Working with Scrum

            Douwe van der Meij

   Goldmund, Wyldebeast & Wunderliebe
vandermeij@gw20e.com
@douwevandermeij
Outline
●   History of scrum
●   Scrum
●   Tooling
●   Conclusion
History
Holistic/Rugby approach
● 1986
● Hirotaka Takeuchi, Ikujiro Nonaka
● New production line tactic
  ○ Increase speed & flexibility
● Based on case studies:
  ○ Automotive, photocopier, restaurant food and
    printer industries
● Like a rugby game
  ○ To gain distance as a group
Scrum
● 1991
● First referred to as Scrum by: Peter
  DeGrace, Leslie Hulet Stahl

● Like scrummage
  (abbr. scrum) in
  rugby
Scrum-like approaches
● 1990's
● Ken Schwaber
  ○ Described "Advanced Development Methods"


● 1993
● Jeff Sutherland, John Scumniotales, Jeff
  McKenna
  ○ Similar approach at Easel Corporation
First workshop
● 1995
● Sutherland, Schwaber
  ○ First presentation/workshop at OOPSLA '95, Austin
    Texas


● They merged all earlier writings
Meanwhile
● 1999
● Mike Beedle
  ○ Scrum patterns
  ○ Chapter in book: "Pattern
    Languages of Program
    Design 4"
Combined forces
● 2001
● Schwaber, Beedle
  ○ Book: "Agile Software
    Development with SCRUM"
Since then...
● A lot of literature appeared
   ○ Mike Cohn


● A lot of companies started using scrum
   ○ In a way
Common sayings:
● "We already use scrum"
● "We don't actually use all parts of scrum
  because ..."
   ○   "... we are a (too) small company"
   ○   "... there is a fixed scope"
   ○   "... the project is fixed price"
   ○   "... the projects are too small"
   ○   "... each project is a project on its own"
   ○   "... we use another method"
Scrum
Roles
● Project manager
● Development team

● Product owner (PO)
● Scrum master
Product owner
● The product owner represents the customer
● The product owner represents the supplier
  ○ The product owner approves finished user stories

                      PO                  Development
                                             team


  Management
                     Scrum master
Product owner
● Two-fold role / pivot point
   ○ Responsible for the user stories
     ■ Towards the development team
   ○ Responsible for the deliverables
     ■ Towards the management
Scrum master
● Process owner
  ○ Guards the process
● Takes care of impediments
  ○ Every impediment you can think of, regarding the
    project
● Mediator
  ○ For everyone
Sprints
● Work takes place in sprints
● Time boxed iterations, fixed!
Sprints
● Development team works on
  ○ Implementing planned user stories
  ○ Defining new user stories


● Product owner works on
  ○ Approving finished user stories
  ○ Defining new user stories
  ○ Prioritizing user stories
User story
● Description of a task that the application is
  supposed to do for a certain reason and can
  be measured.
User story

               " As an <actor>,
              I want to <action>
             because <reason> "
User story
● <actor>
  ○ A user that can perform and measure the action
● <action>
  ○ Something that the application is supposed to do
● <reason>
  ○ Background information to give context to story
User story
● Everyone can should create user stories at
  any time

● Be precise and concise

● Product owner keeps the overview
● Approval only by a product owner
User story
● When is it ready?

● Define visible indicators (measurability)
● Define a (global) "Definition of Done" (DoD)
  ○ Example:
    ■ Tests
    ■ Documentation (e.g., in code, user manual)
User story evolution
Overview (general)
User story lifecycle

                                         Prioritized
                                          backlog


                                                        Sprint
                                                       backlog
                 Backlog




                            Commitment




      Product
     increment    Testing
User story lifecycle

                                         Prioritized
                                          backlog


                                                        Sprint
                                                       backlog
                 Backlog




                            Commitment




      Product
     increment    Testing
How to do that?
Ceremonies
In order of appearance:
● (User story workshop)
● Planning poker
● PO-presentation
● Team planning / commitment
● Daily stand-up
● Review meeting
● Retrospective meeting
Ceremonies
Schematic:

                                           Sprint
               PO
 Planning              Team                                              Retro-
            presen-                                            Review
  poker               planning                                          spective
              tatie
                                   Daily     Daily     Daily
                                 standup   standup   standup
Planning poker
● For all user stories
    ○ Discuss the goal
● Find spikes

●   Discussion = information
●   Questions = important to subject
●   Add all information to user story
●   Define "Definition of Done (DOD)"
Planning poker
● For all user stories
● Grade in terms of:
   ○ Complexity
   ○ Amount of time to implement

              0   ½      1   2      3    5



              8   13   20    40    100   ?
Planning poker
● Use your gut feeling
● The more you poker the better you draw

● Provides insights in thoughts of the
  developers about the implementation
Rules of planning poker
● The user story gets the (highest) score ...
  a. ... that is unanimously chosen
  b. ... when there is a difference of at most 1 card

● When difference > 1 card
  a. Discuss differences (especially outliers)
  b. Re-estimate until estimates converge
Business value poker
● For all ideas about the project
● Grade in terms of importance / business
  value

              100   200    300    500



              800   1300   2000   3000
Business value poker
● Done by PO & management
● Defines priority
  ○ The most important and least complex user stories
    get done first
  ○ The least important and most complex user stories
    get done later
                  Business value score
       Priority =
                      Story points
Re-modeling your kitchen
                                 Product item backlog                     Estimate

  a   Install new hardwood floor

  b   Sand and re-paint cabinets

  c   Replace tile countertop with granite

  d   Re-paint entire kitchen

  e   Lay shelf paper

  f   Install recessed (down) lighting

  g   Install a built-in refrigerator

  h   Replace existing oven with a new one

  i   Run a water line to existing island and install a sink

  j   Replace existing simple window with a bay window

                                                               Copyright © 2011, Mountain Goat Software
PO-presentation
● Present general direction of the product
● Present voted prioritized backlog
● The complete development team is
  attending
● Developers ask questions about the
  implementation
● All developers must have a clear
  understanding of each user story
Team planning / commitment
● Development team pulls in user stories and
  commits to delivery

● User stories that certainly get finished
   ○ Actual commitment
● User stories that maybe get finished
   ○ Bonus


● Psychological effect
Team planning / commitment




                https://learn.test.dau.mil/CourseWare/800949_1/pbl0202/pbl0202_0080p1.htm
Daily stand-up
● Talk about the user stories under
  development
  ○ Yesterday
  ○ Today
  ○ Impediments
● Discuss mini-spikes
Review meeting
● Discuss spike results
● Discuss the user stories worked on

● Re-calibrate planning poker, if needed
● Calculate team velocity
Retrospective meeting
● What went well
● What went wrong
● What to improve
  ○ Inspect and adapt


● If we can't improve, we're doing something
  wrong
  ○ Should end up in actions for the next sprint
Inspect and adapt
Overview (total)




                   © 2010 Pete Deemer, Gabrielle Benefield, Craig Larman, Bas Vodde
Metrics
Team velocity
● The amount of story points the team is able
  to process during a sprint

● Refined/more precise after each sprint
Burndown chart
● Hours left (and spent)
● Ahead of / behind schedule
Burnup chart
● Total nr. of story points
● Nr. of approved story points
Relation between charts
Tooling
Tools
●   Jira
●   Trac
●   Lighthouse
●   Spreadsheet
Lighthouse
● www.lighthouseapp.com
● Slightly other terminology
   ○ Sprints → Milestones
   ○ User stories → Tickets
● Signalling with tickets/milestones
Ticket responsible
● Unassigned
  ○ Not yet pulled by a team member


● Assigned
  ○ Someone is working on / responsible for this ticket


● Tip:
  ○ Max. 1 ticket assigned to a person except PO, or
    have a good reason not to
Ticket milestone (sprint)
● Not linked
  ○ Ticket is in the product backlog
  ○ Doesn't need to be voted yet
  ○ Doesn't need to be prioritized


● Linked
  ○ Ticket is in the sprint backlog
  ○ Must be voted
  ○ Is prioritized
The product backlog
● All unlinked tickets (not linked to milestone)
● All tickets linked to older milestones

● Product owner should watch this closely
● Prepare (tickets) before poker planning
  meeting
Conclusion
Conclusion
●   Define user stories, find spikes
●   Do planning poker
●   Do PO-presentations
●   Only work on planned user stories
    ○ No more, no less
● Find your team velocity

● Timeboxed sprints, no excuses!
    ○ 1 to 4 weeks
Thank you!
            Douwe van der Meij

   Goldmund, Wyldebeast & Wunderliebe
vandermeij@gw20e.com
@douwevandermeij
Kanban
● Signaling system
● Ideal for small projects

● Priority queue
● WIP limit
   ○ Nr. of user stories in progress
Kanban

Not planned   Planned    In progress Testing   Done




                         Max. 3
                         WIP Limit

              Priority
              queue

Mais conteúdo relacionado

Destaque (10)

Familyandjuveniledelinquency 090824170709-phpapp02
Familyandjuveniledelinquency 090824170709-phpapp02Familyandjuveniledelinquency 090824170709-phpapp02
Familyandjuveniledelinquency 090824170709-phpapp02
 
The Film Industry
The Film IndustryThe Film Industry
The Film Industry
 
20131019 digital collections - if you build them will anyone visit [library 2...
20131019 digital collections - if you build them will anyone visit [library 2...20131019 digital collections - if you build them will anyone visit [library 2...
20131019 digital collections - if you build them will anyone visit [library 2...
 
De guias ppodddddddd
De guias ppoddddddddDe guias ppodddddddd
De guias ppodddddddd
 
Argia
ArgiaArgia
Argia
 
antihyper lipidemia & plantcons
antihyper lipidemia & plantconsantihyper lipidemia & plantcons
antihyper lipidemia & plantcons
 
Andrulius
AndruliusAndrulius
Andrulius
 
IWB Workshop Part 1: Reveal Techniques
IWB Workshop Part 1: Reveal TechniquesIWB Workshop Part 1: Reveal Techniques
IWB Workshop Part 1: Reveal Techniques
 
เฉลยสถาบันหลักของชาติ M.5
เฉลยสถาบันหลักของชาติ M.5เฉลยสถาบันหลักของชาติ M.5
เฉลยสถาบันหลักของชาติ M.5
 
From hear to there
From hear to thereFrom hear to there
From hear to there
 

Semelhante a Scrum in practice

Agile – scrum +
Agile – scrum +Agile – scrum +
Agile – scrum +
Alon Lahav
 
An Introduction to Scrum: presented at PyTexas 2012
An Introduction to Scrum: presented at PyTexas 2012An Introduction to Scrum: presented at PyTexas 2012
An Introduction to Scrum: presented at PyTexas 2012
Tomo Popovic
 

Semelhante a Scrum in practice (20)

Running Agile on a non-Agile Environment, by Nuno Caneco
Running Agile on a non-Agile Environment, by Nuno CanecoRunning Agile on a non-Agile Environment, by Nuno Caneco
Running Agile on a non-Agile Environment, by Nuno Caneco
 
Running Scrum on a non-Agile environment - Tales from a past experience" By N...
Running Scrum on a non-Agile environment - Tales from a past experience" By N...Running Scrum on a non-Agile environment - Tales from a past experience" By N...
Running Scrum on a non-Agile environment - Tales from a past experience" By N...
 
GUI & Modern UI Design
GUI & Modern UI DesignGUI & Modern UI Design
GUI & Modern UI Design
 
Laura Delnevo - Winning your clients' trust with Agile project management
Laura Delnevo - Winning your clients' trust with Agile project managementLaura Delnevo - Winning your clients' trust with Agile project management
Laura Delnevo - Winning your clients' trust with Agile project management
 
Hack 2.0 Lego Agile Workshop
Hack 2.0 Lego Agile WorkshopHack 2.0 Lego Agile Workshop
Hack 2.0 Lego Agile Workshop
 
Agile and Scrum - GB
Agile and Scrum - GBAgile and Scrum - GB
Agile and Scrum - GB
 
Scrum master
Scrum masterScrum master
Scrum master
 
Scrum overview
Scrum overviewScrum overview
Scrum overview
 
Agile and Scrum Overview for PMs, Designers and Developers
Agile and Scrum Overview for PMs, Designers and Developers Agile and Scrum Overview for PMs, Designers and Developers
Agile and Scrum Overview for PMs, Designers and Developers
 
Art of Estimation. Vlad Savitsky
Art of Estimation. Vlad SavitskyArt of Estimation. Vlad Savitsky
Art of Estimation. Vlad Savitsky
 
Agile Scrum Mastery: Learn How To Bring Complex Projects To life!
Agile Scrum Mastery: Learn How To Bring Complex Projects To life!Agile Scrum Mastery: Learn How To Bring Complex Projects To life!
Agile Scrum Mastery: Learn How To Bring Complex Projects To life!
 
Agile – scrum +
Agile – scrum +Agile – scrum +
Agile – scrum +
 
Common Sense Agile
Common Sense AgileCommon Sense Agile
Common Sense Agile
 
An Introduction to Scrum: presented at PyTexas 2012
An Introduction to Scrum: presented at PyTexas 2012An Introduction to Scrum: presented at PyTexas 2012
An Introduction to Scrum: presented at PyTexas 2012
 
Being Productive at Work
Being Productive at WorkBeing Productive at Work
Being Productive at Work
 
Agile Scrum Training Process
Agile Scrum Training ProcessAgile Scrum Training Process
Agile Scrum Training Process
 
Agile Estimation & Planning by Bachan Anand
Agile Estimation & Planning by Bachan AnandAgile Estimation & Planning by Bachan Anand
Agile Estimation & Planning by Bachan Anand
 
Agile in summary (and scrum)
Agile in summary (and scrum)Agile in summary (and scrum)
Agile in summary (and scrum)
 
Agile or: how I learned to stop worrying and love changing requirements
Agile or: how I learned to stop worrying and love changing requirementsAgile or: how I learned to stop worrying and love changing requirements
Agile or: how I learned to stop worrying and love changing requirements
 
Introduction to Scrum
Introduction to ScrumIntroduction to Scrum
Introduction to Scrum
 

Último

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Victor Rentea
 

Último (20)

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdfRising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
Rising Above_ Dubai Floods and the Fortitude of Dubai International Airport.pdf
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 

Scrum in practice

  • 1. Working with Scrum Douwe van der Meij Goldmund, Wyldebeast & Wunderliebe vandermeij@gw20e.com @douwevandermeij
  • 2. Outline ● History of scrum ● Scrum ● Tooling ● Conclusion
  • 4. Holistic/Rugby approach ● 1986 ● Hirotaka Takeuchi, Ikujiro Nonaka ● New production line tactic ○ Increase speed & flexibility ● Based on case studies: ○ Automotive, photocopier, restaurant food and printer industries ● Like a rugby game ○ To gain distance as a group
  • 5. Scrum ● 1991 ● First referred to as Scrum by: Peter DeGrace, Leslie Hulet Stahl ● Like scrummage (abbr. scrum) in rugby
  • 6. Scrum-like approaches ● 1990's ● Ken Schwaber ○ Described "Advanced Development Methods" ● 1993 ● Jeff Sutherland, John Scumniotales, Jeff McKenna ○ Similar approach at Easel Corporation
  • 7. First workshop ● 1995 ● Sutherland, Schwaber ○ First presentation/workshop at OOPSLA '95, Austin Texas ● They merged all earlier writings
  • 8. Meanwhile ● 1999 ● Mike Beedle ○ Scrum patterns ○ Chapter in book: "Pattern Languages of Program Design 4"
  • 9. Combined forces ● 2001 ● Schwaber, Beedle ○ Book: "Agile Software Development with SCRUM"
  • 10. Since then... ● A lot of literature appeared ○ Mike Cohn ● A lot of companies started using scrum ○ In a way
  • 11. Common sayings: ● "We already use scrum" ● "We don't actually use all parts of scrum because ..." ○ "... we are a (too) small company" ○ "... there is a fixed scope" ○ "... the project is fixed price" ○ "... the projects are too small" ○ "... each project is a project on its own" ○ "... we use another method"
  • 12. Scrum
  • 13. Roles ● Project manager ● Development team ● Product owner (PO) ● Scrum master
  • 14. Product owner ● The product owner represents the customer ● The product owner represents the supplier ○ The product owner approves finished user stories PO Development team Management Scrum master
  • 15. Product owner ● Two-fold role / pivot point ○ Responsible for the user stories ■ Towards the development team ○ Responsible for the deliverables ■ Towards the management
  • 16. Scrum master ● Process owner ○ Guards the process ● Takes care of impediments ○ Every impediment you can think of, regarding the project ● Mediator ○ For everyone
  • 17. Sprints ● Work takes place in sprints ● Time boxed iterations, fixed!
  • 18. Sprints ● Development team works on ○ Implementing planned user stories ○ Defining new user stories ● Product owner works on ○ Approving finished user stories ○ Defining new user stories ○ Prioritizing user stories
  • 19. User story ● Description of a task that the application is supposed to do for a certain reason and can be measured.
  • 20. User story " As an <actor>, I want to <action> because <reason> "
  • 21. User story ● <actor> ○ A user that can perform and measure the action ● <action> ○ Something that the application is supposed to do ● <reason> ○ Background information to give context to story
  • 22. User story ● Everyone can should create user stories at any time ● Be precise and concise ● Product owner keeps the overview ● Approval only by a product owner
  • 23. User story ● When is it ready? ● Define visible indicators (measurability) ● Define a (global) "Definition of Done" (DoD) ○ Example: ■ Tests ■ Documentation (e.g., in code, user manual)
  • 26. User story lifecycle Prioritized backlog Sprint backlog Backlog Commitment Product increment Testing
  • 27. User story lifecycle Prioritized backlog Sprint backlog Backlog Commitment Product increment Testing
  • 28. How to do that?
  • 29. Ceremonies In order of appearance: ● (User story workshop) ● Planning poker ● PO-presentation ● Team planning / commitment ● Daily stand-up ● Review meeting ● Retrospective meeting
  • 30. Ceremonies Schematic: Sprint PO Planning Team Retro- presen- Review poker planning spective tatie Daily Daily Daily standup standup standup
  • 31. Planning poker ● For all user stories ○ Discuss the goal ● Find spikes ● Discussion = information ● Questions = important to subject ● Add all information to user story ● Define "Definition of Done (DOD)"
  • 32. Planning poker ● For all user stories ● Grade in terms of: ○ Complexity ○ Amount of time to implement 0 ½ 1 2 3 5 8 13 20 40 100 ?
  • 33. Planning poker ● Use your gut feeling ● The more you poker the better you draw ● Provides insights in thoughts of the developers about the implementation
  • 34. Rules of planning poker ● The user story gets the (highest) score ... a. ... that is unanimously chosen b. ... when there is a difference of at most 1 card ● When difference > 1 card a. Discuss differences (especially outliers) b. Re-estimate until estimates converge
  • 35. Business value poker ● For all ideas about the project ● Grade in terms of importance / business value 100 200 300 500 800 1300 2000 3000
  • 36. Business value poker ● Done by PO & management ● Defines priority ○ The most important and least complex user stories get done first ○ The least important and most complex user stories get done later Business value score Priority = Story points
  • 37. Re-modeling your kitchen Product item backlog Estimate a Install new hardwood floor b Sand and re-paint cabinets c Replace tile countertop with granite d Re-paint entire kitchen e Lay shelf paper f Install recessed (down) lighting g Install a built-in refrigerator h Replace existing oven with a new one i Run a water line to existing island and install a sink j Replace existing simple window with a bay window Copyright © 2011, Mountain Goat Software
  • 38. PO-presentation ● Present general direction of the product ● Present voted prioritized backlog ● The complete development team is attending ● Developers ask questions about the implementation ● All developers must have a clear understanding of each user story
  • 39. Team planning / commitment ● Development team pulls in user stories and commits to delivery ● User stories that certainly get finished ○ Actual commitment ● User stories that maybe get finished ○ Bonus ● Psychological effect
  • 40. Team planning / commitment https://learn.test.dau.mil/CourseWare/800949_1/pbl0202/pbl0202_0080p1.htm
  • 41. Daily stand-up ● Talk about the user stories under development ○ Yesterday ○ Today ○ Impediments ● Discuss mini-spikes
  • 42. Review meeting ● Discuss spike results ● Discuss the user stories worked on ● Re-calibrate planning poker, if needed ● Calculate team velocity
  • 43. Retrospective meeting ● What went well ● What went wrong ● What to improve ○ Inspect and adapt ● If we can't improve, we're doing something wrong ○ Should end up in actions for the next sprint
  • 45. Overview (total) © 2010 Pete Deemer, Gabrielle Benefield, Craig Larman, Bas Vodde
  • 47. Team velocity ● The amount of story points the team is able to process during a sprint ● Refined/more precise after each sprint
  • 48. Burndown chart ● Hours left (and spent) ● Ahead of / behind schedule
  • 49. Burnup chart ● Total nr. of story points ● Nr. of approved story points
  • 52. Tools ● Jira ● Trac ● Lighthouse ● Spreadsheet
  • 53. Lighthouse ● www.lighthouseapp.com ● Slightly other terminology ○ Sprints → Milestones ○ User stories → Tickets ● Signalling with tickets/milestones
  • 54. Ticket responsible ● Unassigned ○ Not yet pulled by a team member ● Assigned ○ Someone is working on / responsible for this ticket ● Tip: ○ Max. 1 ticket assigned to a person except PO, or have a good reason not to
  • 55. Ticket milestone (sprint) ● Not linked ○ Ticket is in the product backlog ○ Doesn't need to be voted yet ○ Doesn't need to be prioritized ● Linked ○ Ticket is in the sprint backlog ○ Must be voted ○ Is prioritized
  • 56. The product backlog ● All unlinked tickets (not linked to milestone) ● All tickets linked to older milestones ● Product owner should watch this closely ● Prepare (tickets) before poker planning meeting
  • 58. Conclusion ● Define user stories, find spikes ● Do planning poker ● Do PO-presentations ● Only work on planned user stories ○ No more, no less ● Find your team velocity ● Timeboxed sprints, no excuses! ○ 1 to 4 weeks
  • 59. Thank you! Douwe van der Meij Goldmund, Wyldebeast & Wunderliebe vandermeij@gw20e.com @douwevandermeij
  • 60. Kanban ● Signaling system ● Ideal for small projects ● Priority queue ● WIP limit ○ Nr. of user stories in progress
  • 61. Kanban Not planned Planned In progress Testing Done Max. 3 WIP Limit Priority queue