  1. 1. PROJECT LIFECYCLE • During each phase, the federated BIM model can get updated • Updates are usually more frequent in earlier stages of project development • BIM elements can be added, modified or even removed • It is important to maintain BIM analysis data regardless of changes in the model
  2. 2. PROJECT STRUCTURE Super Project • Represents a group of Project Versions • Contains only basic information (name, description, ID) • Does not contain BIM model itself Project Version • Represents one instance of the project • Identified by ID and Version Name (description is optional) • Contains entire federated BIM model and associated analysis data Example of Super Project and Project Version in Bexel Manager
  3. 3. PROJECT UPDATE OVERVIEW  User can choose which part of the federated BIM model gets updated  User can control what happens with removed elements during the update  All affected smart selection sets get automatically updated  All affected QTO and custom breakdown structures get automatically updated  All affected clash jobs get automatically marked for reevaluation  All affected cost assignments get automatically adjusted for changes  All affected schedules and tasks with link rules get automatically updated
  4. 4. PROJECT UPDATE • Project can be updated with one or multiple IFC or BX3 files simultaneously (batch) • User can choose whether to keep or delete the elements that have been removed • Once updated, a new project version is created • The previous project version is left intact and can be accessed at any time
  5. 5. PROJECT UPDATE - ELEMENTS • Elements are matched using their unique IDs • Additional element data such as properties, materials and relations are updated as well • Newly added, removed or updated elements are grouped in dedicated selection sets and can be easily isolated • All groups, breakdowns and other element dependent BIM analysis data such as cost, schedule and BOQ are automatically updated to reflect the changes in the model
  6. 6. PROJECT UPDATE – SELECTION SETS • Smart selection sets are automatically updated to reflect the changed BIM model • E.g. 1 If a selection set is targeting all Walls on the project, and a new wall is added in the project, it will be automatically added to that selection set as well • E.g. 2 If a selection set is targeting all elements with Area > 100m2 and an element got its Area increased from 90m2 to 110m2, it will automatically be added to that selection set • If an element is deleted, it will be removed from all associated selection sets • Changes in selection sets will automatically trigger changes in all BIM modules which depend on it (QTO, clash detection, schedule etc.) MODELUPDATE
  7. 7. PROJECT UPDATE – QTO/CBS • Newly added elements will be automatically distributed in Quantity Takeoff (QTO) and Custom Breakdowns (CBS) based on their rules • Updated element quantities will be automatically reflected in associated QTO/CBS • Deleted elements will be removed from all associated QTO/CBS automatically MODEL UPDATE QTOs are automatically updated
  8. 8. PROJECT UPDATE – CLASH DETECTION • Clashes which contain elements with changed geometry will automatically be flagged and clash warning will be raised inside a clash job • Clash job needs to be run again manually due to potential time complexity of reevaluating the clashes again • Once reevaluated, the specific clash warning will be cleared • The updated clashes can now either be resolved, in which case they automatically get the status Resolved, or they can stay Active • Deleted elements will cause all associated clashes to be removed automatically MODEL UPDATE UPDATEOF CLASHES
  9. 9. PROJECT UPDATE – COST ASSIGNMENTS • Elements with changed quantities will automatically update associated cost assignment’s quantities and cost • Changes in cost assignments will automatically trigger changes in all BIM modules which depend on it (schedule etc.) • Deleted elements will be removed from all associated cost assignments • If user decided to preserve deleted elements, they can be easily located in dedicated selection set which can then be used to filter out associated cost assignments before actually deleting elements MODELUPDATE Round concrete columns size was changed from 45cm to 60cm. All cost assignments were automatically updated.
  10. 10. PROJECT UPDATE - SCHEDULE • Newly added elements will automatically be distributed in associated tasks and activities if task link rules are specified • Elements with changed quantities will automatically reflect in tasks either directly or indirectly (through changes in selection sets, cost assignments etc.) • Deleted elements will be removed from all associated tasks automatically • If user decided to preserve deleted elements, they can be easily located in dedicated selection set which can then be used to filter out associated tasks before actually deleting elements • Schedule progress entries will remain unaffected by changes in BIM model as they represent work that is already completed Schedule and cost comparison

×