5. PROCEDURE
Designing
Approval
Demarcation and layout at site
Execution plan (Calculation and purchase of
materials)
Construction and Installation
6. PLANNING HIGH TENSION WIRE
PARK
Labor(10),Plumber (1), Mason (1)- will be mustered through existing resources
Water point & quantity of water available (checked)
Irrigation (purchase of pipes- estimate being worked out by engineer branch)
Benches (50, under construction at lahore-1 week time)
Bhul soil & soil ammendments- 10 trolleys will be purchased amounting Rs
20,000(Purchase -& Filling)
Cement, gravel, sand, boulders- to be estimated in collaboration with
Engineering Dept (Purchase)
Concrete slabs, bricks- to be estimated in collaboration with Engineering Dept
(purchase, installation, marking)
Plants/ shrubs - will be purchased in March 1st week amounting Rs 50,000
(remaining required will be prepared in nursery this year).
Flowers pansy, petunia, antrhinum will be transplanted in mid feb and will last
till May(available)
Digging for plantation- after completion of Hardscape area
Purchase brush cutters (5) tentative cost (100000)
7. On going maintenance operations
Trees and shrubs pruning
Trees basins
Mowing
Palms pruning
Pesticide applications
Termiticide applications
Edging
Weeding
Production of seasonal flowers
Wild growth trimming
Making of flowers beds
Limestone application
Irrigation
Nursery and tunnel farm operations
Rotary and disc tractor operations