SlideShare uma empresa Scribd logo
1 de 23
Baixar para ler offline
SEMINAR REPORT ON:

SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS.
At

NTPC-SAIL Power Company Private Limited, Rourkela.

Submitted By:

PARTHA SARATHI PARIDA
REG NO. 10010133
7TH SEMESTER
ELECTRICAL ENGINEERING

VEER SURENDRA SAI UNIVERSITY OF TECHNOLOGY, BURLA, ODISHA.
DEPARTMENT OF ELECTRICAL ENGINEERING
NSPCL, ROURKELA CAPTIVE POWER PLANT
NTPC Ltd formed joint venture with SAIL on 50:50 basis in March 2001 in the name
of NTPC-SAIL Power Company Private Limited (NSPCL). NSPCL took over captive
power plant-II located at Rourkela Steel Plant (2X60 MW) from SAIL.

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

2
AN OVERVIEW OF CPP :-

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

3
MAJOR EQUIPMENT IN CPP :• 2 GENERATORS
• 2 GENERATOR TRANSFORMERS
• 2 UNIT AUXILIARY TRANSFORMERS
• STATION TRANSFORMERS

• FEEDERS

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

4
TECHNICAL DATA OF GENERATOR UNIT 1 AND 2:
• Generator Type :

THRI 86/35

• Year of manufacture :

1985

• Stator No. :

1134 & 1135

• Rotor No. :

1134 & 1135

• Exciter type :

Static

• Apparent power :

75 MVA

• Active power :

60 MW

• Current :

3.766 KA

• Voltage :

11.5 KV +5%

• Speed :

3000 Rpm

• Frequency :

50 Hz

• Power Factor :

0.8

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

5
TECHNICAL DATA OF GEN. TRANSFORMER UNIT
1 AND 2:
• Make :

Crompton Greaves Ltd

• Rating :

16.5/33/82.5/ MVA

• Type of cooling :

ONAN/ONAF/OFAF

• No load voltage :

HV : 138KV , LV : 11.5KV

• Winding :

HV : STAR , LV : DELTA

• Phases :

3/3

• Frequency :

50 Hz

• Vector group :

Ynd 11

• Rated current :

HV : 345.20Amps ,LV 4141.90
Amps

• Total oil qty :

24,470 Lts

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

6
TECHNICAL DATA OF UNIT AUX. TRANSFORMER
UNIT 1 AND 2:
• Make :

Crompton Greaves Ltd

• Rating :

12.5 MVA

• Type of cooling :

ONAN

• Voltage :

HV : 11.5 KV , LV : 6.9 KV

• Phases :

3/3

• Frequency :

50 Hz

• Vector group :

DYN 1

• Rated current :

HV : 627.5 Amps ,
LV:1045.9 Amps

• Total oil qty. :

9,000 Lts

• Percentage impedance voltage :

7%

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

7
TECHNICAL DATA OF STATION AUXILIARY
TRANSFORMER:
• Make :

Crompton Graeves Ltd

• Rating :

20/25 MVA

• Cooling :

ONAN/ONAF

• No Load voltage :

132/6.9/3.3 KV (UNLOADED )

• Current:

HV 109.3 Amps LV 2091.8 Amps

• Frequency :

50 Hz

• Vector Group :

YNY nd 011

• quantity of oil :

17500Lts

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

8
SWITCHYARD:
SALIENT FEATURES OF 132KV SWITCHTYARD:•
•
•
•
•
•
•
•
•

20 OPERATING BAYS
02 GENERATORS
04 GRIDCO FEEDERS
06 SMELTER FEEDERS
BUS COUPLER
BUS TIE CUM BUS COUPLER
STATION TRANSFORMERS
01 BT BAY
ISOLATION TRANSFORMERS

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

9
IMPORTANT COMPONENTS OF THE SWITCH YARD:
1. BUSBARS:
TYPES OF BUSBAR ARRANGEMENTS:
1. Single Bus-bar Arrangement.
2. Single Bus-bar System with Sectionalization
3. Ring Bus-bar system
4. Double Main and Transfer Bus-bar Arrangement
5. Duplicate Bus-bars System

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

10
1. SINGLE BUS-BAR ARRANGEMENT
In this arrangement a set of bus-bars is used for complete power station and
to this bus-bar are connected all generators, transformers and feeders
through circuit breakers and isolating switches.

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

11
2. SINGLE BUS-BAR SYSTEM WITH SECTIONALIZATION
With increased number of generators and outgoing feeders connected to
the bus-bars, it becomes essential to provide arrangement for
sectionalizing the bus-bars so that a fault on any one section of the busbars may not cause a complete shutdown. This is achieved by providing
a circuit breaker and isolating switches between the section.

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

12
3. RING BUS-BAR SYSTEM
In this arrangement each feeder is supplied from two paths, so that in
case of failure of a section, supply is not interrupted.

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

13
4. DOUBLE MAIN AND TRANSFER BUS-BAR
ARRANGEMENT
This arrangement incorporates all advantages of the double bus as well as
transfer bus scheme. This scheme needs a bus-coupler for the on load transfer of
circuits from one main bus to the other and a transfer coupler for taking out
circuit breaker of various circuits for maintenance.

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

14
2. BUS COUPLER:
• Two different bus sections of two different power transformers are
connected by means of a bus coupler.
• The bus coupler becomes useful when one of the power transformers
fails or a fault occurs in either of the bus sections.

3. INSULATORS:
• The overhead line conductors should be supported on the poles or
towers in such a way that currents from conductors do not flow to
earth through supports i.e., line conductors must be properly insulated
from supports. This is achieved by securing line conductors to supports
with the help of INSULATORS.
• The insulators provide necessary insulation between line conductors
and supports and thus prevent any leakage current from conductors to
earth.

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

15
TYPES OF INSULATORS:

1.PIN TYPE:

3. STRAIN
INSULATORS:
03-Nov-2013

2. SUSPENSION
TYPE:

4. SHACKEL
INSULATORS:

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

16
4. CIRCUIT BREAKER & RELAYS:
• A circuit breaker is an automatically operated electrical switch designed
to protect an electrical current from damage caused by overload or
short circuit.
• Its basic function is to detect a fault condition and, by interrupting
continuity, to immediately discontinue electrical flow.
• The circuit breaker works along with the relays which give a tripping
signal in case of any irregularity or the faults.

• The circuit breaker then opens to open the circuit such that other
instruments of the system can be protected.

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

17
5. ISOLATORS: (GOD)- GROUP OPERATED DISCONNECTOR:
• It is used to make sure that an electrical circuit can be completely deenergised for service or maintenance.

• It allows isolation of apparatus such as circuit breakers and
transformers, and transmission lines, for maintenance.
• GOD’s are provided to facilitate isolation of breakers supplying power to
various feeders. In 220kv Switchyard, they are designed as 29A, 29B,
29C & 29E as follows





03-Nov-2013

29 A – main bus side GOD.
29 B - Equipment side GOD.
29 C - Transfer bus side GOD.
29 E - Earth GOD.

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

18
6. Current and voltage transformers
• Current or voltage instrument transformers are necessary for isolating
the protection, control and measurement equipment from the high
voltages of a power system, and for supplying the equipment with the
appropriate values of current and voltage - generally these are 1A or 5Α
for the current coils, and 120 V for the voltage coils.

CURRENT TRANSFORMER
03-Nov-2013

VOLTAGE TRANSFORMER

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

19
8. LIGHTNING ARRESTER:
• A lightning arrester is a device used on electrical power systems
and telecommunication systems to protect the insulation and
conductors of the system from the damaging effects of lightning.
• The typical lightning arrester has a high-voltage terminal and a ground
terminal.
• When a lightning surge (or switching surge, which is very similar) travels
along the power line to the arrester, the current from the surge is
diverted through the arrestor, in most cases to earth.

LIGHTNING ARRESTER
03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

20
TRANSFORMER YARD:
• Transformer yard consists of following types of transformers

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

21
CONCLUSION :• Switchyard is most essential part of the power system.
• It is the protective part of the whole power system.
• Switch yard is also most essential part for transmission, distribution, and
collection.

BIBILIOGRAPHY :1. http://wikipedia.com
2. http://google.co.in
3. http://www.engineersedge.com
4. http://www.scribd.com
5. http://electricals4u.com
6. Power system Engineering by O P KOTHARI and I J NAGRATH
7. Power System By J B GUPTA

03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

22
03-Nov-2013

DEPARTMENT OF ELECTRICAL ENGINEERING,
V.S.S.U.T,BURLA

23

Mais conteúdo relacionado

Mais procurados

ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
J. FR
 

Mais procurados (20)

Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakir
 
Substations
SubstationsSubstations
Substations
 
IEEE substation design
IEEE substation designIEEE substation design
IEEE substation design
 
Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training
 
Substation protection devices
Substation protection devicesSubstation protection devices
Substation protection devices
 
132 33kv substation
132 33kv substation132 33kv substation
132 33kv substation
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substation
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 
5. Switchyard & Substation
5. Switchyard & Substation5. Switchyard & Substation
5. Switchyard & Substation
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
220kv substation
220kv substation220kv substation
220kv substation
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protection
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
 
132 kv
132 kv132 kv
132 kv
 
BUSBAR PROTECTION
BUSBAR PROTECTIONBUSBAR PROTECTION
BUSBAR PROTECTION
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
Power transformer protection
Power transformer protectionPower transformer protection
Power transformer protection
 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 
transformer protection
transformer protection transformer protection
transformer protection
 

Destaque

distribution system fault mangement
distribution system fault mangementdistribution system fault mangement
distribution system fault mangement
Manjunath Ds
 
Y R ENGG Company Profile 2
Y R ENGG Company Profile 2Y R ENGG Company Profile 2
Y R ENGG Company Profile 2
R.K. Mathuria
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
Biswajit Pratihari
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
moiz89
 

Destaque (19)

distribution system fault mangement
distribution system fault mangementdistribution system fault mangement
distribution system fault mangement
 
Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...
 
File 1 power system fault analysis
File 1 power system fault analysisFile 1 power system fault analysis
File 1 power system fault analysis
 
Practical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesPractical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety Rules
 
Y R ENGG Company Profile 2
Y R ENGG Company Profile 2Y R ENGG Company Profile 2
Y R ENGG Company Profile 2
 
Earthing system
Earthing systemEarthing system
Earthing system
 
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...ppt of Three phase fault analysis with auto reset for temporary fault and tri...
ppt of Three phase fault analysis with auto reset for temporary fault and tri...
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthing
 
Earthing Concepts
Earthing ConceptsEarthing Concepts
Earthing Concepts
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
 
Electrical earthing
Electrical earthingElectrical earthing
Electrical earthing
 
POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION POWER SYSTEM PROTECTION
POWER SYSTEM PROTECTION
 
Importance of industrial safety
Importance of industrial safetyImportance of industrial safety
Importance of industrial safety
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety
 
Top 10 rules for electric safety
Top 10 rules for electric safetyTop 10 rules for electric safety
Top 10 rules for electric safety
 
Electrical safety new
Electrical safety newElectrical safety new
Electrical safety new
 
Industrial safety
Industrial safetyIndustrial safety
Industrial safety
 
Substation overview
Substation overviewSubstation overview
Substation overview
 

Semelhante a SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS

Manish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptxManish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptx
Manish Gangwal
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
Mohit Kothari
 
Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0
Mohit Kothari
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
Mohit Kothari
 
Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7
Sachin Airan
 
Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02
Md Hasan
 

Semelhante a SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS (20)

pptpdf-131117235616-phpapp02.pdf
pptpdf-131117235616-phpapp02.pdfpptpdf-131117235616-phpapp02.pdf
pptpdf-131117235616-phpapp02.pdf
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 
INTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptx
INTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptxINTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptx
INTERNSHhjjhuhjjkhhjhjjhhjhhIP ppt-1.pptx
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
Manish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptxManish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptx
 
Design of substation
Design of substationDesign of substation
Design of substation
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
 
Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0Gssherap 110901224655-phpapp0
Gssherap 110901224655-phpapp0
 
Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02Gssherap 110901224655-phpapp02
Gssherap 110901224655-phpapp02
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmission
 
132 kv substation
132 kv substation132 kv substation
132 kv substation
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
 
Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7Lab manual psd v sem experiment no 7
Lab manual psd v sem experiment no 7
 
Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02Amanppt 140826070457-phpapp02
Amanppt 140826070457-phpapp02
 
132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL
 
DPL Transmission And Distribution
DPL Transmission And DistributionDPL Transmission And Distribution
DPL Transmission And Distribution
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
 
Indusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptxIndusrtrial training ppt (1).pptx
Indusrtrial training ppt (1).pptx
 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
 

Último

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 

Último (20)

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 

SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS

  • 1. SEMINAR REPORT ON: SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS. At NTPC-SAIL Power Company Private Limited, Rourkela. Submitted By: PARTHA SARATHI PARIDA REG NO. 10010133 7TH SEMESTER ELECTRICAL ENGINEERING VEER SURENDRA SAI UNIVERSITY OF TECHNOLOGY, BURLA, ODISHA. DEPARTMENT OF ELECTRICAL ENGINEERING
  • 2. NSPCL, ROURKELA CAPTIVE POWER PLANT NTPC Ltd formed joint venture with SAIL on 50:50 basis in March 2001 in the name of NTPC-SAIL Power Company Private Limited (NSPCL). NSPCL took over captive power plant-II located at Rourkela Steel Plant (2X60 MW) from SAIL. 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 2
  • 3. AN OVERVIEW OF CPP :- 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 3
  • 4. MAJOR EQUIPMENT IN CPP :• 2 GENERATORS • 2 GENERATOR TRANSFORMERS • 2 UNIT AUXILIARY TRANSFORMERS • STATION TRANSFORMERS • FEEDERS 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 4
  • 5. TECHNICAL DATA OF GENERATOR UNIT 1 AND 2: • Generator Type : THRI 86/35 • Year of manufacture : 1985 • Stator No. : 1134 & 1135 • Rotor No. : 1134 & 1135 • Exciter type : Static • Apparent power : 75 MVA • Active power : 60 MW • Current : 3.766 KA • Voltage : 11.5 KV +5% • Speed : 3000 Rpm • Frequency : 50 Hz • Power Factor : 0.8 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 5
  • 6. TECHNICAL DATA OF GEN. TRANSFORMER UNIT 1 AND 2: • Make : Crompton Greaves Ltd • Rating : 16.5/33/82.5/ MVA • Type of cooling : ONAN/ONAF/OFAF • No load voltage : HV : 138KV , LV : 11.5KV • Winding : HV : STAR , LV : DELTA • Phases : 3/3 • Frequency : 50 Hz • Vector group : Ynd 11 • Rated current : HV : 345.20Amps ,LV 4141.90 Amps • Total oil qty : 24,470 Lts 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 6
  • 7. TECHNICAL DATA OF UNIT AUX. TRANSFORMER UNIT 1 AND 2: • Make : Crompton Greaves Ltd • Rating : 12.5 MVA • Type of cooling : ONAN • Voltage : HV : 11.5 KV , LV : 6.9 KV • Phases : 3/3 • Frequency : 50 Hz • Vector group : DYN 1 • Rated current : HV : 627.5 Amps , LV:1045.9 Amps • Total oil qty. : 9,000 Lts • Percentage impedance voltage : 7% 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 7
  • 8. TECHNICAL DATA OF STATION AUXILIARY TRANSFORMER: • Make : Crompton Graeves Ltd • Rating : 20/25 MVA • Cooling : ONAN/ONAF • No Load voltage : 132/6.9/3.3 KV (UNLOADED ) • Current: HV 109.3 Amps LV 2091.8 Amps • Frequency : 50 Hz • Vector Group : YNY nd 011 • quantity of oil : 17500Lts 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 8
  • 9. SWITCHYARD: SALIENT FEATURES OF 132KV SWITCHTYARD:• • • • • • • • • 20 OPERATING BAYS 02 GENERATORS 04 GRIDCO FEEDERS 06 SMELTER FEEDERS BUS COUPLER BUS TIE CUM BUS COUPLER STATION TRANSFORMERS 01 BT BAY ISOLATION TRANSFORMERS 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 9
  • 10. IMPORTANT COMPONENTS OF THE SWITCH YARD: 1. BUSBARS: TYPES OF BUSBAR ARRANGEMENTS: 1. Single Bus-bar Arrangement. 2. Single Bus-bar System with Sectionalization 3. Ring Bus-bar system 4. Double Main and Transfer Bus-bar Arrangement 5. Duplicate Bus-bars System 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 10
  • 11. 1. SINGLE BUS-BAR ARRANGEMENT In this arrangement a set of bus-bars is used for complete power station and to this bus-bar are connected all generators, transformers and feeders through circuit breakers and isolating switches. 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 11
  • 12. 2. SINGLE BUS-BAR SYSTEM WITH SECTIONALIZATION With increased number of generators and outgoing feeders connected to the bus-bars, it becomes essential to provide arrangement for sectionalizing the bus-bars so that a fault on any one section of the busbars may not cause a complete shutdown. This is achieved by providing a circuit breaker and isolating switches between the section. 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 12
  • 13. 3. RING BUS-BAR SYSTEM In this arrangement each feeder is supplied from two paths, so that in case of failure of a section, supply is not interrupted. 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 13
  • 14. 4. DOUBLE MAIN AND TRANSFER BUS-BAR ARRANGEMENT This arrangement incorporates all advantages of the double bus as well as transfer bus scheme. This scheme needs a bus-coupler for the on load transfer of circuits from one main bus to the other and a transfer coupler for taking out circuit breaker of various circuits for maintenance. 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 14
  • 15. 2. BUS COUPLER: • Two different bus sections of two different power transformers are connected by means of a bus coupler. • The bus coupler becomes useful when one of the power transformers fails or a fault occurs in either of the bus sections. 3. INSULATORS: • The overhead line conductors should be supported on the poles or towers in such a way that currents from conductors do not flow to earth through supports i.e., line conductors must be properly insulated from supports. This is achieved by securing line conductors to supports with the help of INSULATORS. • The insulators provide necessary insulation between line conductors and supports and thus prevent any leakage current from conductors to earth. 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 15
  • 16. TYPES OF INSULATORS: 1.PIN TYPE: 3. STRAIN INSULATORS: 03-Nov-2013 2. SUSPENSION TYPE: 4. SHACKEL INSULATORS: DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 16
  • 17. 4. CIRCUIT BREAKER & RELAYS: • A circuit breaker is an automatically operated electrical switch designed to protect an electrical current from damage caused by overload or short circuit. • Its basic function is to detect a fault condition and, by interrupting continuity, to immediately discontinue electrical flow. • The circuit breaker works along with the relays which give a tripping signal in case of any irregularity or the faults. • The circuit breaker then opens to open the circuit such that other instruments of the system can be protected. 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 17
  • 18. 5. ISOLATORS: (GOD)- GROUP OPERATED DISCONNECTOR: • It is used to make sure that an electrical circuit can be completely deenergised for service or maintenance. • It allows isolation of apparatus such as circuit breakers and transformers, and transmission lines, for maintenance. • GOD’s are provided to facilitate isolation of breakers supplying power to various feeders. In 220kv Switchyard, they are designed as 29A, 29B, 29C & 29E as follows     03-Nov-2013 29 A – main bus side GOD. 29 B - Equipment side GOD. 29 C - Transfer bus side GOD. 29 E - Earth GOD. DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 18
  • 19. 6. Current and voltage transformers • Current or voltage instrument transformers are necessary for isolating the protection, control and measurement equipment from the high voltages of a power system, and for supplying the equipment with the appropriate values of current and voltage - generally these are 1A or 5Α for the current coils, and 120 V for the voltage coils. CURRENT TRANSFORMER 03-Nov-2013 VOLTAGE TRANSFORMER DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 19
  • 20. 8. LIGHTNING ARRESTER: • A lightning arrester is a device used on electrical power systems and telecommunication systems to protect the insulation and conductors of the system from the damaging effects of lightning. • The typical lightning arrester has a high-voltage terminal and a ground terminal. • When a lightning surge (or switching surge, which is very similar) travels along the power line to the arrester, the current from the surge is diverted through the arrestor, in most cases to earth. LIGHTNING ARRESTER 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 20
  • 21. TRANSFORMER YARD: • Transformer yard consists of following types of transformers 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 21
  • 22. CONCLUSION :• Switchyard is most essential part of the power system. • It is the protective part of the whole power system. • Switch yard is also most essential part for transmission, distribution, and collection. BIBILIOGRAPHY :1. http://wikipedia.com 2. http://google.co.in 3. http://www.engineersedge.com 4. http://www.scribd.com 5. http://electricals4u.com 6. Power system Engineering by O P KOTHARI and I J NAGRATH 7. Power System By J B GUPTA 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 22
  • 23. 03-Nov-2013 DEPARTMENT OF ELECTRICAL ENGINEERING, V.S.S.U.T,BURLA 23