What is a Stream?
… a body of water with a current,
confined within a bed and
streambanks

Synonyms: bayou, beck, branch,
brook, burn, creek, crick, kill, lick,
rill, river, rivulet, run, slough, syke

A stream is:
• conduit in the water cycle
• critical habitat
• connected to a watershed
Fluvial Geomorphology:
The study of landforms and fluvial processes
Fluvial processes are associated with flowing
   water, including sediment
   erosion, transport, deposition
Fluvial Forms
•   Bar
•   Channel
•   Confluence
•   Cutoff channel
•   Delta
•   Floodplain
•   Gorge
•   Gully
•   Meander
•   Oxbow lake
•   Pool
•   Riffle
•   Stream
•   Valley
•   Waterfall
•   Watershed
Meandering Stream: Alluvial Forms
Riffle     Point Bar
          (deposition)




Glide              Run
          Pool
Bankfull
Bankfull Stage
      “corresponds to the discharge at which channel maintenance
      is the most effective, that is, the discharge at which moving
      sediment, forming or removing bars, forming or changing
      bends and meanders, and generally doing work results in the
      average morphologic characteristics” (Dunne and Leopold,1978)




Stream Corridor Restoration: Principles, Processes, and Practices. 1998. Federal Interagency Stream Restoration Working Group.
Stream Ecosystems
• Channel (bed & banks)
• Floodplain
• Water & Sediment
• Plants & Animals




                          Photo Credit: Eve Brantley, Auburn University
Stream Functions & Services
1. Transport water
2. Transport sediment
3. Habitat (aquatic & terrestrial)
4. Recreation & aesthetics
5. Safe Water Supply
Effects of Urbanization on Streams (US EPA)
Urban Stream Syndrome (USS)
•   Response to watershed changes
•   Loss of natural functions & values
•   Causes problems locally & downstream
•   Requires systematic assessment & treatment
Symptoms of USS
• Erosion & incision
• Water quality decline
• Habitat loss
• Ecosystem degradation
• Flooding
• Land loss
• Infrastructure damage
• Recreation impaired
• Aesthetics impaired
• Economic loss
Urban Stream: Incision & bank erosion
Causes of USS
• Watershed impervious
• Channelization
• Impoundments
• Diversions
• Floodplain filling
• Pollution discharges
• Sedimentation
• Stormwater runoff
• Utilities & culverts
• Buffer loss
• Neglect & Ignorance
Urban Disturbances to Hydrologic Cycle




                       University of Central Florida
Hydrograph Changes Due to Urbanization


                      Higher Peak Flow
      Urban           More Runoff Volume
                      Flashier Response
                      Lower Baseflow



                                Rural
Runoff: more
Infiltration: less
Flooding: more
Baseflow: less
Constraints: Utilities, Road, Bridges, Culverts
What Makes a Stream Healthy?
1. Bed stability & diversity
2. Sediment transport balance
3. In-stream habitat & flow diversity
4. Bank stability (native plant roots)
5. Riparian buffer (streamside forest)
6. Active floodplain
7. Healthy watershed
1. Bed Stability & Diversity
• Appropriate size sediments to
  resist shear stress
• Riffle/Pool sequences in
  alluvial streams
• Step/Pool sequences in high-
  gradient streams




                               Photo Credit: Eve Brantley, Auburn University
Riffles
•   Steep slope
•   High velocity & shear stress
•   Large substrate
•   High porosity & groundwater
    exchange



Pools
•   Flat slope
•   Low velocity & shear stress
•   Small substrate
•   Scour during high flow
Problems: Bed Stability & Diversity
• Headcut and excess scour
• Plane bed – filling of pools
• Armoring
2. Sediment Transport Balance
• Minor erosion & deposition
• Alluvial bars and benches
• Sufficient stream power to avoid aggradation
Problems: Sediment Transport Balance
• Excess stream power – eroding bed
• Insufficient stream power – aggradation
Streams convey water and sediment




Lane’s Balance (Lane, 1955)




                              Channel Evolution Model (Schumm, 1984)
3. In-stream Habitat
   & Flow Diversity

Macrohabitats: riffles,
 runs, pools, glides,
 steps, side channels,
 scour holes

Microhabitats: roots, leaf
  packs, wood, rocks,
  plants, hyporheic zone
Problems: In-stream Habitats
• Uniform flow – lack of diversity
• Lack of wood, leaves, roots
• Water quality – DO, nutrients, toxics
4. Bank Stability
• Dense native
  plant roots
• Low banks with
  low stress
Problems: Bank Stability
•   Loss of vegetation
• High, steep banks – channelization
5. Riparian Buffer (Streamside Forest)
• Diverse native plants
• Food and shade
Problems: Riparian Buffer
• Mowers and moo’ers
• Invasive plants
• Armoring and impervious surfaces
6. Active Floodplain
• Regular (every year) flooding to relieve stress
• Riparian wetlands
• Stormwater retention & treatment
Problems: Active Floodplain
•   Channel incision
• Floodplain fill and encroachment
7. Healthy Watershed
• Stormwater management
• Wastewater management
• Upstream sediment control
Problems: Healthy Watershed
• Stormwater energy and volume
• Point and nonpoint source pollution
• Erosion and sediment
Ecosystem Restoration:

“activities that initiate or accelerate the recovery of
ecosystem health, integrity, and sustainability”
(SER, 2004)
Planning a Stream Project:

•   Goals? Stability, Habitat, Recreation?
•   Constraints? Access, Land Availability, Utilities?
•   Feasibility? Will it Work?
•   Constructability? Equipment, Materials, Time/$?
Case Study: Long Creek (1995-2005)
•   Dairy Farm: Fencing, Bank Stabilization, Planting




                                                  10 years later
Roaring River, Stone Mt State Park (2000-10)
•   Trout Stream: Channel Realignment, Structures, Planting




                                                10 years later
Rocky Branch, NCSU Campus
•   Urban Stream: Channel Realignment, Structures, Planting
Restoration Components
 1. Channel morphology

 2. Floodplain structure

 3. Hydrologic & hydraulic
    analysis

 4. In-stream structures

 5. Habitats & vegetation

 6. Site & watershed conditions

 7. Monitoring, maintenance, educ
    ation
1. Channel Morphology
  • Dimension (baseflow, bankfull, flood flows)
  • Pattern (meandering, straight, braided)
  • Profile (bedform – riffle, run, pool, glide, step)




          Photo Credits: Darrell Westmoreland, North State Environmental, Inc.


2005               South Fork Mitchell River                                     2006
2011   South Fork Mitchell River
2011   South Fork Mitchell River
High-quality
“reference”
streams serve as
design templates
Bankfull Width, Wbkf = 9.3 ft; Bankfull Area, Abkf = 13.9 ft2
Mean Depth, dbkf = Abkf / Wbkf = 13.9 / 9.3 = 1.5 ft
Width to Depth Ratio, W/d = Wbkf / dbkf = 9.3 / 1.5 = 6.2
Morphologic Stream Classification Systems
• Schumm (1977)
  – Alluvial channels
  – Meandering, straight, braided
  – Type related to channel stability & sediment transport
• Montgomery & Buffington (1993)
  – Alluvial, colluvial, bedrock channels
  – Channel response related to sediment inputs
  – 6 classes of alluvial channels: cascade, step-
    pool, plane-bed, riffle-pool, regime, and braided
• Rosgen (1994)
  www.wildlandhydrology.com
Rosgen Classification of Natural Rivers
• Based on physical
  characteristics (empirical)
• Requires field
  measurements
• Requires bankfull
  dimensions




                                www.wildlandhydrology.com
www.wildlandhydrology.com
G4 Eastern NC
2000          2001




       2003   2003
2. Floodplain Structure
• Regular (every year) flooding to relieve stress
• Floodwater retention & riparian wetlands
• Stormwater discharge retention & treatment
Entrenchment Ratio
   ER = Wfpa / Wbkf
    Wfpa = Width of Flood Prone Area measured at the
    elevation twice bankfull max depth above thalweg
    Wbkf = Width of Bankfull Channel
                         Wfpa


                         Bankfull
  2 x dmbkf
                                       dmbkf
above thalweg

                                Wbkf
Priority 1: Raise channel to existing valley
     and construct new meandering channel

                                      ER = 15; W/d = 12




Rain will come during and
immediately following construction!

2006              Town Creek Tributary             2007
2008   Town Creek Tributary
Priority 1:
       lift channel




           Incised
           Stream



 Priority 2 & 3:
lower floodplain

Stream Corridor Restoration: Principles, Processes, and Practices.
1998. Federal Interagency Stream Restoration Working Group.
Priority 2: Excavate lower floodplain and
    construct new meandering channel

                                 ER = 6; W/d = 11




2008              White Slough               2010
Entrenchment Ratio = Wfpa / Wbkf = 90/15 = 6




                White Slough            2010
Priority 2: Excavate lower floodplain and
     construct new meandering channel




2004           NCSU Rocky Branch              2005
Rocky Branch Phase II Reach 2:
  Priority 2 (floodplain excavation, C channel)
 Entrenchment Ratio = Wfpa / Wbkf = 90/20 = 4.5




Flood water flows onto floodplain
several times each year
Priority 3: Excavate narrow floodplain
    benches in confined systems

                            ER = 2.2; W/d = 12




2005          NCSU Rocky Branch           2006
Rocky Branch Phase II Reach 1:
Priority 3 (floodplain excavation, Bc channel)
Entrenchment Ratio = Wfpa / Wbkf = 40/20 = 2
2008   NCSU Rocky Branch
Priority 3: Excavate narrow floodplain
    benches in confined systems

                             ER = 1.6; W/d = 15




2009          Little Shades Creek         2010
Entrenchment Ratio = Wfpa / Wbkf = 60/38 = 1.6
Little Shades Creek   2010
In-Stream Structures (Logs & Rocks)
•   Streambank protection
•   Habitat enhancement (pools, aeration, cover)
•   Grade control
•   Sediment transport
Structure Criteria:
•   Natural materials
•   Habitats & passage for aquatic organisms
•   Natural sediment transport (alluvial systems)

                             Do you like these?
Boulder J-Hook Vane
Runaway Truck Ramp
Boulder J-Hook Vane
• 3-5 % arm slopes
• 20-25 degree arm angles
• Boulder footers & non-woven geotextile
• 0.5 ft drops over j-hook inverts
Boulder Vane
                   20-25 degree angles
                   3-5 % arm slopes




20-25 degrees


3-5 % arm slopes
Boulder
J-Hook Vane
Log Vane
• 2-4 % arm slopes
• 20 degree arm angles
• Sealed with woven geotextile & backer logs
Log J-Hook Vane
• Direct flow away from bank around bend
• Grade control and scour pool
• Brush toe buried under log vane
• Backer logs & geotextile
Log J-Hook Vane
• Hook boulders control grade
• Footer boulders and geotextile
• Boulder sills
Log J-Hook Vane
• Hook boulders control grade
• Footer boulders and geotextile
• Boulder sills
Log J-Hook Vane
Multiple Log
              Vanes
              Saugahatchee
              Creek

2007




       2008
Multiple Log
                    Vanes
                    Saugahatchee
                    Creek

2009 January




    2009 July
                Photo Credit: Dan Ballard, Town of Auburn
Multiple Log Vanes: Saugahatchee Creek




                       Photo Credit: Dan Ballard, Town of Auburn
Boulder Cross Vane
Cross Vane
• Direct flow in new channel alignment
• Grade control and scour pool
• Footer boulders & geotextile
Cross Vane (logs embedded)

• Undercut bed 2 ft and backfill with
  gravel, cobble, boulders, wood
• Cut thalweg 0.5 ft deep
Double-Drop Boulder Cross Vane




          Photo Credit: Darrell Westmoreland, North State Environmental, Inc.
Double-Drop Boulder Cross Vane
Offset Boulder Cross Vane at a Bridge
Boulder W-Vane
Boulder Double Wing Deflector
Constructed Riffle
1st Order Streambed Transplant
• Substrate transfer from old channel to new channel
Constructed Riffle
• Undercut bed 2 ft and backfill with
  gravel, cobble, boulders, wood
• Cut thalweg 0.5 ft deep
Constructed Riffle
• Undercut bed 2 ft and backfill with
  gravel, cobble, boulders, wood
• Cut thalweg 0.5 ft deep
Riffles with
Bouder/Log Steps
Wood
•   Food sources
•   Cover
•   Scour pools
•   Flow diversity
Brush Toe
• Layers of logs and brush under water in pools
• Live cuttings above water (silky dogwood, elderberry)
• Matting, seed, transplanted alders on top
Brush Toe
• Layers of logs and brush under water in pools
• Live cuttings above water (silky dogwood, elderberry)
• Matting, seed, transplanted alders on top
Summary: Plan for Success
1. Plan for floods -- immediately & often
2. Plan for dry weather
3. Plan for vegetation maintenance
4. Understand constraints
5. Expect the Unexpected

Mais conteúdo relacionado

Mais procurados

Chapter 7 dams and reservoirs
Chapter 7 dams and reservoirsChapter 7 dams and reservoirs
Chapter 7 dams and reservoirs
Mohammed Salahat
 
L10 Hard Engineering Flood Solutions
L10 Hard Engineering Flood SolutionsL10 Hard Engineering Flood Solutions
L10 Hard Engineering Flood Solutions
tudorgeog
 

Mais procurados (20)

Planning of irrigation system
Planning of irrigation systemPlanning of irrigation system
Planning of irrigation system
 
CH-2.pptx
CH-2.pptxCH-2.pptx
CH-2.pptx
 
Rational and scs method for peak discharge
Rational and scs method for peak dischargeRational and scs method for peak discharge
Rational and scs method for peak discharge
 
Chapter 7 dams and reservoirs
Chapter 7 dams and reservoirsChapter 7 dams and reservoirs
Chapter 7 dams and reservoirs
 
7 routing
7 routing7 routing
7 routing
 
How to do integrated watershed management in the world
How to do integrated watershed management in the worldHow to do integrated watershed management in the world
How to do integrated watershed management in the world
 
T1w6 flood management
T1w6   flood managementT1w6   flood management
T1w6 flood management
 
River engineering
River engineeringRiver engineering
River engineering
 
Dam Breach Analysis.pptx
Dam Breach Analysis.pptxDam Breach Analysis.pptx
Dam Breach Analysis.pptx
 
Drop structure lecture 1
Drop structure lecture 1Drop structure lecture 1
Drop structure lecture 1
 
L10 Hard Engineering Flood Solutions
L10 Hard Engineering Flood SolutionsL10 Hard Engineering Flood Solutions
L10 Hard Engineering Flood Solutions
 
lecture Design of Alluvial Canal -.pdf
lecture Design of Alluvial Canal -.pdflecture Design of Alluvial Canal -.pdf
lecture Design of Alluvial Canal -.pdf
 
Subcatchment management plan
Subcatchment management planSubcatchment management plan
Subcatchment management plan
 
Chapter two
Chapter twoChapter two
Chapter two
 
Dam Breach Analysis: Large and Small
Dam Breach Analysis: Large and SmallDam Breach Analysis: Large and Small
Dam Breach Analysis: Large and Small
 
Water resource engineering project list 3
Water resource engineering project list  3Water resource engineering project list  3
Water resource engineering project list 3
 
Lined or non erodible design channel study
Lined or non erodible design channel studyLined or non erodible design channel study
Lined or non erodible design channel study
 
Integrated water resource management
Integrated water resource managementIntegrated water resource management
Integrated water resource management
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation Works
 
Flood modeling of river godavari using hec ras
Flood modeling of river godavari using hec rasFlood modeling of river godavari using hec ras
Flood modeling of river godavari using hec ras
 

Destaque (7)

Rc201 day 3 jennings 10
Rc201 day 3 jennings 10Rc201 day 3 jennings 10
Rc201 day 3 jennings 10
 
UnconVentional Wisdom and the Effects of Dams on Downstream Coarse Sediment S...
UnconVentional Wisdom and the Effects of Dams on Downstream Coarse Sediment S...UnconVentional Wisdom and the Effects of Dams on Downstream Coarse Sediment S...
UnconVentional Wisdom and the Effects of Dams on Downstream Coarse Sediment S...
 
Rc101 day3
Rc101 day3Rc101 day3
Rc101 day3
 
Rc401 construction jennings e&s
Rc401 construction jennings e&sRc401 construction jennings e&s
Rc401 construction jennings e&s
 
Meandering Rivers
Meandering RiversMeandering Rivers
Meandering Rivers
 
Meander Formation
Meander FormationMeander Formation
Meander Formation
 
River landforms in the upper course
River landforms in the upper course River landforms in the upper course
River landforms in the upper course
 

Semelhante a Jennings tdec stream small

Rc401 construction jennings intro
Rc401 construction jennings introRc401 construction jennings intro
Rc401 construction jennings intro
Greg Jennings
 
Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12
Christopher Hayes
 
NRCS Mohawk Watershed Symposium
NRCS Mohawk Watershed SymposiumNRCS Mohawk Watershed Symposium
NRCS Mohawk Watershed Symposium
donmeltz
 
Rc101 Day 1 Jennings 10
Rc101 Day 1 Jennings 10Rc101 Day 1 Jennings 10
Rc101 Day 1 Jennings 10
Greg Jennings
 
Rc201 day 1 jennings 10
Rc201 day 1 jennings 10Rc201 day 1 jennings 10
Rc201 day 1 jennings 10
Greg Jennings
 
The State of Our Groundwater
The State of Our GroundwaterThe State of Our Groundwater
The State of Our Groundwater
Steve Oberle
 
Making the case for valley scale restoration
Making the case for valley scale restorationMaking the case for valley scale restoration
Making the case for valley scale restoration
Leif Embertson
 
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Sweet Water
 
EVS 311 Central TX Hydro RKM
EVS 311 Central TX Hydro RKMEVS 311 Central TX Hydro RKM
EVS 311 Central TX Hydro RKM
Ryan McKeeman
 
Keynote: Science in Large Scale River Restoration - Dahm
Keynote: Science in Large Scale River Restoration - DahmKeynote: Science in Large Scale River Restoration - Dahm
Keynote: Science in Large Scale River Restoration - Dahm
Willamette River Initiative
 

Semelhante a Jennings tdec stream small (20)

Rc101 day1
Rc101 day1Rc101 day1
Rc101 day1
 
July 30-350-Barry Southerland
July 30-350-Barry SoutherlandJuly 30-350-Barry Southerland
July 30-350-Barry Southerland
 
Rc401 construction jennings intro
Rc401 construction jennings introRc401 construction jennings intro
Rc401 construction jennings intro
 
Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12Flood resilient presentation 05.16.12
Flood resilient presentation 05.16.12
 
Massachusetts' Rivers Response to Tropical Storm Irene
Massachusetts' Rivers Response to Tropical Storm IreneMassachusetts' Rivers Response to Tropical Storm Irene
Massachusetts' Rivers Response to Tropical Storm Irene
 
10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC10. Restoring the River Camac - Mary-Liz Walshe, DCC
10. Restoring the River Camac - Mary-Liz Walshe, DCC
 
NRCS Mohawk Watershed Symposium
NRCS Mohawk Watershed SymposiumNRCS Mohawk Watershed Symposium
NRCS Mohawk Watershed Symposium
 
Processes and Landforms of the Willamette River and Floodplain
Processes and Landforms of the Willamette River and FloodplainProcesses and Landforms of the Willamette River and Floodplain
Processes and Landforms of the Willamette River and Floodplain
 
Rc101 Day 1 Jennings 10
Rc101 Day 1 Jennings 10Rc101 Day 1 Jennings 10
Rc101 Day 1 Jennings 10
 
Rc201 day 1 jennings 10
Rc201 day 1 jennings 10Rc201 day 1 jennings 10
Rc201 day 1 jennings 10
 
Upstream -Downstream Delaware River Watershed
Upstream -Downstream Delaware River WatershedUpstream -Downstream Delaware River Watershed
Upstream -Downstream Delaware River Watershed
 
Modifying River-Floodplain Systems: A Historical and Ecological Perspective
Modifying River-Floodplain Systems: A Historical and Ecological PerspectiveModifying River-Floodplain Systems: A Historical and Ecological Perspective
Modifying River-Floodplain Systems: A Historical and Ecological Perspective
 
The State of Our Groundwater
The State of Our GroundwaterThe State of Our Groundwater
The State of Our Groundwater
 
Making the case for valley scale restoration
Making the case for valley scale restorationMaking the case for valley scale restoration
Making the case for valley scale restoration
 
Abbe Sess10 101309
Abbe Sess10 101309Abbe Sess10 101309
Abbe Sess10 101309
 
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
Clean Rivers, Clean Lake 8 -- New Projects on KK and Menomonee Rivers -- Dave...
 
EVS 311 Central TX Hydro RKM
EVS 311 Central TX Hydro RKMEVS 311 Central TX Hydro RKM
EVS 311 Central TX Hydro RKM
 
Duke Bitsko - Alewife Stormwater Wetland
Duke Bitsko - Alewife Stormwater WetlandDuke Bitsko - Alewife Stormwater Wetland
Duke Bitsko - Alewife Stormwater Wetland
 
ESA 324 - Dams Project
ESA 324 - Dams ProjectESA 324 - Dams Project
ESA 324 - Dams Project
 
Keynote: Science in Large Scale River Restoration - Dahm
Keynote: Science in Large Scale River Restoration - DahmKeynote: Science in Large Scale River Restoration - Dahm
Keynote: Science in Large Scale River Restoration - Dahm
 

Mais de Greg Jennings

Mais de Greg Jennings (6)

Asce nc jennings
Asce nc jenningsAsce nc jennings
Asce nc jennings
 
Rc101 day2
Rc101 day2Rc101 day2
Rc101 day2
 
Kramer land use
Kramer land useKramer land use
Kramer land use
 
Rc101 Day 2 Jennings 10
Rc101 Day 2 Jennings 10Rc101 Day 2 Jennings 10
Rc101 Day 2 Jennings 10
 
Rc101 Day 3 Jennings 10
Rc101 Day 3 Jennings 10Rc101 Day 3 Jennings 10
Rc101 Day 3 Jennings 10
 
Jess Roberts Farewell
Jess Roberts FarewellJess Roberts Farewell
Jess Roberts Farewell
 

Último

IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Enterprise Knowledge
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
vu2urc
 

Último (20)

Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 

Jennings tdec stream small

  • 1. Understanding and Restoring Streams Greg Jennings, PhD, PE Professor, Biological & Agricultural Engineering North Carolina State University jennings@ncsu.edu
  • 2. What is a Stream? … a body of water with a current, confined within a bed and streambanks Synonyms: bayou, beck, branch, brook, burn, creek, crick, kill, lick, rill, river, rivulet, run, slough, syke A stream is: • conduit in the water cycle • critical habitat • connected to a watershed
  • 3. Fluvial Geomorphology: The study of landforms and fluvial processes Fluvial processes are associated with flowing water, including sediment erosion, transport, deposition
  • 4. Fluvial Forms • Bar • Channel • Confluence • Cutoff channel • Delta • Floodplain • Gorge • Gully • Meander • Oxbow lake • Pool • Riffle • Stream • Valley • Waterfall • Watershed
  • 5. Meandering Stream: Alluvial Forms Riffle Point Bar (deposition) Glide Run Pool
  • 7. Bankfull Stage “corresponds to the discharge at which channel maintenance is the most effective, that is, the discharge at which moving sediment, forming or removing bars, forming or changing bends and meanders, and generally doing work results in the average morphologic characteristics” (Dunne and Leopold,1978) Stream Corridor Restoration: Principles, Processes, and Practices. 1998. Federal Interagency Stream Restoration Working Group.
  • 8.
  • 9. Stream Ecosystems • Channel (bed & banks) • Floodplain • Water & Sediment • Plants & Animals Photo Credit: Eve Brantley, Auburn University
  • 10. Stream Functions & Services 1. Transport water 2. Transport sediment 3. Habitat (aquatic & terrestrial) 4. Recreation & aesthetics 5. Safe Water Supply
  • 11. Effects of Urbanization on Streams (US EPA)
  • 12. Urban Stream Syndrome (USS) • Response to watershed changes • Loss of natural functions & values • Causes problems locally & downstream • Requires systematic assessment & treatment
  • 13. Symptoms of USS • Erosion & incision • Water quality decline • Habitat loss • Ecosystem degradation • Flooding • Land loss • Infrastructure damage • Recreation impaired • Aesthetics impaired • Economic loss
  • 14. Urban Stream: Incision & bank erosion
  • 15. Causes of USS • Watershed impervious • Channelization • Impoundments • Diversions • Floodplain filling • Pollution discharges • Sedimentation • Stormwater runoff • Utilities & culverts • Buffer loss • Neglect & Ignorance
  • 16. Urban Disturbances to Hydrologic Cycle University of Central Florida
  • 17. Hydrograph Changes Due to Urbanization Higher Peak Flow Urban More Runoff Volume Flashier Response Lower Baseflow Rural
  • 19. Constraints: Utilities, Road, Bridges, Culverts
  • 20. What Makes a Stream Healthy? 1. Bed stability & diversity 2. Sediment transport balance 3. In-stream habitat & flow diversity 4. Bank stability (native plant roots) 5. Riparian buffer (streamside forest) 6. Active floodplain 7. Healthy watershed
  • 21. 1. Bed Stability & Diversity • Appropriate size sediments to resist shear stress • Riffle/Pool sequences in alluvial streams • Step/Pool sequences in high- gradient streams Photo Credit: Eve Brantley, Auburn University
  • 22. Riffles • Steep slope • High velocity & shear stress • Large substrate • High porosity & groundwater exchange Pools • Flat slope • Low velocity & shear stress • Small substrate • Scour during high flow
  • 23. Problems: Bed Stability & Diversity • Headcut and excess scour • Plane bed – filling of pools • Armoring
  • 24. 2. Sediment Transport Balance • Minor erosion & deposition • Alluvial bars and benches • Sufficient stream power to avoid aggradation
  • 25. Problems: Sediment Transport Balance • Excess stream power – eroding bed • Insufficient stream power – aggradation
  • 26. Streams convey water and sediment Lane’s Balance (Lane, 1955) Channel Evolution Model (Schumm, 1984)
  • 27. 3. In-stream Habitat & Flow Diversity Macrohabitats: riffles, runs, pools, glides, steps, side channels, scour holes Microhabitats: roots, leaf packs, wood, rocks, plants, hyporheic zone
  • 28. Problems: In-stream Habitats • Uniform flow – lack of diversity • Lack of wood, leaves, roots • Water quality – DO, nutrients, toxics
  • 29. 4. Bank Stability • Dense native plant roots • Low banks with low stress
  • 30. Problems: Bank Stability • Loss of vegetation • High, steep banks – channelization
  • 31. 5. Riparian Buffer (Streamside Forest) • Diverse native plants • Food and shade
  • 32. Problems: Riparian Buffer • Mowers and moo’ers • Invasive plants • Armoring and impervious surfaces
  • 33. 6. Active Floodplain • Regular (every year) flooding to relieve stress • Riparian wetlands • Stormwater retention & treatment
  • 34. Problems: Active Floodplain • Channel incision • Floodplain fill and encroachment
  • 35. 7. Healthy Watershed • Stormwater management • Wastewater management • Upstream sediment control
  • 36. Problems: Healthy Watershed • Stormwater energy and volume • Point and nonpoint source pollution • Erosion and sediment
  • 37. Ecosystem Restoration: “activities that initiate or accelerate the recovery of ecosystem health, integrity, and sustainability” (SER, 2004)
  • 38. Planning a Stream Project: • Goals? Stability, Habitat, Recreation? • Constraints? Access, Land Availability, Utilities? • Feasibility? Will it Work? • Constructability? Equipment, Materials, Time/$?
  • 39. Case Study: Long Creek (1995-2005) • Dairy Farm: Fencing, Bank Stabilization, Planting 10 years later
  • 40. Roaring River, Stone Mt State Park (2000-10) • Trout Stream: Channel Realignment, Structures, Planting 10 years later
  • 41. Rocky Branch, NCSU Campus • Urban Stream: Channel Realignment, Structures, Planting
  • 42. Restoration Components 1. Channel morphology 2. Floodplain structure 3. Hydrologic & hydraulic analysis 4. In-stream structures 5. Habitats & vegetation 6. Site & watershed conditions 7. Monitoring, maintenance, educ ation
  • 43. 1. Channel Morphology • Dimension (baseflow, bankfull, flood flows) • Pattern (meandering, straight, braided) • Profile (bedform – riffle, run, pool, glide, step) Photo Credits: Darrell Westmoreland, North State Environmental, Inc. 2005 South Fork Mitchell River 2006
  • 44. 2011 South Fork Mitchell River
  • 45. 2011 South Fork Mitchell River
  • 47. Bankfull Width, Wbkf = 9.3 ft; Bankfull Area, Abkf = 13.9 ft2 Mean Depth, dbkf = Abkf / Wbkf = 13.9 / 9.3 = 1.5 ft Width to Depth Ratio, W/d = Wbkf / dbkf = 9.3 / 1.5 = 6.2
  • 48. Morphologic Stream Classification Systems • Schumm (1977) – Alluvial channels – Meandering, straight, braided – Type related to channel stability & sediment transport • Montgomery & Buffington (1993) – Alluvial, colluvial, bedrock channels – Channel response related to sediment inputs – 6 classes of alluvial channels: cascade, step- pool, plane-bed, riffle-pool, regime, and braided • Rosgen (1994) www.wildlandhydrology.com
  • 49. Rosgen Classification of Natural Rivers • Based on physical characteristics (empirical) • Requires field measurements • Requires bankfull dimensions www.wildlandhydrology.com
  • 52. 2000 2001 2003 2003
  • 53.
  • 54. 2. Floodplain Structure • Regular (every year) flooding to relieve stress • Floodwater retention & riparian wetlands • Stormwater discharge retention & treatment
  • 55. Entrenchment Ratio ER = Wfpa / Wbkf Wfpa = Width of Flood Prone Area measured at the elevation twice bankfull max depth above thalweg Wbkf = Width of Bankfull Channel Wfpa Bankfull 2 x dmbkf dmbkf above thalweg Wbkf
  • 56. Priority 1: Raise channel to existing valley and construct new meandering channel ER = 15; W/d = 12 Rain will come during and immediately following construction! 2006 Town Creek Tributary 2007
  • 57. 2008 Town Creek Tributary
  • 58. Priority 1: lift channel Incised Stream Priority 2 & 3: lower floodplain Stream Corridor Restoration: Principles, Processes, and Practices. 1998. Federal Interagency Stream Restoration Working Group.
  • 59. Priority 2: Excavate lower floodplain and construct new meandering channel ER = 6; W/d = 11 2008 White Slough 2010
  • 60. Entrenchment Ratio = Wfpa / Wbkf = 90/15 = 6 White Slough 2010
  • 61. Priority 2: Excavate lower floodplain and construct new meandering channel 2004 NCSU Rocky Branch 2005
  • 62. Rocky Branch Phase II Reach 2: Priority 2 (floodplain excavation, C channel) Entrenchment Ratio = Wfpa / Wbkf = 90/20 = 4.5 Flood water flows onto floodplain several times each year
  • 63. Priority 3: Excavate narrow floodplain benches in confined systems ER = 2.2; W/d = 12 2005 NCSU Rocky Branch 2006
  • 64. Rocky Branch Phase II Reach 1: Priority 3 (floodplain excavation, Bc channel) Entrenchment Ratio = Wfpa / Wbkf = 40/20 = 2
  • 65. 2008 NCSU Rocky Branch
  • 66. Priority 3: Excavate narrow floodplain benches in confined systems ER = 1.6; W/d = 15 2009 Little Shades Creek 2010
  • 67. Entrenchment Ratio = Wfpa / Wbkf = 60/38 = 1.6
  • 69. In-Stream Structures (Logs & Rocks) • Streambank protection • Habitat enhancement (pools, aeration, cover) • Grade control • Sediment transport
  • 70. Structure Criteria: • Natural materials • Habitats & passage for aquatic organisms • Natural sediment transport (alluvial systems) Do you like these?
  • 73. Boulder J-Hook Vane • 3-5 % arm slopes • 20-25 degree arm angles • Boulder footers & non-woven geotextile • 0.5 ft drops over j-hook inverts
  • 74. Boulder Vane 20-25 degree angles 3-5 % arm slopes 20-25 degrees 3-5 % arm slopes
  • 76. Log Vane • 2-4 % arm slopes • 20 degree arm angles • Sealed with woven geotextile & backer logs
  • 77. Log J-Hook Vane • Direct flow away from bank around bend • Grade control and scour pool • Brush toe buried under log vane • Backer logs & geotextile
  • 78. Log J-Hook Vane • Hook boulders control grade • Footer boulders and geotextile • Boulder sills
  • 79. Log J-Hook Vane • Hook boulders control grade • Footer boulders and geotextile • Boulder sills
  • 81. Multiple Log Vanes Saugahatchee Creek 2007 2008
  • 82. Multiple Log Vanes Saugahatchee Creek 2009 January 2009 July Photo Credit: Dan Ballard, Town of Auburn
  • 83. Multiple Log Vanes: Saugahatchee Creek Photo Credit: Dan Ballard, Town of Auburn
  • 85. Cross Vane • Direct flow in new channel alignment • Grade control and scour pool • Footer boulders & geotextile
  • 86. Cross Vane (logs embedded) • Undercut bed 2 ft and backfill with gravel, cobble, boulders, wood • Cut thalweg 0.5 ft deep
  • 87. Double-Drop Boulder Cross Vane Photo Credit: Darrell Westmoreland, North State Environmental, Inc.
  • 89. Offset Boulder Cross Vane at a Bridge
  • 91. Boulder Double Wing Deflector
  • 93. 1st Order Streambed Transplant • Substrate transfer from old channel to new channel
  • 94.
  • 95. Constructed Riffle • Undercut bed 2 ft and backfill with gravel, cobble, boulders, wood • Cut thalweg 0.5 ft deep
  • 96. Constructed Riffle • Undercut bed 2 ft and backfill with gravel, cobble, boulders, wood • Cut thalweg 0.5 ft deep
  • 98. Wood • Food sources • Cover • Scour pools • Flow diversity
  • 99. Brush Toe • Layers of logs and brush under water in pools • Live cuttings above water (silky dogwood, elderberry) • Matting, seed, transplanted alders on top
  • 100. Brush Toe • Layers of logs and brush under water in pools • Live cuttings above water (silky dogwood, elderberry) • Matting, seed, transplanted alders on top
  • 101. Summary: Plan for Success 1. Plan for floods -- immediately & often 2. Plan for dry weather 3. Plan for vegetation maintenance 4. Understand constraints 5. Expect the Unexpected