SlideShare uma empresa Scribd logo
1 de 33
Baixar para ler offline
Risk Management Plan




Project Management Templates

RISK MANAGEMENT PLAN
           2013




                                       Page | 1
Risk Management Plan



Index

Table of Contents
1       Purpose ..............................................................................................................5

2       Scope ...................................................................................................................5

3       Audience ............................................................................................................5

4       References.........................................................................................................5

5       Glossary..............................................................................................................6
5.1     Acronyms .............................................................................................................6
5.2     Definitions ............................................................................................................7

Stakeholder Analysis...............................................................................................7
5.3     Project Team .......................................................................................................7
5.4     Sponsor ................................................................................................................8
5.5     Steering Committee ...........................................................................................8
5.6     Other Stakeholder(s) Group 1 .........................................................................9
5.7     Other Stakeholder (s) Group 2 ...................................................................... 10

6       Communication Requirements & Responsibilities ........................... 10

7       Communication Process and Technology ............................................ 15
                                                                                                                                     Page | 2
Risk Management Plan




8      Communication Record .............................................................................. 17

9      Escalation Process........................................................................................ 18
9.1    Issue Categories ............................................................................................... 18
9.2    Escalation Process for Stakeholder Group 1 ............................................... 19
9.3    Escalation Process for Stakeholder Group 2 ............................................... 19

10     Purpose ............................................................................................................ 22

11     Scope ................................................................................................................. 22

12     Audience .......................................................................................................... 22

13     References....................................................................................................... 23

14     Glossary............................................................................................................ 23
14.1      Acronyms ........................................................................................................ 23
14.2      Definitions....................................................................................................... 24

15     Risk Identification ........................................................................................ 25

16     Risk List ............................................................................................................ 25

17     Qualitative Risk Analysis ........................................................................... 26

18     Quantitative Risk Analysis ........................................................................ 28

19     Risk Response Planning ............................................................................. 30
                                                                                                                                    Page | 3
Risk Management Plan




20   Risk Monitoring & Control ......................................................................... 32

21   Organization & Responsibilities .............................................................. 33




                                                                                                              Page | 4
Risk Management Plan




1 Purpose



2 Scope




3 Audience



4 References




                                      Page | 5
Risk Management Plan




5 Glossary
5.1 Acronyms


         Acronym   Description
         PMP       Project Management Plan

         PMO       Project Management Office




                                                    Page | 6
Risk Management Plan




  5.2 Definitions


Term                   Definition
Stakeholder            Project Stakeholders are individuals and organizations that
                       are actively involved in the project, or whose interests
                       maybe positively or negatively affected as a project
                       execution or project completion.




Stakeholder Analysis
  5.3 Project Team


              S.No. Name            Department        Role                 Email




                                                                                     Page | 7
Risk Management Plan




5.4 Sponsor


    S.No.     Name       Department           Role            Email




5.5 Steering Committee


      S.No.    Name      Department           Role           Email




                                                                      Page | 8
Risk Management Plan




  5.6 Other Stakeholder(s) Group 1


[Capture information regarding other stakeholder(s), for example a group of stakeholders at customer end.]



               S.No. Name                 Department         Role               Email




                                                                                                             Page | 9
Risk Management Plan




  5.7 Other Stakeholder (s) Group 2


[Capture information regarding other stakeholder(s), for example a group of stakeholders at customer end.]



               S.No. Name             Department        Role             Email




 6 Communication Requirements & Responsibilities
This section analyzes and captures the communication requirements of each of the Stakeholder’s group and also
captures their responsibilities towards the other group.


                                                                                                             Page | 10
Risk Management Plan



S.No.   Stakeholder      Communication Requirements              Communication
        Group                                                    Responsibilities


1       Program               Communicate project                     Updating all other
        Management/            objectives.                              stakeholder group with
        Project Office                                                  accurate information about
                                                                        the project progress.
                              Objective expectation from all
                               other Stakeholder group about
                               the project aim.                        Remove conflict regarding
                                                                        any requirements

                              Conflicting requirement
                                                                       Providing all relevant project
                                                                        information in a user friendly
                              Communicate policies and                 and timely manner.
                               standards, escalation process

                                                                       Any Cost or schedule
                              Communicate success factors,             overrun
                               training benefits, deliverables
                               quality requirements
                              Getting up to date and                  Project stakeholder
                               accurate information from the            satisfaction.
                               Project team about the status
                               of the ongoing tasks.
                           



                                                                                                         Page | 11
Risk Management Plan



2   Project Team      Timely clarification of project          Updating Project Office with
                       related requirements                      ongoing tasks progress


                      Task assigned to individual              Communicate any training
                       team members                              requirements to be
                                                                 addressed by PMO Office

                      Any dependencies of their
                       tasks.                                   Seek Clarification on
                                                                 conflicting roles and
                                                                 responsibilities
                      Resolution of Issues within the
                       Project Team
                                                                Any issue impacting their
                                                                 task performance
                      Resolution of Issues with other
                       Project Team
                                                                Raise any conflict to PMO
                                                                 office with any team
                                                                 members


                                                                Timely update of Issue(s)
                                                                 assigned to a team member.
3   Steering          Summarized Project Progress              Timely resolution of
    Committee          Information.                              escalated Issues


                      Summarized Issues                        Updating Organization level
                                                                                                Page | 12
Risk Management Plan



                  Information.                              Stakeholder with the Project
                                                            Progress

                 Deviation between Planned and
                  Actual Schedule (s).


                 Deviation from allocated
                  budget.



4   Sponsor      Deviation from allocated                 Map rewards against
                  budget.                                   performance.


                 Deviation from Scope of Work.            Timely resolution of
                                                            escalated Issues.

                 Project Progress Information
                                                           Analyze Project Success

                 Issues Information
                                                           Contribute to Lesson Learnt

                 Risks
                                                           Project Sign off.
                 Performance reporting of
                  project team members


                                                                                           Page | 13
Risk Management Plan




                     Nonconformance of
                      deliverables to project
                      objectives.




5   Other
    Stakeholder
    Group 1


6   Other
    Stakeholder
    Group 2




                                                           Page | 14
Risk Management Plan




 7 Communication Process and Technology
This section captures the communication process used in the Project and technologies used to have effective communication.


            Stakeholder        Communication                 Steps to get Desired        Communication
            Group              Requirements                  Information                 Technology

            Business User             Up to date                                             PMO Tool
                                   information about
                                   Project Progress



                                      Regular                      Send / Receive            Microsoft
                                       communication with            Email                      Exchange
                                       e-Business team



                                     Formal meeting with           Face to Face              Meeting
                                      members working on             Meeting                    Minutes
                                      the project for                                           Template
                                      clarification
            Program                  Information about                                       PMO Tool
            Management/            project/Task Progress
            Project Office



                                                                                                                    Page | 15
Risk Management Plan



   Regular                       Send / Receive          Microsoft
    communication with             Email                    Exchange
    the Project Team
   Formal meeting with           Face to Face            Meeting
    members working on             Meeting                  Minutes
    the project                                             Template
   Issues capturing              Face to Face            Microsoft
                                   Meeting                  Exchange
                                  Send/ Receive E-
                                   Mail
                                                           Issue Log
                                                            Template
   Escalation Channel            Face to Face            Microsoft
                                   Meeting including,       Exchange
                                   Sponsor, General
                                   Manager, and
                                   Steering                Issue Log
                                   Committee                Template
                                  Send/ Receive E-
                                   Mail to/from above
                                   stakeholders
   Summarized Project         
    Team
    Communication
    (Trouble Tickets,
    Issues, Resolution)




                                                                        Page | 16
Risk Management Plan




 8 Communication Record
The tabular format describes the Communication Record followed in the project.

       Communication    Purpose     Responsibility   Audience/          Timing/        Type of       Communication
                                                     Participants/      Frequency      Communicati   Record
                                                     Stakeholders                      on

       WSR Report       Project                                         Weekly         Meeting       Meeting Minutes
                        status
                        review
                        reporting

       Steering         Project                                         Monthly or     Meeting       Meeting Minutes
       Committee        Review                                          Need base
       Meeting

       Iteration        Iteration                                       End of every   Meeting       Iteration
       Success Report   Review                                          Iteration                    Summary Report
                                                                                       Email




                                                                                                                       Page | 17
Risk Management Plan




 9 Escalation Process
This section covers the escalation process followed in the Project for speedy resolution of the issues identified in the Project.
The escalation process is identified in terms of the Key resources of the Project and the next authority in line to address the
issues. There shall be different escalation process for different stakeholder group identified above in this plan.

  9.1 Issue Categories

Escalation process depends upon the Issue categories. There shall be different escalation process and authority for different
types of issues. This sections list the three different types of Issue categories identified for the Project.


      Technical
      Commercial
      Project Management




                                                                                                                            Page | 18
Risk Management Plan




9.2 Escalation Process for Stakeholder Group 1


       S.No.   From: Role    To: Escalation        Issue Category        When to Escalate
               & Name        Role & Name




9.3 Escalation Process for Stakeholder Group 2


    S.No.   From: Role      To: Escalation Role    Issue Category         When to Escalate
            & Name          & Name




                                                                                             Page | 19
Risk Management Plan




TEMPLATE 7: Risk Management Plan
    Project Name: <<                   >>

              Version:
            Release Date:




                                            Page | 20
Risk Management Plan




Document Information


             Author

             Reviewer

             Approver




Revision History

             Date       Version   Section       Change Description   Author
                                  Changed




                                                                              Page | 21
Risk Management Plan




 10 Purpose
The purpose of this Risk Management Plan is to identify the risks in the project, analyze the impact of these risks and propose
steps to manage them. The objectives of Project Risk Management are to increase the probability and impact of positive events,
and decrease the probability of events adverse to the project.



 11 Scope
This document primarily concerns itself with Risks & Mitigation Plan relating to the XXX Project. Risk Management
includes processes concerned with conducting risk management planning, identification, analysis, responses, and
monitoring and control on a project. The scope of the document is limited to:

   o   Risk Identification
   o   Risk List
   o   Qualitative Risk Analysis
   o   Quantitative Risk Analysis
   o   Risk Response Planning, and
   o   Risk Monitoring & Control



 12 Audience
The intended audience of this document is:
   o

                                                                                                                      Page | 22
Risk Management Plan




13 References
o
o



14 Glossary
14.1      Acronyms


    Acronym          Description




                                                          Page | 23
Risk Management Plan



14.2   Definitions


         Term          Definition
         Risk          Risk is an uncertain event or condition, that if occurs,
                       has a positive or negative effect on project objective,
                       such as cost, time, scope, or quality. A risk has a
                       cause and, if it occurs, a consequence.

         Stakeholder   Project Stakeholders are individuals and organizations
                       that are actively involved in the project, or whose
                       interests may be positively or negatively affected as a
                       project execution or project completion.




                                                                                  Page | 24
Risk Management Plan




 15 Risk Identification
Risk identification involves determining which risks might affect the project and documenting their characteristics. It
is an iterative process. Risks are identified throughout the project life cycle.

Following Risk Identification process shall be followed in XXX project.




 16 Risk List
This section lists all identified Risks in the XXX Project. This is the list of Risks as of now and subject to change as
the project progresses. Project Manager shall be responsible to continuously update the risk list.

                 Risk      Risk Description                         Risk Category       Identified
                 No                                                                     During


                 R 001

                 R 002

                 R 003

                 R 004


                                                                                                                   Page | 25
Risk Management Plan



                 R 005

                 R 006

                 R 007

                 R 008

                 R 009

                 R 010


 17 Qualitative Risk Analysis


Qualitative Risk Analysis is the process of assessing the impact and likelihood of identified Risks. Based on this
analysis, the prioritized risks shall be identified and further analyzed and managed.

Risk Probability and Impact Assessment: investigates the likelihood that each risk will occur. Risk impact
assessment investigates the potential effect on a project objective such as time, cost, scope, or quality, including
both negative effects for threats and positive effects for opportunities.
The analysis is done in terms of Risk probability and Risk consequences. Risk probability is the likelihood that Risk
will occur. Risk consequence is the effect on project objectives if the risk event occurs. Both the parameters are
described in three qualitative levels, which are Low, Medium and High.
                                                                                                               Page | 26
Risk Management Plan



The Probability –Impact (PI) value is the multiplication of Probability and Impact. Its value is calculated with the
following equation.

                              Risk Probability (P)   Risk Impact (I)       PI Value

                              High                   High                  Very High

                              High                   Medium                High




                              High                   Low                   Medium

                              Medium                 High                  High

                              Medium                 Medium                Medium




                              Medium                 Low                   Low

                              Low                    High                  Medium

                              Low                    Medium                Low




                              Low                    Low                   Low




                                                                                                                Page | 27
Risk Management Plan




                Risk    Risk Description                    Risk              Risk Impact   PI Value
                No                                          Probability       (I)
                                                            (P)

                R 001

                R 002

                R 003

                R 004

                R 005

                R 007




 18 Quantitative Risk Analysis
The quantitative Risk Analysis process aims to analyze numerically the probability of each risk and its consequence
on project objectives. The Risk Probabilities are measured on a scale of 1 to 1.0 and these values correspond to
10% probability of Risk happening to 100%. The impact of the Risk is captured also on a scale of 1 to 10.




                                                                                                            Page | 28
Risk Management Plan



The PI value is multiplication of these values and all Risks who have a PI value of less than four are not considered
for Risk response planning. However, these calculations shall be periodically reviewed by the PMO.

                Risk    Risk Description                     Risk              Risk         PI Value
                No                                           Probability       Impact (I)
                                                             (P)

                R 001

                R 002

                R 003

                R 004

                R 005

                R 007




                                                                                                              Page | 29
Risk Management Plan




 19 Risk Response Planning


Risk response planning is the process of developing options and determining actions to enhance opportunities and
reduce threats to the project objectives. It includes the identification and assignment of one or more persons (risk
response owner) to take responsibility for each agreed to risk response.

One of the following four approaches shall be used to respond to the Risk.

   o   Avoidance: Risk Avoidance is changing the Project Plan to eliminate the Risk or to protect the Project
       objectives from its impact.


   o   Transference: Risk Transference is to shift the consequence of the Risk to a third party together with
       ownership of the response.


   o   Mitigation: Risk Mitigation is to reduce the probability or consequence of an adverse Risk event to an
       acceptable threshold.


   o   Acceptance: Risk Acceptance is to accept the risk as it is and have a contingency plan in case it occurs.


                 Risk   Risk Description           Risk Response     Risk Response

                                                                                                                Page | 30
Risk Management Plan



No      Technique




R 001

R 002

R 003

R 004

R 005

R 007

R 008

R 009

R 010




                                   Page | 31
Risk Management Plan




 20 Risk Monitoring & Control
Risk monitoring and control is the process of keeping track of the identified Risks, identifying new Risks, ensuring
the execution of the risk response plan and evaluating their effectiveness in reducing Risks. Risk monitoring &
control shall be done throughout the project lifecycle.

Recommended Corrective Actions: include Contingency plans and Workaround Plans. The latter are responses
that were not initially planned, but are required to deal with emerging risks that were previously unidentified or
accepted passively.

Recommended Preventive Actions: These are used to bring the project into compliance with the project
management plan.

                                                       Risk Review and
         Risk No      Risk Description                                         Update on Risk    Status
                                                       Reporting Schedules

         R 001

         R 002

         R 003

         R 004

         R 005

         R 007


                                                                                                               Page | 32
Risk Management Plan




 21 Organization & Responsibilities
This section lists the organization responsibilities of the project with respect to Risks.

           Person                       Role (s)                         Tasks & Responsibilities




                                                                                                    Page | 33

Mais conteúdo relacionado

Mais procurados

Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Managementmovinghats
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principlestltiede
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/FailurePeter Salmon
 
Pmbok 4th edition chapter 4 - Project Integration Management
Pmbok 4th edition   chapter 4 - Project Integration Management Pmbok 4th edition   chapter 4 - Project Integration Management
Pmbok 4th edition chapter 4 - Project Integration Management Ahmad Maharma, PMP,RMP
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project managementMohamed Amin
 
Project portfolio management - webinar
Project portfolio management - webinarProject portfolio management - webinar
Project portfolio management - webinarAli Zeeshan
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP) Ahmad Maharma, PMP,RMP
 
Project Portfolio Management
Project Portfolio ManagementProject Portfolio Management
Project Portfolio ManagementAnand Subramaniam
 
Project Management 101 Primer
Project Management 101   PrimerProject Management 101   Primer
Project Management 101 PrimerGary Drumm
 
Corso di Project Management
Corso di Project ManagementCorso di Project Management
Corso di Project Managementifoasapereutile
 
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...GlobalSkillup
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...JustAcademy
 
Project portfolio management an introduction
Project portfolio management   an introductionProject portfolio management   an introduction
Project portfolio management an introductionAnand Manimaran
 

Mais procurados (20)

Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project portfolio management
Project portfolio managementProject portfolio management
Project portfolio management
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
9.3 Acquire Resources
9.3 Acquire Resources9.3 Acquire Resources
9.3 Acquire Resources
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/Failure
 
Pmbok 4th edition chapter 4 - Project Integration Management
Pmbok 4th edition   chapter 4 - Project Integration Management Pmbok 4th edition   chapter 4 - Project Integration Management
Pmbok 4th edition chapter 4 - Project Integration Management
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project management
 
Project portfolio management - webinar
Project portfolio management - webinarProject portfolio management - webinar
Project portfolio management - webinar
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
 
Project Portfolio Management
Project Portfolio ManagementProject Portfolio Management
Project Portfolio Management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project Management 101 Primer
Project Management 101   PrimerProject Management 101   Primer
Project Management 101 Primer
 
Corso di Project Management
Corso di Project ManagementCorso di Project Management
Corso di Project Management
 
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
 
Project portfolio management an introduction
Project portfolio management   an introductionProject portfolio management   an introduction
Project portfolio management an introduction
 
PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?
 

Semelhante a PMP - Risk Management plan & template

Programme start up document - Optimised Programme Methodology
Programme start up document - Optimised Programme Methodology Programme start up document - Optimised Programme Methodology
Programme start up document - Optimised Programme Methodology Simon Misiewicz
 
System Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptSystem Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptAynetuTerefe2
 
Work shop project management
Work shop project managementWork shop project management
Work shop project managementrakeshsatpathy07
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptxKamranKhan353531
 
2 project management-level 1
2 project management-level 12 project management-level 1
2 project management-level 1Juwad AlOmari
 
Duncan.william
Duncan.williamDuncan.william
Duncan.williamNASAPMC
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptxFawadAfridi6
 
Project Management Foundations Series Course 103 - Project Stakeholder Manage...
Project Management Foundations Series Course 103 - Project Stakeholder Manage...Project Management Foundations Series Course 103 - Project Stakeholder Manage...
Project Management Foundations Series Course 103 - Project Stakeholder Manage...Think For A Change
 
Mandarkulkarni 111003065827-phpapp01
Mandarkulkarni 111003065827-phpapp01Mandarkulkarni 111003065827-phpapp01
Mandarkulkarni 111003065827-phpapp01PMI_IREP_TP
 
13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management OverviewDavidMcLachlan1
 
SE_Lec 11_ Project Management
SE_Lec 11_ Project ManagementSE_Lec 11_ Project Management
SE_Lec 11_ Project ManagementAmr E. Mohamed
 
Project Management Professional (PMP) Fundamentals
Project Management Professional (PMP) FundamentalsProject Management Professional (PMP) Fundamentals
Project Management Professional (PMP) FundamentalsSowmak Bardhan
 
Practical Strategies for Project Recovery Webinar Slides
Practical Strategies for Project Recovery Webinar SlidesPractical Strategies for Project Recovery Webinar Slides
Practical Strategies for Project Recovery Webinar SlidesPM Solutions
 
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SAN
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SANProject Management Discipline - Brown Bag CXB V03 Jun 2009 SAN
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SANcj_barbosa
 
Role andresponsiblities in project management
Role andresponsiblities in project managementRole andresponsiblities in project management
Role andresponsiblities in project managementim8home85
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleAndrew Schwartz
 

Semelhante a PMP - Risk Management plan & template (20)

Programme start up document - Optimised Programme Methodology
Programme start up document - Optimised Programme Methodology Programme start up document - Optimised Programme Methodology
Programme start up document - Optimised Programme Methodology
 
System Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).pptSystem Analysis & Design (CHAPTER TWO) (1).ppt
System Analysis & Design (CHAPTER TWO) (1).ppt
 
Work shop project management
Work shop project managementWork shop project management
Work shop project management
 
Day 1 framework
Day 1 frameworkDay 1 framework
Day 1 framework
 
11. Project Risk Management.pptx
11. Project Risk Management.pptx11. Project Risk Management.pptx
11. Project Risk Management.pptx
 
2 project management-level 1
2 project management-level 12 project management-level 1
2 project management-level 1
 
Duncan.william
Duncan.williamDuncan.william
Duncan.william
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Project Management Foundations Series Course 103 - Project Stakeholder Manage...
Project Management Foundations Series Course 103 - Project Stakeholder Manage...Project Management Foundations Series Course 103 - Project Stakeholder Manage...
Project Management Foundations Series Course 103 - Project Stakeholder Manage...
 
Mandarkulkarni 111003065827-phpapp01
Mandarkulkarni 111003065827-phpapp01Mandarkulkarni 111003065827-phpapp01
Mandarkulkarni 111003065827-phpapp01
 
Ch22
Ch22Ch22
Ch22
 
13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview13.0 Project Stakeholder Management Overview
13.0 Project Stakeholder Management Overview
 
SE_Lec 11_ Project Management
SE_Lec 11_ Project ManagementSE_Lec 11_ Project Management
SE_Lec 11_ Project Management
 
Project Management Professional (PMP) Fundamentals
Project Management Professional (PMP) FundamentalsProject Management Professional (PMP) Fundamentals
Project Management Professional (PMP) Fundamentals
 
Practical Strategies for Project Recovery Webinar Slides
Practical Strategies for Project Recovery Webinar SlidesPractical Strategies for Project Recovery Webinar Slides
Practical Strategies for Project Recovery Webinar Slides
 
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SAN
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SANProject Management Discipline - Brown Bag CXB V03 Jun 2009 SAN
Project Management Discipline - Brown Bag CXB V03 Jun 2009 SAN
 
Role andresponsiblities in project management
Role andresponsiblities in project managementRole andresponsiblities in project management
Role andresponsiblities in project management
 
Iss 02
Iss 02Iss 02
Iss 02
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern Sample
 

Último

The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGSujit Pal
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...HostedbyConfluent
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Paola De la Torre
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 

Último (20)

The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Google AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAGGoogle AI Hackathon: LLM based Evaluator for RAG
Google AI Hackathon: LLM based Evaluator for RAG
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
Transforming Data Streams with Kafka Connect: An Introduction to Single Messa...
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101Salesforce Community Group Quito, Salesforce 101
Salesforce Community Group Quito, Salesforce 101
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 

PMP - Risk Management plan & template

  • 1. Risk Management Plan Project Management Templates RISK MANAGEMENT PLAN 2013 Page | 1
  • 2. Risk Management Plan Index Table of Contents 1 Purpose ..............................................................................................................5 2 Scope ...................................................................................................................5 3 Audience ............................................................................................................5 4 References.........................................................................................................5 5 Glossary..............................................................................................................6 5.1 Acronyms .............................................................................................................6 5.2 Definitions ............................................................................................................7 Stakeholder Analysis...............................................................................................7 5.3 Project Team .......................................................................................................7 5.4 Sponsor ................................................................................................................8 5.5 Steering Committee ...........................................................................................8 5.6 Other Stakeholder(s) Group 1 .........................................................................9 5.7 Other Stakeholder (s) Group 2 ...................................................................... 10 6 Communication Requirements & Responsibilities ........................... 10 7 Communication Process and Technology ............................................ 15 Page | 2
  • 3. Risk Management Plan 8 Communication Record .............................................................................. 17 9 Escalation Process........................................................................................ 18 9.1 Issue Categories ............................................................................................... 18 9.2 Escalation Process for Stakeholder Group 1 ............................................... 19 9.3 Escalation Process for Stakeholder Group 2 ............................................... 19 10 Purpose ............................................................................................................ 22 11 Scope ................................................................................................................. 22 12 Audience .......................................................................................................... 22 13 References....................................................................................................... 23 14 Glossary............................................................................................................ 23 14.1 Acronyms ........................................................................................................ 23 14.2 Definitions....................................................................................................... 24 15 Risk Identification ........................................................................................ 25 16 Risk List ............................................................................................................ 25 17 Qualitative Risk Analysis ........................................................................... 26 18 Quantitative Risk Analysis ........................................................................ 28 19 Risk Response Planning ............................................................................. 30 Page | 3
  • 4. Risk Management Plan 20 Risk Monitoring & Control ......................................................................... 32 21 Organization & Responsibilities .............................................................. 33 Page | 4
  • 5. Risk Management Plan 1 Purpose 2 Scope 3 Audience 4 References Page | 5
  • 6. Risk Management Plan 5 Glossary 5.1 Acronyms Acronym Description PMP Project Management Plan PMO Project Management Office Page | 6
  • 7. Risk Management Plan 5.2 Definitions Term Definition Stakeholder Project Stakeholders are individuals and organizations that are actively involved in the project, or whose interests maybe positively or negatively affected as a project execution or project completion. Stakeholder Analysis 5.3 Project Team S.No. Name Department Role Email Page | 7
  • 8. Risk Management Plan 5.4 Sponsor S.No. Name Department Role Email 5.5 Steering Committee S.No. Name Department Role Email Page | 8
  • 9. Risk Management Plan 5.6 Other Stakeholder(s) Group 1 [Capture information regarding other stakeholder(s), for example a group of stakeholders at customer end.] S.No. Name Department Role Email Page | 9
  • 10. Risk Management Plan 5.7 Other Stakeholder (s) Group 2 [Capture information regarding other stakeholder(s), for example a group of stakeholders at customer end.] S.No. Name Department Role Email 6 Communication Requirements & Responsibilities This section analyzes and captures the communication requirements of each of the Stakeholder’s group and also captures their responsibilities towards the other group. Page | 10
  • 11. Risk Management Plan S.No. Stakeholder Communication Requirements Communication Group Responsibilities 1 Program  Communicate project  Updating all other Management/ objectives. stakeholder group with Project Office accurate information about the project progress.  Objective expectation from all other Stakeholder group about the project aim.  Remove conflict regarding any requirements  Conflicting requirement  Providing all relevant project information in a user friendly  Communicate policies and and timely manner. standards, escalation process  Any Cost or schedule  Communicate success factors, overrun training benefits, deliverables quality requirements  Getting up to date and  Project stakeholder accurate information from the satisfaction. Project team about the status of the ongoing tasks.  Page | 11
  • 12. Risk Management Plan 2 Project Team  Timely clarification of project  Updating Project Office with related requirements ongoing tasks progress  Task assigned to individual  Communicate any training team members requirements to be addressed by PMO Office  Any dependencies of their tasks.  Seek Clarification on conflicting roles and responsibilities  Resolution of Issues within the Project Team  Any issue impacting their task performance  Resolution of Issues with other Project Team  Raise any conflict to PMO office with any team members  Timely update of Issue(s) assigned to a team member. 3 Steering  Summarized Project Progress  Timely resolution of Committee Information. escalated Issues  Summarized Issues  Updating Organization level Page | 12
  • 13. Risk Management Plan Information. Stakeholder with the Project Progress  Deviation between Planned and Actual Schedule (s).  Deviation from allocated budget. 4 Sponsor  Deviation from allocated  Map rewards against budget. performance.  Deviation from Scope of Work.  Timely resolution of escalated Issues.  Project Progress Information  Analyze Project Success  Issues Information  Contribute to Lesson Learnt  Risks  Project Sign off.  Performance reporting of project team members Page | 13
  • 14. Risk Management Plan  Nonconformance of deliverables to project objectives. 5 Other Stakeholder Group 1 6 Other Stakeholder Group 2 Page | 14
  • 15. Risk Management Plan 7 Communication Process and Technology This section captures the communication process used in the Project and technologies used to have effective communication. Stakeholder Communication Steps to get Desired Communication Group Requirements Information Technology Business User  Up to date   PMO Tool information about Project Progress  Regular  Send / Receive  Microsoft communication with Email Exchange e-Business team  Formal meeting with  Face to Face  Meeting members working on Meeting Minutes the project for Template clarification Program  Information about   PMO Tool Management/ project/Task Progress Project Office Page | 15
  • 16. Risk Management Plan  Regular  Send / Receive  Microsoft communication with Email Exchange the Project Team  Formal meeting with  Face to Face  Meeting members working on Meeting Minutes the project Template  Issues capturing  Face to Face  Microsoft Meeting Exchange  Send/ Receive E- Mail  Issue Log Template  Escalation Channel  Face to Face  Microsoft Meeting including, Exchange Sponsor, General Manager, and Steering  Issue Log Committee Template  Send/ Receive E- Mail to/from above stakeholders  Summarized Project  Team Communication (Trouble Tickets, Issues, Resolution) Page | 16
  • 17. Risk Management Plan 8 Communication Record The tabular format describes the Communication Record followed in the project. Communication Purpose Responsibility Audience/ Timing/ Type of Communication Participants/ Frequency Communicati Record Stakeholders on WSR Report Project Weekly Meeting Meeting Minutes status review reporting Steering Project Monthly or Meeting Meeting Minutes Committee Review Need base Meeting Iteration Iteration End of every Meeting Iteration Success Report Review Iteration Summary Report Email Page | 17
  • 18. Risk Management Plan 9 Escalation Process This section covers the escalation process followed in the Project for speedy resolution of the issues identified in the Project. The escalation process is identified in terms of the Key resources of the Project and the next authority in line to address the issues. There shall be different escalation process for different stakeholder group identified above in this plan. 9.1 Issue Categories Escalation process depends upon the Issue categories. There shall be different escalation process and authority for different types of issues. This sections list the three different types of Issue categories identified for the Project.  Technical  Commercial  Project Management Page | 18
  • 19. Risk Management Plan 9.2 Escalation Process for Stakeholder Group 1 S.No. From: Role To: Escalation Issue Category When to Escalate & Name Role & Name 9.3 Escalation Process for Stakeholder Group 2 S.No. From: Role To: Escalation Role Issue Category When to Escalate & Name & Name Page | 19
  • 20. Risk Management Plan TEMPLATE 7: Risk Management Plan Project Name: << >> Version: Release Date: Page | 20
  • 21. Risk Management Plan Document Information Author Reviewer Approver Revision History Date Version Section Change Description Author Changed Page | 21
  • 22. Risk Management Plan 10 Purpose The purpose of this Risk Management Plan is to identify the risks in the project, analyze the impact of these risks and propose steps to manage them. The objectives of Project Risk Management are to increase the probability and impact of positive events, and decrease the probability of events adverse to the project. 11 Scope This document primarily concerns itself with Risks & Mitigation Plan relating to the XXX Project. Risk Management includes processes concerned with conducting risk management planning, identification, analysis, responses, and monitoring and control on a project. The scope of the document is limited to: o Risk Identification o Risk List o Qualitative Risk Analysis o Quantitative Risk Analysis o Risk Response Planning, and o Risk Monitoring & Control 12 Audience The intended audience of this document is: o Page | 22
  • 23. Risk Management Plan 13 References o o 14 Glossary 14.1 Acronyms Acronym Description Page | 23
  • 24. Risk Management Plan 14.2 Definitions Term Definition Risk Risk is an uncertain event or condition, that if occurs, has a positive or negative effect on project objective, such as cost, time, scope, or quality. A risk has a cause and, if it occurs, a consequence. Stakeholder Project Stakeholders are individuals and organizations that are actively involved in the project, or whose interests may be positively or negatively affected as a project execution or project completion. Page | 24
  • 25. Risk Management Plan 15 Risk Identification Risk identification involves determining which risks might affect the project and documenting their characteristics. It is an iterative process. Risks are identified throughout the project life cycle. Following Risk Identification process shall be followed in XXX project. 16 Risk List This section lists all identified Risks in the XXX Project. This is the list of Risks as of now and subject to change as the project progresses. Project Manager shall be responsible to continuously update the risk list. Risk Risk Description Risk Category Identified No During R 001 R 002 R 003 R 004 Page | 25
  • 26. Risk Management Plan R 005 R 006 R 007 R 008 R 009 R 010 17 Qualitative Risk Analysis Qualitative Risk Analysis is the process of assessing the impact and likelihood of identified Risks. Based on this analysis, the prioritized risks shall be identified and further analyzed and managed. Risk Probability and Impact Assessment: investigates the likelihood that each risk will occur. Risk impact assessment investigates the potential effect on a project objective such as time, cost, scope, or quality, including both negative effects for threats and positive effects for opportunities. The analysis is done in terms of Risk probability and Risk consequences. Risk probability is the likelihood that Risk will occur. Risk consequence is the effect on project objectives if the risk event occurs. Both the parameters are described in three qualitative levels, which are Low, Medium and High. Page | 26
  • 27. Risk Management Plan The Probability –Impact (PI) value is the multiplication of Probability and Impact. Its value is calculated with the following equation. Risk Probability (P) Risk Impact (I) PI Value High High Very High High Medium High High Low Medium Medium High High Medium Medium Medium Medium Low Low Low High Medium Low Medium Low Low Low Low Page | 27
  • 28. Risk Management Plan Risk Risk Description Risk Risk Impact PI Value No Probability (I) (P) R 001 R 002 R 003 R 004 R 005 R 007 18 Quantitative Risk Analysis The quantitative Risk Analysis process aims to analyze numerically the probability of each risk and its consequence on project objectives. The Risk Probabilities are measured on a scale of 1 to 1.0 and these values correspond to 10% probability of Risk happening to 100%. The impact of the Risk is captured also on a scale of 1 to 10. Page | 28
  • 29. Risk Management Plan The PI value is multiplication of these values and all Risks who have a PI value of less than four are not considered for Risk response planning. However, these calculations shall be periodically reviewed by the PMO. Risk Risk Description Risk Risk PI Value No Probability Impact (I) (P) R 001 R 002 R 003 R 004 R 005 R 007 Page | 29
  • 30. Risk Management Plan 19 Risk Response Planning Risk response planning is the process of developing options and determining actions to enhance opportunities and reduce threats to the project objectives. It includes the identification and assignment of one or more persons (risk response owner) to take responsibility for each agreed to risk response. One of the following four approaches shall be used to respond to the Risk. o Avoidance: Risk Avoidance is changing the Project Plan to eliminate the Risk or to protect the Project objectives from its impact. o Transference: Risk Transference is to shift the consequence of the Risk to a third party together with ownership of the response. o Mitigation: Risk Mitigation is to reduce the probability or consequence of an adverse Risk event to an acceptable threshold. o Acceptance: Risk Acceptance is to accept the risk as it is and have a contingency plan in case it occurs. Risk Risk Description Risk Response Risk Response Page | 30
  • 31. Risk Management Plan No Technique R 001 R 002 R 003 R 004 R 005 R 007 R 008 R 009 R 010 Page | 31
  • 32. Risk Management Plan 20 Risk Monitoring & Control Risk monitoring and control is the process of keeping track of the identified Risks, identifying new Risks, ensuring the execution of the risk response plan and evaluating their effectiveness in reducing Risks. Risk monitoring & control shall be done throughout the project lifecycle. Recommended Corrective Actions: include Contingency plans and Workaround Plans. The latter are responses that were not initially planned, but are required to deal with emerging risks that were previously unidentified or accepted passively. Recommended Preventive Actions: These are used to bring the project into compliance with the project management plan. Risk Review and Risk No Risk Description Update on Risk Status Reporting Schedules R 001 R 002 R 003 R 004 R 005 R 007 Page | 32
  • 33. Risk Management Plan 21 Organization & Responsibilities This section lists the organization responsibilities of the project with respect to Risks. Person Role (s) Tasks & Responsibilities Page | 33