SlideShare uma empresa Scribd logo
1 de 23
PROJECT MANAGEMENT
CAPTIVE
POWER
PLANT
PROJECT
Presentation by
Mahesh V. Kulkarni
Vth Term - Operations
Manipal University
 A Power plant
PROJECT – Turnkey in Nature
 2 x 2.5 MW Captive Power Plant spread over 4 acres of
land (free field)
 2 x G3612, 11 KV, 1500 RPM Natural Gas Gensets
 Customer: Southern Energy Development Corporation
Ltd. (SEDCO) – a Carborandum Universal Group
 Location: Nallur, Mannargudi (near Tanjavur), Tamilnadu
 Consultant: Aquatherm Consulting Engineers, Chennai
 Guarantees-
 Fuel Consumption,
 Lube oil Consumption,
 Genset output power
NEED FOR PROJECT MGMT.- WHY DID OUR COMPANY
FORM A PROJECT MGT. DEPARTMENT?
• Too many projects running
over time and over
budget
 Project scope creep
 Project management
responsibility not clear
 Too much emphasis on outputs
rather than
outcomes
 Insufficient emphasis on risks
Saves company TIME….MONEY
 Triple constraint
Quality
Scope
Time
Cost
Project department - Sandwich
Takeover from
Sales
Handover to Service
department
Sales Service
P
r
o
j
e
c
t
Five Phases of Project Management
 Phases
Developing the
Plan
Scoping the
Project
Launching the
Plan
Monitoring &
Controlling
Closing Out the
Project
Scoping the project- Primarily it is the definition and
control of what IS & IS NOT included in the project
Project Scoping Form
Project Name –
SEDCO
Project Manager –
Mahesh Kulkarni
Team Members –
05 nos.
Opportunity (Why do this project?): To earn profit
Project Goal: Smooth execution
Objectives: Timely completion within a allotted costs
Success Criteria (Outcomes): Effective commissioning of all
equipment by suppliers
Assumptions, Risks, Obstacles: Technological,Environmental,
Interpersonal, Cultural, Political
SCOPE
 Imported supply from USA – Value USD 1.5 Mn
 Indigenous supply (Balance of plant) – INR 2.62 Crores
 Erection of all supplied items
 Time frame – 6 months
 Imported scope by Letter of Credit
 Indigenous supply payment terms – 50 % advance, 30 % against supply
and 20 % after commissioning.
 33 KV Substation supply and erection by Bharat Bijlee
 Govt. approvals from 1. TNEB, 2. GAIL, 3. CEIG, 4. Pollution control board
 Total vendors in the project – 11 nos. (EPC Contractor – mechanical &
electrical, manufacturers of air compressors, air receivers, Radiator, NGR
Panel, Circuit breaker panel, MCC panel, main and auxiliary transformer,
LAVT panel, Control & Relay panel, etc.)
Developing The Plan
Construct/Analyze
Project Network
Prepare the
Project Proposal
Identify Project
Tasks (WBS)
Estimate Task
Duration
Determine Resource
Requirements
Project Planning Activity
• Create a work break
down structure (WBS)
for the project you
identified in the
scoping document.
Identify and sequence
tasks.
WBS - A WBS is the functional decomposition of a system, it breaks the
project into chunks of work at a level of detail that meets planning and
scheduling needs
WBS:
SEDCO PROJECT
3. CONSTRUCTION2. PROCUREMENT1. DESIGN & ENGINEERING
1.1 Sizing of
equipment
1.1.1 Foundation
1.1.2 Piping
layout
1.2 Drawings
1.3 Consultant
approvals
2.1 Order placement
2.1.1 Long
delivery items
2.1.2 Short
delivery items
2.2 Inspection
2.3 Clearance &
Transportation to
site
3.1 Unloading at site
& Erection
3.1.1 Erection of
equipment on foundation
3.1.2 Piping and cabling
3.2 Pre-commissioning
checks
3.3 Plant trial run
and handover
Advance
Project Planning: Resources
 1. People - skills and value
 2. Facilities – Office, AutoCAD,
computers and softwares, Vehicles,
etc.
 3. Equipment – like Crane –
hired
General Manager
…
DRAFTSMAN
…..
ELECTRICAL ENGR.
…….
Manager Projects
……..
SITE MANAGER
…….
Manager Projects
(S. Sridhar)
Project Manager
……
Commissioning Engr.
…..
Finance Manager
….
Principal …..
Suppliers for
indigenous supplies
(11 vendors)
Service Manager
(Singuttuvan)
Customer - SEDCO
(Project Mgr.)
Consultant–Aquatherm
….
4. Time – Six months
starting 1st
March
Role of a Project Manager
 Role:
Process
Responsibilities
People
Responsibilities
• Project issues
• Disseminating project information
• Mitigating project risk
• Quality
• Managing scope
• Metrics
• Managing the overall work plan
• Implementing standard processes
• Establishing leadership skills
• Setting expectations
• Team building
• Communicator skills
Duties & Responsibilities of PM
I. PLANNING:
 Breaking down Project into independent
activities or events with the help of Bar
Chart.
 Providing progress reporting at regular
intervals to the Customer, Consultant and
Caterpillar with a copy to Service
department.
 Reallocation / rearranging
money/resources to improve schedule.
III. INSPECTIONS & DESPATCHES:
 Witnessing the equipment inspection at
suppliers place.
 coordinating with Customer for allotting safe
equipment unloading and storage area at site.
IV. SITE CO-ORDINATION :
 Visiting site for checking Civil developments.
 Guiding mechanical contractor and Customer at
site for flushing of piping, welding & surface
preparation, pre-commissioning checks to suit
Caterpillar standards.
II. TECHNICAL ACTIVITIES:
 Preparation of Specification of material for
mechanical bought out items like Pipes,
Elbows, Valves, Flexible hoses required for
Cooling system, Starting air system.
 Preparation of Material specification for
fabricated items like Chimney, Exhaust &
Intake duct, etc.
 Preparation of Mechanical Drawings – As
built P & I drawings and Isometric
drawings for Natural Gas system, Air start
system, Cooling Water system, etc
V. COMMERCIAL:
 Evaluation of the offers from vendors techno–
commercially.
 Negotiating with suppliers effectively to avoid
cost over run & make maximum profit margins.
 Planning cash flow (in & out) with the help of
Finance department for smooth project
operation.
 Coordinating with Finance Department for
releasing the payment to suppliers after
checking proper attached documents.
 Collecting payment for additional supply of
material other than Purchase order.
 Calculating the profit earned in the project
Gantt Chart (Microsoft Office Project Professional
2003)
 Visual scheduling tool
 Graphical representation
of information in WBS
 Show dependencies
between tasks,
personnel, and other
resources allocations
 Track progress towards
completion
Gantt Chart – Example
Estimated time to complete a task
Tasks
Bars indicate time
requirement
Arrows indicate
task dependencies:
Predecessor task
Successor task
Look Out for the Creepers!
 Scope Creep - Change is constant – must be
accommodated (Comes from the customer)
 Civil design – due to change in civil structure by
Customer
 Power plant logic - Frequent changes in the electrical
logic by Customer’s site manager
Accommodated and completed the project on time
Project communication - Absolutely critical to the
success of projects!
 Project meetings with suppliers - Meets weekly to resolve short-term
conflicts, look ahead to the remaining development cycle. Attended by project
manager, project engineers, projects manager (if required).
 Planning meetings – Inter-organizational - review progress on goals,
resolution of cross division functional conflicts, perform mid-course corrections,
review cash flow, etc. Attended by division heads, project manager, GM (if reqd.)
 Fortnight coordination meetings with Customer and Consultants –
Meets for reviewing the progress, approvals, set milestones for future weeks,
commissioning schedule, etc. Attended by project manager, project engineers,
projects manager (if required).
Quality Management
 Quality Management is the process that
insure the project will meet the needs via:
 Quality Planning, Quality Assurance, and Quality
Control. Quality is ensured by
 Clearly Defined Quality Performance Standards
 Stage inspection of equipment to verify
conformity / adherence to specifications,
 Testing and Quality Assurance Processes will
ensure standards are satisfied
 Continuous ongoing quality control
Project Financial Management
 Divide and conquer
 To make a better estimate, divided the
project into individual subsystems.
 Then divided each subsystem further
into the activities that will be required to
develop it.
 Next, made a series of detailed
estimates for each individual activity.
 And sum the results to arrive at the
grand total estimate for the project.
 Tight control of costs by supervising any
changes in the scope.
 Preparation of cash inflow and outflow
statement
Budget
SUCCESSES
Customer Requirements
satisfied
Completed within
allocated time frame + 2
extra months with prior
notification (out of 2
months, 1 month recorded
as Force majeure)
Completed within
allocated budget
Accepted by the customer
Difficulties and Risks in Project Management
 Road Transport strike lasted for 2 weeks,
 Difficulty in transporting the heavy equipment to the rural area due
to lots of curves,
 Communist area – additional amount to Comrades for each truck,
 Language barrier – interior people speaks Tamil only,
 Slowing of erection activities due to heavy Monsoon,
 Erection contractor – Inexperienced junior engr. appointed at site,
 Delays due to short fall of material at site,
 Finance Manager transferring the project funds to other projects or
emergency without the consent of project manager. Thereby, delay
the payment to the Suppliers
 Food at site
LESSONS
 Planning and Engineering – most important,
 Contingency in Time need to be considered,
 PESTEL Analysis (Environment scanning) shall be done,
 Project management Training to the individuals,
 Getting the scale of the project management in proportion to
the size and impact of the project,
 Better monitoring of milestones (and remedial action
when milestones are not being met)
 Project team shall be micro-managing
Rewards – Direct & Indirect
 SEDCO admired our team efforts and gifted
a Silver Peacock Monument in a ceremony
 Our company announced a bonus of INR
30,000 to project team,
 Recognition in the company,
 New doors of opportunities opened.

Mais conteúdo relacionado

Mais procurados

ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-SlidesICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-SlidesRussell Archibald
 
Why agile is best for managing projects in principle but not always in practice
Why agile is best for managing projects in principle but not always in practiceWhy agile is best for managing projects in principle but not always in practice
Why agile is best for managing projects in principle but not always in practiceGlen Alleman
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Glen Alleman
 
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Control Plan
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Control PlanJavier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Control Plan
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Control PlanJ. García - Verdugo
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingGlen Alleman
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance ManagementGlen Alleman
 
Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short CourseGlen Alleman
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bagGlen Alleman
 
Estimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsEstimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project integration management quiz
Project integration management quizProject integration management quiz
Project integration management quize2e4
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysGlen Alleman
 
Agile Importance in Pharmaceutical Industry
Agile Importance in Pharmaceutical IndustryAgile Importance in Pharmaceutical Industry
Agile Importance in Pharmaceutical IndustryVijay Brzee
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government ContractingGlen Alleman
 

Mais procurados (20)

ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-SlidesICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
 
Why agile is best for managing projects in principle but not always in practice
Why agile is best for managing projects in principle but not always in practiceWhy agile is best for managing projects in principle but not always in practice
Why agile is best for managing projects in principle but not always in practice
 
D11 Define Review
D11 Define ReviewD11 Define Review
D11 Define Review
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Control Plan
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Control PlanJavier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Control Plan
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W2 Control Plan
 
Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement Baseling
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance Management
 
Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short Course
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
Event based scheduling brown bag
Event based scheduling brown bagEvent based scheduling brown bag
Event based scheduling brown bag
 
Estimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsEstimating and Reporting Agile Projects
Estimating and Reporting Agile Projects
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project integration management quiz
Project integration management quizProject integration management quiz
Project integration management quiz
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 
Pl Pr3
Pl Pr3Pl Pr3
Pl Pr3
 
Agile Importance in Pharmaceutical Industry
Agile Importance in Pharmaceutical IndustryAgile Importance in Pharmaceutical Industry
Agile Importance in Pharmaceutical Industry
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government Contracting
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 

Semelhante a PROJECT MGT. PRESENTATION

Project Careers Oil&Gas
Project Careers Oil&Gas Project Careers Oil&Gas
Project Careers Oil&Gas Rushi Pru Dhvi
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerSankar Sundaram PMP
 
Cv s.sankarasubramanian - senior planning engineer
Cv   s.sankarasubramanian - senior planning engineerCv   s.sankarasubramanian - senior planning engineer
Cv s.sankarasubramanian - senior planning engineerSankar Sundaram PMP
 
Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016khaja jeelani
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 ) SAJJAD KHUDHUR ABBAS
 
CV for civil engineer (Updated)--- Alpesh Parmar
CV for civil engineer (Updated)--- Alpesh ParmarCV for civil engineer (Updated)--- Alpesh Parmar
CV for civil engineer (Updated)--- Alpesh ParmarALPESH CONTRACTOR
 
Senior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanSenior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanMohideen Sheik Asan
 
GURUDEV S M - 2016
GURUDEV S M - 2016GURUDEV S M - 2016
GURUDEV S M - 2016GURUDEV S M
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentationRiaz Zalil
 
Samir Patil 16 YRs EXP
Samir Patil 16 YRs EXPSamir Patil 16 YRs EXP
Samir Patil 16 YRs EXPSamir Patil
 
1. Usman Ali CV Project Engineer Electrical.pdf
1. Usman Ali CV Project Engineer Electrical.pdf1. Usman Ali CV Project Engineer Electrical.pdf
1. Usman Ali CV Project Engineer Electrical.pdfEmmanuelMatutu
 

Semelhante a PROJECT MGT. PRESENTATION (20)

Project Careers Oil&Gas
Project Careers Oil&Gas Project Careers Oil&Gas
Project Careers Oil&Gas
 
Prudhivi__Rushi_CV
Prudhivi__Rushi_CVPrudhivi__Rushi_CV
Prudhivi__Rushi_CV
 
Prashant Wani1
Prashant Wani1Prashant Wani1
Prashant Wani1
 
CV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning EngineerCV - S.Sankarasubramanian - Senior Planning Engineer
CV - S.Sankarasubramanian - Senior Planning Engineer
 
Cv s.sankarasubramanian - senior planning engineer
Cv   s.sankarasubramanian - senior planning engineerCv   s.sankarasubramanian - senior planning engineer
Cv s.sankarasubramanian - senior planning engineer
 
CV hmsnegi
CV hmsnegiCV hmsnegi
CV hmsnegi
 
Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016Updtd tbm-jkf-photo-cv 06032016
Updtd tbm-jkf-photo-cv 06032016
 
Bill resume
Bill resumeBill resume
Bill resume
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
CV for civil engineer (Updated)--- Alpesh Parmar
CV for civil engineer (Updated)--- Alpesh ParmarCV for civil engineer (Updated)--- Alpesh Parmar
CV for civil engineer (Updated)--- Alpesh Parmar
 
vijay cv
vijay cvvijay cv
vijay cv
 
CURRICULUM VITAE World Bank Format V3
CURRICULUM VITAE World Bank Format V3CURRICULUM VITAE World Bank Format V3
CURRICULUM VITAE World Bank Format V3
 
Samrat Khanorkar_Resume
Samrat Khanorkar_ResumeSamrat Khanorkar_Resume
Samrat Khanorkar_Resume
 
Senior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanSenior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik Asan
 
GURUDEV S M - 2016
GURUDEV S M - 2016GURUDEV S M - 2016
GURUDEV S M - 2016
 
CV of broosto -7-2016
CV of broosto -7-2016CV of broosto -7-2016
CV of broosto -7-2016
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
 
ASIF CV - HVAC O & M
ASIF CV - HVAC O & MASIF CV - HVAC O & M
ASIF CV - HVAC O & M
 
Samir Patil 16 YRs EXP
Samir Patil 16 YRs EXPSamir Patil 16 YRs EXP
Samir Patil 16 YRs EXP
 
1. Usman Ali CV Project Engineer Electrical.pdf
1. Usman Ali CV Project Engineer Electrical.pdf1. Usman Ali CV Project Engineer Electrical.pdf
1. Usman Ali CV Project Engineer Electrical.pdf
 

PROJECT MGT. PRESENTATION

  • 1. PROJECT MANAGEMENT CAPTIVE POWER PLANT PROJECT Presentation by Mahesh V. Kulkarni Vth Term - Operations Manipal University  A Power plant
  • 2. PROJECT – Turnkey in Nature  2 x 2.5 MW Captive Power Plant spread over 4 acres of land (free field)  2 x G3612, 11 KV, 1500 RPM Natural Gas Gensets  Customer: Southern Energy Development Corporation Ltd. (SEDCO) – a Carborandum Universal Group  Location: Nallur, Mannargudi (near Tanjavur), Tamilnadu  Consultant: Aquatherm Consulting Engineers, Chennai  Guarantees-  Fuel Consumption,  Lube oil Consumption,  Genset output power
  • 3. NEED FOR PROJECT MGMT.- WHY DID OUR COMPANY FORM A PROJECT MGT. DEPARTMENT? • Too many projects running over time and over budget  Project scope creep  Project management responsibility not clear  Too much emphasis on outputs rather than outcomes  Insufficient emphasis on risks Saves company TIME….MONEY  Triple constraint Quality Scope Time Cost
  • 4. Project department - Sandwich Takeover from Sales Handover to Service department Sales Service P r o j e c t
  • 5. Five Phases of Project Management  Phases Developing the Plan Scoping the Project Launching the Plan Monitoring & Controlling Closing Out the Project
  • 6. Scoping the project- Primarily it is the definition and control of what IS & IS NOT included in the project Project Scoping Form Project Name – SEDCO Project Manager – Mahesh Kulkarni Team Members – 05 nos. Opportunity (Why do this project?): To earn profit Project Goal: Smooth execution Objectives: Timely completion within a allotted costs Success Criteria (Outcomes): Effective commissioning of all equipment by suppliers Assumptions, Risks, Obstacles: Technological,Environmental, Interpersonal, Cultural, Political
  • 7. SCOPE  Imported supply from USA – Value USD 1.5 Mn  Indigenous supply (Balance of plant) – INR 2.62 Crores  Erection of all supplied items  Time frame – 6 months  Imported scope by Letter of Credit  Indigenous supply payment terms – 50 % advance, 30 % against supply and 20 % after commissioning.  33 KV Substation supply and erection by Bharat Bijlee  Govt. approvals from 1. TNEB, 2. GAIL, 3. CEIG, 4. Pollution control board  Total vendors in the project – 11 nos. (EPC Contractor – mechanical & electrical, manufacturers of air compressors, air receivers, Radiator, NGR Panel, Circuit breaker panel, MCC panel, main and auxiliary transformer, LAVT panel, Control & Relay panel, etc.)
  • 8. Developing The Plan Construct/Analyze Project Network Prepare the Project Proposal Identify Project Tasks (WBS) Estimate Task Duration Determine Resource Requirements
  • 9. Project Planning Activity • Create a work break down structure (WBS) for the project you identified in the scoping document. Identify and sequence tasks.
  • 10. WBS - A WBS is the functional decomposition of a system, it breaks the project into chunks of work at a level of detail that meets planning and scheduling needs WBS: SEDCO PROJECT 3. CONSTRUCTION2. PROCUREMENT1. DESIGN & ENGINEERING 1.1 Sizing of equipment 1.1.1 Foundation 1.1.2 Piping layout 1.2 Drawings 1.3 Consultant approvals 2.1 Order placement 2.1.1 Long delivery items 2.1.2 Short delivery items 2.2 Inspection 2.3 Clearance & Transportation to site 3.1 Unloading at site & Erection 3.1.1 Erection of equipment on foundation 3.1.2 Piping and cabling 3.2 Pre-commissioning checks 3.3 Plant trial run and handover Advance
  • 11. Project Planning: Resources  1. People - skills and value  2. Facilities – Office, AutoCAD, computers and softwares, Vehicles, etc.  3. Equipment – like Crane – hired General Manager … DRAFTSMAN ….. ELECTRICAL ENGR. ……. Manager Projects …….. SITE MANAGER ……. Manager Projects (S. Sridhar) Project Manager …… Commissioning Engr. ….. Finance Manager …. Principal ….. Suppliers for indigenous supplies (11 vendors) Service Manager (Singuttuvan) Customer - SEDCO (Project Mgr.) Consultant–Aquatherm …. 4. Time – Six months starting 1st March
  • 12. Role of a Project Manager  Role: Process Responsibilities People Responsibilities • Project issues • Disseminating project information • Mitigating project risk • Quality • Managing scope • Metrics • Managing the overall work plan • Implementing standard processes • Establishing leadership skills • Setting expectations • Team building • Communicator skills
  • 13. Duties & Responsibilities of PM I. PLANNING:  Breaking down Project into independent activities or events with the help of Bar Chart.  Providing progress reporting at regular intervals to the Customer, Consultant and Caterpillar with a copy to Service department.  Reallocation / rearranging money/resources to improve schedule. III. INSPECTIONS & DESPATCHES:  Witnessing the equipment inspection at suppliers place.  coordinating with Customer for allotting safe equipment unloading and storage area at site. IV. SITE CO-ORDINATION :  Visiting site for checking Civil developments.  Guiding mechanical contractor and Customer at site for flushing of piping, welding & surface preparation, pre-commissioning checks to suit Caterpillar standards. II. TECHNICAL ACTIVITIES:  Preparation of Specification of material for mechanical bought out items like Pipes, Elbows, Valves, Flexible hoses required for Cooling system, Starting air system.  Preparation of Material specification for fabricated items like Chimney, Exhaust & Intake duct, etc.  Preparation of Mechanical Drawings – As built P & I drawings and Isometric drawings for Natural Gas system, Air start system, Cooling Water system, etc V. COMMERCIAL:  Evaluation of the offers from vendors techno– commercially.  Negotiating with suppliers effectively to avoid cost over run & make maximum profit margins.  Planning cash flow (in & out) with the help of Finance department for smooth project operation.  Coordinating with Finance Department for releasing the payment to suppliers after checking proper attached documents.  Collecting payment for additional supply of material other than Purchase order.  Calculating the profit earned in the project
  • 14. Gantt Chart (Microsoft Office Project Professional 2003)  Visual scheduling tool  Graphical representation of information in WBS  Show dependencies between tasks, personnel, and other resources allocations  Track progress towards completion
  • 15. Gantt Chart – Example Estimated time to complete a task Tasks Bars indicate time requirement Arrows indicate task dependencies: Predecessor task Successor task
  • 16. Look Out for the Creepers!  Scope Creep - Change is constant – must be accommodated (Comes from the customer)  Civil design – due to change in civil structure by Customer  Power plant logic - Frequent changes in the electrical logic by Customer’s site manager Accommodated and completed the project on time
  • 17. Project communication - Absolutely critical to the success of projects!  Project meetings with suppliers - Meets weekly to resolve short-term conflicts, look ahead to the remaining development cycle. Attended by project manager, project engineers, projects manager (if required).  Planning meetings – Inter-organizational - review progress on goals, resolution of cross division functional conflicts, perform mid-course corrections, review cash flow, etc. Attended by division heads, project manager, GM (if reqd.)  Fortnight coordination meetings with Customer and Consultants – Meets for reviewing the progress, approvals, set milestones for future weeks, commissioning schedule, etc. Attended by project manager, project engineers, projects manager (if required).
  • 18. Quality Management  Quality Management is the process that insure the project will meet the needs via:  Quality Planning, Quality Assurance, and Quality Control. Quality is ensured by  Clearly Defined Quality Performance Standards  Stage inspection of equipment to verify conformity / adherence to specifications,  Testing and Quality Assurance Processes will ensure standards are satisfied  Continuous ongoing quality control
  • 19. Project Financial Management  Divide and conquer  To make a better estimate, divided the project into individual subsystems.  Then divided each subsystem further into the activities that will be required to develop it.  Next, made a series of detailed estimates for each individual activity.  And sum the results to arrive at the grand total estimate for the project.  Tight control of costs by supervising any changes in the scope.  Preparation of cash inflow and outflow statement Budget
  • 20. SUCCESSES Customer Requirements satisfied Completed within allocated time frame + 2 extra months with prior notification (out of 2 months, 1 month recorded as Force majeure) Completed within allocated budget Accepted by the customer
  • 21. Difficulties and Risks in Project Management  Road Transport strike lasted for 2 weeks,  Difficulty in transporting the heavy equipment to the rural area due to lots of curves,  Communist area – additional amount to Comrades for each truck,  Language barrier – interior people speaks Tamil only,  Slowing of erection activities due to heavy Monsoon,  Erection contractor – Inexperienced junior engr. appointed at site,  Delays due to short fall of material at site,  Finance Manager transferring the project funds to other projects or emergency without the consent of project manager. Thereby, delay the payment to the Suppliers  Food at site
  • 22. LESSONS  Planning and Engineering – most important,  Contingency in Time need to be considered,  PESTEL Analysis (Environment scanning) shall be done,  Project management Training to the individuals,  Getting the scale of the project management in proportion to the size and impact of the project,  Better monitoring of milestones (and remedial action when milestones are not being met)  Project team shall be micro-managing
  • 23. Rewards – Direct & Indirect  SEDCO admired our team efforts and gifted a Silver Peacock Monument in a ceremony  Our company announced a bonus of INR 30,000 to project team,  Recognition in the company,  New doors of opportunities opened.