SlideShare uma empresa Scribd logo
1 de 43
Presented
By
K.Lavanya
M.Tech
1
FORMWORK
DEFINITION:
2
 Its is an artificial support provided below and around the precast
or cast insitu concrete work.
 Formwork is commonly made of
 Steel
 wood
 Formwork construction & casting is of prime importance in
concrete industry. It share a significant amount of concrete cost.
 Formwork is designed according to The ACI document SP-4.
Qualities of formwork:
3
It should be water tight
It should be strong
It can be reusable
Its contact surface should be uniform
It should be according to the size of member.
Uses:
4
 Formwork molds the concrete to the desired
shape and size, and controls its position and
alignment.
 It is used to transfer the temporary external
loads.
Major objectives considered in formwork:
5
 Quality
 Safety
 Economy
6
 Quality:
Forms must be designed and built with sufficient stiffness and
accuracy so that the size, shape, position, and finish of the cast concrete
are maintained.
 Safety:
Forms must be built sufficient strength and factor of safety so that
they have the capable of all supporting loads.
 Economy:
Forms must be built efficiently, minimizing time and cost..
Requirements of formwork:
7
 Material should be cheap and re usable,
 It should be practically water proof, so that it should not absorb water
from concrete,
 Swelling and shrinkage should be minimum,
 Strong enough to with stand all external loads,
 Deflection should be minimum,
 Surface should be smooth, and afford easy striping,
 Light in weight, so that easy to transfer,
 Joints should be stiff, so that lateral deformation and leak is minimum .
THREE STAGES:
8
a) Assembly and erection
b) Concrete placement
c) Stripping and dismantling
TYPES OF FORMWORK:
9
Temporary Structure
Temporary structure required to safely support
concrete until it reaches adequate strength
Permanent Structure
Formwork detail for different structural
members
10
In concrete construction formwork is commonly
provided for the following structural members.
o Wall
o Column
o Slabs & Beams
o Stairs
o Chimneys
o Water tanks
o Cooling Towers
Formwork for Wall
11
 It consists of
• Timber sheeting
• Vertical posts
• Horizontal members
• Rackers
• Stakes
• Wedges
 After completing one
side of formwork
reinforcement is
provided at the place
then the second side
formwork is provided.
Wall forms:
12
 Wall forms principally resist the lateral pressure generated by fresh
concrete as a liquid or semi liquid material.
 The pressure can be quite large, certainly many times the magnitude
of live loads on permanent floors.
 So design often involves closely spaced and well-supported members.
 Snap ties, flat ties, loop ties are single use ties usually relatively low
capacity 680 kg to 1450 kg.
 Coil ties, he bolts, she bolts are left embedded in concrete , or it can
be reused.
 The tension capacity of heavy ties around 27,230 kg.
13
Wall forms:
Formwork for Column
14
It consists of the
following
Side & End Planks
Yoke
Nut & Bolts
Two end & two side
planks are joined by the
yokes and bolts.
Column forms:
15
 Column-forms materials tend to vary with the column shape.
 Wood or steel is often used with square or rectangular column.
 Round column forms more typically pre manufactured in a range of
standard diameters, are available in steel, paper board, and fiber
reinforced plastic.
 Round column are more structural efficient compared to square, since
the internal pressures can be resisted by the hoop membrane.
 Round steel forms are generally used for larger columns and bridge
piers and come in diameters about 0.36m to 3mts..
16
Formwork for columns
17
Formwork for Slabs & beams:
18
 It consists of
Sole plates
Wedges
Props
Head tree
Planks
Batten
Ledgers
 Beam formwork
rests on head tree
 Slab form work rests
on battens and joists
 If prop height are
more than 8’ provide
horizontal braces.
Lintel or Beam Formwork:
19
FORMWORK FOR SLAB:
20
FORMWORK FOR STAIRS:
21
It consists of
Vertical & inclined
posts
Inclined members
Wooden Planks or
sheeting
Stringer
Riser Planks
FORMWORK FOR STAIRS:
22
 The sheathing or decking for deck slabs is carried on cross-
joists which are in turn supported on raking ledgers
 The ledgers are generally of 7.5cm x 10cm size .
 The cross- joists may be 5cm x 10cm size
 The riser planks are 4-5 cm thick and equal to the height
of riser
 The riser planks are placed after the reinforcement is
placed in position
FORMWORK FOR STAIRS:
23
FORMWORK FOR STAIRS:
24
FORMWORK FOR CHIMNEYS:
25
For tall chimneys two types of forms techniques are
in generally use in our country
a) Jump form
b) Slip form
26
Jump Form:
In this type jacking bars are either cast in concrete or else
are carried in tubes which are cast in concrete.
After casting a lift, concrete is allowed to set and then
the forms are raised by jacks and the next lift is cast.
Jacks are usually placed about 2m apart and are designed.
27
28
Slip Form:
The slip form method of concrete construction is used
for forming both horizontal and vertical concrete
structures.
It often used for forming highway pavements as
continuous operation.
Slip form methods is also been used for forming various
types of vertical concrete structures.
FORMWORK FOR CHIMNEYS:
29
FORMWORK FOR CHIMNEYS:
30
Removal of formwork:
31
 Time of formwork removal depends on the following factors
1. Type of Cement
1. Rapid hardening cements require lesser time as compared to OPC
(Ordinary Portland Cement)
2. Ratio of concrete mix
1. Rich ratio concrete gain strength earlier as compared to weak ratio
concrete.
3. Weather condition
1. Hydration process accelerates in hot weather conditions as compared to
cold and humid weather conditions.
Time of Removal of formwork:
32
Sr
.
N
o
Structural Member
OPC
(Ordinary
Portland
Cement)
Rapid
Hardeni
ng
Cement
1 Beam sides, walls &
Columns
2-3 Days 2 Days
2 Slab (Vertical Supports remains
intact)
4 Days 3 Days
3 Slab (Complete Formwork
removal)
10 Days 5 Days
4 Beams (Removal of Sheeting,
Props remains intact)
8 Days 5 Days
5 Beams & Arches (Complete
formwork removal) (up to 6 m span)
14 Days 5-8 Days
6 Beams & Arches (Complete
formwork removal) (more than 6 m
span)
21 Days 8-10 Days
Maintenance of formwork:
33
Due to continuous use wooden planks & steel plates
surfaces become uneven and require maintenance.
For wooden formwork use cardboard or plastic fiber
board. Bolt hole places must also be repaired.
For steel formwork plates must be leveled by mallet
and loose corners must be welded.
Cost of formwork
34
 For normal works cost of formwork is about 30%-40% of the
concrete cost.
 For special works cost of formwork is about 50%-60% of the
concrete cost.
 Formwork cost is controlled by the following factors
• Formwork Material cost
• Formwork erecting cost
• Formwork removal cost
• Formwork jointing cost (Nails and Cables)
• Labor charges.
Advantages of steel form work:
35
 It can be used for a no. of times.
 It is non absorbent.
 Smooth finish surface obtained.
 No shrinkage of formwork occurs.
 Easy to use.
 Its volume is less
 Its strength is more.
LOADS ON FORMWORK:
36
Formwork is subjected to following loads:
a) Dead weight of concrete
b) Hydrostatic pressure of the concrete
c) Live load due to working laborers
d) Impact effect at the time of pouring concrete into the
formwork
e) Vibrations transmitted to formwork during pouring
concrete
FORMWORK DESIGN
37
Guiding points in the Design of formwork
 For design purpose, temporary live load due to labor and
equipment including impact may be taken from 3700N/m2
to
4000N/m2
 Dead weight of wet concrete (26000 N/m3
)
 Planks or boards used to form the vertical facing of the columns
or walls is known as sheathing whereas those used for floor slabs
are called decking
38
 The hydrostatic pressure due to fluidity of concrete in the initial stages
of pouring depends upon several factors such as amount of water, size of
aggregates, rate of pouring etc.,
 The hydrostatic pressure is maximum at the time of pouring, but after
some time it starts decreasing, as concrete starts setting and hardening.
This pressure is mainly dependent on the depth of concrete poured
before it starts setting
 Deflection of the sheathing and joists should be limited to a maximum
value of 2.5mm
Contd...
39
 The minimum wind design pressure q not less than 15 psf and
bracing should be designed for at least
w =46 kg/ft- length applied to the top
 The minimum lateral load w, for design of bracing system would
be greater than,
q .(h/2) or 46 kg/ft
Contd...
40
For design practice the maximum pressure is given by:
p = wh
Where,
p => lateral pressure of concrete,
w => unit weight of concrete,
h => depth of fluid or plastic concrete.
Contd...
41
For horizontal pressure of concrete is given by:
For walls constructing R less than 2.1m/hr;
p =150+9000(R/T)
For walls constructing R varies from 2.1m/hr to 3m/hr;
p = 150+(43,400/T)+2800(R/T)
For columns 3m/hr;
p = 150+9000(R/T)
Where, R => rate of vertical placement,
T => time for placement.
DESIGN OF SLAB FORMWORK:
42
Design of slab forms can be summarized in the following design steps:
 Step 1: Estimate design loads
 Step 2: Determine sheathing thickness and spacing of its supports (joist
spacing)
 Step 3: Determine joist size and spacing of supports (stringer spacing)
 Step 4: Determine stringer size and span (shore spacing)
 Step 5: Perform shore design to support stringers
 Step 6: Check bearing stresses
 Step 7: Design lateral bracing
43

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

Formwork
FormworkFormwork
Formwork
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
Form Work
Form Work Form Work
Form Work
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC) Reinforced Cement Concrete (RCC)
Reinforced Cement Concrete (RCC)
 
BRICK MASONRY
BRICK MASONRYBRICK MASONRY
BRICK MASONRY
 
Damp Proof Course
Damp Proof Course Damp Proof Course
Damp Proof Course
 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wall
 
Scaffolding, underepinning and shoring
Scaffolding, underepinning and shoringScaffolding, underepinning and shoring
Scaffolding, underepinning and shoring
 
Slipform
SlipformSlipform
Slipform
 
Floors
FloorsFloors
Floors
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
 
Formwork
FormworkFormwork
Formwork
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Building Components
Building ComponentsBuilding Components
Building Components
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Formwork
FormworkFormwork
Formwork
 
Scaffolding and formwork ppt
Scaffolding and  formwork pptScaffolding and  formwork ppt
Scaffolding and formwork ppt
 
Concrete
ConcreteConcrete
Concrete
 

Destaque

Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
Hamdija Velagic
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
Abhishek Shah
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
kiransuresh7
 
FORM WORK AND SUPPORT WORK
FORM WORK AND SUPPORT WORKFORM WORK AND SUPPORT WORK
FORM WORK AND SUPPORT WORK
Elsje Nel
 
36th Safety Committee Meeting - draft 28-3-13 new
36th  Safety Committee Meeting - draft 28-3-13 new36th  Safety Committee Meeting - draft 28-3-13 new
36th Safety Committee Meeting - draft 28-3-13 new
Emad Salem
 

Destaque (20)

Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Formwork in civil engineering
Formwork in civil engineeringFormwork in civil engineering
Formwork in civil engineering
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Formwork design vs falsework design key differences
Formwork design vs falsework design  key differencesFormwork design vs falsework design  key differences
Formwork design vs falsework design key differences
 
Admixture of concrete
Admixture of concreteAdmixture of concrete
Admixture of concrete
 
Slip form Construction Technology
Slip form Construction TechnologySlip form Construction Technology
Slip form Construction Technology
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Formwork & falsework
Formwork & falseworkFormwork & falsework
Formwork & falsework
 
43 privet drive
43 privet drive43 privet drive
43 privet drive
 
Group no 9
Group no 9Group no 9
Group no 9
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Basic Scaffolding Awareness
Basic Scaffolding AwarenessBasic Scaffolding Awareness
Basic Scaffolding Awareness
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 
Slip formwork technique
Slip formwork techniqueSlip formwork technique
Slip formwork technique
 
PreCast Construction
PreCast ConstructionPreCast Construction
PreCast Construction
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
 
FORM WORK AND SUPPORT WORK
FORM WORK AND SUPPORT WORKFORM WORK AND SUPPORT WORK
FORM WORK AND SUPPORT WORK
 
Scheme of work
Scheme of workScheme of work
Scheme of work
 
36th Safety Committee Meeting - draft 28-3-13 new
36th  Safety Committee Meeting - draft 28-3-13 new36th  Safety Committee Meeting - draft 28-3-13 new
36th Safety Committee Meeting - draft 28-3-13 new
 

Semelhante a Formwork

Formwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdfFormwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdf
LiesaStone
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
Perwez Ahmad
 
Estimating Systems for Homes1
Estimating Systems for Homes1Estimating Systems for Homes1
Estimating Systems for Homes1
Keith Daggett
 
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
FaizanSolanki
 

Semelhante a Formwork (20)

Formwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdfFormwork & Falsework Practice_2009(July)_to AK.pdf
Formwork & Falsework Practice_2009(July)_to AK.pdf
 
Formwork
FormworkFormwork
Formwork
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
Atecon product catalogue 2017
Atecon product catalogue 2017Atecon product catalogue 2017
Atecon product catalogue 2017
 
Precast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examplesPrecast Concrete Structure: Architectural examples
Precast Concrete Structure: Architectural examples
 
RCC Floor
RCC FloorRCC Floor
RCC Floor
 
From work & shuttering
From work & shutteringFrom work & shuttering
From work & shuttering
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
FormWork
FormWork FormWork
FormWork
 
Precast compound wall
Precast compound wallPrecast compound wall
Precast compound wall
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
Formwork
FormworkFormwork
Formwork
 
Aci , structural concrete design
Aci , structural concrete designAci , structural concrete design
Aci , structural concrete design
 
Aci structural concrete_design
Aci structural concrete_designAci structural concrete_design
Aci structural concrete_design
 
Experimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor SlabExperimental Investigation on Steel Concrete Composite Floor Slab
Experimental Investigation on Steel Concrete Composite Floor Slab
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
 
Estimating Systems for Homes1
Estimating Systems for Homes1Estimating Systems for Homes1
Estimating Systems for Homes1
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
8-formworksandscaffoldings-120525181221-phpapp02 (1).pdf
 

Último

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Último (20)

FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 

Formwork

  • 2. DEFINITION: 2  Its is an artificial support provided below and around the precast or cast insitu concrete work.  Formwork is commonly made of  Steel  wood  Formwork construction & casting is of prime importance in concrete industry. It share a significant amount of concrete cost.  Formwork is designed according to The ACI document SP-4.
  • 3. Qualities of formwork: 3 It should be water tight It should be strong It can be reusable Its contact surface should be uniform It should be according to the size of member.
  • 4. Uses: 4  Formwork molds the concrete to the desired shape and size, and controls its position and alignment.  It is used to transfer the temporary external loads.
  • 5. Major objectives considered in formwork: 5  Quality  Safety  Economy
  • 6. 6  Quality: Forms must be designed and built with sufficient stiffness and accuracy so that the size, shape, position, and finish of the cast concrete are maintained.  Safety: Forms must be built sufficient strength and factor of safety so that they have the capable of all supporting loads.  Economy: Forms must be built efficiently, minimizing time and cost..
  • 7. Requirements of formwork: 7  Material should be cheap and re usable,  It should be practically water proof, so that it should not absorb water from concrete,  Swelling and shrinkage should be minimum,  Strong enough to with stand all external loads,  Deflection should be minimum,  Surface should be smooth, and afford easy striping,  Light in weight, so that easy to transfer,  Joints should be stiff, so that lateral deformation and leak is minimum .
  • 8. THREE STAGES: 8 a) Assembly and erection b) Concrete placement c) Stripping and dismantling
  • 9. TYPES OF FORMWORK: 9 Temporary Structure Temporary structure required to safely support concrete until it reaches adequate strength Permanent Structure
  • 10. Formwork detail for different structural members 10 In concrete construction formwork is commonly provided for the following structural members. o Wall o Column o Slabs & Beams o Stairs o Chimneys o Water tanks o Cooling Towers
  • 11. Formwork for Wall 11  It consists of • Timber sheeting • Vertical posts • Horizontal members • Rackers • Stakes • Wedges  After completing one side of formwork reinforcement is provided at the place then the second side formwork is provided.
  • 12. Wall forms: 12  Wall forms principally resist the lateral pressure generated by fresh concrete as a liquid or semi liquid material.  The pressure can be quite large, certainly many times the magnitude of live loads on permanent floors.  So design often involves closely spaced and well-supported members.  Snap ties, flat ties, loop ties are single use ties usually relatively low capacity 680 kg to 1450 kg.  Coil ties, he bolts, she bolts are left embedded in concrete , or it can be reused.  The tension capacity of heavy ties around 27,230 kg.
  • 14. Formwork for Column 14 It consists of the following Side & End Planks Yoke Nut & Bolts Two end & two side planks are joined by the yokes and bolts.
  • 15. Column forms: 15  Column-forms materials tend to vary with the column shape.  Wood or steel is often used with square or rectangular column.  Round column forms more typically pre manufactured in a range of standard diameters, are available in steel, paper board, and fiber reinforced plastic.  Round column are more structural efficient compared to square, since the internal pressures can be resisted by the hoop membrane.  Round steel forms are generally used for larger columns and bridge piers and come in diameters about 0.36m to 3mts..
  • 16. 16
  • 18. Formwork for Slabs & beams: 18  It consists of Sole plates Wedges Props Head tree Planks Batten Ledgers  Beam formwork rests on head tree  Slab form work rests on battens and joists  If prop height are more than 8’ provide horizontal braces.
  • 19. Lintel or Beam Formwork: 19
  • 21. FORMWORK FOR STAIRS: 21 It consists of Vertical & inclined posts Inclined members Wooden Planks or sheeting Stringer Riser Planks
  • 22. FORMWORK FOR STAIRS: 22  The sheathing or decking for deck slabs is carried on cross- joists which are in turn supported on raking ledgers  The ledgers are generally of 7.5cm x 10cm size .  The cross- joists may be 5cm x 10cm size  The riser planks are 4-5 cm thick and equal to the height of riser  The riser planks are placed after the reinforcement is placed in position
  • 25. FORMWORK FOR CHIMNEYS: 25 For tall chimneys two types of forms techniques are in generally use in our country a) Jump form b) Slip form
  • 26. 26 Jump Form: In this type jacking bars are either cast in concrete or else are carried in tubes which are cast in concrete. After casting a lift, concrete is allowed to set and then the forms are raised by jacks and the next lift is cast. Jacks are usually placed about 2m apart and are designed.
  • 27. 27
  • 28. 28 Slip Form: The slip form method of concrete construction is used for forming both horizontal and vertical concrete structures. It often used for forming highway pavements as continuous operation. Slip form methods is also been used for forming various types of vertical concrete structures.
  • 31. Removal of formwork: 31  Time of formwork removal depends on the following factors 1. Type of Cement 1. Rapid hardening cements require lesser time as compared to OPC (Ordinary Portland Cement) 2. Ratio of concrete mix 1. Rich ratio concrete gain strength earlier as compared to weak ratio concrete. 3. Weather condition 1. Hydration process accelerates in hot weather conditions as compared to cold and humid weather conditions.
  • 32. Time of Removal of formwork: 32 Sr . N o Structural Member OPC (Ordinary Portland Cement) Rapid Hardeni ng Cement 1 Beam sides, walls & Columns 2-3 Days 2 Days 2 Slab (Vertical Supports remains intact) 4 Days 3 Days 3 Slab (Complete Formwork removal) 10 Days 5 Days 4 Beams (Removal of Sheeting, Props remains intact) 8 Days 5 Days 5 Beams & Arches (Complete formwork removal) (up to 6 m span) 14 Days 5-8 Days 6 Beams & Arches (Complete formwork removal) (more than 6 m span) 21 Days 8-10 Days
  • 33. Maintenance of formwork: 33 Due to continuous use wooden planks & steel plates surfaces become uneven and require maintenance. For wooden formwork use cardboard or plastic fiber board. Bolt hole places must also be repaired. For steel formwork plates must be leveled by mallet and loose corners must be welded.
  • 34. Cost of formwork 34  For normal works cost of formwork is about 30%-40% of the concrete cost.  For special works cost of formwork is about 50%-60% of the concrete cost.  Formwork cost is controlled by the following factors • Formwork Material cost • Formwork erecting cost • Formwork removal cost • Formwork jointing cost (Nails and Cables) • Labor charges.
  • 35. Advantages of steel form work: 35  It can be used for a no. of times.  It is non absorbent.  Smooth finish surface obtained.  No shrinkage of formwork occurs.  Easy to use.  Its volume is less  Its strength is more.
  • 36. LOADS ON FORMWORK: 36 Formwork is subjected to following loads: a) Dead weight of concrete b) Hydrostatic pressure of the concrete c) Live load due to working laborers d) Impact effect at the time of pouring concrete into the formwork e) Vibrations transmitted to formwork during pouring concrete
  • 37. FORMWORK DESIGN 37 Guiding points in the Design of formwork  For design purpose, temporary live load due to labor and equipment including impact may be taken from 3700N/m2 to 4000N/m2  Dead weight of wet concrete (26000 N/m3 )  Planks or boards used to form the vertical facing of the columns or walls is known as sheathing whereas those used for floor slabs are called decking
  • 38. 38  The hydrostatic pressure due to fluidity of concrete in the initial stages of pouring depends upon several factors such as amount of water, size of aggregates, rate of pouring etc.,  The hydrostatic pressure is maximum at the time of pouring, but after some time it starts decreasing, as concrete starts setting and hardening. This pressure is mainly dependent on the depth of concrete poured before it starts setting  Deflection of the sheathing and joists should be limited to a maximum value of 2.5mm
  • 39. Contd... 39  The minimum wind design pressure q not less than 15 psf and bracing should be designed for at least w =46 kg/ft- length applied to the top  The minimum lateral load w, for design of bracing system would be greater than, q .(h/2) or 46 kg/ft
  • 40. Contd... 40 For design practice the maximum pressure is given by: p = wh Where, p => lateral pressure of concrete, w => unit weight of concrete, h => depth of fluid or plastic concrete.
  • 41. Contd... 41 For horizontal pressure of concrete is given by: For walls constructing R less than 2.1m/hr; p =150+9000(R/T) For walls constructing R varies from 2.1m/hr to 3m/hr; p = 150+(43,400/T)+2800(R/T) For columns 3m/hr; p = 150+9000(R/T) Where, R => rate of vertical placement, T => time for placement.
  • 42. DESIGN OF SLAB FORMWORK: 42 Design of slab forms can be summarized in the following design steps:  Step 1: Estimate design loads  Step 2: Determine sheathing thickness and spacing of its supports (joist spacing)  Step 3: Determine joist size and spacing of supports (stringer spacing)  Step 4: Determine stringer size and span (shore spacing)  Step 5: Perform shore design to support stringers  Step 6: Check bearing stresses  Step 7: Design lateral bracing
  • 43. 43