IT and IS Case study
Unleash Team strongly believes in customer data and information
confidentiality.


All the information used in this case study has been studied and
approved by the end client and does not divulge any information
which did not receive approval of the client’s executive department.
Context and the setting
A medium sized IT and ITES organization based out of HiTech City,
Hyderabad mostly servicing clients based out of US follows CMM
standards, employing about 4000 members in their Hyderabad
office in addition to another 3000 members in the Gurgaon office.

The work involves several ERP projects based on huge databases
and web based e-commerce technologies. Requirements by the
customers are usually agreed in advance and executed as per the
needs.
Context and the setting
Many of the projects are multi-year fixed price contracts and are
executed using the work flow tools developed in house, which
consists of change control systems and tracking mechanisms.
While changes are common and have always been accommodated
to ensure customer satisfaction, they have started becoming more
frequent along with price erosion due to competition to retain
existing contracts.

While efficiency improvements are happening continuously the
changes, specially towards the later part of project are increasing
the costs tremendously.
Context and the setting
The organization has decided to follow Agile practices to better deal
with changes and few projects have adopted Scrum methodology
for projects execution. This seemed to have improved the ability to
work more efficiently with respect to changes, but the CMM
standards proved difficult to follow and Audits have pointed out
many discrepancies in the systems which need to be addressed
urgently. Specially the documentation of meeting notes and work
flow changes with tracking needed better methods.

Various tracking techniques like mobile camera pictures etc were
done to meet CMMI standards in the interim. The scrum practices
like planning and retrospective were manually planned on physical
calendars which had to be done manually for different projects.
Problem Statement
A solution was urgently required which would allow the organization
to continue following the internally developed work flow systems for
projects execution and allow a few teams to adopt Agile practices.

Due to the nature of Industry and competition involved, the tools
have to be CMMI compliant and be able to integrate with the
existing work flow systems. Preference is for systems which allow
greater automation of various projects and work with SAP systems
already in place in the organization.
Solution with “Unleash”
Unleash is a complete project management system which has tools
for change controls, waterfall and Agile project management. The
tools is CMMI level 3 complaint with Audit trails and automated
mechanisms for creation of road maps, release schedules, iteration
planning, review and retrospective schedules defined and assigned
to the individual team member calendars. A work dashboard to
manage portfolios, programs and “episodic events” is available.

Since the tools are based on cloud, it is easy to integrate and has
the ability to synchronize with SAP systems by automated reading
of excel files generated by SAP through scripts which run in
automated mode every midnight.
Solution Methodology
  The following solution methodology was followed for integration of
  “Unleash” into the client’s PMIS already in place, managed by PMO.

                                        Implemen
   Analyze           Suggest                              Adjust
                                            t
                                   A team of 2
                 Proposal
                                   senior
                 provided
                                   managers and      The software
Requirements     including
                                   4 dedicated       was adjusted as
are gathered.    consulting and
                                   software          needed after the
Systems          training
                                   engineers         implementation
analysis.        schedules
                                   allocated to      along with
PMIS are         Feedback
                                   customize         completion of
studied.         received and
                                   “Unleash” core    team training.
                 proposal
                                   modules using
                 finalized
                                   Agile practices
Lessons Learned
• It was realized that the implementation of solution was a challenge
but the biggest challenge was a lack of focus on “change
management” required for the team to adopt to new environment.

• The project management trainings provided have gone a long way in
helping team members adopt the new systems. Many members had a
lack of awareness of Agile methodologies and had persisted with
usage of command and control systems. These were addressed as a
part of change management and were realized to be a key aspect of
ultimate client success.
Data Concerns, Contracts and solution
The customer has agreed to have our system be implemented on
their servers with a two year contract to have any changes be made
by our team.

The contract can be renewed after two years with an option to
completely buy the source code, for in-house customization by the
customers IT teams.

Mais conteúdo relacionado

Mais procurados

Erp implementation life cycle
Erp implementation life cycleErp implementation life cycle
Erp implementation life cycle
sawanlaladiya
 
Md050 application extensions_functional_design_080112
Md050 application extensions_functional_design_080112Md050 application extensions_functional_design_080112
Md050 application extensions_functional_design_080112
magik570
 
Erp ipmlemetation life cycle
Erp ipmlemetation life cycleErp ipmlemetation life cycle
Erp ipmlemetation life cycle
Rahul Hande
 
Software Reengineering
Software ReengineeringSoftware Reengineering
Software Reengineering
Abdul Wahid
 
Case Study: Experiences Using IBM Rational Method Composer to Deliver a BPM I...
Case Study: Experiences Using IBM Rational Method Composer to Deliver a BPM I...Case Study: Experiences Using IBM Rational Method Composer to Deliver a BPM I...
Case Study: Experiences Using IBM Rational Method Composer to Deliver a BPM I...
ghodgkinson
 
Legacy Systems in Software Engineering SE26
Legacy Systems in Software Engineering SE26Legacy Systems in Software Engineering SE26
Legacy Systems in Software Engineering SE26
koolkampus
 

Mais procurados (20)

Erp implementation life cycle
Erp implementation life cycleErp implementation life cycle
Erp implementation life cycle
 
Agile meets Enterprise ERP
Agile meets Enterprise ERPAgile meets Enterprise ERP
Agile meets Enterprise ERP
 
Md050 application extensions_functional_design_080112
Md050 application extensions_functional_design_080112Md050 application extensions_functional_design_080112
Md050 application extensions_functional_design_080112
 
Erp ipmlemetation life cycle
Erp ipmlemetation life cycleErp ipmlemetation life cycle
Erp ipmlemetation life cycle
 
Sap implementation
Sap implementationSap implementation
Sap implementation
 
Software Reengineering
Software ReengineeringSoftware Reengineering
Software Reengineering
 
Aim PPT For Oracle HRMS
Aim PPT For Oracle HRMSAim PPT For Oracle HRMS
Aim PPT For Oracle HRMS
 
Rsc 2009 Understanding Ibm Rational Method Composer
Rsc 2009   Understanding Ibm Rational Method ComposerRsc 2009   Understanding Ibm Rational Method Composer
Rsc 2009 Understanding Ibm Rational Method Composer
 
SAP Model -Smarterenergyconsulting.com
SAP Model -Smarterenergyconsulting.comSAP Model -Smarterenergyconsulting.com
SAP Model -Smarterenergyconsulting.com
 
Upgrading to 9.2 - Setting Yourself Up For Success
Upgrading to 9.2 - Setting Yourself Up For SuccessUpgrading to 9.2 - Setting Yourself Up For Success
Upgrading to 9.2 - Setting Yourself Up For Success
 
Oracle AIM Methodology
Oracle AIM MethodologyOracle AIM Methodology
Oracle AIM Methodology
 
Case Study: Experiences Using IBM Rational Method Composer to Deliver a BPM I...
Case Study: Experiences Using IBM Rational Method Composer to Deliver a BPM I...Case Study: Experiences Using IBM Rational Method Composer to Deliver a BPM I...
Case Study: Experiences Using IBM Rational Method Composer to Deliver a BPM I...
 
Oracle Fusion HCM Adoption Workshop
Oracle Fusion HCM Adoption WorkshopOracle Fusion HCM Adoption Workshop
Oracle Fusion HCM Adoption Workshop
 
Software reengineering
Software reengineeringSoftware reengineering
Software reengineering
 
Legacy Systems in Software Engineering SE26
Legacy Systems in Software Engineering SE26Legacy Systems in Software Engineering SE26
Legacy Systems in Software Engineering SE26
 
PeopleSoft Update Manager During the Upgrade and Beyond
PeopleSoft Update Manager During the Upgrade and BeyondPeopleSoft Update Manager During the Upgrade and Beyond
PeopleSoft Update Manager During the Upgrade and Beyond
 
Software maintenance
Software maintenanceSoftware maintenance
Software maintenance
 
Software re engineering
Software re engineeringSoftware re engineering
Software re engineering
 
Presentation "Analysis, design and development of ERP-systems: abstract 1.0"
Presentation "Analysis, design and development of ERP-systems: abstract 1.0"Presentation "Analysis, design and development of ERP-systems: abstract 1.0"
Presentation "Analysis, design and development of ERP-systems: abstract 1.0"
 
Just in Time
Just in Time Just in Time
Just in Time
 

Semelhante a Unleash It Casestudy

Project Management Solutions
Project Management SolutionsProject Management Solutions
Project Management Solutions
RCM Technologies
 
Sap implementation by priya pangam
Sap implementation by priya pangamSap implementation by priya pangam
Sap implementation by priya pangam
amol1212
 

Semelhante a Unleash It Casestudy (20)

Enterprise Project Management and the US Armed Forces - EPC Group
Enterprise Project Management and the US Armed Forces - EPC GroupEnterprise Project Management and the US Armed Forces - EPC Group
Enterprise Project Management and the US Armed Forces - EPC Group
 
Erp implementation life cycle
Erp implementation life cycleErp implementation life cycle
Erp implementation life cycle
 
Master Project Manager for Information Technology: sysenegacademy@gmail.com
Master Project Manager for Information Technology: sysenegacademy@gmail.comMaster Project Manager for Information Technology: sysenegacademy@gmail.com
Master Project Manager for Information Technology: sysenegacademy@gmail.com
 
The Journey to Mainframe DevOps
The Journey to Mainframe DevOpsThe Journey to Mainframe DevOps
The Journey to Mainframe DevOps
 
Software Engineering (An Agile View of Process)
Software Engineering (An Agile View of Process)Software Engineering (An Agile View of Process)
Software Engineering (An Agile View of Process)
 
Project Management Solutions
Project Management SolutionsProject Management Solutions
Project Management Solutions
 
CONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information GovernanceCONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information Governance
 
4. ch 3-agile process
4. ch 3-agile process4. ch 3-agile process
4. ch 3-agile process
 
Conig® v1.5 Converged Information Governance
Conig® v1.5 Converged Information GovernanceConig® v1.5 Converged Information Governance
Conig® v1.5 Converged Information Governance
 
Sap implementation by priya pangam
Sap implementation by priya pangamSap implementation by priya pangam
Sap implementation by priya pangam
 
ERPAL + ERP Solution, Case Study
ERPAL + ERP Solution, Case StudyERPAL + ERP Solution, Case Study
ERPAL + ERP Solution, Case Study
 
CMMI Implementation with Digité Enterprise
CMMI Implementation with Digité EnterpriseCMMI Implementation with Digité Enterprise
CMMI Implementation with Digité Enterprise
 
Erp Selection, Design, And Implementation Support
Erp Selection, Design, And Implementation SupportErp Selection, Design, And Implementation Support
Erp Selection, Design, And Implementation Support
 
Agile at scale
Agile at scaleAgile at scale
Agile at scale
 
20 best practices for fusion hcm cloud implementation
20   best practices for fusion hcm cloud implementation20   best practices for fusion hcm cloud implementation
20 best practices for fusion hcm cloud implementation
 
Best practices for fusion hcm cloud implementation
Best practices for fusion hcm cloud implementationBest practices for fusion hcm cloud implementation
Best practices for fusion hcm cloud implementation
 
I•systems - THE IMPLEMENTATION 
 OF BUSINESS PROCESS AUTOMATION 
 IN YOUR BUS...
I•systems - THE IMPLEMENTATION 
 OF BUSINESS PROCESS AUTOMATION 
 IN YOUR BUS...I•systems - THE IMPLEMENTATION 
 OF BUSINESS PROCESS AUTOMATION 
 IN YOUR BUS...
I•systems - THE IMPLEMENTATION 
 OF BUSINESS PROCESS AUTOMATION 
 IN YOUR BUS...
 
Abhi bhalla a 02
Abhi bhalla a 02Abhi bhalla a 02
Abhi bhalla a 02
 
CMMI with Digité Universal Process Framework
CMMI with Digité Universal Process FrameworkCMMI with Digité Universal Process Framework
CMMI with Digité Universal Process Framework
 
Chapter1 Advanced Software Engineering overview
Chapter1 Advanced Software Engineering overviewChapter1 Advanced Software Engineering overview
Chapter1 Advanced Software Engineering overview
 

Unleash It Casestudy

  • 1. IT and IS Case study
  • 2. Unleash Team strongly believes in customer data and information confidentiality. All the information used in this case study has been studied and approved by the end client and does not divulge any information which did not receive approval of the client’s executive department.
  • 3. Context and the setting A medium sized IT and ITES organization based out of HiTech City, Hyderabad mostly servicing clients based out of US follows CMM standards, employing about 4000 members in their Hyderabad office in addition to another 3000 members in the Gurgaon office. The work involves several ERP projects based on huge databases and web based e-commerce technologies. Requirements by the customers are usually agreed in advance and executed as per the needs.
  • 4. Context and the setting Many of the projects are multi-year fixed price contracts and are executed using the work flow tools developed in house, which consists of change control systems and tracking mechanisms. While changes are common and have always been accommodated to ensure customer satisfaction, they have started becoming more frequent along with price erosion due to competition to retain existing contracts. While efficiency improvements are happening continuously the changes, specially towards the later part of project are increasing the costs tremendously.
  • 5. Context and the setting The organization has decided to follow Agile practices to better deal with changes and few projects have adopted Scrum methodology for projects execution. This seemed to have improved the ability to work more efficiently with respect to changes, but the CMM standards proved difficult to follow and Audits have pointed out many discrepancies in the systems which need to be addressed urgently. Specially the documentation of meeting notes and work flow changes with tracking needed better methods. Various tracking techniques like mobile camera pictures etc were done to meet CMMI standards in the interim. The scrum practices like planning and retrospective were manually planned on physical calendars which had to be done manually for different projects.
  • 6. Problem Statement A solution was urgently required which would allow the organization to continue following the internally developed work flow systems for projects execution and allow a few teams to adopt Agile practices. Due to the nature of Industry and competition involved, the tools have to be CMMI compliant and be able to integrate with the existing work flow systems. Preference is for systems which allow greater automation of various projects and work with SAP systems already in place in the organization.
  • 7. Solution with “Unleash” Unleash is a complete project management system which has tools for change controls, waterfall and Agile project management. The tools is CMMI level 3 complaint with Audit trails and automated mechanisms for creation of road maps, release schedules, iteration planning, review and retrospective schedules defined and assigned to the individual team member calendars. A work dashboard to manage portfolios, programs and “episodic events” is available. Since the tools are based on cloud, it is easy to integrate and has the ability to synchronize with SAP systems by automated reading of excel files generated by SAP through scripts which run in automated mode every midnight.
  • 8. Solution Methodology The following solution methodology was followed for integration of “Unleash” into the client’s PMIS already in place, managed by PMO. Implemen Analyze Suggest Adjust t A team of 2 Proposal senior provided managers and The software Requirements including 4 dedicated was adjusted as are gathered. consulting and software needed after the Systems training engineers implementation analysis. schedules allocated to along with PMIS are Feedback customize completion of studied. received and “Unleash” core team training. proposal modules using finalized Agile practices
  • 9. Lessons Learned • It was realized that the implementation of solution was a challenge but the biggest challenge was a lack of focus on “change management” required for the team to adopt to new environment. • The project management trainings provided have gone a long way in helping team members adopt the new systems. Many members had a lack of awareness of Agile methodologies and had persisted with usage of command and control systems. These were addressed as a part of change management and were realized to be a key aspect of ultimate client success.
  • 10. Data Concerns, Contracts and solution The customer has agreed to have our system be implemented on their servers with a two year contract to have any changes be made by our team. The contract can be renewed after two years with an option to completely buy the source code, for in-house customization by the customers IT teams.