SlideShare uma empresa Scribd logo
1 de 10
Table of contents 
1. General. 
2. Management Organization Chart 
3. Sequence of works. 
4. Formwork design. 
5. Construction joint treatment. 
6. Re bars fabrication & setting. 
7. Installation of embed item. 
8. Placing of concrete. 
9. Compaction of concrete. 
10.Removal of formworks 
11.Curing 
12.Protecting against raining 
13.Electricity 
14.Equipment & Manpower 
Appendix 
A. First floor plan 
B. Typical formworks & Scaffolding arrangement. 
1. General
This method statement describes how we carry out the concrete works of column in 
building works. 
Concrete class shall be approved ready-mix concrete B25 (Grade 35NM/m2) 
Please refer to Appendix A for first floor plan of three main building. 
2. Management Organization Chart 
Mr. N.N.Hai 
HSE Manager 
Mr. Tran Thanh Minh 
Site Engineer 
Mr. Hoang Hung 
Site Engineer 
Sub Contractor Sub Contractor 
2.1 Project Manager 
Mr. T. UCHIDA 
Project Manager 
Mr. A . IKEGAMI 
Construction 
Manager 
Mr. A.M. Cabonce 
QA/QC Manager 
Mr. K.Miyara 
Chief Engineer 
Mr. P. C. TRUNG 
Chief site Engineer 
Mr. Dang Trong Dung 
Site Engineer 
Sub Contractor 
· To oversee and control all aspects of the Piling activities, and dictate schedule 
requirements 
· To ensure that all field staff are fully aware of the requirements of this method 
statement, and that these requirements, in all respects, are fully implemented. 
· To ensure that Safety and Environmental procedures, particularly, are in place 
before activity commences, and strictly complied with, throughout the duration 
of concreting works.
2.2 Construction Managers, directly reports to Project Manager. 
· To oversee all construction works, with respect to schedule. 
· To ensure that all field staff follow the requirements of this method statement, 
including quality control and HSE. 
2.3 Chief Engineer, reports to Construction Manager 
· To ensure that all relevant preparations have been made. 
· To ensure that all provisions of this method statement are followed. 
· To ensure that all quality inspection is carried out and record taken, if 
required. 
· To ensure that all necessary safety and environmental precautions are in 
place and that all workers under their direct control are fully aware of all 
procedure requirements 
· To control execution of the entire activity 
2.4 Site Engineer 
· To assist Chief Engineer to control the Subcontractor for all activities relative 
to this method statement. 
· To ensure safe working environment at all times, during Subcontractor 
execution of concreting works. 
2.5 Surveyor 
· To give control points & grid line to Subcontractor for concreting works. 
· To supervise Subcontractor and conduct survey checks from time to time. 
· To carry out all surveying work and to ensure all required records are taken 
and maintained. 
2.6 QA/QC department 
· To oversee construction activity with respect to quality control. 
· To ensure quality procedures has been followed.
· To ensure that all required inspections have been carried out and that 
records, if required have been taken and properly stored. 
· Advise the laboratory and Site Engineers to control the quality of works. 
2.7 Health, Safety & Environmental department 
· To monitor that all the working activities are executed in accordance with site 
Construction Joint 
treatment 
safety procedures. 
· To ensure that precautions with respect to Environmental matters have been 
implemented on site. 
3. Sequence of works. 
Assembling re bar 
Inspection of re bar 
Setting Formwork & Form oil 
sheathing 
Setting Temporary Staging for 
casting 
Inspection for casting 
concrete 
Placing Concrete
Stripping of form works 
Curing for Concrete 
4. Formworks Design 
Formwork shall be set in correct position following specification and the approved 
structure drawing. Temporary opening will be provided at bottom & middle of column for 
cleaning, inspection & casting purpose. 
Please refer to Appendix B for detail of formworks for each building. 
Approved form oil will be applied to form surface prior to installation of form. 
5. Construction joint treatment 
All construction joints will be chipped to remove cement sand surface to make rough 
surface. 
In some cases, approved retarder for concrete surface will be used as another method 
to make construction joint properly. 
6. Rebar fabrication & setting 
Approved re-bar type will be delivered to site and it will be inspected & tested prior to 
use. 
Re-bar shall be cut and bent according to the approved schedule at the site workshop 
and transport to site by truck. After delivery to the site re-bars shall be fixed according to 
specification and approved drawings by Engineer or Consultant. 
Rebar shall be inspected by Engineer or Consultant before setting of formworks. 
Approved concrete spacer shall be used; its concrete grade shall be 35 MN/m2.
7. Installation of embed item 
All the embed item showing in the drawings shall be firmly installed in correct position. 
8. Placing of Concrete 
Approved ready-mix concrete will be transported from batching plant to the site by mixer 
truck. During transportation & waiting time the concrete shall be kept continuously 
agitated. 
From mixer truck concrete will be poured to casting location by concrete pump or by 
bucket. The height from discharge position to casting level shall not be over 1.5m. 
On each concreting day and for each grade of concrete mix, samples shall be taken. 
When samples are taken at sites, samples shall be taken for every 24m3 of concrete or 
part thereof, of each grade of concrete. 
Minimum requirement of sample 
- Each concreting day 
- Each part of structure (each building) 
- After filling above condition, samples shall be taken for every four mixer or 
agitating truck (20~24m2). 
9. Compaction of Concrete. 
Concrete after pouring to position shall be compacted by immersion vibrator. Proper 
staging for vibration works will be arranged. 
Wooden or rubber hammer also will be used as external vibrator. 
Please refer to Appendix B for scaffolding arrangement. 
10. Removal of formworks 
Form works removal shall be accordance with specification. 
All tie rod holes & defects on surface will be repaired following approved method.
11. Curing. 
After removal of form works, concrete shall be cured minimum of 6 days according to 
TCXDVN 391:2007– Requirements for Natural Moist Curing, apply for Area C of Viet 
Nam. 
Curing of concrete will be carried out by spraying water periodically to the surface of the 
newly placed concrete. Jute bag or nylon sheet shall be used to cover the concrete 
surface for keeping wet. 
Water to be used for curing and cleaning works is portable water from local authority. 
Approved curing compound also can be used in several cases. 
12. Protecting against raining. 
Against raining, plastic sheet shall be prepared to cover over the concrete area before 
concreting. 
13. Electricity 
Electricity will be supplied by generators on site. 
14. Equipment & Manpower 
a)Equipment 
Equipment Unit Quantity 
Mixer truck Nos 04 
Vibrator Nos 03 
Concrete Pump No 01 
Water Pump 2 HP No 01 
Water Pump 1HP No 01 
Generator 15KVA No 01 
Generator 10KVA Nos 02 
Bucket Nos 10 
Showel Nos 05 
Trowel Nos 05 
b)Manpower 
Description Unit Quantity 
Supervisor No 01
Surveyor Nos 02 
Foreman No 01 
Electrician No 01 
Worker Nos 10 
APPENDIX A 
FIRST FLOOR PLAN
APPENDIX B 
TYPICAL FORMWORKS & 
SCAFFOLDING ARRANGEMENT

Mais conteúdo relacionado

Mais procurados

Building Construction
Building ConstructionBuilding Construction
Building Construction
Wilden How
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
Minh Bui Si
 
Method stm lean concrete
Method stm lean concreteMethod stm lean concrete
Method stm lean concrete
Minh Bui Si
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
Minh Bui Si
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
Ranjith Kumar
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
Minh Bui Si
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
Minh Bui Si
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''
Nabeel Rajpoot
 

Mais procurados (20)

PHC pile Installation methods
PHC  pile Installation methodsPHC  pile Installation methods
PHC pile Installation methods
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
 
Method stm lean concrete
Method stm lean concreteMethod stm lean concrete
Method stm lean concrete
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Piling work method statement cm- ms- bw - 002
Piling work method statement   cm- ms- bw - 002Piling work method statement   cm- ms- bw - 002
Piling work method statement cm- ms- bw - 002
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
 
Method statement honycomb repairing
Method statement  honycomb repairingMethod statement  honycomb repairing
Method statement honycomb repairing
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion joint
 
Material approval procedure
Material approval procedureMaterial approval procedure
Material approval procedure
 
Ms for concrete repairing
Ms for concrete repairingMs for concrete repairing
Ms for concrete repairing
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT
 
Construction process''column,beam,slab''
Construction process''column,beam,slab''Construction process''column,beam,slab''
Construction process''column,beam,slab''
 
Project Execution Plan for Bridge Construction
Project Execution Plan for Bridge ConstructionProject Execution Plan for Bridge Construction
Project Execution Plan for Bridge Construction
 

Semelhante a Column & beam

Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
hlksd
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
Ali Issa
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
Minh Bui Si
 
A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)
Ahmed Youssef
 
Hassan Essa CV (20)
Hassan Essa CV (20)Hassan Essa CV (20)
Hassan Essa CV (20)
Hassan Essa
 

Semelhante a Column & beam (20)

Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
Method statement of temporary office and fa
Method statement of temporary office and faMethod statement of temporary office and fa
Method statement of temporary office and fa
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
1008 caissons-specification
1008 caissons-specification1008 caissons-specification
1008 caissons-specification
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)A.youssef_c.v.2014.doc-2(3)
A.youssef_c.v.2014.doc-2(3)
 
HCB Manual gtz 2008.doc
HCB Manual gtz 2008.docHCB Manual gtz 2008.doc
HCB Manual gtz 2008.doc
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concrete
 
Precast
PrecastPrecast
Precast
 
Advanced Building Measurement
Advanced Building MeasurementAdvanced Building Measurement
Advanced Building Measurement
 
Concreting work
Concreting workConcreting work
Concreting work
 
Hassan Essa CV (20)
Hassan Essa CV (20)Hassan Essa CV (20)
Hassan Essa CV (20)
 
Manual Of Concrete Compression Test
Manual Of Concrete Compression Test Manual Of Concrete Compression Test
Manual Of Concrete Compression Test
 
AH15019
AH15019AH15019
AH15019
 
PREFABRICATION BUILDING
PREFABRICATION BUILDINGPREFABRICATION BUILDING
PREFABRICATION BUILDING
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposal
 
distress of concrete
distress of concretedistress of concrete
distress of concrete
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 

Column & beam

  • 1. Table of contents 1. General. 2. Management Organization Chart 3. Sequence of works. 4. Formwork design. 5. Construction joint treatment. 6. Re bars fabrication & setting. 7. Installation of embed item. 8. Placing of concrete. 9. Compaction of concrete. 10.Removal of formworks 11.Curing 12.Protecting against raining 13.Electricity 14.Equipment & Manpower Appendix A. First floor plan B. Typical formworks & Scaffolding arrangement. 1. General
  • 2. This method statement describes how we carry out the concrete works of column in building works. Concrete class shall be approved ready-mix concrete B25 (Grade 35NM/m2) Please refer to Appendix A for first floor plan of three main building. 2. Management Organization Chart Mr. N.N.Hai HSE Manager Mr. Tran Thanh Minh Site Engineer Mr. Hoang Hung Site Engineer Sub Contractor Sub Contractor 2.1 Project Manager Mr. T. UCHIDA Project Manager Mr. A . IKEGAMI Construction Manager Mr. A.M. Cabonce QA/QC Manager Mr. K.Miyara Chief Engineer Mr. P. C. TRUNG Chief site Engineer Mr. Dang Trong Dung Site Engineer Sub Contractor · To oversee and control all aspects of the Piling activities, and dictate schedule requirements · To ensure that all field staff are fully aware of the requirements of this method statement, and that these requirements, in all respects, are fully implemented. · To ensure that Safety and Environmental procedures, particularly, are in place before activity commences, and strictly complied with, throughout the duration of concreting works.
  • 3. 2.2 Construction Managers, directly reports to Project Manager. · To oversee all construction works, with respect to schedule. · To ensure that all field staff follow the requirements of this method statement, including quality control and HSE. 2.3 Chief Engineer, reports to Construction Manager · To ensure that all relevant preparations have been made. · To ensure that all provisions of this method statement are followed. · To ensure that all quality inspection is carried out and record taken, if required. · To ensure that all necessary safety and environmental precautions are in place and that all workers under their direct control are fully aware of all procedure requirements · To control execution of the entire activity 2.4 Site Engineer · To assist Chief Engineer to control the Subcontractor for all activities relative to this method statement. · To ensure safe working environment at all times, during Subcontractor execution of concreting works. 2.5 Surveyor · To give control points & grid line to Subcontractor for concreting works. · To supervise Subcontractor and conduct survey checks from time to time. · To carry out all surveying work and to ensure all required records are taken and maintained. 2.6 QA/QC department · To oversee construction activity with respect to quality control. · To ensure quality procedures has been followed.
  • 4. · To ensure that all required inspections have been carried out and that records, if required have been taken and properly stored. · Advise the laboratory and Site Engineers to control the quality of works. 2.7 Health, Safety & Environmental department · To monitor that all the working activities are executed in accordance with site Construction Joint treatment safety procedures. · To ensure that precautions with respect to Environmental matters have been implemented on site. 3. Sequence of works. Assembling re bar Inspection of re bar Setting Formwork & Form oil sheathing Setting Temporary Staging for casting Inspection for casting concrete Placing Concrete
  • 5. Stripping of form works Curing for Concrete 4. Formworks Design Formwork shall be set in correct position following specification and the approved structure drawing. Temporary opening will be provided at bottom & middle of column for cleaning, inspection & casting purpose. Please refer to Appendix B for detail of formworks for each building. Approved form oil will be applied to form surface prior to installation of form. 5. Construction joint treatment All construction joints will be chipped to remove cement sand surface to make rough surface. In some cases, approved retarder for concrete surface will be used as another method to make construction joint properly. 6. Rebar fabrication & setting Approved re-bar type will be delivered to site and it will be inspected & tested prior to use. Re-bar shall be cut and bent according to the approved schedule at the site workshop and transport to site by truck. After delivery to the site re-bars shall be fixed according to specification and approved drawings by Engineer or Consultant. Rebar shall be inspected by Engineer or Consultant before setting of formworks. Approved concrete spacer shall be used; its concrete grade shall be 35 MN/m2.
  • 6. 7. Installation of embed item All the embed item showing in the drawings shall be firmly installed in correct position. 8. Placing of Concrete Approved ready-mix concrete will be transported from batching plant to the site by mixer truck. During transportation & waiting time the concrete shall be kept continuously agitated. From mixer truck concrete will be poured to casting location by concrete pump or by bucket. The height from discharge position to casting level shall not be over 1.5m. On each concreting day and for each grade of concrete mix, samples shall be taken. When samples are taken at sites, samples shall be taken for every 24m3 of concrete or part thereof, of each grade of concrete. Minimum requirement of sample - Each concreting day - Each part of structure (each building) - After filling above condition, samples shall be taken for every four mixer or agitating truck (20~24m2). 9. Compaction of Concrete. Concrete after pouring to position shall be compacted by immersion vibrator. Proper staging for vibration works will be arranged. Wooden or rubber hammer also will be used as external vibrator. Please refer to Appendix B for scaffolding arrangement. 10. Removal of formworks Form works removal shall be accordance with specification. All tie rod holes & defects on surface will be repaired following approved method.
  • 7. 11. Curing. After removal of form works, concrete shall be cured minimum of 6 days according to TCXDVN 391:2007– Requirements for Natural Moist Curing, apply for Area C of Viet Nam. Curing of concrete will be carried out by spraying water periodically to the surface of the newly placed concrete. Jute bag or nylon sheet shall be used to cover the concrete surface for keeping wet. Water to be used for curing and cleaning works is portable water from local authority. Approved curing compound also can be used in several cases. 12. Protecting against raining. Against raining, plastic sheet shall be prepared to cover over the concrete area before concreting. 13. Electricity Electricity will be supplied by generators on site. 14. Equipment & Manpower a)Equipment Equipment Unit Quantity Mixer truck Nos 04 Vibrator Nos 03 Concrete Pump No 01 Water Pump 2 HP No 01 Water Pump 1HP No 01 Generator 15KVA No 01 Generator 10KVA Nos 02 Bucket Nos 10 Showel Nos 05 Trowel Nos 05 b)Manpower Description Unit Quantity Supervisor No 01
  • 8. Surveyor Nos 02 Foreman No 01 Electrician No 01 Worker Nos 10 APPENDIX A FIRST FLOOR PLAN
  • 9.
  • 10. APPENDIX B TYPICAL FORMWORKS & SCAFFOLDING ARRANGEMENT