SlideShare uma empresa Scribd logo
1 de 148
Baixar para ler offline
Chapter five – Transport                                                                                              107




  proposals

5.1 Introduction – a balanced                                   medium distance, particularly in growing areas
                                                                such as the London Thames Gateway can be
and integrated approach                                         best accommodated by bus, tram or light rail
                                                                such as DLR, whereas the more dispersed trips
233   Chapter four outlines the strategic policies
                                                                in Outer London tend to favour bus, bike (over
      that are required to meet the objectives of the
                                                                a shorter distance) and car Local short distance
      MTS There are a number of tools available
                                                                journeys present the best opportunity for
      to implement these policies such as investing
                                                                walking and cycling
      in the transport network to provide more
      capacity and better connectivity, managing
                                                          236   As a consequence, different areas of London
      and influencing the demand for travel and
                                                                require different policy interventions Proposals
      introduction of new technology to reduce
                                                                for central London will inevitably focus on
      emissions As always, there are trade-offs which
                                                                tackling congestion, increasing the capacity
      means a balanced approach must be taken
                                                                of the rail network, encouraging walking and
                                                                cycling, and managing demand In Outer
234   London’s transport network is finite and there
                                                                London, proposals need to acknowledge the




                                                                                                                         Chapter five
      is often competition for this limited space,
                                                                role of the car, especially low emission cars
      whether it is for road space or rail paths In
                                                                For Outer London town centres, measures to
      striking the right balance in using this scarce
                                                                improve bus accessibility, public realm, walking
      resource the proposals in this chapter recognise
                                                                and cycling will generally be prioritised There
      that all the varying needs of London need to
                                                                may be places where a number of options are
      be met – the needs for international links (as
                                                                possible In these cases further work will be
      a global city), for national links (as a national
                                                                required to assess the most effective solution,
      capital), and more local links (London is a
                                                                bearing in mind the cost of the scheme both in
      place where people live, visit and work)
                                                                construction and during operation The need
      The proposals set out in this chapter cater
                                                                to recognise affordability and business case
      for all of these needs
                                                                constraints will be paramount given the current
                                                                financial environment, and this will inevitably
235   The specific transport proposals have to
                                                                preclude some schemes
      be considered in terms of effectiveness,
      acceptability and cost There may be an obvious
                                                          237   Due to the dispersed nature of trips in Outer
      ‘best mode for the task’, for example, only
                                                                London, the role of the car is acknowledged as
      rail-based modes can provide the sufficient
                                                                sometimes necessary, particularly for medium
      capacity to cater for the very high volume
                                                                to longer distance trips The use of cleaner, low
      ‘same time, same place’ demand that occurs
                                                                emission cars will be encouraged over others
      twice a day during the week to, and from,
      central London Similarly, regular high to
                                                          238   Most freight is moved by road While a mode
      medium volume demand over a short to
                                                                shift from road to rail and water is needed to

                                                                                   Chapter five – Transport proposals
108     Mayor’s Transport Strategy – Public Draft




            achieve the goals of the strategy, for some                economic sectors, as well as more flexible
            types of freight, and for many servicing trips,            working practices This highlights the need for a
            access by road will remain a requirement The               transport strategy that is integrated with other
            strategy therefore needs to ensure that the                broader policy areas such as land use planning,
            freight left on the roads (which will be the               education and healthcare provision
            majority) is moved as efficiently as possible
            while contributing to goals of the strategy          240   The proposals for each mode or policy area
            This will require cleaner, better driven vehicles,         contained in the following chapter are derived
            better journey planning and the integration of             from how they can best support the strategic
            freight and land use planning                              transport policies set out in chapter four,
                                                                       having regard to the nature of the mode
      239   Interventions can also be temporal as well as              and policy objectives They have also been
            spatial The need to satisfy and cater for peak             developed using an integrated approach,
            demand means there is spare capacity off-peak              taking account of wider strategies both within
            Greater use of transport throughout the week               London such as the London Plan, Economic
            can help cover the fixed costs of provision and            Development Strategy, Air Quality and Housing
            make the best use of investment The seven-                 strategies, as well as looking beyond the GLA
            day week, 365-day-a-year, diverse economy                  boundary to the Greater South East region
            is something the London Plan seeks to
            encourage through policy support for tourism,
            retail, arts and entertainment and emerging




      Chapter five – Transport proposals
109




Proposals to manage and
enhance the transport system
5.2 National Rail, Crossrail,                             243   Eurostar services currently either run non-stop
                                                                or make only one intermediate stop between
Thameslink, Overground,                                         St Pancras International and the Channel
DLR, Tramlink                                                   Tunnel, with services calling at either Ebbsfleet
                                                                International or Ashford International Beyond
5.2.1 Introduction                                              2010, EU policies will permit competition




                                                                                                                          Chapter five
                                                                for international rail services, which may
241   London is more dependent on rail than any
                                                                result in an increase in international high-
      other city in the UK: 70 per cent of all rail
                                                                speed rail services to/from London This
      travel in the UK is to, or from, the Capital
                                                                will provide an opportunity to encourage
      London’s success is bound up with the future
                                                                more direct rail services to a wider range of
      of its rail network and services It is vitally
                                                                European destinations and to utilise Stratford
      important, therefore, that Network Rail and
                                                                International station in order to reduce
      the train operating companies better serve the
                                                                congestion at St Pancras International, and to
      city’s needs, and that the Mayor has greater
                                                                provide better international connections to
      input and influence over planning and delivery
                                                                the Isle of Dogs and east London
      of their services

5.2.2 International and National Rail                            Proposal 1
links and services                                               The Mayor, through TfL, and working
                                                                 with the DfT, Network Rail, the operators
International rail passenger links                               of international rail services and other
242   The strategy fully supports expansion of                   transport stakeholders, will encourage more
      international rail services that improve London’s          international rail services direct to a wider
      connectivity with Europe and provide a viable              range of European destinations, and that
      alternative to air travel                                  some of those new services also stop at
                                                                 Stratford International station



                                                                                    Chapter five – Transport proposals
110     Mayor’s Transport Strategy – Public Draft




      International and national rail freight
                                                                       Proposal 2
      245   International and national movement of                     The Mayor, through TfL, and working with the
            freight plays an important role in the success             DfT, Network Rail, train operating companies,
            of London’s economy and the Mayor will                     freight operating companies, boroughs and
            work with others to seek to deliver enhanced               other transport stakeholders, will support the
            rail freight capacity through supporting new               development of more rail freight terminals
            terminals to facilitate efficient movement of              in or near London, including connections to
            goods; and encourage transfer of freight from              HS1 for international freight, in line with the
            road to rail wherever possible                             London Plan policy to identify new sites for
                                                                       strategic rail freight interchanges
      246   The new £1 5bn container port, known as
            London Gateway, near Tilbury, will provide          250   A number of rail routes in London are used by
            substantial additional port capacity in the               freight services passing through the Capital,
            South East when it opens in 2011, which                   for example, on their way to the Midlands from
            will generate new rail freight flows passing              Channel ports and from Europe via the Channel
            through London                                            Tunnel While the use of rail for these kinds of
                                                                      freight movements is supported, this ‘through’
      247   A rail connected freight transhipment facility
                                                                      traffic should have a minimal impact on the
            at Howbury Park, near Slade Green, is being
                                                                      capacity of the passenger rail network and on
            developed, and is expected to open in 2010,
                                                                      local communities through noise
            enabling the transfer of road freight to rail
            A new rail freight hub is also proposed at
            Brent Cross/Cricklewood                                    Proposal 3
                                                                       The Mayor, through TfL and working with the
      248   High Speed 1 (HS1) is an under-used facility               DfT, Network Rail, train operating companies,
            for rail freight and has the unique benefits of            freight operating companies, boroughs and
            the larger European gauge clearance for ‘high-             other transport stakeholders, will support
            cube’ containers and the possibility of express            the development of National Rail routes that
            freight services carrying high value goods                 relieve London of freight without an origin or
            To enable this, terminal facilities are required,          destination in the Capital
            with the London riverside area of the Thames
            Gateway being the site identified




      Chapter five – Transport proposals
111




Domestic high-speed rail                               flights, yet generate up to £55bn in revenue
                                                       and benefits over a 60-year period for the
252   The introduction of the first domestic high-     UK economy With the potential to offer
      speed services in the UK on HS1 in 2009, has     journey times from London to Manchester in
      significantly reduced journey times from Kent    66 minutes and to Edinburgh in two hours
      and the Thames Gateway to central London         and nine minutes, such a new line could also
      Elsewhere, domestic rail service journey times   provide new capacity of 9,100 seats per hour
      from London to the regions can be longer than    into central London Further benefits according
      passenger expectations, particularly when        to Network Rail, could include significant CO2
      compared to European competitors who have        reductions from modal switch to high-speed
      invested in high-speed rail networks             rail from both air and road, and the release
                                                       of capacity on the existing West Coast Main
253   Peak-hour crowding is also a major issue,        Line for more commuter and freight services
      emphasised by the fact that the National Rail    Network Rail is sharing the results of its new
      network carries 60 per cent more passengers      line study with High Speed Two, the company
      today than it did in 1994, yet the number




                                                                                                               Chapter five
                                                       set up by the government to investigate
      of actual train services has only increased by   options for a new-high speed line from London
      five per cent Capacity is critical on a number   to the west Midlands and potentially beyond,
      of main lines out of London, in particular the   which is due to report back with its own
      East Coast Main Line to Yorkshire, the north     findings by the end of 2009
      east and Scotland and the Great Western Main
      Line to the southwest and south Wales The
                                                        Proposal 4
      West Coast Main Line to the west Midlands,
      northwest and Scotland has recently benefited     The Mayor and TfL support the
      from a £9bn upgrade allowing faster and more      development of a national high-speed
      frequent services, yet according to Network       rail network and will work with the DfT,
      Rail, by 2020, the main line from London to       Network Rail, High Speed Two and other
      Birmingham and the northwest will be full,        transport stakeholders to ensure that the
      given projected growth                            London terminal for any new high-speed
                                                        line is centrally located, well-connected
254   Network Rail has recently published its           to the existing public transport network,
      proposals for a new high-speed rail line          and widely accessible in order to maximise
      from the centre of London to Birmingham,          access to jobs and London’s population
      Manchester and on to Glasgow and Edinburgh        It is currently considered that Euston best
      The strategic business case that forms part       meets these criteria and further evaluation
      of its new line study identifies that such a      will be made of this and other locations
      new high-speed line could lead to a reduction
      of up to 20,000 annual domestic short haul

                                                                         Chapter five – Transport proposals
112     Mayor’s Transport Strategy – Public Draft




      5.2.3 London and the South East rail                      Crossrail
      links and services
                                                                259   Crossrail is the biggest transport project in
      Accommodating growth on the                                     Europe and a scheme of national importance
      National Rail network                                           that will provide a rail spine across London
                                                                      from east to west, as shown in Figure 30 It is
      256   Rail will continue to be the dominant mode in             needed to underpin the most rapid economic
            accessing central London, with three quarters             growth areas of London and will be a very
            of all trips from Outer London to central                 significant capacity addition to the transport
            London made by National Rail, Tube and DLR                network Figure 29 illustrates the immense
            As the number of trips into central London                scale of the scheme with the example of the
            increases, inevitably the demand on the                   new station at Tottenham Court Road, which
            National Rail network will increase, with some            will transform access to this area of the West
            lines into London seeing demand growth of                 End from the current crowded and congested
            up to 30 per cent by 2031                                 conditions to a spacious, high quality and
                                                                      attractive travel environment, capable of
      257   BAA/Heathrow Airport Limited have recently                supporting local economic intensification
            applied to the Secretary of State for Transport
            as part of the Transport and Works Act 1992         260   When completed in 2017, Crossrail will enable
            process, to authorise construction of Airtrack,           the City and Canary Wharf to continue to
            a new rail link connecting the existing rail              maintain their leading business status in the
            line from Waterloo to Reading with Heathrow               world, support the continued development
            Terminal 5 More information about Airtrack is             of the West End, help to lock-in the legacy
            contained in the Airports section of the strategy         benefits of the 2012 Games, and transform the
                                                                      Thames Gateway through links to northeast
      258   The DfT has also announced its intention to               and southeast London and on into Essex
            electrify the Great Western Main Line from
            London Paddington to Oxford, Bristol and            261   Crossrail will facilitate easier, faster and for the
            Swansea The Mayor welcomes this project and is            first time, direct journeys by public transport
            committed to working with the DfT to maximise             from Heathrow to Canary Wharf, as well as
            the benefits to London, including the potential           improved links to London’s other central
            to extend Crossrail westwards to Reading The              business areas, helping to improve London’s
            Mayor also remains committed to seeing other              international links Crossrail is the only transport
            rail electrification proposals for London taken           project that can deliver the capacity needed to
            forward, such as Gospel Oak to Barking (which             support more jobs in central London and the
            will also contribute to improving air quality)            Isle of Dogs, improve the east-west employment
                                                                      corridor and support development of new
                                                                      employment areas, thereby providing additional

      Chapter five – Transport proposals
113




 Figure 29: Layout of the expanded Tottenham Court Road station




                                                                                                                         Chapter five
      jobs in areas including the Thames Gateway               additional 5 8 million passenger kilometres
      Without Crossrail, London would have been                are added to peak capacity and Crossrail will
      prevented from continuing the development                deliver significant crowding relief on the Tube
      of its second business centre at Canary Wharf,           (including the Central, Piccadilly, Metropolitan,
      which will allow this area to maximise its               Hammersmith & City, Circle and Jubilee lines)
      contribution to the wider UK economy                     and the DLR

262   Crossrail provides the largest single increase     263   As a project of national significance, Crossrail
      in public transport capacity exactly where               will bring transport improvements that will be
      it is most needed It will add 10 per cent to             felt across the country The scheme will be a
      the overall capacity of London’s rail network            catalyst for safeguarding a national economy
      through the provision of 24 high-capacity,               inextricably linked with that of London (See
      10-coach trains an hour in each direction in the         spotlight on the wider economic benefits
      central section during peak periods According            of Crossrail) The provision of high quality
      to forecasting work undertaken by TfL, an                information to keep people informed about the

                                                                                   Chapter five – Transport proposals
114     Mayor’s Transport Strategy – Public Draft




        Spotlight on: The wider economic benefits of Crossrail

        Crossrail will deliver significant benefits to the national economy, the wider southeast region as
        well as to London In addition to the wide ranging transport benefits, such as reduced crowding,
        additional capacity, new direct links across London and reduced journey times, Crossrail also delivers
        a broad range of direct economic benefits Crossrail supports a development potential of more
        than 260,000 jobs and 70,000 people within the key Opportunity Areas alone (Isle of Dogs,
        City fringe, Lower Lea Valley, Paddington) and is expected to generate up to 30,000 extra jobs –
        through productivity improvements in central London by 2027

        The Crossrail project will employ up to 14,000 people at the peak of construction during 2013-2015,
        and it will contribute to an ongoing pool of skilled workers through the new tunnelling academies
        being established by the Mayor In the longer-term, Crossrail will generate an estimated 1,000 jobs
        when fully operational Crossrail will also require the services of regionally-based manufacturers and
        other suppliers

        Crossrail will serve significant new residential areas, for example, parts of the Thames Gateway
        and beyond in the South East region, and employment accessibility will be significantly enhanced,
        bringing an additional 1 5 million more people across London within an hour’s travel of the West End,
        City and Docklands However, it is not just central London and Docklands economies which benefit
        from Crossrail, Outer London gains considerable benefits too, as illustrated in the following table
        Crossrail also links key Outer London metropolitan town centres, such as Romford, Ilford and Ealing,
        delivering further regeneration benefits




      Chapter five – Transport proposals
115




Figure 30: Crossrail route connections and regional maps




  construction programme, especially to minimise                                                                    Chapter five

  inconvenience to users of other transport                Proposal 5:
  services, local residents and businesses, will be        The Mayor, through TfL, and working with
  a high priority for Crossrail Overall the benefits       the DfT, Network Rail, train operating
  of Crossrail are estimated to be worth at least          companies, freight operating companies,
  £36bn in current prices to the national GDP              boroughs and other transport stakeholders
  over the next 60 years                                   will seek to ensure that Crossrail is delivered
                                                           by 2017, and that it is fully integrated
                                                           with the rest of London’s public transport
                                                           system; that the impacts of construction on
                                                           residents and businesses are minimised as
                                                           far as possible; and that the future benefits
                                                           Crossrail brings are monitored to ensure the
                                                           rail link achieves its objectives

                                                                              Chapter five – Transport proposals
116     Mayor’s Transport Strategy – Public Draft




      265   London is the centre of the Greater South East            and approval given to Network Rail’s Delivery
            region of England, the fastest developing area            Plan to implement HLOS. As such, HLOS is
            of the country, with a number of nationally               now a committed programme of National Rail
            designated Growth Areas. Continued economic               funding from Government to 2014. The process
            growth is mutually beneficial – much of                   is planned to be repeated for control period
            London’s workforce live beyond the GLA area.              five, from 2014 to 2019.
            It is therefore important to look across regional
            boundaries. Future extensions of Crossrail, to      268   The improvements to London’s rail network
            the east and west, could help reduce congestion           to be achieved by 2014 through HLOS,
            and improve connectivity and, together with               forms a key element of the transport strategy
            longer trains, ensure maximum benefit is                  and it is essential it is delivered as planned.
            derived from the Crossrail infrastructure.                The improvements are shown in Figure 31
                                                                       and include:
             Proposal 6                                               •	 Improvements to capacity on each of
             The Mayor, through TfL, and working with                    London’s main radial rail corridors, including
             the DfT, Network Rail, train operating                      the Thameslink programme, and 900 new
             companies and other stakeholders, will                      carriages by 2014 (Thameslink by 2015)
             consider future extensions of Crossrail that             •	 Improved reliability
             reduce congestion and improve connectivity
                                                                      •	 Acceptance of Oyster at all National Rail
             on London commuter routes.
                                                                         stations in London in early 2010
      5.2.4 London–wide rail links                                    •	 Improving access at stations through
      and services                                                       the Access for All obstacle-free stations
                                                                         programme. Approximately 50 per cent of
      High Level Output Specification investment                         stations in the first phase are located in
      in rail capacity                                                   London or the South East

      267   In July 2007, the Government presented                    •	 Enhancements to the freight gauge
            the HLOS detailing the development of                        and route capacity on the Felixstowe to
            the National Rail network to 2014 (control                   Nuneaton line (providing a direct route
            period four). The HLOS was accompanied by                    avoiding London for freight trains, which
            a Statement of Funds Available (SoFA), which                 releases capacity for more passenger trains
            detailed proposals for funding arrangements for              in London)
            the railways in the same time period to deliver           •	 Gauge enhancements to the Gospel Oak-
            the proposals put forward in the HLOS. The                   Barking line, which will provide a route for
            SoFA has now been reviewed by the Office of                  rail freight services from the east to the
            Rail Regulation, agreed with the Government                  north of London


      Chapter five – Transport proposals
117




Spotlight on: Thameslink

The Thameslink Programme is a £5 5bn project to deliver a high capacity, north-south rail spine
through central London that complements the east-west Crossrail route When completed in 2015,
Thameslink will provide greater capacity, higher frequencies, new services and improved access to
central London from a range of destinations within London and across southeast England

Major benefits to London from the works to expand the capacity and operating network that will use
Thameslink, include a capacity increase in the core section between Farringdon and Blackfriars of 127
per cent by 2015, compared to current levels Large-scale works include the rebuilding of Blackfriars
station, which will become the first station to span the Thames, providing direct access to both the
north and south banks; Farringdon, will have 12-car platforms and become a major interchange
between Thameslink and Crossrail; and London Bridge, will be significantly rebuilt to provide a major
increase in capacity and better facilities for passengers A new station will also be provided at Brent
Cross/Cricklewood as part of the comprehensive redevelopment of this area




                                                                                                                 Chapter five




                                                                           Chapter five – Transport proposals
118     Mayor’s Transport Strategy – Public Draft




        Figure 31: Committed enhancements to London’s rail network
           Chiltern Railways                            Thameslink                               Southwest
           • Frequency improvements                     • 12-car maximum capability              • 10-car Windsor lines and inner
                                                        • 24 trains per hour through core          suburban capability


           West Coast Main Line                         London, Tilbury and Southend             South central London
           • Trains lengthened and frequency            • 12-car capability on all routes        • 10-car inner capability
             increased


           Great Western Main Line                      West Anglia                              Southeast London
           • Train lengthening                          • 12-car capability Stansted and         • 12-car inner suburban trains
           • New Crossrail services                       Cambridge


                                                                                                 Great Eastern Main Line
                                                                                                 • High-capacity new trains
                                                                                                 • Additional services
                                                                                                 • New Crossrail service




                                                                                Wood Green

                                                  Harrow                                                        Romford
                                                                                                 Ilford
                                Uxbridge

                                              Ealing
                                                   Shepherd’s Bush


                                           Hounslow


                                                           Kingston
                                                                                             Bromley

                                                                                  Croydon
                                                                      Sutton




          Key
             Opportunity Area
             Outer London
             Inner London
             Central Activities Zone



      Chapter five – Transport proposals
119




                                                                               Further rail investment beyond the
   Proposal 7                                                                  current programme
   The Mayor, through TfL, will seek to
   ensure that Network Rail and the train                                      270   Despite the significant investment in the
   operating companies deliver the committed                                         National Rail network being delivered though
   improvements to the rail network and                                              the TfL Business Plan and HLOS, congestion
   services in London as set out by the DfT’s                                        will still be a significant issue on some radial
   High Level Output Specification for the                                           rail corridors (Figure 32) Additional schemes
   period 2009-2014                                                                  and interventions will therefore be required
                                                                                     to address specific capacity and connectivity
                                                                                     problems in the longer-term As most of these
                                                                                     will need to be delivered by Network Rail




                                                                                                                                                       Chapter five
Figure 32:         National Rail and Tube ‘stress’ on radial corridors into central London


   2006                J       K                   2017                J       K                     2031                J       K
               I                       L                       I                         L                       I                       L
       H                                   M           H                                     M           H                                   M
   G                   Central                 N   G                   Central                   N   G                   Central                 N
                       London                                          London                                            London
    F                                          O    F                                            O    F                                          O
           E                               A               E                                 A               E                               A
                   D       C       B                               D       C         B                               D       C       B

    Severely ‘stressed’ corridor:                  Highly ‘stressed’ corridor:                       Moderately ‘stressed’ corridor:
    On average residents in the                    On average residents in the                       On average residents in the
    corridor experience severe                     corridor experience high                          corridor experience moderate
    levels of crowding on rail                     levels of crowding on rail                        levels of crowding on rail
    public transport on their way                  public transport on their way                     public transport on their way
    to central London during AM                    to central London during AM                       to central London during AM
    peak for some part or all of                   peak for some part or all of                      peak for some part or all of
    their journey                                  their journey                                     their journey

    Note: Corridor letters correspond to corridors in Figure 8




                                                                                                                 Chapter five – Transport proposals
120     Mayor’s Transport Strategy – Public Draft




       Figure 33:          Further capacity needed on radial rail routes to central London




                      Chiltern, London Midland and        Thameslink                Great Northern capacity            West Anglia lines
                      Thameslink capacity enhancement                               enhancement                        four-tracking, serving
                      (serving Luton airport)                                                                          Stansted airport


                                                                                                                       Chelsea Hackney line
                                                                                                                       (Crossrail 2)

                      Croxley link
                                                                                                                       Great Eastern capacity
                      High-speed rail                                                                                  enhancements




                                                                                                                       DLR extensions and
                                                                                                                       capacity enhancements
                      Crossrail extensions

                                                                                                                       Longer trains on London,
                                                                                                                       Tilbury, Southend lines
                      Airtrack and other orbital
                      links to Heathrow
                                                                   Northern line Upgrade
                                                                   2 and extension to
                                                                   Nine Elms                                           Thames crossings

                      Chelsea Hackney                                                                                  Crossrail extensions
                      line (Crossrail 2)

                                                                                                                       Rail/Tube improved
                                                                                                                       capacity and connectivity
                                                   Longer trains on south               Tramlink                       to southeast London,
                      Longer trains on             central lines (serving               enhancements                   including potential
                      southwest lines              Gatwick airport)                     and extensions                 Bakerloo line extension




                                                        Bus services will continue          Greater use of the River             Smoothing tra c flow
         Key                                            to support economic growth          Thames
                                                        and regeneration
            Opportunity Area
            Rail termini
                                                        London terminals capacity           Upgrade of all National Rail         Cycle and walking
            Route improvements                          upgrades and strategic              stations and services to London      improvements
                                                        interchanges                        Overground standards and
            London-wide improvements                                                        integration with Oyster



      Chapter five – Transport proposals
121




      and the train operating companies through                important new line Forecast demand shows
      the franchising system, it is essential that TfL         that crowding and congestion remains a
      works closely with the DfT to influence the              significant issue in this corridor (Figure 32)
      future HLOS and franchising process in order             even with new investments such as Crossrail
      to deliver the improvements that are vital to            and Thameslink in place This new line is
      support London’s growth                                  needed in the longer-term to reduce crowding
                                                               on existing routes, but also to provide the
271   A number of options to enhance the capacity              capacity that is required to meet London’s
      provision on radial rail routes to central               growth and provide connections to the National
      London in order to address the levels of                 Rail network, including dispersal of people
      crowding and congestion after the measures               across London from the main line termini
      in the TfL Business Plan and HLOS have been
      implemented, are illustrated in Figure 33 The      274   It is important that the route of the Chelsea
      effectiveness of these schemes at reducing rail          Hackney line is reviewed to ensure it is providing
      and Tube crowding, when combined with other              the maximum benefits and value for money
      capacity improvements on the Underground




                                                                                                                         Chapter five
      network, are shown in Figure 34                           Proposal 9
                                                                The Mayor supports new rail capacity in
       Proposal 8                                               the broad southwest to northeast corridor,
       The Mayor, through TfL, and working with the             for example, new lines or services using the
       DfT, Network Rail, train operating companies,            Chelsea Hackney line safeguarded alignment
       boroughs and other transport stakeholders,               TfL will undertake a review of the route to
       will seek further rail capacity across London’s          ensure it is providing the maximum benefits
       rail network, beyond those schemes                       and value for money
       already committed The highest priorities
       are to further increase capacity on London        National Rail reliability
       Overground, southwest routes, the West
       Anglia Main Line and at congested stations        276   National Rail punctuality has improved
                                                               considerably since 2002/03 as a result of
Chelsea Hackney line                                           the improved maintenance of infrastructure
                                                               by Network Rail, investment in new trains
273   The Chelsea Hackney line (or Crossrail 2)                and signalling, franchise reorganisation
      provides significant new rail capacity on the            to better reflect rail network geography,
      northeast to southwest corridor and major                franchise performance incentives and improved
      congestion relief to existing rail and Tube              timetabling However, despite these substantial
      lines The route of the line is safeguarded               achievements, there is still room for further
      by Government and it is essential that this              improvement (see Figure 35)
      safeguarding remains in place to protect this

                                                                                   Chapter five – Transport proposals
122     Mayor’s Transport Strategy – Public Draft




       Figure 34: The potential benefits from implementing measures beyond those in the TfL Business Plan
                  and HLOS to reduce crowding on London’s rail and Tube network




                                                  Increased crowding
                                                  in 2031 as a result of
                                                  growth in employment
                                                  and population                                  Proportion crowded in 2031 without any new investment would be 67%
                                             70
        Proportion of passenger kilometres
         crowded (weekday morning peak)




                                             60                                                                                    Proportion crowded in 2006 was 55%

                                             50
                                                                                                                              Proportion crowded in 2031 would be 50%
                                             40

                                             30
                                                                                                 Proportion crowded in 2031 with the full strategy package would be 32%1
                                             20                                                                                                                             Total impact
                                                                                                                                                                            of the
                                                                                                                                                                            strategy
                                             10                                                                                                                             on rail
                                                                                                                                                                            crowding2
                                              0
                                                                      Crossrail, Tube     Further             Chelsea             Further DLR         Other investment
         1. It would not be good value                                line upgrades,      investment on       Hackney line*       extensions,         including Airtrack,
         for money or of benefit to the                                investment on the   the National Rail                       Bakerloo line       Crossrail
         economy to attempt to                                        National Rail       network,                                north and south     extensions, and
         eliminate all crowding                                       network including   extensions to                           extensions and      other service
         2. ‘Rail crowding’ includes                                  Thameslink and      the DLR and                             Croxley link*       improvments*
         crowding on the Tube, DLR,                                   other funded        Northern line and
         National Rail and Tramlink                                   measures            Underground
                                                                                          upgrades


                                                                     Funded measures                                 Unfunded measures




         * Note: These schemes improve accessibility (connectivity more so than crowding)


      Chapter five – Transport proposals
123




Figure 35: National Rail punctuality (London and southeast operators total, including peak services)




                                 National Rail punctuality (London and southeast operators total, including peak services)
                            95
minutes of scheduled time
% of arrivals within five




                            90

                            85

                            80

                            75

                            70
                                    2002/03      2003/04       2004/05       2005/06       2006/07      2007/08        2008/09




                                                                                                                                            Chapter five
                Proposal 10                                                  Station capacity enhancements

                The Mayor, through TfL, will seek to ensure                  278   Many National Rail stations are congested,
                that the DfT, Network Rail and the train                           especially at peak times and enhancements
                operating companies achieve the HLOS                               to station capacity are required to improve
                ‘public performance measure’ for reliability,                      customer service and to enable London’s
                as well as an overall reduction in significant                     growth in rail demand to be accommodated
                lateness and cancellations for London and                          Schemes will be taken forward where they are
                southeast services                                                 shown to be value for money and affordable




                                                                                                      Chapter five – Transport proposals
124     Mayor’s Transport Strategy – Public Draft




        Spotlight on: Central London rail termini

        Increasing population and employment, plus the additional capacity on much of London’s rail
        network through the current rail investment programme, means rail arrivals into central London
        termini are forecast to increase by up to 25 per cent by 2026 This will result in increased strain on
        National Rail termini, and on the transport networks and services within central London

        Limited concourse space means that station crowding is a key issue High levels of connectivity and
        very large volumes of interchange passengers add extra complexities to this crowding and movement
        The main termini and interchanges, which are already at, or near capacity, during peak periods, need
        to be reviewed to ensure they are safe and efficient into the future

        Congestion relief schemes such as those at King’s Cross/St Pancras and the proposed scheme at
        Victoria can go a long way to relieving the problems However, these schemes are expensive and
        disruptive, take time to deliver and ideally need to be linked with increases in onward dispersal
        capacity Encouraging more onward trips by walking and cycling is a quick and cost-effective way to
        free-up capacity on the Underground and buses, and ensure that limited space on these services is
        used more effectively Better streets, better information provision and better facilities for cyclists, such
        as bike parking will help The strategic interchange concept, improving and encouraging interchange at
        stations away from the central London termini, would also help onward dispersal (see proposal 46)




      Chapter five – Transport proposals
125




                                                                seven-days-a-week, without disruptions due
       Proposal 11                                              to engineering works, except where absolutely
       The Mayor, through TfL, and working with                 necessary The Mayor also believes that train
       the DfT, Network Rail, train operating                   operating companies should provide sufficient
       companies and boroughs, will seek to deliver             capacity in terms of train lengths, in order
       capacity enhancements at some of London’s                to sufficiently meet demand at all times
       most congested stations The highest                      This includes weekends when acute crowding
       priorities include:                                      can occur due to shorter train formations
       a) Central London termini station
                                                          281   The Mayor will promote a common service
          congestion relief and onward distribution
                                                                standard across the London rail network and
          enhancements (the potential of all onward
                                                                believes that Overground service standards
          modes will be considered)
                                                                provide an evidenced template to follow which
       b) Clapham Junction station capacity                     has been adopted almost in full for the recent
          enhancement (new improved links                       South Central refranchise with more than 40
          between platforms, additional entrances               stations and extensive patterns of routes This




                                                                                                                          Chapter five
          and more ticketing facilities)                        has specified minimum standards including:
       c) Improved capacity at National Rail stations           •	 Staffing over the traffic day
          with severe congestion, including Finsbury
                                                                •	 Oyster acceptance and retailing via ticket
          Park, Bromley South, Wimbledon, Vauxhall
                                                                   machines within Travelcard Zones 1 to 6
          and Barking
                                                                •	 Station facilities such as seating
       d) Improved capacity at National Rail stations
                                                                   and shelters
          with moderate congestion, including
          Willesden Junction, Balham, West Croydon,             •	 Multi-modal customer information at
          Norwood Junction and Surbiton                            stations, through posters and electronic
                                                                   means, on-system and off, scheduled
Improving customer standards across the                            and realtime
National Rail network in London                                 •	 Security features such as lighting, CCTV and
                                                                   Help points
280   Despite improvements in National Rail services
      being delivered by Network Rail, TfL and others           •	 Graffiti removal, litter removal and cleaning
      over the next 10 years, rail passengers still do          •	 Train frequency of at least four trains per
      not always benefit from the level of service or              hour on each route where the infrastructure
      frequencies that those who travel on the Tube                allows, up to 23:00
      enjoy, particularly outside peak hours The Mayor
      is keen that London benefits from a full ‘seven-          •	 First and last trains broadly aligned with the
      day railway’, supporting the Capital’s diverse               Underground’s operating hours
      economy with regular, frequent services operating

                                                                                    Chapter five – Transport proposals
126     Mayor’s Transport Strategy – Public Draft




            •	 Cycle parking to basic standard and          5.2.5 Local and orbital rail links
               monitoring regime at every station within    and services
               two years
                                                            London Overground
      282   This will require the influencing of the
            franchise process, as well as reducing          285   Work on London Overground includes
            disruption to passenger journeys at weekends,         reinstatement of disused National Rail routes
            acknowledging that sometimes, the                     to link the East London and North London lines
            undertaking of maintenance works at these             at Dalston, modifying existing infrastructure
            times will remain inevitable Network Rail is          to reach West Croydon and Crystal Palace (the
            already looking at how some engineering works         East London line extension) and delivering a
            could be undertaken through shorter overnight         rolling stock maintenance and control centre
            ‘possessions’ instead, possibly through               at New Cross Gate The North London Railway,
            undertaking more preparatory work off-site            also part of London Overground, is to be
                                                                  increased in capacity by up to 50 per cent
                                                                  and will also provide more frequent services
             Proposal 12
                                                                  A further phase now approved will see the
             The Mayor, through TfL, and working with             completion of the Inner London Overground
             Network Rail, train operating companies and          orbital rail network between Surrey Quays
             other transport stakeholders will encourage          and Clapham Junction Completion of the
             the achievement of a ‘seven day railway’             London Overground network enhancements
             by better planning and management of                 in 2012 will provide an orbital rail network in
             necessary engineering and maintenance                Inner London that will allow, either directly or
             work on the railway                                  with a single change of trains, journeys such
                                                                  as Clapham Junction to Dalston and Crystal
                                                                  Palace to West Hampstead This network of
             Proposal 13
                                                                  Overground rail services is shown in Figure 36
             The Mayor, through TfL, and working with             The DLR extension to Stratford International
             Network Rail, train operating companies              in summer 2010 will also improve orbital
             and other transport stakeholders will                frequency and capacity in east London
             encourage the provision of rail services in
             London that meet common service standards      286   There are, however, significant further
             including improved ambience, amenities               opportunities to improve orbital travel, such
             and wayfinding at all stations, and staff            as by providing or improving interchange
             availability at each station It is intended          opportunities where radial and orbital lines
             these improvements will be rolled out as             cross Forecasting shows that rapid demand
             franchises are renewed                               growth can be expected over the next
                                                                  few years, which means that parts of the


      Chapter five – Transport proposals
127




Figure 36: London Overground route map (2012)




                                                                                                                                            Chapter five
       Step-free access from the platform to the street
       (existing and planned)




 London Overground delivers:

 •		 ast	London	line	reopening	in	
   E                                                      •		 	high	capacity	orbital	railway	for	
                                                            A
   2010, with extensions to                                 London for the first time
   Crystal Palace and West Croydon                        •		 ervices	provide	metro	
                                                            S
   by 2011                                                  frequencies of four trains per hour
 •		 xtension	to	Clapham	Junction	
   E                                                      •		 ew	longer	trains	and	enhanced	
                                                            N
   opens 2012                                               stations


  Overground could justify investment in longer
  five or six-car trains TfL will also investigate                                  Proposal 14
  where there may be additional routes that                                         The Mayor, through TfL, working with the
  warrant extensions to the Overground,                                             DfT and Network Rail, will investigate the
  if found feasible                                                                 feasibility of providing extra capacity to
                                                                                    assist orbital movement on the Overground
                                                                                    network and will review potential benefits of
                                                                                    extensions to the network of services

                                                                                                      Chapter five – Transport proposals
128     Mayor’s Transport Strategy – Public Draft




      Docklands Light Railway
                                                                       Proposal 15
      288   Since opening in 1987, the DLR network has                 The Mayor, through TfL, will investigate the
            grown to become a vital part of London’s                   feasibility of further capacity and network
            public transport system supporting growth                  expansion of the DLR including an extension
            and regeneration in the Thames Gateway (see                to Dagenham Dock, as part of the housing
            Docklands case study) Improvements to the                  proposals for Barking Riverside, and further
            DLR include a network extension to Stratford               network extensions, including options south
            International and delivery of 55 new carriages             of Lewisham, west of Bank and north of
            to enable three-car operation on most of                   Stratford International
            the system by 2010 (with further station
            and infrastructure enhancements to follow)          Tramlink
            Delivering new rolling stock to maximise the
            benefits of full three-car operation across the     291   Tramlink has been a great success since
            network, double tracking between Bow Church               opening in 2000, providing important
            and Stratford, installing a new signalling system         orbital links into Croydon and connections to
            and renewing and replacing the existing rolling           neighbouring Outer London town centres –
            stock will all contribute to ensuring that the            and encouraging a shift from car to public
            DLR is fully able to support continued growth             transport Improvements to Tramlink as part of
            and regeneration in the Thames Gateway area               a £54m investment in maintenance, renewals,
                                                                      upgrades and capacity enhancement, are taking
      289   An extension of the DLR to Dagenham Dock                  place between now and 2015
            has been identified as a key component of
            the Government’s housing plans for Barking
            Riverside There is also further scope to extend
            the DLR network in the longer-term to provide
            better links to Stratford, improved orbital links
            and connectivity in the Thames Gateway, and
            better integration with the central London
            transport system, for example, through a
            westwards extension from Bank to Victoria




      Chapter five – Transport proposals
129




292   Beyond these initial improvements,                5.3 London Underground
      consideration will be given to looking at
      further extensions of Tramlink, with a strong     5.3.1 Introduction
      focus on a potential north-south axis, in
      order to accommodate Croydon’s future             294   Over the last decade, the Underground has
      growth needs, and potentially to improve                experienced unprecedented growth in demand,
      east-west links to neighbouring Outer London            with more than a billion passenger journeys a
      town centres to support improved orbital                year now made by Tube LU carries as many
      connectivity Both short extensions to provide           passengers as the entire National Rail network
      better access from key centres to Tramlink,             with up to four million journeys made each
      and longer extensions opening up completely             day, on 11 lines serving 270 stations As a
      new routes are being considered                         result, the Underground is now providing a
                                                              higher volume of service than ever before This
                                                              customer driven approach has been recognised
       Proposal 16
                                                              by LU’s customers, with LU achieving a
       The Mayor, through TfL, and working with               record 79 out of 100 in terms of customer




                                                                                                                          Chapter five
       London boroughs and other transport                    satisfaction
       stakeholders, will investigate the feasibility
       of providing extra capacity on the Tramlink      295   This performance has been made possible by
       network and will review potential benefits of          understanding the needs of customers, and
       extensions to the system                               implementing a strategy based upon this,
                                                              namely, to combine a reliable train service
                                                              with the highest standards of customer
                                                              care Maintaining the focus on this strategy,
                                                              requires the Tube to renew its bedrock assets
                                                              (track, civils, trains, signals, stations), to allow
                                                              enhanced train service capacity to keep up
                                                              with rising levels of demand The strategy
                                                              also provides focus upon other key aspects
                                                              of the service – creating a welcoming and
                                                              secure environment, offering personal service
                                                              to customers, providing accurate and timely
                                                              service information, and creating ease of
                                                              access This will deliver the world-class service
                                                              Londoners rightly deserve




                                                                                    Chapter five – Transport proposals
130     Mayor’s Transport Strategy – Public Draft




      296   To support the growth of London, LU has             298   A key function of this renewal are the line
            embarked on its largest investment programme              upgrades which are the critical foundation for
            for 70 years, focusing on improving reliability,          the transformation of the Tube Without them
            delivering faster journey times, along with               LU would not be able to provide the capacity
            increasing capacity across the network                    required to support the Capital’s economy
                                                                      and meet the demands of the future or even
      5.3.2 Renewal and repair of                                     maintain the service that is currently delivered
      the network                                                     Work to upgrade each line is therefore the
                                                                      cornerstone of the Underground’s plan By the
      297   The Tube is the oldest metro system in the                end of the current programme, the Tube will
            world, with some infrastructure dating back to            have delivered up to an additional 30 per cent
            the 1860s After decades of under-investment,              capacity – including new trains and signalling
            the network is now undergoing major renewal,              systems, allowing the Underground to run more
            rebuilding and refurbishment, a transformation of         trains, providing quicker and more comfortable
            the Tube The key elements of the programme are:           journeys Beyond this, the Tube will require
            •	 Rolling stock – replace the majority of train          investment to ensure that its asset condition
               fleets, which if not renewed would have an             remains in a state of good repair and does
               average age of 50 years in 2031, 15 years              not fall to the levels seen through decades of
               beyond their design life This will increase            under-investment in the network
               fleet reliability and capacity
                                                                299   While this transformation takes place, the
            •	 Signalling – replace assets (more than 40
                                                                      network faces the tremendous challenge of
               years old in many cases) to reduce service
                                                                      keeping London moving on a daily basis while
               delays and increase network capacity
                                                                      simultaneously rebuilding the system This
            •	 Track – reduce the backlog of investment               massive task cannot be achieved overnight –
               to reduce safety risks, and remove speed               and not without some disruption to services
               restrictions brought in to manage safety               In order to facilitate these works while carrying
               risks to increase capacity                             out regular essential maintenance, weekend
            •	 Civil structures – renew assets such as                closures have become more frequent The high
               bridges, viaducts, embankments and                     profile campaign advising customers to ‘check
               drainage systems to maintain a safe service,           before they travel’ has proven highly successful
               reduce the risks of flooding, and the service          and will continue, employing many Travel Tools
               effects of speed and weight restrictions               to help customers plan their journeys

            •	 Stations – modernise stations by replacing
               safety and service critical systems such as
               fire systems, public address, CCTV, and lifts
               and escalators

      Chapter five – Transport proposals
131




Spotlight on: Sub-surface line upgrade

The Sub-Surface Railway (SSR) comprising the Circle, District, Hammersmith & City and Metropolitan
lines, covers more than 300km of track and represents around 40 per cent of the Tube network It is
the part of the Tube in greatest need of renewal The upgrade will be delivered progressively over the
next decade and will provide the greatest capacity improvements across the entire network, helping
to reduce congestion and accommodate predicted growth

In December 2009, a new service pattern will be delivered on the Circle line, almost doubling the
frequency of trains on the Hammersmith branch It will also improve the reliability of the Circle line,
with knock-on benefits for reliability across the whole of the SSR The new service pattern will be
followed by the introduction of a new signalling system to allow higher train service frequencies

In July 2009, LU issued an invitation to tender for the resignalling of the sub-surface lines This
contract is the single Tube element of the Investment Programme




                                                                                                                   Chapter five
One hundred and ninety nine new, larger trains are being built and will enter service from 2010
They will feature energy-saving regenerative breaking, walk-through carriages, better accessibility,
improved customer information (audio and visual) and enhanced security The Circle and
Hammersmith & City line trains will also have an additional carriage Most significantly, the new trains
will be the first to be air-conditioned on the Tube network




                                                                             Chapter five – Transport proposals
132     Mayor’s Transport Strategy – Public Draft




      300   By 2012, this programme will deliver an upgrade             programme has, and will continue to deliver, key
            of the Jubilee, Victoria and Northern lines By              system improvements (CCTV, public address,
            2020, upgrades will have been completed on                  communications equipment and fire systems),
            the Piccadilly line and the sub-surface railway             as well as improving customer service features
            A key aspect of this will be a new signalling               These include, passenger Help points, new
            system and the introduction of new, air-                    electronic information displays in ticket halls and
            conditioned trains, which were unveiled in 2008             on platforms, improved seating and lighting, as
            The trains, representing 40 per cent of the                 well as improvement to accessibility features,
            LU total fleet, will serve the Metropolitan line            such as tactile strips and colour-contrasted
            starting from 2010 and will then be rolled out              handrails for visually impaired people
            progressively across the Circle, Hammersmith &
            City and District lines The Bakerloo line upgrade     303   TfL is committed to improving accessibility
            is expected to be completed with new trains in              from street to platform on the Tube Over time,
            place by 2020 The replacement of the Central                TfL will seek to increase the accessibility of the
            line fleet will follow, delivered into service from         network, building upon the foundation of step-
            2020 Considerable benefits and efficiencies can             free stations already in place
            be achieved by specifying lighter, more energy
            efficient and higher capacity trains for both lines          Proposal 18
                                                                         The Mayor, through TfL, will continue to
             Proposal 17                                                 deliver an ongoing programme of Tube
             The Mayor, through TfL, will seek to deliver                station refurbishments and asset stabilisation
             upgrades to all Tube lines in a phased                      to ensure stations are operable and deliver
             programme to provide a significant increase                 customer service requirements, as well as
             in network capacity This will involve a                     continuing to improve station accessibility
             combination of new rolling stock and/                       over the life of the strategy
             or signalling systems and other asset
             replacement As part of this, continued               5.3.4 Station congestion relief
             investment to bring the network to a good
             state of repair and maintain it at that level        305   To relieve congestion experienced by Tube
             will be supported                                          customers at key locations across the network,
                                                                        and to enable quicker journeys, some stations
      5.3.3 Station refurbishments                                      require more extensive improvements to
                                                                        ensure safe and efficient station operations
      and accessibility
                                                                        while also enhancing passengers’ journey
      302   Between 2003 and 2009, 124 stations have                    experience The delivery of capacity
            been refurbished and this programme will                    enhancements to strategic Underground
            continue to be rolled out across the network                stations and interchanges are critical to the
            subject to availability of funding This                     functioning of the Tube as an integrated

      Chapter five – Transport proposals
133




      network to assist existing passenger flow, and
                                                              b) Schemes at further strategic Tube
      also cater for future increases in demand
                                                                 interchanges that are critical to London’s
                                                                 transport system (eg Vauxhall, Finsbury
306   The current station congestion relief
                                                                 Park, Highbury & Islington, Holborn,
      programme contains the key central London
                                                                 Camden Town, Oxford Circus, Edgware
      interchanges of Victoria, Tottenham Court
                                                                 Road and Northern line City branch,
      Road, Bond Street, Paddington (Hammersmith
                                                                 in particular Old Street and Moorgate)
      & City), and Bank These stations are essential
      to maintain access to the Underground                   c) Major strategic multi-modal/National
      and to optimise the benefits of investment                 Rail interchanges on to the Underground
      from the line upgrades, Crossrail and other                network to disperse onward demand arising
      developments They will also greatly improve                from National Rail proposals (HLOS2 and
      central London step-free access                            HS2 proposals), eg London Bridge, Euston,
                                                                 Liverpool Street, Paddington, Elephant &
307   Further station improvements will address the              Castle and Waterloo
      next level of priority schemes where strategic




                                                                                                                      Chapter five
      access to, or interchange across, the network    5.3.5 Cooling the Tube
      will be restricted without further capacity
      enhancements, for example: Vauxhall, Finsbury    309   High tunnel temperatures during the summer
      Park and Highbury & Islington                          months are one of the biggest challenges
                                                             facing LU, particularly for the deep tunnelled
                                                             sections of the Underground, such as the
       Proposal 19
                                                             Victoria line These are essentially closed
       The Mayor, through TfL, and working with              systems where the major proportion of the
       the London boroughs and other transport               energy that enters (for example, train motors)
       stakeholders, will develop and implement              is released as heat, which in turn raises
       a prioritised programme to deliver station            temperatures in the tunnels and on the trains
       capacity and accessibility enhancements               As a result of increased train service capacity
       at London’s most congested Underground                (primarily through higher train frequencies)
       stations, including:                                  and reduced journey times (primarily through
       a) Congestion relief schemes to complement            quicker acceleration and faster maximum
          Tube line upgrades and/or integrate                speeds), electricity usage on the Underground
          with Crossrail at the key central London           is anticipated to increase by 2020, resulting
          interchanges of Victoria, Tottenham                in more heat being released in the tunnels
          Court Road, Bond Street, Paddington                This will be exacerbated by increasing passenger
          (Hammersmith & City) and Bank                      numbers and possible increases in air
                                                             temperature due to climate change Therefore
                                                             maintaining safe temperatures on deep

                                                                                Chapter five – Transport proposals
134     Mayor’s Transport Strategy – Public Draft




            tunnelled sections of the Tube will present an            nearly eight out of 10 The success of the Tube is
            ever increasing challenge in the future Already           also recognised elsewhere, with the Underground
            the Tube has implemented a programme to                   recently named Best Metro in Europe at the
            tackle heat on the network, and this will                 prestigious Metro Awards in 2009
            continue over the long-term
                                                                313   Customer information and personal service
             Proposal 20                                              from staff will be especially important as
                                                                      the renewal programme, which can disrupt
             The Mayor, through TfL, will implement                   service, is delivered over the next decade
             the following measures in order to cool the              The Underground will continue to invest in
             Underground:                                             customer-focused training including disability
             a) New air-conditioned rolling stock across              awareness training, and in information
                the sub-surface (Metropolitan, Circle,                systems to deliver the right information to
                Hammersmith & City and District) lines,               customers when they want it, when planning
                introduced progressively from 2010                    or undertaking journeys on the network
             b) Improved ventilation shafts and
                                                                314   Customers value the presence of staff especially
                replacements of out of service fans
                                                                      when travelling at night The Underground
                                                                      will continue to staff its stations and invest
      5.3.6 Customer care                                             in systems which enhance the management of
      311   The core renewal programme is essential to                the station, such as CCTV, as well as ensuring
            deliver a safe and reliable service, but LU               the stations are well-lit and visibly managed –
            aspires to the highest standards of customer              clean and graffiti free
            care Customers most value getting from A to
            B as quickly and reliably as possible, but valued   315   There is a rich heritage of art and design on
            almost as much are all the different aspects              the Tube High quality, value for money design
            of service they experience during the journey             will continue to be a feature of the investment
            Customers value personal security, a welcoming            programme Art on the Underground, LU’s
            environment, accurate and timely information,             art programme, continues the Tube’s long
            and when customers need assistance, they want             tradition of working with artists This can
            high quality personal service from staff                  delight customers and improves the travelling
                                                                      environment, as well supporting and
      312   In 2008, for the third year running, the                  celebrating the rich and vibrant art scene
            Underground carried more customers than ever              in London Licensed busking and ‘Poems
            before, in excess of one billion At the same              on the Underground’ bring music and poetry
            time, customer satisfaction with the service also         to the wide-ranging audience of customers
            reached a record high of 79 out of 100, most              on the Tube
            people scored the overall service provided at

      Chapter five – Transport proposals
135




                                                               simplifying and recasting the service patterns
       Proposal 21                                             it will be possible to increase capacity on the
       The Mayor, through TfL, will continue to                Northern line by a further 20 per cent by 2020
       develop and implement measures to deliver               – over and above the capacity delivered by the
       the highest standards of customer care on               original line upgrade in 2012 This will act as
       the Underground, including the high quality             the equivalent of adding a new north-south
       provision of information about engineering              line across London, reducing levels of crowding
       works that affect regular Tube services, and            as well as providing reliability improvements It
       an accessible Tube map showing step-free                will help the Capital to keep pace with growth
       and mostly step-free routes                             in demand, and support London’s future
                                                               economic development
5.3.7 Further improvements and
extensions to the network                                319   In addition, further enhancements to the
                                                               Northern line are possible With private sector
317   Over the lifetime of this strategy, there are            funding, there is the potential to extend the
                                                               Northern line to Battersea in order to support




                                                                                                                         Chapter five
      opportunities for further enhancements and
      extensions to the LU network to improve                  developer-led growth in the Vauxhall/Nine Elms/
      journey times and provide additional capacity            Battersea Opportunity Area, an area identified as
      essential for the continued growth of London             being capable of accommodating at least 15,000
      Any potential schemes will have to be subject            new jobs and 16,000 homes by 2031
      to a thorough value for money and feasibility
      analysis and will have to be considered in light   320   The Bakerloo line has an important role in
      of any future funding constraints                        London’s transport geography, serving the
                                                               strategic northwest-southeast corridor with
318   Beyond the current investment programme,                 its important regeneration zones including
      even with the introduction of Crossrail and              Harlesden, Paddington, Elephant & Castle and
      Thameslink proposals, crowding will remain               inner southeast London The Bakerloo line
      on the LU network The Northern line is the               upgrade, incorporating new train technology,
      busiest metro line in Europe with more than              will boost capacity and reliability on the
      800,000 passengers a day Even with the                   line, while a longer-term Bakerloo southern
      Northern line upgrade and other transport                extension would allow the line to serve inner
      investment, it is forecast that by 2031 there            and outer southeast London, creating a new
      will be severe pressure on London’s north-south          southeast to northwest strategic route through
      routes, particularly through the City, resulting         the Capital, serving areas with poor transport
      in congestion levels very similar to that                accessibility and freeing up National Rail
      experienced today A further upgrade of the               capacity at London Bridge for other service
      line can be achieved by recasting the service            improvements
      through the partial separation of the line By

                                                                                   Chapter five – Transport proposals
136     Mayor’s Transport Strategy – Public Draft




        Spotlight on: Northern line Upgrade 2 (service pattern changes)

        Work has commenced to upgrade the Northern line, with new computerised signalling and a new
        control centre which will reduce journey times by 18 per cent and increase capacity by around 20 per
        cent However, even with the upgrade it is forecast that due to growth in demand, there will still be
        severe pressure on London’s north-south routes, particularly through the City, resulting in crowding
        levels similar to that experienced today A recast of service patterns to partially separate the two
        branches of the line would increase capacity and journey times further, delivering an additional
        33 per cent capacity on the City branch, and a 17 per cent increase on the Charing Cross Branch

        For example, on the Charing Cross branch, during the busiest parts of the morning peak, service
        frequencies could rise from the current 20 trains per hour (tph) to 24 tph following the first upgrade,
        eventually reaching a potential 28 tph following partial separation

        The further upgrade would require more rolling stock alongside the existing fleet, as well as
        additional stabling facilities, power, improved signalling and tunnel cooling

        Once delivered, it will act as the equivalent of adding a new north-south line across London, helping
        the Capital keep pace with growth in demand and supporting economic development




      Chapter five – Transport proposals
137




Spotlight on: Transforming the Tube

Over the last decade, the number of journeys made on the Tube have risen to record levels of
more than one billion journeys a year To support this growth and correct historic under-funding,
LU has embarked on its largest investment programme for 70 years The line upgrades, which will
include new signalling and control systems, as well as the introduction of new trains on some lines,
will focus on improving reliability They will deliver faster journey times and increase capacity by
up to 30 per cent across the network By 2012, this programme will deliver an upgrade of the
Jubilee, Victoria and Northern lines, each providing between 20 and 33 per cent more capacity
per line into central London

By 2020, upgrades will have been completed on the District, Circle, Hammersmith & City and
Metropolitan lines (including air-conditioned trains) increasing capacity across the sub-surface
network, while the Piccadilly line upgrade will provide a 24 per cent increase in line capacity
The Bakerloo line will also be upgraded Other enhancements include: major station improvements at




                                                                                                                  Chapter five
Victoria, Paddington (Hammersmith & City), Tottenham Court Road, Bond Street and Bank; cooling;
power upgrades to cater for expanded services; and accessibility improvements




                                                                            Chapter five – Transport proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals
Mayor Transport Strategy Transport Proposals

Mais conteúdo relacionado

Mais procurados

Analysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnalysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnirban Mahajan
 
L & T Metro Rail Impact Assessment Study - Stage 3
L & T Metro Rail Impact Assessment Study - Stage 3L & T Metro Rail Impact Assessment Study - Stage 3
L & T Metro Rail Impact Assessment Study - Stage 3Ramesh Satyam
 
MRT REPORT TPT 250
MRT REPORT TPT 250MRT REPORT TPT 250
MRT REPORT TPT 250Shadina Shah
 
PPP in Transport - Mumbai Metro One
PPP in Transport - Mumbai Metro OnePPP in Transport - Mumbai Metro One
PPP in Transport - Mumbai Metro Onekopila
 
IRJET- Upcoming Longest Elevated Flyover Carridor of the State of Madhya Prad...
IRJET- Upcoming Longest Elevated Flyover Carridor of the State of Madhya Prad...IRJET- Upcoming Longest Elevated Flyover Carridor of the State of Madhya Prad...
IRJET- Upcoming Longest Elevated Flyover Carridor of the State of Madhya Prad...IRJET Journal
 
DPR Model Template for Rural Roads Upgradation in Andhra Pradesh
DPR Model Template for  Rural Roads Upgradation in Andhra PradeshDPR Model Template for  Rural Roads Upgradation in Andhra Pradesh
DPR Model Template for Rural Roads Upgradation in Andhra PradeshValleru Muni Chandra Naidu
 
Appraising kolkata metro rail project case
Appraising kolkata metro rail project caseAppraising kolkata metro rail project case
Appraising kolkata metro rail project caseRahul Pagaria
 
Hyderabad metro rail reducing the negative impact on city environment - env...
Hyderabad metro rail   reducing the negative impact on city environment - env...Hyderabad metro rail   reducing the negative impact on city environment - env...
Hyderabad metro rail reducing the negative impact on city environment - env...Umamaheswara Rao
 
Parking Annex (London Plan 2008)
Parking Annex (London Plan 2008)Parking Annex (London Plan 2008)
Parking Annex (London Plan 2008)Anthony Eskinazi
 
Impacts of Rail Deregulation on Rail Transport Performance
Impacts of Rail Deregulation on Rail Transport PerformanceImpacts of Rail Deregulation on Rail Transport Performance
Impacts of Rail Deregulation on Rail Transport PerformanceRodrigo Dourado
 
Smart Transportation Case Study by IBM
Smart Transportation Case Study by IBMSmart Transportation Case Study by IBM
Smart Transportation Case Study by IBMIBMTransportation
 
Priorities infrastructure retreat- web
Priorities   infrastructure retreat- webPriorities   infrastructure retreat- web
Priorities infrastructure retreat- webDr Lendy Spires
 
Public Private Partnership in Urban Rail Transit
Public Private Partnership in Urban Rail TransitPublic Private Partnership in Urban Rail Transit
Public Private Partnership in Urban Rail TransitKapil Sinha
 
The Current Transport Policy Environment
The Current Transport Policy Environment The Current Transport Policy Environment
The Current Transport Policy Environment Bakhtiar Zein
 
Footbridge2020 wing woolf
Footbridge2020 wing woolfFootbridge2020 wing woolf
Footbridge2020 wing woolfInterrelated
 

Mais procurados (20)

Uk
UkUk
Uk
 
Analysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land UseAnalysis of Impact of East West Metro Corridor on Land Use
Analysis of Impact of East West Metro Corridor on Land Use
 
URBAN TRANSPORT DEVELOPMENT PLANNING
URBAN TRANSPORT DEVELOPMENT PLANNINGURBAN TRANSPORT DEVELOPMENT PLANNING
URBAN TRANSPORT DEVELOPMENT PLANNING
 
TramsLightRailMelbourne
TramsLightRailMelbourneTramsLightRailMelbourne
TramsLightRailMelbourne
 
L & T Metro Rail Impact Assessment Study - Stage 3
L & T Metro Rail Impact Assessment Study - Stage 3L & T Metro Rail Impact Assessment Study - Stage 3
L & T Metro Rail Impact Assessment Study - Stage 3
 
MRT REPORT TPT 250
MRT REPORT TPT 250MRT REPORT TPT 250
MRT REPORT TPT 250
 
PPP in Transport - Mumbai Metro One
PPP in Transport - Mumbai Metro OnePPP in Transport - Mumbai Metro One
PPP in Transport - Mumbai Metro One
 
IRJET- Upcoming Longest Elevated Flyover Carridor of the State of Madhya Prad...
IRJET- Upcoming Longest Elevated Flyover Carridor of the State of Madhya Prad...IRJET- Upcoming Longest Elevated Flyover Carridor of the State of Madhya Prad...
IRJET- Upcoming Longest Elevated Flyover Carridor of the State of Madhya Prad...
 
DPR Model Template for Rural Roads Upgradation in Andhra Pradesh
DPR Model Template for  Rural Roads Upgradation in Andhra PradeshDPR Model Template for  Rural Roads Upgradation in Andhra Pradesh
DPR Model Template for Rural Roads Upgradation in Andhra Pradesh
 
Appraising kolkata metro rail project case
Appraising kolkata metro rail project caseAppraising kolkata metro rail project case
Appraising kolkata metro rail project case
 
Hyderabad metro rail reducing the negative impact on city environment - env...
Hyderabad metro rail   reducing the negative impact on city environment - env...Hyderabad metro rail   reducing the negative impact on city environment - env...
Hyderabad metro rail reducing the negative impact on city environment - env...
 
Parking Annex (London Plan 2008)
Parking Annex (London Plan 2008)Parking Annex (London Plan 2008)
Parking Annex (London Plan 2008)
 
Slater response to question 2
Slater response to question 2Slater response to question 2
Slater response to question 2
 
Feasibility Report of Hyd Metro
Feasibility Report of Hyd MetroFeasibility Report of Hyd Metro
Feasibility Report of Hyd Metro
 
Impacts of Rail Deregulation on Rail Transport Performance
Impacts of Rail Deregulation on Rail Transport PerformanceImpacts of Rail Deregulation on Rail Transport Performance
Impacts of Rail Deregulation on Rail Transport Performance
 
Smart Transportation Case Study by IBM
Smart Transportation Case Study by IBMSmart Transportation Case Study by IBM
Smart Transportation Case Study by IBM
 
Priorities infrastructure retreat- web
Priorities   infrastructure retreat- webPriorities   infrastructure retreat- web
Priorities infrastructure retreat- web
 
Public Private Partnership in Urban Rail Transit
Public Private Partnership in Urban Rail TransitPublic Private Partnership in Urban Rail Transit
Public Private Partnership in Urban Rail Transit
 
The Current Transport Policy Environment
The Current Transport Policy Environment The Current Transport Policy Environment
The Current Transport Policy Environment
 
Footbridge2020 wing woolf
Footbridge2020 wing woolfFootbridge2020 wing woolf
Footbridge2020 wing woolf
 

Destaque

PT Modeling in S'pore [Terence Ng]
PT Modeling in S'pore [Terence Ng]PT Modeling in S'pore [Terence Ng]
PT Modeling in S'pore [Terence Ng]Terence Ng
 
Consumer Focus/ Passenger focus open rail data
Consumer Focus/ Passenger focus open rail dataConsumer Focus/ Passenger focus open rail data
Consumer Focus/ Passenger focus open rail dataJonathan Raper
 
PUBLIC TRANSPORT SYSTEM PRODUCT DEVELOPMENT AND MARKETING GUIDELINES FOR A SO...
PUBLIC TRANSPORT SYSTEM PRODUCT DEVELOPMENT AND MARKETING GUIDELINES FOR A SO...PUBLIC TRANSPORT SYSTEM PRODUCT DEVELOPMENT AND MARKETING GUIDELINES FOR A SO...
PUBLIC TRANSPORT SYSTEM PRODUCT DEVELOPMENT AND MARKETING GUIDELINES FOR A SO...Friedrich Chitauka
 
A study on passenger’s satisfaction towards railway services in erode junction
A study on passenger’s satisfaction towards railway services in erode junctionA study on passenger’s satisfaction towards railway services in erode junction
A study on passenger’s satisfaction towards railway services in erode junctionIAEME Publication
 
NKEA: Greater KL / Klang Valley - Dato' Ahmad Suhaili Idrus
NKEA: Greater KL / Klang Valley - Dato' Ahmad Suhaili IdrusNKEA: Greater KL / Klang Valley - Dato' Ahmad Suhaili Idrus
NKEA: Greater KL / Klang Valley - Dato' Ahmad Suhaili Idruschinesechamber
 
What is Universal Design
What is Universal DesignWhat is Universal Design
What is Universal DesignCindy Jennings
 

Destaque (20)

PT Modeling in S'pore [Terence Ng]
PT Modeling in S'pore [Terence Ng]PT Modeling in S'pore [Terence Ng]
PT Modeling in S'pore [Terence Ng]
 
Consumer Focus/ Passenger focus open rail data
Consumer Focus/ Passenger focus open rail dataConsumer Focus/ Passenger focus open rail data
Consumer Focus/ Passenger focus open rail data
 
PUBLIC TRANSPORT SYSTEM PRODUCT DEVELOPMENT AND MARKETING GUIDELINES FOR A SO...
PUBLIC TRANSPORT SYSTEM PRODUCT DEVELOPMENT AND MARKETING GUIDELINES FOR A SO...PUBLIC TRANSPORT SYSTEM PRODUCT DEVELOPMENT AND MARKETING GUIDELINES FOR A SO...
PUBLIC TRANSPORT SYSTEM PRODUCT DEVELOPMENT AND MARKETING GUIDELINES FOR A SO...
 
A study on passenger’s satisfaction towards railway services in erode junction
A study on passenger’s satisfaction towards railway services in erode junctionA study on passenger’s satisfaction towards railway services in erode junction
A study on passenger’s satisfaction towards railway services in erode junction
 
Metro Rail and the City
Metro Rail and the CityMetro Rail and the City
Metro Rail and the City
 
NKEA: Greater KL / Klang Valley - Dato' Ahmad Suhaili Idrus
NKEA: Greater KL / Klang Valley - Dato' Ahmad Suhaili IdrusNKEA: Greater KL / Klang Valley - Dato' Ahmad Suhaili Idrus
NKEA: Greater KL / Klang Valley - Dato' Ahmad Suhaili Idrus
 
Scheme Of Work Imd 203
Scheme Of Work Imd 203Scheme Of Work Imd 203
Scheme Of Work Imd 203
 
Imd 203 Questions
Imd 203 QuestionsImd 203 Questions
Imd 203 Questions
 
Comp 5 Computer Concepts
Comp 5   Computer ConceptsComp 5   Computer Concepts
Comp 5 Computer Concepts
 
Chapter09
Chapter09Chapter09
Chapter09
 
Excel 2007 Unit D
Excel 2007 Unit DExcel 2007 Unit D
Excel 2007 Unit D
 
Homework Assignments
Homework   AssignmentsHomework   Assignments
Homework Assignments
 
Gps Introduction
Gps IntroductionGps Introduction
Gps Introduction
 
Cost Of Computing
Cost Of ComputingCost Of Computing
Cost Of Computing
 
Making Online Learning Accessible - A Resource Guide
Making Online Learning Accessible - A Resource GuideMaking Online Learning Accessible - A Resource Guide
Making Online Learning Accessible - A Resource Guide
 
What is Universal Design
What is Universal DesignWhat is Universal Design
What is Universal Design
 
Ppt unit d
Ppt unit dPpt unit d
Ppt unit d
 
Excel 2007 Unit B
Excel 2007 Unit BExcel 2007 Unit B
Excel 2007 Unit B
 
Power Point Unit B
Power Point Unit BPower Point Unit B
Power Point Unit B
 
Gis Mapping Examples
Gis Mapping ExamplesGis Mapping Examples
Gis Mapping Examples
 

Semelhante a Mayor Transport Strategy Transport Proposals

Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbai
Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbaiSustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbai
Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbaiGargee Ghosh
 
Report on sustainable urban travel bw
Report on sustainable urban travel bwReport on sustainable urban travel bw
Report on sustainable urban travel bwGargee Ghosh
 
Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2Fairfax County
 
Multi-modal transportation, dissertation brief
Multi-modal transportation, dissertation brief Multi-modal transportation, dissertation brief
Multi-modal transportation, dissertation brief Piyush KumAr
 
Systems Level Approach To Sustainable Urban Arterial Revitalization
Systems Level Approach To Sustainable Urban Arterial RevitalizationSystems Level Approach To Sustainable Urban Arterial Revitalization
Systems Level Approach To Sustainable Urban Arterial Revitalizationbrianhuey
 
Future Agenda Future Of Transport
Future Agenda   Future Of TransportFuture Agenda   Future Of Transport
Future Agenda Future Of TransportFuture Agenda
 
Introduction to transportation engineering
Introduction to transportation engineeringIntroduction to transportation engineering
Introduction to transportation engineeringAbdul Bais
 
Transit oriented development
Transit oriented developmentTransit oriented development
Transit oriented developmentPooja Jariwala
 
Breakout 1: Intersections & Interchanges
Breakout 1: Intersections & InterchangesBreakout 1: Intersections & Interchanges
Breakout 1: Intersections & Interchangesgrplanning
 
H041024856
H041024856H041024856
H041024856IOSR-JEN
 
Land use transportation relation
Land use  transportation relationLand use  transportation relation
Land use transportation relationSiddhi Vakharia
 
Transportation system
Transportation systemTransportation system
Transportation systemhome
 
Corridor Intensification Strategy (CIS) | Amman Institute
Corridor Intensification Strategy (CIS) | Amman InstituteCorridor Intensification Strategy (CIS) | Amman Institute
Corridor Intensification Strategy (CIS) | Amman InstituteAmman Institute
 
Uirr news q3 2012-final
Uirr news q3 2012-finalUirr news q3 2012-final
Uirr news q3 2012-finalCombinant nv
 
Build it Right
Build it RightBuild it Right
Build it RightLee Haber
 

Semelhante a Mayor Transport Strategy Transport Proposals (20)

Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbai
Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbaiSustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbai
Sustainable urban travel- brts ahmedabad,brts pune,suburban railway mumbai
 
Report on sustainable urban travel bw
Report on sustainable urban travel bwReport on sustainable urban travel bw
Report on sustainable urban travel bw
 
Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2
 
Multi-modal transportation, dissertation brief
Multi-modal transportation, dissertation brief Multi-modal transportation, dissertation brief
Multi-modal transportation, dissertation brief
 
Systems Level Approach To Sustainable Urban Arterial Revitalization
Systems Level Approach To Sustainable Urban Arterial RevitalizationSystems Level Approach To Sustainable Urban Arterial Revitalization
Systems Level Approach To Sustainable Urban Arterial Revitalization
 
Settlement
Settlement Settlement
Settlement
 
Future Agenda Future Of Transport
Future Agenda   Future Of TransportFuture Agenda   Future Of Transport
Future Agenda Future Of Transport
 
AN M.ENG PRESENTATION ON ROAD NETWORK
AN M.ENG PRESENTATION ON ROAD NETWORKAN M.ENG PRESENTATION ON ROAD NETWORK
AN M.ENG PRESENTATION ON ROAD NETWORK
 
Introduction to transportation engineering
Introduction to transportation engineeringIntroduction to transportation engineering
Introduction to transportation engineering
 
Transit oriented development
Transit oriented developmentTransit oriented development
Transit oriented development
 
Breakout 1: Intersections & Interchanges
Breakout 1: Intersections & InterchangesBreakout 1: Intersections & Interchanges
Breakout 1: Intersections & Interchanges
 
H041024856
H041024856H041024856
H041024856
 
IMPACT OF BRTS ON CITIES
IMPACT OF BRTS ON CITIESIMPACT OF BRTS ON CITIES
IMPACT OF BRTS ON CITIES
 
Land use transportation relation
Land use  transportation relationLand use  transportation relation
Land use transportation relation
 
Paratransit
ParatransitParatransit
Paratransit
 
Transportation system
Transportation systemTransportation system
Transportation system
 
J0470201020111
J0470201020111J0470201020111
J0470201020111
 
Corridor Intensification Strategy (CIS) | Amman Institute
Corridor Intensification Strategy (CIS) | Amman InstituteCorridor Intensification Strategy (CIS) | Amman Institute
Corridor Intensification Strategy (CIS) | Amman Institute
 
Uirr news q3 2012-final
Uirr news q3 2012-finalUirr news q3 2012-final
Uirr news q3 2012-final
 
Build it Right
Build it RightBuild it Right
Build it Right
 

Último

Haitian culture and stuff and places and food and travel.pptx
Haitian culture and stuff and places and food and travel.pptxHaitian culture and stuff and places and food and travel.pptx
Haitian culture and stuff and places and food and travel.pptxhxhlixia
 
8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCRdollysharma2066
 
"Fly with Ease: Booking Your Flights with Air Europa"
"Fly with Ease: Booking Your Flights with Air Europa""Fly with Ease: Booking Your Flights with Air Europa"
"Fly with Ease: Booking Your Flights with Air Europa"flyn goo
 
Inspirational Quotes About Italy and Food
Inspirational Quotes About Italy and FoodInspirational Quotes About Italy and Food
Inspirational Quotes About Italy and FoodKasia Chojecki
 
Where to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasdWhere to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasdusmanghaniwixpatriot
 
Aeromexico Airlines Flight Name Change Policy
Aeromexico Airlines Flight Name Change PolicyAeromexico Airlines Flight Name Change Policy
Aeromexico Airlines Flight Name Change PolicyFlyFairTravels
 
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)Escort Service
 
Dubai Call Girls O528786472 Call Girls Dubai Big Juicy
Dubai Call Girls O528786472 Call Girls Dubai Big JuicyDubai Call Girls O528786472 Call Girls Dubai Big Juicy
Dubai Call Girls O528786472 Call Girls Dubai Big Juicyhf8803863
 
Italia Lucca 1 Un tesoro nascosto tra le sue mura
Italia Lucca 1 Un tesoro nascosto tra le sue muraItalia Lucca 1 Un tesoro nascosto tra le sue mura
Italia Lucca 1 Un tesoro nascosto tra le sue murasandamichaela *
 
Hoi An Ancient Town, Vietnam (越南 會安古鎮).ppsx
Hoi An Ancient Town, Vietnam (越南 會安古鎮).ppsxHoi An Ancient Town, Vietnam (越南 會安古鎮).ppsx
Hoi An Ancient Town, Vietnam (越南 會安古鎮).ppsxChung Yen Chang
 
Apply Indian E-Visa Process Online (Evisa)
Apply Indian E-Visa Process Online (Evisa)Apply Indian E-Visa Process Online (Evisa)
Apply Indian E-Visa Process Online (Evisa)RanjeetKumar108130
 
Exploring Sicily Your Comprehensive Ebook Travel Guide
Exploring Sicily Your Comprehensive Ebook Travel GuideExploring Sicily Your Comprehensive Ebook Travel Guide
Exploring Sicily Your Comprehensive Ebook Travel GuideTime for Sicily
 
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCRsoniya singh
 
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)Mazie Garcia
 
Moroccan Architecture presentation ( Omar & Yasine ).pptx
Moroccan Architecture presentation ( Omar & Yasine ).pptxMoroccan Architecture presentation ( Omar & Yasine ).pptx
Moroccan Architecture presentation ( Omar & Yasine ).pptxOmarOuazzani1
 
question 2: airplane vocabulary presentation
question 2: airplane vocabulary presentationquestion 2: airplane vocabulary presentation
question 2: airplane vocabulary presentationcaminantesdaauga
 
Authentic Travel Experience 2024 Greg DeShields.pptx
Authentic Travel Experience 2024 Greg DeShields.pptxAuthentic Travel Experience 2024 Greg DeShields.pptx
Authentic Travel Experience 2024 Greg DeShields.pptxGregory DeShields
 
How Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s WatersHow Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s WatersMakena Coast Charters
 

Último (20)

Haitian culture and stuff and places and food and travel.pptx
Haitian culture and stuff and places and food and travel.pptxHaitian culture and stuff and places and food and travel.pptx
Haitian culture and stuff and places and food and travel.pptx
 
8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR
 
"Fly with Ease: Booking Your Flights with Air Europa"
"Fly with Ease: Booking Your Flights with Air Europa""Fly with Ease: Booking Your Flights with Air Europa"
"Fly with Ease: Booking Your Flights with Air Europa"
 
Enjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCR
 
Inspirational Quotes About Italy and Food
Inspirational Quotes About Italy and FoodInspirational Quotes About Italy and Food
Inspirational Quotes About Italy and Food
 
Where to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasdWhere to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasd
 
Aeromexico Airlines Flight Name Change Policy
Aeromexico Airlines Flight Name Change PolicyAeromexico Airlines Flight Name Change Policy
Aeromexico Airlines Flight Name Change Policy
 
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
 
Dubai Call Girls O528786472 Call Girls Dubai Big Juicy
Dubai Call Girls O528786472 Call Girls Dubai Big JuicyDubai Call Girls O528786472 Call Girls Dubai Big Juicy
Dubai Call Girls O528786472 Call Girls Dubai Big Juicy
 
Italia Lucca 1 Un tesoro nascosto tra le sue mura
Italia Lucca 1 Un tesoro nascosto tra le sue muraItalia Lucca 1 Un tesoro nascosto tra le sue mura
Italia Lucca 1 Un tesoro nascosto tra le sue mura
 
Hoi An Ancient Town, Vietnam (越南 會安古鎮).ppsx
Hoi An Ancient Town, Vietnam (越南 會安古鎮).ppsxHoi An Ancient Town, Vietnam (越南 會安古鎮).ppsx
Hoi An Ancient Town, Vietnam (越南 會安古鎮).ppsx
 
Enjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCR
 
Apply Indian E-Visa Process Online (Evisa)
Apply Indian E-Visa Process Online (Evisa)Apply Indian E-Visa Process Online (Evisa)
Apply Indian E-Visa Process Online (Evisa)
 
Exploring Sicily Your Comprehensive Ebook Travel Guide
Exploring Sicily Your Comprehensive Ebook Travel GuideExploring Sicily Your Comprehensive Ebook Travel Guide
Exploring Sicily Your Comprehensive Ebook Travel Guide
 
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR
 
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
 
Moroccan Architecture presentation ( Omar & Yasine ).pptx
Moroccan Architecture presentation ( Omar & Yasine ).pptxMoroccan Architecture presentation ( Omar & Yasine ).pptx
Moroccan Architecture presentation ( Omar & Yasine ).pptx
 
question 2: airplane vocabulary presentation
question 2: airplane vocabulary presentationquestion 2: airplane vocabulary presentation
question 2: airplane vocabulary presentation
 
Authentic Travel Experience 2024 Greg DeShields.pptx
Authentic Travel Experience 2024 Greg DeShields.pptxAuthentic Travel Experience 2024 Greg DeShields.pptx
Authentic Travel Experience 2024 Greg DeShields.pptx
 
How Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s WatersHow Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s Waters
 

Mayor Transport Strategy Transport Proposals

  • 1. Chapter five – Transport 107 proposals 5.1 Introduction – a balanced medium distance, particularly in growing areas such as the London Thames Gateway can be and integrated approach best accommodated by bus, tram or light rail such as DLR, whereas the more dispersed trips 233 Chapter four outlines the strategic policies in Outer London tend to favour bus, bike (over that are required to meet the objectives of the a shorter distance) and car Local short distance MTS There are a number of tools available journeys present the best opportunity for to implement these policies such as investing walking and cycling in the transport network to provide more capacity and better connectivity, managing 236 As a consequence, different areas of London and influencing the demand for travel and require different policy interventions Proposals introduction of new technology to reduce for central London will inevitably focus on emissions As always, there are trade-offs which tackling congestion, increasing the capacity means a balanced approach must be taken of the rail network, encouraging walking and cycling, and managing demand In Outer 234 London’s transport network is finite and there London, proposals need to acknowledge the Chapter five is often competition for this limited space, role of the car, especially low emission cars whether it is for road space or rail paths In For Outer London town centres, measures to striking the right balance in using this scarce improve bus accessibility, public realm, walking resource the proposals in this chapter recognise and cycling will generally be prioritised There that all the varying needs of London need to may be places where a number of options are be met – the needs for international links (as possible In these cases further work will be a global city), for national links (as a national required to assess the most effective solution, capital), and more local links (London is a bearing in mind the cost of the scheme both in place where people live, visit and work) construction and during operation The need The proposals set out in this chapter cater to recognise affordability and business case for all of these needs constraints will be paramount given the current financial environment, and this will inevitably 235 The specific transport proposals have to preclude some schemes be considered in terms of effectiveness, acceptability and cost There may be an obvious 237 Due to the dispersed nature of trips in Outer ‘best mode for the task’, for example, only London, the role of the car is acknowledged as rail-based modes can provide the sufficient sometimes necessary, particularly for medium capacity to cater for the very high volume to longer distance trips The use of cleaner, low ‘same time, same place’ demand that occurs emission cars will be encouraged over others twice a day during the week to, and from, central London Similarly, regular high to 238 Most freight is moved by road While a mode medium volume demand over a short to shift from road to rail and water is needed to Chapter five – Transport proposals
  • 2. 108 Mayor’s Transport Strategy – Public Draft achieve the goals of the strategy, for some economic sectors, as well as more flexible types of freight, and for many servicing trips, working practices This highlights the need for a access by road will remain a requirement The transport strategy that is integrated with other strategy therefore needs to ensure that the broader policy areas such as land use planning, freight left on the roads (which will be the education and healthcare provision majority) is moved as efficiently as possible while contributing to goals of the strategy 240 The proposals for each mode or policy area This will require cleaner, better driven vehicles, contained in the following chapter are derived better journey planning and the integration of from how they can best support the strategic freight and land use planning transport policies set out in chapter four, having regard to the nature of the mode 239 Interventions can also be temporal as well as and policy objectives They have also been spatial The need to satisfy and cater for peak developed using an integrated approach, demand means there is spare capacity off-peak taking account of wider strategies both within Greater use of transport throughout the week London such as the London Plan, Economic can help cover the fixed costs of provision and Development Strategy, Air Quality and Housing make the best use of investment The seven- strategies, as well as looking beyond the GLA day week, 365-day-a-year, diverse economy boundary to the Greater South East region is something the London Plan seeks to encourage through policy support for tourism, retail, arts and entertainment and emerging Chapter five – Transport proposals
  • 3. 109 Proposals to manage and enhance the transport system 5.2 National Rail, Crossrail, 243 Eurostar services currently either run non-stop or make only one intermediate stop between Thameslink, Overground, St Pancras International and the Channel DLR, Tramlink Tunnel, with services calling at either Ebbsfleet International or Ashford International Beyond 5.2.1 Introduction 2010, EU policies will permit competition Chapter five for international rail services, which may 241 London is more dependent on rail than any result in an increase in international high- other city in the UK: 70 per cent of all rail speed rail services to/from London This travel in the UK is to, or from, the Capital will provide an opportunity to encourage London’s success is bound up with the future more direct rail services to a wider range of of its rail network and services It is vitally European destinations and to utilise Stratford important, therefore, that Network Rail and International station in order to reduce the train operating companies better serve the congestion at St Pancras International, and to city’s needs, and that the Mayor has greater provide better international connections to input and influence over planning and delivery the Isle of Dogs and east London of their services 5.2.2 International and National Rail Proposal 1 links and services The Mayor, through TfL, and working with the DfT, Network Rail, the operators International rail passenger links of international rail services and other 242 The strategy fully supports expansion of transport stakeholders, will encourage more international rail services that improve London’s international rail services direct to a wider connectivity with Europe and provide a viable range of European destinations, and that alternative to air travel some of those new services also stop at Stratford International station Chapter five – Transport proposals
  • 4. 110 Mayor’s Transport Strategy – Public Draft International and national rail freight Proposal 2 245 International and national movement of The Mayor, through TfL, and working with the freight plays an important role in the success DfT, Network Rail, train operating companies, of London’s economy and the Mayor will freight operating companies, boroughs and work with others to seek to deliver enhanced other transport stakeholders, will support the rail freight capacity through supporting new development of more rail freight terminals terminals to facilitate efficient movement of in or near London, including connections to goods; and encourage transfer of freight from HS1 for international freight, in line with the road to rail wherever possible London Plan policy to identify new sites for strategic rail freight interchanges 246 The new £1 5bn container port, known as London Gateway, near Tilbury, will provide 250 A number of rail routes in London are used by substantial additional port capacity in the freight services passing through the Capital, South East when it opens in 2011, which for example, on their way to the Midlands from will generate new rail freight flows passing Channel ports and from Europe via the Channel through London Tunnel While the use of rail for these kinds of freight movements is supported, this ‘through’ 247 A rail connected freight transhipment facility traffic should have a minimal impact on the at Howbury Park, near Slade Green, is being capacity of the passenger rail network and on developed, and is expected to open in 2010, local communities through noise enabling the transfer of road freight to rail A new rail freight hub is also proposed at Brent Cross/Cricklewood Proposal 3 The Mayor, through TfL and working with the 248 High Speed 1 (HS1) is an under-used facility DfT, Network Rail, train operating companies, for rail freight and has the unique benefits of freight operating companies, boroughs and the larger European gauge clearance for ‘high- other transport stakeholders, will support cube’ containers and the possibility of express the development of National Rail routes that freight services carrying high value goods relieve London of freight without an origin or To enable this, terminal facilities are required, destination in the Capital with the London riverside area of the Thames Gateway being the site identified Chapter five – Transport proposals
  • 5. 111 Domestic high-speed rail flights, yet generate up to £55bn in revenue and benefits over a 60-year period for the 252 The introduction of the first domestic high- UK economy With the potential to offer speed services in the UK on HS1 in 2009, has journey times from London to Manchester in significantly reduced journey times from Kent 66 minutes and to Edinburgh in two hours and the Thames Gateway to central London and nine minutes, such a new line could also Elsewhere, domestic rail service journey times provide new capacity of 9,100 seats per hour from London to the regions can be longer than into central London Further benefits according passenger expectations, particularly when to Network Rail, could include significant CO2 compared to European competitors who have reductions from modal switch to high-speed invested in high-speed rail networks rail from both air and road, and the release of capacity on the existing West Coast Main 253 Peak-hour crowding is also a major issue, Line for more commuter and freight services emphasised by the fact that the National Rail Network Rail is sharing the results of its new network carries 60 per cent more passengers line study with High Speed Two, the company today than it did in 1994, yet the number Chapter five set up by the government to investigate of actual train services has only increased by options for a new-high speed line from London five per cent Capacity is critical on a number to the west Midlands and potentially beyond, of main lines out of London, in particular the which is due to report back with its own East Coast Main Line to Yorkshire, the north findings by the end of 2009 east and Scotland and the Great Western Main Line to the southwest and south Wales The Proposal 4 West Coast Main Line to the west Midlands, northwest and Scotland has recently benefited The Mayor and TfL support the from a £9bn upgrade allowing faster and more development of a national high-speed frequent services, yet according to Network rail network and will work with the DfT, Rail, by 2020, the main line from London to Network Rail, High Speed Two and other Birmingham and the northwest will be full, transport stakeholders to ensure that the given projected growth London terminal for any new high-speed line is centrally located, well-connected 254 Network Rail has recently published its to the existing public transport network, proposals for a new high-speed rail line and widely accessible in order to maximise from the centre of London to Birmingham, access to jobs and London’s population Manchester and on to Glasgow and Edinburgh It is currently considered that Euston best The strategic business case that forms part meets these criteria and further evaluation of its new line study identifies that such a will be made of this and other locations new high-speed line could lead to a reduction of up to 20,000 annual domestic short haul Chapter five – Transport proposals
  • 6. 112 Mayor’s Transport Strategy – Public Draft 5.2.3 London and the South East rail Crossrail links and services 259 Crossrail is the biggest transport project in Accommodating growth on the Europe and a scheme of national importance National Rail network that will provide a rail spine across London from east to west, as shown in Figure 30 It is 256 Rail will continue to be the dominant mode in needed to underpin the most rapid economic accessing central London, with three quarters growth areas of London and will be a very of all trips from Outer London to central significant capacity addition to the transport London made by National Rail, Tube and DLR network Figure 29 illustrates the immense As the number of trips into central London scale of the scheme with the example of the increases, inevitably the demand on the new station at Tottenham Court Road, which National Rail network will increase, with some will transform access to this area of the West lines into London seeing demand growth of End from the current crowded and congested up to 30 per cent by 2031 conditions to a spacious, high quality and attractive travel environment, capable of 257 BAA/Heathrow Airport Limited have recently supporting local economic intensification applied to the Secretary of State for Transport as part of the Transport and Works Act 1992 260 When completed in 2017, Crossrail will enable process, to authorise construction of Airtrack, the City and Canary Wharf to continue to a new rail link connecting the existing rail maintain their leading business status in the line from Waterloo to Reading with Heathrow world, support the continued development Terminal 5 More information about Airtrack is of the West End, help to lock-in the legacy contained in the Airports section of the strategy benefits of the 2012 Games, and transform the Thames Gateway through links to northeast 258 The DfT has also announced its intention to and southeast London and on into Essex electrify the Great Western Main Line from London Paddington to Oxford, Bristol and 261 Crossrail will facilitate easier, faster and for the Swansea The Mayor welcomes this project and is first time, direct journeys by public transport committed to working with the DfT to maximise from Heathrow to Canary Wharf, as well as the benefits to London, including the potential improved links to London’s other central to extend Crossrail westwards to Reading The business areas, helping to improve London’s Mayor also remains committed to seeing other international links Crossrail is the only transport rail electrification proposals for London taken project that can deliver the capacity needed to forward, such as Gospel Oak to Barking (which support more jobs in central London and the will also contribute to improving air quality) Isle of Dogs, improve the east-west employment corridor and support development of new employment areas, thereby providing additional Chapter five – Transport proposals
  • 7. 113 Figure 29: Layout of the expanded Tottenham Court Road station Chapter five jobs in areas including the Thames Gateway additional 5 8 million passenger kilometres Without Crossrail, London would have been are added to peak capacity and Crossrail will prevented from continuing the development deliver significant crowding relief on the Tube of its second business centre at Canary Wharf, (including the Central, Piccadilly, Metropolitan, which will allow this area to maximise its Hammersmith & City, Circle and Jubilee lines) contribution to the wider UK economy and the DLR 262 Crossrail provides the largest single increase 263 As a project of national significance, Crossrail in public transport capacity exactly where will bring transport improvements that will be it is most needed It will add 10 per cent to felt across the country The scheme will be a the overall capacity of London’s rail network catalyst for safeguarding a national economy through the provision of 24 high-capacity, inextricably linked with that of London (See 10-coach trains an hour in each direction in the spotlight on the wider economic benefits central section during peak periods According of Crossrail) The provision of high quality to forecasting work undertaken by TfL, an information to keep people informed about the Chapter five – Transport proposals
  • 8. 114 Mayor’s Transport Strategy – Public Draft Spotlight on: The wider economic benefits of Crossrail Crossrail will deliver significant benefits to the national economy, the wider southeast region as well as to London In addition to the wide ranging transport benefits, such as reduced crowding, additional capacity, new direct links across London and reduced journey times, Crossrail also delivers a broad range of direct economic benefits Crossrail supports a development potential of more than 260,000 jobs and 70,000 people within the key Opportunity Areas alone (Isle of Dogs, City fringe, Lower Lea Valley, Paddington) and is expected to generate up to 30,000 extra jobs – through productivity improvements in central London by 2027 The Crossrail project will employ up to 14,000 people at the peak of construction during 2013-2015, and it will contribute to an ongoing pool of skilled workers through the new tunnelling academies being established by the Mayor In the longer-term, Crossrail will generate an estimated 1,000 jobs when fully operational Crossrail will also require the services of regionally-based manufacturers and other suppliers Crossrail will serve significant new residential areas, for example, parts of the Thames Gateway and beyond in the South East region, and employment accessibility will be significantly enhanced, bringing an additional 1 5 million more people across London within an hour’s travel of the West End, City and Docklands However, it is not just central London and Docklands economies which benefit from Crossrail, Outer London gains considerable benefits too, as illustrated in the following table Crossrail also links key Outer London metropolitan town centres, such as Romford, Ilford and Ealing, delivering further regeneration benefits Chapter five – Transport proposals
  • 9. 115 Figure 30: Crossrail route connections and regional maps construction programme, especially to minimise Chapter five inconvenience to users of other transport Proposal 5: services, local residents and businesses, will be The Mayor, through TfL, and working with a high priority for Crossrail Overall the benefits the DfT, Network Rail, train operating of Crossrail are estimated to be worth at least companies, freight operating companies, £36bn in current prices to the national GDP boroughs and other transport stakeholders over the next 60 years will seek to ensure that Crossrail is delivered by 2017, and that it is fully integrated with the rest of London’s public transport system; that the impacts of construction on residents and businesses are minimised as far as possible; and that the future benefits Crossrail brings are monitored to ensure the rail link achieves its objectives Chapter five – Transport proposals
  • 10. 116 Mayor’s Transport Strategy – Public Draft 265 London is the centre of the Greater South East and approval given to Network Rail’s Delivery region of England, the fastest developing area Plan to implement HLOS. As such, HLOS is of the country, with a number of nationally now a committed programme of National Rail designated Growth Areas. Continued economic funding from Government to 2014. The process growth is mutually beneficial – much of is planned to be repeated for control period London’s workforce live beyond the GLA area. five, from 2014 to 2019. It is therefore important to look across regional boundaries. Future extensions of Crossrail, to 268 The improvements to London’s rail network the east and west, could help reduce congestion to be achieved by 2014 through HLOS, and improve connectivity and, together with forms a key element of the transport strategy longer trains, ensure maximum benefit is and it is essential it is delivered as planned. derived from the Crossrail infrastructure. The improvements are shown in Figure 31 and include: Proposal 6 • Improvements to capacity on each of The Mayor, through TfL, and working with London’s main radial rail corridors, including the DfT, Network Rail, train operating the Thameslink programme, and 900 new companies and other stakeholders, will carriages by 2014 (Thameslink by 2015) consider future extensions of Crossrail that • Improved reliability reduce congestion and improve connectivity • Acceptance of Oyster at all National Rail on London commuter routes. stations in London in early 2010 5.2.4 London–wide rail links • Improving access at stations through and services the Access for All obstacle-free stations programme. Approximately 50 per cent of High Level Output Specification investment stations in the first phase are located in in rail capacity London or the South East 267 In July 2007, the Government presented • Enhancements to the freight gauge the HLOS detailing the development of and route capacity on the Felixstowe to the National Rail network to 2014 (control Nuneaton line (providing a direct route period four). The HLOS was accompanied by avoiding London for freight trains, which a Statement of Funds Available (SoFA), which releases capacity for more passenger trains detailed proposals for funding arrangements for in London) the railways in the same time period to deliver • Gauge enhancements to the Gospel Oak- the proposals put forward in the HLOS. The Barking line, which will provide a route for SoFA has now been reviewed by the Office of rail freight services from the east to the Rail Regulation, agreed with the Government north of London Chapter five – Transport proposals
  • 11. 117 Spotlight on: Thameslink The Thameslink Programme is a £5 5bn project to deliver a high capacity, north-south rail spine through central London that complements the east-west Crossrail route When completed in 2015, Thameslink will provide greater capacity, higher frequencies, new services and improved access to central London from a range of destinations within London and across southeast England Major benefits to London from the works to expand the capacity and operating network that will use Thameslink, include a capacity increase in the core section between Farringdon and Blackfriars of 127 per cent by 2015, compared to current levels Large-scale works include the rebuilding of Blackfriars station, which will become the first station to span the Thames, providing direct access to both the north and south banks; Farringdon, will have 12-car platforms and become a major interchange between Thameslink and Crossrail; and London Bridge, will be significantly rebuilt to provide a major increase in capacity and better facilities for passengers A new station will also be provided at Brent Cross/Cricklewood as part of the comprehensive redevelopment of this area Chapter five Chapter five – Transport proposals
  • 12. 118 Mayor’s Transport Strategy – Public Draft Figure 31: Committed enhancements to London’s rail network Chiltern Railways Thameslink Southwest • Frequency improvements • 12-car maximum capability • 10-car Windsor lines and inner • 24 trains per hour through core suburban capability West Coast Main Line London, Tilbury and Southend South central London • Trains lengthened and frequency • 12-car capability on all routes • 10-car inner capability increased Great Western Main Line West Anglia Southeast London • Train lengthening • 12-car capability Stansted and • 12-car inner suburban trains • New Crossrail services Cambridge Great Eastern Main Line • High-capacity new trains • Additional services • New Crossrail service Wood Green Harrow Romford Ilford Uxbridge Ealing Shepherd’s Bush Hounslow Kingston Bromley Croydon Sutton Key Opportunity Area Outer London Inner London Central Activities Zone Chapter five – Transport proposals
  • 13. 119 Further rail investment beyond the Proposal 7 current programme The Mayor, through TfL, will seek to ensure that Network Rail and the train 270 Despite the significant investment in the operating companies deliver the committed National Rail network being delivered though improvements to the rail network and the TfL Business Plan and HLOS, congestion services in London as set out by the DfT’s will still be a significant issue on some radial High Level Output Specification for the rail corridors (Figure 32) Additional schemes period 2009-2014 and interventions will therefore be required to address specific capacity and connectivity problems in the longer-term As most of these will need to be delivered by Network Rail Chapter five Figure 32: National Rail and Tube ‘stress’ on radial corridors into central London 2006 J K 2017 J K 2031 J K I L I L I L H M H M H M G Central N G Central N G Central N London London London F O F O F O E A E A E A D C B D C B D C B Severely ‘stressed’ corridor: Highly ‘stressed’ corridor: Moderately ‘stressed’ corridor: On average residents in the On average residents in the On average residents in the corridor experience severe corridor experience high corridor experience moderate levels of crowding on rail levels of crowding on rail levels of crowding on rail public transport on their way public transport on their way public transport on their way to central London during AM to central London during AM to central London during AM peak for some part or all of peak for some part or all of peak for some part or all of their journey their journey their journey Note: Corridor letters correspond to corridors in Figure 8 Chapter five – Transport proposals
  • 14. 120 Mayor’s Transport Strategy – Public Draft Figure 33: Further capacity needed on radial rail routes to central London Chiltern, London Midland and Thameslink Great Northern capacity West Anglia lines Thameslink capacity enhancement enhancement four-tracking, serving (serving Luton airport) Stansted airport Chelsea Hackney line (Crossrail 2) Croxley link Great Eastern capacity High-speed rail enhancements DLR extensions and capacity enhancements Crossrail extensions Longer trains on London, Tilbury, Southend lines Airtrack and other orbital links to Heathrow Northern line Upgrade 2 and extension to Nine Elms Thames crossings Chelsea Hackney Crossrail extensions line (Crossrail 2) Rail/Tube improved capacity and connectivity Longer trains on south Tramlink to southeast London, Longer trains on central lines (serving enhancements including potential southwest lines Gatwick airport) and extensions Bakerloo line extension Bus services will continue Greater use of the River Smoothing tra c flow Key to support economic growth Thames and regeneration Opportunity Area Rail termini London terminals capacity Upgrade of all National Rail Cycle and walking Route improvements upgrades and strategic stations and services to London improvements interchanges Overground standards and London-wide improvements integration with Oyster Chapter five – Transport proposals
  • 15. 121 and the train operating companies through important new line Forecast demand shows the franchising system, it is essential that TfL that crowding and congestion remains a works closely with the DfT to influence the significant issue in this corridor (Figure 32) future HLOS and franchising process in order even with new investments such as Crossrail to deliver the improvements that are vital to and Thameslink in place This new line is support London’s growth needed in the longer-term to reduce crowding on existing routes, but also to provide the 271 A number of options to enhance the capacity capacity that is required to meet London’s provision on radial rail routes to central growth and provide connections to the National London in order to address the levels of Rail network, including dispersal of people crowding and congestion after the measures across London from the main line termini in the TfL Business Plan and HLOS have been implemented, are illustrated in Figure 33 The 274 It is important that the route of the Chelsea effectiveness of these schemes at reducing rail Hackney line is reviewed to ensure it is providing and Tube crowding, when combined with other the maximum benefits and value for money capacity improvements on the Underground Chapter five network, are shown in Figure 34 Proposal 9 The Mayor supports new rail capacity in Proposal 8 the broad southwest to northeast corridor, The Mayor, through TfL, and working with the for example, new lines or services using the DfT, Network Rail, train operating companies, Chelsea Hackney line safeguarded alignment boroughs and other transport stakeholders, TfL will undertake a review of the route to will seek further rail capacity across London’s ensure it is providing the maximum benefits rail network, beyond those schemes and value for money already committed The highest priorities are to further increase capacity on London National Rail reliability Overground, southwest routes, the West Anglia Main Line and at congested stations 276 National Rail punctuality has improved considerably since 2002/03 as a result of Chelsea Hackney line the improved maintenance of infrastructure by Network Rail, investment in new trains 273 The Chelsea Hackney line (or Crossrail 2) and signalling, franchise reorganisation provides significant new rail capacity on the to better reflect rail network geography, northeast to southwest corridor and major franchise performance incentives and improved congestion relief to existing rail and Tube timetabling However, despite these substantial lines The route of the line is safeguarded achievements, there is still room for further by Government and it is essential that this improvement (see Figure 35) safeguarding remains in place to protect this Chapter five – Transport proposals
  • 16. 122 Mayor’s Transport Strategy – Public Draft Figure 34: The potential benefits from implementing measures beyond those in the TfL Business Plan and HLOS to reduce crowding on London’s rail and Tube network Increased crowding in 2031 as a result of growth in employment and population Proportion crowded in 2031 without any new investment would be 67% 70 Proportion of passenger kilometres crowded (weekday morning peak) 60 Proportion crowded in 2006 was 55% 50 Proportion crowded in 2031 would be 50% 40 30 Proportion crowded in 2031 with the full strategy package would be 32%1 20 Total impact of the strategy 10 on rail crowding2 0 Crossrail, Tube Further Chelsea Further DLR Other investment 1. It would not be good value line upgrades, investment on Hackney line* extensions, including Airtrack, for money or of benefit to the investment on the the National Rail Bakerloo line Crossrail economy to attempt to National Rail network, north and south extensions, and eliminate all crowding network including extensions to extensions and other service 2. ‘Rail crowding’ includes Thameslink and the DLR and Croxley link* improvments* crowding on the Tube, DLR, other funded Northern line and National Rail and Tramlink measures Underground upgrades Funded measures Unfunded measures * Note: These schemes improve accessibility (connectivity more so than crowding) Chapter five – Transport proposals
  • 17. 123 Figure 35: National Rail punctuality (London and southeast operators total, including peak services) National Rail punctuality (London and southeast operators total, including peak services) 95 minutes of scheduled time % of arrivals within five 90 85 80 75 70 2002/03 2003/04 2004/05 2005/06 2006/07 2007/08 2008/09 Chapter five Proposal 10 Station capacity enhancements The Mayor, through TfL, will seek to ensure 278 Many National Rail stations are congested, that the DfT, Network Rail and the train especially at peak times and enhancements operating companies achieve the HLOS to station capacity are required to improve ‘public performance measure’ for reliability, customer service and to enable London’s as well as an overall reduction in significant growth in rail demand to be accommodated lateness and cancellations for London and Schemes will be taken forward where they are southeast services shown to be value for money and affordable Chapter five – Transport proposals
  • 18. 124 Mayor’s Transport Strategy – Public Draft Spotlight on: Central London rail termini Increasing population and employment, plus the additional capacity on much of London’s rail network through the current rail investment programme, means rail arrivals into central London termini are forecast to increase by up to 25 per cent by 2026 This will result in increased strain on National Rail termini, and on the transport networks and services within central London Limited concourse space means that station crowding is a key issue High levels of connectivity and very large volumes of interchange passengers add extra complexities to this crowding and movement The main termini and interchanges, which are already at, or near capacity, during peak periods, need to be reviewed to ensure they are safe and efficient into the future Congestion relief schemes such as those at King’s Cross/St Pancras and the proposed scheme at Victoria can go a long way to relieving the problems However, these schemes are expensive and disruptive, take time to deliver and ideally need to be linked with increases in onward dispersal capacity Encouraging more onward trips by walking and cycling is a quick and cost-effective way to free-up capacity on the Underground and buses, and ensure that limited space on these services is used more effectively Better streets, better information provision and better facilities for cyclists, such as bike parking will help The strategic interchange concept, improving and encouraging interchange at stations away from the central London termini, would also help onward dispersal (see proposal 46) Chapter five – Transport proposals
  • 19. 125 seven-days-a-week, without disruptions due Proposal 11 to engineering works, except where absolutely The Mayor, through TfL, and working with necessary The Mayor also believes that train the DfT, Network Rail, train operating operating companies should provide sufficient companies and boroughs, will seek to deliver capacity in terms of train lengths, in order capacity enhancements at some of London’s to sufficiently meet demand at all times most congested stations The highest This includes weekends when acute crowding priorities include: can occur due to shorter train formations a) Central London termini station 281 The Mayor will promote a common service congestion relief and onward distribution standard across the London rail network and enhancements (the potential of all onward believes that Overground service standards modes will be considered) provide an evidenced template to follow which b) Clapham Junction station capacity has been adopted almost in full for the recent enhancement (new improved links South Central refranchise with more than 40 between platforms, additional entrances stations and extensive patterns of routes This Chapter five and more ticketing facilities) has specified minimum standards including: c) Improved capacity at National Rail stations • Staffing over the traffic day with severe congestion, including Finsbury • Oyster acceptance and retailing via ticket Park, Bromley South, Wimbledon, Vauxhall machines within Travelcard Zones 1 to 6 and Barking • Station facilities such as seating d) Improved capacity at National Rail stations and shelters with moderate congestion, including Willesden Junction, Balham, West Croydon, • Multi-modal customer information at Norwood Junction and Surbiton stations, through posters and electronic means, on-system and off, scheduled Improving customer standards across the and realtime National Rail network in London • Security features such as lighting, CCTV and Help points 280 Despite improvements in National Rail services being delivered by Network Rail, TfL and others • Graffiti removal, litter removal and cleaning over the next 10 years, rail passengers still do • Train frequency of at least four trains per not always benefit from the level of service or hour on each route where the infrastructure frequencies that those who travel on the Tube allows, up to 23:00 enjoy, particularly outside peak hours The Mayor is keen that London benefits from a full ‘seven- • First and last trains broadly aligned with the day railway’, supporting the Capital’s diverse Underground’s operating hours economy with regular, frequent services operating Chapter five – Transport proposals
  • 20. 126 Mayor’s Transport Strategy – Public Draft • Cycle parking to basic standard and 5.2.5 Local and orbital rail links monitoring regime at every station within and services two years London Overground 282 This will require the influencing of the franchise process, as well as reducing 285 Work on London Overground includes disruption to passenger journeys at weekends, reinstatement of disused National Rail routes acknowledging that sometimes, the to link the East London and North London lines undertaking of maintenance works at these at Dalston, modifying existing infrastructure times will remain inevitable Network Rail is to reach West Croydon and Crystal Palace (the already looking at how some engineering works East London line extension) and delivering a could be undertaken through shorter overnight rolling stock maintenance and control centre ‘possessions’ instead, possibly through at New Cross Gate The North London Railway, undertaking more preparatory work off-site also part of London Overground, is to be increased in capacity by up to 50 per cent and will also provide more frequent services Proposal 12 A further phase now approved will see the The Mayor, through TfL, and working with completion of the Inner London Overground Network Rail, train operating companies and orbital rail network between Surrey Quays other transport stakeholders will encourage and Clapham Junction Completion of the the achievement of a ‘seven day railway’ London Overground network enhancements by better planning and management of in 2012 will provide an orbital rail network in necessary engineering and maintenance Inner London that will allow, either directly or work on the railway with a single change of trains, journeys such as Clapham Junction to Dalston and Crystal Palace to West Hampstead This network of Proposal 13 Overground rail services is shown in Figure 36 The Mayor, through TfL, and working with The DLR extension to Stratford International Network Rail, train operating companies in summer 2010 will also improve orbital and other transport stakeholders will frequency and capacity in east London encourage the provision of rail services in London that meet common service standards 286 There are, however, significant further including improved ambience, amenities opportunities to improve orbital travel, such and wayfinding at all stations, and staff as by providing or improving interchange availability at each station It is intended opportunities where radial and orbital lines these improvements will be rolled out as cross Forecasting shows that rapid demand franchises are renewed growth can be expected over the next few years, which means that parts of the Chapter five – Transport proposals
  • 21. 127 Figure 36: London Overground route map (2012) Chapter five Step-free access from the platform to the street (existing and planned) London Overground delivers: • ast London line reopening in E • high capacity orbital railway for A 2010, with extensions to London for the first time Crystal Palace and West Croydon • ervices provide metro S by 2011 frequencies of four trains per hour • xtension to Clapham Junction E • ew longer trains and enhanced N opens 2012 stations Overground could justify investment in longer five or six-car trains TfL will also investigate Proposal 14 where there may be additional routes that The Mayor, through TfL, working with the warrant extensions to the Overground, DfT and Network Rail, will investigate the if found feasible feasibility of providing extra capacity to assist orbital movement on the Overground network and will review potential benefits of extensions to the network of services Chapter five – Transport proposals
  • 22. 128 Mayor’s Transport Strategy – Public Draft Docklands Light Railway Proposal 15 288 Since opening in 1987, the DLR network has The Mayor, through TfL, will investigate the grown to become a vital part of London’s feasibility of further capacity and network public transport system supporting growth expansion of the DLR including an extension and regeneration in the Thames Gateway (see to Dagenham Dock, as part of the housing Docklands case study) Improvements to the proposals for Barking Riverside, and further DLR include a network extension to Stratford network extensions, including options south International and delivery of 55 new carriages of Lewisham, west of Bank and north of to enable three-car operation on most of Stratford International the system by 2010 (with further station and infrastructure enhancements to follow) Tramlink Delivering new rolling stock to maximise the benefits of full three-car operation across the 291 Tramlink has been a great success since network, double tracking between Bow Church opening in 2000, providing important and Stratford, installing a new signalling system orbital links into Croydon and connections to and renewing and replacing the existing rolling neighbouring Outer London town centres – stock will all contribute to ensuring that the and encouraging a shift from car to public DLR is fully able to support continued growth transport Improvements to Tramlink as part of and regeneration in the Thames Gateway area a £54m investment in maintenance, renewals, upgrades and capacity enhancement, are taking 289 An extension of the DLR to Dagenham Dock place between now and 2015 has been identified as a key component of the Government’s housing plans for Barking Riverside There is also further scope to extend the DLR network in the longer-term to provide better links to Stratford, improved orbital links and connectivity in the Thames Gateway, and better integration with the central London transport system, for example, through a westwards extension from Bank to Victoria Chapter five – Transport proposals
  • 23. 129 292 Beyond these initial improvements, 5.3 London Underground consideration will be given to looking at further extensions of Tramlink, with a strong 5.3.1 Introduction focus on a potential north-south axis, in order to accommodate Croydon’s future 294 Over the last decade, the Underground has growth needs, and potentially to improve experienced unprecedented growth in demand, east-west links to neighbouring Outer London with more than a billion passenger journeys a town centres to support improved orbital year now made by Tube LU carries as many connectivity Both short extensions to provide passengers as the entire National Rail network better access from key centres to Tramlink, with up to four million journeys made each and longer extensions opening up completely day, on 11 lines serving 270 stations As a new routes are being considered result, the Underground is now providing a higher volume of service than ever before This customer driven approach has been recognised Proposal 16 by LU’s customers, with LU achieving a The Mayor, through TfL, and working with record 79 out of 100 in terms of customer Chapter five London boroughs and other transport satisfaction stakeholders, will investigate the feasibility of providing extra capacity on the Tramlink 295 This performance has been made possible by network and will review potential benefits of understanding the needs of customers, and extensions to the system implementing a strategy based upon this, namely, to combine a reliable train service with the highest standards of customer care Maintaining the focus on this strategy, requires the Tube to renew its bedrock assets (track, civils, trains, signals, stations), to allow enhanced train service capacity to keep up with rising levels of demand The strategy also provides focus upon other key aspects of the service – creating a welcoming and secure environment, offering personal service to customers, providing accurate and timely service information, and creating ease of access This will deliver the world-class service Londoners rightly deserve Chapter five – Transport proposals
  • 24. 130 Mayor’s Transport Strategy – Public Draft 296 To support the growth of London, LU has 298 A key function of this renewal are the line embarked on its largest investment programme upgrades which are the critical foundation for for 70 years, focusing on improving reliability, the transformation of the Tube Without them delivering faster journey times, along with LU would not be able to provide the capacity increasing capacity across the network required to support the Capital’s economy and meet the demands of the future or even 5.3.2 Renewal and repair of maintain the service that is currently delivered the network Work to upgrade each line is therefore the cornerstone of the Underground’s plan By the 297 The Tube is the oldest metro system in the end of the current programme, the Tube will world, with some infrastructure dating back to have delivered up to an additional 30 per cent the 1860s After decades of under-investment, capacity – including new trains and signalling the network is now undergoing major renewal, systems, allowing the Underground to run more rebuilding and refurbishment, a transformation of trains, providing quicker and more comfortable the Tube The key elements of the programme are: journeys Beyond this, the Tube will require • Rolling stock – replace the majority of train investment to ensure that its asset condition fleets, which if not renewed would have an remains in a state of good repair and does average age of 50 years in 2031, 15 years not fall to the levels seen through decades of beyond their design life This will increase under-investment in the network fleet reliability and capacity 299 While this transformation takes place, the • Signalling – replace assets (more than 40 network faces the tremendous challenge of years old in many cases) to reduce service keeping London moving on a daily basis while delays and increase network capacity simultaneously rebuilding the system This • Track – reduce the backlog of investment massive task cannot be achieved overnight – to reduce safety risks, and remove speed and not without some disruption to services restrictions brought in to manage safety In order to facilitate these works while carrying risks to increase capacity out regular essential maintenance, weekend • Civil structures – renew assets such as closures have become more frequent The high bridges, viaducts, embankments and profile campaign advising customers to ‘check drainage systems to maintain a safe service, before they travel’ has proven highly successful reduce the risks of flooding, and the service and will continue, employing many Travel Tools effects of speed and weight restrictions to help customers plan their journeys • Stations – modernise stations by replacing safety and service critical systems such as fire systems, public address, CCTV, and lifts and escalators Chapter five – Transport proposals
  • 25. 131 Spotlight on: Sub-surface line upgrade The Sub-Surface Railway (SSR) comprising the Circle, District, Hammersmith & City and Metropolitan lines, covers more than 300km of track and represents around 40 per cent of the Tube network It is the part of the Tube in greatest need of renewal The upgrade will be delivered progressively over the next decade and will provide the greatest capacity improvements across the entire network, helping to reduce congestion and accommodate predicted growth In December 2009, a new service pattern will be delivered on the Circle line, almost doubling the frequency of trains on the Hammersmith branch It will also improve the reliability of the Circle line, with knock-on benefits for reliability across the whole of the SSR The new service pattern will be followed by the introduction of a new signalling system to allow higher train service frequencies In July 2009, LU issued an invitation to tender for the resignalling of the sub-surface lines This contract is the single Tube element of the Investment Programme Chapter five One hundred and ninety nine new, larger trains are being built and will enter service from 2010 They will feature energy-saving regenerative breaking, walk-through carriages, better accessibility, improved customer information (audio and visual) and enhanced security The Circle and Hammersmith & City line trains will also have an additional carriage Most significantly, the new trains will be the first to be air-conditioned on the Tube network Chapter five – Transport proposals
  • 26. 132 Mayor’s Transport Strategy – Public Draft 300 By 2012, this programme will deliver an upgrade programme has, and will continue to deliver, key of the Jubilee, Victoria and Northern lines By system improvements (CCTV, public address, 2020, upgrades will have been completed on communications equipment and fire systems), the Piccadilly line and the sub-surface railway as well as improving customer service features A key aspect of this will be a new signalling These include, passenger Help points, new system and the introduction of new, air- electronic information displays in ticket halls and conditioned trains, which were unveiled in 2008 on platforms, improved seating and lighting, as The trains, representing 40 per cent of the well as improvement to accessibility features, LU total fleet, will serve the Metropolitan line such as tactile strips and colour-contrasted starting from 2010 and will then be rolled out handrails for visually impaired people progressively across the Circle, Hammersmith & City and District lines The Bakerloo line upgrade 303 TfL is committed to improving accessibility is expected to be completed with new trains in from street to platform on the Tube Over time, place by 2020 The replacement of the Central TfL will seek to increase the accessibility of the line fleet will follow, delivered into service from network, building upon the foundation of step- 2020 Considerable benefits and efficiencies can free stations already in place be achieved by specifying lighter, more energy efficient and higher capacity trains for both lines Proposal 18 The Mayor, through TfL, will continue to Proposal 17 deliver an ongoing programme of Tube The Mayor, through TfL, will seek to deliver station refurbishments and asset stabilisation upgrades to all Tube lines in a phased to ensure stations are operable and deliver programme to provide a significant increase customer service requirements, as well as in network capacity This will involve a continuing to improve station accessibility combination of new rolling stock and/ over the life of the strategy or signalling systems and other asset replacement As part of this, continued 5.3.4 Station congestion relief investment to bring the network to a good state of repair and maintain it at that level 305 To relieve congestion experienced by Tube will be supported customers at key locations across the network, and to enable quicker journeys, some stations 5.3.3 Station refurbishments require more extensive improvements to ensure safe and efficient station operations and accessibility while also enhancing passengers’ journey 302 Between 2003 and 2009, 124 stations have experience The delivery of capacity been refurbished and this programme will enhancements to strategic Underground continue to be rolled out across the network stations and interchanges are critical to the subject to availability of funding This functioning of the Tube as an integrated Chapter five – Transport proposals
  • 27. 133 network to assist existing passenger flow, and b) Schemes at further strategic Tube also cater for future increases in demand interchanges that are critical to London’s transport system (eg Vauxhall, Finsbury 306 The current station congestion relief Park, Highbury & Islington, Holborn, programme contains the key central London Camden Town, Oxford Circus, Edgware interchanges of Victoria, Tottenham Court Road and Northern line City branch, Road, Bond Street, Paddington (Hammersmith in particular Old Street and Moorgate) & City), and Bank These stations are essential to maintain access to the Underground c) Major strategic multi-modal/National and to optimise the benefits of investment Rail interchanges on to the Underground from the line upgrades, Crossrail and other network to disperse onward demand arising developments They will also greatly improve from National Rail proposals (HLOS2 and central London step-free access HS2 proposals), eg London Bridge, Euston, Liverpool Street, Paddington, Elephant & 307 Further station improvements will address the Castle and Waterloo next level of priority schemes where strategic Chapter five access to, or interchange across, the network 5.3.5 Cooling the Tube will be restricted without further capacity enhancements, for example: Vauxhall, Finsbury 309 High tunnel temperatures during the summer Park and Highbury & Islington months are one of the biggest challenges facing LU, particularly for the deep tunnelled sections of the Underground, such as the Proposal 19 Victoria line These are essentially closed The Mayor, through TfL, and working with systems where the major proportion of the the London boroughs and other transport energy that enters (for example, train motors) stakeholders, will develop and implement is released as heat, which in turn raises a prioritised programme to deliver station temperatures in the tunnels and on the trains capacity and accessibility enhancements As a result of increased train service capacity at London’s most congested Underground (primarily through higher train frequencies) stations, including: and reduced journey times (primarily through a) Congestion relief schemes to complement quicker acceleration and faster maximum Tube line upgrades and/or integrate speeds), electricity usage on the Underground with Crossrail at the key central London is anticipated to increase by 2020, resulting interchanges of Victoria, Tottenham in more heat being released in the tunnels Court Road, Bond Street, Paddington This will be exacerbated by increasing passenger (Hammersmith & City) and Bank numbers and possible increases in air temperature due to climate change Therefore maintaining safe temperatures on deep Chapter five – Transport proposals
  • 28. 134 Mayor’s Transport Strategy – Public Draft tunnelled sections of the Tube will present an nearly eight out of 10 The success of the Tube is ever increasing challenge in the future Already also recognised elsewhere, with the Underground the Tube has implemented a programme to recently named Best Metro in Europe at the tackle heat on the network, and this will prestigious Metro Awards in 2009 continue over the long-term 313 Customer information and personal service Proposal 20 from staff will be especially important as the renewal programme, which can disrupt The Mayor, through TfL, will implement service, is delivered over the next decade the following measures in order to cool the The Underground will continue to invest in Underground: customer-focused training including disability a) New air-conditioned rolling stock across awareness training, and in information the sub-surface (Metropolitan, Circle, systems to deliver the right information to Hammersmith & City and District) lines, customers when they want it, when planning introduced progressively from 2010 or undertaking journeys on the network b) Improved ventilation shafts and 314 Customers value the presence of staff especially replacements of out of service fans when travelling at night The Underground will continue to staff its stations and invest 5.3.6 Customer care in systems which enhance the management of 311 The core renewal programme is essential to the station, such as CCTV, as well as ensuring deliver a safe and reliable service, but LU the stations are well-lit and visibly managed – aspires to the highest standards of customer clean and graffiti free care Customers most value getting from A to B as quickly and reliably as possible, but valued 315 There is a rich heritage of art and design on almost as much are all the different aspects the Tube High quality, value for money design of service they experience during the journey will continue to be a feature of the investment Customers value personal security, a welcoming programme Art on the Underground, LU’s environment, accurate and timely information, art programme, continues the Tube’s long and when customers need assistance, they want tradition of working with artists This can high quality personal service from staff delight customers and improves the travelling environment, as well supporting and 312 In 2008, for the third year running, the celebrating the rich and vibrant art scene Underground carried more customers than ever in London Licensed busking and ‘Poems before, in excess of one billion At the same on the Underground’ bring music and poetry time, customer satisfaction with the service also to the wide-ranging audience of customers reached a record high of 79 out of 100, most on the Tube people scored the overall service provided at Chapter five – Transport proposals
  • 29. 135 simplifying and recasting the service patterns Proposal 21 it will be possible to increase capacity on the The Mayor, through TfL, will continue to Northern line by a further 20 per cent by 2020 develop and implement measures to deliver – over and above the capacity delivered by the the highest standards of customer care on original line upgrade in 2012 This will act as the Underground, including the high quality the equivalent of adding a new north-south provision of information about engineering line across London, reducing levels of crowding works that affect regular Tube services, and as well as providing reliability improvements It an accessible Tube map showing step-free will help the Capital to keep pace with growth and mostly step-free routes in demand, and support London’s future economic development 5.3.7 Further improvements and extensions to the network 319 In addition, further enhancements to the Northern line are possible With private sector 317 Over the lifetime of this strategy, there are funding, there is the potential to extend the Northern line to Battersea in order to support Chapter five opportunities for further enhancements and extensions to the LU network to improve developer-led growth in the Vauxhall/Nine Elms/ journey times and provide additional capacity Battersea Opportunity Area, an area identified as essential for the continued growth of London being capable of accommodating at least 15,000 Any potential schemes will have to be subject new jobs and 16,000 homes by 2031 to a thorough value for money and feasibility analysis and will have to be considered in light 320 The Bakerloo line has an important role in of any future funding constraints London’s transport geography, serving the strategic northwest-southeast corridor with 318 Beyond the current investment programme, its important regeneration zones including even with the introduction of Crossrail and Harlesden, Paddington, Elephant & Castle and Thameslink proposals, crowding will remain inner southeast London The Bakerloo line on the LU network The Northern line is the upgrade, incorporating new train technology, busiest metro line in Europe with more than will boost capacity and reliability on the 800,000 passengers a day Even with the line, while a longer-term Bakerloo southern Northern line upgrade and other transport extension would allow the line to serve inner investment, it is forecast that by 2031 there and outer southeast London, creating a new will be severe pressure on London’s north-south southeast to northwest strategic route through routes, particularly through the City, resulting the Capital, serving areas with poor transport in congestion levels very similar to that accessibility and freeing up National Rail experienced today A further upgrade of the capacity at London Bridge for other service line can be achieved by recasting the service improvements through the partial separation of the line By Chapter five – Transport proposals
  • 30. 136 Mayor’s Transport Strategy – Public Draft Spotlight on: Northern line Upgrade 2 (service pattern changes) Work has commenced to upgrade the Northern line, with new computerised signalling and a new control centre which will reduce journey times by 18 per cent and increase capacity by around 20 per cent However, even with the upgrade it is forecast that due to growth in demand, there will still be severe pressure on London’s north-south routes, particularly through the City, resulting in crowding levels similar to that experienced today A recast of service patterns to partially separate the two branches of the line would increase capacity and journey times further, delivering an additional 33 per cent capacity on the City branch, and a 17 per cent increase on the Charing Cross Branch For example, on the Charing Cross branch, during the busiest parts of the morning peak, service frequencies could rise from the current 20 trains per hour (tph) to 24 tph following the first upgrade, eventually reaching a potential 28 tph following partial separation The further upgrade would require more rolling stock alongside the existing fleet, as well as additional stabling facilities, power, improved signalling and tunnel cooling Once delivered, it will act as the equivalent of adding a new north-south line across London, helping the Capital keep pace with growth in demand and supporting economic development Chapter five – Transport proposals
  • 31. 137 Spotlight on: Transforming the Tube Over the last decade, the number of journeys made on the Tube have risen to record levels of more than one billion journeys a year To support this growth and correct historic under-funding, LU has embarked on its largest investment programme for 70 years The line upgrades, which will include new signalling and control systems, as well as the introduction of new trains on some lines, will focus on improving reliability They will deliver faster journey times and increase capacity by up to 30 per cent across the network By 2012, this programme will deliver an upgrade of the Jubilee, Victoria and Northern lines, each providing between 20 and 33 per cent more capacity per line into central London By 2020, upgrades will have been completed on the District, Circle, Hammersmith & City and Metropolitan lines (including air-conditioned trains) increasing capacity across the sub-surface network, while the Piccadilly line upgrade will provide a 24 per cent increase in line capacity The Bakerloo line will also be upgraded Other enhancements include: major station improvements at Chapter five Victoria, Paddington (Hammersmith & City), Tottenham Court Road, Bond Street and Bank; cooling; power upgrades to cater for expanded services; and accessibility improvements Chapter five – Transport proposals