2. Independent Vs. Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 A B(4) C(2) D(2) E(1) D(3) F(2) Independent Demand Items Dependent Demand Items
3.
4.
5.
6.
7. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 Create a production schedule to satisfy demand B(4) E(1) D(2) C(2) F(2) D(3) A Product Structure Tree for Assembly A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares)
8.
9.
10. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 LT=1 day B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 Order placement 50
11. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 4 B’s go into an A B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 Order placement 50 B Required 20 200 Order placement 20 200
12. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 LT=2 days (from A) B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 Order placement 50 B Required 20 200 Order placement 20 200
13. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 LT=2 days (spares) B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 Order placement 50 B Required 20 200 Order placement 20 200
14. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 2 C’s go into an A B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 Order placement 50 C Required 100 Order placement 100
15. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 LT=1 day (from A) B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 Order placement 50 C Required 100 Order placement 100
16. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 2 D’s go into a B B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 B Required 20 200 Order placement 20 200 C Required 100 Order placement 100 D Required 40 400 300 Order placement 40 400 300
17. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 3 D’s go into a C B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 B Required 20 200 Order placement 20 200 C Required 100 Order placement 100 D Required 40 400 300 Order placement 40 400 300
18. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 Demand for spares : 40+ 15 =55 B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 B Required 20 200 Order placement 20 200 C Required 100 Order placement 100 D Required 55 400 300 Order placement 55 400 300
19. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 LT=3 days (from B and C and spares) B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 B Required 20 200 Order placement 20 200 C Required 100 Order placement 100 D Required 55 400 300 Order placement 55 400 300
20. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 1 E goes into a B B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 B Required 20 200 Order placement 20 200 E Required 20 200 Order placement 20 200
21. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 LT=4 days (from B) B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 B Required 20 200 Order placement 20 200 E Required 20 200 Order placement 20 200
22. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 2 F’s go into a C B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 C Required 100 Order placement 100 F Required 200 Order placement
23. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 LT=1 day (from C) B(4) E(1) D(2) C(2) F(2) D(3) A Lead Times A: 1 day B: 2 days C: 1 day D: 3 days E: 4 days F: 1 day Demand Day 10: 50 A Day 8: 20 B (Spares) Day 6: 15 D (Spares) Item Day: 1 2 3 4 5 6 7 8 9 10 C Required 100 Order placement 100 F Required 200 Order placement 200
24. Example - Dependent Demand 250-450 Dr. Tom Bramorski Slide of 57 Item Day: 1 2 3 4 5 6 7 8 9 10 A Required 50 Order placement 50 B Required 20 200 Order placement 20 200 C Required 100 Order placement 100 D Required 55 400 300 Order placement 55 400 300 E Required 20 200 Order placement 20 200 F Required 200 Order placement 200
25.
26.
27. Time Fences 250-450 Dr. Tom Bramorski Slide of 57 8 15 26 Weeks Frozen Moderately Firm Flexible Firm Customer Orders Forecast and available capacity Capacity
28.
29. Production Planning Hierarchy 250-450 Dr. Tom Bramorski Slide of 57 Firm orders from known customers Forecast of demand from random customers Aggregate Product Plan Master Production Schedule (MPS) Material Requirements Planning (MRP) Engineering design changes Bill of Materials (BOM) file Inventory transactions Inventory records file Reports
30. Inputs To and Outputs From MRP 250-450 Dr. Tom Bramorski Slide of 57 Order Changes Planning Reports MRP System Inventory Transaction Data Bill of Materials File Master Production Schedule Inventory Status File Service-Parts Orders and Forecasts Performance Reports Inputs Outputs Planned Order Schedule Exception Reports
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49. Closed Loop MRP 250-450 Dr. Tom Bramorski Slide of 57 Production Planning Master Production Scheduling Material Requirements Planning Capacity Requirements Planning Realistic? No Feedback Execute: Capacity Plans Material Plans Yes Feedback
50.
51.
52. MRP Example #2 250-450 Dr. Tom Bramorski Slide of 57 A(2) C(3) B(1) D(5) C(2) X Product Structure Tree for X Item Lead-time (weeks) On-hand quantity X 2 50 A 3 75 B 1 25 C 2 10 D 2 20
53. MRP Example #2 250-450 Dr. Tom Bramorski Slide of 57 Create a planned order release schedule The requirements for product X include 95 units (80 firm orders and 15 forecast) for X in week 10. In addition, there is independent demand for other items (spares), as shown in the MPS below: Week Item 1 2 3 4 5 6 7 8 9 10 X 95 A 12 B 7 C 10 D 15