Sample Balanced Scorecard for
Project Management
Key Performance Indicator Target Remarks Why it is important
Time Management Perspective
Leading Indicators
Expected Schedule Performance Index for
Critical Path (EX SPICP)
>1
Value of worked planned in Critical Path to be completed in Next
Month /
Value of Planned worked in Critical Path to be completed in Next
Month as per the baseline
Monitor the planned performance on the
critical path for coming month. If the Value is
below the targeted, it means project is going
to be delayed in next month.
Number of Changes in Schedule
<3
This can be monitored from the revisions with the project schedule
and benchmarking figure to be decided as per the company past
performance.
This highlights accuracy of the project
baseline / how often baseline get changed.
Tasks Completed Delayed Planned
Duration
<10% Duration of Tasks Delayed / Duration of Total Tasks Completed
Potential variation of Scheduled duration.
Pending Works Slack Ratio >1
Total Slack for pending works at Last Month / Total Slack for Pending
Works as per Project Baseline
This indicates if the project critical path is
going to change because reduction in slack
shows noncritical activities getting delayed.
Lagging Indicators
Past Schedule Performance Index for
Critical Path (P SPICP)
>1
Value of work in Critical Path Executed in Last Month / Value of
Planned worked in Critical Path in Last Month as per the baseline
This shows that how much results were
achieved in critical path against plan, how
critical path is time goals are achieving against
time plan.
Schedule Performance Index >1 Earned Value of Works Completed/ Planned Value of Works
Completed
How generally project is achieved time goals
Duration to Complete Ratio <1
Critical path Works Required Duration / Available duration to
Handover.
To show that project is moving toward to
completion date and duration available for
longest work path.
TBD : To be decided by the PM
Key Performance Indicator Target Remarks Why it is important
Cost Management Perspective
Leading Indicators
Billing Efficiency =1 Cost Value of Bills Raised / Value of Works Done To receive the cash, bills need to be raised
Cash Flow Index =1 Total Funds Received /Total Value of Bills raised To manage the cash flow into the project
Estimating Accuracy <1 (Actual Cost – Reworks)/Estimated Cost for works Done To see the how accurate the estimations are
and how much additional cost may occur.
Safety Cost Index TBD Safety Expenditure in Last Month/ Total Budgeted amount for Safety
activities in Last Month
To make sure constant focus is maintained
for safety and
Quality Cost Index TBD (Expenditure for Quality works in Last Month – Reworks cost in last
Month)/ Total budgeted amount for Quality management
Continuous Quality Improvement is done
Lagging Indicators
Cost Performance Index >1 Actual Value of Works Done/Earned Value from Work done To see the overall financial health of the
project
Expected Project Closing Cost TBD (Actual Cost) *(1+ (Total Budgeted Value-Earned Value of Done) /
Earned Value of Work Done
If the trend continues. Target to be defined.
Next Month Cash Flow >1 (Allocated Cash Reserve for the Project+ Payment receivable in coming
two Month)/ Value of Work to be done in Coming Three Months.
Expected Reworks Cost TBD (Reworks Cost/Estimated Value of works done) * Total Value of the
Project
Figures to be decided for milestones.
Variations ratio 1 Value of variations done / Value of work done in Changes Approved To monitor variations are billed and added
and done properly.
Key Performance Indicator Target Remarks Why it is important
Scope Management Perspective
Leading Indicators
Admin & Skilled Staff Ratio =1 = Actual available Skilled Staff for Last Month Works Estimated / Total
requirement of Skilled Staff for Last Month Works
To make sure fewer quality issues
raised and less reworks are done.
Problem Solving Efficiency =1 = Concerned solve at Last Meeting/Concerns was to be solve at Last Month
Meetings
progress works without delays by
solving problems are prioritizing.
Risk Register Duration <1 = Workdays from Last Risk Register reviewed / 20 Make sure monthly risk register is
reviewed and updated.
Scope Update =1 = Latest Work Breakdown Structure Number / Latest Approved Change Number This indicates how project scope
management documents are updated.
Milestones reviewed meetings =1 =Number of Milestone Meetings held/ (Millstone passed +1)
Milestone Meeting
When a new milestone is ended the team is gathered and meeting is held. This is to ensure team
members are aware of their role in the next milestone, risks ahead and what mistakes they made in last
milestone to perform well.
Make sure everyone in the team is
aware about the scope of works.
Lagging Indicators
Reworks Percentage TBD =Value of Reworks done/ Value of Total Works Done Identify the how much reworks are
done.
Clients Feedback in Last Milestones TBD = 1 – 5 rating from a surveyor Identify how smooth works are
progressing in client’s prospective.
Variation Requested TBD =value of variations approved / value of variations requested
Key Performance Indicator Target Remarks Why it is important
Change Management Perspective
Leading Indicators
Change Acceptance Ratio 1 = Changes Approved / Changes Requested To identify the how well change request
process is progressing and how efficient is it.
Average Change Request Pending time TBD = Total Duration for the change requesting pending/ Number of Change
Requests pending
To see how long it takes to get a respond for
a change by Change Advisory Board
Number of Emergency Changes Increment ratio <1 =Urgent Changes Raised This Month/ Urgent Changes Raised Last Month How number of urgent changes are
increasing.
Change Approval Awareness 1 =Number of changes Awareness Memos or meeting /Number of Changes
Approved
How many changes have been informed to
the team Leaders, and receives their
feedback?
Lagging Indicators
Change Request Ratio TBD =Value of Change Request / Total Project Value This is highlight what is the scale of the
changes happening compares to the project
operation.
Pending Urgent Changes TBD =Number of Urgent Changes raised – Number of Urgent Changes Solved To see whether how many urgent change
requests are pending a decision.
Delayed Change Requests TBD =Delayed Change Requests / Total Change Requests To see how often feedback for the changes
are getting delayed.
Loss of Value of Poor Change Management TBD Loss of Value due to Delayed Responds to Changes and Reworks/ Total Project
Value
To see how much value loss is due to weak
change management.
Pending Changes Request TBD Total Changes requested -Total Changes Commented Pending changes Requested to be

Mais conteúdo relacionado

Mais procurados

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Kateri Manglicmot
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
BhuWan Khadka
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
Vladimir Vujovic
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Hayat Denzi
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
BECM, RUET, Bangladesh
 
Monitoring the control
Monitoring the control Monitoring the control
Monitoring the control
north south university
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
Akash Prasanna
 
Project cost management
Project cost managementProject cost management
Project cost management
Mohammad Ashraf Khan, PMP
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plantabhishekthakur309
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
Mohamed Salah Eldien Mohamed Ali
 
Project Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesProject Monitoring and Controlling Processes
Project Monitoring and Controlling Processes
Nishant Munjal
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
Joshua Render
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on scheduling
Gunjan Lal
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementOleksandr Lutsaievskyi
 
Building Commissioing Rev Feb 21
Building Commissioing Rev Feb 21Building Commissioing Rev Feb 21
Building Commissioing Rev Feb 21
jsgibby
 
Cert iv cost part 2
Cert iv  cost part 2Cert iv  cost part 2
Cert iv cost part 2Skript
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
Karin Rheeder
 

Mais procurados (20)

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Monitoring the control
Monitoring the control Monitoring the control
Monitoring the control
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plant
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Project Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesProject Monitoring and Controlling Processes
Project Monitoring and Controlling Processes
 
Project Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge AreaProject Management: Project Schedule Management Knowledge Area
Project Management: Project Schedule Management Knowledge Area
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Presentation on scheduling
Presentation on schedulingPresentation on scheduling
Presentation on scheduling
 
PMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost ManagementPMBoK, discussion #5: Project Cost Management
PMBoK, discussion #5: Project Cost Management
 
Building Commissioing Rev Feb 21
Building Commissioing Rev Feb 21Building Commissioing Rev Feb 21
Building Commissioing Rev Feb 21
 
Cert iv cost part 2
Cert iv  cost part 2Cert iv  cost part 2
Cert iv cost part 2
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 

Semelhante a Sample balanced score card for project management

Project Proposal (final paperpresentation) last week of class. On.docx
Project Proposal (final paperpresentation) last week of class. On.docxProject Proposal (final paperpresentation) last week of class. On.docx
Project Proposal (final paperpresentation) last week of class. On.docx
bfingarjcmc
 
Aiesec vietnam national award
Aiesec vietnam national awardAiesec vietnam national award
Aiesec vietnam national award
samsoonkum
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
Daniel Brody
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
Waleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
waleed hamdy
 
Final Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptFinal Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.ppt
GeorgeKabongah2
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
VarunSubramanyam
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
Yogesh Singh
 
Cost management-plan template
Cost management-plan templateCost management-plan template
Cost management-plan template
Vivek Srivastava
 
Mar 2012 cdphe contractor performance monitoring trng
Mar 2012 cdphe contractor performance monitoring trngMar 2012 cdphe contractor performance monitoring trng
Mar 2012 cdphe contractor performance monitoring trngBrandon Williams
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Cost unit 2012 part 2
Cost unit 2012   part 2Cost unit 2012   part 2
Cost unit 2012 part 2Skript
 
Testing Junior Management Course v2
Testing Junior Management Course v2Testing Junior Management Course v2
Testing Junior Management Course v2sharon elgarat
 
Project management basics
Project management basicsProject management basics
Project management basics
Adewale Alafia
 
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh MahasnehTop Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars
 
UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
Raja Manyam
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdf
apoorvaguptaspn27
 
CV for Dave Lavender 11-2015(v6.0)
CV for Dave Lavender 11-2015(v6.0)CV for Dave Lavender 11-2015(v6.0)
CV for Dave Lavender 11-2015(v6.0)Dave Lavender
 

Semelhante a Sample balanced score card for project management (20)

6 pom kc controlling
6 pom kc controlling6 pom kc controlling
6 pom kc controlling
 
Project Proposal (final paperpresentation) last week of class. On.docx
Project Proposal (final paperpresentation) last week of class. On.docxProject Proposal (final paperpresentation) last week of class. On.docx
Project Proposal (final paperpresentation) last week of class. On.docx
 
Aiesec vietnam national award
Aiesec vietnam national awardAiesec vietnam national award
Aiesec vietnam national award
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Final Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.pptFinal Class Presentation on Project Audit and Closure.ppt
Final Class Presentation on Project Audit and Closure.ppt
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Cost management-plan template
Cost management-plan templateCost management-plan template
Cost management-plan template
 
Mar 2012 cdphe contractor performance monitoring trng
Mar 2012 cdphe contractor performance monitoring trngMar 2012 cdphe contractor performance monitoring trng
Mar 2012 cdphe contractor performance monitoring trng
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Cost unit 2012 part 2
Cost unit 2012   part 2Cost unit 2012   part 2
Cost unit 2012 part 2
 
Testing Junior Management Course v2
Testing Junior Management Course v2Testing Junior Management Course v2
Testing Junior Management Course v2
 
Project management basics
Project management basicsProject management basics
Project management basics
 
Top Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh MahasnehTop Pillars | Cost & Time Management by Salameh Mahasneh
Top Pillars | Cost & Time Management by Salameh Mahasneh
 
UNIT-3.pptx
UNIT-3.pptxUNIT-3.pptx
UNIT-3.pptx
 
Project Management Presentation Template.pdf
Project Management Presentation Template.pdfProject Management Presentation Template.pdf
Project Management Presentation Template.pdf
 
CV for Dave Lavender 11-2015(v6.0)
CV for Dave Lavender 11-2015(v6.0)CV for Dave Lavender 11-2015(v6.0)
CV for Dave Lavender 11-2015(v6.0)
 

Último

一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
gcljeuzdu
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
Muhammad Adil Jamil
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
strikingabalance
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
Pinta Partners
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
juniourjohnstone
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
EUS+ Management & Consulting Excellence
 
Protected Workmen required today for growth
Protected Workmen required today for growthProtected Workmen required today for growth
Protected Workmen required today for growth
rivaraj2711
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
tdt5v4b
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
Rob Healy
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
Alexey Krivitsky
 
Employment Practices Regulation and Multinational Corporations
Employment PracticesRegulation and Multinational CorporationsEmployment PracticesRegulation and Multinational Corporations
Employment Practices Regulation and Multinational Corporations
RoopaTemkar
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
akaash13
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
William (Bill) H. Bender, FCSI
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
Matthew Sinclair
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
tdt5v4b
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
tdt5v4b
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
Jim Smith
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
bernanbumatay1
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
tdt5v4b
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
William (Bill) H. Bender, FCSI
 

Último (20)

一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
一比一原版杜克大学毕业证(Duke毕业证)成绩单留信认证
 
Leadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact PlanLeadership Ethics and Change, Purpose to Impact Plan
Leadership Ethics and Change, Purpose to Impact Plan
 
Enriching engagement with ethical review processes
Enriching engagement with ethical review processesEnriching engagement with ethical review processes
Enriching engagement with ethical review processes
 
Public Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdfPublic Speaking Tips to Help You Be A Strong Leader.pdf
Public Speaking Tips to Help You Be A Strong Leader.pdf
 
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
SOCIO-ANTHROPOLOGY FACULTY OF NURSING.....
 
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish GermanCV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
CV Ensio Suopanki1.pdf ENGLISH Russian Finnish German
 
Protected Workmen required today for growth
Protected Workmen required today for growthProtected Workmen required today for growth
Protected Workmen required today for growth
 
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
原版制作(CDU毕业证书)查尔斯达尔文大学毕业证PDF成绩单一模一样
 
Comparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile SystemsComparing Stability and Sustainability in Agile Systems
Comparing Stability and Sustainability in Agile Systems
 
Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™Strategic Org Design with Org Topologies™
Strategic Org Design with Org Topologies™
 
Employment Practices Regulation and Multinational Corporations
Employment PracticesRegulation and Multinational CorporationsEmployment PracticesRegulation and Multinational Corporations
Employment Practices Regulation and Multinational Corporations
 
Training- integrated management system (iso)
Training- integrated management system (iso)Training- integrated management system (iso)
Training- integrated management system (iso)
 
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
W.H.Bender Quote 66 - ServPoints Sequence of Service™ should be Identified fo...
 
20240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 202420240608 QFM019 Engineering Leadership Reading List May 2024
20240608 QFM019 Engineering Leadership Reading List May 2024
 
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
在线办理(Murdoch毕业证书)莫道克大学毕业证电子版成绩单一模一样
 
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
在线办理(UVic毕业证书)维多利亚大学毕业证录取通知书一模一样
 
Senior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdfSenior Project and Engineering Leader Jim Smith.pdf
Senior Project and Engineering Leader Jim Smith.pdf
 
Risk-Management-presentation for cooperatives
Risk-Management-presentation for cooperativesRisk-Management-presentation for cooperatives
Risk-Management-presentation for cooperatives
 
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
原版制作(澳洲WSU毕业证书)西悉尼大学毕业证文凭证书一模一样
 
W.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest ExperienceW.H.Bender Quote 65 - The Team Member and Guest Experience
W.H.Bender Quote 65 - The Team Member and Guest Experience
 

Sample balanced score card for project management

  • 1. Sample Balanced Scorecard for Project Management
  • 2. Key Performance Indicator Target Remarks Why it is important Time Management Perspective Leading Indicators Expected Schedule Performance Index for Critical Path (EX SPICP) >1 Value of worked planned in Critical Path to be completed in Next Month / Value of Planned worked in Critical Path to be completed in Next Month as per the baseline Monitor the planned performance on the critical path for coming month. If the Value is below the targeted, it means project is going to be delayed in next month. Number of Changes in Schedule <3 This can be monitored from the revisions with the project schedule and benchmarking figure to be decided as per the company past performance. This highlights accuracy of the project baseline / how often baseline get changed. Tasks Completed Delayed Planned Duration <10% Duration of Tasks Delayed / Duration of Total Tasks Completed Potential variation of Scheduled duration. Pending Works Slack Ratio >1 Total Slack for pending works at Last Month / Total Slack for Pending Works as per Project Baseline This indicates if the project critical path is going to change because reduction in slack shows noncritical activities getting delayed. Lagging Indicators Past Schedule Performance Index for Critical Path (P SPICP) >1 Value of work in Critical Path Executed in Last Month / Value of Planned worked in Critical Path in Last Month as per the baseline This shows that how much results were achieved in critical path against plan, how critical path is time goals are achieving against time plan. Schedule Performance Index >1 Earned Value of Works Completed/ Planned Value of Works Completed How generally project is achieved time goals Duration to Complete Ratio <1 Critical path Works Required Duration / Available duration to Handover. To show that project is moving toward to completion date and duration available for longest work path. TBD : To be decided by the PM
  • 3. Key Performance Indicator Target Remarks Why it is important Cost Management Perspective Leading Indicators Billing Efficiency =1 Cost Value of Bills Raised / Value of Works Done To receive the cash, bills need to be raised Cash Flow Index =1 Total Funds Received /Total Value of Bills raised To manage the cash flow into the project Estimating Accuracy <1 (Actual Cost – Reworks)/Estimated Cost for works Done To see the how accurate the estimations are and how much additional cost may occur. Safety Cost Index TBD Safety Expenditure in Last Month/ Total Budgeted amount for Safety activities in Last Month To make sure constant focus is maintained for safety and Quality Cost Index TBD (Expenditure for Quality works in Last Month – Reworks cost in last Month)/ Total budgeted amount for Quality management Continuous Quality Improvement is done Lagging Indicators Cost Performance Index >1 Actual Value of Works Done/Earned Value from Work done To see the overall financial health of the project Expected Project Closing Cost TBD (Actual Cost) *(1+ (Total Budgeted Value-Earned Value of Done) / Earned Value of Work Done If the trend continues. Target to be defined. Next Month Cash Flow >1 (Allocated Cash Reserve for the Project+ Payment receivable in coming two Month)/ Value of Work to be done in Coming Three Months. Expected Reworks Cost TBD (Reworks Cost/Estimated Value of works done) * Total Value of the Project Figures to be decided for milestones. Variations ratio 1 Value of variations done / Value of work done in Changes Approved To monitor variations are billed and added and done properly.
  • 4. Key Performance Indicator Target Remarks Why it is important Scope Management Perspective Leading Indicators Admin & Skilled Staff Ratio =1 = Actual available Skilled Staff for Last Month Works Estimated / Total requirement of Skilled Staff for Last Month Works To make sure fewer quality issues raised and less reworks are done. Problem Solving Efficiency =1 = Concerned solve at Last Meeting/Concerns was to be solve at Last Month Meetings progress works without delays by solving problems are prioritizing. Risk Register Duration <1 = Workdays from Last Risk Register reviewed / 20 Make sure monthly risk register is reviewed and updated. Scope Update =1 = Latest Work Breakdown Structure Number / Latest Approved Change Number This indicates how project scope management documents are updated. Milestones reviewed meetings =1 =Number of Milestone Meetings held/ (Millstone passed +1) Milestone Meeting When a new milestone is ended the team is gathered and meeting is held. This is to ensure team members are aware of their role in the next milestone, risks ahead and what mistakes they made in last milestone to perform well. Make sure everyone in the team is aware about the scope of works. Lagging Indicators Reworks Percentage TBD =Value of Reworks done/ Value of Total Works Done Identify the how much reworks are done. Clients Feedback in Last Milestones TBD = 1 – 5 rating from a surveyor Identify how smooth works are progressing in client’s prospective. Variation Requested TBD =value of variations approved / value of variations requested
  • 5. Key Performance Indicator Target Remarks Why it is important Change Management Perspective Leading Indicators Change Acceptance Ratio 1 = Changes Approved / Changes Requested To identify the how well change request process is progressing and how efficient is it. Average Change Request Pending time TBD = Total Duration for the change requesting pending/ Number of Change Requests pending To see how long it takes to get a respond for a change by Change Advisory Board Number of Emergency Changes Increment ratio <1 =Urgent Changes Raised This Month/ Urgent Changes Raised Last Month How number of urgent changes are increasing. Change Approval Awareness 1 =Number of changes Awareness Memos or meeting /Number of Changes Approved How many changes have been informed to the team Leaders, and receives their feedback? Lagging Indicators Change Request Ratio TBD =Value of Change Request / Total Project Value This is highlight what is the scale of the changes happening compares to the project operation. Pending Urgent Changes TBD =Number of Urgent Changes raised – Number of Urgent Changes Solved To see whether how many urgent change requests are pending a decision. Delayed Change Requests TBD =Delayed Change Requests / Total Change Requests To see how often feedback for the changes are getting delayed. Loss of Value of Poor Change Management TBD Loss of Value due to Delayed Responds to Changes and Reworks/ Total Project Value To see how much value loss is due to weak change management. Pending Changes Request TBD Total Changes requested -Total Changes Commented Pending changes Requested to be