SlideShare uma empresa Scribd logo
1 de 15
CASE STUDY ON CONSTRUCTION OF
SUPER STRUCTURE BY CAST IN PLACE
METHOD
PRESENTED BY :
KHAUSHAL TADAS
Cast in Place
INTRODUCTION:-
Cast-in-place concrete, also known as poured-in-place, is a concreting technique which is
undertaken in situ or in the concrete component’s finished position. Cast-in-place
concrete is the preferred choice for concrete slabs and foundations, as well
as components such as beams, columns, walls, roof’s, and so on.
 Allows concrete to be formed to site conditions
 Used on most construction sites for structural members
 Concrete placed in forms to cure
 Forms removed after enough strength in concrete to support self and additional
construction loads
ADVANTAGES OF CAST-IN-PLACE METHOD & PRECAST
CONCRETE
CAST-IN-PLACE PRECAST CONCRETE
 Limitless flexibility of shape and size.  Entire building can be precast-walls,
floors, beams etc.
 Wide variety of surface and textures can
be achieved.
 More durable than real masonry.
 Homogeneous connections.  Optimum use of materials.
DISADVANTAGES OF CAST-IN-PLACE METHOD &
PRECAST CONCRETE
CAST-IN-PLACE PRECAST CONCRETE
 Needs high labor and plant on site.  Very heavy members.
 Formwork is time consuming.  Connections may be difficult.
 Quality control is difficult.  Somewhat limited building design.
CASE STUDY :- IOWA RIVER BRIDGE
INTRODUCTION:-
 The bridge was constructed using the launching method due to a number of very
stringent environmental restrictions near the project.
 These environmental issues included endangered mussel species residing in the
Iowa, endangered plant species near the site and Native American artifacts near
the site.
 In addition, a bald eagle roosting area was identified near the site. An extensive
environmental monitoring program was established and maintained during
construction.
BRIDGE STRUCTURAL DESCRIPTION
 The bridge consists of two parallel deck superstructures, each with five equal
spans of 92 m (302’). A 19 m (62’) prestressed concrete jump span is provided
on each end of the steel unit.
 The I-girders were fabricated from ASTM A709 Grade 345 weathering steel;
they are 3450 mm (11’) deep and spaced at 3600 mm (12’) centers.
 To make the I-girder superstructure act as much like a torsionally rigid box
girder as possible during launching, a stiff system of diaphragms and lateral
bracing was used.
 A diaphragm spacing of 7,000 mm (23’) was used for spans two through five,
but was reduced to 3,500 mm (11’6”) in the leading span that would be
cantilevered during launching.
BRIDGE LAUNCHING SYSTEM
 The bridge superstructure was completely erected on steel falsework and
custom-made 18” diameter rollers behind the east abutment.
 A 146’ long, tapered steel launching nose was erected at the leading end of
the girders and used to reduce the cantilever deflection during each launching
operation.
 After each span was launched forward, additional steel girder sections,
including diaphragms and bracing, were pushed forward to land on the
subsequent pier.
 The process was completed five times for each steel superstructure. After the
complete launching of the eastbound girders, the falsework was removed and
reinstalled to perform an identical launching of the westbound superstructure.
PROJECT PHOTOS
CASE STUDY:- THE STONEY TRAIL
BRIDGE
INTRODUCTION
 The Stoney Trail Bridge is a horizontally curved, segmentally constructed
bridge and was the second incrementally launched reinforced concrete bridge
to be built in North America (first in Canada).
 Each of the concrete segments was built on one bank and then jacked
horizontally into its final position atop 30 m high ‘Y’ shaped concrete piers.
 This structure is the featured element of a $48M (Canada) project forming the
first leg of a long awaited northwest perimeter transportation corridor for the
city of Calgary.
 The incremental launching technique was particularly well suited for this
project because of the $1.5M (Canada) cost savings that this method offered,
and also because of the sensitive nature of the surrounding environment: the
south bank contains one of the few stands of Douglas Fir trees in this area.
BRIDGE DESCRIPTION
 The bridge is a 476 m (1562 ft) x 21 m (68 ft), 5-span structure with a main
span of 102 m (335 ft), 40 m (131 ft) above the Bow river valley. The
superstructure consists of a 4.5 m (15 ft) deep girder elements.
 It consists of cast-inplace concrete abutments, piers and superstructures.
 The superstructure section is a post-tensioned, double-celled monolithic
concrete box structure and was cast in two stages: soffit and webs cast
together, followed by the deck in two segmental casting beds.
 The box girder and deck was assembled in segments (total of 19 segments) on
the north bank, post-tensioned with steel reinforcing cables, and then pushed
from the north abutment to the south.
 Each completed segment (1200 tons) is 25.5 m (84 ft) long with the exception
of end segments which are 22 m (72 ft) long
BRIDGE CONSTRUCTION AND LAUNCHING
 The bridge construction involved curved, post-tensioned segmental concrete
placed with hydraulic jacks for both vertical lifting and horizontal sliding.
 The bridge superstructure was pushed and pulled with hydraulic jacks over a
system of temporary sliding bearings and lateral guides that were mounted on
permanent and temporary piers.
 During the launching, external post-tensioning was performed inside each cell
to provide the structural support.
 The precise/prestressed construction methodology reduced the amount of
equipment and limited work crew contact with environmentally sensitive sites.
Special attention was given to minimize the amount of runoff discharge
directly into the river.
PROJECT PHOTOS
THANK YOU

Mais conteúdo relacionado

Mais procurados

Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training pptSumit Singh
 
Scaffolding & underpinning
Scaffolding & underpinningScaffolding & underpinning
Scaffolding & underpinningJitesh Dhule
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed ConcreteRavi Savani
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameAbdul Rahman
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionMadan Mohan Jana
 
PREFABRICATION AND MODULAR COORDINATION
PREFABRICATION AND MODULAR COORDINATIONPREFABRICATION AND MODULAR COORDINATION
PREFABRICATION AND MODULAR COORDINATIONsreestr18
 
Steel connections
Steel connectionsSteel connections
Steel connectionsbabunaveen
 
TYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSTYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSMaharshi Dave
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSASHOK KUMAR TIWARY
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundationSourabh Jain
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridgesmukul srivastava
 

Mais procurados (20)

Presentation1
Presentation1Presentation1
Presentation1
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Scaffolding & underpinning
Scaffolding & underpinningScaffolding & underpinning
Scaffolding & underpinning
 
Staircase design
Staircase designStaircase design
Staircase design
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
Slipform
SlipformSlipform
Slipform
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
PREFABRICATION AND MODULAR COORDINATION
PREFABRICATION AND MODULAR COORDINATIONPREFABRICATION AND MODULAR COORDINATION
PREFABRICATION AND MODULAR COORDINATION
 
Steel connections
Steel connectionsSteel connections
Steel connections
 
Retaining walls
Retaining walls Retaining walls
Retaining walls
 
Roof truss
Roof trussRoof truss
Roof truss
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
TYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONSTYPES OF PILE FOUNDATION & APPLICATIONS
TYPES OF PILE FOUNDATION & APPLICATIONS
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Composite floors
Composite  floorsComposite  floors
Composite floors
 
Precast segmental construction of bridges
Precast segmental construction of bridgesPrecast segmental construction of bridges
Precast segmental construction of bridges
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 

Semelhante a Cast in situ bridge superstracture

stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkKAVYA H
 
steelstructures-130906015820-.pdf
steelstructures-130906015820-.pdfsteelstructures-130906015820-.pdf
steelstructures-130906015820-.pdfrubini32
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxRajeshKumar25548
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridgejupallipavan2911
 
Application of plate girders in steel construction
Application of plate girders in steel constructionApplication of plate girders in steel construction
Application of plate girders in steel constructionHaider Jafferi
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
BURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural SystemBURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural SystemABDURRAB ANSARI
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 
Dhruvin kurilpa bridge
Dhruvin kurilpa bridgeDhruvin kurilpa bridge
Dhruvin kurilpa bridgeDhruv Seth
 
Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysisMohammad Ali
 
Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.Franco Bontempi
 

Semelhante a Cast in situ bridge superstracture (20)

stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Tony
TonyTony
Tony
 
steelstructures-130906015820-.pdf
steelstructures-130906015820-.pdfsteelstructures-130906015820-.pdf
steelstructures-130906015820-.pdf
 
Steel structures
Steel structuresSteel structures
Steel structures
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
Bridges Functionality and Aesthetics
Bridges Functionality and AestheticsBridges Functionality and Aesthetics
Bridges Functionality and Aesthetics
 
Bridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdfBridge-SGI-01_Pranoti.pdf
Bridge-SGI-01_Pranoti.pdf
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
 
Application of plate girders in steel construction
Application of plate girders in steel constructionApplication of plate girders in steel construction
Application of plate girders in steel construction
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
BURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural SystemBURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural System
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Bridge-SIT-01.pptx
Bridge-SIT-01.pptxBridge-SIT-01.pptx
Bridge-SIT-01.pptx
 
Dhruvin kurilpa bridge
Dhruvin kurilpa bridgeDhruvin kurilpa bridge
Dhruvin kurilpa bridge
 
Suspension Bridges
Suspension BridgesSuspension Bridges
Suspension Bridges
 
Al dar hq
Al dar hqAl dar hq
Al dar hq
 
Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
 
Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.Cable stayed bridges of prestressed concrete.
Cable stayed bridges of prestressed concrete.
 

Último

ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Último (20)

ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

Cast in situ bridge superstracture

  • 1. CASE STUDY ON CONSTRUCTION OF SUPER STRUCTURE BY CAST IN PLACE METHOD PRESENTED BY : KHAUSHAL TADAS
  • 2. Cast in Place INTRODUCTION:- Cast-in-place concrete, also known as poured-in-place, is a concreting technique which is undertaken in situ or in the concrete component’s finished position. Cast-in-place concrete is the preferred choice for concrete slabs and foundations, as well as components such as beams, columns, walls, roof’s, and so on.  Allows concrete to be formed to site conditions  Used on most construction sites for structural members  Concrete placed in forms to cure  Forms removed after enough strength in concrete to support self and additional construction loads
  • 3. ADVANTAGES OF CAST-IN-PLACE METHOD & PRECAST CONCRETE CAST-IN-PLACE PRECAST CONCRETE  Limitless flexibility of shape and size.  Entire building can be precast-walls, floors, beams etc.  Wide variety of surface and textures can be achieved.  More durable than real masonry.  Homogeneous connections.  Optimum use of materials.
  • 4. DISADVANTAGES OF CAST-IN-PLACE METHOD & PRECAST CONCRETE CAST-IN-PLACE PRECAST CONCRETE  Needs high labor and plant on site.  Very heavy members.  Formwork is time consuming.  Connections may be difficult.  Quality control is difficult.  Somewhat limited building design.
  • 5. CASE STUDY :- IOWA RIVER BRIDGE
  • 6. INTRODUCTION:-  The bridge was constructed using the launching method due to a number of very stringent environmental restrictions near the project.  These environmental issues included endangered mussel species residing in the Iowa, endangered plant species near the site and Native American artifacts near the site.  In addition, a bald eagle roosting area was identified near the site. An extensive environmental monitoring program was established and maintained during construction.
  • 7. BRIDGE STRUCTURAL DESCRIPTION  The bridge consists of two parallel deck superstructures, each with five equal spans of 92 m (302’). A 19 m (62’) prestressed concrete jump span is provided on each end of the steel unit.  The I-girders were fabricated from ASTM A709 Grade 345 weathering steel; they are 3450 mm (11’) deep and spaced at 3600 mm (12’) centers.  To make the I-girder superstructure act as much like a torsionally rigid box girder as possible during launching, a stiff system of diaphragms and lateral bracing was used.  A diaphragm spacing of 7,000 mm (23’) was used for spans two through five, but was reduced to 3,500 mm (11’6”) in the leading span that would be cantilevered during launching.
  • 8. BRIDGE LAUNCHING SYSTEM  The bridge superstructure was completely erected on steel falsework and custom-made 18” diameter rollers behind the east abutment.  A 146’ long, tapered steel launching nose was erected at the leading end of the girders and used to reduce the cantilever deflection during each launching operation.  After each span was launched forward, additional steel girder sections, including diaphragms and bracing, were pushed forward to land on the subsequent pier.  The process was completed five times for each steel superstructure. After the complete launching of the eastbound girders, the falsework was removed and reinstalled to perform an identical launching of the westbound superstructure.
  • 10. CASE STUDY:- THE STONEY TRAIL BRIDGE
  • 11. INTRODUCTION  The Stoney Trail Bridge is a horizontally curved, segmentally constructed bridge and was the second incrementally launched reinforced concrete bridge to be built in North America (first in Canada).  Each of the concrete segments was built on one bank and then jacked horizontally into its final position atop 30 m high ‘Y’ shaped concrete piers.  This structure is the featured element of a $48M (Canada) project forming the first leg of a long awaited northwest perimeter transportation corridor for the city of Calgary.  The incremental launching technique was particularly well suited for this project because of the $1.5M (Canada) cost savings that this method offered, and also because of the sensitive nature of the surrounding environment: the south bank contains one of the few stands of Douglas Fir trees in this area.
  • 12. BRIDGE DESCRIPTION  The bridge is a 476 m (1562 ft) x 21 m (68 ft), 5-span structure with a main span of 102 m (335 ft), 40 m (131 ft) above the Bow river valley. The superstructure consists of a 4.5 m (15 ft) deep girder elements.  It consists of cast-inplace concrete abutments, piers and superstructures.  The superstructure section is a post-tensioned, double-celled monolithic concrete box structure and was cast in two stages: soffit and webs cast together, followed by the deck in two segmental casting beds.  The box girder and deck was assembled in segments (total of 19 segments) on the north bank, post-tensioned with steel reinforcing cables, and then pushed from the north abutment to the south.  Each completed segment (1200 tons) is 25.5 m (84 ft) long with the exception of end segments which are 22 m (72 ft) long
  • 13. BRIDGE CONSTRUCTION AND LAUNCHING  The bridge construction involved curved, post-tensioned segmental concrete placed with hydraulic jacks for both vertical lifting and horizontal sliding.  The bridge superstructure was pushed and pulled with hydraulic jacks over a system of temporary sliding bearings and lateral guides that were mounted on permanent and temporary piers.  During the launching, external post-tensioning was performed inside each cell to provide the structural support.  The precise/prestressed construction methodology reduced the amount of equipment and limited work crew contact with environmentally sensitive sites. Special attention was given to minimize the amount of runoff discharge directly into the river.