Falcon's Invoice Discounting: Your Path to Prosperity
23 03-2013
1. STATUS REPORT OF MY HOME ABHRA Tower-”A”As On 23.03.13
1.Basement-II Slab Completed.
2. Basement-I slab flat no 1 & 2 completed reaming slab planning today
3.Ground Floor slab Flat No 01 & 02 Shuttering Completed
2. STATUS REPORT OF MY HOME ABHRA Tower-”B”As On 23.03.13
1.Basement-II Slab Completed.
2.Basement-I Slab completed
3.Ground floor slab flat no 1 & 2 completed
4.First Floor flat no 01 & 02 Shuttering In Progress
3. STATUS REPORT OF MY HOME ABHRA Tower-”C”As On 23.03.13
1.Basement II Slab Completed.
2.Basement I flat no 01 Completed
3.Basement I flat no 02 Beam Bottom Shuttering work in progress
4. STATUS REPORT OF MY HOME ABHRA Tower-”D”As On 23.03.13
1.Basement II Slab Completed.
2.Basement I Slab Completed
3.Ground Floor flat no 1 & 02 Shuttering Completed
5. STATUS REPORT OF MY HOME ABHRA Tower-”E”As On 23.03.13
1.Basement II Slab Completed
2. Basement I slab for flat 1 &2 completed
3.Remains Slab Beam Bottom Shuttering Work In Progress
6. STATUS REPORT OF MY HOME ABHRA “CENTRAL LAWN”As On 23.03.13
1.Grade Slab- (Out Of 3-Parts) 1 Part Completed
2.Sand Leveling Work in Progress
7. STATUS REPORT OF MY HOME ABHRA “TOTAL SITE”As On 23.03.13
1.Total Site Basement II slab- Completed
2.Total site Basement I Slab (Except Tower-C 1flat and Tower-E 3 Flats)-Remaining Completed
3.Ground Floor slab Tower B 1&2 flats completed