Two-dimensional planning based on time and location
Combines CAD and project management features
Excellent presentation capabilities Superb progress tracking
Data exchange with other major project planning software

2. Characteristics of a linear project
Repetition of each activity along the length of the project
The goal is to optimize the productivity rates thus minimizing the
total time of crews on the ROW thereby reducing project duration
and overall cost
Continuous movement of activities and crews along right-of-way
Typical projects include: rail, tunnel, highway, pipeline, bridge and
high voltage transmission line projects
4. TILOS vs. traditional CPM and Gantt charts
TILOS connects the geography and constructability issues of a project with the
schedule (what is built, when and where)
Traditional CPM schedules and network diagrams fail to provide a visual
connection between the project plan and the project itself
Present your project on a single page using TILOS!
40-page Primavera schedule
represented on one page using linear
planning
6. - How it works
Top soil
Bridge
Fill
Cut
Grading
Stabilisation
7. - The Gantt Chart features
Natural working with interactive Gantt chart
- Milestone symbols can be defined free and put to 1 task line
- Multiple tasks on one line
- Task steps to monitor micro tasks or extra work to happen before, during and after the task execution time
Multiple Windows support
- Move or copy tasks across the windows by mouse
- Create links across the windows
8. - Railway Project
High quality layouts keep attraction
Be one step ahead of your completion
o Pictures from site
o Scale with side map
o Main construction windows
o Detailed work
9. - Railway Project
o Generated sitemap and grid
from sector table
o Track renewal with hindrance
and setup times
o Full calculated ballast trains
incl. train setup
o Train runs for drive in and out
Realistic scheduling using site data that influences construction progress
Full integration of logistic and train rides
10. - Metro tunnel building
o Rock classification
table with drilling
speed for tasks
o Connector tunnels
o Tunnel lining
(1 task based on
work profile)
o Water draw down
zone
11. - Metro project: Elevated line
o Bend and Coordinates based
on station table
o Pile works generated based
on station table incl.
relationships
o Deck works generated by
station table
o Elevated station
Quick plan creation based
on station tables with
quantity values
Ideal overview on the
construction program
12. - Metro Rail Project in South Africa
o 8 zones with different station
numbering (non linear axis)
o Left part build as underground
o Cut and fill sections
o Evaluation phase
First basic construction
program in TILOS with later
detailing in Primavera
Update of TILOS schedule
done every 1 month using link
to Primavera
13. - Industry sample: Pipeline
o Elevation profile
o Strong rain fall
o Pump stations
o Linear works
Pipeline project planned in 2 spreads to cover weather conditions
Rainfall is shown in colors in the background of the schedule
16. - Highway Project
o Preparation
o Bridges
o Cut & Fill
o Black tops
o Monitoring
o Handover
17. TILOS progress reporting
Progress always contains distance
information, not just % completed
Enter progress directly into TILOS for
an immediate evaluation
Record progress
Import progress (Clipboard or XML)
Analyse progress
Apply progress
18. Project description in XLS
Description of the track including
GPS co-ordinates
Description of the project
complexities
19. Planning result in Google Maps
Track renewal activity sliced into 3 hour
working and reporting steps
06:00 – 09:00
03:00 – 06:00
00:00 – 03:00
20. Progress in Google
XML Export with time sliced data shows progress status along the ROW
Comparison: planned (thick line)
@ 3am
actual (thin line)
@ 6am
@ 9am
22. - XML: Data Exchange concept
o Library data
ASC
Clipboard / File
- Resources and accounts
- Categories (Codes)
- Distance and time profile data
o Tasks
o Task data
- Resource and cost data
- Actual resource data
- Links
- Progress
XML
TILOS
Microsoft Project
o XLS Exchange
- Same items as for ASC
- Each object in a separate data sheet
o XLS Report
Excel
- Export of task list with resources assignments
- Summary of resource consumption at the end
- Time sliced values (Days / Week / Month / Years)
- Empty lines for collect actual data
ASTA Power Project
Oracle Primavera
Other programs
23. - XML: Export from TILOS
o Select Action
- File / Import
- File / Export
o Select format
- ASC
- XML
- Excel
o Data source
- Select Clipboard or File
o Select profile
- Data exchange rules
o Select project
- Select sub projects
- Set a filter
o Start exchange
24. - XML Exchange with Primavera
o Log in
- Standard Primavera Log in
o Select action
- Import or Export
- Create user fields
o Data source
- Select profile to use
(Contains exchange rules)
- Select data file
(Contains exchange data)
o Projects and filters
- Select project
- Select a filter for export
o Start Import
25. - Primavera Master Project
o Task ID from TILOS (alternatively GUID)
o WBS code
o Location data (UDF fields)
o TILOS Template as code assignment
26. TILOS – professional linear project management solution
A tool that connects schedule and site
information in a single chart. Site
constraints are integrated into the plan
from the beginning
Is used in any project phase: FEED,
Tendering and Estimating, Execution
and Claim analysis.
A tool that can be used by any
participant in the construction process:
Owners, Engineers and Construction
company.
TIME DISTANCE is superior to GANTT CHARTS for
linear projects.
Rapid creation of repetitive tasks in different locations
saves time and effort for detailed planning. Easy clash
detection and avoiding errors saves money during
construction phase.
Powerful progress measurement tool to monitor
construction exactly as it was done in the field ( movearounds, work stoppages and out of sequence
progress).
Flexible integration methods allow usage of TILOS
along with other software and also if the project has
already started.
27. What one of our clients is saying
"TILOS transformed our engineers' attitude
towards project scheduling from something
extra they never had time for to a tool they
"owned" and wouldn't go to a meeting without.”
James Lyon - HDR Inc. in USA
28. Cityringen project in Kopenhagen, Length: 15.2 km
Finish: in 2018
TILOS was used in early design phase to schedule
TBM and the work in stations. We got the following
remark on TILOS from :
“TILOS is being used as the strategic planning tool for
the Copenhagen Cityringen Project. Early in the
project it was used to assess the impact of different
TBM sequences and number of TBM’s on both the
overall programme and the interfaces with the
individual station construction. As the project has
developed the tool has been invaluable in quickly
assessing the affects of changes, possible delays and
determining suitable mitigation measures, for both
the TBM drives and the station constructions. Not
only has TILOS been great as an analysis tool, but the
easy to understand graphical output provides a simple
tool for explaining the planning to all members of the
project team.”
This from :
Steen Nielsen
Head of Planning
Metroselskabet I/S
Metrovej 5
DK - 2300 Copenhagen S
More info about project and contracts: http://intl.m.dk/Cityringen-en.aspx
29. Pipeline project Alberta Clipper, Canada
Enbridge Pipelines Inc. operates, in Canada and the U.S., the
world’s longest crude oil and liquids pipeline system. These
pipeline systems have operated for over 55 years and now
comprise approximately 13,500 kilometres (8,500 miles) of
pipeline, delivering more than 2 million barrels per day of crude oil
and liquids. Alberta Clipper is a crude oil pipeline that will provide
service between Hardisty, Alberta, and Superior, Wis. This 1,000mile / 1,607-km pipeline will have an initial capacity of 450,000
barrels per day (bpd), with ultimate capacity of up to 800,000 bpd
available.
Enbridge Pipelines Inc. used TILOS as their best in class linear
scheduling tool for managing the Alberta Clipper Mainline
Construction for this immense project in Canada. The software
was used in the field, and in the main offices to bring together
stakeholders to greatly enhance planning, and reporting making
the project a huge success.
More info about pipeline projects: http://linearproject.com/pipeline-construction.html
30. Who is using TILOS ?
Railway companies: Saudi Archirodon, DB, SNCF, Network Rail, Herzog, Nurol Construction,
Dogus, Larsen & Toubro Ltd., Qatar Railway Company, MMC Gamuda
Railway equipment: Alstom, Bombardier, Siemens, IJM CorporationBuilding companies: Bilfinger Berger, Hochtief, Strabag, Skanska, Bouygues, Vinci, Hill
International, Kiewit, Flatiron, Enka, Parsons-UAE
Engineering: Bechtel, Fluor, HDR Inc, Drees & Sommer, Lahmeyer, DB Consult,
SNC Lavalin, Gulf Interstate, Worley Parsons, Engineers India Ltd. Indian
Institute of Technology, Leighton Contractors Asia Limited, AECOM
Pipeline: TransCanada, Enbridge, Willbros, Henkels & McCoy, Techint, Repsol, Rel.Gas
Transport. Infra.LTD, NABUCCO Consortium, Stroytransgaz, Punj Lloyd Oil & Gas
Power: ATCO Electric, Balfour Beatty
Road: Mota-Engil, Hess. Straßenbauamt, Hermann Kirchner, DMRC
Metro / light rail: Kopenhagen, Dallas, Toronto Transit, Houston Rapid Transit, Astaldi,
Gulermak
TILOS (TIme LOcation System)