Compass surveying
Prismatic compass
Compass traversing:
Important Definition
 True meridian: Line or plane passing
through geographical north pole and
geographical south pole
 Magnetic meridian: When the magnetic
needle is suspended freely and balanced
properly, unaffected by magnetic
substances, it indicates a direction. This
direction is known as magnetic meridian.
The angle between the magnetic meridian
and a line is known as magnetic bearing or
simple bearing of the line.
North
pole
True meridian
Magnetic meridian
True bearing
Magnetic bearing
 Arbitrary meridian: Convenient direction is assumed as a meridian.
 Grid meridian: Sometimes for preparing a map some state agencies
assume several lines parallel to the true meridian for a particular
zone these lines are termed as grid meridian.
 Designation of magnetic bearing
 Whole circle bearing (WCB)
 Quadrantal bearing (QB)
 WCB: The magnetic bearing of a line measured clockwise from the North
Pole towards the line is known as WCB. Varies 0-360°
 Quadrantal Bearing: The magnetic bearing of a line measured
clockwise or anticlockwise from NP or SP (whichever is nearer to the
line) towards the east or west is known as QB. This system consists of 4-
quadrants NE, SE, NW, SW. The values lie between 0-90°
 QB of OA = N a E
 Reduced Bearing: When the whole circle bearing of a line is
converted to quadrantal bearing it is termed as reduced bearing.
 Fore and Back Bearing:
 In WCB the difference between FB and BB should be exactly 180°
 BB=FB+/-180°
 Use the +ve sign when FB<180°
 Use the –ve sign when FB> 180°
 Magnetic declination: The horizontal angle between the magnetic meridian and
true meridian is known as magnetic declination.
 Dip of the magnetic needle: If the needle is perfectly balanced before
magnetisation, it does not remain in the balanced position after it is magnetised. This
is due to the magnetic influence of the earth. The needle is found to be inclined
towards the pole. This inclination of the needle with the horizontal is known
as dip of the magnetic needle.
 Local Attraction
 Method of correction for traverse:
 First method: Sum of the interior angle should be equal to (2n-4) x 90. if not
than distribute the total error equally to all interior angles of the traverse. Then
starting from unaffected line the bearings of all the lines are corrected using
corrected interior angles.
 Second method: Unaffected line is first detected. Then, commencing from the
unaffected line, the bearing of other affected lines are corrected by finding the
amount of correction at each station.
Methods of traversing
 Chain traversing:
 Compass traversing: Fore bearings and back bearings between the traverse
leg are measured
 Theodolite traversing: Horizontal angles between the traverse legs are
measured. The length of the traverse legs are measured by chain/tape or by
stadia method
 Plane table traversing: Plane table is set at every traverse station in
clockwise and anticlockwise direction and the circuit is finally closed. During
traversing the sides of the traverse are plotted according to any suitable scale.
15 m
15 m
Checks on traverse: Closed traverse
 Check on closed traverse:
 Sum of the measured interior angles (2n-4) x 90°
 Sum of the measured exterior angles (2n+4) x 90 °
 The algebric sum of the deflection angles should be equal to 360°.
Right hand deflection is considered +ve, left hand deflection –ve
 Check on linear measurement
 The lines should be measured once each on two different days
(along opposite directions). Both measurement should tally.
 Linear measurement should also be taken by the stadia method.
The measurement by chaining and stadia method should tally.
Checks on traverse: Open traverse
 Taking cut-off lines: measured the
bearings and lengths of cut off
lines after plotting and tally with
actual values.
 Taking an auxiliary point: Take P
permanent point as auxiliary point
measured bearings and lengths of
P from each traverse point. If
survey is accurate, while plotting
all the measured bearing of P
should meet at P.
Problems:
 Convert the following WCBs to QBs
 (a) WCB of AB = 45°30’
(Ans 45°30’)
 (b) WCB of BC = 125°45’
(Ans 180- 125°45’ = 54° 15’)
 Fore bearing of the following lines are given. Find back bearing
 AB=S 30°30’ E
 BC=N 40°30’ W
 The magnetic bearing of a line AB is 135°30’ what will be the true
bearing, if the declination is 5°15’ W.
Problems
Contd…
Problems
Included angle at A= 280-180-40=60
=FB of DA-180-FB of AB
Included angle at B= 40+180-70= 150
=FB of AB+180-FB of BC
Included angle at C= 70+180-210
=FB of BC+180-FB of CD
Formula: FB of previous line+/-180-
FB of next line
Compass surveying

Mais conteúdo relacionado

Mais procurados

Contouring pdf
Contouring pdfContouring pdf
Contouring pdf
Gokul Saud
 

Mais procurados (20)

2.2 linear measurement
2.2 linear measurement2.2 linear measurement
2.2 linear measurement
 
Plane Table Survey
Plane Table SurveyPlane Table Survey
Plane Table Survey
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levelling
 
Plane table surveying ppt
Plane table surveying pptPlane table surveying ppt
Plane table surveying ppt
 
Levelling
LevellingLevelling
Levelling
 
Surveying presentation and its objectives in detail including principles,hist...
Surveying presentation and its objectives in detail including principles,hist...Surveying presentation and its objectives in detail including principles,hist...
Surveying presentation and its objectives in detail including principles,hist...
 
Compass surveying_Surveying, Civil Engineering
Compass surveying_Surveying, Civil EngineeringCompass surveying_Surveying, Civil Engineering
Compass surveying_Surveying, Civil Engineering
 
Instruments used in surveying
Instruments used in surveyingInstruments used in surveying
Instruments used in surveying
 
Plane Table Survey
Plane Table SurveyPlane Table Survey
Plane Table Survey
 
Traditional surveying techniques (introduction to civil engineering)
Traditional surveying techniques (introduction to civil engineering)Traditional surveying techniques (introduction to civil engineering)
Traditional surveying techniques (introduction to civil engineering)
 
Contouring in "Survey & Levelling".
Contouring in "Survey & Levelling".Contouring in "Survey & Levelling".
Contouring in "Survey & Levelling".
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
 
Theodolite surveying part1
Theodolite surveying part1Theodolite surveying part1
Theodolite surveying part1
 
3.compass surveying
3.compass surveying3.compass surveying
3.compass surveying
 
Contouring pdf
Contouring pdfContouring pdf
Contouring pdf
 
Advanced surveying equipment ppt
Advanced surveying equipment pptAdvanced surveying equipment ppt
Advanced surveying equipment ppt
 
traversing of survey
traversing of surveytraversing of survey
traversing of survey
 
Plane Table Surveying PPt
Plane Table Surveying PPtPlane Table Surveying PPt
Plane Table Surveying PPt
 
Chain surveying.1
Chain surveying.1Chain surveying.1
Chain surveying.1
 
Survey lecture-notes
Survey lecture-notesSurvey lecture-notes
Survey lecture-notes
 

Destaque (6)

Compass Surveying
Compass Surveying Compass Surveying
Compass Surveying
 
The Uses of Prismatic Compass Components
The Uses of Prismatic Compass ComponentsThe Uses of Prismatic Compass Components
The Uses of Prismatic Compass Components
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
Chap.6 traverse surveys
Chap.6 traverse surveysChap.6 traverse surveys
Chap.6 traverse surveys
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 

Semelhante a Compass surveying

Traverse Computations
Traverse ComputationsTraverse Computations
Traverse Computations
Bahzad5
 
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptxUnit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
OKOKILOUISmefgi
 
COMPASS SURVEYING btech civil ...-I.pptx
COMPASS SURVEYING btech civil ...-I.pptxCOMPASS SURVEYING btech civil ...-I.pptx
COMPASS SURVEYING btech civil ...-I.pptx
Ayushsharma131736
 

Semelhante a Compass surveying (20)

Compass surveying.ppt
Compass surveying.pptCompass surveying.ppt
Compass surveying.ppt
 
Compass surveying (1).ppt
Compass surveying (1).pptCompass surveying (1).ppt
Compass surveying (1).ppt
 
Compass Survaying
Compass SurvayingCompass Survaying
Compass Survaying
 
Compasssurveying 160050106053
Compasssurveying 160050106053Compasssurveying 160050106053
Compasssurveying 160050106053
 
1392741020 traverse survey
1392741020 traverse survey1392741020 traverse survey
1392741020 traverse survey
 
Traverse surveiying
Traverse surveiyingTraverse surveiying
Traverse surveiying
 
types of bearing
types of bearingtypes of bearing
types of bearing
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
traversing survey principles.docx
traversing survey principles.docxtraversing survey principles.docx
traversing survey principles.docx
 
COMPASS AND PLANE TABLE SURVEYING
COMPASS AND PLANE TABLE SURVEYINGCOMPASS AND PLANE TABLE SURVEYING
COMPASS AND PLANE TABLE SURVEYING
 
Traverse Computations
Traverse ComputationsTraverse Computations
Traverse Computations
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
Angular measurement for surveying
Angular measurement for surveyingAngular measurement for surveying
Angular measurement for surveying
 
Angular measurement
Angular measurementAngular measurement
Angular measurement
 
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptxUnit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
Unit3AngularMeasurementpptx__2022_01_08_11_22_11.pptx
 
Compass Surveying.ppt
Compass Surveying.pptCompass Surveying.ppt
Compass Surveying.ppt
 
CE(PC)403 Surveying & Geomatics
CE(PC)403 Surveying & GeomaticsCE(PC)403 Surveying & Geomatics
CE(PC)403 Surveying & Geomatics
 
Variations in Magnetic Declination
Variations in Magnetic DeclinationVariations in Magnetic Declination
Variations in Magnetic Declination
 
COMPASS SURVEYING btech civil ...-I.pptx
COMPASS SURVEYING btech civil ...-I.pptxCOMPASS SURVEYING btech civil ...-I.pptx
COMPASS SURVEYING btech civil ...-I.pptx
 
Prismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabus
Prismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabusPrismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabus
Prismetic compass ppt 3rd sem diploma and b.tech as per mdu and hsbte syllabus
 

Mais de Land Surveyors United Community

Mais de Land Surveyors United Community (20)

Introduction to Land Surveying
Introduction to Land SurveyingIntroduction to Land Surveying
Introduction to Land Surveying
 
Survey instruments
Survey instrumentsSurvey instruments
Survey instruments
 
Sokkia spectrum survey field reference manual
Sokkia spectrum survey field reference manualSokkia spectrum survey field reference manual
Sokkia spectrum survey field reference manual
 
Sokkia set20 k
Sokkia set20 kSokkia set20 k
Sokkia set20 k
 
Sokkia set6 manual
Sokkia set6 manualSokkia set6 manual
Sokkia set6 manual
 
Sokkia setx10 instruction_manual
Sokkia setx10 instruction_manualSokkia setx10 instruction_manual
Sokkia setx10 instruction_manual
 
Sokkia sdr-8100 operations manual
Sokkia sdr-8100 operations manualSokkia sdr-8100 operations manual
Sokkia sdr-8100 operations manual
 
216 surveying traverse explained
216 surveying traverse explained216 surveying traverse explained
216 surveying traverse explained
 
nikon nivo m-series instruction manual
nikon nivo m-series instruction manualnikon nivo m-series instruction manual
nikon nivo m-series instruction manual
 
Land Surveying Resources Handbook
Land Surveying Resources HandbookLand Surveying Resources Handbook
Land Surveying Resources Handbook
 
Fundamentals hp33s exam-review
Fundamentals hp33s exam-reviewFundamentals hp33s exam-review
Fundamentals hp33s exam-review
 
Using the scientific calculator
Using the scientific calculatorUsing the scientific calculator
Using the scientific calculator
 
Complex numbers & vectors hp35s overview
Complex numbers & vectors hp35s overviewComplex numbers & vectors hp35s overview
Complex numbers & vectors hp35s overview
 
Using the hp35s Calculator
Using the hp35s CalculatorUsing the hp35s Calculator
Using the hp35s Calculator
 
Programming 33s simple
Programming 33s simpleProgramming 33s simple
Programming 33s simple
 
Summing up 33_s
Summing up 33_sSumming up 33_s
Summing up 33_s
 
Hp33s calculator user_guide
Hp33s calculator user_guideHp33s calculator user_guide
Hp33s calculator user_guide
 
Programming Hp33s talk v3
Programming Hp33s talk v3Programming Hp33s talk v3
Programming Hp33s talk v3
 
Trimble R8 gnss r6-5800-364_userguide
Trimble R8 gnss r6-5800-364_userguideTrimble R8 gnss r6-5800-364_userguide
Trimble R8 gnss r6-5800-364_userguide
 
Nikon DTN502 instruction-manual-english
Nikon DTN502 instruction-manual-englishNikon DTN502 instruction-manual-english
Nikon DTN502 instruction-manual-english
 

Último

Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 

Último (20)

Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 

Compass surveying

  • 3. Compass traversing: Important Definition  True meridian: Line or plane passing through geographical north pole and geographical south pole  Magnetic meridian: When the magnetic needle is suspended freely and balanced properly, unaffected by magnetic substances, it indicates a direction. This direction is known as magnetic meridian. The angle between the magnetic meridian and a line is known as magnetic bearing or simple bearing of the line. North pole True meridian Magnetic meridian True bearing Magnetic bearing
  • 4.  Arbitrary meridian: Convenient direction is assumed as a meridian.  Grid meridian: Sometimes for preparing a map some state agencies assume several lines parallel to the true meridian for a particular zone these lines are termed as grid meridian.  Designation of magnetic bearing  Whole circle bearing (WCB)  Quadrantal bearing (QB)  WCB: The magnetic bearing of a line measured clockwise from the North Pole towards the line is known as WCB. Varies 0-360°
  • 5.  Quadrantal Bearing: The magnetic bearing of a line measured clockwise or anticlockwise from NP or SP (whichever is nearer to the line) towards the east or west is known as QB. This system consists of 4- quadrants NE, SE, NW, SW. The values lie between 0-90°  QB of OA = N a E  Reduced Bearing: When the whole circle bearing of a line is converted to quadrantal bearing it is termed as reduced bearing.  Fore and Back Bearing:  In WCB the difference between FB and BB should be exactly 180°  BB=FB+/-180°  Use the +ve sign when FB<180°  Use the –ve sign when FB> 180°
  • 6.  Magnetic declination: The horizontal angle between the magnetic meridian and true meridian is known as magnetic declination.  Dip of the magnetic needle: If the needle is perfectly balanced before magnetisation, it does not remain in the balanced position after it is magnetised. This is due to the magnetic influence of the earth. The needle is found to be inclined towards the pole. This inclination of the needle with the horizontal is known as dip of the magnetic needle.  Local Attraction  Method of correction for traverse:  First method: Sum of the interior angle should be equal to (2n-4) x 90. if not than distribute the total error equally to all interior angles of the traverse. Then starting from unaffected line the bearings of all the lines are corrected using corrected interior angles.  Second method: Unaffected line is first detected. Then, commencing from the unaffected line, the bearing of other affected lines are corrected by finding the amount of correction at each station.
  • 7.
  • 8.
  • 9. Methods of traversing  Chain traversing:  Compass traversing: Fore bearings and back bearings between the traverse leg are measured  Theodolite traversing: Horizontal angles between the traverse legs are measured. The length of the traverse legs are measured by chain/tape or by stadia method  Plane table traversing: Plane table is set at every traverse station in clockwise and anticlockwise direction and the circuit is finally closed. During traversing the sides of the traverse are plotted according to any suitable scale. 15 m 15 m
  • 10. Checks on traverse: Closed traverse  Check on closed traverse:  Sum of the measured interior angles (2n-4) x 90°  Sum of the measured exterior angles (2n+4) x 90 °  The algebric sum of the deflection angles should be equal to 360°. Right hand deflection is considered +ve, left hand deflection –ve  Check on linear measurement  The lines should be measured once each on two different days (along opposite directions). Both measurement should tally.  Linear measurement should also be taken by the stadia method. The measurement by chaining and stadia method should tally.
  • 11. Checks on traverse: Open traverse  Taking cut-off lines: measured the bearings and lengths of cut off lines after plotting and tally with actual values.  Taking an auxiliary point: Take P permanent point as auxiliary point measured bearings and lengths of P from each traverse point. If survey is accurate, while plotting all the measured bearing of P should meet at P.
  • 12. Problems:  Convert the following WCBs to QBs  (a) WCB of AB = 45°30’ (Ans 45°30’)  (b) WCB of BC = 125°45’ (Ans 180- 125°45’ = 54° 15’)  Fore bearing of the following lines are given. Find back bearing  AB=S 30°30’ E  BC=N 40°30’ W  The magnetic bearing of a line AB is 135°30’ what will be the true bearing, if the declination is 5°15’ W.
  • 14.
  • 16. Problems Included angle at A= 280-180-40=60 =FB of DA-180-FB of AB Included angle at B= 40+180-70= 150 =FB of AB+180-FB of BC Included angle at C= 70+180-210 =FB of BC+180-FB of CD Formula: FB of previous line+/-180- FB of next line