SlideShare uma empresa Scribd logo
1 de 92
Baixar para ler offline
UNIT-IV CANAL IRRIGATION
SYLLABUS:
Canal regulations – direct sluice - Canal
drop – Cross drainage works-Canal outlets
– Design of prismatic canal-canal
alignments-Canal lining - Kennedy’s and
Lacey’s Regime theory-Design of unlined
canal
INTRODUCTION:
It is a direct irrigation system, which makes use of a weir
or a barrage, as well as a storage irrigation scheme which
makes use of a storage dam or a storage reservoir,
necessitates the construction.
DISTRIBUTION SYSTEMS FOR CANAL
IRRIGATION:
Main canal
Branch canal
Distributaries (major Distributaries)
Minor Distributaries
Watercourse
Main canal:
 Canal head works are generally situated on the river
flowing valley and canal should reach the ridge line in
shortest possible distance.
 Therefore the canal aligned very carefully and has to
excavate deep cutting below N.S.L
Branch canal:
 These are taken off the water from the main canal on
either side.
 It supply the water to the distributaries.
Distributaries:
 These are smaller canals get water from the branch canal
and distribute their supply through outlets into minors or
water courses.
Minors Distributaries:
 The distance between the distributary outlet and land is
very long, discharge in a minor.(less than 2.5 cumec)
Water courses:
 These are excavated and maintained by the land
cultivators.
Classification of Canal
Nature of
source of
supply
Financial
output
Function of
canal
Boundary
surface of
canal
Permanent
canal
Inundation
canal
Protective
canal
Productive
canal
Power canal
Navigation
canal
Feeder canal
Carrier canal
Irrigation canal
Rigid-boundary
canal
Non-alluvial
canal
Alluvial canal
Permanent
source of
supply
High stage
of supply
Net
revenue
to
nation
Protect
some
area
CANAL REGULATORS
Head regulator:
 It is provided at the head of the off-taking canal, controls
the flow of water entering the new channel.
Cross regulator:
 It is required in the main channel downstream in off-
taking channel, operated when necessary.
MAIN FUNCTIONS OFA HEAD REGULATOR:
 Regulate or control supply the off-taking canal.
 Control the entry of silt into off-taking canal.
 Serve the measuring discharge.
MAIN FUNCTIONS OFA CROSS REGULATOR:
 To control entire canal irrigation system.
 Help to fed the water from upstream to off-taking canal.
 Help to reduce fluctuations and possibilities to reach the
tail end of canal.
 It is combined with bridges and falls, if required.
RIVER TRAINING WORKS:
These are required near the weir site in order to ensure a
smooth and axial flow of water & to prevent the river
from outflanking works due to a change in its course.
It required on a canal headworks are,
(a) guide banks
(b) marginal bunds
(c) spurs or groynes
(a) Guide Banks:
 When a barrage is constructed across a river which flows
through the alluvial soil, guide banks must be constructed
on both sides of canal to protect from soil erosion.
Purposes:
o Protects from effects of scouring and erosion.
o Provides straight approach towards the barrage.
o Controls the tendency of changing the course of river.
o Controls velocity of flow near the structure.
(b)Marginal bunds:
 These are earthen embankments which are constructed
parallel to the river bank one or both banks according to
the condition.
 Top width is 3 to 4m and slope on river side 1.5:1 and
other side 2:1
Purposes:
o Prevent the flood or storage water from entering the
surrounding area may be lead to water logged.
o Retains flood water or storage water within a specified
section.
o Prevents towns and villages from floods.
o Protects valuable agricultural lands.
(c)Spurs or groynes:
(i) Spurs:
 These are temporary structures permeable in nature
provided on the curve of a river to protect the river bank
from erosion.
 These are projected from the river bank and make an
angle of 60 to 750 with river bank.
 The length of the spur is based on the width & sharpness
of the river.
 The function of spur is to break the velocity of flow and
form a water pocket in upstream for sediments get
deposited.
 It has the following types;
(a) bamboo spur
(b) timber spur
(c) boulder spur
(a) Bamboo spur:
• These are like compartment is prepared by bamboo piles
at 15cm c/c.
• Piles are secured by bamboo bracings and hollow space is
filled by sand bags.
• It is permeable in nature and water can seep through its
body.
• This is suitable for small rivers and purely temporary
structures .
• It requires repair work every year & length of bamboo
piles depends upon the bed condition.
(b) Timber spur:
• This is box like compartment is prepared by driving
timber piles at 15cm to 30cm c/c.
• Piles are secured by wooden bracings.
• The hollow space filled by boulders and it is permeable
also stable.
• It is recommended for the rivers with high velocity of
flow.
• The length of timber piles depend on bed condition.
(c) Boulder spur:
• Here boulders are enclosed in G.I wire net in circular
shape.
• The boulders should be heavy, varying from 30kg to 50kg
and wire net made of 4mm diameter G.I wires.
• It laid in river bank towards bed making angle of 600 –
750
• These type is recommended in velocity of flow is very
high.
(ii) Groynes:
 The function of groynes are similar to spur & these are
impervious permanent structures constructed on the
curve of a river to protect river bank from erosion.
 Extend an angle of 600 to 750 with bank and towards
upstream or downstream, sometimes it is perpendicular.
 These are constructed with rubble masonry in trapezoidal
section and surface finished with stone pitching or
concrete blocks.
Stone pitching or concrete blocks are set with rich cement
mortar.
Length of groyne based on width & nature of river.
Top width varies from 3 to 4m, side slope may be 1.5:1 or
2:1
These are provided in series throughout the affected
length of river bank.
Spacing of groynes = 2L (L-length of groyne)
It is recommended for river where the permanent solution
of erosion control necessary.
These are may be designed as follows;
(a) Attracting groyne:
 It is constructed obliquely to bank @ angle 60 – 750
towards downstream.
 Flow of water attracted by bank and bank protected of
stone pitching for safety.
(b) Repelling groyne:
 It is constructed obliquely to bank @ angle 60 – 750
towards upstream.
 So that water pocket formed and silts get deposited.
 Bank protection not necessary because the flow of water
does not touch the bank.
 For safety purpose boulder pitching is provided.
(c) Deflecting groyne:
 It is constructed perpendicular to bank.
 The flow of water deflected from bank by perpendicular
obstruction and eddy current formed upstream of groyne.
 For safety purpose boulder pitching is provided.
Modification of groyne:
(a) Denehy’s groyne or T-headed groyne:
After long investigation, deheny developed a groyne in
shape of T.
Length of head kept as L/2, (L-length of groyne).
All others are same as other groynes.
(b) Hockey head groyne:
The head of the groyne is curved towards the downstream
in shape of a hockey stick & it behaves like a attracting
groyne.
But it allows the water to flow smoothly over the head of
the groyne.
SILT REGULATION WORKS
Special works to reduced the entry of silt into the canal.
(a) Silt excluders
(b) Silt ejectors
(a) Silt excluders:
 Constructed on the bed of river in upstream of head
regulator.
 The clear water enter the head works and silted water
entered the silt excluder.
(b) Silt ejectors:
 It is also called silt extractor, which extract silt from canal
water after silted water travelled a certain distance.
TYPES OF SLUICE GATE
Flap sluice
gate
Vertical
rising SG
Radial SG
Rising
sector SG
Needle SG
Automatic
type(by
pressure)
Plate
sliding
vertical
direction
Cylindrical
surface
act as gate
same
radial, @
bottom &
rotates
center
Thin
needles
formed by
sluices
Wood Cast iron
Stainless
steel
FRP
TYPES OF MATERIALS USED FOR SLUICE GATE
CANAL FALL:
 Generally canals are provided some slope. But sometimes
the ground surface is not uniform, so that the vertical drop
is provided to continue the flow.
NECESSITY OF CANAL FALLS:
 When the slope of ground suddenly changes to steeper
slope, the permissible bed slope can't be maintained.
 So that it required excessive earth filling to maintain the
slope. In such case falls are provided to avoid excessive
earth work in filling.
 Slope of ground is more or less uniform and slope is
greater than permissible bed slope , the canal fall is
provided.
 In cross drainage works the F.S.L of canal is above the
bed level of drainage the canal fall is necessary.
TYPES OF CANAL FALLS:
The followings are the types of canal falls based on the site
condition;
a) Ogee fall
b) Rapid fall
c) Stepped fall
d) Trapezoidal notch fall
e) Vertical drop fall
f) Glacis fall
(a) Ogee fall:
 In this type, ogee curve(combination of convex curve and
concave curve) is provided for carrying the canal water
from higher level to lower level.
 This fall is recommended when the natural ground surface
suddenly changes to steeper slope along the alignment of
canal.
It consists of concrete vertical wall and concrete bed.
Over the concrete bed the rubble masonry is provided in
shape of ogee curve.
Surface of masonry is finished with rich cement
mortar(1:3)
Upstream and downstream side of fall is protected by
stone pitching with cement grouting & the design is based
on site condition.
(b) Rapid fall:
 This is suitable when the slope of natural ground surface
is even and long.
 It consists of slope varies from 1 in 10 to 1 in 20.
Curtain walls are provided on the upstream and
downstream side of slopes.
Sloping bed is provided with rubble masonry.
The upstream and downstream side of fall is also
protected by rubble masonry.
The surface finished with cement mortar 1:3
(c) Stepped fall:
 It consists of series of vertical drops in form of steps.
 This fall is suitable where the sloping ground is very long
and requires long glacis(easy slopes) to connect the higher
bed level to lower bed level.
This is practically modification of the rapid fall.
The sloping glacis(easy slope) divided to numbers of
drops, so that the flowing water may not cause to damage
the canal bed.
Brick walls are provided at each of the crops.
The bed of canal protected by rubble masonry and the
surface finished with cement mortar 1:3
(d) Trapezoidal notch fall:
 The body wall is constructed across the canal and wall
consists of several trapezoidal notches in b/w the side
piers.
The body wall constructed with masonry or concrete.
An impervious layer is provided to resist the scoring
effect of falling water.
The upstream and downstream side of fall is protected by
stone pitching with cement grouting.
The size and number of notches depends upon the full
supply discharge of the canal.
(e) Vertical drop fall:
 It consists of a vertical drop walls which constructed with
masonry work.
 The water eastern is provided on the downstream side
which acts as a water cushion to dissipate the energy of
falling water.
A concrete floor if provided @ downstream to control the
scouring effects.
Curtain walls are provided on upstream and downstream
side.
Stone pitching provided with cement grouting provided to
protect from scouring.
(f) Glacis fall:
 It consists of a straight glacis provided with a crest.
 A water cushion is provided on downstream to dissipate
the energy of falling water.
Sloping glacis constructed with cement concrete.
Curtain walls and toe walls are provided on upstream and
downstream sides.
The space b/w the toe walls and curtain walls is protected
by stone pitching.
This type of fall is suitable for drops up to 1.5m.
CROSS DRAINAGE WORKS
Suitable structures must be constructed at the crossing
point for easy flow of water of canal and drainage in
respective directions.
NECESSITY OF CROSS-DRAINAGE WORKS
 The water-shed canals do not cross natural drainages and
there is some obstacles like natural drainages.
 Some points, the water of canal and drainage get
intermixed.
 The site condition of crossing point, the water of canal
and natural drainage may get mixed so need some
structures.
TYPES OF CROSS-DRAINAGE WORKS
TYPE-I:
a) Aqueduct
b) Siphon aqueduct
TYPE-II:
a) Super passage
b) Siphon super passage
TYPE- III:
a) Level crossing
b) Inlet and outlet
TYPE-I:
a) Aqueduct:
 It is like a bridge where a canal is taken over the deck
supported by piers instead of a road or railway.
 The canal may be a rectangular or trapezoidal.
Inspection road is provided along the side of the trough.
The bed and banks of drainage below the trough is
protected by boulder pitching with cement grouting.
The trough design is according to full supply discharge of
canal.
Free board is 0.50m
Height and section of piers designed based on H.F.L and
velocity of flow & it is a stone masonry or RCC.
b) Siphon Aqueduct:
 Bed of the drainage is depressed below the bottom level
of canal trough by providing sloping apron on both sides
of the crossing.
Sloping apron is constructed by stone pitching or cement
concrete.
Section of below the canal is constructed by cement
concrete to form tunnel, it is act as a siphon.
Cut off walls and boulder pitching are provided on both
sides to prevent scouring.
The other components are same as aqueduct.
TYPE-II:
a) Super passage:
 It is opposite of the aqueduct.
 Here the drainage is passing above the canal & it is may
be a rectangular or trapezoidal shapes supported by piers.
The section of drainage trough is based on the high flood
discharge.
Free board is 1.5m & trough constructed by RCC.
Bed and banks of canal below the drainage is protected by
boulder pitching or lining with concrete slabs.
Foundation of piers will be same as in the case of
aqueduct.
b) Siphon super passage:
 It is opposite to the siphon aqueduct & the canal passes
below the drainage trough.
 Section of trough is designed based on high flood
discharge.
 The bed of the canal is depressed below the bottom level
on both sides(made like sloping apron).
Sloping apron may be constructed with stone pitching or
concrete slabs.
Section of canal below the trough is constructed with CC
in form of tunnel which acts as siphon.
Cut off walls provided on U/S and D/S side of sloping
apron and other components are same as siphon aqueduct.
TYPE-III:
a) Level crossing:
 It is arrangement provided to regulate the flow of water
through the drainage and the canal when they cross each
other approximately in the same bed level.
Crest wall:
 It is provided across the drainage just at the upstream side
of crossing point & top level is full supply of canal.
Drainage regulator:
 It is provided across the drainage just at the downstream
side of crossing point & it consists adjustable shutters.
Canal regulator:
 It is provided across the drainage just at the downstream
side of crossing point & it consists adjustable shutters.
b) Inlet and outlet:
 Crossing of small drainage with small channel no
hydraulic structure is constructed.
 Simple openings only provided for their respective
directions.
Inlet is provided in the channel bank simply by open cut
and the drainage water is allowed to join the channel.
Inlet and outlet ends are protected by stone pitching.
CANAL ESCAPES:
It is a side channel constructed to remove the surplus
water from an irrigation channel into a natural drain.
CANALALIGNMENT:
Canal has to be aligned, produce minimum losses,
irrigated to entire area with short length and economical
manner.
FACTORS TO BE CONSIDERED FOR CANAL
ALIGNMENT:
 Most economical way to distributing the water to land.
 Minimum number of cross drainage works.
 The alignment of canal should be occupied by
distributaries.
 Length of inlet and outlet should be minimum.
 Contour alignment should be changed to minimize the
cross drainage works.
 Alignment should avoid the valuable properties.
 Alignment should be minimum cutting and filling.
 Acute curves are minimum.
 Idle and branches of canals are minimum.
 Alignment should not be made in rocky and strong strata.
Types of canal alignment:
i) Watershed canal or ridge canal
ii) Contour canal
iii) Side-slope canal
i) Watershed canal or ridge canal:
 The dividing ridge line between the catchment areas of
two streams(drains) is called watershed or ridge line.
 The main streams are divided into two streams by
watershed(ridge line).
 The canal which is aligned along the natural watershed is
known as watershed canal or ridge canal.
 Aligning the canal on ridge ensures gravity irrigation on
both sides of the canal.
 Canal aligned on the watershed saves the cost of
construction of cross-drainage works.
ii) Contour canal:
 In hilly regions the watershed canals are not possible. So
the contour canal alignment was take place.
 Contour channels are follow a contour except longitudinal
slope of the canal.
 The river slope is much steeper than the canal bed slope,
the canal encompasses more and more area itself.
 It irrigates only one side because the area on the other side
is higher.
iii) Side-slope canal:
 It is aligned at right angles to the contours.
 The canal runs parallel to the natural drainage works the
cross drainage works are not necessary.
CANAL LINING:
 An impermeable layer is provided at the bed and sides of
canal to improve the life & discharge capacity of canal.
 Irrigation loss is generally occurred in canals are 30-40%.
TYPES OF CANAL LININGS
Earthen type lining Hard surface lining
Compacted
earth lining
Soil
cement
lining
Cement
concrete
lining
Brick
lining
Plastic
lining
Boulder
lining
1.EARTHEN TYPE LINING:
a) Compacted earth lining:
 If suitable earthen material available near the construction
site or in-situ, it is the efficient method of canal lining.
 Compaction reduces the permeability of soil, pore sizes,
voids and increases the density , compressive strength and
shear strength of soil.
 Also reduction of volume and settlement of surface
occurred.
 Proper compaction is essential for increase the stability
and decrease the erosion and seepage losses.
b) Soil cement lining:
 It is the mixture of cement ,sandy soil and water to make
the harden material like concrete.
 Cement content should be from 2-8% of soil by volume.
 The construction of soil-cement linings two methods are;
i) dry-mix method
ii) plastic mix method
 Sometimes the coarse soil is covered the soil-cement layer
for protection of erosion.
 Soil-cement lining is protected from weather for 7 days
by spreading approximately 50mm of soil.
 Proper curing takes place for 28 days with water
sprinkling and some other methods.
2.Hard surface lining:
a) Cement concrete lining:
 This method is widely used for lining but it is costly.
 They are tough, durable, relatively impermeable and
hydraulically efficient.
 It can be suitable for small and large channels and both
high and low flow velocities.
 It has several procedures;
i) cast in-situ lining
ii) shotcrete lining
iii) precast concrete lining
iv) cement mortar lining
b) Brick lining:
 The canal sides are lined with bricks laid in cement
mortar.
c) Plastic lining:
 As a modern technique use of plastic as a lining material.
i) low density poly ethylene
ii) high molecular high density polythene
iii) polyvinyl chloride
 These are low in weight, easy for handling, transport.
 These are prepared subgrade of the canal & to anchor on
banks ‘V’ trenches are provided.
 The film is then covered with productive soil cover.
b) Boulder lining:
 This type of lining is constructed with dressed stone
blocks laid in mortar.
 This type of lining is limited to the situation where loss of
head is not an important consideration and where stones
are available at moderate cost.
CANAL DESIGN:
a) Kennedy’s theory
b) Lacey’s regime theory
a) Kennedy’s equation:
 For design of canal, the following equations are used;
Continuity equation:
Q = Area x Velocity
Kutter’s equation:
Kennedy’s equation,
Vo = 0.55 m D0.64 (Kennedy’s regime equation)
Design procedure:
Case 1: Given Q,N, m and S (from L-section)
Step -1: Assume a trial value of ‘D’ in meters
Step -2: Calculate the velocity Vo from the equation.
Vo = 0.55 m D0.64
Step -3: Get area of section ‘A’ from the continuity equation.
A= Q/ Vo
Step-4: Knowing ‘D’ and ‘A’ calculate bed width ‘B’ from
geometry of canal section & side slope assumed 0.5:1 when
the canal run for some time.
A = BD + D2 / 2
From which ‘B’ can be calculated.
Step-5: Calculate the perimeter and hydraulic mean depth
from following relations,
𝑷 = 𝑩 + 𝑫 𝟓
R = A / P = (BD+D2/2) / (B+D√5)
Step-6: Calculate the actual mean velocity of flow(V) from
kutter’s equation.
If V= Vo, assume depth is correct.
If not, repeat evaluations with a changed value of ‘D’
till V=Vo
Case-2: Given Q, N, m and B/D ratio.
Step-1: Calculate ‘A’ interms of ‘D’
Let, B/D = x (or) B= Dx
𝑨 = 𝑩𝑫 +
𝑫 𝟐
𝟐
= 𝑿𝑫 𝟐 +
𝑫 𝟐
𝟐
= 𝑫 𝟐(𝑿 + 𝟎. 𝟓)
Step-2: The value of velocity Vo is known in terms of ‘D’ by
kennedy’s equation,
Vo = 0.55 m D0.64
Substitute the values of ‘Vo’ and ‘A’ in the continuity
equation and solve ‘D’.
Q= A * Vo = 𝐷2(𝑋 + 0.5) * 0.55 m D0.64
Q= 0.55m(x + 0.5) D2.64
Hence , 𝑫 =
𝑸
𝟎.𝟓𝟓𝒎 𝒙+𝟎.𝟓
1/2.64
Hence, D is determined.
Step-3: Calculate ‘B’ and ‘R’ from relations:
B = xD and R = (BD+D2/2) / (B+D√5)
Step-4: Calculate the velocity Vo from kennedy’s equation
Vo = 0.55 m D0.64
Step-5: Knowing ‘Vo’ and ‘R’, determine the slope ‘S’ from
kutter’s equation. The equation can be solved by trail and
error.
DRAWBACKS IN KENNEDY’S THEORY:
1. Kennedy did not notice the importance of B/D ratio.
2. Silt grade and silt charge were not defined.
3. He aimed to find out only the average regime conditions
for the design of channel.
4. He did not give any slope equation.
5. He used kutter’s equation for determination of mean
velocity and therefore the limitations of kutter’s equation
got incorporated in kennedy’s theory of channel design.
b) Lacey’s regime theory:
 Silt is kept in suspension by vertical component of eddies
generated at all points of forces normal to the wetted
perimeter.
Regime channel:
 A channel is said to in regime, if there is neither silting
nor scouring.
 According to lacey there may be three regime conditions;
i) True regime
ii) Initial regime
iii) Final regime
i) True regime:
 Discharge is constant
 Flow is uniform
 Amount is silt is constant
 Type and size of silt is always same
 Channel flowing through a material which can be scoured
as easily as it can be deposited and transported.
But in practice all these conditions can never satisfied.
Therefore the artificial channels can never be in ‘true
regime’ they can either be in initial or final regime.
ii) Initial regime:
 Bed slope varies
 Cross section or wetted perimeter remains unaffected.
iii) Final regime:
 All the variables such as perimeter, depth, slope, etc. are
free to vary and achieve permanent stability.
Lacey’s equations:
Fundamental equations;
𝑉 =
2
5
𝑓𝑅 𝑜𝑟 𝑓 =
5𝑉2
2𝑅
Where, f= 1.76√D50
D50 – average grain/particle size in ‘mm’
Af2 = 140 V5
V = 10.8 R2/3 S1/2
Derived equations;
𝑃 = 4.75 𝑄
𝑉 =
𝑄𝑓2
140
1/6
S= f3/2 / (4980 R1/2) [upper indus basin, f=0.8 to 1.3]
S= f5/3 / (3340 Q1/6) [sindh plain, f=0.7 to 0.8]
V= 1/ Na( R3/4 S1/2) [Lacey’s Non-regime flow equation]
Lacey’s Normal regime scour depth = 0.473(Q/f)1/3
[𝑃 = 4.75 𝑄]
For other values of active river width,
Lacey’s normal scour depth = 1.35(q/f)1/3 , q=Q/L
Where, q= discharge intensity
L= actual river width at the given site
Lacey’s channel design procedure:
Step-1: Calculate the velocity from equation,
𝑉 =
𝑄𝑓2
140
1/6
Where,
Q = cumecs
V = m/s
f = silt factor, f=1.76√dmm [dmm – avg particle size]
Step-2: Workout the hydraulic mean depth (R),
R= (5/2) (V2/f) [V = m/sec; R= m]
𝐷 = 𝑃 − (𝑃2 − 6.944𝐴)/3.742
B=P - √5 D
Step-3: Compute area of channel section, A= Q/V
Step-4: Compute wetted perimeter, P = 4.75 √Q
Step-5: Knowing these values, the channel section is known
and finally the bed slope ‘S’ determined by following
equation,
S= f5/3 / (3340 Q1/6)
Drawbacks in Lacey’s theory:
The concept of true regime is only theoretical and cannot
be achieved practically.
Various equations are derived by considering various silt
factor.
Concentration of silt is not taken into account.
Silt grade and charge are not clearly defined.
Equations are empirical and based on the available data
from a particular type of channel.
Characteristics of regime of channel may not be same foe
all cases.
COMPARISON BETWEEN KENNEDY’S AND
LACEY’S THEORIES
S.No KENNEDY THEORY LACEY’S THEORY
1
Silt carried by the
flowing water is kept
vertical component,
generated from bed of
channel.
Silt carried by the flowing
water is kept vertical
component, generated from
entire wetted perimeter.
2 Relation between ‘V’
and ‘D’
Relation between ‘V’ and
‘R’
3 Critical velocity ratio
‘m’ is introduced to
make different channels
with different channels.
Silt factor ‘f’ is introduced to
make different channels with
different channels.
S.No KENNEDY THEORY LACEY’S THEORY
4 Kutter’s equation is
used for finding the
mean velocity.
Theory gives an equation for
finding the mean velocity.
5 No equation for bed
slope.
It gives an equation for
finding the mean velocity.
6 Design based on trial
and error method.
It does not involve trial and
error method.
DESIGN OF UNLINED CANAL:
 Unlined canals exist mostly in underdeveloped countries
when lining cannot be easily afforded.
Uniform flow formulae:
a) Chezy’s formula:
𝑉 = 𝐶 𝑅𝑆
Where, V – Velocity of flow (m/s)
S – longitudinal slope of channel (energy slope)
C – chezy’s co-efficient.
C
Where,
N – kutter’s co-efficient (based on nature of bed and sides of
channel)
R – hydraulic mean radius (A/P)
‘C’ also determined by Bazin’s equation;
𝐶 =
87
1 +
𝐾
𝑅
Where, K – Bazin’s co-efficient
b) Kutter’s formula:
Where,
V – Velocity of flow (m/s)
S – longitudinal slope of channel
N – rugosity coefficient
R - hydraulic mean radius (A/P)
Value of ‘N’ in kutter’s equation:
c) Manning’s Formula:
V= (1/n)R2/3 S1/2
Where,
n – manning’s roughness coefficient
S.No Condition of channel Value of N
1 Very good 0.0225
2 Good 0.0250
3 Indifferent 0.0275
4 Bad 0.0300
Values of manning’s roughness coefficient
Material n
Concrete 0.012
Gravel bottom with sides-
concrete 0.20
Moderated stone
Natural clean, straight natural
stream
0.030
Natural stream with heavy bush
and timber
0.100

Mais conteúdo relacionado

Mais procurados (20)

Irrigation canals
Irrigation canalsIrrigation canals
Irrigation canals
 
Canal regulation works. m4pptx
Canal regulation works. m4pptxCanal regulation works. m4pptx
Canal regulation works. m4pptx
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
Design of a channel Reach
Design of a channel ReachDesign of a channel Reach
Design of a channel Reach
 
Hydraulic jump
Hydraulic jumpHydraulic jump
Hydraulic jump
 
Irrigation Channels
Irrigation ChannelsIrrigation Channels
Irrigation Channels
 
050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators050218 chapter 7 spillways and energy dissipators
050218 chapter 7 spillways and energy dissipators
 
Cross drainage work
Cross drainage workCross drainage work
Cross drainage work
 
Spillways
SpillwaysSpillways
Spillways
 
types of canal
types of canaltypes of canal
types of canal
 
Canal alignment
Canal alignmentCanal alignment
Canal alignment
 
presentation : cross drainage work
presentation : cross drainage workpresentation : cross drainage work
presentation : cross drainage work
 
Canal
CanalCanal
Canal
 
Weirs on Permeable Foundations
Weirs on Permeable FoundationsWeirs on Permeable Foundations
Weirs on Permeable Foundations
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
design of weirs
design of weirsdesign of weirs
design of weirs
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Kennedy's and laccy's theory
Kennedy's and laccy's theoryKennedy's and laccy's theory
Kennedy's and laccy's theory
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 
Cross Drainage Work
Cross Drainage Work Cross Drainage Work
Cross Drainage Work
 

Semelhante a CANAL IRRIGATION

Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Saqib Imran
 
Chapter Five-CANAL APPURTENANT STRUCTURES.pdf
Chapter Five-CANAL APPURTENANT STRUCTURES.pdfChapter Five-CANAL APPURTENANT STRUCTURES.pdf
Chapter Five-CANAL APPURTENANT STRUCTURES.pdfAbdanurJihad
 
hydraulic structures in civil engineering
hydraulic structures in civil engineeringhydraulic structures in civil engineering
hydraulic structures in civil engineeringBittuRajkumar
 
Canal MASONRY WORK
Canal MASONRY WORKCanal MASONRY WORK
Canal MASONRY WORKSAGAR RAUT
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksGAURAV. H .TANDON
 
Diversion of headwork
Diversion of headwork Diversion of headwork
Diversion of headwork Jay Khoradiya
 
UNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptxUNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptxDivs97
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworksJimit Shah
 
diversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdfdiversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdfShrutiLotliker
 
Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01saibabu48
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation WorksSANJEEV Wazir
 

Semelhante a CANAL IRRIGATION (20)

Design of hydraulic structures ce 413
Design of hydraulic structures ce 413Design of hydraulic structures ce 413
Design of hydraulic structures ce 413
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Chapter Five-CANAL APPURTENANT STRUCTURES.pdf
Chapter Five-CANAL APPURTENANT STRUCTURES.pdfChapter Five-CANAL APPURTENANT STRUCTURES.pdf
Chapter Five-CANAL APPURTENANT STRUCTURES.pdf
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
 
hydraulic structures in civil engineering
hydraulic structures in civil engineeringhydraulic structures in civil engineering
hydraulic structures in civil engineering
 
Canal MASONRY WORK
Canal MASONRY WORKCanal MASONRY WORK
Canal MASONRY WORK
 
12. Canal Head Regulation.1.pdf
12. Canal Head Regulation.1.pdf12. Canal Head Regulation.1.pdf
12. Canal Head Regulation.1.pdf
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage Works
 
Diversion of headwork
Diversion of headwork Diversion of headwork
Diversion of headwork
 
06. Diversion Headworks-2.pdf
06. Diversion Headworks-2.pdf06. Diversion Headworks-2.pdf
06. Diversion Headworks-2.pdf
 
Canal Fall
Canal FallCanal Fall
Canal Fall
 
UNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptxUNIT 5 Distribution Works.pptx
UNIT 5 Distribution Works.pptx
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Diversion headwork
Diversion headwork Diversion headwork
Diversion headwork
 
Canals
CanalsCanals
Canals
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
diversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdfdiversionheadworks-150327075328-conversion-gate01.pdf
diversionheadworks-150327075328-conversion-gate01.pdf
 
Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01Diversionheadworks 150327075328-conversion-gate01
Diversionheadworks 150327075328-conversion-gate01
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation Works
 

Último

Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 

Último (20)

Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 

CANAL IRRIGATION

  • 1. UNIT-IV CANAL IRRIGATION SYLLABUS: Canal regulations – direct sluice - Canal drop – Cross drainage works-Canal outlets – Design of prismatic canal-canal alignments-Canal lining - Kennedy’s and Lacey’s Regime theory-Design of unlined canal
  • 2. INTRODUCTION: It is a direct irrigation system, which makes use of a weir or a barrage, as well as a storage irrigation scheme which makes use of a storage dam or a storage reservoir, necessitates the construction. DISTRIBUTION SYSTEMS FOR CANAL IRRIGATION: Main canal Branch canal Distributaries (major Distributaries) Minor Distributaries Watercourse
  • 3. Main canal:  Canal head works are generally situated on the river flowing valley and canal should reach the ridge line in shortest possible distance.  Therefore the canal aligned very carefully and has to excavate deep cutting below N.S.L Branch canal:  These are taken off the water from the main canal on either side.  It supply the water to the distributaries. Distributaries:  These are smaller canals get water from the branch canal and distribute their supply through outlets into minors or water courses.
  • 4. Minors Distributaries:  The distance between the distributary outlet and land is very long, discharge in a minor.(less than 2.5 cumec) Water courses:  These are excavated and maintained by the land cultivators.
  • 5. Classification of Canal Nature of source of supply Financial output Function of canal Boundary surface of canal Permanent canal Inundation canal Protective canal Productive canal Power canal Navigation canal Feeder canal Carrier canal Irrigation canal Rigid-boundary canal Non-alluvial canal Alluvial canal Permanent source of supply High stage of supply Net revenue to nation Protect some area
  • 6. CANAL REGULATORS Head regulator:  It is provided at the head of the off-taking canal, controls the flow of water entering the new channel. Cross regulator:  It is required in the main channel downstream in off- taking channel, operated when necessary.
  • 7. MAIN FUNCTIONS OFA HEAD REGULATOR:  Regulate or control supply the off-taking canal.  Control the entry of silt into off-taking canal.  Serve the measuring discharge. MAIN FUNCTIONS OFA CROSS REGULATOR:  To control entire canal irrigation system.  Help to fed the water from upstream to off-taking canal.  Help to reduce fluctuations and possibilities to reach the tail end of canal.  It is combined with bridges and falls, if required.
  • 8. RIVER TRAINING WORKS: These are required near the weir site in order to ensure a smooth and axial flow of water & to prevent the river from outflanking works due to a change in its course. It required on a canal headworks are, (a) guide banks (b) marginal bunds (c) spurs or groynes (a) Guide Banks:  When a barrage is constructed across a river which flows through the alluvial soil, guide banks must be constructed on both sides of canal to protect from soil erosion.
  • 9. Purposes: o Protects from effects of scouring and erosion. o Provides straight approach towards the barrage. o Controls the tendency of changing the course of river. o Controls velocity of flow near the structure. (b)Marginal bunds:  These are earthen embankments which are constructed parallel to the river bank one or both banks according to the condition.  Top width is 3 to 4m and slope on river side 1.5:1 and other side 2:1
  • 10. Purposes: o Prevent the flood or storage water from entering the surrounding area may be lead to water logged. o Retains flood water or storage water within a specified section. o Prevents towns and villages from floods. o Protects valuable agricultural lands. (c)Spurs or groynes: (i) Spurs:  These are temporary structures permeable in nature provided on the curve of a river to protect the river bank from erosion.
  • 11.  These are projected from the river bank and make an angle of 60 to 750 with river bank.  The length of the spur is based on the width & sharpness of the river.  The function of spur is to break the velocity of flow and form a water pocket in upstream for sediments get deposited.  It has the following types; (a) bamboo spur (b) timber spur (c) boulder spur
  • 12. (a) Bamboo spur: • These are like compartment is prepared by bamboo piles at 15cm c/c. • Piles are secured by bamboo bracings and hollow space is filled by sand bags. • It is permeable in nature and water can seep through its body. • This is suitable for small rivers and purely temporary structures . • It requires repair work every year & length of bamboo piles depends upon the bed condition.
  • 13.
  • 14. (b) Timber spur: • This is box like compartment is prepared by driving timber piles at 15cm to 30cm c/c. • Piles are secured by wooden bracings. • The hollow space filled by boulders and it is permeable also stable. • It is recommended for the rivers with high velocity of flow. • The length of timber piles depend on bed condition.
  • 15. (c) Boulder spur: • Here boulders are enclosed in G.I wire net in circular shape. • The boulders should be heavy, varying from 30kg to 50kg and wire net made of 4mm diameter G.I wires. • It laid in river bank towards bed making angle of 600 – 750 • These type is recommended in velocity of flow is very high.
  • 16.
  • 17. (ii) Groynes:  The function of groynes are similar to spur & these are impervious permanent structures constructed on the curve of a river to protect river bank from erosion.  Extend an angle of 600 to 750 with bank and towards upstream or downstream, sometimes it is perpendicular.  These are constructed with rubble masonry in trapezoidal section and surface finished with stone pitching or concrete blocks. Stone pitching or concrete blocks are set with rich cement mortar. Length of groyne based on width & nature of river.
  • 18.
  • 19. Top width varies from 3 to 4m, side slope may be 1.5:1 or 2:1 These are provided in series throughout the affected length of river bank. Spacing of groynes = 2L (L-length of groyne) It is recommended for river where the permanent solution of erosion control necessary. These are may be designed as follows; (a) Attracting groyne:  It is constructed obliquely to bank @ angle 60 – 750 towards downstream.  Flow of water attracted by bank and bank protected of stone pitching for safety.
  • 20.
  • 21. (b) Repelling groyne:  It is constructed obliquely to bank @ angle 60 – 750 towards upstream.  So that water pocket formed and silts get deposited.  Bank protection not necessary because the flow of water does not touch the bank.  For safety purpose boulder pitching is provided. (c) Deflecting groyne:  It is constructed perpendicular to bank.  The flow of water deflected from bank by perpendicular obstruction and eddy current formed upstream of groyne.  For safety purpose boulder pitching is provided.
  • 22.
  • 23. Modification of groyne: (a) Denehy’s groyne or T-headed groyne: After long investigation, deheny developed a groyne in shape of T. Length of head kept as L/2, (L-length of groyne). All others are same as other groynes.
  • 24. (b) Hockey head groyne: The head of the groyne is curved towards the downstream in shape of a hockey stick & it behaves like a attracting groyne. But it allows the water to flow smoothly over the head of the groyne.
  • 25. SILT REGULATION WORKS Special works to reduced the entry of silt into the canal. (a) Silt excluders (b) Silt ejectors (a) Silt excluders:  Constructed on the bed of river in upstream of head regulator.  The clear water enter the head works and silted water entered the silt excluder. (b) Silt ejectors:  It is also called silt extractor, which extract silt from canal water after silted water travelled a certain distance.
  • 26.
  • 27. TYPES OF SLUICE GATE Flap sluice gate Vertical rising SG Radial SG Rising sector SG Needle SG Automatic type(by pressure) Plate sliding vertical direction Cylindrical surface act as gate same radial, @ bottom & rotates center Thin needles formed by sluices Wood Cast iron Stainless steel FRP TYPES OF MATERIALS USED FOR SLUICE GATE
  • 28. CANAL FALL:  Generally canals are provided some slope. But sometimes the ground surface is not uniform, so that the vertical drop is provided to continue the flow.
  • 29. NECESSITY OF CANAL FALLS:  When the slope of ground suddenly changes to steeper slope, the permissible bed slope can't be maintained.  So that it required excessive earth filling to maintain the slope. In such case falls are provided to avoid excessive earth work in filling.  Slope of ground is more or less uniform and slope is greater than permissible bed slope , the canal fall is provided.  In cross drainage works the F.S.L of canal is above the bed level of drainage the canal fall is necessary.
  • 30.
  • 31. TYPES OF CANAL FALLS: The followings are the types of canal falls based on the site condition; a) Ogee fall b) Rapid fall c) Stepped fall d) Trapezoidal notch fall e) Vertical drop fall f) Glacis fall
  • 32. (a) Ogee fall:  In this type, ogee curve(combination of convex curve and concave curve) is provided for carrying the canal water from higher level to lower level.  This fall is recommended when the natural ground surface suddenly changes to steeper slope along the alignment of canal. It consists of concrete vertical wall and concrete bed. Over the concrete bed the rubble masonry is provided in shape of ogee curve. Surface of masonry is finished with rich cement mortar(1:3) Upstream and downstream side of fall is protected by stone pitching with cement grouting & the design is based on site condition.
  • 33.
  • 34. (b) Rapid fall:  This is suitable when the slope of natural ground surface is even and long.  It consists of slope varies from 1 in 10 to 1 in 20. Curtain walls are provided on the upstream and downstream side of slopes. Sloping bed is provided with rubble masonry. The upstream and downstream side of fall is also protected by rubble masonry. The surface finished with cement mortar 1:3
  • 35.
  • 36. (c) Stepped fall:  It consists of series of vertical drops in form of steps.  This fall is suitable where the sloping ground is very long and requires long glacis(easy slopes) to connect the higher bed level to lower bed level. This is practically modification of the rapid fall. The sloping glacis(easy slope) divided to numbers of drops, so that the flowing water may not cause to damage the canal bed. Brick walls are provided at each of the crops. The bed of canal protected by rubble masonry and the surface finished with cement mortar 1:3
  • 37.
  • 38. (d) Trapezoidal notch fall:  The body wall is constructed across the canal and wall consists of several trapezoidal notches in b/w the side piers. The body wall constructed with masonry or concrete. An impervious layer is provided to resist the scoring effect of falling water. The upstream and downstream side of fall is protected by stone pitching with cement grouting. The size and number of notches depends upon the full supply discharge of the canal.
  • 39.
  • 40. (e) Vertical drop fall:  It consists of a vertical drop walls which constructed with masonry work.  The water eastern is provided on the downstream side which acts as a water cushion to dissipate the energy of falling water. A concrete floor if provided @ downstream to control the scouring effects. Curtain walls are provided on upstream and downstream side. Stone pitching provided with cement grouting provided to protect from scouring.
  • 41.
  • 42. (f) Glacis fall:  It consists of a straight glacis provided with a crest.  A water cushion is provided on downstream to dissipate the energy of falling water. Sloping glacis constructed with cement concrete. Curtain walls and toe walls are provided on upstream and downstream sides. The space b/w the toe walls and curtain walls is protected by stone pitching. This type of fall is suitable for drops up to 1.5m.
  • 43.
  • 44. CROSS DRAINAGE WORKS Suitable structures must be constructed at the crossing point for easy flow of water of canal and drainage in respective directions. NECESSITY OF CROSS-DRAINAGE WORKS  The water-shed canals do not cross natural drainages and there is some obstacles like natural drainages.  Some points, the water of canal and drainage get intermixed.  The site condition of crossing point, the water of canal and natural drainage may get mixed so need some structures.
  • 45. TYPES OF CROSS-DRAINAGE WORKS TYPE-I: a) Aqueduct b) Siphon aqueduct TYPE-II: a) Super passage b) Siphon super passage TYPE- III: a) Level crossing b) Inlet and outlet
  • 46. TYPE-I: a) Aqueduct:  It is like a bridge where a canal is taken over the deck supported by piers instead of a road or railway.  The canal may be a rectangular or trapezoidal. Inspection road is provided along the side of the trough. The bed and banks of drainage below the trough is protected by boulder pitching with cement grouting. The trough design is according to full supply discharge of canal. Free board is 0.50m Height and section of piers designed based on H.F.L and velocity of flow & it is a stone masonry or RCC.
  • 47.
  • 48. b) Siphon Aqueduct:  Bed of the drainage is depressed below the bottom level of canal trough by providing sloping apron on both sides of the crossing. Sloping apron is constructed by stone pitching or cement concrete. Section of below the canal is constructed by cement concrete to form tunnel, it is act as a siphon. Cut off walls and boulder pitching are provided on both sides to prevent scouring. The other components are same as aqueduct.
  • 49.
  • 50. TYPE-II: a) Super passage:  It is opposite of the aqueduct.  Here the drainage is passing above the canal & it is may be a rectangular or trapezoidal shapes supported by piers. The section of drainage trough is based on the high flood discharge. Free board is 1.5m & trough constructed by RCC. Bed and banks of canal below the drainage is protected by boulder pitching or lining with concrete slabs. Foundation of piers will be same as in the case of aqueduct.
  • 51.
  • 52. b) Siphon super passage:  It is opposite to the siphon aqueduct & the canal passes below the drainage trough.  Section of trough is designed based on high flood discharge.  The bed of the canal is depressed below the bottom level on both sides(made like sloping apron). Sloping apron may be constructed with stone pitching or concrete slabs. Section of canal below the trough is constructed with CC in form of tunnel which acts as siphon. Cut off walls provided on U/S and D/S side of sloping apron and other components are same as siphon aqueduct.
  • 53.
  • 54. TYPE-III: a) Level crossing:  It is arrangement provided to regulate the flow of water through the drainage and the canal when they cross each other approximately in the same bed level. Crest wall:  It is provided across the drainage just at the upstream side of crossing point & top level is full supply of canal. Drainage regulator:  It is provided across the drainage just at the downstream side of crossing point & it consists adjustable shutters. Canal regulator:  It is provided across the drainage just at the downstream side of crossing point & it consists adjustable shutters.
  • 55.
  • 56. b) Inlet and outlet:  Crossing of small drainage with small channel no hydraulic structure is constructed.  Simple openings only provided for their respective directions. Inlet is provided in the channel bank simply by open cut and the drainage water is allowed to join the channel. Inlet and outlet ends are protected by stone pitching.
  • 57.
  • 58. CANAL ESCAPES: It is a side channel constructed to remove the surplus water from an irrigation channel into a natural drain.
  • 59. CANALALIGNMENT: Canal has to be aligned, produce minimum losses, irrigated to entire area with short length and economical manner. FACTORS TO BE CONSIDERED FOR CANAL ALIGNMENT:  Most economical way to distributing the water to land.  Minimum number of cross drainage works.  The alignment of canal should be occupied by distributaries.  Length of inlet and outlet should be minimum.  Contour alignment should be changed to minimize the cross drainage works.
  • 60.  Alignment should avoid the valuable properties.  Alignment should be minimum cutting and filling.  Acute curves are minimum.  Idle and branches of canals are minimum.  Alignment should not be made in rocky and strong strata. Types of canal alignment: i) Watershed canal or ridge canal ii) Contour canal iii) Side-slope canal i) Watershed canal or ridge canal:  The dividing ridge line between the catchment areas of two streams(drains) is called watershed or ridge line.
  • 61.  The main streams are divided into two streams by watershed(ridge line).  The canal which is aligned along the natural watershed is known as watershed canal or ridge canal.  Aligning the canal on ridge ensures gravity irrigation on both sides of the canal.  Canal aligned on the watershed saves the cost of construction of cross-drainage works.
  • 62.
  • 63. ii) Contour canal:  In hilly regions the watershed canals are not possible. So the contour canal alignment was take place.  Contour channels are follow a contour except longitudinal slope of the canal.  The river slope is much steeper than the canal bed slope, the canal encompasses more and more area itself.  It irrigates only one side because the area on the other side is higher.
  • 64.
  • 65. iii) Side-slope canal:  It is aligned at right angles to the contours.  The canal runs parallel to the natural drainage works the cross drainage works are not necessary.
  • 66. CANAL LINING:  An impermeable layer is provided at the bed and sides of canal to improve the life & discharge capacity of canal.  Irrigation loss is generally occurred in canals are 30-40%. TYPES OF CANAL LININGS Earthen type lining Hard surface lining Compacted earth lining Soil cement lining Cement concrete lining Brick lining Plastic lining Boulder lining
  • 67. 1.EARTHEN TYPE LINING: a) Compacted earth lining:  If suitable earthen material available near the construction site or in-situ, it is the efficient method of canal lining.  Compaction reduces the permeability of soil, pore sizes, voids and increases the density , compressive strength and shear strength of soil.  Also reduction of volume and settlement of surface occurred.  Proper compaction is essential for increase the stability and decrease the erosion and seepage losses.
  • 68. b) Soil cement lining:  It is the mixture of cement ,sandy soil and water to make the harden material like concrete.  Cement content should be from 2-8% of soil by volume.  The construction of soil-cement linings two methods are; i) dry-mix method ii) plastic mix method  Sometimes the coarse soil is covered the soil-cement layer for protection of erosion.  Soil-cement lining is protected from weather for 7 days by spreading approximately 50mm of soil.  Proper curing takes place for 28 days with water sprinkling and some other methods.
  • 69. 2.Hard surface lining: a) Cement concrete lining:  This method is widely used for lining but it is costly.  They are tough, durable, relatively impermeable and hydraulically efficient.  It can be suitable for small and large channels and both high and low flow velocities.  It has several procedures; i) cast in-situ lining ii) shotcrete lining iii) precast concrete lining iv) cement mortar lining
  • 70. b) Brick lining:  The canal sides are lined with bricks laid in cement mortar. c) Plastic lining:  As a modern technique use of plastic as a lining material. i) low density poly ethylene ii) high molecular high density polythene iii) polyvinyl chloride  These are low in weight, easy for handling, transport.  These are prepared subgrade of the canal & to anchor on banks ‘V’ trenches are provided.  The film is then covered with productive soil cover.
  • 71. b) Boulder lining:  This type of lining is constructed with dressed stone blocks laid in mortar.  This type of lining is limited to the situation where loss of head is not an important consideration and where stones are available at moderate cost.
  • 72. CANAL DESIGN: a) Kennedy’s theory b) Lacey’s regime theory a) Kennedy’s equation:  For design of canal, the following equations are used; Continuity equation: Q = Area x Velocity Kutter’s equation:
  • 73. Kennedy’s equation, Vo = 0.55 m D0.64 (Kennedy’s regime equation) Design procedure: Case 1: Given Q,N, m and S (from L-section) Step -1: Assume a trial value of ‘D’ in meters Step -2: Calculate the velocity Vo from the equation. Vo = 0.55 m D0.64 Step -3: Get area of section ‘A’ from the continuity equation. A= Q/ Vo Step-4: Knowing ‘D’ and ‘A’ calculate bed width ‘B’ from geometry of canal section & side slope assumed 0.5:1 when the canal run for some time.
  • 74. A = BD + D2 / 2 From which ‘B’ can be calculated. Step-5: Calculate the perimeter and hydraulic mean depth from following relations, 𝑷 = 𝑩 + 𝑫 𝟓 R = A / P = (BD+D2/2) / (B+D√5)
  • 75. Step-6: Calculate the actual mean velocity of flow(V) from kutter’s equation. If V= Vo, assume depth is correct. If not, repeat evaluations with a changed value of ‘D’ till V=Vo Case-2: Given Q, N, m and B/D ratio. Step-1: Calculate ‘A’ interms of ‘D’ Let, B/D = x (or) B= Dx 𝑨 = 𝑩𝑫 + 𝑫 𝟐 𝟐 = 𝑿𝑫 𝟐 + 𝑫 𝟐 𝟐 = 𝑫 𝟐(𝑿 + 𝟎. 𝟓) Step-2: The value of velocity Vo is known in terms of ‘D’ by kennedy’s equation, Vo = 0.55 m D0.64
  • 76. Substitute the values of ‘Vo’ and ‘A’ in the continuity equation and solve ‘D’. Q= A * Vo = 𝐷2(𝑋 + 0.5) * 0.55 m D0.64 Q= 0.55m(x + 0.5) D2.64 Hence , 𝑫 = 𝑸 𝟎.𝟓𝟓𝒎 𝒙+𝟎.𝟓 1/2.64 Hence, D is determined. Step-3: Calculate ‘B’ and ‘R’ from relations: B = xD and R = (BD+D2/2) / (B+D√5) Step-4: Calculate the velocity Vo from kennedy’s equation Vo = 0.55 m D0.64 Step-5: Knowing ‘Vo’ and ‘R’, determine the slope ‘S’ from kutter’s equation. The equation can be solved by trail and error.
  • 77. DRAWBACKS IN KENNEDY’S THEORY: 1. Kennedy did not notice the importance of B/D ratio. 2. Silt grade and silt charge were not defined. 3. He aimed to find out only the average regime conditions for the design of channel. 4. He did not give any slope equation. 5. He used kutter’s equation for determination of mean velocity and therefore the limitations of kutter’s equation got incorporated in kennedy’s theory of channel design.
  • 78. b) Lacey’s regime theory:  Silt is kept in suspension by vertical component of eddies generated at all points of forces normal to the wetted perimeter. Regime channel:  A channel is said to in regime, if there is neither silting nor scouring.  According to lacey there may be three regime conditions; i) True regime ii) Initial regime iii) Final regime
  • 79. i) True regime:  Discharge is constant  Flow is uniform  Amount is silt is constant  Type and size of silt is always same  Channel flowing through a material which can be scoured as easily as it can be deposited and transported. But in practice all these conditions can never satisfied. Therefore the artificial channels can never be in ‘true regime’ they can either be in initial or final regime.
  • 80. ii) Initial regime:  Bed slope varies  Cross section or wetted perimeter remains unaffected. iii) Final regime:  All the variables such as perimeter, depth, slope, etc. are free to vary and achieve permanent stability.
  • 81. Lacey’s equations: Fundamental equations; 𝑉 = 2 5 𝑓𝑅 𝑜𝑟 𝑓 = 5𝑉2 2𝑅 Where, f= 1.76√D50 D50 – average grain/particle size in ‘mm’ Af2 = 140 V5 V = 10.8 R2/3 S1/2 Derived equations; 𝑃 = 4.75 𝑄 𝑉 = 𝑄𝑓2 140 1/6
  • 82. S= f3/2 / (4980 R1/2) [upper indus basin, f=0.8 to 1.3] S= f5/3 / (3340 Q1/6) [sindh plain, f=0.7 to 0.8] V= 1/ Na( R3/4 S1/2) [Lacey’s Non-regime flow equation] Lacey’s Normal regime scour depth = 0.473(Q/f)1/3 [𝑃 = 4.75 𝑄] For other values of active river width, Lacey’s normal scour depth = 1.35(q/f)1/3 , q=Q/L Where, q= discharge intensity L= actual river width at the given site
  • 83. Lacey’s channel design procedure: Step-1: Calculate the velocity from equation, 𝑉 = 𝑄𝑓2 140 1/6 Where, Q = cumecs V = m/s f = silt factor, f=1.76√dmm [dmm – avg particle size] Step-2: Workout the hydraulic mean depth (R), R= (5/2) (V2/f) [V = m/sec; R= m] 𝐷 = 𝑃 − (𝑃2 − 6.944𝐴)/3.742 B=P - √5 D
  • 84. Step-3: Compute area of channel section, A= Q/V Step-4: Compute wetted perimeter, P = 4.75 √Q Step-5: Knowing these values, the channel section is known and finally the bed slope ‘S’ determined by following equation, S= f5/3 / (3340 Q1/6) Drawbacks in Lacey’s theory: The concept of true regime is only theoretical and cannot be achieved practically. Various equations are derived by considering various silt factor. Concentration of silt is not taken into account. Silt grade and charge are not clearly defined.
  • 85. Equations are empirical and based on the available data from a particular type of channel. Characteristics of regime of channel may not be same foe all cases.
  • 86. COMPARISON BETWEEN KENNEDY’S AND LACEY’S THEORIES S.No KENNEDY THEORY LACEY’S THEORY 1 Silt carried by the flowing water is kept vertical component, generated from bed of channel. Silt carried by the flowing water is kept vertical component, generated from entire wetted perimeter. 2 Relation between ‘V’ and ‘D’ Relation between ‘V’ and ‘R’ 3 Critical velocity ratio ‘m’ is introduced to make different channels with different channels. Silt factor ‘f’ is introduced to make different channels with different channels.
  • 87. S.No KENNEDY THEORY LACEY’S THEORY 4 Kutter’s equation is used for finding the mean velocity. Theory gives an equation for finding the mean velocity. 5 No equation for bed slope. It gives an equation for finding the mean velocity. 6 Design based on trial and error method. It does not involve trial and error method.
  • 88. DESIGN OF UNLINED CANAL:  Unlined canals exist mostly in underdeveloped countries when lining cannot be easily afforded. Uniform flow formulae: a) Chezy’s formula: 𝑉 = 𝐶 𝑅𝑆 Where, V – Velocity of flow (m/s) S – longitudinal slope of channel (energy slope) C – chezy’s co-efficient. C
  • 89. Where, N – kutter’s co-efficient (based on nature of bed and sides of channel) R – hydraulic mean radius (A/P) ‘C’ also determined by Bazin’s equation; 𝐶 = 87 1 + 𝐾 𝑅 Where, K – Bazin’s co-efficient
  • 90. b) Kutter’s formula: Where, V – Velocity of flow (m/s) S – longitudinal slope of channel N – rugosity coefficient R - hydraulic mean radius (A/P)
  • 91. Value of ‘N’ in kutter’s equation: c) Manning’s Formula: V= (1/n)R2/3 S1/2 Where, n – manning’s roughness coefficient S.No Condition of channel Value of N 1 Very good 0.0225 2 Good 0.0250 3 Indifferent 0.0275 4 Bad 0.0300
  • 92. Values of manning’s roughness coefficient Material n Concrete 0.012 Gravel bottom with sides- concrete 0.20 Moderated stone Natural clean, straight natural stream 0.030 Natural stream with heavy bush and timber 0.100