1.0     PROJECT BACKGROUND




2.0     SCOPE OF WORKS

The components in this flood mitigation project comprise of two (2) interrelated flood diversion
schemes :

        i)      New diversion channel to divert Sg. Keroh flood flow to Jinjang Detention Ponds.
        ii)     Upgrading Gombak Diversion to allow more discharge diversion from Sg. Gombak to the
                enlarged Batu Detention Pond.
        iii)    Benteng and Puah conceptional detail design.
2.1   GOMBAK DIVERSION’S WORK
Upgrading of the existing Gombak Diversion system:

      i.    Gombak Diversion (3.375 km)
      ii.   Gombak barrage at Gombak River downstream of Gombak Diversion
      iii.  Low overflow weir from Gombak River to Gombak Diversion
      iv.   Inlet gate to Gombak Diversion
      v.    Gombak Diversion outfall structure
      vi.   Ogee weir from regulating pond to Batu Pond
      vii.  Enlargement of Batu Pond capacity to 4.5 million cubic meter
      viii. Control gate for Batu Pond outlet to Batu River
      ix.   Flood walls along Gombak River
2.2   KEROH DIVERSION’S WORK
i.    New diversion scheme from Sungai Keroh to Jinjang Ponds (2.2 km)
         ii.   Keroh barrage at downstream of Seri Segambut Pond
         iii.  Low overflow weir from Keroh river to Seri Segambut Pond
         iv.   Inlet gate to Keroh Diversion
         v.    Keroh Diversion outfall
         vi.   Enlargement of Nanyang pond, Taman Wahyu and Delima Pond capacity to 2.5 million
               cubic meter
         vii.  Control gate at Nanyang Pond outlet
         viii. Deepening of the channel connecting Nanyang and Taman Wahyu Pond
         ix.   Control gate at Taman Wahyu and Delima Pond outlet
         x.    Flood walls along Keroh River
3.0      CONTRACTUAL INFORMATION

i)      Nama Kontrak :                 Projek Mengatasi Masalah Banjir Di Kuala Lumpur
                                       Package B – Batu / Jinjang Ponds And Related Flood
                                       Diversion

ii)     No. Kontrak :                  JPS/IP/S/5/02

iii)    Pemilik Projek :               Kerajaan Malaysia, Kementerian Sumber Asli Dan Alam
                                       Sekitar

iv)     Jabatan Pelaksana :            Jabatan Pengairan dan Saliran, Malaysia

v)      Kontraktor Utama :             PECD Construction Sdn. Bhd.
                                       5th Floor, Block E, Peremba Square
                                       Saujana Resort, Seksyen U2,
                                       40150 Shah Alam
                                       Selangor Darul Ehsan

vi)     Perunding Rekabentuk dan       RPM Engineers Sdn. Bhd.
        Penyeliaan:                    34A, Jalan SS21/39,
                                       Damansara Utama
                                       47400 Petaling Jaya,
                                       Selangor Darul Ehsan

vii)    Perunding Jurukur Bahan :      Perunding Ukur Bahan RB,
                                       Unit G1, Taman Tunku,
                                       Bukit Tunku, 50480 Kuala Lumpur

viii)   Harga Kontrak Asal :           RM 804,993,894.00

ix)     Kos Pembinaan:                 RM 528,880,519.00

x)      Tempoh Kontrak :               45 Bulan (25 Ogos 2003 – 24 Mei 2007)
                                       EOT 1 ( 27 Disember 2007 )
                                       EOT 2 ( 26 Mei 2008 )
                                       EOT 3 ( 25 September 2008 )
                                       EOT 4 ( 24 Disember 2008 )
                                       EOT 5 (24 Ogos 2009)
Project Information 060709[1]

Mais conteúdo relacionado

Semelhante a Project Information 060709[1]

Saravanan CV 2015.1
Saravanan CV 2015.1Saravanan CV 2015.1
Saravanan CV 2015.1Bob Vanan
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...IJERA Editor
 
Bps 5205 sustainability construction and maintainability velpandi & maria
Bps 5205  sustainability construction and maintainability  velpandi & mariaBps 5205  sustainability construction and maintainability  velpandi & maria
Bps 5205 sustainability construction and maintainability velpandi & mariaMaria Archana
 
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power PlantZerry Antro
 
South east kowloon development kai tak approach channel reclamation.
South east kowloon development   kai tak approach channel reclamation.South east kowloon development   kai tak approach channel reclamation.
South east kowloon development kai tak approach channel reclamation.FelixGao
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam JunaidAshraf31
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)engineeringwatch
 
Full of Paper CAFEO 31
Full of Paper  CAFEO 31Full of Paper  CAFEO 31
Full of Paper CAFEO 31Rahmat Muallim
 
1. Berjaya Waterfront Reclamation Works JB.pptx
1. Berjaya Waterfront Reclamation Works JB.pptx1. Berjaya Waterfront Reclamation Works JB.pptx
1. Berjaya Waterfront Reclamation Works JB.pptxosiinterwerks
 
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...IRJET Journal
 
Internship Report
Internship ReportInternship Report
Internship ReportBala Murali
 
List of Completed Projects September 2015
List of Completed Projects September  2015List of Completed Projects September  2015
List of Completed Projects September 2015Haroon Pasha Dar
 
Muhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTSMuhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTSMuhammad Faisal Wattoo
 
Kalpasar Project PPT _NCCR-1.3.22.pdf
Kalpasar Project PPT _NCCR-1.3.22.pdfKalpasar Project PPT _NCCR-1.3.22.pdf
Kalpasar Project PPT _NCCR-1.3.22.pdfAbhinava Tripathi
 

Semelhante a Project Information 060709[1] (20)

Saravanan CV 2015.1
Saravanan CV 2015.1Saravanan CV 2015.1
Saravanan CV 2015.1
 
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
Construction Time Analysis For Different Steps In Drill-And-Blast Method Of H...
 
Bps 5205 sustainability construction and maintainability velpandi & maria
Bps 5205  sustainability construction and maintainability  velpandi & mariaBps 5205  sustainability construction and maintainability  velpandi & maria
Bps 5205 sustainability construction and maintainability velpandi & maria
 
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
0647 Project Development of the Wayang Windu Unit 2 Geothermal Power Plant
 
South east kowloon development kai tak approach channel reclamation.
South east kowloon development   kai tak approach channel reclamation.South east kowloon development   kai tak approach channel reclamation.
South east kowloon development kai tak approach channel reclamation.
 
report draft
report draftreport draft
report draft
 
20srm davinjaniceleemadhavi
20srm davinjaniceleemadhavi20srm davinjaniceleemadhavi
20srm davinjaniceleemadhavi
 
Presentation-Nilantha
Presentation-NilanthaPresentation-Nilantha
Presentation-Nilantha
 
Life cycle of tarbella dam
Life cycle of tarbella dam Life cycle of tarbella dam
Life cycle of tarbella dam
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)
 
Full of Paper CAFEO 31
Full of Paper  CAFEO 31Full of Paper  CAFEO 31
Full of Paper CAFEO 31
 
1. Berjaya Waterfront Reclamation Works JB.pptx
1. Berjaya Waterfront Reclamation Works JB.pptx1. Berjaya Waterfront Reclamation Works JB.pptx
1. Berjaya Waterfront Reclamation Works JB.pptx
 
Project
Project Project
Project
 
JAGMOC RESUME
JAGMOC RESUMEJAGMOC RESUME
JAGMOC RESUME
 
Hassby's CV 2015
Hassby's CV 2015Hassby's CV 2015
Hassby's CV 2015
 
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
 
Internship Report
Internship ReportInternship Report
Internship Report
 
List of Completed Projects September 2015
List of Completed Projects September  2015List of Completed Projects September  2015
List of Completed Projects September 2015
 
Muhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTSMuhammad Faisal Wattoo - COST OF PROJECTS
Muhammad Faisal Wattoo - COST OF PROJECTS
 
Kalpasar Project PPT _NCCR-1.3.22.pdf
Kalpasar Project PPT _NCCR-1.3.22.pdfKalpasar Project PPT _NCCR-1.3.22.pdf
Kalpasar Project PPT _NCCR-1.3.22.pdf
 

Project Information 060709[1]

  • 1. 1.0 PROJECT BACKGROUND 2.0 SCOPE OF WORKS The components in this flood mitigation project comprise of two (2) interrelated flood diversion schemes : i) New diversion channel to divert Sg. Keroh flood flow to Jinjang Detention Ponds. ii) Upgrading Gombak Diversion to allow more discharge diversion from Sg. Gombak to the enlarged Batu Detention Pond. iii) Benteng and Puah conceptional detail design.
  • 2. 2.1 GOMBAK DIVERSION’S WORK
  • 3. Upgrading of the existing Gombak Diversion system: i. Gombak Diversion (3.375 km) ii. Gombak barrage at Gombak River downstream of Gombak Diversion iii. Low overflow weir from Gombak River to Gombak Diversion iv. Inlet gate to Gombak Diversion v. Gombak Diversion outfall structure vi. Ogee weir from regulating pond to Batu Pond vii. Enlargement of Batu Pond capacity to 4.5 million cubic meter viii. Control gate for Batu Pond outlet to Batu River ix. Flood walls along Gombak River 2.2 KEROH DIVERSION’S WORK
  • 4. i. New diversion scheme from Sungai Keroh to Jinjang Ponds (2.2 km) ii. Keroh barrage at downstream of Seri Segambut Pond iii. Low overflow weir from Keroh river to Seri Segambut Pond iv. Inlet gate to Keroh Diversion v. Keroh Diversion outfall vi. Enlargement of Nanyang pond, Taman Wahyu and Delima Pond capacity to 2.5 million cubic meter vii. Control gate at Nanyang Pond outlet viii. Deepening of the channel connecting Nanyang and Taman Wahyu Pond ix. Control gate at Taman Wahyu and Delima Pond outlet x. Flood walls along Keroh River 3.0 CONTRACTUAL INFORMATION i) Nama Kontrak : Projek Mengatasi Masalah Banjir Di Kuala Lumpur Package B – Batu / Jinjang Ponds And Related Flood Diversion ii) No. Kontrak : JPS/IP/S/5/02 iii) Pemilik Projek : Kerajaan Malaysia, Kementerian Sumber Asli Dan Alam Sekitar iv) Jabatan Pelaksana : Jabatan Pengairan dan Saliran, Malaysia v) Kontraktor Utama : PECD Construction Sdn. Bhd. 5th Floor, Block E, Peremba Square Saujana Resort, Seksyen U2, 40150 Shah Alam Selangor Darul Ehsan vi) Perunding Rekabentuk dan RPM Engineers Sdn. Bhd. Penyeliaan: 34A, Jalan SS21/39, Damansara Utama 47400 Petaling Jaya, Selangor Darul Ehsan vii) Perunding Jurukur Bahan : Perunding Ukur Bahan RB, Unit G1, Taman Tunku, Bukit Tunku, 50480 Kuala Lumpur viii) Harga Kontrak Asal : RM 804,993,894.00 ix) Kos Pembinaan: RM 528,880,519.00 x) Tempoh Kontrak : 45 Bulan (25 Ogos 2003 – 24 Mei 2007) EOT 1 ( 27 Disember 2007 ) EOT 2 ( 26 Mei 2008 ) EOT 3 ( 25 September 2008 ) EOT 4 ( 24 Disember 2008 ) EOT 5 (24 Ogos 2009)