpose of footing is to transfer the loads safely in the ground. 1.IsolatedFooting- An isolated footing is used to support the load on a single column. It is usually either square or rectangular in plan. It represents the simplest, most economical type and most widely used footing. Whenever possible, square footings are provided so as to reduce the bending moments and shearing forces at their critical sections. Isolated footings are used in case of light column loads, when columns are not closely spaced. Image3: of isolated column 2.combinedfooting:- A footing which has more than one column is called as combined footing. This kind of footing is adopted when there is a limited space. Due to lack of space we cannot cast individual footing, Therefore footings are combined in one footing.
  • 10. Page 10 Image 4: of combined footing foundation and plinth- • RCC M25 Grade Concrete in strip/isolated footing with grade/plinth beam. • 230 mm thick fly ash brick masonry work from grade beam to plinth level. • M25 grade RCC slab at ground floor/plinth level. Image 5: plinth beam Super structure- RCC frame structure having M25 grade, beam column and slab.  All external walls shell be with 230 mm thick with fly ash bricks and all partition walls shall be with half brick thickness fly ash in cement mortar 1:4
  • 11. Page 11 Flooring and dado work-  Ceramic wall and floor tiles in all toilets.  Mirror polished Kota stone flooring rooms, corridors and stairs with marble pattern.  Rubbed sandstone flooring in courtyard.  Vitrified tiles in food court, visitors room etc. Roofing:-  Brick bat coba for water proofing on roof top and heat resistant tiles over coba treatment.  UPVC pipes for rain water drainage Image 6: thermal tiles Brick masonry- The common materials of masonry construction are brick, building stone such as marble, granite, travertine, and limestone, cast stone, concrete block, glass block, and cob. Masonry is generally a highly durable form of construction. Image 7: brick masonry at construction site
  • 12. Page 12 FORM WORK Formwork is a mould or die used to support or shape the concrete until it attains sufficient strength to carry its self-weight. Formwork holds the concrete until it hardens to required shape & size. Significance of formwork- A-Formwork constitutes 30% of cost & 60% of time in concrete construction. B-Quality of concrete finish and soundness of concrete depends very much on type of formwork system. C-Desired shape of concrete is not possible if formwork is not done properly. D-Formwork should be properly designed fabricated and erected to receive concrete. E-Accident happen because of faulty formwork and scaffolding or staging. Safety in using formwork- -Components are light in weight for manual holding. -Appropriate use of tools. -Loose or hanging components are minimal. Image 8: formwork of a column
  • 13. Page 13 PALCING OF REINFORCEMENT IN A COLUMN Lateral ties 8mm dia provided@150mm c/c in a column Image 9 : Longitudinal steel bars of 20mm dia provided in a column LATERAL TIES WITH 135* BEND
  • 14. Page 14 REINFORCEMENT PLACEMENT AND CASTING OF SLAB At there I was involved while placement of reinforcement bar for monolithic construction of concrete slab with beam. Reinforcement in the slab with alternate bent up bars provided at supports in order to provide negative reinforcement at support in two way slab In concreting, concrete pump, needle vibrator etc. were used
  • 15. Page 15 Image 10: in next day of slab casting Technology used Generally at site survey is carried out by following two instruments : Auto level : Total station Other instruments are use in casting : Mixer : niddle vibretor : pumping machine A-Total Station A total station is an electronic/optical instrument used in modern Surveying and building construction. The total station is an electronic theodolite (Transit) integrated with an electronic distance meter (EDM) to read slope Distances from the instrument to a particular point. By this instrument we can Measure Angle, Distance, Coordinate and also Data Processing.
  • 16. Page 16 Advantages: The following are some of the major advantages of using total station over the conventional surveying instruments 1. Field work is carried out very fast. 2. Accuracy of measurement is high. 3. Manual errors involved in reading and recording are eliminated. B-Auto level- It is a leveling instrument which was on site checking the elevations of various points. Auto level is a modified form of dumpy level. We used auto level to transfer the level of ground to retaining wall and setting thickness of slab in which first of all marking was made to fix the level of particular elevations then casting of slab was performed Transferring of surface level to retaining wall 1 – Set the auto level at the building floor level. 2 – level the instrument 3 – Take the staff reading at point also on floor level surface. 4 – Locate the staff on the formwork of retaining wall and adjust the staff in such a way so that reading of staff is same as staff reading in step 3. Image 11: transfer the concrete and use of niddle vibrator
  • 17. Page 17 Grinding machine- This the power mechanically operated machine which is used to mix the concrete.it consist of a hollow cylindrical part with wing inside it.in which cement, sand, aggregate and water is mixed Transportation- The Process of carrying the concrete mixture from the place of its mixing to final position of deposition is transportation. Method of transportation - 1. transport of concrete by pan 2. transport of concrete by wheel barrow 3. transport of concrete by T.M. 4. transport of concrete by tipping lorries 5. transport of concrete by pumps 6. transport of concrete by belt conveyors At this site transit mixture(T.M.) are using Image 12 : transit mixture at site
  • 18. Page 18 Batching Plant- concrete plant, also known as a batch plant or batching plant or a concrete batching plant, is equipment that combines various ingredients to form concrete. Some of these inputs include water, air, admixtures, sand, aggregate (rocks, gravel, etc.), fly ash, silica fume, slag, and cement Image 13 : batching plant and machine Tower Crane- The tower cranes belong to essential building machines which are widely used for transport of the construction products from storage area or vehicle to their final positions in process of building-up of the constructions. Their positioning affects a fluency, costs and total consumed time of building-up. Image 14 : Tower crane at site
  • 19. Page 19 QUALITY:- The technical audit of works done by CPWD used to be done in-house right from its inception. The functions of Quality Assurance and Technical Audit of works were shifted to CVC in the year 1964. On the recommendation of Ranganathan Committee, the Quality Assurance functions were again shifted to CPWD in the year 1979. The implementation of Quality Assurance in the field will require close co-operation among the three agencies, namely (a) field engineers (b) the construction agency (c) the Quality Assurance team at Circle level for strict compliance of Quality Assurance Procedure forming part of agreement. Quality Control team at Circle Level To keep a watch on the effectiveness/adequacy of Quality Assurance measures at site, a Quality Assurance team with SE of the circle as its head and comprising of one AE. The functions of the Quality Assurance team at Circle level are to check the compliance of Quality Assurance system by the field units, to locate the lapse/deficiency in the implementation of the Quality Assurance Plan, and to guide the field engineers in quality related aspects of the work Quality Assurance units in the Regions Quality Assurance works in various Regions are being looked after by the Regional QA units headed by the Superintending Engineer (TLQA) or Director Works of the Region
  • 20. Page 20 SAFETY INDUCTION Safety is very important part of any work. An induction video was showed which highlighted the need and importance of safety at construction site. Most accidents can be prevented by taking simple measures or adopting proper working procedures. It is very important to discuss issues on safety and health that should be paid attention to on construction sites for easy reference by the workers. If we work carefully and take appropriate safety measures, there will definitely be fewer work injury cases, and our sites will become a safe and secure place to work in. It is important to educate everyone in the site regarding safety for following purposes.  Workers safety  Construction progress  Standard procedure  Legal cases  Working efficiency Precautions at site for safety-  Wear protective equipment.  Do not drink or take drugs while working  Pay attention to personal hygiene  Do not play in the workplace  Report to your supervisor immediately if you notice any unsafe condition. Equipment used for safety at construction site- NETS DAILY WORK
  • 21. Page 21 WEEK 1 1st Day Training Location:- MNIT (Jaipur) Today’s Duties:- To Visit training location Working On:- visiting (analysis entire site) Technology:- NO technology used at first day Key learning:- pumping station ,batching plant, plastering, reinforcement determination 2nd Day Training Location:- MNIT , Jaipur (block No:5A) floor No:04 Today’s Duties:- To learn how to distribute Reinforcement on floor Working On:- distribution of Reinforcement on floor(slab) Technology:- grinder machine, inch tape etc. Key learning:- cutting of Reinforcement ,leveling of slab 3rd DAY Training Location:- MNIT ,Jaipur (block No:5A) Today’s Duties:- To learning of reinforcement distribution of slab Working On:- cross check the pervious spreading of reinforcement Technology:- auto level ,inch tap (including withdrawing) Key learning:- To operate auto level 4th DAY Training Location:- MNIT ,Jaipur (block No:5A) floor nub:04 Today’s Duties:- To about slab casting Working On:- slab casting, concrete mixture Technology:- continuous batching ,mixture, pumping station, mechanical vibrator Key learning:- slab casting
  • 22. Page 22 5th DAY Training Location:- MNIT (Jaipur) block nub 5A Today’s Duties:- To learn about finishing work Working On:- plastering Technology:- plumb bob, threat, trowel, platter Key learning:- how to check plastering is in level 6th DAY Training Location:- MNIT (Jaipur) block nub 5A Today’s Duties:- To learn about the finishing work Working On:- finishing work (walls) Technology:- plumb bob, trowel, platter etc. Key learning:- straightness of walls 2nd WEEK 1st DAY Training Location:- MNIT (Jaipur) block Nub 5 upper most floor Today’s Duties:- To learn about the casting of the tank Working On:-reinforcement distribution for tank casting finishing work on casting of the tank Technology:- grinder, cutter, machine crane, plates pumping stations etc. Key learning:- measurement of the tank 2nd DAY Training Location:- MNIT (Jaipur) block nub 5 upper most floor Today’s Duties:- To learning about the casting of the tank Working On:- to cross check the reinforcement distribution of tank, shuttering work on tank and finishing work Technology:- inch tape, etc. Key learning:- shuttering work
  • 23. Page 23 3rd DAY Training Location:- MNIT (Jaipur) block nub 5 upper most floor Today’s Duties:- To learn about the finishing work Working On:- finishing work on roof (to give slope) placing on heat resisting tiles on roof Technology:- inch tape, trowel, platter etc. Key learning:- to take a slope 4th DAY Training Location:- MNIT (Jaipur) block nub 5 upper most floor Today’s Duties:- To learn about the casting of the tank Working On:- casting of the tank. Technology:- vibrator, pumping station Key learning:- use of vibrator 5th DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- To learn about the auto level Working On:- auto level ( leveling of field),excavation work Technology:- JCB, plumb bob, auto level, trowel, platter ,stone cutter etc. Key learning:- excavation 6th DAY Training Location:- MNIT (Jaipur) all blocks Today’s Duties:- To visiting all blocks Working On:- just impactions (to see all work) Technology:- auto level etc. Key learning:- cross check of plastering, leveling of shuttering 3rd WEEK
  • 24. Page 24 1st DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- excavation , measurement Working On:- excavation , measurement of the field Technology:- JCB, inch tape etc. Key learning:- measurement 2nd DAY Training Location:- MNIT (Jaipur) block nub 5A Today’s Duties:- cladding stone work Working On:- cladding work on block 5A Technology:- stone ,iron frame, nut bolt etc. 3rd DAY Today’s Duties:- see cladding stone work Working On:- cladding stone work on 5A block & area calculate of cladding Technology:- stone , nut bolts, steel frame etc. Key learning:- providing cladding 4th DAY Today’s Duties:- calculate the area of cladding stone work Working On:- calculate area of open space and calculate area of cladding work Technology:- inch tape ,scaffolding etc. Key learning:- calculate 5th DAY Training Location:- MNIT (Jaipur) block nub 5A & 04 Today’s Duties:- to see the plastering work Working On:- plaster work on their blocks Technology:- plumb bob, trowel, thread etc.
  • 25. Page 25 6th DAY Training Location:- MNIT (Jaipur) block nub 5A & 05 Today’s Duties:- to see the plastering work and cladding stone work Working On:- plaster work on their blocks Technology:- plumb bob, trowel, thread etc. Key learning:- to find mistakes in cladding stone work 4TH WEEK 1st DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- to see the working on T.S layout Working On:- To see the T.S. to find the coordinate of column (footing) Technology:- T.S. , marker, thread etc. Key learning:- working on T.S 2nd DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- to see the P.C.C. work Working On:- P.C.C. work Technology:- concrete mixture ( transits Batching mixture) Key learning:- how to do P.C.C. work 3rd DAY Training Location:- MNIT (Jaipur) block nub 01 Today’s Duties:- to see the masonary work Working On:- masonary work Technology:- platter trowel, plumb bob etc. Key learning:- masonary work
  • 26. Page 26 4th DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- to cross check leveling of P.C.C. work& to providing slope Working On:- leveling of the footing Technology:- auto level, cross staff, inch tape etc. Key learning:- providing slope 5th DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- footing work & column reinforcement Working On:- footing work & column reinforcement Technology:- plumb bob , binding wire, concrete mixture etc. Key learning:- footing work 6th DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- calculate quantity of concrete for footing work Working On:- calculate quantity of concrete Technology:- inch tape Key learning:- calculate quantity of concrete for footing only 6th WEEK 1st DAY Training Location:- MNIT (Jaipur) block nub 6A Today’s Duties:- To learn about the finishing work Working On:- plastering, partitions work Technology:- plumb bob, threat, etc. Key learning:- flow to check , plastering is in level or not
  • 27. Page 27 2nd DAY Training Location:- MNIT (Jaipur) block nub 5 upper most floor Today’s Duties:- To learn about the casting of tank Working On:- casting of the tank Technology:- needle vibrator, batching mixture plant. Key learning:-use of vibrator 3rd DAY Training Location:- MNIT (Jaipur) block nub 6A Today’s Duties:- To learn about the finishing work Working On:- finishing work (walls) Technology:- plumb bob, threat, etc. Key learning:- strength of walls 4th DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- To learn about the auto level finishing work Working On:- auto level machine, plumb bob, stone cutter Technology:- plumb bob, auto level Key learning:- auto level work 5th DAY Training Location:- MNIT (Jaipur) block nub 8 Today’s Duties:- cladding of stone work WorkingOn:- claddingof stone workon blocks Technology:- stone ,steel frame ,nutbolt Keylearning:- providingof claddingstone work 6th DAY Training Location:- MNIT (Jaipur) all block
  • 28. Page 28 Today’s Duties:- visiting all blocks Working On:- to see all works on site Technology:- all technological equipment Key learning:- finishing , casting, concreting 7th WEEK 1st DAY Training Location:- MNIT (Jaipur) block nub 2A Today’s Duties:- finishing work Working On:- partition works ,masonary work Technology:- thread, plumb bob, trowel, platter etc. Key learning:- finishing work 2nd DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- footing work & column reinforcement Working On:- footing work, column reinforcement. Technology:- plumb bob, binding wire, concrete mixture etc. Key learning:- footing work 3rd DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:-to see P.C.C work Working On:- P.C.C. work Technology:-concrete mixture Key learning:- learn about P.C.C. work 4th DAY Training Location:- MNIT (Jaipur) block nub 7 Today’s Duties:- to see masonary work
  • 29. Page 29 Working On:- masonary work Technology:-thread , plumb bob, trowel, platter etc. Key learning:- mesonary work 5th DAY Training Location:- MNIT (Jaipur) block nub 8 Today’s Duties:- to know how to provide ramp Working On:- reinforcement detailing of ramp, slope of ramp Technology:-drawing Key learning:- ramp providing , slope providing 6th DAY Training Location:- MNIT (Jaipur) block nub 8 Today’s Duties:- to cross check reinforcement detailing for slab Working On:- cross check reinforcement detailing on slab Technology:- drawing , inch tape etc. Key learning:- to read drawing 8th WEEK 1st DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- to see working on T.S. layout Working On:- to see T.S. to final the co-ordinate of the column Technology:- T.S , marker, thread etc. Key learning:- working on T.S. 2nd DAY Training Location:- MNIT (Jaipur) all block Today’s Duties:- visiting all blocks Working On:- to see all works on site
  • 30. Page 30 Technology:- all technological equipment Key learning:- finishing , casting, concreting 3rd DAY Training Location:- MNIT (Jaipur) block nub 7A Today’s Duties:-to know how to provide roof Working On:- reinforcement detailing of ramp, slope of ramp Technology:-drawing, inch tape etc. Key learning:-slope providing 4th DAY Training Location:- MNIT (Jaipur) block nub 8A Today’s Duties:- to check the beam Working On:- cross checking , beam using drawing Technology:- inch tape , drawing Key learning:- read drawing 5th DAY Training Location:- MNIT (Jaipur) block 8A Today’s Duties:- to cross check reinforcement detailing for slab. Working On:- cross checking reinforcement detailing on slab (floor) Technology:- drawing , inch tape etc. Key learning:- to read the drawing. 6th DAY Training Location:- MNIT (Jaipur) all block Today’s Duties:- to cross check the construction block with site engineer Working On:- error found on chamber ,reconstruction of chamber Technology:- thread , inch tape, plumb bob Key learning:- masonary work &joining of sewer, finishing work
  • 31. Page 31 CONCLUSION The provision of summer training as the curriculum of undergraduate technical courses is a very appreciable step which I consider as a great opportunity to see real life application of materials which we have already studied and seen in our textbooks or our day to day life. The opportunity to work at a location with such an organization was really a great experience and fun . There were several things to learn and experience. Learning to apply the studied concepts and phenomena was really enjoyable . Various things which couldn’t have been possible theoretically were possible to be learnt . Interaction with workers and and local public was also a great experience. All over the whole process was a memorable one and quite informative .