2. • Implemented by: Madhyam Foundation
• Supported by: Jamsetji Tata Trust, Mumbai
• Amount of Support: Rs. 14,24,380/-
• Project Duration: March, 10 – Feb, 11 (One year)
• Project Goal: To promote food security and
increase household income by providing
irrigation facilities to 75 acres of land belonging
to 83 households through 3 DBI structures.
3. Status so far
Sl.no Project No of HH to Expected Status
location be command
benefitted area
1 Jaripada 23 30 acres Completed
2 Sana Tulabi 18 25 acres Work in
progress.
3 Jamuganda 42 20 acres Work in
progress
Total 83 75 acres
4. Activities undertaken so far
• Initial meetings with villagers conducted.
• Permission from Forest dept. obtained.
• Technical survey conducted with help of DBI secretariat and
findings discussed with villagers.
• Social, resource & command area mapping completed.
• Work supervision committee in each village set up.
• Exposure of project staff to GPSS undertaken.
• Digging of canals, intake structure, laying of pipes etc.
completed by the community with guidance from DBI
secretariat. Cont…
5. • 20.70 acres land received irrigation and each of the 23 HH has
now access to water for household consumption.
• Training on organic manure & pesticides conducted. Each
family has started preparing & using organic manure &
pesticides.
• Sunflower, mustard & vegetables (Cauliflower, Radish, green
leaves, Bean, Cabbage, Tamato, Brinjal & Chilly) were sown
with availability of water. Total expected income would be Rs.
51,150/- (approx)
6. Problems encountered
• Digging of trenches started a bit late due to extreme hot
weather and again it was delayed due to prolonged rain
during September/ October.
• The connecting forest road & bridges to the sites were
damaged due to heavy rain and thus transportation of pipes,
got delayed till it was repaired by the forest dept.
• In Sanatulubi village, the laying of pipes was to be done
through paddy fields. So, we had to wait till harvest to start
digging of trenches through the paddy field.