SlideShare uma empresa Scribd logo
1 de 71
Baixar para ler offline
RVU
chala D (PhD)
By
Chala Dechassa (PhD, Assistant
Professor)
Chapter Four
Financial Analysis
Purpose of Financial Feasibility Analysis
• For investors to engage in a new investment project, the
project has to be financially viable.
• Invested capital must show the potential to generate an
economic return to investors at least equal to that available
from other similarly risky investments, i.e. the return on
investment needs to be equal or higher.
• For example, an investor expects a manufacturing facility to
generate sufficient cash flows from operation to pay for the
construction of the facility and ongoing operating expenses
and, have an attractive interest rate of return.
Cont’d
• Estimates the cost of operating and maintaining a
manufacturing plant, as well as expected income generated.
• Financial feasibility analysis is an analytical tool used to
evaluate the viability of an investment.
• A financial decision is dependent on two specific factors,
expected return and expected risk, and a financial feasibility
analysis is a means for examining those two factors.
-
Main reason to conduct financial feasibility
study) to (Reference Chapter 3 Reason Why
Feasibility Study
Cont’d
• It should be conducted before proceeding with the development
of a business idea, and that also applies for financial feasibility
analysis.
• Determining early that a business idea is not financially feasible
can prevent loss of money and waste of valuable time.
• Financial feasibility analysis is usually done during the project
planning process and the results indicate how the project will
perform under a specific set of assumptions regarding
technology, market conditions and financial aspects.
Cont’d
• Analyzing the financial feasibility of a project is an essential part of the
decision making process.
• Even though the analysis is used on the first stages of the decision-
making process as a screening method, the analysis should also be used
throughout the process and should be updated every time any of the
assumptions it is based on changes.
• if the results of the analysis show that the proposed project does not
meet the return on investment requirements of the investor, the
business idea is discarded.
• It is therefore very important to regularly update the analysis and
verify that, given the newest information, the project is financially
feasible.
Feasibility Study vs. Business Plan
• Feasibility studies and business plans are two separate tools used
for decision making in project development.
– Both tools have common components, but should nevertheless not be
confused as their roles are different.
 A feasibility study is a tool for investigating the viability of the
prospective project.
• A business plan is a tool for planning the actions needed to take
the project proposal from an idea to reality.
• The feasibility study refines the initial business idea, while the
business plan uses information from the feasibility study to
further prepare the project to evolve into an operating business.
Cont’d
• A feasibility study is conducted on the very first stages of project
development, before financing is secured and a GO/NON-GO
decision has been made.
• The purpose of the study is to reveal whether or not the project
is viable from all aspects, feasibility study components
• If the results of the study are positive, indicating that the project
will be successful, much of the information from the study is
incorporated into a business plan.
• However, if the results are negative, there is no need to create a
business plan (Matson, 2000).
• A feasibility study usually analyzes several project alternatives or
methods of achieving success.
Cont’d
• The purpose is to narrow the scope of the project and to
identify the best scenario.
– A business plan only deals with one scenario, i.e. the scenario found to be
most prominent by the feasibility study.
• A business plan captures the goals and objectives of a business
idea.
• The plan serves as a blueprint for the implementation of the project, as
well as the actions taken during and after project
implementation.
Cont’d
• A feasibility study is used throughout the whole process, first as a
screening tool and then as a part of a business plan.
– As the financial feasibility of a project is a key element in a
feasibility study, it is also a key element in a business plan.
• The business plan is often used as a sales document, helping the
project owners to secure financing for the project.
– It is also used to persuade specialists to participate in the
project and public authorities to give permissions for
operations.
Conducting Financial Feasibility Analysis
• Financial feasibility analysis is conducted by developing a base
case financial plan and assessing the sensitivity of the
profitability of the project, and the projected return, on the
investor’s equity to various contingencies.
• Needed for analyzing fluctuation in product price, changes in
operating and maintenance cost, the effects of cost overruns,
delay in completion, interruptions of project operations and
other significant factors.
Cont’d
The following outline when conducting financial feasibility analysis:
 Estimate the total capital requirements – seed capital, capital for facilities and
equipment, working capital, start-up capital, contingency capital, etc;
 Estimate equity and credit needs - identify equity sources and capital
availability, identify credit sources, assess expected financing requirements,
and establish debt to equity levels;
 Budget expected costs and returns of various alternatives – estimate expected
cost and revenue, the profit margin and expected net profit, the sales or usage
needed to break-even, the returns under various production, price and sales
levels,
Project financing
• There are two types of project financing:
– equity and
– debt financing.
– When looking for money, you must consider your company’s debt-to-
equity ratio.
– The relation between amounts borrowed and amounts invested to the
business by the owners. The more money owners have invested in their
business, the easier it is to attract financing.
Equity Financing:
 Most small or growth-stage businesses use limited equity financing.
 As with debt financing, additional equity often comes from non-
professional investors such as friends, relatives, employees, customers,
or industry colleagues.
– However, the most common source of professional equity funding
comes from venture capitalists.
– These are institutional risk takers and may be groups of wealthy
individuals,
Cont’d
• Government-assisted sources, or major financial institutions.
• Most specialize in one or a few closely related industries.
• Venture capitalists may scrutinize thousands of potential
investments annually, but only invest in a handful.
• The possibility of a public stock offering is critical to venture
capitalists.
• Quality management, a competitive or innovative advantage,
and industry growth are also major concerns
Debt Financing:
• There are many sources for debt financing:
• banks,
• savings and loans
• , commercial finance companies, and
• the microfinance institutions.
Cont’d
• State and local governments have developed many programs
in recent years to encourage the growth of small businesses in
recognition of their positive effects on the economy.
• Family members, friends, and former associates are all
potential sources, especially when capital requirements are
smaller.
Cont’d
• Traditionally, banks have been the major source of small
business funding.
• Their principal role has been as a short-term lender offering
demand loans, seasonal lines of credit, and single-purpose
loans for machinery and equipment.
• In addition to equity considerations, lenders commonly require
the borrower’s personal guarantees in case of default. This
ensures that the borrower has a sufficient personal interest at
stake to give paramount attention to the business. For most
borrowers this is a burden, but also a necessity.
Project Decision Making Criteria
The investment criteria could be classified into two:
1. Non-discounting Criteria
2. Discounting criteria
What is the difference between these techniques?
8/1/2021 19
20
1. Non-discounted techniques:
• These techniques are simple to understand and easy to compute.
• They don’t recognize the time value of money
• Though these techniques are simple to understand and easy to
compute, they suffer from the following limitations.
 They don’t recognize the time value of money
 They fail to recognize the projects return in totality-they
ignore cash flows beyond the payback period
8/1/2021
8/1/2021
2. Discounted appraisal techniques considers both the estimated
total cash inflows and the time value of money.
That is:
 Recognize the time value of money
 Recognize the benefits of the project in totality (except
discounted pay back period)
21
1) Non-discounting Criteria
a) Payback period
b) Accounting rate of return
2) Discounting criteria include:
a) Net present value
b) Profitability Index/Benefit cost ratio
c) Internal rate of return
d) Discounted pay back period
8/1/2021 22
Methods of Evaluating Projects:
• In order to evaluate the financial feasibility of an investment
project, relevant measurements or criteria need to be
specified. Remer and Nieto (1995) categorize the evaluation
methods into five basic types:
Discounting Non discounting
1. Net Present Value 4. Payback period
2. Benefit-Cost Ratio 5. accounting rate of return
3. Internal rate of return 6. ROI.
Net Present Value:
• Net Present Value (NPV) is the difference between the present
value of all cash inflows and cash outflows associated with an
investment project.
• Net present value of a project is the sum of the present values
of all the cash flows associated with it. The cash flows can be
positive or negative.
NPV
• In order to calculate the NPV, (considerate )
– the interest rate used for discounting the cash flows needs to
be determined. The interest rate is often referred to as
Minimum
– Attractive Rate of Return (ARR) and it represents the rate at
which the investor can alternatively invest his money, i.e. the
return of the most preferable alternative investment.
– The planning horizon of the project also needs to be
determined, and the cash flows for each period of the
planning horizon projected .
Net Present Value(Measures of Project Worth)
• The Net Present Value (NPV) of a project is the sum of the project values of all
the cash flows-positive as well as negative-that are expected to occur over the life
of the project.
• The general formula for NPV is:
• where
• Ct = net cash flow at the end of year t(
• n= life of the project
• r = discount rate
• I investment cost
I
r
c
NPV
n
t
t
t


 
1 )
1
(
CONT’D
• If the NPV(i) is positive for a single project, the project should be accepted,
since a positive
• NPV means that the project has greater equivalent value of
inflows than outflows and therefore makes a profit (Park, 2002).
• According to Park (2002) the decision rule for NPV is:
• If NPV(i) > 0, accept the investment;
• If NPV(i) =0, remain indifferent to the investment;
• NPV(i) < 0, reject the investment.
CONT’D
• When comparing mutually exclusive alternatives the
one with the greatest positive NPV is selected.
– However, when comparing alternatives it is important
to use the same interest rate for all alternatives.
– All projects must also be compared over equal time
periods.
• In the case of mutually exclusive alternatives
generating the same revenues, compare the projects
on a cost-only basis.
– Then the project resulting in the smallest, or least
negative, NPV should be accepted, since the objective is
to minimize cost.
Measures of Project Worth ( example 1)
Year Cash flow
0 Birr (1,000,000)
1 200,000
2 200,000
3 300,000
4 300,000
5 350,000
If the cost of capital (discount rate) is 10%, then NPV is calculated
as follows
273
,
5
000
,
000
,
1
)
10
.
1
(
000
,
350
)
10
.
1
(
000
,
300
)
10
.
1
(
000
,
300
)
10
.
1
(
000
,
200
)
10
.
1
(
000
,
200
5
4
3
2
1








NPV
NPV/I = Profitability Index
Measures of Project Worth
• The NPV represents the net benefit over and above the
compensation for time and risk.
• Hence, the decision rule associated with the net present value
criterion is:
–accept the project if the NPV is positive and
–reject it if NPV is negative.
Measures of Project Worth( example 2)
Interest rate 14% 15% 16% 18% 20%
Investment -12000
Cash flow 4,000 5,000 7,000 6,000 5,000
3509
14
.
1
/
000
,
4
1


C
PV
3814
)
15
.
1
14
.
1
/(
000
,
5
2



C
PV
4603
)
16
.
1
15
.
1
14
.
1
/(
000
,
7
3




C
PV
3344
)
18
.
1
16
.
1
15
.
1
14
.
1
/(
000
,
6
4





C
PV
2322
)
20
.
1
18
.
1
16
.
1
15
.
1
14
.
1
/(
000
,
5
5






C
PV
NPV of Project =3509+3814+4603+3344+2322-12000 = 5592
Project Analysis & Management
(ASA)
Example 3
After tax cash flows of a small scale tannery project is given
below. Find the profitability index if discount rate is assumed to
be 12%?
Year 0 1 2 3 4 5
CFs 40,000 15,000 14,000 13,000 12,000 11,000
…Cont’d
Project Analysis & Management
(ASA)
…Cont’d
Solutions
Year Cash Flow Rate = (12%) PV
1 15,000 0.893 13,395
2 14,000 0.797 11,158
3 13,000 0.712 9,256
4 12,000 0.636 7,636
5 11,000 0.567 6,237
Total
Therefore, PI=47,678 = 1.192
40,000
47,678
CONT’D
Advantages:
• It takes into account the time value of money with changing
discount rate.
• It can be used to evaluate mutually exclusive projects.
• It takes into consideration the total benefits arising out of the
project over its lifetime.
Disadvantages
• It does not take into account the life of the project and may
not give dependable result for projects having different lives.
• The NPV method is an absolute method and may not give
dependable results in case the projects have different outlays.
Benefit-Cost Ratio
• The benefit-cost method is often used for public projects.
• The method compares project benefits to the cost of the
project, and for the project to be viable, the benefits have to
be greater than the cost.
• Park (2002) describes benefit-cost analysis as “a decision-
making tool used to systematically develop useful
information about the desirable and undesirable effects of
public projects”.
• Benefit-Cost Ratio BCR= Present value of inflows/Initial
Investments PI= Present value of cash inflows/Present value
of cash outflows
– If BCR is greater than 1, accept the project If BCR is less than 1,
reject the project.
CONT’D
• three types of benefit-cost analysis problems:
1. Maximizing the benefits for any given set of cost;
2. Maximizing the net benefits when both benefits and
costs vary;
3. Minimizing cost to achieve any given level of benefits.
• The worthiness of a public project can be expressed by
comparing the benefits (B) of the project to the cost (C) of the
project by taking the ratio B/C, i.e. the Benefit- Cost ratio.
Benefit-Cost Ratio:
• Benefit-Cost Ratio: There are two ways of defining the relationship
between benefits and costs:
• Example: 12% discount
NBCR = BCR-1= 0.145
I
PVB
BCR 
1



 BCR
I
I
PVB
NBCR
(1)
(2)
PVB = present value of benefits, I = initial investment
100,000
Benefits Year 1 25000
Year 2 40000
Year 3 40000
Year 4 50000
145
.
1
000
,
100
)
12
.
1
(
000
,
50
)
12
.
1
(
000
,
40
)
12
.
1
(
000
,
40
)
12
.
1
(
000
,
25
4
3
2





BCR
When BCR > 1 or NBCR > 0 accept
When BCR < 1 or NBCR < 0 reject the project
Cont’d
• Advantages
• Evaluate the project in the relative terms
– Two projects having different cash outlays and lifetime can be evaluated
• Takes into consideration time value of money and totality of benefits
• Dis advantages
– When comparing mutually exclusive alternatives, the Benefit-Cost Ratio
cannot be used unless using incremental analysis.
– This is due to the fact that the ratio does not differentiate between
investments of different sizes, e.g. a $10 investment and a $1000
investment.
– Then the incremental differences for each term are calculated and the
B/C ratio taken from these differences (Park, 2002).
Internal Rate of Return:
– Internal Rate of Return (IRR) is a concept based on the
return on invested capital in terms of a project
investment.
– The internal rate of return( IRR) is defined as the rate of
discount, which brings about equality between the present
value of future net benefits & initial investment.
– The investment has zero NPV at this rate of return, noted as
r*. Therefore, r*serves as a benchmark interest rate, making
investors able to accept or reject decision consistent with the
NPV analysis.
CONT’D
• Internal rate of return (IRR) is the discount rate which makes
its net present value equal to zero.
• It is the value of r in the following equation.
• Where,
– I – investment cost
– Ct – Net benefit for year t
– r - IRR
– n - Life of the project
• Illustration: For project A in the table below can be formulated
as follows:
 

 

n
t
t
t
r
C
I
1 1
Measures of Project Worth
• The calculation of r involves a process of trial and error. We try different values r till
we find that the right-hand side of the above equation is equal to 100,000. Let us
try to use 15%. This makes the right-hand side to be:
       4
3
2
1
1
000
,
45
1
000
,
40
1
000
,
30
1
000
,
30
000
,
100
r
r
r
r 







Year 0 1 2 3 4
Cash flow (100,000) 30,000 30,000 40,000 45,000
IRR is the value of r which satisfies the following equation:
       
802
,
100
15
.
1
000
,
45
15
.
1
000
,
40
15
.
1
000
,
30
15
.
1
000
,
30
000
,
100 4
3
2





Since the value is slightly higher than our target value, which is 100,000, we
increase the value to 16%.
       
641
,
98
16
.
1
000
,
45
16
.
1
000
,
40
16
.
1
000
,
30
16
.
1
000
,
30
000
,
100 4
3
2





Measures of Project Worth
• Since this value is now less than 100,000, we conclude that the value of r lies
between 15 and 16%. For most of the purposes, this indication suffices.
• If a more refined estimate of r is needed, we use the following procedure:
1. Determine the NPV of the two closest rates of return
(NPV/15%) = 802
(NPV/16%) = 1,359
2. Find the sum of the absolute values of the NPVs obtained in Step 1
802+1,359 = 2,161
3. Calculate the ratio of the NPV of the smaller discount rate, identified in Step 1, to
the sum obtained in Step 2
802/2,161 = 0.37
4. Add the number obtained in Step 3 to the smallest discount rate
15+0.37 = 15.37
Project Analysis & Management
(ASA)
Class Work
A project has a total outlay of Br. 500,000 with the following pattern of
cash inflow. Compute the IRR of the project
Year 1 2 3 4 5
CFs 120 120 120 150 150
(in thousands)
…Cont’d
Project Analysis & Management
(ASA)
Year 1 2 3 4 5
CFs 5000 4000 3000 2000 8000
…Cont’d
Exercise
A project requires a new investment of 20,000 and produces the
following cash flows. Compute the IRR of the project
Cont’d
NPV Vs IRR
 For making choice between two projects competing for
the funds at the disposal of a concern, the NPV method
can give a better choice because it can give idea of
ranking of the projects.
Project Analysis & Management
(ASA)
Advantages
• Takes into consideration time value of money and totality of benefit
Provides the rate of return which indicates the profitability of the
proposal
• The difference between the IRR and the cost of capital indicates the
additional return for risk that the project provides.
Disadvantages of IRR
• Tedious calculations.
• May not give dependable results while evaluating mutually exclusive
projects as the project with Highest IRR will be selected.
• If a firm has to rank mutually exclusive projects, choosing the project
with the highest IRR may result in optimal outcome.
…Cont’d
6.Profitability Index (PI)
• A part of discounted cash flow family
• PI = PV of Cash Inflows/initial investment
• Accept a project if PI ≥ 1.0, which means positive NPV
• Usually, PI consistent with NPV
• PI may be in conflict with NPV if
– Projects are mutually exclusive
• Scale of projects differ
• Pattern of cash flows of projects is different
• When in conflict with NPV, use NPV
8/1/2021 47
Profitability Index (PI)
• Modified version of NPV
• Decision Criteria
– PI > 1.0, accept project
– PI < 1.0, reject project
8/1/2021 48
Profitability Index (PI)
• Close to NPV as we calculate present value of future
positive cash flows (present value of benefits) and
initial cash flow (NPV)
→PI = (NPV + Initial cost) / Initial Cost
• Choosing between two different projects?
→Higher PI is best choice
8/1/2021 49
II. Non-Discounting Criteria
A. Payback Period
– It is one of the most popular and widely used method
– It indicates the number of years the project will take to
repay its investment cost
– The payback period can be calculated using the following
formula:
PBP = Total Investment
Annual Cash Flow
• How long will it take (usually, in years) to pay back
the project, and accrued costs:
Measures of Project Worth
Alternative
projects
Year Investment cost Net
incremental
benefits
Cumulative net
incremental benefits
I 1
2
3
4
5
20000 -
2000
8000
12000
9000
31000
II 1
2
3
4
5
20000 -
2000
12000
8000
12000
34000
III 1
2
3
4
5
6
7
8
20000 -
1000
5000
6000
8000
10000
5000
2000
37000
Measures of Project Worth
• Project I & II have a payback period of 4 year.
• But project III has a payback period of 5 years.
• Thus, based on this criterion, project I & II have equal higher rank
than project III.
• Therefore, the method fails to consider the time & amount of
net incremental benefit after the payback period- project III.
• In addition, the method results equal rank for both project I and II.
• Yet we know by inspection that we would choose project II over
project I because more of the returns to project II are realized earlier.
– This method is a measure of cash recovery, not
profitability.
Project Analysis & Management
(ASA)
Example 1
If a project has an investment of Br. 60,000 and annual cash inflow is Br.
15,000 per year for 10 years. Compute the PBP?
PBP = 60,000/15000= 4 years
Example 2
If the project cash inflow is not in “annuity form”, cumulative cash
inflow method may be used to compute that PBP. Assuming an initial
investment of Br. 30,000 for the following stream of cash flows and
compute the PBP.
…Cont’d
Project Analysis & Management
(ASA)
Year Cash inflows Cumulative
1 10,000 10,000
2 8,000 18,000
3 12,000 30,000
4 7,000 37,000
5 9,000 46,000
6 3,000 49,000
…Cont’d
Project Analysis & Management
(ASA)
Cont.
Hence, PBR, is 3 years
Example 3
If the project cumulative cash flow does not exactly match to
the investment outlay, but in annuity form of inflow, then
compute the PBP in the following way (assuming initial
investment of $10,000)
Project Analysis & Management
(ASA)
Year Cash inflow Cumulative
1 4,000 4,000
2 4,000 8,000
3 4,000 12,000
4 4,000 16,000
5 4,000 20,000
PBP = 10,000 = 2.5 Years
4000
…Cont’d
Project Analysis & Management
(ASA)
…Cont’d
Example 4
In case the cumulative inflow does not exactly match
the amount of investment and the inflow is not in
annuity form use the interpolation method (assume
an investment outlay of 15,000); compute the PBP.
Project Analysis & Management
(ASA)
Year Cash in flow Cumulative
1 3,000 3,000
2 5,000 8,000
3 10,000 18,000
4 2,000 20,000
5 4,000 24,000
PBP = 2+ (12 months x 7000)=
10,000
…Cont’d
2 years and 8
months or 28/12
years
Measures of Project Worth
• Exercise 1: Find the PBP
Year
(1)
Initial Investment
(Rs)
(2)
Cash Inflows
(Rs)
(3)
Cumulative
Cash Inflows
(Rs)
(4)
0 10,000 - -
1 - 1,500 1,500
2 - 3,000 4,500
3 - 9,000 13,500
4 - 27,000 40,500
The PBP is-----------------------------
Project Analysis & Management
(ASA)
…Cont’d
Advantages of Payback Period
(1) Applying the technique and understanding the concept is easy to
understand
(2) It is quick and simple to use
Disadvantages of Payback Period
(1) It ignores the cash flows that occur after the payback period.
(2) It ignores the time value of money.
Accounting Rate of Return
• ARR differs from the payback period in using accounting profits
rather than cash flows
• It is calculated by taking the average annual profits expected
from a project as a percentage of the capital invested
 Accounting rate of return =Book Value of the
Investment/Profit After Tax
 The Higher the accounting rate of return, the better the project
ARR = Average annual profit x100/outlay,
Measures of Project Worth
• Accounting Rate of Return (ARR)
Cash Flows A B C
Outlay 120,000 120,000 120,000
After deducting depreciation
Year 1 30,000 20,000 10,000
Year 2 30,000 20,000 70,000
Year 3 30,000 20,000 80,000
Average Annual Profit 30,000 20,000 53,333
ARR of A = 30,000 x100/120,000 = 25%,
ARR of B = 20,000 x 100/120,000 = 16.7%,
ARR of C = 53,333 x 100/120,000 = 44.44%
Disadvantages Does not take into account time value of money Based on the
accounting profit and not cash flows
Average Return on Investment
• It is a measure of aggregate benefits that the investment will produce.
The desired ARI will reflect the bare minimum that will make investors
commit funds for the project
• Steps to compute ARI:
1. Find the total cash inflows over the project life
2. Subtract the initial investment from the total cash inflows. This is the
total net income over the project life
3. Find the average annual income by dividing total net income by the
project life in years
4. ARI is the ratio of the average annual income to the initial investment
ARI considers all the cash flows generated from a project during its life
Measures of Project Worth
• Exercise 2: Compute ARI from the following data
Year Initial Investment Cash
Inflows
0 2,300 -
1 - 331
2 - 430
3 - 553
4 - 544
5 - 536
Total
(1)
2,300
(2)
2,394
(3)
1. Initial Investment: (2300)
2. Total Net income: (2300)-(2394) = 94
3. Average Annual Income: 94/2300
=0.04
4. 0.04*`100= 4%
Individual Home Based exam (20%)
Quick Quiz Q1(10%)
• Assume that a minimum of 10 percent return is required and
select the best project alternative using:
A. Payback period
B. NPV
C. IRR
Expected financial Return (in Birr)
66
year Project A Project B Project C
0-Investment (1,000) (1,000) (1,000)
1 300 1,500 525
2 300 250 525
3 300 250 525
4 300 250 525
5 1,500 250 525
Total 1,700 1,500 1,625
Quiz 2(5%)
Year Project I Project II
0 (500) (500)
1 325 175
2 150 175
3 150 175
4 50 175
• Example: Assume that Mina PLC, a financial analyst, is doing a
consulting work for evaluating the two projects given below. The projects
costs Br. 500 million each and the required rate of return for each of the
projects is 12%, the projects’ expected net cash flows are as follows:
Required:
1. Calculate each of the project’s payback, net present value( NPV) and
Internal rate of return (IRR)
2. Which project or projects should be accepted if they are independent?
Q 3(5%)
• Find the NPV of the following projects and choose the best project
Projects Initial Investment (Outlay) Cash Flows
Year 1 Year 2
A 10,000 10,000
B 10,000 10,000 1,100
C 10,000 3762 7762
D 10,000 5762 5762
Cost of capital (discount rate) is 6%
 Use the same discount rate and find the NPV of a project with a life of five
years and an initial investment outlay of Birr 100,000 and a cash flow of
50,000 each year across the project life span
Interest rate 6%
Investment ( -100,000)
1 Year 2 year 3 year 4 year 5 year
Cash Flow 50,000 50,000 50,000 50,000 50,000
Financial statement
Balance sheet
Cash flow statement

Mais conteúdo relacionado

Mais procurados

Financial Planning and Forecasting
Financial Planning and ForecastingFinancial Planning and Forecasting
Financial Planning and ForecastingFinOnseT
 
Employee benefits ias 19
Employee benefits ias 19Employee benefits ias 19
Employee benefits ias 19Khalid Aziz
 
Ch7 acctg cycle service business
Ch7 acctg cycle  service businessCh7 acctg cycle  service business
Ch7 acctg cycle service businessSowie Althea
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgetingKhalid Aziz
 
Introduction to financial management and financial markets
Introduction to financial management and financial markets Introduction to financial management and financial markets
Introduction to financial management and financial markets sonarevankar
 
Intro strategic management accounting For MBA-Accounting
Intro strategic management accounting For  MBA-AccountingIntro strategic management accounting For  MBA-Accounting
Intro strategic management accounting For MBA-AccountingClementDamoahAbabio
 
2 annuity and its types
 2 annuity and its types 2 annuity and its types
2 annuity and its typesReena Kumari
 
Capital rationing - Meaning, Types and Problems of Project Selection under ca...
Capital rationing - Meaning, Types and Problems of Project Selection under ca...Capital rationing - Meaning, Types and Problems of Project Selection under ca...
Capital rationing - Meaning, Types and Problems of Project Selection under ca...Sundar B N
 
Cost of capital
Cost of capitalCost of capital
Cost of capitalNirmal PR
 
How to Calculate Profit Margin
How to Calculate Profit MarginHow to Calculate Profit Margin
How to Calculate Profit MarginBlaine Bertsch
 
521974482-AUDITING-and-ASSURANCE-Specialized-Industries-1.pptx
521974482-AUDITING-and-ASSURANCE-Specialized-Industries-1.pptx521974482-AUDITING-and-ASSURANCE-Specialized-Industries-1.pptx
521974482-AUDITING-and-ASSURANCE-Specialized-Industries-1.pptxOliviaCelestine
 
At (07) code of ethics
At   (07) code of ethicsAt   (07) code of ethics
At (07) code of ethicsRoward Patnaan
 

Mais procurados (20)

Financial Planning and Forecasting
Financial Planning and ForecastingFinancial Planning and Forecasting
Financial Planning and Forecasting
 
Employee benefits ias 19
Employee benefits ias 19Employee benefits ias 19
Employee benefits ias 19
 
Ch7 acctg cycle service business
Ch7 acctg cycle  service businessCh7 acctg cycle  service business
Ch7 acctg cycle service business
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Capital rationing
Capital rationingCapital rationing
Capital rationing
 
Introduction to financial management and financial markets
Introduction to financial management and financial markets Introduction to financial management and financial markets
Introduction to financial management and financial markets
 
Intro strategic management accounting For MBA-Accounting
Intro strategic management accounting For  MBA-AccountingIntro strategic management accounting For  MBA-Accounting
Intro strategic management accounting For MBA-Accounting
 
ABC costing
ABC costing ABC costing
ABC costing
 
2 annuity and its types
 2 annuity and its types 2 annuity and its types
2 annuity and its types
 
Adjusting entries 08022013
Adjusting entries 08022013Adjusting entries 08022013
Adjusting entries 08022013
 
Chapter 5- capital budgeting
Chapter   5- capital budgetingChapter   5- capital budgeting
Chapter 5- capital budgeting
 
Commerce:Receivables Management
Commerce:Receivables ManagementCommerce:Receivables Management
Commerce:Receivables Management
 
Capital rationing - Meaning, Types and Problems of Project Selection under ca...
Capital rationing - Meaning, Types and Problems of Project Selection under ca...Capital rationing - Meaning, Types and Problems of Project Selection under ca...
Capital rationing - Meaning, Types and Problems of Project Selection under ca...
 
Target Costing
Target CostingTarget Costing
Target Costing
 
Cost of capital
Cost of capitalCost of capital
Cost of capital
 
How to Calculate Profit Margin
How to Calculate Profit MarginHow to Calculate Profit Margin
How to Calculate Profit Margin
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Working Capital Cycle
Working Capital CycleWorking Capital Cycle
Working Capital Cycle
 
521974482-AUDITING-and-ASSURANCE-Specialized-Industries-1.pptx
521974482-AUDITING-and-ASSURANCE-Specialized-Industries-1.pptx521974482-AUDITING-and-ASSURANCE-Specialized-Industries-1.pptx
521974482-AUDITING-and-ASSURANCE-Specialized-Industries-1.pptx
 
At (07) code of ethics
At   (07) code of ethicsAt   (07) code of ethics
At (07) code of ethics
 

Semelhante a CHAPTER 4.pdf

Semelhante a CHAPTER 4.pdf (20)

UU-Project Chapter 3.pptx
UU-Project Chapter 3.pptxUU-Project Chapter 3.pptx
UU-Project Chapter 3.pptx
 
Unit 4 Capital Budgeting
Unit 4 Capital BudgetingUnit 4 Capital Budgeting
Unit 4 Capital Budgeting
 
Capital Budgeting PPT.pptx
Capital Budgeting PPT.pptxCapital Budgeting PPT.pptx
Capital Budgeting PPT.pptx
 
Capital Budgeting
Capital BudgetingCapital Budgeting
Capital Budgeting
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
02_lecture 8.ppt
02_lecture 8.ppt02_lecture 8.ppt
02_lecture 8.ppt
 
Developing a business plan
Developing a business planDeveloping a business plan
Developing a business plan
 
UNIT-1-FDM.pptx
UNIT-1-FDM.pptxUNIT-1-FDM.pptx
UNIT-1-FDM.pptx
 
capital budgeting ppt.pptx
capital budgeting ppt.pptxcapital budgeting ppt.pptx
capital budgeting ppt.pptx
 
Capital Budgeting
Capital Budgeting Capital Budgeting
Capital Budgeting
 
Process of Capital Budegeting
Process of Capital BudegetingProcess of Capital Budegeting
Process of Capital Budegeting
 
UNIT....................................
UNIT....................................UNIT....................................
UNIT....................................
 
Entrepreneurship Development: Unit No. 2
Entrepreneurship Development: Unit No. 2Entrepreneurship Development: Unit No. 2
Entrepreneurship Development: Unit No. 2
 
Capital Budgeting Decisions
Capital Budgeting DecisionsCapital Budgeting Decisions
Capital Budgeting Decisions
 
Module 2.pdf
Module 2.pdfModule 2.pdf
Module 2.pdf
 
Feasibility Study Chapter 1
Feasibility Study Chapter 1Feasibility Study Chapter 1
Feasibility Study Chapter 1
 
Feasibility study Chapter 1
Feasibility study Chapter 1Feasibility study Chapter 1
Feasibility study Chapter 1
 
A Business Analyst Approach -Developing A Business Case That Delivers Value T...
A Business Analyst Approach -Developing A Business Case That Delivers Value T...A Business Analyst Approach -Developing A Business Case That Delivers Value T...
A Business Analyst Approach -Developing A Business Case That Delivers Value T...
 
A business analyst approach
A business analyst approachA business analyst approach
A business analyst approach
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 

Mais de kena6

Addis_Ababa_Resilient_cities_program.pdf
Addis_Ababa_Resilient_cities_program.pdfAddis_Ababa_Resilient_cities_program.pdf
Addis_Ababa_Resilient_cities_program.pdfkena6
 
Ahmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdfAhmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdfkena6
 
Ahmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdfAhmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdfkena6
 
Addis_Ababa_Resilient_cities_program.pdf
Addis_Ababa_Resilient_cities_program.pdfAddis_Ababa_Resilient_cities_program.pdf
Addis_Ababa_Resilient_cities_program.pdfkena6
 
achwashp1.pdf
achwashp1.pdfachwashp1.pdf
achwashp1.pdfkena6
 
Abiy Girma Abebe Final Dissertation Amended.pdf
Abiy Girma Abebe Final Dissertation Amended.pdfAbiy Girma Abebe Final Dissertation Amended.pdf
Abiy Girma Abebe Final Dissertation Amended.pdfkena6
 
A-guide-for-Municipalities-Inclusive-and-Sustainable-Urban-Development-Planni...
A-guide-for-Municipalities-Inclusive-and-Sustainable-Urban-Development-Planni...A-guide-for-Municipalities-Inclusive-and-Sustainable-Urban-Development-Planni...
A-guide-for-Municipalities-Inclusive-and-Sustainable-Urban-Development-Planni...kena6
 
Ahmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdfAhmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdfkena6
 
Acceptedpaper_Delay.pdf
Acceptedpaper_Delay.pdfAcceptedpaper_Delay.pdf
Acceptedpaper_Delay.pdfkena6
 

Mais de kena6 (9)

Addis_Ababa_Resilient_cities_program.pdf
Addis_Ababa_Resilient_cities_program.pdfAddis_Ababa_Resilient_cities_program.pdf
Addis_Ababa_Resilient_cities_program.pdf
 
Ahmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdfAhmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdf
 
Ahmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdfAhmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdf
 
Addis_Ababa_Resilient_cities_program.pdf
Addis_Ababa_Resilient_cities_program.pdfAddis_Ababa_Resilient_cities_program.pdf
Addis_Ababa_Resilient_cities_program.pdf
 
achwashp1.pdf
achwashp1.pdfachwashp1.pdf
achwashp1.pdf
 
Abiy Girma Abebe Final Dissertation Amended.pdf
Abiy Girma Abebe Final Dissertation Amended.pdfAbiy Girma Abebe Final Dissertation Amended.pdf
Abiy Girma Abebe Final Dissertation Amended.pdf
 
A-guide-for-Municipalities-Inclusive-and-Sustainable-Urban-Development-Planni...
A-guide-for-Municipalities-Inclusive-and-Sustainable-Urban-Development-Planni...A-guide-for-Municipalities-Inclusive-and-Sustainable-Urban-Development-Planni...
A-guide-for-Municipalities-Inclusive-and-Sustainable-Urban-Development-Planni...
 
Ahmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdfAhmed Motuma Assen proposal.pdf
Ahmed Motuma Assen proposal.pdf
 
Acceptedpaper_Delay.pdf
Acceptedpaper_Delay.pdfAcceptedpaper_Delay.pdf
Acceptedpaper_Delay.pdf
 

Último

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 

Último (20)

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 

CHAPTER 4.pdf

  • 1. RVU chala D (PhD) By Chala Dechassa (PhD, Assistant Professor) Chapter Four Financial Analysis
  • 2. Purpose of Financial Feasibility Analysis • For investors to engage in a new investment project, the project has to be financially viable. • Invested capital must show the potential to generate an economic return to investors at least equal to that available from other similarly risky investments, i.e. the return on investment needs to be equal or higher. • For example, an investor expects a manufacturing facility to generate sufficient cash flows from operation to pay for the construction of the facility and ongoing operating expenses and, have an attractive interest rate of return.
  • 3. Cont’d • Estimates the cost of operating and maintaining a manufacturing plant, as well as expected income generated. • Financial feasibility analysis is an analytical tool used to evaluate the viability of an investment. • A financial decision is dependent on two specific factors, expected return and expected risk, and a financial feasibility analysis is a means for examining those two factors.
  • 4. - Main reason to conduct financial feasibility study) to (Reference Chapter 3 Reason Why Feasibility Study
  • 5. Cont’d • It should be conducted before proceeding with the development of a business idea, and that also applies for financial feasibility analysis. • Determining early that a business idea is not financially feasible can prevent loss of money and waste of valuable time. • Financial feasibility analysis is usually done during the project planning process and the results indicate how the project will perform under a specific set of assumptions regarding technology, market conditions and financial aspects.
  • 6. Cont’d • Analyzing the financial feasibility of a project is an essential part of the decision making process. • Even though the analysis is used on the first stages of the decision- making process as a screening method, the analysis should also be used throughout the process and should be updated every time any of the assumptions it is based on changes. • if the results of the analysis show that the proposed project does not meet the return on investment requirements of the investor, the business idea is discarded. • It is therefore very important to regularly update the analysis and verify that, given the newest information, the project is financially feasible.
  • 7. Feasibility Study vs. Business Plan • Feasibility studies and business plans are two separate tools used for decision making in project development. – Both tools have common components, but should nevertheless not be confused as their roles are different.  A feasibility study is a tool for investigating the viability of the prospective project. • A business plan is a tool for planning the actions needed to take the project proposal from an idea to reality. • The feasibility study refines the initial business idea, while the business plan uses information from the feasibility study to further prepare the project to evolve into an operating business.
  • 8. Cont’d • A feasibility study is conducted on the very first stages of project development, before financing is secured and a GO/NON-GO decision has been made. • The purpose of the study is to reveal whether or not the project is viable from all aspects, feasibility study components • If the results of the study are positive, indicating that the project will be successful, much of the information from the study is incorporated into a business plan. • However, if the results are negative, there is no need to create a business plan (Matson, 2000). • A feasibility study usually analyzes several project alternatives or methods of achieving success.
  • 9. Cont’d • The purpose is to narrow the scope of the project and to identify the best scenario. – A business plan only deals with one scenario, i.e. the scenario found to be most prominent by the feasibility study. • A business plan captures the goals and objectives of a business idea. • The plan serves as a blueprint for the implementation of the project, as well as the actions taken during and after project implementation.
  • 10. Cont’d • A feasibility study is used throughout the whole process, first as a screening tool and then as a part of a business plan. – As the financial feasibility of a project is a key element in a feasibility study, it is also a key element in a business plan. • The business plan is often used as a sales document, helping the project owners to secure financing for the project. – It is also used to persuade specialists to participate in the project and public authorities to give permissions for operations.
  • 11. Conducting Financial Feasibility Analysis • Financial feasibility analysis is conducted by developing a base case financial plan and assessing the sensitivity of the profitability of the project, and the projected return, on the investor’s equity to various contingencies. • Needed for analyzing fluctuation in product price, changes in operating and maintenance cost, the effects of cost overruns, delay in completion, interruptions of project operations and other significant factors.
  • 12. Cont’d The following outline when conducting financial feasibility analysis:  Estimate the total capital requirements – seed capital, capital for facilities and equipment, working capital, start-up capital, contingency capital, etc;  Estimate equity and credit needs - identify equity sources and capital availability, identify credit sources, assess expected financing requirements, and establish debt to equity levels;  Budget expected costs and returns of various alternatives – estimate expected cost and revenue, the profit margin and expected net profit, the sales or usage needed to break-even, the returns under various production, price and sales levels,
  • 13. Project financing • There are two types of project financing: – equity and – debt financing. – When looking for money, you must consider your company’s debt-to- equity ratio. – The relation between amounts borrowed and amounts invested to the business by the owners. The more money owners have invested in their business, the easier it is to attract financing.
  • 14. Equity Financing:  Most small or growth-stage businesses use limited equity financing.  As with debt financing, additional equity often comes from non- professional investors such as friends, relatives, employees, customers, or industry colleagues. – However, the most common source of professional equity funding comes from venture capitalists. – These are institutional risk takers and may be groups of wealthy individuals,
  • 15. Cont’d • Government-assisted sources, or major financial institutions. • Most specialize in one or a few closely related industries. • Venture capitalists may scrutinize thousands of potential investments annually, but only invest in a handful. • The possibility of a public stock offering is critical to venture capitalists. • Quality management, a competitive or innovative advantage, and industry growth are also major concerns
  • 16. Debt Financing: • There are many sources for debt financing: • banks, • savings and loans • , commercial finance companies, and • the microfinance institutions.
  • 17. Cont’d • State and local governments have developed many programs in recent years to encourage the growth of small businesses in recognition of their positive effects on the economy. • Family members, friends, and former associates are all potential sources, especially when capital requirements are smaller.
  • 18. Cont’d • Traditionally, banks have been the major source of small business funding. • Their principal role has been as a short-term lender offering demand loans, seasonal lines of credit, and single-purpose loans for machinery and equipment. • In addition to equity considerations, lenders commonly require the borrower’s personal guarantees in case of default. This ensures that the borrower has a sufficient personal interest at stake to give paramount attention to the business. For most borrowers this is a burden, but also a necessity.
  • 19. Project Decision Making Criteria The investment criteria could be classified into two: 1. Non-discounting Criteria 2. Discounting criteria What is the difference between these techniques? 8/1/2021 19
  • 20. 20 1. Non-discounted techniques: • These techniques are simple to understand and easy to compute. • They don’t recognize the time value of money • Though these techniques are simple to understand and easy to compute, they suffer from the following limitations.  They don’t recognize the time value of money  They fail to recognize the projects return in totality-they ignore cash flows beyond the payback period 8/1/2021
  • 21. 8/1/2021 2. Discounted appraisal techniques considers both the estimated total cash inflows and the time value of money. That is:  Recognize the time value of money  Recognize the benefits of the project in totality (except discounted pay back period) 21
  • 22. 1) Non-discounting Criteria a) Payback period b) Accounting rate of return 2) Discounting criteria include: a) Net present value b) Profitability Index/Benefit cost ratio c) Internal rate of return d) Discounted pay back period 8/1/2021 22
  • 23. Methods of Evaluating Projects: • In order to evaluate the financial feasibility of an investment project, relevant measurements or criteria need to be specified. Remer and Nieto (1995) categorize the evaluation methods into five basic types: Discounting Non discounting 1. Net Present Value 4. Payback period 2. Benefit-Cost Ratio 5. accounting rate of return 3. Internal rate of return 6. ROI.
  • 24. Net Present Value: • Net Present Value (NPV) is the difference between the present value of all cash inflows and cash outflows associated with an investment project. • Net present value of a project is the sum of the present values of all the cash flows associated with it. The cash flows can be positive or negative.
  • 25. NPV • In order to calculate the NPV, (considerate ) – the interest rate used for discounting the cash flows needs to be determined. The interest rate is often referred to as Minimum – Attractive Rate of Return (ARR) and it represents the rate at which the investor can alternatively invest his money, i.e. the return of the most preferable alternative investment. – The planning horizon of the project also needs to be determined, and the cash flows for each period of the planning horizon projected .
  • 26. Net Present Value(Measures of Project Worth) • The Net Present Value (NPV) of a project is the sum of the project values of all the cash flows-positive as well as negative-that are expected to occur over the life of the project. • The general formula for NPV is: • where • Ct = net cash flow at the end of year t( • n= life of the project • r = discount rate • I investment cost I r c NPV n t t t     1 ) 1 (
  • 27. CONT’D • If the NPV(i) is positive for a single project, the project should be accepted, since a positive • NPV means that the project has greater equivalent value of inflows than outflows and therefore makes a profit (Park, 2002). • According to Park (2002) the decision rule for NPV is: • If NPV(i) > 0, accept the investment; • If NPV(i) =0, remain indifferent to the investment; • NPV(i) < 0, reject the investment.
  • 28. CONT’D • When comparing mutually exclusive alternatives the one with the greatest positive NPV is selected. – However, when comparing alternatives it is important to use the same interest rate for all alternatives. – All projects must also be compared over equal time periods. • In the case of mutually exclusive alternatives generating the same revenues, compare the projects on a cost-only basis. – Then the project resulting in the smallest, or least negative, NPV should be accepted, since the objective is to minimize cost.
  • 29. Measures of Project Worth ( example 1) Year Cash flow 0 Birr (1,000,000) 1 200,000 2 200,000 3 300,000 4 300,000 5 350,000 If the cost of capital (discount rate) is 10%, then NPV is calculated as follows 273 , 5 000 , 000 , 1 ) 10 . 1 ( 000 , 350 ) 10 . 1 ( 000 , 300 ) 10 . 1 ( 000 , 300 ) 10 . 1 ( 000 , 200 ) 10 . 1 ( 000 , 200 5 4 3 2 1         NPV NPV/I = Profitability Index
  • 30. Measures of Project Worth • The NPV represents the net benefit over and above the compensation for time and risk. • Hence, the decision rule associated with the net present value criterion is: –accept the project if the NPV is positive and –reject it if NPV is negative.
  • 31. Measures of Project Worth( example 2) Interest rate 14% 15% 16% 18% 20% Investment -12000 Cash flow 4,000 5,000 7,000 6,000 5,000 3509 14 . 1 / 000 , 4 1   C PV 3814 ) 15 . 1 14 . 1 /( 000 , 5 2    C PV 4603 ) 16 . 1 15 . 1 14 . 1 /( 000 , 7 3     C PV 3344 ) 18 . 1 16 . 1 15 . 1 14 . 1 /( 000 , 6 4      C PV 2322 ) 20 . 1 18 . 1 16 . 1 15 . 1 14 . 1 /( 000 , 5 5       C PV NPV of Project =3509+3814+4603+3344+2322-12000 = 5592
  • 32. Project Analysis & Management (ASA) Example 3 After tax cash flows of a small scale tannery project is given below. Find the profitability index if discount rate is assumed to be 12%? Year 0 1 2 3 4 5 CFs 40,000 15,000 14,000 13,000 12,000 11,000 …Cont’d
  • 33. Project Analysis & Management (ASA) …Cont’d Solutions Year Cash Flow Rate = (12%) PV 1 15,000 0.893 13,395 2 14,000 0.797 11,158 3 13,000 0.712 9,256 4 12,000 0.636 7,636 5 11,000 0.567 6,237 Total Therefore, PI=47,678 = 1.192 40,000 47,678
  • 34. CONT’D Advantages: • It takes into account the time value of money with changing discount rate. • It can be used to evaluate mutually exclusive projects. • It takes into consideration the total benefits arising out of the project over its lifetime. Disadvantages • It does not take into account the life of the project and may not give dependable result for projects having different lives. • The NPV method is an absolute method and may not give dependable results in case the projects have different outlays.
  • 35. Benefit-Cost Ratio • The benefit-cost method is often used for public projects. • The method compares project benefits to the cost of the project, and for the project to be viable, the benefits have to be greater than the cost. • Park (2002) describes benefit-cost analysis as “a decision- making tool used to systematically develop useful information about the desirable and undesirable effects of public projects”. • Benefit-Cost Ratio BCR= Present value of inflows/Initial Investments PI= Present value of cash inflows/Present value of cash outflows – If BCR is greater than 1, accept the project If BCR is less than 1, reject the project.
  • 36. CONT’D • three types of benefit-cost analysis problems: 1. Maximizing the benefits for any given set of cost; 2. Maximizing the net benefits when both benefits and costs vary; 3. Minimizing cost to achieve any given level of benefits. • The worthiness of a public project can be expressed by comparing the benefits (B) of the project to the cost (C) of the project by taking the ratio B/C, i.e. the Benefit- Cost ratio.
  • 37. Benefit-Cost Ratio: • Benefit-Cost Ratio: There are two ways of defining the relationship between benefits and costs: • Example: 12% discount NBCR = BCR-1= 0.145 I PVB BCR  1     BCR I I PVB NBCR (1) (2) PVB = present value of benefits, I = initial investment 100,000 Benefits Year 1 25000 Year 2 40000 Year 3 40000 Year 4 50000 145 . 1 000 , 100 ) 12 . 1 ( 000 , 50 ) 12 . 1 ( 000 , 40 ) 12 . 1 ( 000 , 40 ) 12 . 1 ( 000 , 25 4 3 2      BCR When BCR > 1 or NBCR > 0 accept When BCR < 1 or NBCR < 0 reject the project
  • 38. Cont’d • Advantages • Evaluate the project in the relative terms – Two projects having different cash outlays and lifetime can be evaluated • Takes into consideration time value of money and totality of benefits • Dis advantages – When comparing mutually exclusive alternatives, the Benefit-Cost Ratio cannot be used unless using incremental analysis. – This is due to the fact that the ratio does not differentiate between investments of different sizes, e.g. a $10 investment and a $1000 investment. – Then the incremental differences for each term are calculated and the B/C ratio taken from these differences (Park, 2002).
  • 39. Internal Rate of Return: – Internal Rate of Return (IRR) is a concept based on the return on invested capital in terms of a project investment. – The internal rate of return( IRR) is defined as the rate of discount, which brings about equality between the present value of future net benefits & initial investment. – The investment has zero NPV at this rate of return, noted as r*. Therefore, r*serves as a benchmark interest rate, making investors able to accept or reject decision consistent with the NPV analysis.
  • 40. CONT’D • Internal rate of return (IRR) is the discount rate which makes its net present value equal to zero. • It is the value of r in the following equation. • Where, – I – investment cost – Ct – Net benefit for year t – r - IRR – n - Life of the project • Illustration: For project A in the table below can be formulated as follows:       n t t t r C I 1 1
  • 41. Measures of Project Worth • The calculation of r involves a process of trial and error. We try different values r till we find that the right-hand side of the above equation is equal to 100,000. Let us try to use 15%. This makes the right-hand side to be:        4 3 2 1 1 000 , 45 1 000 , 40 1 000 , 30 1 000 , 30 000 , 100 r r r r         Year 0 1 2 3 4 Cash flow (100,000) 30,000 30,000 40,000 45,000 IRR is the value of r which satisfies the following equation:         802 , 100 15 . 1 000 , 45 15 . 1 000 , 40 15 . 1 000 , 30 15 . 1 000 , 30 000 , 100 4 3 2      Since the value is slightly higher than our target value, which is 100,000, we increase the value to 16%.         641 , 98 16 . 1 000 , 45 16 . 1 000 , 40 16 . 1 000 , 30 16 . 1 000 , 30 000 , 100 4 3 2     
  • 42. Measures of Project Worth • Since this value is now less than 100,000, we conclude that the value of r lies between 15 and 16%. For most of the purposes, this indication suffices. • If a more refined estimate of r is needed, we use the following procedure: 1. Determine the NPV of the two closest rates of return (NPV/15%) = 802 (NPV/16%) = 1,359 2. Find the sum of the absolute values of the NPVs obtained in Step 1 802+1,359 = 2,161 3. Calculate the ratio of the NPV of the smaller discount rate, identified in Step 1, to the sum obtained in Step 2 802/2,161 = 0.37 4. Add the number obtained in Step 3 to the smallest discount rate 15+0.37 = 15.37
  • 43. Project Analysis & Management (ASA) Class Work A project has a total outlay of Br. 500,000 with the following pattern of cash inflow. Compute the IRR of the project Year 1 2 3 4 5 CFs 120 120 120 150 150 (in thousands) …Cont’d
  • 44. Project Analysis & Management (ASA) Year 1 2 3 4 5 CFs 5000 4000 3000 2000 8000 …Cont’d Exercise A project requires a new investment of 20,000 and produces the following cash flows. Compute the IRR of the project
  • 45. Cont’d NPV Vs IRR  For making choice between two projects competing for the funds at the disposal of a concern, the NPV method can give a better choice because it can give idea of ranking of the projects.
  • 46. Project Analysis & Management (ASA) Advantages • Takes into consideration time value of money and totality of benefit Provides the rate of return which indicates the profitability of the proposal • The difference between the IRR and the cost of capital indicates the additional return for risk that the project provides. Disadvantages of IRR • Tedious calculations. • May not give dependable results while evaluating mutually exclusive projects as the project with Highest IRR will be selected. • If a firm has to rank mutually exclusive projects, choosing the project with the highest IRR may result in optimal outcome. …Cont’d
  • 47. 6.Profitability Index (PI) • A part of discounted cash flow family • PI = PV of Cash Inflows/initial investment • Accept a project if PI ≥ 1.0, which means positive NPV • Usually, PI consistent with NPV • PI may be in conflict with NPV if – Projects are mutually exclusive • Scale of projects differ • Pattern of cash flows of projects is different • When in conflict with NPV, use NPV 8/1/2021 47
  • 48. Profitability Index (PI) • Modified version of NPV • Decision Criteria – PI > 1.0, accept project – PI < 1.0, reject project 8/1/2021 48
  • 49. Profitability Index (PI) • Close to NPV as we calculate present value of future positive cash flows (present value of benefits) and initial cash flow (NPV) →PI = (NPV + Initial cost) / Initial Cost • Choosing between two different projects? →Higher PI is best choice 8/1/2021 49
  • 50. II. Non-Discounting Criteria A. Payback Period – It is one of the most popular and widely used method – It indicates the number of years the project will take to repay its investment cost – The payback period can be calculated using the following formula: PBP = Total Investment Annual Cash Flow • How long will it take (usually, in years) to pay back the project, and accrued costs:
  • 51. Measures of Project Worth Alternative projects Year Investment cost Net incremental benefits Cumulative net incremental benefits I 1 2 3 4 5 20000 - 2000 8000 12000 9000 31000 II 1 2 3 4 5 20000 - 2000 12000 8000 12000 34000 III 1 2 3 4 5 6 7 8 20000 - 1000 5000 6000 8000 10000 5000 2000 37000
  • 52. Measures of Project Worth • Project I & II have a payback period of 4 year. • But project III has a payback period of 5 years. • Thus, based on this criterion, project I & II have equal higher rank than project III. • Therefore, the method fails to consider the time & amount of net incremental benefit after the payback period- project III. • In addition, the method results equal rank for both project I and II. • Yet we know by inspection that we would choose project II over project I because more of the returns to project II are realized earlier. – This method is a measure of cash recovery, not profitability.
  • 53. Project Analysis & Management (ASA) Example 1 If a project has an investment of Br. 60,000 and annual cash inflow is Br. 15,000 per year for 10 years. Compute the PBP? PBP = 60,000/15000= 4 years Example 2 If the project cash inflow is not in “annuity form”, cumulative cash inflow method may be used to compute that PBP. Assuming an initial investment of Br. 30,000 for the following stream of cash flows and compute the PBP. …Cont’d
  • 54. Project Analysis & Management (ASA) Year Cash inflows Cumulative 1 10,000 10,000 2 8,000 18,000 3 12,000 30,000 4 7,000 37,000 5 9,000 46,000 6 3,000 49,000 …Cont’d
  • 55. Project Analysis & Management (ASA) Cont. Hence, PBR, is 3 years Example 3 If the project cumulative cash flow does not exactly match to the investment outlay, but in annuity form of inflow, then compute the PBP in the following way (assuming initial investment of $10,000)
  • 56. Project Analysis & Management (ASA) Year Cash inflow Cumulative 1 4,000 4,000 2 4,000 8,000 3 4,000 12,000 4 4,000 16,000 5 4,000 20,000 PBP = 10,000 = 2.5 Years 4000 …Cont’d
  • 57. Project Analysis & Management (ASA) …Cont’d Example 4 In case the cumulative inflow does not exactly match the amount of investment and the inflow is not in annuity form use the interpolation method (assume an investment outlay of 15,000); compute the PBP.
  • 58. Project Analysis & Management (ASA) Year Cash in flow Cumulative 1 3,000 3,000 2 5,000 8,000 3 10,000 18,000 4 2,000 20,000 5 4,000 24,000 PBP = 2+ (12 months x 7000)= 10,000 …Cont’d 2 years and 8 months or 28/12 years
  • 59. Measures of Project Worth • Exercise 1: Find the PBP Year (1) Initial Investment (Rs) (2) Cash Inflows (Rs) (3) Cumulative Cash Inflows (Rs) (4) 0 10,000 - - 1 - 1,500 1,500 2 - 3,000 4,500 3 - 9,000 13,500 4 - 27,000 40,500 The PBP is-----------------------------
  • 60. Project Analysis & Management (ASA) …Cont’d Advantages of Payback Period (1) Applying the technique and understanding the concept is easy to understand (2) It is quick and simple to use Disadvantages of Payback Period (1) It ignores the cash flows that occur after the payback period. (2) It ignores the time value of money.
  • 61. Accounting Rate of Return • ARR differs from the payback period in using accounting profits rather than cash flows • It is calculated by taking the average annual profits expected from a project as a percentage of the capital invested  Accounting rate of return =Book Value of the Investment/Profit After Tax  The Higher the accounting rate of return, the better the project ARR = Average annual profit x100/outlay,
  • 62. Measures of Project Worth • Accounting Rate of Return (ARR) Cash Flows A B C Outlay 120,000 120,000 120,000 After deducting depreciation Year 1 30,000 20,000 10,000 Year 2 30,000 20,000 70,000 Year 3 30,000 20,000 80,000 Average Annual Profit 30,000 20,000 53,333 ARR of A = 30,000 x100/120,000 = 25%, ARR of B = 20,000 x 100/120,000 = 16.7%, ARR of C = 53,333 x 100/120,000 = 44.44% Disadvantages Does not take into account time value of money Based on the accounting profit and not cash flows
  • 63. Average Return on Investment • It is a measure of aggregate benefits that the investment will produce. The desired ARI will reflect the bare minimum that will make investors commit funds for the project • Steps to compute ARI: 1. Find the total cash inflows over the project life 2. Subtract the initial investment from the total cash inflows. This is the total net income over the project life 3. Find the average annual income by dividing total net income by the project life in years 4. ARI is the ratio of the average annual income to the initial investment ARI considers all the cash flows generated from a project during its life
  • 64. Measures of Project Worth • Exercise 2: Compute ARI from the following data Year Initial Investment Cash Inflows 0 2,300 - 1 - 331 2 - 430 3 - 553 4 - 544 5 - 536 Total (1) 2,300 (2) 2,394 (3) 1. Initial Investment: (2300) 2. Total Net income: (2300)-(2394) = 94 3. Average Annual Income: 94/2300 =0.04 4. 0.04*`100= 4%
  • 65. Individual Home Based exam (20%)
  • 66. Quick Quiz Q1(10%) • Assume that a minimum of 10 percent return is required and select the best project alternative using: A. Payback period B. NPV C. IRR Expected financial Return (in Birr) 66 year Project A Project B Project C 0-Investment (1,000) (1,000) (1,000) 1 300 1,500 525 2 300 250 525 3 300 250 525 4 300 250 525 5 1,500 250 525 Total 1,700 1,500 1,625
  • 67. Quiz 2(5%) Year Project I Project II 0 (500) (500) 1 325 175 2 150 175 3 150 175 4 50 175 • Example: Assume that Mina PLC, a financial analyst, is doing a consulting work for evaluating the two projects given below. The projects costs Br. 500 million each and the required rate of return for each of the projects is 12%, the projects’ expected net cash flows are as follows: Required: 1. Calculate each of the project’s payback, net present value( NPV) and Internal rate of return (IRR) 2. Which project or projects should be accepted if they are independent?
  • 68. Q 3(5%) • Find the NPV of the following projects and choose the best project Projects Initial Investment (Outlay) Cash Flows Year 1 Year 2 A 10,000 10,000 B 10,000 10,000 1,100 C 10,000 3762 7762 D 10,000 5762 5762 Cost of capital (discount rate) is 6%  Use the same discount rate and find the NPV of a project with a life of five years and an initial investment outlay of Birr 100,000 and a cash flow of 50,000 each year across the project life span Interest rate 6% Investment ( -100,000) 1 Year 2 year 3 year 4 year 5 year Cash Flow 50,000 50,000 50,000 50,000 50,000