SlideShare uma empresa Scribd logo
1 de 39
Baixar para ler offline
 Hazard Identification merupakan suatu
study yang bertujuan untuk melakukan
identifikasi potential hazards dengan
sumber dari external facilities yang
mempengaruhi fasilitas atau hazard
dengan sumber dari internal fasilitas yang
berpengaruh ke environmental, community
atau surrounding area.
 Review difokuskan pada PFD, P&ID dan Plot
Plan dari fasilitas.
2IJK & team
 Sejumlah metode untuk melaksanakan identifikasi hazard
telah dikembangkan.
 Overview terhadap hazard identification telah diberikan
dalam:
◦ Chemical Industries Association (CIA) Guide to Hazard and
Operability Studies (CIHSC, 1977/3) (the CIA Hazop Study Guide)
◦ Guidelines for Hazard Evaluatuion Procedures (CCPS, 1985/1,
1992/9) (the CCPS Hazard Evaluation Guidelines)
◦ A Manual of Hazard and Operability Studies (Knowlton, 1992) (the
Chemetics Hazard Study Manual).
 Hazard Identification sering disebut juga dengan Process
Hazard Analysis (PHA)
3IJK & team
 What if? Analysis
 Checklist
 What-If/Checklist
 Event tree and fault tree analysis
 Preliminary hazard analysis
 Coarse hazard studies
 Hazard and operability studies
 Failure modes, effects and criticality analysis
 dll
4IJK & team
5IJK & team
 HAZOPS stands for HAZard and
Operability Study.
 HAZOPS merupakan suatu metode untuk
mengidentifikasi bahaya dan operability
masalah dalam proses desain.
 Ini adalah teknik sistematis yang
diaplikasikan secara bertahap ke bagian
kecil dari proses desain sampai semua
bagian desain.
6IJK & team
A Process System Hazard Analysis technique
that common to be used to identify potential of
an operational deviation that may occur, its
cause, its consequences, identify the existing
safeguards, then produce a recommendation for
action item to be accomplished when existing
safeguard found to be insufficient.
7IJK & team
1. Exploratory Phase
identification of basic hazard and assessment of suitability of
possible sites.
2. Flowsheet Phase
identification and assessment of significant hazard.
3. Detailed Design – HAZOP
4. Construction
a check that decisions made in earlier studies have been
implemented
5. Commissioning
final inspection
6. Post-commissioning
safety audit and review of modifications
8IJK & team
Project Phase Safety Activities
Design
Construction and Instalation
Commissioning & Start Up
Operation
PHA / HAZID / HAZOPS
• Contractor Assessment
• Safety Audit & Inspection
• Punch List Review
•Pre-Start Up Review
•Training
•Handover Procedure
• Management of Change
• Incident Investigation
• Safety Audit and Inspection
9IJK & team
10IJK & team
 Tahap Design
◦ Preliminary HAZOPS
◦ Full HAZOPS
 Tahap Modifikasi
◦ Mini HAZOPS
11IJK & team
External and Environmental Hazards
Hazard Type Guideword Expanders
Natural Hazards Extreme Weather Temperature extremes; wave; wind; dust;
flooding; sandstorm; ice; blizzards
Lightning
Seismic Activity
Erosion Ground slide; coastal
Subsidence Ground structure; foundation; reservoir
depletion
Environmental Impact Discharges to Air Flaring; venting; fugitive emissions;
energy efficiency
Discharges to Water Drainage; water quality; waste disposal
options
Discharges to Soil Drainage; chemical spillage; waste
disposal options
Location and Layout Previous land use; vulnerable fauna and
flora; visual impact; local population; area
minimization
External & 3rd Party Hazards Sabotage Internal & external security threats
Terrorist Activity Riots; civil disturbance; strikes; military
action; political unrest
Third Party Activities Farming; fishing; local industry
Helicopter/Aircraft Crash
12IJK & team
Facility Hazards
Hazard Type Guideword Expanders
Process Hazards Process Releases
- Unignited
Gas clouds; gas detection;
emergency response
Process releases
- Ignited
Fire; explosion; heat; smoke; fire
detection; emergency response
Process releases
- toxic
H2S detection; emergency
response
Flaring Heat; ignition source; location
Venting Discharge to atmosphere;
location; dispersion
Draining
Sampling Operator error
Accommodation and
Non-Process Area
Hazards
Non Process Fires Control room; accommodation
building
Smoke/Gas Ingress Ingress to safe areas; HVAC
shutdown
Stacking and Storage 13IJK & team
Health Hazards
Hazard Type Guideword Expanders
Health Hazards Disease Hazards Endemic diseases; infection;
contaminated water; social e.g.
HIV
Working Environment Physical Drinking water; lighting; noise
Temperature Extreme hot/cold; ventilation,
guarding
Atmospheres Exhaust fumes; confined spaces
14IJK & team
What if Consequence / hazard Recommendations
Coolant pump to
reaktor fails
Runaway condition in
reactor explosion/fatality
•Provide accurate temperature
monitoring in reactor
•Employ backup pump/high
temperature alarm
•Relieve reactor pressure in
reactor through automatic
control to stop reactions
•Provide automatic shut off of
ethylene flow
Coolant
temperature to
jacket is high
15IJK & team
 Preliminary Hazard Analysis merupakan metode
identifikasi bahaya pada tahap awal dari desain proses.
 Guidelines:
1) Bahan baku, produk antara dan produk akhir.
2) Plant equipment
3) Fasilitas
4) Safety equipment
5) Interfaces between system components
6) Lingkungan
7) Operasi (maintenance, testing, dll)
16IJK & team
Hazard Cause Major Effects Corrective/Preventive
Measures
Flamable
gas release
CH4 storage tank
(line) leak/rupture
(fuel for the
furnace)
Potential for
injuries and
fatalities due to
fire or explosion
• Provide warning system
• Minimize on-site
storage
• Develop procedure for
tank inspection
• Develop emergency
response system
• Provide gas monitoring
system
…
17IJK & team
 Coarse Hazard Studies disusun dengan kompilasi dari 2
daftar berikut:
1) Daftar hazard dan nuisance (sesuatu yang
mengganggu) dari sifat material
2) Potensi hazard dan nuisance dari materi lain
yang berhubungan.
 Guide words
 Fire
 Explosion
 Toxicity
 Corrosion
 Smell
 Effluent
18IJK & team
HAZOPS
(Hazard & Operability Study)
A systematic review of the design & operation of a system to
identify the potential for accidental releases of hazardous
material, or operability problems.(Potential accident scenarios)
Based on the premise that :
 A hazard is not realized if the process is always operated
within its design intent
 Creative input of a team is better than of an individual
 Item can be applied, independent of process technologies
19IJK & team
 Drawing board
 Construction
 Only during process modifications
 Whenever accident occurs
20IJK & team
• Intentions: How the Process/Facility operations are
expected to occur
• Deviation: Departures from the design intention
• Causes: Ways deviations might occur
• Consequences: Results of the deviations
• Safeguards: Provision for reducing the frequency of
causes or the severity of consequences.
• Action: Suggestions for procedural changes, design
changes or further study (do not debate the relative
merit of suggested actions, but record them all)
21IJK & team
Node
• A node is a location on a process diagram (usually
P&ID’s) at which process parameters are investigated
for deviations.
• Nodes are points where the process parameters have
an identified design intent.
• Nodes are usually pipe sections or vessels.
• Plant components (e.g..., pumps, compressors,
exchangers) are found within nodes
22IJK & team
P& ID
C lassification
N o.O f
E quipem nets
N o.O f Pipe
lines
N o.of
Interlocks
Sim ple 1 to 4 1 to 9 <2
Standard 5 to 6 10 to 20 2 to 4
C om plex >6 >30 >10
V ery C om plex >6 >30 >10
23IJK & team
Parameter
A parameter is an aspect of the process that describes it
physically, chemically, or in terms of what is happening.
Parameters are usually classified as specific or general.
• Specific parameters are those that describe aspects of
the process.
• General parameters are those that describe aspects of
design intent remaining after the specific parameters
have been removed
24IJK & team
Common Parameters
Specific General
Flow Addition, Reaction
Temperature Maintenance, Testing
Pressure Instrumentation
Composition Sampling, Relief
Phase Corrosion / Erosion
Level Safety
25IJK & team
Guide Words
Guide words are simple words or phases used to qualify
or quantify the intention and associated parameters in
order to discover deviations.
There are seven standard guide words.
26IJK & team
• Process Hazard
• Previous Accident/Incident Record
• Engineering System for Risk Mitigation.
• Administrative Control
• Potential of discrepancy / failure of
Engineering System and Administrative
Control
• Facility and Equipment Site and Ergonomic.
• Potential for Human Error
27IJK & team
• Drawing: P&ID, Engineering Drawing, Electrical
Diagram, etc.
• Process Safety Information (Material Safety Data
Sheet)
• Design Specification.
• Operating Procedure, Operating Condition
• Site Situation and Condition of Facility
• Accident/Incident Record
• People record who doing the job
• HAZOPS Guideword
28IJK & team
Nothing but RECOMMENDATION
• Safety
• Operability
• Action
• Comment
29IJK & team
1. Material Hazard:
Toxicity, Exposure Limit (TLV-TWA,
TLV-STEL, TLV C)
2. Process Technology
3. Equipment Design
4. Accident Report
5. Previous Hazop Report
30IJK & team
Flow
Pressure
Level
Temperature
Phase
Time
No
More
Less
Reverse
Other than
31IJK & team
Relief
Contamination
Properties of Chemicals
Rupture/Leak
Ignition
Service Failure
Abnormal Operation
Sampling
Maintenance
Corrosion/Erosion
Equipment Siting
Human Factors
32IJK & team
In addition to the seven standard guide words, the
following auxiliary guide words may be considered :
- How ? How is the step to be accomplished ? Are adequate
facilities provided to allow the operator to perform the
step as specified ?
- Why ? Is the step or operation really needed ?
- When ? Is timing of the step or operation important ?
- Where ? Is it important where the step is performed ?
And so on
33IJK & team
HAZOP - Hazard Vs Operability
Relative Percentage : Operability to Hazard
Status Operability Hazards
of Plant Problem Identified Identified
(%) (%)
New 60 40
Existing 70 30
34IJK & team
An interdisciplinary team of experts
systematically examines every part of the process
or facility to discover how deviations from the
design intentions can occurs
35IJK & team
Team Composition
Team Leader
Team Members
Engineers
Scientists
Operators
Project Engineering
Process
Control
Corrosion
36IJK & team
 Step-1 : Selection of a Study Node to be
Review
 Step-2 : Selection of a Process Deviation or a
Review Check Item
 Step-3 : Identification and Analysis of
Consequence and Causes
 Step-4 : Evaluation of Existing Safeguards
 Step-5 : Investigation of Recommendation
 Step-6 : Recording of the Review Results
 Step-7 : Repeat of the Review
37IJK & team
38IJK & team
Hazid &amp; hazops

Mais conteúdo relacionado

Mais procurados

Conducting Hot Work Operations
Conducting Hot Work OperationsConducting Hot Work Operations
Conducting Hot Work OperationsAaron Johnson
 
Spill Prevention Control and Countermeasures by University of Alaska Fairbanks
Spill Prevention Control and Countermeasures by University of Alaska FairbanksSpill Prevention Control and Countermeasures by University of Alaska Fairbanks
Spill Prevention Control and Countermeasures by University of Alaska FairbanksAtlantic Training, LLC.
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety ManagementShirazeh arghami
 
Mechanical Integrity.pdf
Mechanical Integrity.pdfMechanical Integrity.pdf
Mechanical Integrity.pdfaashir14
 
Safety awareness training program
Safety awareness training programSafety awareness training program
Safety awareness training programNoel Tan
 
HEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRYHEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRYAlex TX
 
Process Safety Management Fundamentals.pptx
Process Safety Management Fundamentals.pptxProcess Safety Management Fundamentals.pptx
Process Safety Management Fundamentals.pptxImtiazHussain312057
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY damomech92
 
Process Safety
Process SafetyProcess Safety
Process SafetyConsultivo
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Emergency spill control drill
Emergency spill control drillEmergency spill control drill
Emergency spill control drillSami Ullah
 
Offshore disasters
Offshore disastersOffshore disasters
Offshore disastersAhmed Taha
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARDPersonal Secret
 
Hazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh RajputHazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh RajputGaurav Singh Rajput
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)TheSafetyGuru
 

Mais procurados (20)

Process safety managment
Process safety managmentProcess safety managment
Process safety managment
 
Conducting Hot Work Operations
Conducting Hot Work OperationsConducting Hot Work Operations
Conducting Hot Work Operations
 
Spill Prevention Control and Countermeasures by University of Alaska Fairbanks
Spill Prevention Control and Countermeasures by University of Alaska FairbanksSpill Prevention Control and Countermeasures by University of Alaska Fairbanks
Spill Prevention Control and Countermeasures by University of Alaska Fairbanks
 
Elements of Process Safety Management
Elements of Process Safety ManagementElements of Process Safety Management
Elements of Process Safety Management
 
Mechanical Integrity.pdf
Mechanical Integrity.pdfMechanical Integrity.pdf
Mechanical Integrity.pdf
 
Safety awareness training program
Safety awareness training programSafety awareness training program
Safety awareness training program
 
HEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRYHEALT & SAFETY IN THE OIL & GAS INDUSTRY
HEALT & SAFETY IN THE OIL & GAS INDUSTRY
 
Process Safety Management Fundamentals.pptx
Process Safety Management Fundamentals.pptxProcess Safety Management Fundamentals.pptx
Process Safety Management Fundamentals.pptx
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY HAZOP AND OPERABILITY STUDY
HAZOP AND OPERABILITY STUDY
 
Process Safety
Process SafetyProcess Safety
Process Safety
 
Storage Tank Safety
Storage Tank SafetyStorage Tank Safety
Storage Tank Safety
 
Piper alpha disaster 1988
Piper alpha disaster 1988Piper alpha disaster 1988
Piper alpha disaster 1988
 
Line of fire safety
Line of fire safetyLine of fire safety
Line of fire safety
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
Emergency spill control drill
Emergency spill control drillEmergency spill control drill
Emergency spill control drill
 
Offshore disasters
Offshore disastersOffshore disasters
Offshore disasters
 
Process safety ADNOC STANDARD
Process safety ADNOC STANDARDProcess safety ADNOC STANDARD
Process safety ADNOC STANDARD
 
Hazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh RajputHazard and Operability Study (HAZOP) | Gaurav Singh Rajput
Hazard and Operability Study (HAZOP) | Gaurav Singh Rajput
 
Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)Prestartup Safety Review (PSSR)
Prestartup Safety Review (PSSR)
 

Semelhante a Hazid &amp; hazops

Hazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsHazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsJohn Kingsley
 
HAZOP ppt for chambal urea -1.pptx
HAZOP ppt for chambal urea -1.pptxHAZOP ppt for chambal urea -1.pptx
HAZOP ppt for chambal urea -1.pptxvidhyasagarverma
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputGaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputGaurav Singh Rajput
 
HAZOP I Hazard and operability study I Risk Assessment I Gaurav Singh Rajput
HAZOP I Hazard and operability study I Risk Assessment I Gaurav Singh RajputHAZOP I Hazard and operability study I Risk Assessment I Gaurav Singh Rajput
HAZOP I Hazard and operability study I Risk Assessment I Gaurav Singh RajputGaurav Singh Rajput
 
1675091151425_Process Management Risk.pptx
1675091151425_Process Management Risk.pptx1675091151425_Process Management Risk.pptx
1675091151425_Process Management Risk.pptxZerayacobTeklearegay
 
How to Ensure Safety and Efficiency in Stormwater Sampling
How to Ensure Safety and Efficiency in Stormwater SamplingHow to Ensure Safety and Efficiency in Stormwater Sampling
How to Ensure Safety and Efficiency in Stormwater SamplingTriumvirate Environmental
 
industrial safety and hazar
industrial safety and hazarindustrial safety and hazar
industrial safety and hazarmannukumar24
 
Root Cause Analysis .pdf
Root Cause Analysis .pdfRoot Cause Analysis .pdf
Root Cause Analysis .pdfssuser089410
 
Seminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptxSeminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptxMoonJ3
 
Unit-III Safety in process.pptx
Unit-III Safety in process.pptxUnit-III Safety in process.pptx
Unit-III Safety in process.pptxTYPPEOnlineLecture
 
HAZOP Module.pptx
HAZOP Module.pptxHAZOP Module.pptx
HAZOP Module.pptxakaash13
 
HAZOP (Hazard & Operability) Study.pdf
HAZOP (Hazard & Operability) Study.pdfHAZOP (Hazard & Operability) Study.pdf
HAZOP (Hazard & Operability) Study.pdfiFluidsEngineering1
 
Unit v11 proactive maintenance analysis
Unit v11 proactive maintenance analysisUnit v11 proactive maintenance analysis
Unit v11 proactive maintenance analysisCharlton Inao
 
Asset Integrity Management for purpose-built FPSOs and subsea system facilities
Asset Integrity Management for purpose-built FPSOs and subsea system facilitiesAsset Integrity Management for purpose-built FPSOs and subsea system facilities
Asset Integrity Management for purpose-built FPSOs and subsea system facilitiesAdvisian
 

Semelhante a Hazid &amp; hazops (20)

Hazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluidsHazop Fundamentals Online Training iFluids
Hazop Fundamentals Online Training iFluids
 
HAZOP.pptx
HAZOP.pptxHAZOP.pptx
HAZOP.pptx
 
HAZOP ppt for chambal urea -1.pptx
HAZOP ppt for chambal urea -1.pptxHAZOP ppt for chambal urea -1.pptx
HAZOP ppt for chambal urea -1.pptx
 
hazopanalysis-.pdf
hazopanalysis-.pdfhazopanalysis-.pdf
hazopanalysis-.pdf
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 
HAZOP I Hazard and operability study I Risk Assessment I Gaurav Singh Rajput
HAZOP I Hazard and operability study I Risk Assessment I Gaurav Singh RajputHAZOP I Hazard and operability study I Risk Assessment I Gaurav Singh Rajput
HAZOP I Hazard and operability study I Risk Assessment I Gaurav Singh Rajput
 
Hazop analysis
Hazop analysisHazop analysis
Hazop analysis
 
1675091151425_Process Management Risk.pptx
1675091151425_Process Management Risk.pptx1675091151425_Process Management Risk.pptx
1675091151425_Process Management Risk.pptx
 
How to Ensure Safety and Efficiency in Stormwater Sampling
How to Ensure Safety and Efficiency in Stormwater SamplingHow to Ensure Safety and Efficiency in Stormwater Sampling
How to Ensure Safety and Efficiency in Stormwater Sampling
 
industrial safety and hazar
industrial safety and hazarindustrial safety and hazar
industrial safety and hazar
 
Root Cause Analysis .pdf
Root Cause Analysis .pdfRoot Cause Analysis .pdf
Root Cause Analysis .pdf
 
Root Cause Analysis.pdf
Root Cause Analysis.pdfRoot Cause Analysis.pdf
Root Cause Analysis.pdf
 
Seminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptxSeminar- Process Safety Management_.pptx
Seminar- Process Safety Management_.pptx
 
Unit-III Safety in process.pptx
Unit-III Safety in process.pptxUnit-III Safety in process.pptx
Unit-III Safety in process.pptx
 
HAZOP Module.pptx
HAZOP Module.pptxHAZOP Module.pptx
HAZOP Module.pptx
 
HAZOP (Hazard & Operability) Study.pdf
HAZOP (Hazard & Operability) Study.pdfHAZOP (Hazard & Operability) Study.pdf
HAZOP (Hazard & Operability) Study.pdf
 
2.pptx
2.pptx2.pptx
2.pptx
 
Unit v11 proactive maintenance analysis
Unit v11 proactive maintenance analysisUnit v11 proactive maintenance analysis
Unit v11 proactive maintenance analysis
 
Asset Integrity Management for purpose-built FPSOs and subsea system facilities
Asset Integrity Management for purpose-built FPSOs and subsea system facilitiesAsset Integrity Management for purpose-built FPSOs and subsea system facilities
Asset Integrity Management for purpose-built FPSOs and subsea system facilities
 

Último

Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 

Último (20)

Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 

Hazid &amp; hazops

  • 1.
  • 2.  Hazard Identification merupakan suatu study yang bertujuan untuk melakukan identifikasi potential hazards dengan sumber dari external facilities yang mempengaruhi fasilitas atau hazard dengan sumber dari internal fasilitas yang berpengaruh ke environmental, community atau surrounding area.  Review difokuskan pada PFD, P&ID dan Plot Plan dari fasilitas. 2IJK & team
  • 3.  Sejumlah metode untuk melaksanakan identifikasi hazard telah dikembangkan.  Overview terhadap hazard identification telah diberikan dalam: ◦ Chemical Industries Association (CIA) Guide to Hazard and Operability Studies (CIHSC, 1977/3) (the CIA Hazop Study Guide) ◦ Guidelines for Hazard Evaluatuion Procedures (CCPS, 1985/1, 1992/9) (the CCPS Hazard Evaluation Guidelines) ◦ A Manual of Hazard and Operability Studies (Knowlton, 1992) (the Chemetics Hazard Study Manual).  Hazard Identification sering disebut juga dengan Process Hazard Analysis (PHA) 3IJK & team
  • 4.  What if? Analysis  Checklist  What-If/Checklist  Event tree and fault tree analysis  Preliminary hazard analysis  Coarse hazard studies  Hazard and operability studies  Failure modes, effects and criticality analysis  dll 4IJK & team
  • 6.  HAZOPS stands for HAZard and Operability Study.  HAZOPS merupakan suatu metode untuk mengidentifikasi bahaya dan operability masalah dalam proses desain.  Ini adalah teknik sistematis yang diaplikasikan secara bertahap ke bagian kecil dari proses desain sampai semua bagian desain. 6IJK & team
  • 7. A Process System Hazard Analysis technique that common to be used to identify potential of an operational deviation that may occur, its cause, its consequences, identify the existing safeguards, then produce a recommendation for action item to be accomplished when existing safeguard found to be insufficient. 7IJK & team
  • 8. 1. Exploratory Phase identification of basic hazard and assessment of suitability of possible sites. 2. Flowsheet Phase identification and assessment of significant hazard. 3. Detailed Design – HAZOP 4. Construction a check that decisions made in earlier studies have been implemented 5. Commissioning final inspection 6. Post-commissioning safety audit and review of modifications 8IJK & team
  • 9. Project Phase Safety Activities Design Construction and Instalation Commissioning & Start Up Operation PHA / HAZID / HAZOPS • Contractor Assessment • Safety Audit & Inspection • Punch List Review •Pre-Start Up Review •Training •Handover Procedure • Management of Change • Incident Investigation • Safety Audit and Inspection 9IJK & team
  • 11.  Tahap Design ◦ Preliminary HAZOPS ◦ Full HAZOPS  Tahap Modifikasi ◦ Mini HAZOPS 11IJK & team
  • 12. External and Environmental Hazards Hazard Type Guideword Expanders Natural Hazards Extreme Weather Temperature extremes; wave; wind; dust; flooding; sandstorm; ice; blizzards Lightning Seismic Activity Erosion Ground slide; coastal Subsidence Ground structure; foundation; reservoir depletion Environmental Impact Discharges to Air Flaring; venting; fugitive emissions; energy efficiency Discharges to Water Drainage; water quality; waste disposal options Discharges to Soil Drainage; chemical spillage; waste disposal options Location and Layout Previous land use; vulnerable fauna and flora; visual impact; local population; area minimization External & 3rd Party Hazards Sabotage Internal & external security threats Terrorist Activity Riots; civil disturbance; strikes; military action; political unrest Third Party Activities Farming; fishing; local industry Helicopter/Aircraft Crash 12IJK & team
  • 13. Facility Hazards Hazard Type Guideword Expanders Process Hazards Process Releases - Unignited Gas clouds; gas detection; emergency response Process releases - Ignited Fire; explosion; heat; smoke; fire detection; emergency response Process releases - toxic H2S detection; emergency response Flaring Heat; ignition source; location Venting Discharge to atmosphere; location; dispersion Draining Sampling Operator error Accommodation and Non-Process Area Hazards Non Process Fires Control room; accommodation building Smoke/Gas Ingress Ingress to safe areas; HVAC shutdown Stacking and Storage 13IJK & team
  • 14. Health Hazards Hazard Type Guideword Expanders Health Hazards Disease Hazards Endemic diseases; infection; contaminated water; social e.g. HIV Working Environment Physical Drinking water; lighting; noise Temperature Extreme hot/cold; ventilation, guarding Atmospheres Exhaust fumes; confined spaces 14IJK & team
  • 15. What if Consequence / hazard Recommendations Coolant pump to reaktor fails Runaway condition in reactor explosion/fatality •Provide accurate temperature monitoring in reactor •Employ backup pump/high temperature alarm •Relieve reactor pressure in reactor through automatic control to stop reactions •Provide automatic shut off of ethylene flow Coolant temperature to jacket is high 15IJK & team
  • 16.  Preliminary Hazard Analysis merupakan metode identifikasi bahaya pada tahap awal dari desain proses.  Guidelines: 1) Bahan baku, produk antara dan produk akhir. 2) Plant equipment 3) Fasilitas 4) Safety equipment 5) Interfaces between system components 6) Lingkungan 7) Operasi (maintenance, testing, dll) 16IJK & team
  • 17. Hazard Cause Major Effects Corrective/Preventive Measures Flamable gas release CH4 storage tank (line) leak/rupture (fuel for the furnace) Potential for injuries and fatalities due to fire or explosion • Provide warning system • Minimize on-site storage • Develop procedure for tank inspection • Develop emergency response system • Provide gas monitoring system … 17IJK & team
  • 18.  Coarse Hazard Studies disusun dengan kompilasi dari 2 daftar berikut: 1) Daftar hazard dan nuisance (sesuatu yang mengganggu) dari sifat material 2) Potensi hazard dan nuisance dari materi lain yang berhubungan.  Guide words  Fire  Explosion  Toxicity  Corrosion  Smell  Effluent 18IJK & team
  • 19. HAZOPS (Hazard & Operability Study) A systematic review of the design & operation of a system to identify the potential for accidental releases of hazardous material, or operability problems.(Potential accident scenarios) Based on the premise that :  A hazard is not realized if the process is always operated within its design intent  Creative input of a team is better than of an individual  Item can be applied, independent of process technologies 19IJK & team
  • 20.  Drawing board  Construction  Only during process modifications  Whenever accident occurs 20IJK & team
  • 21. • Intentions: How the Process/Facility operations are expected to occur • Deviation: Departures from the design intention • Causes: Ways deviations might occur • Consequences: Results of the deviations • Safeguards: Provision for reducing the frequency of causes or the severity of consequences. • Action: Suggestions for procedural changes, design changes or further study (do not debate the relative merit of suggested actions, but record them all) 21IJK & team
  • 22. Node • A node is a location on a process diagram (usually P&ID’s) at which process parameters are investigated for deviations. • Nodes are points where the process parameters have an identified design intent. • Nodes are usually pipe sections or vessels. • Plant components (e.g..., pumps, compressors, exchangers) are found within nodes 22IJK & team
  • 23. P& ID C lassification N o.O f E quipem nets N o.O f Pipe lines N o.of Interlocks Sim ple 1 to 4 1 to 9 <2 Standard 5 to 6 10 to 20 2 to 4 C om plex >6 >30 >10 V ery C om plex >6 >30 >10 23IJK & team
  • 24. Parameter A parameter is an aspect of the process that describes it physically, chemically, or in terms of what is happening. Parameters are usually classified as specific or general. • Specific parameters are those that describe aspects of the process. • General parameters are those that describe aspects of design intent remaining after the specific parameters have been removed 24IJK & team
  • 25. Common Parameters Specific General Flow Addition, Reaction Temperature Maintenance, Testing Pressure Instrumentation Composition Sampling, Relief Phase Corrosion / Erosion Level Safety 25IJK & team
  • 26. Guide Words Guide words are simple words or phases used to qualify or quantify the intention and associated parameters in order to discover deviations. There are seven standard guide words. 26IJK & team
  • 27. • Process Hazard • Previous Accident/Incident Record • Engineering System for Risk Mitigation. • Administrative Control • Potential of discrepancy / failure of Engineering System and Administrative Control • Facility and Equipment Site and Ergonomic. • Potential for Human Error 27IJK & team
  • 28. • Drawing: P&ID, Engineering Drawing, Electrical Diagram, etc. • Process Safety Information (Material Safety Data Sheet) • Design Specification. • Operating Procedure, Operating Condition • Site Situation and Condition of Facility • Accident/Incident Record • People record who doing the job • HAZOPS Guideword 28IJK & team
  • 29. Nothing but RECOMMENDATION • Safety • Operability • Action • Comment 29IJK & team
  • 30. 1. Material Hazard: Toxicity, Exposure Limit (TLV-TWA, TLV-STEL, TLV C) 2. Process Technology 3. Equipment Design 4. Accident Report 5. Previous Hazop Report 30IJK & team
  • 32. Relief Contamination Properties of Chemicals Rupture/Leak Ignition Service Failure Abnormal Operation Sampling Maintenance Corrosion/Erosion Equipment Siting Human Factors 32IJK & team
  • 33. In addition to the seven standard guide words, the following auxiliary guide words may be considered : - How ? How is the step to be accomplished ? Are adequate facilities provided to allow the operator to perform the step as specified ? - Why ? Is the step or operation really needed ? - When ? Is timing of the step or operation important ? - Where ? Is it important where the step is performed ? And so on 33IJK & team
  • 34. HAZOP - Hazard Vs Operability Relative Percentage : Operability to Hazard Status Operability Hazards of Plant Problem Identified Identified (%) (%) New 60 40 Existing 70 30 34IJK & team
  • 35. An interdisciplinary team of experts systematically examines every part of the process or facility to discover how deviations from the design intentions can occurs 35IJK & team
  • 36. Team Composition Team Leader Team Members Engineers Scientists Operators Project Engineering Process Control Corrosion 36IJK & team
  • 37.  Step-1 : Selection of a Study Node to be Review  Step-2 : Selection of a Process Deviation or a Review Check Item  Step-3 : Identification and Analysis of Consequence and Causes  Step-4 : Evaluation of Existing Safeguards  Step-5 : Investigation of Recommendation  Step-6 : Recording of the Review Results  Step-7 : Repeat of the Review 37IJK & team