Change Management:
One University’s Evolution from Chaos to Calm
John Borwick, Director of IT Portfolio Management
Rita Mewing, Manager of IT Change and Metrics Management
Wake Forest University
Thursday, October 18th at 11am (Eastern)
Wake Forest University implemented department-wide IT service change management in 2008. The process has persisted and flourished during a CIO transition and a major service management tool upgrade. Now in 2012, the process appears to be anchored in our culture.
This presentation summarizes the lessons learned with the implementation and subsequent improvements, for example: the major obstacles we created in our initial roll-out and how we addressed them, how we controlled the process during our tool upgrade, how CAB has evolved to include change reviews for pending work, how we changed the perception of emergency changes, and how we have built on our change management process to solve pressing IT management issues such as allocating resources for major initiatives. Additionally, we will review our key metrics for change management and illustrate how process improvements affected these metrics.
Finally, before answering questions we will summarize what we think you should do if you are implementing or managing a change management process.
Status Quo or Status Whoa? with Brad Utterback, an ITSM Academy Webinar
Wake Forest University CAB an ITSM Academy Webinar
1. Change Management: One University's
evolution from chaos to calm
John Borwick, Director IS Portfolio Management
Rita Mewing, Change Manager, Sr.
Wake Forest University
k
2. About ITSM Academy
Accredited Education Since 2003 - Tens of Thousands
Certified Process Design Engineer (CPDE)
g g ( ) Trained and Certified
ITIL® Foundation
ITSM Professional Diplomas
ITIL Capability (OSA|PPO|RCV|SOA)
Change/Support/SLM
ITIL Lifecycle (SS|SD|ST|SO|CSI)
ITIL Managing Across the Lifecycle (MALC) Public Classes throughout U S
U.S.
ISO/IEC 20000 Foundation & Bridge Corporate On-Site Classes
MOF Foundation
Virtual Classes
P
Practical, V l Add W k h
i l Value-Add Workshops
Courseware Licensing
Building Blocks, Roles, Service Catalog, etc.
Corporate & Partner (GEM)
ITIL, MOF, ISO 20K Overviews
Apollo 13 Visible Ops The Class
13, Ops: Alumni Program
g
And more! PMI Global Education Provider
Certified Woman-Owned
ITIL® is a Registered Trade Mark of the Cabinet Office. Welcome!
4. Information Systems at WFU
• Central IT: Academic &
Administrative
• Grew in the mid-1990s
due to laptop program
p pp g
• Over 100 staff, with low
turnover
5. Agenda
• Scope, assumptions, and vocabulary
• Change management implementation and change
implementation,
management v2
• Timeline, 2008-Present
2008 Present
• 2008-March 2010
• Tool Upgrade
• March 2010-Now
• What You Should Do to Reduce the Chaos
• Q&A
8. What is a “change” in this context?
IN SCOPE:
• Production changes
• Department process changes
• “Service modifications”
Service modifications
• Project deliverables
OUT OF SCOPE:
• Projects
• Low-risk service provisioning
• Low risk
Low-risk maintenance
9. Assumptions
• This is not the first time you've heard of "change
management
management"
• Our implementation isn't a blueprint, but some of our
ideas will help y
p you
• Our pain is your gain
10. Vocabulary
RFC: Request For Change
EC: Emergency Change
CAB: Change Advisory Board
ISMB (or MB): Information Systems Management Board
Governing document: a controlled description of our
p
process
17. Our first Change Advisory Board
(January 2008)
I. Attendees People
2.1
2 1 Business Concept Document
2.2 CAB Schedule Process
2.3
2 3 Remedy Change Management Module
2.4 Change Management Procedure Products
2.5
2 5 CAB Infrastructure
Partners
18. The People
• Chair: Assistant CIO
• Standing members: Directors
• Change managers: Continual Service Improvement
Team
• Presenters: People requesting the change
CAB met 4 times a week
20. The Process
- Linear
- Designed by one person
- Same process for all
changes
21. The Products
• Remedy 5.5 change management module
• MS Office
• Email and Calendar
• Blackboard (Learning management tool)
Note: Tool did not reinforce the process
22. The Partners
Consultants attending the interim CIO
John B eventually attended ITIL v2 Release & Control
23. Opportunities for Improvement
• Approvals too slow
• Rubber-stamp
Rubber stamp approvals
• Lots of emergency changes
• One size fits all
25. In change management v1, changes were
approved after they had been built and tested.
Identify a change
Change built Change tested
Change submitted …wait…
CAB approval Change
implemented
26. In change management v2, changes were
approved before they have been built.
Identify a change Approve change
Change built Change tested
Change scheduled
Change
implemented
27. In change management v1, all changes were
approved by the CAB.
Turn on a new
service
Minor application
upgrade
CAB
Add record for HR
28. In change management v2, there were three
levels of “approval authority.”
approval authority.
Turn on a new
service ISMB
Minor application
upgrade CAB
Add record for HR Local Authority
29. In change management v1, we spent a lot of
time figuring out who should handle a change.
Service request Team A? Team
submitted B?
Help Desk ticket Team C? Team
T T
submitted D?
Internal request Who knows??
submitted
b itt d
30. In change management v2, all changes are
sent to “change intake” to be classified.
change intake
Service request
submitted
Help Desk ticket
submitted Change intake
Internal request
submitted
b itt d
31. Other improvements included…
Holding additional training
Creating notification listserves
Reviewing and minimizing data collected
Identifying
Id tif i on-going change managers
i h
38. Rita and Angie take on change
management
Emergency Change (EC)
• Paper form
• Requestor and the
change manager seek
signatures
• Di t sponsor
Director
signature
• CIO office approval
signature
44. new tool stirred up some chaos
Teams culled the clutter
Closed tickets became archived/read only
Training
T i i provided t early
id d too l
Tool enforced approvals
45. new tool started to calm the chaos
Timing – easier to track different change types
Fields with workflow
Approval proxies
Performance ratings
50. Meetings and meeting deadlines
CAB/MB deadline:
Friday at noon
CAB & MB agendas sent
out by Friday at 4 PM
CAB:
Monday at 10:15 AM
ISMB:
Tuesday at 2:00 PM
52. Why are emergency changes
happening?
Emergency Change (EC)
• Paper form
• Requestor and the
change manager seek
s g atu es
signatures
• Director sponsor
signature
• CIO office approval
signature
58. The CAB Agenda Today
1. Attendees
2. On-call pages
3. Post-Implementation Review, Emergency Changes
4.
4 Post-Implementation R i
P tI l t ti Review, NNormal Ch
l Changes
5. Post-Implementation Review, No Impact Changes
6. Old Business
7. Regular Changes
8. Briefings
9. Other Action Items
Oh A i I
10. Open CRQ tickets
11. IS Change Schedule Calendar
g
60. Do these things
Stand firm on deadlines, process
Stand firm on deadlines for RFCs to go on the CAB and MB agendas
agendas.
Put up with grief now to save a lot of grief later.
Make others feel the pain so you don’t have to—you are enforcing the process.
61. Do these things
Buy-in and support from upper management
You can only stand firm on process when management wants the process to
work.
62. Do these things
Create standard templates for the agenda
Have a placeholder for “parking lot” items
parking lot items.
Change these templates to anticipate problems you’ve seen in the past.
CAB/MB questions that we have added in our template:
Communication plan needed?
Security review needed?
Training impact?
Reporting impact?
63. Do these things
Send the agenda with time to review before the
meeting
We have a CAB listserv and email the agenda
Anyone can subscribe
We also send calendar invitations for each agenda item
64. Do these things
Have written rules, process
Governing documents that are updated regularly
We are on version 13
We review twice annually
65. Do these things
Assign the roles and have people dedicated to change
management
Our roles:
Change coordinators
Approvers
Change Schedulers
We have ~1 FTE dedicated to change management.
66. Do these things
Delegate approval authority
Deputy CIO
Directors
Managers,
Managers …
67. Do these things
Watch Your Process Triggers
Only trigger change management for “real” changes—things that require
real changes things
review.
72. Connections to other processes
Project management
Scrum/Agile software development
73. Projects & Products
ECT
ROLL
PROJE
INITIATE PLAN CLOSING
OUT
s)
PRODUCTS S
verables
PRODUCT PRODUCT PRODUCT …
#1 #2 #3
(Deliv
74. Projects & Products
ECT
ROLL
PROJE
INITIATE PLAN CLOSING
OUT
s)
PRODUCTS S
verables
PRODUCT PRODUCT PRODUCT …
#1 #2 #3
(Deliv
THE KIND OF CHANGE MANAGEMENT
WE’RE TALKING ABOUT GOES HERE
75. Projects & Products
ECT
ROLL
PROJE
INITIATE PLAN CLOSING
OUT
PROJECT SCOPE CHANGE MANAGEMENT
IS CONFUSING TO PEOPLE
s)
PRODUCTS S
verables
PRODUCT PRODUCT PRODUCT …
#1 #2 #3
(Deliv
76. Scrum/Development &
Change Requests
Ap Dev
Process
Add to Ready to Development Verified in
Backlog
g Work and Testing
g Production
pp
Management
Change
Change
Request Approve
pp Scheduled and
created CRQ Implemented