Measuring and reporting project metrics
2
Visualize and navigate by geographical location
3
Access P6 Analytics on the go
4
Challenge #3 – Make better use of scarce resources
and deliver to expectations
• Improving the accuracy of schedules and forecasts
• No common method for communicating risk, likelihood and possible impact
clearly to prompt mitigating action and justify proposed spends
Challenge
• Develop & deploy an enterprise risk solution to manage risk and contingency
planning
Solution
5
Project risk management and mitigation strategies
9
Challenge #4 – Poor coordination and tracking of
communication between internal & external parties
• Inefficient work processes, document coordination, and collaboration for
internal and external resources increasing the impact on cost, schedule,
scope and quality of projects and programs
• Thousands of documents, formats, sources…so, insufficient or missing
documentation for claims
Challenge
• Develop standards and repeatable processes for managing programs/projects
• Store documents in a centralized repository with real-time access by all parties
Solution
10
Easily
maintain a
clear,
complete
and search-
able record
for claims
protection
Efficiently manage and control documents
11
Hold internal
and external
team members
accountable
Efficiently manage and control documents
12
Quickly identify
holdups and…
Efficiently manage and control documents
13
impact on
schedule
Quickly identify
holdups and…
Efficiently manage and control documents
14
Challenge #5 - Managing change orders and RFIs
• Governance & rigor for change process
• Slow RFI response times lead to increased cost and possibly project delays
Challenge
• End-to-end change management solution
Solution
15
Managing RFIs electronically
Operate
17
Challenge #1 – Inefficient processes for managing
work orders
• Utilize manual, homegrown systems to schedule work orders and assign
resources …so they don’t optimize resources
Challenge
• Integrate best of breed systems to provide accurate and timely forecasting of
cost, schedule and resources to completion
• Provide one access point for all project and resource information
Solution
18
Optimization through integrated work management
with EAM (Enterprise Asset Mgmt)
19
Import work orders from EAM → sequence them
according to priority and resource availability → send
dates back to EAM
20
One access point for all project information
Sample integration with SAP via Inspire
21
Challenge #2 – Inefficient use of craft labor
• Low craft productivity (Avg is 35%) due to poor planning and utilization
• Difficulty managing emergent (unplanned) work due to lack of enterprise-wide
resource visibility
Challenge
• Visualize leveling resources to optimize utilization
• Optimize resource utilization on the critical path during shutdowns/outages
Solution
22
Visualize resources across all types of work
Capital, Routine/Daily, Shutdown/Turnaround/Outage
23
Optimize resource utilization
Consolidated repository; Powerful, flexible resource analysis
24
Resource leveling to optimize craft productivity
25
Visualize sequence of activities
26
Challenge #3 – Aging workforce
• Knowledge “walking out the door”
• Inability to capture best practices
Challenge
• Deploy a knowledge retention strategy
Solution
27
Use templates to capture best practices of retiring
workforce
• Quickly “ramp up”
new hires
• Drive operational
savings through
standardized project
management
approaches
Oracle eppm for asset intensive industries ppt part 2

Mais conteúdo relacionado

Mais procurados

CE Partners meeting Nrb enos_Swahili version
CE Partners meeting Nrb enos_Swahili versionCE Partners meeting Nrb enos_Swahili version
CE Partners meeting Nrb enos_Swahili versionEnos Omondi
 
Integrated solutions project management
Integrated solutions project managementIntegrated solutions project management
Integrated solutions project managementPatrick Vandenbemd
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Project monitoring activity
Project monitoring activityProject monitoring activity
Project monitoring activityKundan Sanap
 
Project Management Control
Project Management ControlProject Management Control
Project Management Controlahmad bassiouny
 
Benefits long term
Benefits long termBenefits long term
Benefits long termDavid Waller
 
SEAMS: Should I manage the assets or the projects?
SEAMS: Should I manage the assets or the projects?SEAMS: Should I manage the assets or the projects?
SEAMS: Should I manage the assets or the projects?seamsltd
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Agus Suhanto
 
Digitalization of Capital Project Mgmt Fiatech
Digitalization of Capital Project Mgmt FiatechDigitalization of Capital Project Mgmt Fiatech
Digitalization of Capital Project Mgmt FiatechSiemens PLM Software
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceLewisFowlerLLC
 
Bse 3105 lecture 3-software evolution planning
Bse 3105  lecture 3-software evolution planningBse 3105  lecture 3-software evolution planning
Bse 3105 lecture 3-software evolution planningAlonzee Tash
 
Stages of Management Consulting Engagment
Stages of Management Consulting EngagmentStages of Management Consulting Engagment
Stages of Management Consulting EngagmentRoselle Fuentes
 

Mais procurados (20)

CE Partners meeting Nrb enos_Swahili version
CE Partners meeting Nrb enos_Swahili versionCE Partners meeting Nrb enos_Swahili version
CE Partners meeting Nrb enos_Swahili version
 
Transmission Integrity Management
Transmission Integrity ManagementTransmission Integrity Management
Transmission Integrity Management
 
Jean-Luc Ozoux
Jean-Luc OzouxJean-Luc Ozoux
Jean-Luc Ozoux
 
Project managment 6
Project managment 6Project managment 6
Project managment 6
 
Integrated solutions project management
Integrated solutions project managementIntegrated solutions project management
Integrated solutions project management
 
Cost management
Cost managementCost management
Cost management
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Project monitoring activity
Project monitoring activityProject monitoring activity
Project monitoring activity
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
Scope Management
Scope ManagementScope Management
Scope Management
 
Benefits long term
Benefits long termBenefits long term
Benefits long term
 
Flyer ProTrack
Flyer ProTrackFlyer ProTrack
Flyer ProTrack
 
SEAMS: Should I manage the assets or the projects?
SEAMS: Should I manage the assets or the projects?SEAMS: Should I manage the assets or the projects?
SEAMS: Should I manage the assets or the projects?
 
Project Risk Management - PMBOK6
Project Risk Management - PMBOK6Project Risk Management - PMBOK6
Project Risk Management - PMBOK6
 
Digitalization of Capital Project Mgmt Fiatech
Digitalization of Capital Project Mgmt FiatechDigitalization of Capital Project Mgmt Fiatech
Digitalization of Capital Project Mgmt Fiatech
 
What is CEM
What is CEMWhat is CEM
What is CEM
 
Measurement & metrics
Measurement & metricsMeasurement & metrics
Measurement & metrics
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
 
Bse 3105 lecture 3-software evolution planning
Bse 3105  lecture 3-software evolution planningBse 3105  lecture 3-software evolution planning
Bse 3105 lecture 3-software evolution planning
 
Stages of Management Consulting Engagment
Stages of Management Consulting EngagmentStages of Management Consulting Engagment
Stages of Management Consulting Engagment
 

Destaque

Leveraging oracle technology within your contract management environment
Leveraging oracle technology within your contract management environmentLeveraging oracle technology within your contract management environment
Leveraging oracle technology within your contract management environmentp6academy
 
Change management process in pcm
Change management process in pcmChange management process in pcm
Change management process in pcmp6academy
 
Does better scheduling drive execution success ppt
Does better scheduling drive execution success pptDoes better scheduling drive execution success ppt
Does better scheduling drive execution success pptp6academy
 
Program management at an electric utility
Program management at an electric utilityProgram management at an electric utility
Program management at an electric utilityp6academy
 
Primavera p6 r8 in a complex healthcare environment ppt
Primavera p6 r8 in a complex healthcare environment pptPrimavera p6 r8 in a complex healthcare environment ppt
Primavera p6 r8 in a complex healthcare environment pptp6academy
 
Contractor updates at the new york school construction authority ppt
Contractor updates at the new york school construction authority pptContractor updates at the new york school construction authority ppt
Contractor updates at the new york school construction authority pptp6academy
 
Projects controls on a 900 project substation network upgrade ppt
Projects controls on a 900 project substation network upgrade pptProjects controls on a 900 project substation network upgrade ppt
Projects controls on a 900 project substation network upgrade pptp6academy
 
Primavera integration possibilities technical overview ppt
Primavera integration possibilities   technical overview pptPrimavera integration possibilities   technical overview ppt
Primavera integration possibilities technical overview pptp6academy
 
Project management modernization why and how western moved from spreadsheet...
Project management modernization   why and how western moved from spreadsheet...Project management modernization   why and how western moved from spreadsheet...
Project management modernization why and how western moved from spreadsheet...p6academy
 
You were not hired to be a fireman keep fires from starting with primavera ppt
You were not hired to be a fireman   keep fires from starting with primavera pptYou were not hired to be a fireman   keep fires from starting with primavera ppt
You were not hired to be a fireman keep fires from starting with primavera pptp6academy
 
Cm cost management
Cm cost managementCm cost management
Cm cost managementp6academy
 
Project management through the use of oracle products
Project management through the use of oracle productsProject management through the use of oracle products
Project management through the use of oracle productsp6academy
 
Increase your resource capacity without hiring ppt
Increase your resource capacity without hiring pptIncrease your resource capacity without hiring ppt
Increase your resource capacity without hiring pptp6academy
 
Managing the p6 schedule from the perspective of an owner ppt
Managing the p6 schedule from the perspective of an owner pptManaging the p6 schedule from the perspective of an owner ppt
Managing the p6 schedule from the perspective of an owner pptp6academy
 
Managing light rail at light speed ppt
Managing light rail at light speed pptManaging light rail at light speed ppt
Managing light rail at light speed pptp6academy
 
Implementation demystification 10 keys to a successful p6 implementation ppt
Implementation demystification   10 keys to a successful p6 implementation pptImplementation demystification   10 keys to a successful p6 implementation ppt
Implementation demystification 10 keys to a successful p6 implementation pptp6academy
 
How do you manage a multi agency 1.8 billion rail bridge design and construct...
How do you manage a multi agency 1.8 billion rail bridge design and construct...How do you manage a multi agency 1.8 billion rail bridge design and construct...
How do you manage a multi agency 1.8 billion rail bridge design and construct...p6academy
 
Introduction to P6 Analytics 2.0
Introduction to P6 Analytics 2.0Introduction to P6 Analytics 2.0
Introduction to P6 Analytics 2.0p6academy
 
Whole enterprise integration with primavera and business process mgmt ppt
Whole enterprise integration with primavera and business process mgmt pptWhole enterprise integration with primavera and business process mgmt ppt
Whole enterprise integration with primavera and business process mgmt pptp6academy
 
Data flow between p6 and cm ppt
Data flow between p6 and cm pptData flow between p6 and cm ppt
Data flow between p6 and cm pptp6academy
 

Destaque (20)

Leveraging oracle technology within your contract management environment
Leveraging oracle technology within your contract management environmentLeveraging oracle technology within your contract management environment
Leveraging oracle technology within your contract management environment
 
Change management process in pcm
Change management process in pcmChange management process in pcm
Change management process in pcm
 
Does better scheduling drive execution success ppt
Does better scheduling drive execution success pptDoes better scheduling drive execution success ppt
Does better scheduling drive execution success ppt
 
Program management at an electric utility
Program management at an electric utilityProgram management at an electric utility
Program management at an electric utility
 
Primavera p6 r8 in a complex healthcare environment ppt
Primavera p6 r8 in a complex healthcare environment pptPrimavera p6 r8 in a complex healthcare environment ppt
Primavera p6 r8 in a complex healthcare environment ppt
 
Contractor updates at the new york school construction authority ppt
Contractor updates at the new york school construction authority pptContractor updates at the new york school construction authority ppt
Contractor updates at the new york school construction authority ppt
 
Projects controls on a 900 project substation network upgrade ppt
Projects controls on a 900 project substation network upgrade pptProjects controls on a 900 project substation network upgrade ppt
Projects controls on a 900 project substation network upgrade ppt
 
Primavera integration possibilities technical overview ppt
Primavera integration possibilities   technical overview pptPrimavera integration possibilities   technical overview ppt
Primavera integration possibilities technical overview ppt
 
Project management modernization why and how western moved from spreadsheet...
Project management modernization   why and how western moved from spreadsheet...Project management modernization   why and how western moved from spreadsheet...
Project management modernization why and how western moved from spreadsheet...
 
You were not hired to be a fireman keep fires from starting with primavera ppt
You were not hired to be a fireman   keep fires from starting with primavera pptYou were not hired to be a fireman   keep fires from starting with primavera ppt
You were not hired to be a fireman keep fires from starting with primavera ppt
 
Cm cost management
Cm cost managementCm cost management
Cm cost management
 
Project management through the use of oracle products
Project management through the use of oracle productsProject management through the use of oracle products
Project management through the use of oracle products
 
Increase your resource capacity without hiring ppt
Increase your resource capacity without hiring pptIncrease your resource capacity without hiring ppt
Increase your resource capacity without hiring ppt
 
Managing the p6 schedule from the perspective of an owner ppt
Managing the p6 schedule from the perspective of an owner pptManaging the p6 schedule from the perspective of an owner ppt
Managing the p6 schedule from the perspective of an owner ppt
 
Managing light rail at light speed ppt
Managing light rail at light speed pptManaging light rail at light speed ppt
Managing light rail at light speed ppt
 
Implementation demystification 10 keys to a successful p6 implementation ppt
Implementation demystification   10 keys to a successful p6 implementation pptImplementation demystification   10 keys to a successful p6 implementation ppt
Implementation demystification 10 keys to a successful p6 implementation ppt
 
How do you manage a multi agency 1.8 billion rail bridge design and construct...
How do you manage a multi agency 1.8 billion rail bridge design and construct...How do you manage a multi agency 1.8 billion rail bridge design and construct...
How do you manage a multi agency 1.8 billion rail bridge design and construct...
 
Introduction to P6 Analytics 2.0
Introduction to P6 Analytics 2.0Introduction to P6 Analytics 2.0
Introduction to P6 Analytics 2.0
 
Whole enterprise integration with primavera and business process mgmt ppt
Whole enterprise integration with primavera and business process mgmt pptWhole enterprise integration with primavera and business process mgmt ppt
Whole enterprise integration with primavera and business process mgmt ppt
 
Data flow between p6 and cm ppt
Data flow between p6 and cm pptData flow between p6 and cm ppt
Data flow between p6 and cm ppt
 

Semelhante a Oracle eppm for asset intensive industries ppt part 2

Maintenance-Planning-and-Scheduling-Overview.pptx
Maintenance-Planning-and-Scheduling-Overview.pptxMaintenance-Planning-and-Scheduling-Overview.pptx
Maintenance-Planning-and-Scheduling-Overview.pptxTun Lin Oo
 
Project: Monitoring
Project: Monitoring Project: Monitoring
Project: Monitoring Mfb Firoz
 
Oracle eppm for asset intensive industries ppt part 1
Oracle eppm for asset intensive industries ppt part 1Oracle eppm for asset intensive industries ppt part 1
Oracle eppm for asset intensive industries ppt part 1p6academy
 
Why Project Management with Primavera?
Why Project Management with Primavera?Why Project Management with Primavera?
Why Project Management with Primavera?Abhi Kalyan
 
Lean Product Development
Lean Product DevelopmentLean Product Development
Lean Product DevelopmentTim McMahon
 
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...Evergreen Systems
 
Beyond Automation: Extracting Actionable Intelligence from Clinical Trials
Beyond Automation: Extracting Actionable Intelligence from Clinical TrialsBeyond Automation: Extracting Actionable Intelligence from Clinical Trials
Beyond Automation: Extracting Actionable Intelligence from Clinical TrialsMontrium
 
Introduction to ict project management
Introduction to ict project managementIntroduction to ict project management
Introduction to ict project managementmanproy
 
Just Say No to Spreadsheets: A Practical Approach to Automating Capacity Mana...
Just Say No to Spreadsheets: A Practical Approach to Automating Capacity Mana...Just Say No to Spreadsheets: A Practical Approach to Automating Capacity Mana...
Just Say No to Spreadsheets: A Practical Approach to Automating Capacity Mana...Precisely
 
Carins M - V1Resume
Carins M - V1ResumeCarins M - V1Resume
Carins M - V1ResumeMarco Carins
 
Towards a hybrid approach between agile and traditional methods
Towards a hybrid approach between agile and traditional methodsTowards a hybrid approach between agile and traditional methods
Towards a hybrid approach between agile and traditional methodsRachid Meziani, PhD, CGEIT, PMP
 
Project management communication
Project management communicationProject management communication
Project management communicationlaksha vijayaratnam
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 

Semelhante a Oracle eppm for asset intensive industries ppt part 2 (20)

Maintenance-Planning-and-Scheduling-Overview.pptx
Maintenance-Planning-and-Scheduling-Overview.pptxMaintenance-Planning-and-Scheduling-Overview.pptx
Maintenance-Planning-and-Scheduling-Overview.pptx
 
Project: Monitoring
Project: Monitoring Project: Monitoring
Project: Monitoring
 
Oracle eppm for asset intensive industries ppt part 1
Oracle eppm for asset intensive industries ppt part 1Oracle eppm for asset intensive industries ppt part 1
Oracle eppm for asset intensive industries ppt part 1
 
Why Project Management with Primavera?
Why Project Management with Primavera?Why Project Management with Primavera?
Why Project Management with Primavera?
 
Lean Product Development
Lean Product DevelopmentLean Product Development
Lean Product Development
 
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
 
Beyond Automation: Extracting Actionable Intelligence from Clinical Trials
Beyond Automation: Extracting Actionable Intelligence from Clinical TrialsBeyond Automation: Extracting Actionable Intelligence from Clinical Trials
Beyond Automation: Extracting Actionable Intelligence from Clinical Trials
 
Proj mgmt and scm
Proj mgmt and scmProj mgmt and scm
Proj mgmt and scm
 
Introduction to ict project management
Introduction to ict project managementIntroduction to ict project management
Introduction to ict project management
 
PM LnL
PM LnLPM LnL
PM LnL
 
Lesson2.pptx
Lesson2.pptxLesson2.pptx
Lesson2.pptx
 
Just Say No to Spreadsheets: A Practical Approach to Automating Capacity Mana...
Just Say No to Spreadsheets: A Practical Approach to Automating Capacity Mana...Just Say No to Spreadsheets: A Practical Approach to Automating Capacity Mana...
Just Say No to Spreadsheets: A Practical Approach to Automating Capacity Mana...
 
Carins M - V1Resume
Carins M - V1ResumeCarins M - V1Resume
Carins M - V1Resume
 
Towards a hybrid approach between agile and traditional methods
Towards a hybrid approach between agile and traditional methodsTowards a hybrid approach between agile and traditional methods
Towards a hybrid approach between agile and traditional methods
 
Project management communication
Project management communicationProject management communication
Project management communication
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Planning and monitoring work section 22
Planning and monitoring work section 22Planning and monitoring work section 22
Planning and monitoring work section 22
 
IFPRI - Results and Impact Management System (RIMS)
IFPRI - Results and Impact Management System (RIMS)IFPRI - Results and Impact Management System (RIMS)
IFPRI - Results and Impact Management System (RIMS)
 
Shruti ppt
Shruti pptShruti ppt
Shruti ppt
 

Mais de p6academy

Oracle OpenWorld 2015
Oracle OpenWorld 2015Oracle OpenWorld 2015
Oracle OpenWorld 2015p6academy
 
Plan and Execute the Right Projects— Easily and Affordably
Plan and Execute the Right Projects—  Easily and AffordablyPlan and Execute the Right Projects—  Easily and Affordably
Plan and Execute the Right Projects— Easily and Affordablyp6academy
 
What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1p6academy
 
Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2p6academy
 
Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2p6academy
 
What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1p6academy
 
What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1p6academy
 
What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1p6academy
 
What's New in Unifier 16.1
What's New in Unifier 16.1What's New in Unifier 16.1
What's New in Unifier 16.1p6academy
 
20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktopp6academy
 
Oracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 AnnouncedOracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 Announcedp6academy
 
Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1p6academy
 
P6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations OverviewP6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations Overviewp6academy
 
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM  (Web) Release 8 and laterAdministering Users, Access and Views in P6 EPPM  (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and laterp6academy
 
P6 Release 8 Installation Orientation
P6 Release 8 Installation OrientationP6 Release 8 Installation Orientation
P6 Release 8 Installation Orientationp6academy
 
Oracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value PropositionOracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value Propositionp6academy
 
Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition p6academy
 
Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)p6academy
 
Oracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study GuideOracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study Guidep6academy
 
Oracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study GuideOracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study Guidep6academy
 

Mais de p6academy (20)

Oracle OpenWorld 2015
Oracle OpenWorld 2015Oracle OpenWorld 2015
Oracle OpenWorld 2015
 
Plan and Execute the Right Projects— Easily and Affordably
Plan and Execute the Right Projects—  Easily and AffordablyPlan and Execute the Right Projects—  Easily and Affordably
Plan and Execute the Right Projects— Easily and Affordably
 
What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1What's New In Primavera P6 EPPM 17.1
What's New In Primavera P6 EPPM 17.1
 
Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2Oracle Primavera Unifier What's New in Release 16.2
Oracle Primavera Unifier What's New in Release 16.2
 
Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2Oracle What's New In Primavera P6 16.2
Oracle What's New In Primavera P6 16.2
 
What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1What's New in Primavera Prime 16.1
What's New in Primavera Prime 16.1
 
What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1What's New in Primavera Gateway 16.1
What's New in Primavera Gateway 16.1
 
What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1What's New In Primavera Analytics 16.1
What's New In Primavera Analytics 16.1
 
What's New in Unifier 16.1
What's New in Unifier 16.1What's New in Unifier 16.1
What's New in Unifier 16.1
 
20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop20160405 How to Install Primavera P6 16.1 Professional desktop
20160405 How to Install Primavera P6 16.1 Professional desktop
 
Oracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 AnnouncedOracle Primavera P6 16.1 Announced
Oracle Primavera P6 16.1 Announced
 
Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1Oracle Primavera Unifier 16.1
Oracle Primavera Unifier 16.1
 
P6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations OverviewP6 Release 8 Application Considerations Overview
P6 Release 8 Application Considerations Overview
 
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM  (Web) Release 8 and laterAdministering Users, Access and Views in P6 EPPM  (Web) Release 8 and later
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
 
P6 Release 8 Installation Orientation
P6 Release 8 Installation OrientationP6 Release 8 Installation Orientation
P6 Release 8 Installation Orientation
 
Oracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value PropositionOracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 R8 Release Value Proposition
 
Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition
 
Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)Oracle Primavera P6 Release Content Document (RCD)
Oracle Primavera P6 Release Content Document (RCD)
 
Oracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study GuideOracle Support Accreditation – Level 1 Study Guide
Oracle Support Accreditation – Level 1 Study Guide
 
Oracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study GuideOracle Primavera Support Accreditation Study Guide
Oracle Primavera Support Accreditation Study Guide
 

Oracle eppm for asset intensive industries ppt part 2

  • 1. 1 Measuring and reporting project metrics
  • 2. 2 Visualize and navigate by geographical location
  • 4. 4 Challenge #3 – Make better use of scarce resources and deliver to expectations • Improving the accuracy of schedules and forecasts • No common method for communicating risk, likelihood and possible impact clearly to prompt mitigating action and justify proposed spends Challenge • Develop & deploy an enterprise risk solution to manage risk and contingency planning Solution
  • 5. 5 Project risk management and mitigation strategies
  • 6. 9 Challenge #4 – Poor coordination and tracking of communication between internal & external parties • Inefficient work processes, document coordination, and collaboration for internal and external resources increasing the impact on cost, schedule, scope and quality of projects and programs • Thousands of documents, formats, sources…so, insufficient or missing documentation for claims Challenge • Develop standards and repeatable processes for managing programs/projects • Store documents in a centralized repository with real-time access by all parties Solution
  • 7. 10 Easily maintain a clear, complete and search- able record for claims protection Efficiently manage and control documents
  • 8. 11 Hold internal and external team members accountable Efficiently manage and control documents
  • 9. 12 Quickly identify holdups and… Efficiently manage and control documents
  • 10. 13 impact on schedule Quickly identify holdups and… Efficiently manage and control documents
  • 11. 14 Challenge #5 - Managing change orders and RFIs • Governance & rigor for change process • Slow RFI response times lead to increased cost and possibly project delays Challenge • End-to-end change management solution Solution
  • 14. 17 Challenge #1 – Inefficient processes for managing work orders • Utilize manual, homegrown systems to schedule work orders and assign resources …so they don’t optimize resources Challenge • Integrate best of breed systems to provide accurate and timely forecasting of cost, schedule and resources to completion • Provide one access point for all project and resource information Solution
  • 15. 18 Optimization through integrated work management with EAM (Enterprise Asset Mgmt)
  • 16. 19 Import work orders from EAM → sequence them according to priority and resource availability → send dates back to EAM
  • 17. 20 One access point for all project information Sample integration with SAP via Inspire
  • 18. 21 Challenge #2 – Inefficient use of craft labor • Low craft productivity (Avg is 35%) due to poor planning and utilization • Difficulty managing emergent (unplanned) work due to lack of enterprise-wide resource visibility Challenge • Visualize leveling resources to optimize utilization • Optimize resource utilization on the critical path during shutdowns/outages Solution
  • 19. 22 Visualize resources across all types of work Capital, Routine/Daily, Shutdown/Turnaround/Outage
  • 20. 23 Optimize resource utilization Consolidated repository; Powerful, flexible resource analysis
  • 21. 24 Resource leveling to optimize craft productivity
  • 23. 26 Challenge #3 – Aging workforce • Knowledge “walking out the door” • Inability to capture best practices Challenge • Deploy a knowledge retention strategy Solution
  • 24. 27 Use templates to capture best practices of retiring workforce • Quickly “ramp up” new hires • Drive operational savings through standardized project management approaches