Dense Bituminous Macadam
Presentation Outline:
• Introduction
• Why DBM?
• Design Criteria
• Materials
• Construction
• References
Introduction:
• Dense Bituminous Macadam (DBM) is a binder course used
for roads with more number of heavy commercial vehicles
and a close-graded premix material having a voids content of
5-10 per cent.
Why DBM?
• This material has increased in popularity due to durable
surface which performs almost well as in all situations.
• Suitable for all pavement layers and for all traffic conditions.
• DBM provides a good quality smooth surface and improved
skid resistance.
DESIGN CRITERIA(IRC:94-1996):
• Due to high cost of DBM it should be properly designed
according to standard design method so as to satisfy certain
criteria needed to assure adequate stability and durability.
SR No. Designation Requirement
(I) Number of Compaction blows on each end of
Marshall specimen
75
(II) Marshall Stability in Kg.(Minimum) 340
(III) Marshall flow in mm 2-4
(IV) VMA 5-10
(V) VFB 55-75
(VI) Bitumen content percent by weight of total mix 4.5-6.0
MATERIALS:
• In order to satisfy Design criteria, DBM mix shall consists of
Coarse Aggregate, Fine Aggregate and filler in suitable
proportions with required binder content.
• Proper Blend of aggregates should be done to so that final
gradation will satisfy either two limits according to thickness
in following table.
CONTI..
Sieve Size(mm)
Grading Number
1(For Layer thickness
≤50mm)
2(For Layer thickness
≥50mm)
(Percentage Passing)
37.5 - 100
26.5 100 85-100
19 85-100 71-95
13.2 63-82 58-82
9.5 52-74 52-72
4.75 39-54 35-50
2.36 28-43 28-43
0.60 15-27 15-27
0.3 7-21 7-21
0.15 5-15 5-15
0.075 2-8 2-8
Coarse Aggregate (retained on 2.36mm sieve):
• Preferably it should be hydrophobic and of low porosity.
• If hydrophilic aggregates are to be used the bitumen shall be
treated with antistripping agents.
• In case of more porous aggregates extra bitumen for
absorption by aggregates shall be provided to satisfy design
criteria.
CONTI..
Test Maximum percent
Aggregate impact value 35
Los Angeles Abrasion Value 40
Flakiness Index 35
Stripping Value 25
Soundness:
I)Loss with sodium sulphate-5 cycles
II)Loss with Magnesium sulphate-5
cycles
12
18
Water Absorption 2
Fine Aggregate (passing on 2.36mm and
retained on 75µm):
• Crushed Screenings, natural sand or mixture of both.
• Shall be clean, hard, durable dry and free from organic
substances.
Filler (passing 75 µm):
• Stone dust, cement, hydrated lime, fly ash or other non-
plastic mineral matter.
• Normally Filler requirement is met by the material passing
through 75 µm sieve in fine aggregate, if fine aggregate is
deficient then extra filler is added. Extra filler should be as
following:
CONTI..
Sieve % passing
600 µm 100
150 µm At least 90
75 µm >70
BITUMEN:
• The bitumen shall be viscosity grade paving bitumen
complying with the Indian Standard specification IS:73.
JOB MIX FORMULA:
• While the laboratory mix design gives the different
proportions of the mineral aggregate combinations in terms
of individual sieve sizes, for actual operational purposes in the
field, blending of two or more sizes of aggregate in terms of
weight or volume would be necessary.
• This blending ratio can be on a weight basis by giving percent
weight of the CA, FA and filler needed to give the aggregate
gradation.
• It can also be proportioned on a volumetric basis based on
the unit weight or bulk density of the aggregate supplied.
CONTI..
• The mineral aggregate content with Optimum Binder Content
as determined in the laboratory constitutes the job-mix
formula.
• Mix design shall be carried out, based on a correct and truly
representative sample of the materials that will actually be
used in the specific construction project.
CONSTRUCTION:
– PREPARATION OF BASE:
• The base on which dense bituminous macadam is to be laid
shall be prepared to the specified dimensions.
• The surface shall be thoroughly swept and free from dust and
other materials.
• If the base is irregular and wavy then proper corrective course
of adequate thickness is provided to rectify the profile.
CONTI..
• After that Tack coat(asphalt applied before a road is laid to
form an adhesive bond) is provided as per type of surface as
follows:
Rate Surface
6 to 7.5 Kg per 10 square meter Dry
5 to 5.5 Kg per 10 square meter Normal bituminous surface
7.5 to 10 Kg per 10 square meter Non-bituminous surface
CONTI..
- PREPARATION OF MIX:
• Preparation of mix is carried out in Hot Mix Plant of adequate
capacity.
• Plant may be either batch type or a continuous type.
CONTI..
-SPREADING OF THE MIX:
• The Mix shall be transported by tipper truck and spreading
done by mechanical paver.
• It should be spread in such a manner that after compacting
required thickness binder course is uniformly laid.
CONTI..
-COMPACTION:
• The Mix after spreading shall be compacted by rolling by a set
of rollers at a speed not more than 5km/hour.
• Typical roller position used in compaction is:
1) Initial or break down rolling » By 8 to 12 tonnes, three
wheel steel roller
CONTI..
2) Intermediate rolling
» By 15 to 30 tonnes,
smooth wheel pneumatic
roller
3) Finished rolling
» By 8 to 10 tonnes,
tandem roller
CONTI..
• Wheel of rollers should be kept moist to prevent the mix from
adhering to them. Rolling shall commence from longitudinally
from edge and proceed towards centre. Rolling shall be
continued till desired density is achieved.
CONTI..
-OPENING TO TRAFFIC:
• Traffic can be allowed after completion of the final rolling
when the mix has cooled down to the surrounding
temperature.
REFERENCES:
• IRC 94-1986 : Specification for Dense Bituminous
Macadam
• MORTH(5th Revision):SPECIFICATIONS FOR ROAD
AND BRIDGE WORK
• pavementinteractive.org
• pavingexpert.com

Mais conteúdo relacionado

Mais procurados

PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTPWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
Satyam Anand
 

Mais procurados (20)

Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
water bound macadam road
water bound macadam roadwater bound macadam road
water bound macadam road
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement Techniques
 
ppt on pavement design
ppt on pavement designppt on pavement design
ppt on pavement design
 
Seal coat,prime coat and tack coat
Seal coat,prime coat and tack coatSeal coat,prime coat and tack coat
Seal coat,prime coat and tack coat
 
Marshall Mix Design
Marshall Mix Design Marshall Mix Design
Marshall Mix Design
 
road construction
road constructionroad construction
road construction
 
PQC concrete road
PQC concrete roadPQC concrete road
PQC concrete road
 
Bitumen and modified bitumen
Bitumen and modified bitumenBitumen and modified bitumen
Bitumen and modified bitumen
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavement
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
 
Pavement design
Pavement designPavement design
Pavement design
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
 
Dense Bituminous Macadam Road
Dense Bituminous Macadam RoadDense Bituminous Macadam Road
Dense Bituminous Macadam Road
 
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTPWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studies
 
GROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODSGROUND IMPROVEMENT-DENSIFICATION METHODS
GROUND IMPROVEMENT-DENSIFICATION METHODS
 

Semelhante a Dense Bituminous macadam

Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
eSAT Journals
 

Semelhante a Dense Bituminous macadam (20)

Dense bituminous macadam
Dense bituminous macadamDense bituminous macadam
Dense bituminous macadam
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
 
Cold mix bituminous plant
Cold mix bituminous plantCold mix bituminous plant
Cold mix bituminous plant
 
crri_csir_odisha new tech JULY 2022.pptx
crri_csir_odisha new tech JULY 2022.pptxcrri_csir_odisha new tech JULY 2022.pptx
crri_csir_odisha new tech JULY 2022.pptx
 
Self Compacting concrete & Light Weight concrete
Self Compacting concrete & Light Weight concreteSelf Compacting concrete & Light Weight concrete
Self Compacting concrete & Light Weight concrete
 
Interface treatment
Interface treatmentInterface treatment
Interface treatment
 
Presentation of 5_weeks_summer_training_,dept
Presentation of 5_weeks_summer_training_,deptPresentation of 5_weeks_summer_training_,dept
Presentation of 5_weeks_summer_training_,dept
 
Ready Mix Concrete++.pptx
Ready Mix Concrete++.pptxReady Mix Concrete++.pptx
Ready Mix Concrete++.pptx
 
Concrete Superiority and Resilience characteristics in Construction.ppt
Concrete Superiority and Resilience characteristics in Construction.pptConcrete Superiority and Resilience characteristics in Construction.ppt
Concrete Superiority and Resilience characteristics in Construction.ppt
 
Effect of the use of crumb rubber in conventional
Effect of the use of crumb rubber in conventionalEffect of the use of crumb rubber in conventional
Effect of the use of crumb rubber in conventional
 
Road construction pavements flexible rigid
Road construction pavements flexible rigidRoad construction pavements flexible rigid
Road construction pavements flexible rigid
 
CONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSCONSTRUCTION OF ROADS
CONSTRUCTION OF ROADS
 
rigid and flexiable pavement design ppt
rigid and flexiable pavement design pptrigid and flexiable pavement design ppt
rigid and flexiable pavement design ppt
 
FOAM CONCRETE STUDY AND TESTING
FOAM CONCRETE STUDY AND TESTINGFOAM CONCRETE STUDY AND TESTING
FOAM CONCRETE STUDY AND TESTING
 
Production of concrete
Production of concreteProduction of concrete
Production of concrete
 
SANDEEP PPT
SANDEEP PPTSANDEEP PPT
SANDEEP PPT
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)
 
CONCRETE PPT SA JBP
CONCRETE PPT SA JBPCONCRETE PPT SA JBP
CONCRETE PPT SA JBP
 
Industrial training abhi edited.pdf
Industrial training abhi edited.pdfIndustrial training abhi edited.pdf
Industrial training abhi edited.pdf
 
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
Effect of the use of crumb rubber in conventional bitumen on the marshall sta...
 

Mais de pradip dangar (13)

Shear walls
Shear wallsShear walls
Shear walls
 
Best civil engineering structures
Best civil engineering structuresBest civil engineering structures
Best civil engineering structures
 
Airpot design
Airpot designAirpot design
Airpot design
 
hot mix plant
hot mix plant hot mix plant
hot mix plant
 
Cement and cement concrete
Cement and cement concreteCement and cement concrete
Cement and cement concrete
 
pavement materials:aggregates
pavement materials:aggregates pavement materials:aggregates
pavement materials:aggregates
 
Superpavemixdesign
Superpavemixdesign Superpavemixdesign
Superpavemixdesign
 
Soil stabilisation
Soil stabilisation Soil stabilisation
Soil stabilisation
 
Roads in difficult areas
Roads in difficult areasRoads in difficult areas
Roads in difficult areas
 
Low cost road
Low cost roadLow cost road
Low cost road
 
Roller compaction machines
Roller compaction machinesRoller compaction machines
Roller compaction machines
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
Roads in desert, swamp & black cotton
Roads in desert, swamp & black cottonRoads in desert, swamp & black cotton
Roads in desert, swamp & black cotton
 

Último

Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
chumtiyababu
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Último (20)

Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 

Dense Bituminous macadam

  • 2. Presentation Outline: • Introduction • Why DBM? • Design Criteria • Materials • Construction • References
  • 3. Introduction: • Dense Bituminous Macadam (DBM) is a binder course used for roads with more number of heavy commercial vehicles and a close-graded premix material having a voids content of 5-10 per cent.
  • 4. Why DBM? • This material has increased in popularity due to durable surface which performs almost well as in all situations. • Suitable for all pavement layers and for all traffic conditions. • DBM provides a good quality smooth surface and improved skid resistance.
  • 5. DESIGN CRITERIA(IRC:94-1996): • Due to high cost of DBM it should be properly designed according to standard design method so as to satisfy certain criteria needed to assure adequate stability and durability. SR No. Designation Requirement (I) Number of Compaction blows on each end of Marshall specimen 75 (II) Marshall Stability in Kg.(Minimum) 340 (III) Marshall flow in mm 2-4 (IV) VMA 5-10 (V) VFB 55-75 (VI) Bitumen content percent by weight of total mix 4.5-6.0
  • 6. MATERIALS: • In order to satisfy Design criteria, DBM mix shall consists of Coarse Aggregate, Fine Aggregate and filler in suitable proportions with required binder content. • Proper Blend of aggregates should be done to so that final gradation will satisfy either two limits according to thickness in following table.
  • 7. CONTI.. Sieve Size(mm) Grading Number 1(For Layer thickness ≤50mm) 2(For Layer thickness ≥50mm) (Percentage Passing) 37.5 - 100 26.5 100 85-100 19 85-100 71-95 13.2 63-82 58-82 9.5 52-74 52-72 4.75 39-54 35-50 2.36 28-43 28-43 0.60 15-27 15-27 0.3 7-21 7-21 0.15 5-15 5-15 0.075 2-8 2-8
  • 8. Coarse Aggregate (retained on 2.36mm sieve): • Preferably it should be hydrophobic and of low porosity. • If hydrophilic aggregates are to be used the bitumen shall be treated with antistripping agents. • In case of more porous aggregates extra bitumen for absorption by aggregates shall be provided to satisfy design criteria.
  • 9. CONTI.. Test Maximum percent Aggregate impact value 35 Los Angeles Abrasion Value 40 Flakiness Index 35 Stripping Value 25 Soundness: I)Loss with sodium sulphate-5 cycles II)Loss with Magnesium sulphate-5 cycles 12 18 Water Absorption 2
  • 10. Fine Aggregate (passing on 2.36mm and retained on 75µm): • Crushed Screenings, natural sand or mixture of both. • Shall be clean, hard, durable dry and free from organic substances. Filler (passing 75 µm): • Stone dust, cement, hydrated lime, fly ash or other non- plastic mineral matter. • Normally Filler requirement is met by the material passing through 75 µm sieve in fine aggregate, if fine aggregate is deficient then extra filler is added. Extra filler should be as following:
  • 11. CONTI.. Sieve % passing 600 µm 100 150 µm At least 90 75 µm >70 BITUMEN: • The bitumen shall be viscosity grade paving bitumen complying with the Indian Standard specification IS:73.
  • 12. JOB MIX FORMULA: • While the laboratory mix design gives the different proportions of the mineral aggregate combinations in terms of individual sieve sizes, for actual operational purposes in the field, blending of two or more sizes of aggregate in terms of weight or volume would be necessary. • This blending ratio can be on a weight basis by giving percent weight of the CA, FA and filler needed to give the aggregate gradation. • It can also be proportioned on a volumetric basis based on the unit weight or bulk density of the aggregate supplied.
  • 13. CONTI.. • The mineral aggregate content with Optimum Binder Content as determined in the laboratory constitutes the job-mix formula. • Mix design shall be carried out, based on a correct and truly representative sample of the materials that will actually be used in the specific construction project.
  • 14. CONSTRUCTION: – PREPARATION OF BASE: • The base on which dense bituminous macadam is to be laid shall be prepared to the specified dimensions. • The surface shall be thoroughly swept and free from dust and other materials. • If the base is irregular and wavy then proper corrective course of adequate thickness is provided to rectify the profile.
  • 15. CONTI.. • After that Tack coat(asphalt applied before a road is laid to form an adhesive bond) is provided as per type of surface as follows: Rate Surface 6 to 7.5 Kg per 10 square meter Dry 5 to 5.5 Kg per 10 square meter Normal bituminous surface 7.5 to 10 Kg per 10 square meter Non-bituminous surface
  • 16. CONTI.. - PREPARATION OF MIX: • Preparation of mix is carried out in Hot Mix Plant of adequate capacity. • Plant may be either batch type or a continuous type.
  • 17. CONTI.. -SPREADING OF THE MIX: • The Mix shall be transported by tipper truck and spreading done by mechanical paver. • It should be spread in such a manner that after compacting required thickness binder course is uniformly laid.
  • 18. CONTI.. -COMPACTION: • The Mix after spreading shall be compacted by rolling by a set of rollers at a speed not more than 5km/hour. • Typical roller position used in compaction is: 1) Initial or break down rolling » By 8 to 12 tonnes, three wheel steel roller
  • 19. CONTI.. 2) Intermediate rolling » By 15 to 30 tonnes, smooth wheel pneumatic roller 3) Finished rolling » By 8 to 10 tonnes, tandem roller
  • 20. CONTI.. • Wheel of rollers should be kept moist to prevent the mix from adhering to them. Rolling shall commence from longitudinally from edge and proceed towards centre. Rolling shall be continued till desired density is achieved.
  • 21. CONTI.. -OPENING TO TRAFFIC: • Traffic can be allowed after completion of the final rolling when the mix has cooled down to the surrounding temperature.
  • 22. REFERENCES: • IRC 94-1986 : Specification for Dense Bituminous Macadam • MORTH(5th Revision):SPECIFICATIONS FOR ROAD AND BRIDGE WORK • pavementinteractive.org • pavingexpert.com