Dammam Community College
Safety Technology Program
Construction Safety Training
SHORT COURSE
Instructor: Mr. Muizz Anibire, MSc
Tel: +966501296203, Email: muizzanibire10@gmail.com
 Describe the risk assessment process.
 Carry out risk assessment studies of construction tasks.
 Highlight control measures for identified risks.
 Understand Methods Statement as a part of the risk
assessment process.
Learning objectives
Introduction
 April 14th 1912, the Titanic hit an
iceberg on her maiden voyage and 2
hours and 40 minutes later she sank.
 Despite warnings of potential ice flow
the captain was instructed to increase
speed.
 Too few lifeboats available; only enough
to accommodate 1200 passengers on a
ship transporting 2200.
 The lookout had not been provided with
binoculars.
Titanic disaster led to an investigation that
transformed the ship building industry and almost
created the risk analysis industry overnight.
Introduction
 Risk assessment is an essential part of the planning stage of any
health and safety management system.
 Risk assessment methods are used to decide on priorities and to set
objectives for eliminating hazards and reducing risks. Wherever possible,
risks are eliminated through selection and design of facilities, equipment
and processes. If risks cannot be eliminated, they are minimized by the use
of physical controls or, as a last resort, through systems of work and
personal protective equipment.
Legal aspects of risk assessment
 The following requirements are laid down in the regulations:
o the risk assessment shall be ‘suitable and sufficient’ and cover both
employees and non-employees affected by the employer’s undertaking
(e.g. contractors, members of the public, students, patients, customers
etc);
o every self-employed person shall make a ‘suitable and sufficient’
assessment of the risks to which they or those affected by the
undertaking may be exposed;
o any risk assessment shall be reviewed if there is reason to suspect that
it is no longer valid or if a significant change has taken place;
o where there are more than 4 employees, the significant findings of the
assessment shall be recorded and any specially at risk group of
employees identified. (This does not mean that employers with 4 or less
employees need not undertake risk assessments.)
Forms of risk assessment
 There are two basic forms of risk assessment.
o A quantitative risk assessment attempts to measure the risk by
relating the probability of the risk occurring to the possible
severity of the outcome and then giving the risk a numerical
value. This method of risk assessment is used in situations where a
malfunction could be very serious (e.g. aircraft design and maintenance
or the petrochemical industry).
o The more common form of risk assessment is the qualitative
assessment which is based purely on personal judgement and is
normally defined as high, medium or low.
o Qualitative risk assessments are usually satisfactory since the
definition (high, medium or low) is normally used to
determine the time frame in which further action is to be
taken.
Some definitions
 A hazard is the potential of a substance, activity or process to
cause harm. Hazards take many forms including, for example,
chemicals, electricity and the use of a ladder.
 Occupational or work-related ill-health. This is concerned with those
illnesses or physical and mental disorders that are either caused
or triggered by workplace activities.
 Accident … ‘any unplanned event that results in injury or ill-health
of people, or damage or loss to property, plant, materials or the
environment or a loss of a business opportunity’.
 Near miss. This is any incident that could have resulted in an
accident. Knowledge of near misses is very important since
research has shown that, approximately, for every 10 ‘near miss’
events at a particular location in the workplace, a minor accident
will occur.
Some definitions
 A hazard is the potential of a substance, activity or process to
cause harm. Hazards take many forms including, for example,
chemicals, electricity and the use of a ladder.
 A risk is the likelihood of a substance, activity or process to cause
harm. Risk (or strictly the level of risk) is also linked to the
severity of its consequences. A risk can be reduced and the
hazard controlled by good management.
It is very important to distinguish between a hazard and a risk – the two terms
are often confused and activities often called high risk are in fact high hazard.
Overview of Hazard ID and Risk Assessment
Some definitions
HAZARD RISK (likelihood of …)
No safety helmet Head injuries
No goggles Foreign matter in eyes
No gloves Hand injuries
No ear defenders Damage to hearing
Improper footwear Injuries to feet
No respiratory mask Damage to lungs etc.
240V electrical supply Electrocution
No RCD trip device Electrocution
Poor electrical connections Electrocution
Site debris laying around Tripping
Some definitions
The objectives of risk assessment
 The main objective of risk assessment is to determine the
measures required by the organization to comply with relevant
health and safety legislation and, thereby, reduce the level of
occupational injuries and ill-health.
 It is important that all these costs are taken into account when
the full cost of an accident is calculated.
 Direct costs are costs that are directly related to the accident.
They may be insured (claims on employers’ and public liability
insurance, damage to buildings, equipment or vehicles) or
uninsured (fines, sick pay, damage to product, equipment or
process).
 Indirect costs may be insured (business loss, product or process
liability) or uninsured (loss of goodwill, extra overtime payments,
accident investigation time, production delays).
Accident categories
 There are several categories of accident and each has a particular
significance in the construction industry.
o Crane accidents
o Slips, Trips and Falls
o Electrical/Heat/Chemical burns
o Power tool accidents
o Falls from height
o Falling object
o Fire outbreak/explosions
o Struck by fixed/moving objects
o Exposure to toxic/hazardous materials
o Scaffold accidents
o Structural collapse
o Asphyxiation/ respiratory issues
o Trench/excavation accidents
o Drowning
Health risks
 Risk assessment is not only concerned with injuries in the
workplace but also needs to consider the possibility of
occupational ill-health.
 Health risks fall into the following four categories:
o chemical (e.g. paint solvents, exhaust fumes)
o biological (e.g. bacteria, pathogens)
o physical (e.g. noise, vibrations)
o psychological (e.g. occupational stress).
 There are two possible health effects of occupational ill-health.
o They may be acute - occurring soon after the exposure and
are often of short duration, although in some cases
emergency admission to hospital may be required.
o They may be chronic - develop with time. It may take several
years for the associated disease to develop and the effects
may be slight (mild asthma) or severe (cancer).
Job Hazard Analysis (JHA)
NO JOB TASK HAZARDS SEVERITY PERSONS AT
RISK
EXISTING
CONTROLS
1
2
3
HAZID Exercise
Identify at least 5 risks in the photos below:
HAZID Exercise
Identify at least 5 risks in the photos below:
HAZID Exercise
Identify at least 5 risks in the photos below:
HAZID Exercise
Identify at least 5 risks in the photos below:
The management of risk assessment
 Risk assessment is part of the planning and implementation stage
of the health and safety management system recommended by
the HSE.
 All aspects of the organization, including health and safety
management, need to be covered by the risk assessment process.
o A general risk assessment of the organization should reveal
the significant hazards present and the general control
measures that are in place.
o Such a risk assessment should be completed first and then
followed by more specific risk assessments that examine
individual work activities.
 HSE has developed a Five step risk assessment process. It gives
practical advice on assessing risks and recording the findings and
is aimed at small and medium-sized companies in the service and
manufacturing sectors.
Risk Management Framework ISO 31010.3
The management of risk assessment
 The five steps are:
o look for the hazards
o decide who might be harmed, and how
o evaluate the risks and decide whether existing precautions are
adequate or more should be done
o record the significant findings
o review the assessment and revise it if necessary.
 Finally, it is important that the risk assessment team is selected on
the basis of its competence to assess risks in terms of their
technical and/or design knowledge and any relevant standards or regulations
relating to the activity or process.
 At least one team member must have communication and report
writing skills. It is likely that team members will require some
basic training in risk assessment.
The risk assessment process
 The previous five steps could be divided into six elements:
o hazard identification
o persons at risk
o evaluation of risk level
o risk controls (existing and additional)
o record of risk assessment findings
o monitoring and review.
Hazard identification
o Only significant hazards, which could result in serious harm to
people, should be identified. Trivial hazards should be ignored.
o A tour of the area under consideration by the risk assessment
team is an essential part of hazard identification as is
consultation with the relevant section of the workforce.
o A review of accident, incident and ill-health records will also
help with the identification.
The risk assessment process
Persons at risk
o Employees and contractors who work full time at the site or
workplace are the most obvious groups at risk and it will be
necessary check that they are competent to perform their
particular tasks.
o However, there may be other groups who spend time in or
around the workplace. These include young workers, trainees, new
and expectant mothers, cleaners, contractor and maintenance
workers and members of the public.
o Members of the public will include visitors, patients, students or
customers as well as passers by.
o The risk assessment must include any additional controls required
due to the vulnerability of any of these groups, perhaps caused
by inexperience or disability. It must also give an indication of the
numbers of people from the different groups who come into
contact with the hazard and the frequency of these contacts.
The risk assessment process
Evaluation of risk level
o During most risk assessment it will be noted that some of the
risks posed by the hazard have already been addressed or
controlled.
o The purpose of the risk assessment, therefore, is to reduce the
remaining risk. This is called the residual risk.
o The goal of risk assessment is to reduce all residual risks to as low
a level as reasonably practicable (ALARP).
o In a relatively complex workplace, this will take time so that a
system of ranking risk is required – the higher the risk level the
sooner it must be addressed and controlled.
The risk assessment process
Evaluation of risk level
o For most situations, a qualitative risk assessment will be
perfectly adequate.
o During the risk assessment, a judgement is made as to whether
the risk level is high, medium or low in terms of the risk of
somebody being injured.
o This designation defines a timetable for remedial actions to be
taken thereby reducing the risk.
o High-risk activities should normally be addressed in days, medium
risks in weeks and low risks in months or in some cases no action
will be required.
The risk assessment process
Evaluation of risk level
o A quantitative risk assessment attempts to quantify the risk
level in terms of the likelihood of an incident and its subsequent
severity.
o Clearly the higher the likelihood and severity, the higher the risk
will be.
o The likelihood depends on such factors as the control measures
in place, the frequency of exposure to the hazard and the
category of person exposed to the hazard.
o The severity will depend on the magnitude of the hazard (e.g.
voltage, toxicity etc.).
The risk assessment matrix
The risk assessment matrix
The risk assessment matrix
The risk assessment matrix
Risk control measures
 The next stage in the risk assessment is the control of the risk. In
established workplaces, some control of risk will already be in
place.
 The effectiveness of these controls needs to be assessed so that
an estimate of the residual risk may be made.
 Many hazards have had specific acts, regulations or other
recognized standards developed to reduce associated risks.
Examples of such hazards are fire, electricity, lead and asbestos.
 The relevant legislation and any accompanying approved codes
of practice or guidance should be consulted first and any
recommendations implemented.
 Advice on control measures may also be available from trade
associations, trade unions or employers’ organizations.
Hierarchy of risk control
 The Management of Health and Safety at Work Regulations 1999
Schedule 1 also specifies the general principles of prevention
which are set out in the European Council Directive. These
principles are:
1. avoiding risks
2. evaluating the risks which cannot be avoided
3. combating the risks at source
4. adapting the work to the individual, especially as regards the
design of the workplace, the choice of work equipment and
the choice of working and production methods, with a view,
in particular, to alleviating monotonous work and work at a
predetermined work-rate and to reducing their effects on
health
5. adapting to technical progress
Hierarchy of risk control
 The Management of Health and Safety at Work Regulations 1999
Schedule 1 also specifies the general principles of prevention
which are set out in the European Council Directive. These
principles are:
6. replacing the dangerous by the non-dangerous or the less
dangerous
7. developing a coherent overall prevention policy which
covers technology, organization of work, working conditions,
social relationships and the influence of factors relating to the
working environment
8. giving collective protective measures priority over individual
protective measures and
9. giving appropriate instruction to employees
Hierarchy of risk control
The usual hierarchy of risk control is as follows:
o elimination
o substitution
o engineering controls (e.g. isolation, insulation and
ventilation)
o reduced or limited time exposure
o good housekeeping
o safe systems of work
o training and information
o personal protective equipment
o welfare
o monitoring and supervision
o reviews.
Hierarchy of risk control
Hierarchy of Risk Control-ANSI Z590.3
Prioritization of risk control
 The prioritization of the implementation of risk control
measures will depend on the risk rating (high, medium and low)
but the time scale in which the measures are introduced will not always follow
the ratings.
 It may be convenient to deal with a low level risk at the same
time as a high level risk or before a medium level risk.
 It may also be that work on a high risk control system is delayed
due to a late delivery of an essential component – this should not
halt the overall risk reduction work.
 It is important to maintain a continuous programme of risk
improvement rather than slavishly following a predetermined
priority list.
Record of risk assessment findings
 It is very useful to keep a written record of the risk assessment
even if there are less than five employees in the organization.
 For an assessment to be ‘suitable and sufficient’ only the
significant hazards and conclusions need be recorded. The record
should also include details of the groups of people affected by
the hazards and the existing control measures and their
effectiveness.
 The conclusions should identify any new controls required and a
review date.
 The written record provides excellent evidence to a health and
safety inspector of compliance with the law.
 The record should be accessible to employees and a copy kept
with the safety manual containing the safety policy and
arrangements. It is useful for future inspection, and should you
become involved in a litigation.
Monitoring and review
 Risk controls should be reviewed periodically.
 This is equally true for the risk assessment as a whole. Review
and revision may be necessary when conditions change as a result
of the introduction of new machinery, processes or hazards.
 If new machines, substance or procedures are introduced to the
site, or existing one are modified, this may introduce additional
hazards.
 There may be new information on hazardous substances or new
legislation. There could also be changes in the workforce, for
example, the introduction of trainees.
 An accident or incident or a series of minor ones provides a
good reason for a review of the risk assessment. This is known as
the post-accident risk assessment.
Risk Assessment for Special cases
Young persons.
o A risk assessment involving young people needs to consider the
particular vulnerability of young persons in the workplace.
o Young workers clearly have a lack of experience and awareness of
risks in the workplace, a tendency to be subject to peer pressure
and a willingness to work hard. Many young workers will be
trainees or on unpaid work experience.
o A young person is anybody under the age of 18 years, and it is stipulated
that a special risk assessment must be completed which takes into
account their immaturity and inexperience and the assessment must
be completed before the young person starts work.
o If the young person is of school age (16 years or less), the parents
or guardian of the child should be notified of the outcome of the
risk assessment and details of any safeguards which will be used to
protect the health and safety of the child.
Expectant mothers.
o If any type of work could present a particular risk to expectant or
nursing mothers, the risk assessment must include an assessment
of such risks.
o Should these risks be unavoidable, then the woman’s working
conditions or hours must be altered to avoid the risks. The
alternatives are for her to be offered other work or be suspended
from work on full pay.
o The woman must notify the employer in writing that she is
pregnant, or has given birth within the previous six months and/or
is breastfeeding. Typical factors which might affect such women
are: manual handling, chemical or biological agents, ionising radiation, passive
smoking, lack of rest room facilities, temperature variations, prolonged
standing or sitting, stress and violence to staff.
Risk Assessment for Special cases
Workers with disability.
o Organizations have been encouraged for many years to employ
workers with disabilities and to ensure that their premises provide
suitable access for such people.
o From a health and safety point of view, it is important that workers
with a disability are covered by special risk assessments so that
appropriate controls are in place to protect them.
o For example, employees with a hearing problem will need to be
warned when the fire alarm sounds or a fork lift truck approaches.
Special vibrating signals or flashing lights may be used.
o Similarly workers in wheelchairs will require a clear, wheelchair
friendly, route to a fire exit and onwards to the assembly point. Safe
systems of work and welfare facilities need to be suitable for any
workers with disabilities.
Risk Assessment for Special cases
Lone workers.
o People who work alone, like those in small workshops, remote
areas of a large site, social workers, sales personnel or mobile
maintenance staff, should not be at more risk than other
employees.
o It is important to consider whether the risks of the job can be
properly controlled by one person.
Risk Assessment for Special cases
Construction site visitors and trespassers.
o Both authorized and unauthorized visitors to a construction site are
vulnerable to an accident particularly if the trespassers are children.
o All authorized visitors should be given a hard hat, briefed on health
and safety issues and supervised throughout the period of their
visit.
o Walkways on the site should avoid hazards from workers at height,
vehicles or excavation work.
o During non-working hours, the site and the equipment on it should
be secured against trespassers. This will involve the use of security
gates, boarding ladders and emptying fuel from vehicles.
Risk Assessment for Special cases
Risk Assessment and Methods Statement (RAMS)
 A risk assessment should be made by the contractor to identify
those hazards that are likely to be encountered and determine the
control measures required.
 The significant findings of an assessment should be recorded, for
example in a method statement.
 Method statements describe ‘Safe working procedures’ for tasks
where hazards have been identified by the risk assessment exercise.
 Method statements should describe the plant and equipment and the
safe methods of working required to control the risks generated.
 Many work tasks are routine, repetitive and relatively free from
hazards and risks. In these circumstances, once a satisfactory
method statement has been prepared for that activity, it can be used
whenever that activity occurs, (i.e., even from one job to another).
Method statements in this category are termed ‘generic’ and most
organizations will accumulate many of these for use over and over
again.
Risk Assessment and Methods Statement (RAMS)
 For new or more complex work tasks, where the risks have not
previously been determined, ‘specific’ method statements will be
required.
 Large construction firms deal with common risks, by developing in-
house Generic Risk Assessment Procedures (with corresponding
Safe Working Practices) that can be incorporated into the Safety
Manual for a given site. Risks not deemed to be ‘’Generic’ are dealt
with via Site Specific Risk Assessment Procedures. Generic Risk
Assessments can account for about 75% of risks on site.
 Methods of work need to take into account the following factors:
o the removal from site of surplus excavated material
o the stockpiling of excavated material which is to be reused
o the provision of storage space for materials and working space
for workers and plant
o the type of compaction equipment to be used
Risk Assessment and Methods Statement (RAMS)
 The method statement should also contain the information about:
o Emergency arrangements
o Site-based personnel trained to administer first aid,
o Location of the nearest hospital with accident and emergency
facilities,
o Method for swift communication, if there is no telephone
available on site,
 The risk assessment also needs to categorize the level of risk.
 High risks include the collapse of the excavation walls, contact with
existing underground or overhead services, plant and materials
falling into excavations and the presence of hazardous atmospheres
and contaminated soil.
 The possibility of persons falling into the excavations is normally
considered a medium risk
 Flooding of excavations is usually designated a low risk.
Risk Assessment for Confined Space – Case Study
Steps in the Risk Assessment Process
1 Describe the activity/task, equipment, process or facility for which the risk
assessment s being carried out.
2 Identify all potential hazards associated with the activity/task, equipment,
process or facility.
3 Identify the people who may be at risk.
4 Assess the risk based on the severity of the hazards, an likelihood of
occurrence/exposure.
5 Describe the measures necessary to control the identified risks based on the
HoC in ANSI Z590.3
6 Re-assess the risk based on the planned/recommended controls to determine
the residual risk.
7 Document the details of the person(s) carrying out the risk assessment and
time.
8 Document and record the risk assessment exercise.
Knowledge Check
Q1 A hazard is defined as the potential to cause harm. T F
Q2 Risk is defined as the likelihood that harm will occur. T F
Q3 Risk avoidance is the first level in ANSI Z590.3 HoCs. T F
Q4 PPEs is the last line of defense is risk control. T F
Q5 Potential control measures may be obtained from trade
associations, trade unions or employers’ organizations.
T F
End of Session 10:

Mais conteúdo relacionado

Mais procurados

Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety ManagementShirazeh arghami
 
12 construction safety
12 construction safety12 construction safety
12 construction safetyazak80
 
OHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessmentOHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessmentTechnoSysCon
 
A real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 ElementsA real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 Elements360factors
 
Working at Height - Falling Objects
Working at Height - Falling ObjectsWorking at Height - Falling Objects
Working at Height - Falling ObjectsRudi Nieuwoudt
 
Hse presentation general rev.00 may 2014
Hse presentation general rev.00 may 2014Hse presentation general rev.00 may 2014
Hse presentation general rev.00 may 2014Fitri Ifony
 
Process Safety Management System
Process Safety Management SystemProcess Safety Management System
Process Safety Management SystemACM Facility Safety
 
Risk assessment-training
Risk assessment-trainingRisk assessment-training
Risk assessment-trainingIshah Khaliq
 
working at height
working at heightworking at height
working at heightJYOTHISHKT
 
OH& S at Construction Sites in Australia
OH& S at Construction Sites in AustraliaOH& S at Construction Sites in Australia
OH& S at Construction Sites in AustraliaDHA Lahore
 
Lifting Presentation.
Lifting Presentation.Lifting Presentation.
Lifting Presentation.paul doherty
 
EHS induction Presentation slides
EHS induction Presentation slidesEHS induction Presentation slides
EHS induction Presentation slidesMaffino
 

Mais procurados (20)

Hira
HiraHira
Hira
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety Management
 
Safety Management System
Safety Management SystemSafety Management System
Safety Management System
 
Near Miss Reporting
Near Miss ReportingNear Miss Reporting
Near Miss Reporting
 
Staff safety hand book
Staff   safety hand bookStaff   safety hand book
Staff safety hand book
 
12 construction safety
12 construction safety12 construction safety
12 construction safety
 
OHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessmentOHSAS Hazard identification & Risk assessment
OHSAS Hazard identification & Risk assessment
 
A real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 ElementsA real-world introduction to PSM’s 14 Elements
A real-world introduction to PSM’s 14 Elements
 
Working at Height - Falling Objects
Working at Height - Falling ObjectsWorking at Height - Falling Objects
Working at Height - Falling Objects
 
Hse presentation general rev.00 may 2014
Hse presentation general rev.00 may 2014Hse presentation general rev.00 may 2014
Hse presentation general rev.00 may 2014
 
Process Safety Management
Process Safety ManagementProcess Safety Management
Process Safety Management
 
Process Safety Management System
Process Safety Management SystemProcess Safety Management System
Process Safety Management System
 
Risk assessment-training
Risk assessment-trainingRisk assessment-training
Risk assessment-training
 
working at height
working at heightworking at height
working at height
 
1 construction sh
1 construction sh1 construction sh
1 construction sh
 
OH& S at Construction Sites in Australia
OH& S at Construction Sites in AustraliaOH& S at Construction Sites in Australia
OH& S at Construction Sites in Australia
 
Hse Action Plan
Hse Action PlanHse Action Plan
Hse Action Plan
 
Lifting Presentation.
Lifting Presentation.Lifting Presentation.
Lifting Presentation.
 
EHS induction Presentation slides
EHS induction Presentation slidesEHS induction Presentation slides
EHS induction Presentation slides
 
HSE Management System
HSE Management SystemHSE Management System
HSE Management System
 

Semelhante a Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control, and Methods Statement

HSE-BMS-006 Risk Assessment & JSA.ppt
HSE-BMS-006 Risk Assessment & JSA.pptHSE-BMS-006 Risk Assessment & JSA.ppt
HSE-BMS-006 Risk Assessment & JSA.pptGkMechanical
 
Risk Assessment and Job Safety Analysis
Risk Assessment and Job Safety AnalysisRisk Assessment and Job Safety Analysis
Risk Assessment and Job Safety AnalysisGaurav Singh Rajput
 
Risk Assessment & Job Safety Analysis | JSA | RA
Risk Assessment & Job Safety Analysis | JSA | RARisk Assessment & Job Safety Analysis | JSA | RA
Risk Assessment & Job Safety Analysis | JSA | RAGaurav Singh Rajput
 
HIRA (hazard identification risk assessment)
HIRA (hazard identification risk assessment)HIRA (hazard identification risk assessment)
HIRA (hazard identification risk assessment)PrasantakumarNayak4
 
Hira – hazard identification & risk assessment
Hira – hazard identification & risk assessment Hira – hazard identification & risk assessment
Hira – hazard identification & risk assessment Salim Solanki
 
Risk Assessment Program For Young Safety Professionals (YSP)
Risk Assessment Program For Young Safety Professionals (YSP)Risk Assessment Program For Young Safety Professionals (YSP)
Risk Assessment Program For Young Safety Professionals (YSP)Muizz Anibire
 
11. CHAPTER 2.0 RISK ASSESSMENT & MANAGEMENT.pdf
11. CHAPTER 2.0 RISK ASSESSMENT & MANAGEMENT.pdf11. CHAPTER 2.0 RISK ASSESSMENT & MANAGEMENT.pdf
11. CHAPTER 2.0 RISK ASSESSMENT & MANAGEMENT.pdfMohdJamilBinMohdHamb
 
pilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptpilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptAsifHussain654789
 
pilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptpilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptShahbazAhmad736457
 
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...PECB
 
Risk Assessment for Building Construction Sites in Myanmar
Risk Assessment for Building Construction Sites in MyanmarRisk Assessment for Building Construction Sites in Myanmar
Risk Assessment for Building Construction Sites in Myanmarijtsrd
 
INTRODUCTION to risk_assessment.ppt
INTRODUCTION to risk_assessment.pptINTRODUCTION to risk_assessment.ppt
INTRODUCTION to risk_assessment.pptchandrasekars29
 
CHAPTER -1 INTRODUCTION to risk_assessment.ppt
CHAPTER -1 INTRODUCTION to risk_assessment.pptCHAPTER -1 INTRODUCTION to risk_assessment.ppt
CHAPTER -1 INTRODUCTION to risk_assessment.pptchandrasekars29
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Gaurav Singh Rajput
 
Risk Analysis and.pdf
Risk Analysis and.pdfRisk Analysis and.pdf
Risk Analysis and.pdfCesarPuma10
 

Semelhante a Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control, and Methods Statement (20)

HSE-BMS-006 Risk Assessment & JSA.ppt
HSE-BMS-006 Risk Assessment & JSA.pptHSE-BMS-006 Risk Assessment & JSA.ppt
HSE-BMS-006 Risk Assessment & JSA.ppt
 
Risk Assessment and Job Safety Analysis
Risk Assessment and Job Safety AnalysisRisk Assessment and Job Safety Analysis
Risk Assessment and Job Safety Analysis
 
Risk Assessment & Job Safety Analysis | JSA | RA
Risk Assessment & Job Safety Analysis | JSA | RARisk Assessment & Job Safety Analysis | JSA | RA
Risk Assessment & Job Safety Analysis | JSA | RA
 
HIRA (hazard identification risk assessment)
HIRA (hazard identification risk assessment)HIRA (hazard identification risk assessment)
HIRA (hazard identification risk assessment)
 
Hira – hazard identification & risk assessment
Hira – hazard identification & risk assessment Hira – hazard identification & risk assessment
Hira – hazard identification & risk assessment
 
Topic 04 risk mangement
Topic 04 risk mangementTopic 04 risk mangement
Topic 04 risk mangement
 
Risk Assessment Program For Young Safety Professionals (YSP)
Risk Assessment Program For Young Safety Professionals (YSP)Risk Assessment Program For Young Safety Professionals (YSP)
Risk Assessment Program For Young Safety Professionals (YSP)
 
11. CHAPTER 2.0 RISK ASSESSMENT & MANAGEMENT.pdf
11. CHAPTER 2.0 RISK ASSESSMENT & MANAGEMENT.pdf11. CHAPTER 2.0 RISK ASSESSMENT & MANAGEMENT.pdf
11. CHAPTER 2.0 RISK ASSESSMENT & MANAGEMENT.pdf
 
pilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptpilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.ppt
 
pilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptpilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.ppt
 
Risk assessment
Risk assessmentRisk assessment
Risk assessment
 
Topic5
Topic5Topic5
Topic5
 
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
 
Risk Assessment for Building Construction Sites in Myanmar
Risk Assessment for Building Construction Sites in MyanmarRisk Assessment for Building Construction Sites in Myanmar
Risk Assessment for Building Construction Sites in Myanmar
 
INTRODUCTION to risk_assessment.ppt
INTRODUCTION to risk_assessment.pptINTRODUCTION to risk_assessment.ppt
INTRODUCTION to risk_assessment.ppt
 
Healthcare Risk Management
Healthcare Risk Management  Healthcare Risk Management
Healthcare Risk Management
 
Risk Assessment
Risk AssessmentRisk Assessment
Risk Assessment
 
CHAPTER -1 INTRODUCTION to risk_assessment.ppt
CHAPTER -1 INTRODUCTION to risk_assessment.pptCHAPTER -1 INTRODUCTION to risk_assessment.ppt
CHAPTER -1 INTRODUCTION to risk_assessment.ppt
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Risk Analysis and.pdf
Risk Analysis and.pdfRisk Analysis and.pdf
Risk Analysis and.pdf
 

Mais de Muizz Anibire

Questionnaire Template.docx
Questionnaire Template.docxQuestionnaire Template.docx
Questionnaire Template.docxMuizz Anibire
 
Turing’s Computing Machinery and Intelligence.pdf
Turing’s Computing Machinery and Intelligence.pdfTuring’s Computing Machinery and Intelligence.pdf
Turing’s Computing Machinery and Intelligence.pdfMuizz Anibire
 
أحكام الجنائز -FUNERAL RITES
أحكام الجنائز   -FUNERAL RITESأحكام الجنائز   -FUNERAL RITES
أحكام الجنائز -FUNERAL RITESMuizz Anibire
 
ISO 31000 risk management process
ISO 31000 risk management processISO 31000 risk management process
ISO 31000 risk management processMuizz Anibire
 
A MACHINE LEARNING-BASED FRAMEWORK FOR DELAY MITIGATION IN TALL BUILDING PROJ...
A MACHINE LEARNING-BASED FRAMEWORK FOR DELAY MITIGATION IN TALL BUILDING PROJ...A MACHINE LEARNING-BASED FRAMEWORK FOR DELAY MITIGATION IN TALL BUILDING PROJ...
A MACHINE LEARNING-BASED FRAMEWORK FOR DELAY MITIGATION IN TALL BUILDING PROJ...Muizz Anibire
 
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIESCAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIESMuizz Anibire
 
Guidelines on writing a research paper
Guidelines on writing a research paperGuidelines on writing a research paper
Guidelines on writing a research paperMuizz Anibire
 
Tall buildings in urban context
Tall buildings in urban contextTall buildings in urban context
Tall buildings in urban contextMuizz Anibire
 
Session 09_Risk Assessment Program for YSP_Risk Assessment Tools and Practica...
Session 09_Risk Assessment Program for YSP_Risk Assessment Tools and Practica...Session 09_Risk Assessment Program for YSP_Risk Assessment Tools and Practica...
Session 09_Risk Assessment Program for YSP_Risk Assessment Tools and Practica...Muizz Anibire
 
Session 08_Risk Assessment Program for YSP_Risk Treatment and Communication
Session 08_Risk Assessment Program for YSP_Risk Treatment and CommunicationSession 08_Risk Assessment Program for YSP_Risk Treatment and Communication
Session 08_Risk Assessment Program for YSP_Risk Treatment and CommunicationMuizz Anibire
 
Session 07_Risk Assessment Program for YSP_Risk Evaluation
Session 07_Risk Assessment Program for YSP_Risk EvaluationSession 07_Risk Assessment Program for YSP_Risk Evaluation
Session 07_Risk Assessment Program for YSP_Risk EvaluationMuizz Anibire
 
Session 06_Risk Assessment Program for YSP_Risk Analysis III
Session 06_Risk Assessment Program for YSP_Risk Analysis IIISession 06_Risk Assessment Program for YSP_Risk Analysis III
Session 06_Risk Assessment Program for YSP_Risk Analysis IIIMuizz Anibire
 
Session 05_Risk Assessment Program for YSP_Risk Analysis II
Session 05_Risk Assessment Program for YSP_Risk Analysis IISession 05_Risk Assessment Program for YSP_Risk Analysis II
Session 05_Risk Assessment Program for YSP_Risk Analysis IIMuizz Anibire
 
Session 04_Risk Assessment Program for YSP_Risk Analysis I
Session 04_Risk Assessment Program for YSP_Risk Analysis ISession 04_Risk Assessment Program for YSP_Risk Analysis I
Session 04_Risk Assessment Program for YSP_Risk Analysis IMuizz Anibire
 
Session 02 Risk Assessment Program for YSP_The Risk Assessment Process
Session 02 Risk Assessment Program for YSP_The Risk Assessment ProcessSession 02 Risk Assessment Program for YSP_The Risk Assessment Process
Session 02 Risk Assessment Program for YSP_The Risk Assessment ProcessMuizz Anibire
 
Session 01 _Risk Assessment Program for YSP_Introduction, Definitions and Sta...
Session 01 _Risk Assessment Program for YSP_Introduction, Definitions and Sta...Session 01 _Risk Assessment Program for YSP_Introduction, Definitions and Sta...
Session 01 _Risk Assessment Program for YSP_Introduction, Definitions and Sta...Muizz Anibire
 
Construction Safety Training_Session 08_Demolition using Explosives
Construction Safety Training_Session 08_Demolition using ExplosivesConstruction Safety Training_Session 08_Demolition using Explosives
Construction Safety Training_Session 08_Demolition using ExplosivesMuizz Anibire
 
Construction Safety Training_Session 04_Working at Heights and Over Water
Construction Safety Training_Session 04_Working at Heights and Over WaterConstruction Safety Training_Session 04_Working at Heights and Over Water
Construction Safety Training_Session 04_Working at Heights and Over WaterMuizz Anibire
 
Construction Safety Training_Session 03_Confined Spaces and Underground Works
Construction Safety Training_Session 03_Confined Spaces and Underground WorksConstruction Safety Training_Session 03_Confined Spaces and Underground Works
Construction Safety Training_Session 03_Confined Spaces and Underground WorksMuizz Anibire
 
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls Muizz Anibire
 

Mais de Muizz Anibire (20)

Questionnaire Template.docx
Questionnaire Template.docxQuestionnaire Template.docx
Questionnaire Template.docx
 
Turing’s Computing Machinery and Intelligence.pdf
Turing’s Computing Machinery and Intelligence.pdfTuring’s Computing Machinery and Intelligence.pdf
Turing’s Computing Machinery and Intelligence.pdf
 
أحكام الجنائز -FUNERAL RITES
أحكام الجنائز   -FUNERAL RITESأحكام الجنائز   -FUNERAL RITES
أحكام الجنائز -FUNERAL RITES
 
ISO 31000 risk management process
ISO 31000 risk management processISO 31000 risk management process
ISO 31000 risk management process
 
A MACHINE LEARNING-BASED FRAMEWORK FOR DELAY MITIGATION IN TALL BUILDING PROJ...
A MACHINE LEARNING-BASED FRAMEWORK FOR DELAY MITIGATION IN TALL BUILDING PROJ...A MACHINE LEARNING-BASED FRAMEWORK FOR DELAY MITIGATION IN TALL BUILDING PROJ...
A MACHINE LEARNING-BASED FRAMEWORK FOR DELAY MITIGATION IN TALL BUILDING PROJ...
 
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIESCAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
CAUSES OF DELAY IN TALL BUILDING PROJECTS IN GCC COUNTRIES
 
Guidelines on writing a research paper
Guidelines on writing a research paperGuidelines on writing a research paper
Guidelines on writing a research paper
 
Tall buildings in urban context
Tall buildings in urban contextTall buildings in urban context
Tall buildings in urban context
 
Session 09_Risk Assessment Program for YSP_Risk Assessment Tools and Practica...
Session 09_Risk Assessment Program for YSP_Risk Assessment Tools and Practica...Session 09_Risk Assessment Program for YSP_Risk Assessment Tools and Practica...
Session 09_Risk Assessment Program for YSP_Risk Assessment Tools and Practica...
 
Session 08_Risk Assessment Program for YSP_Risk Treatment and Communication
Session 08_Risk Assessment Program for YSP_Risk Treatment and CommunicationSession 08_Risk Assessment Program for YSP_Risk Treatment and Communication
Session 08_Risk Assessment Program for YSP_Risk Treatment and Communication
 
Session 07_Risk Assessment Program for YSP_Risk Evaluation
Session 07_Risk Assessment Program for YSP_Risk EvaluationSession 07_Risk Assessment Program for YSP_Risk Evaluation
Session 07_Risk Assessment Program for YSP_Risk Evaluation
 
Session 06_Risk Assessment Program for YSP_Risk Analysis III
Session 06_Risk Assessment Program for YSP_Risk Analysis IIISession 06_Risk Assessment Program for YSP_Risk Analysis III
Session 06_Risk Assessment Program for YSP_Risk Analysis III
 
Session 05_Risk Assessment Program for YSP_Risk Analysis II
Session 05_Risk Assessment Program for YSP_Risk Analysis IISession 05_Risk Assessment Program for YSP_Risk Analysis II
Session 05_Risk Assessment Program for YSP_Risk Analysis II
 
Session 04_Risk Assessment Program for YSP_Risk Analysis I
Session 04_Risk Assessment Program for YSP_Risk Analysis ISession 04_Risk Assessment Program for YSP_Risk Analysis I
Session 04_Risk Assessment Program for YSP_Risk Analysis I
 
Session 02 Risk Assessment Program for YSP_The Risk Assessment Process
Session 02 Risk Assessment Program for YSP_The Risk Assessment ProcessSession 02 Risk Assessment Program for YSP_The Risk Assessment Process
Session 02 Risk Assessment Program for YSP_The Risk Assessment Process
 
Session 01 _Risk Assessment Program for YSP_Introduction, Definitions and Sta...
Session 01 _Risk Assessment Program for YSP_Introduction, Definitions and Sta...Session 01 _Risk Assessment Program for YSP_Introduction, Definitions and Sta...
Session 01 _Risk Assessment Program for YSP_Introduction, Definitions and Sta...
 
Construction Safety Training_Session 08_Demolition using Explosives
Construction Safety Training_Session 08_Demolition using ExplosivesConstruction Safety Training_Session 08_Demolition using Explosives
Construction Safety Training_Session 08_Demolition using Explosives
 
Construction Safety Training_Session 04_Working at Heights and Over Water
Construction Safety Training_Session 04_Working at Heights and Over WaterConstruction Safety Training_Session 04_Working at Heights and Over Water
Construction Safety Training_Session 04_Working at Heights and Over Water
 
Construction Safety Training_Session 03_Confined Spaces and Underground Works
Construction Safety Training_Session 03_Confined Spaces and Underground WorksConstruction Safety Training_Session 03_Confined Spaces and Underground Works
Construction Safety Training_Session 03_Confined Spaces and Underground Works
 
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
Construction Safety Training_Session 02_Excavation Works, Hazards and Controls
 

Último

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Último (20)

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control, and Methods Statement

  • 1. Dammam Community College Safety Technology Program Construction Safety Training SHORT COURSE Instructor: Mr. Muizz Anibire, MSc Tel: +966501296203, Email: muizzanibire10@gmail.com
  • 2.  Describe the risk assessment process.  Carry out risk assessment studies of construction tasks.  Highlight control measures for identified risks.  Understand Methods Statement as a part of the risk assessment process. Learning objectives
  • 3. Introduction  April 14th 1912, the Titanic hit an iceberg on her maiden voyage and 2 hours and 40 minutes later she sank.  Despite warnings of potential ice flow the captain was instructed to increase speed.  Too few lifeboats available; only enough to accommodate 1200 passengers on a ship transporting 2200.  The lookout had not been provided with binoculars. Titanic disaster led to an investigation that transformed the ship building industry and almost created the risk analysis industry overnight.
  • 4. Introduction  Risk assessment is an essential part of the planning stage of any health and safety management system.  Risk assessment methods are used to decide on priorities and to set objectives for eliminating hazards and reducing risks. Wherever possible, risks are eliminated through selection and design of facilities, equipment and processes. If risks cannot be eliminated, they are minimized by the use of physical controls or, as a last resort, through systems of work and personal protective equipment.
  • 5. Legal aspects of risk assessment  The following requirements are laid down in the regulations: o the risk assessment shall be ‘suitable and sufficient’ and cover both employees and non-employees affected by the employer’s undertaking (e.g. contractors, members of the public, students, patients, customers etc); o every self-employed person shall make a ‘suitable and sufficient’ assessment of the risks to which they or those affected by the undertaking may be exposed; o any risk assessment shall be reviewed if there is reason to suspect that it is no longer valid or if a significant change has taken place; o where there are more than 4 employees, the significant findings of the assessment shall be recorded and any specially at risk group of employees identified. (This does not mean that employers with 4 or less employees need not undertake risk assessments.)
  • 6. Forms of risk assessment  There are two basic forms of risk assessment. o A quantitative risk assessment attempts to measure the risk by relating the probability of the risk occurring to the possible severity of the outcome and then giving the risk a numerical value. This method of risk assessment is used in situations where a malfunction could be very serious (e.g. aircraft design and maintenance or the petrochemical industry). o The more common form of risk assessment is the qualitative assessment which is based purely on personal judgement and is normally defined as high, medium or low. o Qualitative risk assessments are usually satisfactory since the definition (high, medium or low) is normally used to determine the time frame in which further action is to be taken.
  • 7. Some definitions  A hazard is the potential of a substance, activity or process to cause harm. Hazards take many forms including, for example, chemicals, electricity and the use of a ladder.  Occupational or work-related ill-health. This is concerned with those illnesses or physical and mental disorders that are either caused or triggered by workplace activities.  Accident … ‘any unplanned event that results in injury or ill-health of people, or damage or loss to property, plant, materials or the environment or a loss of a business opportunity’.  Near miss. This is any incident that could have resulted in an accident. Knowledge of near misses is very important since research has shown that, approximately, for every 10 ‘near miss’ events at a particular location in the workplace, a minor accident will occur.
  • 8. Some definitions  A hazard is the potential of a substance, activity or process to cause harm. Hazards take many forms including, for example, chemicals, electricity and the use of a ladder.  A risk is the likelihood of a substance, activity or process to cause harm. Risk (or strictly the level of risk) is also linked to the severity of its consequences. A risk can be reduced and the hazard controlled by good management. It is very important to distinguish between a hazard and a risk – the two terms are often confused and activities often called high risk are in fact high hazard.
  • 9. Overview of Hazard ID and Risk Assessment
  • 10. Some definitions HAZARD RISK (likelihood of …) No safety helmet Head injuries No goggles Foreign matter in eyes No gloves Hand injuries No ear defenders Damage to hearing Improper footwear Injuries to feet No respiratory mask Damage to lungs etc. 240V electrical supply Electrocution No RCD trip device Electrocution Poor electrical connections Electrocution Site debris laying around Tripping
  • 12. The objectives of risk assessment  The main objective of risk assessment is to determine the measures required by the organization to comply with relevant health and safety legislation and, thereby, reduce the level of occupational injuries and ill-health.  It is important that all these costs are taken into account when the full cost of an accident is calculated.  Direct costs are costs that are directly related to the accident. They may be insured (claims on employers’ and public liability insurance, damage to buildings, equipment or vehicles) or uninsured (fines, sick pay, damage to product, equipment or process).  Indirect costs may be insured (business loss, product or process liability) or uninsured (loss of goodwill, extra overtime payments, accident investigation time, production delays).
  • 13. Accident categories  There are several categories of accident and each has a particular significance in the construction industry. o Crane accidents o Slips, Trips and Falls o Electrical/Heat/Chemical burns o Power tool accidents o Falls from height o Falling object o Fire outbreak/explosions o Struck by fixed/moving objects o Exposure to toxic/hazardous materials o Scaffold accidents o Structural collapse o Asphyxiation/ respiratory issues o Trench/excavation accidents o Drowning
  • 14. Health risks  Risk assessment is not only concerned with injuries in the workplace but also needs to consider the possibility of occupational ill-health.  Health risks fall into the following four categories: o chemical (e.g. paint solvents, exhaust fumes) o biological (e.g. bacteria, pathogens) o physical (e.g. noise, vibrations) o psychological (e.g. occupational stress).  There are two possible health effects of occupational ill-health. o They may be acute - occurring soon after the exposure and are often of short duration, although in some cases emergency admission to hospital may be required. o They may be chronic - develop with time. It may take several years for the associated disease to develop and the effects may be slight (mild asthma) or severe (cancer).
  • 15. Job Hazard Analysis (JHA) NO JOB TASK HAZARDS SEVERITY PERSONS AT RISK EXISTING CONTROLS 1 2 3
  • 16. HAZID Exercise Identify at least 5 risks in the photos below:
  • 17. HAZID Exercise Identify at least 5 risks in the photos below:
  • 18. HAZID Exercise Identify at least 5 risks in the photos below:
  • 19. HAZID Exercise Identify at least 5 risks in the photos below:
  • 20. The management of risk assessment  Risk assessment is part of the planning and implementation stage of the health and safety management system recommended by the HSE.  All aspects of the organization, including health and safety management, need to be covered by the risk assessment process. o A general risk assessment of the organization should reveal the significant hazards present and the general control measures that are in place. o Such a risk assessment should be completed first and then followed by more specific risk assessments that examine individual work activities.  HSE has developed a Five step risk assessment process. It gives practical advice on assessing risks and recording the findings and is aimed at small and medium-sized companies in the service and manufacturing sectors.
  • 22. The management of risk assessment  The five steps are: o look for the hazards o decide who might be harmed, and how o evaluate the risks and decide whether existing precautions are adequate or more should be done o record the significant findings o review the assessment and revise it if necessary.  Finally, it is important that the risk assessment team is selected on the basis of its competence to assess risks in terms of their technical and/or design knowledge and any relevant standards or regulations relating to the activity or process.  At least one team member must have communication and report writing skills. It is likely that team members will require some basic training in risk assessment.
  • 23. The risk assessment process  The previous five steps could be divided into six elements: o hazard identification o persons at risk o evaluation of risk level o risk controls (existing and additional) o record of risk assessment findings o monitoring and review. Hazard identification o Only significant hazards, which could result in serious harm to people, should be identified. Trivial hazards should be ignored. o A tour of the area under consideration by the risk assessment team is an essential part of hazard identification as is consultation with the relevant section of the workforce. o A review of accident, incident and ill-health records will also help with the identification.
  • 24. The risk assessment process Persons at risk o Employees and contractors who work full time at the site or workplace are the most obvious groups at risk and it will be necessary check that they are competent to perform their particular tasks. o However, there may be other groups who spend time in or around the workplace. These include young workers, trainees, new and expectant mothers, cleaners, contractor and maintenance workers and members of the public. o Members of the public will include visitors, patients, students or customers as well as passers by. o The risk assessment must include any additional controls required due to the vulnerability of any of these groups, perhaps caused by inexperience or disability. It must also give an indication of the numbers of people from the different groups who come into contact with the hazard and the frequency of these contacts.
  • 25. The risk assessment process Evaluation of risk level o During most risk assessment it will be noted that some of the risks posed by the hazard have already been addressed or controlled. o The purpose of the risk assessment, therefore, is to reduce the remaining risk. This is called the residual risk. o The goal of risk assessment is to reduce all residual risks to as low a level as reasonably practicable (ALARP). o In a relatively complex workplace, this will take time so that a system of ranking risk is required – the higher the risk level the sooner it must be addressed and controlled.
  • 26. The risk assessment process Evaluation of risk level o For most situations, a qualitative risk assessment will be perfectly adequate. o During the risk assessment, a judgement is made as to whether the risk level is high, medium or low in terms of the risk of somebody being injured. o This designation defines a timetable for remedial actions to be taken thereby reducing the risk. o High-risk activities should normally be addressed in days, medium risks in weeks and low risks in months or in some cases no action will be required.
  • 27. The risk assessment process Evaluation of risk level o A quantitative risk assessment attempts to quantify the risk level in terms of the likelihood of an incident and its subsequent severity. o Clearly the higher the likelihood and severity, the higher the risk will be. o The likelihood depends on such factors as the control measures in place, the frequency of exposure to the hazard and the category of person exposed to the hazard. o The severity will depend on the magnitude of the hazard (e.g. voltage, toxicity etc.).
  • 32. Risk control measures  The next stage in the risk assessment is the control of the risk. In established workplaces, some control of risk will already be in place.  The effectiveness of these controls needs to be assessed so that an estimate of the residual risk may be made.  Many hazards have had specific acts, regulations or other recognized standards developed to reduce associated risks. Examples of such hazards are fire, electricity, lead and asbestos.  The relevant legislation and any accompanying approved codes of practice or guidance should be consulted first and any recommendations implemented.  Advice on control measures may also be available from trade associations, trade unions or employers’ organizations.
  • 33. Hierarchy of risk control  The Management of Health and Safety at Work Regulations 1999 Schedule 1 also specifies the general principles of prevention which are set out in the European Council Directive. These principles are: 1. avoiding risks 2. evaluating the risks which cannot be avoided 3. combating the risks at source 4. adapting the work to the individual, especially as regards the design of the workplace, the choice of work equipment and the choice of working and production methods, with a view, in particular, to alleviating monotonous work and work at a predetermined work-rate and to reducing their effects on health 5. adapting to technical progress
  • 34. Hierarchy of risk control  The Management of Health and Safety at Work Regulations 1999 Schedule 1 also specifies the general principles of prevention which are set out in the European Council Directive. These principles are: 6. replacing the dangerous by the non-dangerous or the less dangerous 7. developing a coherent overall prevention policy which covers technology, organization of work, working conditions, social relationships and the influence of factors relating to the working environment 8. giving collective protective measures priority over individual protective measures and 9. giving appropriate instruction to employees
  • 35. Hierarchy of risk control The usual hierarchy of risk control is as follows: o elimination o substitution o engineering controls (e.g. isolation, insulation and ventilation) o reduced or limited time exposure o good housekeeping o safe systems of work o training and information o personal protective equipment o welfare o monitoring and supervision o reviews.
  • 36. Hierarchy of risk control
  • 37. Hierarchy of Risk Control-ANSI Z590.3
  • 38. Prioritization of risk control  The prioritization of the implementation of risk control measures will depend on the risk rating (high, medium and low) but the time scale in which the measures are introduced will not always follow the ratings.  It may be convenient to deal with a low level risk at the same time as a high level risk or before a medium level risk.  It may also be that work on a high risk control system is delayed due to a late delivery of an essential component – this should not halt the overall risk reduction work.  It is important to maintain a continuous programme of risk improvement rather than slavishly following a predetermined priority list.
  • 39. Record of risk assessment findings  It is very useful to keep a written record of the risk assessment even if there are less than five employees in the organization.  For an assessment to be ‘suitable and sufficient’ only the significant hazards and conclusions need be recorded. The record should also include details of the groups of people affected by the hazards and the existing control measures and their effectiveness.  The conclusions should identify any new controls required and a review date.  The written record provides excellent evidence to a health and safety inspector of compliance with the law.  The record should be accessible to employees and a copy kept with the safety manual containing the safety policy and arrangements. It is useful for future inspection, and should you become involved in a litigation.
  • 40. Monitoring and review  Risk controls should be reviewed periodically.  This is equally true for the risk assessment as a whole. Review and revision may be necessary when conditions change as a result of the introduction of new machinery, processes or hazards.  If new machines, substance or procedures are introduced to the site, or existing one are modified, this may introduce additional hazards.  There may be new information on hazardous substances or new legislation. There could also be changes in the workforce, for example, the introduction of trainees.  An accident or incident or a series of minor ones provides a good reason for a review of the risk assessment. This is known as the post-accident risk assessment.
  • 41. Risk Assessment for Special cases Young persons. o A risk assessment involving young people needs to consider the particular vulnerability of young persons in the workplace. o Young workers clearly have a lack of experience and awareness of risks in the workplace, a tendency to be subject to peer pressure and a willingness to work hard. Many young workers will be trainees or on unpaid work experience. o A young person is anybody under the age of 18 years, and it is stipulated that a special risk assessment must be completed which takes into account their immaturity and inexperience and the assessment must be completed before the young person starts work. o If the young person is of school age (16 years or less), the parents or guardian of the child should be notified of the outcome of the risk assessment and details of any safeguards which will be used to protect the health and safety of the child.
  • 42. Expectant mothers. o If any type of work could present a particular risk to expectant or nursing mothers, the risk assessment must include an assessment of such risks. o Should these risks be unavoidable, then the woman’s working conditions or hours must be altered to avoid the risks. The alternatives are for her to be offered other work or be suspended from work on full pay. o The woman must notify the employer in writing that she is pregnant, or has given birth within the previous six months and/or is breastfeeding. Typical factors which might affect such women are: manual handling, chemical or biological agents, ionising radiation, passive smoking, lack of rest room facilities, temperature variations, prolonged standing or sitting, stress and violence to staff. Risk Assessment for Special cases
  • 43. Workers with disability. o Organizations have been encouraged for many years to employ workers with disabilities and to ensure that their premises provide suitable access for such people. o From a health and safety point of view, it is important that workers with a disability are covered by special risk assessments so that appropriate controls are in place to protect them. o For example, employees with a hearing problem will need to be warned when the fire alarm sounds or a fork lift truck approaches. Special vibrating signals or flashing lights may be used. o Similarly workers in wheelchairs will require a clear, wheelchair friendly, route to a fire exit and onwards to the assembly point. Safe systems of work and welfare facilities need to be suitable for any workers with disabilities. Risk Assessment for Special cases
  • 44. Lone workers. o People who work alone, like those in small workshops, remote areas of a large site, social workers, sales personnel or mobile maintenance staff, should not be at more risk than other employees. o It is important to consider whether the risks of the job can be properly controlled by one person. Risk Assessment for Special cases
  • 45. Construction site visitors and trespassers. o Both authorized and unauthorized visitors to a construction site are vulnerable to an accident particularly if the trespassers are children. o All authorized visitors should be given a hard hat, briefed on health and safety issues and supervised throughout the period of their visit. o Walkways on the site should avoid hazards from workers at height, vehicles or excavation work. o During non-working hours, the site and the equipment on it should be secured against trespassers. This will involve the use of security gates, boarding ladders and emptying fuel from vehicles. Risk Assessment for Special cases
  • 46. Risk Assessment and Methods Statement (RAMS)  A risk assessment should be made by the contractor to identify those hazards that are likely to be encountered and determine the control measures required.  The significant findings of an assessment should be recorded, for example in a method statement.  Method statements describe ‘Safe working procedures’ for tasks where hazards have been identified by the risk assessment exercise.  Method statements should describe the plant and equipment and the safe methods of working required to control the risks generated.  Many work tasks are routine, repetitive and relatively free from hazards and risks. In these circumstances, once a satisfactory method statement has been prepared for that activity, it can be used whenever that activity occurs, (i.e., even from one job to another). Method statements in this category are termed ‘generic’ and most organizations will accumulate many of these for use over and over again.
  • 47. Risk Assessment and Methods Statement (RAMS)  For new or more complex work tasks, where the risks have not previously been determined, ‘specific’ method statements will be required.  Large construction firms deal with common risks, by developing in- house Generic Risk Assessment Procedures (with corresponding Safe Working Practices) that can be incorporated into the Safety Manual for a given site. Risks not deemed to be ‘’Generic’ are dealt with via Site Specific Risk Assessment Procedures. Generic Risk Assessments can account for about 75% of risks on site.  Methods of work need to take into account the following factors: o the removal from site of surplus excavated material o the stockpiling of excavated material which is to be reused o the provision of storage space for materials and working space for workers and plant o the type of compaction equipment to be used
  • 48. Risk Assessment and Methods Statement (RAMS)  The method statement should also contain the information about: o Emergency arrangements o Site-based personnel trained to administer first aid, o Location of the nearest hospital with accident and emergency facilities, o Method for swift communication, if there is no telephone available on site,  The risk assessment also needs to categorize the level of risk.  High risks include the collapse of the excavation walls, contact with existing underground or overhead services, plant and materials falling into excavations and the presence of hazardous atmospheres and contaminated soil.  The possibility of persons falling into the excavations is normally considered a medium risk  Flooding of excavations is usually designated a low risk.
  • 49. Risk Assessment for Confined Space – Case Study Steps in the Risk Assessment Process 1 Describe the activity/task, equipment, process or facility for which the risk assessment s being carried out. 2 Identify all potential hazards associated with the activity/task, equipment, process or facility. 3 Identify the people who may be at risk. 4 Assess the risk based on the severity of the hazards, an likelihood of occurrence/exposure. 5 Describe the measures necessary to control the identified risks based on the HoC in ANSI Z590.3 6 Re-assess the risk based on the planned/recommended controls to determine the residual risk. 7 Document the details of the person(s) carrying out the risk assessment and time. 8 Document and record the risk assessment exercise.
  • 50. Knowledge Check Q1 A hazard is defined as the potential to cause harm. T F Q2 Risk is defined as the likelihood that harm will occur. T F Q3 Risk avoidance is the first level in ANSI Z590.3 HoCs. T F Q4 PPEs is the last line of defense is risk control. T F Q5 Potential control measures may be obtained from trade associations, trade unions or employers’ organizations. T F