SlideShare uma empresa Scribd logo
1 de 31
Energy Storage:
New Capabilities for the
Electric Grid –
The Tehachapi Energy
Storage Project
Next Generation Batteries 2015
April 21-22, 2015
San Diego, CA
Loïc Gaillac
Advanced Energy Storage Group Manager
Advanced Technology
Southern California Edison
Kevin Fok
Senior Project Manager
Energy Solution Company
LG Chem
Introduction
• Tehachapi Energy Storage Project (TSP):
– 32 MWh, 9 MVA (8 MW, 4 MVAr) Battery Energy Storage
System (BESS)
– Located at Monolith Substation in the Tehachapi Wind
Resource Area
– Jointly funded by Southern California Edison (SCE) and the
United States Department of Energy (DOE)
• SCE contracted with LG Chem. to:
– Design, construct, and maintain the system for a two-year
measurement and validation (M&V) period
• M&V period includes:
– Collection of BESS and electric system data
– Analysis of the project’s effect on the regional transmission
network
– Gaining experience and knowledge about the operation of a
large BESS
2
Project Objectives
• Test the BESS as a system reliability and/or market
driven device
– Demonstrate the performance of a lithium-ion Battery
Energy Storage System for 13 specific operational uses,
both individually and bundled
– Share data and results with CAISO, CEC, CPUC, DOE,
and other interested parties
– Assist in the integration of large-scale variable energy
resources
• Integrate battery storage technology into SCE’s
grid
– Test and demonstrate smart inverter technology
– Assess performance and life cycle of grid-connected
lithium-ion BESS
– Expand expertise in energy storage technologies and
operations
3
• 14 million customers: one of the
largest utilities in US
• 125 years of service
• Award-winning energy efficiency
and demand response programs
Southern California Edison
Committed to
safely providing,
reliable and
affordable electric
service
4
LG Group
5
LG was founded in 1947 as the first Korean chemical company and has successfully expanded its
business portfolio to a broad range of products and solutions in the chemical, electronics, and
telecommunications and services sectors
Chemicals
Electronics
16
17
16
LG Chem
LG Hausys
LG Life Sciences
LG Household & Healthcare
…
LG Electronics
LG Display
LG Innotek
LG Siltron
…
LG U+
LG CNS
LG International
SERVEONE
...
 Founded – 1947
 Revenue (2014) – $148B USD
 Employees – 226,000
Telecomm-
unications
& Services
• Located in the Tehachapi
area, California’s largest
wind resource
• Massive wind development
potential (up to 4,500MW)
driving grid infrastructure
• Installed at SCE’s Monolith
Substation
• 6,300 ft2 building
• Connected at sub-
transmission level through a
12/66kV transformer
6
BESS facility at Monolith
Substation
BESS facility and 12kV/66kV
transformer
TSP Facility
TSP Layout
7
System
Specifications
• Battery Storage
System
– Li-Ion
– Manufactured by LG
Chem.
– 32MWh usable
• Power Conversion
System
– 9MVA
– 12kV connected
– Manufactured by
ABB
8
System Design
• Several design iterations performed
• Significant challenge to meet required
footprint
• HVAC study for thermal analysis
– Modified and optimized thermal management
based on:
• Battery rack temperature distribution
• Maximum temperature differences
• Temperature transients
• Analysis of fire suppression system
– Performed destructive tests with representative
battery elements using different spatial
configurations for external short circuit, and thermal
runaway conditions
9
System Design (continued)
• Met stringent standards
– Electrolyte: Evaluated using Cup Burner Test NFPA 2001 Standard on Clean Agent Fire
Extinguishing Systems (2012 edition)
– Battery Cells: UL Listed (UL 1642)
– Battery Modules: UL Listed (UL 1973)
– Battery Rack with Modules Installed: Electromagnetic compatibility (FCC Part 15B)
– Battery Protection Unit: Electromagnetic compatibility:
• Conducted Emission EN 61000-6-3:2007+a1:2011
• Electrostatic Discharge(ESD) EN 61000-4-2:2009
• Radiated RF Electromagnetic Fields EN 61000-4-3:2006+A2:2010
• Electrical Fast Transients / Burst(EFT) EN 61000-4-4:2004+A2:2010
• Surges EN 61000-4-5:2006
• Immunity to Conducted Disturbances EN 61000-4-6:2009
• Power Frequency Magnetic Field Immunity Test EN 61000-4-8:2010
• Voltage Dips and Interruptions EN 61000-4-11:2004
– Battery Racks with Modules Installed:
• Tested to IEEE 693-2005 (IEEE Recommended Practice for Seismic Design of Substations)
• Meet Zone 4 seismic requirements
– PCS modules:
• UL Listed (UL 1741)
• Site Security System
– SCE designed and completed security system to substation standards
10
System Configuration
11
x 56 x 18 x 151 x 4
Cell Module Rack Section System
Quantity 608,832 10,872 604 4 1
Voltage 3.7 V 52 V 930 V 930 V 930 V
Energy 60 Wh 3.2 kWh 58 kWh 8.7 MWh 32 MWh (AC)
Weight 380 g 40 kg 950 kg N/A N/A
How to get 32MWh from 60Wh battery cells
Construction
• Dealt with challenges of a remote area
• Site constraints with local railroad tracks, high
pressure gas lines, substation
• Very limited storage space
• Many “non-battery” tasks
• Windy weather
• Rodents and insects
12
Construction
Construction
• Text
14
Commissioning
• Project team members collaborated closely to
develop the commissioning plan
• Plan involved several iterations of reviews and
revisions
• PCS controls, Battery and overall system
controls, and IT components were
commissioned in parallel whenever possible
• June 2014: BESS delivered 32 MWh during initial
commissioning tests
• September 2014: Grand Opening Ceremony
15
Grand Opening Ceremony
16
TSP Testing and Evaluation
• Operational Uses
• Core Tests
• System Operational
&Validation Challenges
• Mini-System Testing
• System Acceptance
Testing
• Preliminary
Characterization Testing
17
TSP 13 Operational Uses
• Transmission
– Provide voltage support/grid stabilization
– Decrease transmission losses
– Diminish congestion
– Increase system reliability
– Defer transmission investment
– Enhance value and effectiveness of
renewable energy-related transmission
• System
– Provide system capacity/resource adequacy
– Integrate renewable energy (smoothing)
– Shift wind generation output
• Market
– Frequency signal/response
– Spin/non-spin/replacement reserves
– Ramp management
– Energy price arbitrage
18
8 Core Tests
1) Provide steady state voltage regulation and dynamic voltage
support at the local 66 kV bus
2) Perform Test 1 while operating under any mode and performing
real power injection/absorption required under such mode
3) Charge during periods of high line loading and discharge during
low line loading under SCE system operator control
4) Charge during off-peak periods and discharge during on-peak
periods under SCE system operator control
5) Charge and discharge seconds-to-minutes as needed to firm
and shape intermittent generation in response to a real-time
signal
6) Respond to CAISO control signals to provide frequency
regulation
7) Respond to CAISO market awards to provide energy and
spin/non-spin reserves
8) Follow a CAISO market signal for energy price
19
System Pre-operation Challenges
20
Challenges Resolutions
System integration between all
components; Sub-components may
be mature but system integration is not
Assess system performance, safety
and reliability prior to field
deployment
System Acceptance Testing (SAT) is
impractical on site
Introduced multi-step Acceptance
testing based on lab evaluation of:
• Communication system by SCE IT
group
• PCS controller on the RTDS (Real
Time Digital Simulator)
• Mini-system
Framework around control ownership
in a non-vertically-integrated utility:
• Generator controlled by Power
Supply Group
• Grid reliability asset controlled by
Grid Control Center
• Shared optimized asset
Engage stakeholders and identify
requirements to be completed for
(inter)connection, deployment and
control
System Validation Challenges
• Large energy storage systems are modular
– Comprised of AC and DC subsystems
– Scaled by adding additional components in
series/parallel
– Multiple manufacturers
– Requires complex integration
– Increased likelihood of problems
• Utilities need to assess safety and reliability prior to
field deployment
• Issues with testing large systems in the field
– Grid/personnel safety
– Geographic distance
– Need to exchange significant power at will
– Hardware/firmware/software problems can take many
months to solve
21
System Validation Approach: Mini-System Lab Testing
Mini-System Full System
Footprint 77 ft2 6300 ft2
building
Power 30 kW 8 MW
Energy 116 kWh 32 MWh
Power
Conversion
System
One Mini-
Cabinet
Two 40-foot
containers
Sections 1 4
Banks 1 32
Racks 2 604
Modules 36 10,872
Cells 2,016 608,832
Mini-System for Sub-scale Testing
Mini-System enables subscale testing in the lab before full-scale
operation of the BESS at Monolith Substation
22
Battery Racks
Power
Conversion
System (PCS)
Mini System at SCE laboratory
Site Energy Controller Battery Section
Controller
PCS & DC
Switchgear
Controls
Mini System at SCE Laboratory (cont.)
Mini-System Testing Key Findings
25
Key Findings Benefits
Discovered and resolved critical
safety and operational aspects
regarding the battery system and
PCS
Minimum impact of safety and
operational issues, quick to
resolve
Several iterations of
software/firmware upgrades
required
Significant time and resources
saved due to upgrades
performed in the lab at subscale
level versus full-scale at remote
substation location
24/7 operation for more than 4
months prior to full system
commissioning yielded feedback
to implement many additional
functional upgrades
System operation and features
have been enhanced
(optimized control algorithms)
System Acceptance Testing
• Purpose
– To verify that the BESS met all technical requirements
including the ability to deliver 32 MWh of energy over four
hours of continuous discharge at 8 MW
• Outcome
– BESS successfully completed all commissioning tests in two
weeks without any technical issues
26
Initial Operation – System Acceptance
Testing
27
Full Discharge:
• 8MW - 4 hours
• 32MWh
Characterization Testing
• Background
– System acceptance tests included a discharge
capacity test to verify 32 MWh discharge
– Capacity test did not measure round trip efficiency
or operate system under continuous cycling profiles
• Objectives
– To characterize behavior and performance of
system during continuous full charge/discharge
cycles at 8 and 4 MW
– To analyze power, energy, efficiency, and
temperature data from battery system, PCS, and
point of common coupling
Preliminary Characterization Results
• Completed testing at 8 MW in December 2014
• Analysis excludes auxiliary loads for battery
building and PCS (to be included in subsequent
tests)
• Test Conditions
• BESS Operating SOC Range: 2.5% to 98%
• Rest Time Between Charge and Discharge: <15 min
• All measurements taking at the 66kV point of
common coupling
Average
Charge
Energy
Average
Discharge
Energy
Average
Round Trip
Efficiency
34.93 MWh 31.64 MWh 90.6 %
Current Status
• In January 2015, a medium voltage transformer failure
occurred in one PCS with no impact to other
equipment
• Root cause analysis showed that the design of
transformer did not support all operational
requirements
• Transformers were redesigned and the facility was shut
down to facilitate replacement
• Operation of the system was restored on April 18th, 2015
• Lessons Learned (vendor perspective)
– Evaluate all requirements and associated impacts on each component’s
design
– Facilitate component replacement in design
– Real operations provide real learning
– Deployment experiences are valuable for all stakeholders
30
Final Thoughts
• Installation, deployment and preliminary operation
of large-scale ESS has:
– Provided key learning to facilitate future deployments
– Demonstrated the benefits of Mini-System testing
– Shown that all components are critical, including
transformers
• Close collaboration between utility and turnkey
system provider has accelerated lessons learned
31

Mais conteúdo relacionado

Mais procurados

B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead StrategyB4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead StrategyIceland Geothermal
 
GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)
GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)
GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)GE코리아
 
Session 03 solar pv rooftop technology overview
Session 03   solar pv rooftop technology overviewSession 03   solar pv rooftop technology overview
Session 03 solar pv rooftop technology overviewChirag Jain
 
Sino danish microgrid tech. research & demonstration
Sino danish microgrid tech. research & demonstrationSino danish microgrid tech. research & demonstration
Sino danish microgrid tech. research & demonstrationJuan C. Vasquez
 
L’esperienza della California, Mark Rothleder
L’esperienza della California, Mark RothlederL’esperienza della California, Mark Rothleder
L’esperienza della California, Mark RothlederTerna SpA
 
Session 06 balance of system components
Session 06   balance of system componentsSession 06   balance of system components
Session 06 balance of system componentsChirag Jain
 
Keynote icdcm Josep Guerrero
Keynote icdcm Josep GuerreroKeynote icdcm Josep Guerrero
Keynote icdcm Josep GuerreroJuan C. Vasquez
 
2017 Atlanta Regional User Seminar - Real-Time Volt/Var Optimization Scheme f...
2017 Atlanta Regional User Seminar - Real-Time Volt/Var Optimization Scheme f...2017 Atlanta Regional User Seminar - Real-Time Volt/Var Optimization Scheme f...
2017 Atlanta Regional User Seminar - Real-Time Volt/Var Optimization Scheme f...OPAL-RT TECHNOLOGIES
 
Session 04 solar pv modules
Session 04   solar pv modulesSession 04   solar pv modules
Session 04 solar pv modulesChirag Jain
 
Lm 80 best practices - 06062016v2
Lm 80 best practices - 06062016v2Lm 80 best practices - 06062016v2
Lm 80 best practices - 06062016v2Ashlee Palka
 
Decentralized Generation In Microgrids
Decentralized Generation In MicrogridsDecentralized Generation In Microgrids
Decentralized Generation In MicrogridsJuan C. Vasquez
 
Presentation SIW7 amjad anvari-moghaddam
Presentation SIW7 amjad anvari-moghaddamPresentation SIW7 amjad anvari-moghaddam
Presentation SIW7 amjad anvari-moghaddamJuan C. Vasquez
 
2017 Atlanta Regional User Seminar - Residential Battery Storage Systems. Des...
2017 Atlanta Regional User Seminar - Residential Battery Storage Systems. Des...2017 Atlanta Regional User Seminar - Residential Battery Storage Systems. Des...
2017 Atlanta Regional User Seminar - Residential Battery Storage Systems. Des...OPAL-RT TECHNOLOGIES
 
EES-UETP Microgrid course
 EES-UETP Microgrid course EES-UETP Microgrid course
EES-UETP Microgrid courseJuan C. Vasquez
 
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...usman1441
 
NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales solpowerpeople
 

Mais procurados (20)

B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead StrategyB4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
B4 - Successful Implementation of a Modular Geothermal Wellhead Strategy
 
GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)
GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)
GE LV5 1500V 태양광 인버터(LV5 1500V Solar Inverter)
 
Session 03 solar pv rooftop technology overview
Session 03   solar pv rooftop technology overviewSession 03   solar pv rooftop technology overview
Session 03 solar pv rooftop technology overview
 
Sino danish microgrid tech. research & demonstration
Sino danish microgrid tech. research & demonstrationSino danish microgrid tech. research & demonstration
Sino danish microgrid tech. research & demonstration
 
L’esperienza della California, Mark Rothleder
L’esperienza della California, Mark RothlederL’esperienza della California, Mark Rothleder
L’esperienza della California, Mark Rothleder
 
Iecon15 AMI
Iecon15 AMIIecon15 AMI
Iecon15 AMI
 
Session 06 balance of system components
Session 06   balance of system componentsSession 06   balance of system components
Session 06 balance of system components
 
Keynote icdcm Josep Guerrero
Keynote icdcm Josep GuerreroKeynote icdcm Josep Guerrero
Keynote icdcm Josep Guerrero
 
2017 Atlanta Regional User Seminar - Real-Time Volt/Var Optimization Scheme f...
2017 Atlanta Regional User Seminar - Real-Time Volt/Var Optimization Scheme f...2017 Atlanta Regional User Seminar - Real-Time Volt/Var Optimization Scheme f...
2017 Atlanta Regional User Seminar - Real-Time Volt/Var Optimization Scheme f...
 
Session 04 solar pv modules
Session 04   solar pv modulesSession 04   solar pv modules
Session 04 solar pv modules
 
isie yajuan guan_final_3x
isie yajuan guan_final_3xisie yajuan guan_final_3x
isie yajuan guan_final_3x
 
Lm 80 best practices - 06062016v2
Lm 80 best practices - 06062016v2Lm 80 best practices - 06062016v2
Lm 80 best practices - 06062016v2
 
Decentralized Generation In Microgrids
Decentralized Generation In MicrogridsDecentralized Generation In Microgrids
Decentralized Generation In Microgrids
 
Presentation SIW7 amjad anvari-moghaddam
Presentation SIW7 amjad anvari-moghaddamPresentation SIW7 amjad anvari-moghaddam
Presentation SIW7 amjad anvari-moghaddam
 
2017 Atlanta Regional User Seminar - Residential Battery Storage Systems. Des...
2017 Atlanta Regional User Seminar - Residential Battery Storage Systems. Des...2017 Atlanta Regional User Seminar - Residential Battery Storage Systems. Des...
2017 Atlanta Regional User Seminar - Residential Battery Storage Systems. Des...
 
EES-UETP Microgrid course
 EES-UETP Microgrid course EES-UETP Microgrid course
EES-UETP Microgrid course
 
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...
Modelling and Control of a Microgrid with100kW PV System and Electrochemical ...
 
Energy Storage solutions
Energy Storage solutionsEnergy Storage solutions
Energy Storage solutions
 
NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales NABCEP Exam Prep Review for PV Installation & Tech Sales 
NABCEP Exam Prep Review for PV Installation & Tech Sales 
 
Quotation 10 kw_ongrid_rajkot_std
Quotation 10 kw_ongrid_rajkot_stdQuotation 10 kw_ongrid_rajkot_std
Quotation 10 kw_ongrid_rajkot_std
 

Semelhante a Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy Storage Project

RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia LaboratoryRT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia LaboratoryOPAL-RT TECHNOLOGIES
 
Smart Grid for US-China Green Energy Council
Smart Grid for US-China Green Energy CouncilSmart Grid for US-China Green Energy Council
Smart Grid for US-China Green Energy CouncilStephen Lee
 
Australian Energy Storage Conference and Exhibition 2017 - 14-15 Jun 2017 in ...
Australian Energy Storage Conference and Exhibition 2017 - 14-15 Jun 2017 in ...Australian Energy Storage Conference and Exhibition 2017 - 14-15 Jun 2017 in ...
Australian Energy Storage Conference and Exhibition 2017 - 14-15 Jun 2017 in ...Michael Willemot, Msc, MBA
 
Rebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futureRebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futurejames hamilton
 
Brian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building PowerBrian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building PowerEnergyTech2015
 
schneider-electric-storage.pptx
schneider-electric-storage.pptxschneider-electric-storage.pptx
schneider-electric-storage.pptxPoooi2
 
ahmed mohamed diaa_original
ahmed mohamed diaa_originalahmed mohamed diaa_original
ahmed mohamed diaa_originalAHMED DIAA
 
Accelerators at ORNL - Application Readiness, Early Science, and Industry Impact
Accelerators at ORNL - Application Readiness, Early Science, and Industry ImpactAccelerators at ORNL - Application Readiness, Early Science, and Industry Impact
Accelerators at ORNL - Application Readiness, Early Science, and Industry Impactinside-BigData.com
 
Critical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignCritical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignConsultingSpecifyingEngineer
 
RT15 Berkeley | Power HIL Simulator (SimP) A prototype to develop a high band...
RT15 Berkeley | Power HIL Simulator (SimP) A prototype to develop a high band...RT15 Berkeley | Power HIL Simulator (SimP) A prototype to develop a high band...
RT15 Berkeley | Power HIL Simulator (SimP) A prototype to develop a high band...OPAL-RT TECHNOLOGIES
 
APsystems Value Proposition
APsystems Value PropositionAPsystems Value Proposition
APsystems Value PropositionClive Rippon
 
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Parker Hannifin Corporation
 
SunSpec SPG & Distributech Briefing
SunSpec SPG & Distributech BriefingSunSpec SPG & Distributech Briefing
SunSpec SPG & Distributech BriefingDylan Tansy
 
RF Battery Solar PPT
RF Battery Solar PPTRF Battery Solar PPT
RF Battery Solar PPTGeof Moser
 

Semelhante a Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy Storage Project (20)

RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia LaboratoryRT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
 
Smart Grid for US-China Green Energy Council
Smart Grid for US-China Green Energy CouncilSmart Grid for US-China Green Energy Council
Smart Grid for US-China Green Energy Council
 
Australian Energy Storage Conference and Exhibition 2017 - 14-15 Jun 2017 in ...
Australian Energy Storage Conference and Exhibition 2017 - 14-15 Jun 2017 in ...Australian Energy Storage Conference and Exhibition 2017 - 14-15 Jun 2017 in ...
Australian Energy Storage Conference and Exhibition 2017 - 14-15 Jun 2017 in ...
 
Rebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-futureRebecca mills-securing-the-n ts-energy-future
Rebecca mills-securing-the-n ts-energy-future
 
Brian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building PowerBrian Patterson: Reinventing Building Power
Brian Patterson: Reinventing Building Power
 
schneider-electric-storage.pptx
schneider-electric-storage.pptxschneider-electric-storage.pptx
schneider-electric-storage.pptx
 
gridFUTURE, A Concept
gridFUTURE, A ConceptgridFUTURE, A Concept
gridFUTURE, A Concept
 
ahmed mohamed diaa_original
ahmed mohamed diaa_originalahmed mohamed diaa_original
ahmed mohamed diaa_original
 
OPAL-RT & Hydro-Quebec - HYPERSIM
OPAL-RT & Hydro-Quebec - HYPERSIMOPAL-RT & Hydro-Quebec - HYPERSIM
OPAL-RT & Hydro-Quebec - HYPERSIM
 
1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid
1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid
1.3. MCAGCC 29 Palms Microgrid_Morrissett_EPRI/SNL Microgrid
 
Accelerators at ORNL - Application Readiness, Early Science, and Industry Impact
Accelerators at ORNL - Application Readiness, Early Science, and Industry ImpactAccelerators at ORNL - Application Readiness, Early Science, and Industry Impact
Accelerators at ORNL - Application Readiness, Early Science, and Industry Impact
 
Session I hahk sung lee
Session I hahk sung leeSession I hahk sung lee
Session I hahk sung lee
 
Critical Power: Generators and Generator System Design
Critical Power: Generators and Generator System DesignCritical Power: Generators and Generator System Design
Critical Power: Generators and Generator System Design
 
RT15 Berkeley | Power HIL Simulator (SimP) A prototype to develop a high band...
RT15 Berkeley | Power HIL Simulator (SimP) A prototype to develop a high band...RT15 Berkeley | Power HIL Simulator (SimP) A prototype to develop a high band...
RT15 Berkeley | Power HIL Simulator (SimP) A prototype to develop a high band...
 
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
10.6_Utility Microgrids_Reid_EPRI/SNL Microgrid Symposium
 
APsystems Value Proposition
APsystems Value PropositionAPsystems Value Proposition
APsystems Value Proposition
 
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017Solving Energy Storage Challenges Offshore | Offshore Europe 2017
Solving Energy Storage Challenges Offshore | Offshore Europe 2017
 
SunSpec SPG & Distributech Briefing
SunSpec SPG & Distributech BriefingSunSpec SPG & Distributech Briefing
SunSpec SPG & Distributech Briefing
 
RF Battery Solar PPT
RF Battery Solar PPTRF Battery Solar PPT
RF Battery Solar PPT
 
HEL-BAH
HEL-BAHHEL-BAH
HEL-BAH
 

Último

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 

Último (20)

DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 

Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy Storage Project

  • 1. Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy Storage Project Next Generation Batteries 2015 April 21-22, 2015 San Diego, CA Loïc Gaillac Advanced Energy Storage Group Manager Advanced Technology Southern California Edison Kevin Fok Senior Project Manager Energy Solution Company LG Chem
  • 2. Introduction • Tehachapi Energy Storage Project (TSP): – 32 MWh, 9 MVA (8 MW, 4 MVAr) Battery Energy Storage System (BESS) – Located at Monolith Substation in the Tehachapi Wind Resource Area – Jointly funded by Southern California Edison (SCE) and the United States Department of Energy (DOE) • SCE contracted with LG Chem. to: – Design, construct, and maintain the system for a two-year measurement and validation (M&V) period • M&V period includes: – Collection of BESS and electric system data – Analysis of the project’s effect on the regional transmission network – Gaining experience and knowledge about the operation of a large BESS 2
  • 3. Project Objectives • Test the BESS as a system reliability and/or market driven device – Demonstrate the performance of a lithium-ion Battery Energy Storage System for 13 specific operational uses, both individually and bundled – Share data and results with CAISO, CEC, CPUC, DOE, and other interested parties – Assist in the integration of large-scale variable energy resources • Integrate battery storage technology into SCE’s grid – Test and demonstrate smart inverter technology – Assess performance and life cycle of grid-connected lithium-ion BESS – Expand expertise in energy storage technologies and operations 3
  • 4. • 14 million customers: one of the largest utilities in US • 125 years of service • Award-winning energy efficiency and demand response programs Southern California Edison Committed to safely providing, reliable and affordable electric service 4
  • 5. LG Group 5 LG was founded in 1947 as the first Korean chemical company and has successfully expanded its business portfolio to a broad range of products and solutions in the chemical, electronics, and telecommunications and services sectors Chemicals Electronics 16 17 16 LG Chem LG Hausys LG Life Sciences LG Household & Healthcare … LG Electronics LG Display LG Innotek LG Siltron … LG U+ LG CNS LG International SERVEONE ...  Founded – 1947  Revenue (2014) – $148B USD  Employees – 226,000 Telecomm- unications & Services
  • 6. • Located in the Tehachapi area, California’s largest wind resource • Massive wind development potential (up to 4,500MW) driving grid infrastructure • Installed at SCE’s Monolith Substation • 6,300 ft2 building • Connected at sub- transmission level through a 12/66kV transformer 6 BESS facility at Monolith Substation BESS facility and 12kV/66kV transformer TSP Facility
  • 8. System Specifications • Battery Storage System – Li-Ion – Manufactured by LG Chem. – 32MWh usable • Power Conversion System – 9MVA – 12kV connected – Manufactured by ABB 8
  • 9. System Design • Several design iterations performed • Significant challenge to meet required footprint • HVAC study for thermal analysis – Modified and optimized thermal management based on: • Battery rack temperature distribution • Maximum temperature differences • Temperature transients • Analysis of fire suppression system – Performed destructive tests with representative battery elements using different spatial configurations for external short circuit, and thermal runaway conditions 9
  • 10. System Design (continued) • Met stringent standards – Electrolyte: Evaluated using Cup Burner Test NFPA 2001 Standard on Clean Agent Fire Extinguishing Systems (2012 edition) – Battery Cells: UL Listed (UL 1642) – Battery Modules: UL Listed (UL 1973) – Battery Rack with Modules Installed: Electromagnetic compatibility (FCC Part 15B) – Battery Protection Unit: Electromagnetic compatibility: • Conducted Emission EN 61000-6-3:2007+a1:2011 • Electrostatic Discharge(ESD) EN 61000-4-2:2009 • Radiated RF Electromagnetic Fields EN 61000-4-3:2006+A2:2010 • Electrical Fast Transients / Burst(EFT) EN 61000-4-4:2004+A2:2010 • Surges EN 61000-4-5:2006 • Immunity to Conducted Disturbances EN 61000-4-6:2009 • Power Frequency Magnetic Field Immunity Test EN 61000-4-8:2010 • Voltage Dips and Interruptions EN 61000-4-11:2004 – Battery Racks with Modules Installed: • Tested to IEEE 693-2005 (IEEE Recommended Practice for Seismic Design of Substations) • Meet Zone 4 seismic requirements – PCS modules: • UL Listed (UL 1741) • Site Security System – SCE designed and completed security system to substation standards 10
  • 11. System Configuration 11 x 56 x 18 x 151 x 4 Cell Module Rack Section System Quantity 608,832 10,872 604 4 1 Voltage 3.7 V 52 V 930 V 930 V 930 V Energy 60 Wh 3.2 kWh 58 kWh 8.7 MWh 32 MWh (AC) Weight 380 g 40 kg 950 kg N/A N/A How to get 32MWh from 60Wh battery cells
  • 12. Construction • Dealt with challenges of a remote area • Site constraints with local railroad tracks, high pressure gas lines, substation • Very limited storage space • Many “non-battery” tasks • Windy weather • Rodents and insects 12
  • 15. Commissioning • Project team members collaborated closely to develop the commissioning plan • Plan involved several iterations of reviews and revisions • PCS controls, Battery and overall system controls, and IT components were commissioned in parallel whenever possible • June 2014: BESS delivered 32 MWh during initial commissioning tests • September 2014: Grand Opening Ceremony 15
  • 17. TSP Testing and Evaluation • Operational Uses • Core Tests • System Operational &Validation Challenges • Mini-System Testing • System Acceptance Testing • Preliminary Characterization Testing 17
  • 18. TSP 13 Operational Uses • Transmission – Provide voltage support/grid stabilization – Decrease transmission losses – Diminish congestion – Increase system reliability – Defer transmission investment – Enhance value and effectiveness of renewable energy-related transmission • System – Provide system capacity/resource adequacy – Integrate renewable energy (smoothing) – Shift wind generation output • Market – Frequency signal/response – Spin/non-spin/replacement reserves – Ramp management – Energy price arbitrage 18
  • 19. 8 Core Tests 1) Provide steady state voltage regulation and dynamic voltage support at the local 66 kV bus 2) Perform Test 1 while operating under any mode and performing real power injection/absorption required under such mode 3) Charge during periods of high line loading and discharge during low line loading under SCE system operator control 4) Charge during off-peak periods and discharge during on-peak periods under SCE system operator control 5) Charge and discharge seconds-to-minutes as needed to firm and shape intermittent generation in response to a real-time signal 6) Respond to CAISO control signals to provide frequency regulation 7) Respond to CAISO market awards to provide energy and spin/non-spin reserves 8) Follow a CAISO market signal for energy price 19
  • 20. System Pre-operation Challenges 20 Challenges Resolutions System integration between all components; Sub-components may be mature but system integration is not Assess system performance, safety and reliability prior to field deployment System Acceptance Testing (SAT) is impractical on site Introduced multi-step Acceptance testing based on lab evaluation of: • Communication system by SCE IT group • PCS controller on the RTDS (Real Time Digital Simulator) • Mini-system Framework around control ownership in a non-vertically-integrated utility: • Generator controlled by Power Supply Group • Grid reliability asset controlled by Grid Control Center • Shared optimized asset Engage stakeholders and identify requirements to be completed for (inter)connection, deployment and control
  • 21. System Validation Challenges • Large energy storage systems are modular – Comprised of AC and DC subsystems – Scaled by adding additional components in series/parallel – Multiple manufacturers – Requires complex integration – Increased likelihood of problems • Utilities need to assess safety and reliability prior to field deployment • Issues with testing large systems in the field – Grid/personnel safety – Geographic distance – Need to exchange significant power at will – Hardware/firmware/software problems can take many months to solve 21
  • 22. System Validation Approach: Mini-System Lab Testing Mini-System Full System Footprint 77 ft2 6300 ft2 building Power 30 kW 8 MW Energy 116 kWh 32 MWh Power Conversion System One Mini- Cabinet Two 40-foot containers Sections 1 4 Banks 1 32 Racks 2 604 Modules 36 10,872 Cells 2,016 608,832 Mini-System for Sub-scale Testing Mini-System enables subscale testing in the lab before full-scale operation of the BESS at Monolith Substation 22
  • 24. Site Energy Controller Battery Section Controller PCS & DC Switchgear Controls Mini System at SCE Laboratory (cont.)
  • 25. Mini-System Testing Key Findings 25 Key Findings Benefits Discovered and resolved critical safety and operational aspects regarding the battery system and PCS Minimum impact of safety and operational issues, quick to resolve Several iterations of software/firmware upgrades required Significant time and resources saved due to upgrades performed in the lab at subscale level versus full-scale at remote substation location 24/7 operation for more than 4 months prior to full system commissioning yielded feedback to implement many additional functional upgrades System operation and features have been enhanced (optimized control algorithms)
  • 26. System Acceptance Testing • Purpose – To verify that the BESS met all technical requirements including the ability to deliver 32 MWh of energy over four hours of continuous discharge at 8 MW • Outcome – BESS successfully completed all commissioning tests in two weeks without any technical issues 26
  • 27. Initial Operation – System Acceptance Testing 27 Full Discharge: • 8MW - 4 hours • 32MWh
  • 28. Characterization Testing • Background – System acceptance tests included a discharge capacity test to verify 32 MWh discharge – Capacity test did not measure round trip efficiency or operate system under continuous cycling profiles • Objectives – To characterize behavior and performance of system during continuous full charge/discharge cycles at 8 and 4 MW – To analyze power, energy, efficiency, and temperature data from battery system, PCS, and point of common coupling
  • 29. Preliminary Characterization Results • Completed testing at 8 MW in December 2014 • Analysis excludes auxiliary loads for battery building and PCS (to be included in subsequent tests) • Test Conditions • BESS Operating SOC Range: 2.5% to 98% • Rest Time Between Charge and Discharge: <15 min • All measurements taking at the 66kV point of common coupling Average Charge Energy Average Discharge Energy Average Round Trip Efficiency 34.93 MWh 31.64 MWh 90.6 %
  • 30. Current Status • In January 2015, a medium voltage transformer failure occurred in one PCS with no impact to other equipment • Root cause analysis showed that the design of transformer did not support all operational requirements • Transformers were redesigned and the facility was shut down to facilitate replacement • Operation of the system was restored on April 18th, 2015 • Lessons Learned (vendor perspective) – Evaluate all requirements and associated impacts on each component’s design – Facilitate component replacement in design – Real operations provide real learning – Deployment experiences are valuable for all stakeholders 30
  • 31. Final Thoughts • Installation, deployment and preliminary operation of large-scale ESS has: – Provided key learning to facilitate future deployments – Demonstrated the benefits of Mini-System testing – Shown that all components are critical, including transformers • Close collaboration between utility and turnkey system provider has accelerated lessons learned 31