A Multi-Team, Full-Cycle, Product-Oriented
Scrum Simulation with LEGO Bricks
the Small & Medium Business Edition
Can be adapted to teach other iteration-based Agile frameworks.
Original paper published in Feb, 2009
Authored by Alexey Krivitsky
Current version 2.0, Oct 2011
info@lego4scrum.com
This work is distributed under a
Creative Commons Attribution 3.0 Unported License
1
PREFACE
WHY A LEGO SIMULATION?
ACKNOWLEDGEMENTS AND APPRECIATIONS
CURRENT VARIATION
LICENSING OF THIS WORK
WEB COMMUNITY AND TRANSLATION PROJECT
THE GAME
DURATION, GROUP SIZE, MATERIALS
ROLES
Product Owner
Scrum Masters
Team Members
Testers – Optional Role
Allow No Observers
WHAT TO OBSERVE
Behaviors
Communication Styles
Broken Process
STAGES OF THE GAME
PRE-GAME: Organizing Teams
PRE-GAME: Project Chartering
PRE-GAME: Building the Backlog
PRE-GAME: Estimating
The fastest technique – swimlane sizing
Planning poker with multiple teams
GAME: Sprint Planning
GAME: Sprinting
GAME: Reviewing
GAME: Release Cycle
POST-GAME: Debriefing
VARIATIONS
Adding Fluctuations
Enterprise Scrum
Have your variation? Let us know
THANK YOU!
2
PREFACE
WHY A LEGO SIMULATION?
Over the last couple of years I have co-trained a dozen Scrum classes both certified
and not. All of those classes had different simulation sessions, but I’ve always felt like
there should be better ones.
Below I am listing the features that a minimal game on Scrum should have, in my
opinion.
1. OPEN BACKLOGS THAT TRIGGER IDEATING
over DETAILED INSTRUCTIONS TO FOLLOW
We want to start a game with an open backlog - an invitation for collaboration
between a customer and teams.
Backlogs can be prepared by trainers, but they should not be closed and precise
like “do this, then do that.” This will sound like “good old” command and control.
We want to teach and demonstrate a totally different kind of relationship between
customers and teams.
2. MINDFUL PRODUCT DEVELOPMENT
over A SERIES OF TASKS TO ACCOMPLISH
We need to teach product development, not micromanagement on a task level.
Hence, backlogs or instructions should not be composed of a series of tasks, rather
they should be a vision of a product – a big thing teams are to build.
3. TEAMS COLLABORATING TOWARD COMMON SUCCESS
over COMPETITION FOR SCORE
The game should be scalable to suit classes of 20 people or more. Which, of course,
will result in splitting the group into teams. This should be used as a chance to
practice skills of inter-team collaboration.
This needs to be done deliberately, as without specific instructions, it is natural for the
teams to start competing.
4. USEFUL METRICS TO ASSESS BENEFITS OF AGILE
over FIGURES THE TRAINERS ASKED TO COLLECT
3
All metrics trainers ask participants to collect need to have an obvious benefit for the
teams, as the games need to teach them to own their process.
5. CONTINUOUS IMPROVEMENTS
over WINNING OR LOSING THE GAME WITH ONE TRY
The game should be designed so that the teams get multiple tries at it. Each session
generates lessons learned and helps them to figure out better processes.
ACKNOWLEDGEMENTS AND APPRECIATIONS
In early 2009 Mykola Gurov who helped me realize the potential of LEGOs as
an “API”1 for product development simulations.
Later that year, I created an early version of the game called “LEGO for extended
SCRUM simulation” after discussing ideas with William Wake, Jurgen De Smet, Yves
Hanoulle, and Xavier Quesada Allue.
Since the first publication on Scrum Alliance website, I have received dozens of
emails with appreciation for this work. Now I’d like to use this chance, in turn, to
thank everyone who has contacted me to share their ideas and experiences with
running the simulations:
Gerry Kirk, Tim Yevgrashyn, Steve Rogalsky, Andriy Yevtushenko, Geoff Watts,
Laurent Godé, Radu Davidescu, Martine Devos, Jo Newcombe Cook, Jakob
Frandsen Martin Muntzing, Ola Ellnestam, Dusan Kocurek, Danny (Danko)
Kovatch, Gustavo Quiroz, Jukka Lindström, Eduardo Bregaida, and Nathaniel
Cadwell.
Special thanks to Robin Dymond and Sergey Dmitriev for letting me run this game in
their Certified Scrum Master classes.
CURRENT VARIATION
Since the first paper was published in 2009, dozens of trainers have tried this game.
The current, improved, version of the simulation described in this paper reflects
feedback and observations made.
LICENSING OF THIS WORK
1Not sure what “API” means? Check out http://en.wikipedia.org/wiki/Application_programming_interface
4
The current work is distributed under a
Creative Commons Attribution 3.0 Unported License
This license lets others distribute, remix, tweak, and build upon your work, even commercially, as long
as they credit you for the original creation. This is the most accommodating of licenses offered.
Recommended for maximum dissemination and use of licensed materials.
WEB COMMUNITY AND TRANSLATION PROJECT
We decided to create a place where people interested in teaching Scrum with LEGOs
could come and collaborate.
www.lego4scrum.com - Join the community, and help us spread the word.
One of the ongoing projects of the community is to translate this paper into world
languages. Check out the current status, and consider helping us out. We really
appreciate your effort.
THE GAME
DURATION, GROUP SIZE, MATERIALS
It is proven that the game can be adapted to fit the particular needs of trainers and
serve different sizes of audience.
A “standard” game is described below, but you are encouraged to adopt it to fit your
particular needs.
Timing: 100-120 minutes
● 100 minutes - when using fast team estimation techniques
● 120 minutes - when using planning poker or other estimation tools
Group Size: 4-25 people
● Ideal is 2-3 teams of 4-6 people (gives 8-18 people)
● Can be extended with Scrum Masters
LEGO Boxes: a LEGO box for a team of 4-6 people
● I use “Basic Brick Set #6177”2
● It takes four boxes for 20 people
Stationary: standard training package
● Stickers, flip chart paper sheets, markers
● Planning poker cards (or hand-made ones)
2 Visit the online LEGO store: http://shop.lego.com/en-US/LEGO-Basic-Bricks-Deluxe-6177
5
Room Setup: a table for each team of 4-6 people
● Extra space (a table or a floor spot) for the integrated product is handy
ROLES
Product Owner
As the trainer, I play the role of the Product Owner."
The goal is to illustrate how Product Owners behave, what they typically expect and
require, which team behaviors they appreciate and which they don't.
Scrum Masters
This game can be played without dedicated Scrum Masters.
Sometimes I do have Scrum Masters in the game by inviting co-instructors. Another
option would be to ask the team to select Scrum Masters.
By having skillful facilitators playing Scrum Masters - who are constantly focused on
the process, and a dedicated trainer - playing the business role, makes the game much
more natural and an easy-going activity.
Team Members
Other students are team members.
Testers – Optional Role
You can have testers on the teams. Their main responsibility would be to help their
teams document agreements on requirements and designs in order to perform
acceptance testing.
The downside, which I've experienced, is that rather than building LEGOs, the testers
were observing quality. As the goal of such games is to learn by doing, I think it
makes sense to encourage everyone to get engaged in the building process.
Allow No Observers
This game is so much fun playing that the observers will be losing more than they are
gaining – my opinion. Otherwise, I’d love to hear good stories on this from you.
WHAT TO OBSERVE
Behaviors
6
From my observations, certain behaviors people demonstrate in games are projections
of working habits. And under stress people will tend to fall back to their natural
behaviors.
This game is deliberately designed to be stressful, so it might expose bad habits that
could harm real Agile adoptions. My goal as a trainer is to point them out to the
group and turn them into learning points and warnings to keep an eye on.
Communication Styles
Watch out for: “managers”, “dictators”, “loud voices,” and similar projections. This is
a fruitful area for debriefing and topics for personal coaching.
Broken Process
Keep an eye on parts of the process the teams don’t do well.
For example, during requirements discussion the teams might not ask as many
clarifying questions as they need.
Most likely they also have this issue, or will have this issue, in the particular area of a
real project. Making this visible on debrief is one way of handling this.
STAGES OF THE GAME
The simulation has natural three parts: pre-game, game, and post-game or debrief.
Pre-game
● Organizing teams
● Defining the Process
● Project chartering
● Building the Backlog
● Estimating
Game
● Sprint Planning
● Sprinting
● Sprint Reviewing
Post-game
● Debriefing
PRE-GAME: Organizing Teams
Will take 5 minutes.
There is no reason why this activity cannot be a part of the game – a learning process.
7
Striving to demonstrate self-organization in action I usually ask the team to self-
organize in groups of 4-6 people and allocate working space
This is a good warm-up activity since it might require moving tables around and
cleaning them up.
PRE-GAME: Project Chartering
Will take 10 minutes. You are 5 minutes into the game now.
As a trainer who is playing the Product Owner I need to communicate the following
messages:
1. All teams will be building a single product – they are not competing, rather they
work for the same vendor.
2. The product is a CITY with certain features.
3. The main building elements are LEGOs, though any other material can be used
in addition.
4. I am the main decision maker of the product – it is my city.
5. I will be involved in the development process by being available to answer
questions and provide feedback.
Running this activity as collaborative chartering might be a good way.
My goal is to make sure the teams practice Scrum by building “products” with LEGO
bricks. Now the tricky question is how to combine the two roles: a Product Owner
(who is not owning the process) and a class trainer (who has an interest in running it
with Scrum).
There are several ways I’ve tried doing this:
1. Changing hats – explain Scrum rules to the team
I explicitly state whether I am currently a Product Owner or a trainer so that
people are not confused.
2. Playing a newbie Product Owner – let the team sell you Scrum
Most often I play a Product Owner who doesn’t know much about Agile or
Scrum and after presenting my vision of a city I ask the team to help us design
out the process that suits.
Personally, I like this second approach more since it helps amplify learning from the
class and let students practice articulating Agile values.
PRE-GAME: Building the Backlog
Will take 15 minutes. You are 15 minutes in the game now.
8
Once you have sketched a charter and agreed on the process, it is the time to share
the features of the city.
I usually do this by showing the showing a team pre-prepared set of sticky notes
hanging on a sheet of flip-chart paper.
Usually it includes the following items:
● One storey building (several of these, one per sticky note)
● Two storey building (several)
● Shop
● School
● Church
● Hospital
● Kindergarten
● Bus stop
● Intersection (can be drawn)
● Park (can be drawn)
● River (can be drawn)
● Bridge
Some of the items can be drawn on flip chart paper, and then the LEGOs are on top.
Here you can get creative and build something more entertaining rather than a simple
city.
Once we’ve played this game with a start-up team, so we were building a “silicon
village”.
It obviously had some other items to be built, like a presentation hall with an iPad
(presenting a screen), a bunch of open co-working areas in the city, a secure building
for web servers, and a monument to a hero entrepreneur (a fancy monument on rails).
That was fun!
While presenting the backlog I briefly explain what I think each of the items may look
like. And I try to postpone discussions until later.
PRE-GAME: Estimating
Will take up to 20 minutes. You are 30 minutes into the game now.
Estimations. The hardest part, somehow.
I may want to:
1. Drop estimates (as agile gurus would recommend)
2. Do it faster and simpler
9
3. Spend a bit of time on practicing planning poker
RT @RonJeffries: "Every year there is new estimation technique. The real Agile
approach would be to throw estimations out." - @agilemanager [YES!]
Based on how much time we have I can decide to do the simplest technique or
poker.
The fastest technique – swimlane sizing
I’ve learned this term from www.theagilepirate.net. Apparently, I do it in a less
sophisticated manner.
Check out a sketch below.
Based on the triangulation concept3 and swimlane sizing4 we simply arrange columns
to mark different story sizes (1 2 3 5 8 13 if you prefer Fibonacci - a little taste of
science is always good), and ask students to drag stories to columns that represent
story size. We do it in groups or altogether.
This activity can also be run silently.
Figure 1: Swimlanes for group estimations
3 Triangulation and other concepts of Agile estimating and planning, by Mike Cohn http://
www.mountaingoatsoftware.com/presentations/85-an-introduction-to-agile-estimating-and-planning
4 Swimlane Sizing – Complete & Fast Backlog Estimation
http://theagilepirate.net/archives/109
10
If a group is big enough that it cannot fit in front of the board, I ask each team to
send a pair. When these pairs are done, the next come, until everyone got a chance to
touch the board.
Once done, I ask the group whether this is “good enough” to start with and whether
they would like to do some real work now.
Planning poker with multiple teams
Running planning poker5 with multiple teams requires agreeing on sample size as a
whole group, firstly.
Agreeing on size is simple: pick up an item which is small and simple enough, but not
trivial and assign it “2”. Usually everyone agrees to have all one-stored buildings as
twos.
Another approach to selecting sample stories to do t-shirt size estimates6 (XS, S, M, L,
XL) and then mark all S-sized stories as “2” and continue with the poker.
I’d like to share hints that help me make multi-team planning poker sessions work:
● Organize swimlanes wall (see sketches above)
● Ask teams to pull stories one by one for estimation.
● Ask teams to attach details to each story when they get clarifications from
Product Owner (as it may be another team building the item).
● Actively encourage and appreciate team members asking clarifying questions
which help define size.
● Once estimated, a story needs to be put on the wall, so that other teams can
benefit from the new information.
● When done ask people to come up to the wall and make a sanity check with
necessary changes (in my experience changes are rarely needed).
If the teams do not know much about planning poker, it is worth doing a test run
so that you can observe them using the technique correctly. I usually ask teams to
guesstimate:
“How much does a pint of Guinness cost in the U.K?”
5 Planning Poker is found by James Grening in 2002 and popularized by Mike Cohn:
http://en.wikipedia.org/wiki/Planning_poker
6 T-shirt sizing
http://blogs.msdn.com/b/oldnewthing/archive/2009/05/12/9605143.aspx
11
This implies asking questions on points to be used, place and date of buying it – acts
as a good warm-up for estimating stories.
Interestingly, both techniques: swimlanes and planning poker provide the necessary
precision for release planning as it has proven by hundreds of release burn-down
charts.
GAME: Sprint Planning
You are 50 minutes into the game now.
(And zero things are built! Does it prove enough that estimations are wasteful?)
Now when the stories are estimated, you have to move them from the Swimlanes
Wall back to the Backlog.
Since we would like to make sprint planning highly visible, we are building a special
Planning Wall that accumulates all teams’ plans for all sprints in the game.
Figure 2: Multi-team Planning Wall, before planning sprint #1
12
Figure 3: Multi-team Planning Wall, inside sprint #2
We time-box Sprint planning activity to three minutes asking teams to pull stories into
their team’s sprint boxes.
When all is done, we ask whether the teams are uncomfortable enough with their
plans to give it a try!
GAME: Sprinting
Will take 7 minutes.
We prefer 7-minutes sprints, as this time is quite enough to build several items with
several people collaborating and without too much polishing it.
To make sure students are stressed enough we show a big visible stopwatch from a
notebook or an overhead projector:
13
Figure 4: A stopwatch from www.online-stopwatch.com - timers of different forms, can be
used offline.
GAME: Reviewing
Will take 5 minutes.
When the time is up, I make sure students really stop building things and start
demanding: “where is my city? ”
As it has been observed, it is only after the second sprint teams start doing continuous
deployments of stories to the demonstration environment (a flip chart paper). So
in most cases after the first sprint, no one has ever thought on how to organize the
demonstration. Sounds similar to the real life?
I always got comments on debrief that I am playing the kindest Product Owner ever
seen. Still, in most cases nothing is accepted after the first sprint, because after I am
shown the buildings, I “come to realize”:
● I like symmetry.
● “All of the same color” actually meant “solid colors of buildings, but different
for each.”
● Buildings are either too small, too big, or too diverse.
● Windows of different floors are not lined up.
● <make up your own reasoning>
Unfinished items are brought back to the Backlog from the Planning Wall.
Remaining work can be re-estimated, although we rarely update estimates.
Once stories are accepted, the Release Burndown chart is updated by a PO, who
makes a clear and loud announcement that the release has to be done in three sprints
and now it looks like we will not be able to accomplish all stories.
14
A few minutes can be spent on retrospecting on the topic of “how can we make it
better the next sprint?”.
GAME: Release Cycle
Without too much time wasted on discussing failures of the first sprint, which is
almost always a disaster, we jump back to Sprint Planning.
I’ve learned it takes an average three sprints to build 80% of the backlog with
anticipated quality, so the full cycle usually looks like this:
1. Sprint #1
a. Planning – 3 minutes
b. Sprinting – 7 minutes
c. Review – 5 minutes
2. Sprint #2
a. Planning – 3 minutes
b. Sprinting – 7 minutes
c. Review – 5 minutes
3. Sprint #3
a. Planning – 3 minutes
b. Sprinting – 7 minutes
c. Review – 5 minutes
Subtotal: 45 minutes
Since the preparations took us about 1 hour (from chartering to estimated backlog),
sprints took 45 minutes, it will take about 15 minutes for debrief, the full game
takes 120 minutes.
Once practiced and with help from co-trainers, who play Scrum Master, it can be
done a bit faster.
POST-GAME: Debriefing
It is probably wise to take a short break once the last sprint is reviewed and before
jumping into debrief to calm down emotions and have a short rest (Did I tell you the
game is designed to be exhaustive? Not only for the teams...)
When gathered back in a circle, we run a facilitated discussion around the following
open-ended questions:
● What did students observe?
● How did it feel being on a Scrum team?
● How did the short iterations go?
15
● How accurate were the estimations (provided the Release Burndown is there)
● What would we have done differently from the beginning, if we had another
chance to play the game?
● What was the job of the Product Owner?
● How did it feel after the first sprint when almost all items required re-work?
● What did the Scrum Masters do?
● How will your strategy change, if you know the Product Owner is unavailable
during sprints?
● How did inter-team communication go? Were there any dependencies? How
were they resolved?
● What did students learn?
VARIATIONS
Adding Fluctuations
Good friends of mine (Askhat Urazbaev and Nikita Filippov) have designed a similar
game, which includes randomized fluctuations to the team size and complexity.
Simply, after sprint planning is done and just before sprint start, the teams throw dice
that either multiply story point estimates or make some team members gone “sick”
for the sprint while the team will have to keep the sprint plan.
The point this game makes is that team collaboration is essential for task balancing
during sprints, as things might go differently than was planned.
Enterprise Scrum
I was able to scale the simulation with LEGOs to engage 100 students playing in
12 teams that were building 4 cities simultaneously. It requires quite a few tons of
LEGOs but it seems to be a good way to demonstrate enterprise-level Scrum. This
deserves another article to cover all rules and settings.
Have your variation? Let us know
We would like to hear your stories, your variation to the simulation – please join us at
www.lego4scrum.com and email us your ideas at info@lego4scrum.com
16
THANK YOU!
Have playful projects!
Alexey Krivitsky
www.lego4scrum.com
17

Mais conteúdo relacionado

Mais procurados

Planning Poker
Planning PokerPlanning Poker
Planning Pokervineet
 
SAFe Lego Game for learning Scaled Agile Framework PI Planning
SAFe Lego Game for learning Scaled Agile Framework PI PlanningSAFe Lego Game for learning Scaled Agile Framework PI Planning
SAFe Lego Game for learning Scaled Agile Framework PI PlanningJoan Nwosu
 
Agile Games - Playful approaches to agile principles
Agile Games - Playful approaches to agile principlesAgile Games - Playful approaches to agile principles
Agile Games - Playful approaches to agile principlesRobert Misch
 
Scrum 101: Introduction to Scrum
Scrum 101: Introduction to ScrumScrum 101: Introduction to Scrum
Scrum 101: Introduction to ScrumArrielle Mali
 
Agile Team Working Agreements
Agile Team Working AgreementsAgile Team Working Agreements
Agile Team Working AgreementsPayton Consulting
 
Agile & SCRUM
Agile & SCRUMAgile & SCRUM
Agile & SCRUMejlp12
 
Henrik Kniberg: Agile at home
Henrik Kniberg: Agile at homeHenrik Kniberg: Agile at home
Henrik Kniberg: Agile at homeAgileee
 
Relative Estimation: Exercises & Illustrations
Relative Estimation: Exercises & IllustrationsRelative Estimation: Exercises & Illustrations
Relative Estimation: Exercises & IllustrationsDavid Hanson
 
Agile Resort Brochure Game July 2011
Agile Resort Brochure Game July 2011Agile Resort Brochure Game July 2011
Agile Resort Brochure Game July 2011Glenn Smith
 
The Daily Scrum (The Scrum Events)
The Daily Scrum (The Scrum Events)The Daily Scrum (The Scrum Events)
The Daily Scrum (The Scrum Events)George Psistakis
 
Scrum Introduction
Scrum IntroductionScrum Introduction
Scrum IntroductionJames Brett
 
Scrum In Ten Slides (v2.0) 2018
Scrum In Ten Slides (v2.0) 2018Scrum In Ten Slides (v2.0) 2018
Scrum In Ten Slides (v2.0) 2018pmengal
 
Scrum and the agile development process
Scrum and the agile development processScrum and the agile development process
Scrum and the agile development processjhericks
 
Backlog Refinement 101 & 202
Backlog Refinement 101 & 202Backlog Refinement 101 & 202
Backlog Refinement 101 & 202David Hanson
 
[HCM Scrum Breakfast] Agile estimation - Story points
[HCM Scrum Breakfast] Agile estimation - Story points[HCM Scrum Breakfast] Agile estimation - Story points
[HCM Scrum Breakfast] Agile estimation - Story pointsScrum Breakfast Vietnam
 

Mais procurados (20)

Scrum
ScrumScrum
Scrum
 
5 Whys of Scrum
5 Whys of Scrum5 Whys of Scrum
5 Whys of Scrum
 
Planning Poker
Planning PokerPlanning Poker
Planning Poker
 
SAFe Lego Game for learning Scaled Agile Framework PI Planning
SAFe Lego Game for learning Scaled Agile Framework PI PlanningSAFe Lego Game for learning Scaled Agile Framework PI Planning
SAFe Lego Game for learning Scaled Agile Framework PI Planning
 
Agile Games - Playful approaches to agile principles
Agile Games - Playful approaches to agile principlesAgile Games - Playful approaches to agile principles
Agile Games - Playful approaches to agile principles
 
Scrum 101: Introduction to Scrum
Scrum 101: Introduction to ScrumScrum 101: Introduction to Scrum
Scrum 101: Introduction to Scrum
 
Agile Team Working Agreements
Agile Team Working AgreementsAgile Team Working Agreements
Agile Team Working Agreements
 
Agile & SCRUM
Agile & SCRUMAgile & SCRUM
Agile & SCRUM
 
Henrik Kniberg: Agile at home
Henrik Kniberg: Agile at homeHenrik Kniberg: Agile at home
Henrik Kniberg: Agile at home
 
Relative Estimation: Exercises & Illustrations
Relative Estimation: Exercises & IllustrationsRelative Estimation: Exercises & Illustrations
Relative Estimation: Exercises & Illustrations
 
Agile Resort Brochure Game July 2011
Agile Resort Brochure Game July 2011Agile Resort Brochure Game July 2011
Agile Resort Brochure Game July 2011
 
The Daily Scrum (The Scrum Events)
The Daily Scrum (The Scrum Events)The Daily Scrum (The Scrum Events)
The Daily Scrum (The Scrum Events)
 
Scrum Introduction
Scrum IntroductionScrum Introduction
Scrum Introduction
 
2017 Scrum by Picture
2017 Scrum by Picture2017 Scrum by Picture
2017 Scrum by Picture
 
User Story Sizing using Agile Relative Estimation
User Story Sizing using Agile Relative EstimationUser Story Sizing using Agile Relative Estimation
User Story Sizing using Agile Relative Estimation
 
Scrum In Ten Slides (v2.0) 2018
Scrum In Ten Slides (v2.0) 2018Scrum In Ten Slides (v2.0) 2018
Scrum In Ten Slides (v2.0) 2018
 
Scrum and the agile development process
Scrum and the agile development processScrum and the agile development process
Scrum and the agile development process
 
Backlog Refinement 101 & 202
Backlog Refinement 101 & 202Backlog Refinement 101 & 202
Backlog Refinement 101 & 202
 
[HCM Scrum Breakfast] Agile estimation - Story points
[HCM Scrum Breakfast] Agile estimation - Story points[HCM Scrum Breakfast] Agile estimation - Story points
[HCM Scrum Breakfast] Agile estimation - Story points
 
SCRUM
SCRUMSCRUM
SCRUM
 

Semelhante a Scrum simulation-with-lego-bricks-v2.0

Lessons from the Trenches of Learning Game Design
Lessons from the Trenches of Learning Game DesignLessons from the Trenches of Learning Game Design
Lessons from the Trenches of Learning Game DesignSharon Boller
 
A Primer On Play: How to use Games for Learning and Results
A Primer On Play: How to use Games for Learning and ResultsA Primer On Play: How to use Games for Learning and Results
A Primer On Play: How to use Games for Learning and ResultsSharon Boller
 
Digital Learning Game Design: Lessons from the Trenches
Digital Learning Game Design: Lessons from the TrenchesDigital Learning Game Design: Lessons from the Trenches
Digital Learning Game Design: Lessons from the TrenchesSharon Boller
 
Boston games forum universal design lessons - dave bisceglia
Boston games forum   universal design lessons - dave biscegliaBoston games forum   universal design lessons - dave bisceglia
Boston games forum universal design lessons - dave biscegliaElizabeth Cormack
 
Play to Learn: Learning Games and Gamification that Get Results
Play to Learn: Learning Games and Gamification that Get ResultsPlay to Learn: Learning Games and Gamification that Get Results
Play to Learn: Learning Games and Gamification that Get ResultsHRDQ-U
 
Game Storming Overview- Big Design
Game Storming Overview- Big DesignGame Storming Overview- Big Design
Game Storming Overview- Big DesignTracey Kelly
 
Universal Design Lessons - Boston Games Forum
Universal Design Lessons - Boston Games ForumUniversal Design Lessons - Boston Games Forum
Universal Design Lessons - Boston Games ForumDave Bisceglia
 
LAFS SVI Level 3 - Game Design and Analysis
LAFS SVI Level 3 - Game Design and AnalysisLAFS SVI Level 3 - Game Design and Analysis
LAFS SVI Level 3 - Game Design and AnalysisDavid Mullich
 
Product Owner Challenge game
Product Owner Challenge game Product Owner Challenge game
Product Owner Challenge game Michael Tarnowski
 
Being an Agile Tester
Being an Agile TesterBeing an Agile Tester
Being an Agile Testerliorf
 
Global Game Jam Overview
Global Game Jam OverviewGlobal Game Jam Overview
Global Game Jam OverviewSusan Gold
 
How to develop a game
How to develop a game How to develop a game
How to develop a game Intersog
 
Developing a serious game to evaluate and train group decision making skills
Developing a serious game to evaluate and train group decision making skills Developing a serious game to evaluate and train group decision making skills
Developing a serious game to evaluate and train group decision making skills Lincoln Social Computing Research Centre
 
The-Stockless-Challenge-Participant-Briefing-Slides.pptx
The-Stockless-Challenge-Participant-Briefing-Slides.pptxThe-Stockless-Challenge-Participant-Briefing-Slides.pptx
The-Stockless-Challenge-Participant-Briefing-Slides.pptxSaqib Mansoor Ahmed
 
Play to Learn: Effective Learning Game Design
Play to Learn: Effective Learning Game DesignPlay to Learn: Effective Learning Game Design
Play to Learn: Effective Learning Game DesignSharon Boller
 
Designing games with kodu_game_lab_v1
Designing games with kodu_game_lab_v1Designing games with kodu_game_lab_v1
Designing games with kodu_game_lab_v1KerryJTurner
 
Continuous Improvement Tricks
Continuous Improvement TricksContinuous Improvement Tricks
Continuous Improvement TricksLitheSpeed
 
User Experience 6: Qualitative Methods, Playtesting and Interviews
User Experience 6: Qualitative Methods, Playtesting and InterviewsUser Experience 6: Qualitative Methods, Playtesting and Interviews
User Experience 6: Qualitative Methods, Playtesting and InterviewsMarc Miquel
 

Semelhante a Scrum simulation-with-lego-bricks-v2.0 (20)

Lessons from the Trenches of Learning Game Design
Lessons from the Trenches of Learning Game DesignLessons from the Trenches of Learning Game Design
Lessons from the Trenches of Learning Game Design
 
A Primer On Play: How to use Games for Learning and Results
A Primer On Play: How to use Games for Learning and ResultsA Primer On Play: How to use Games for Learning and Results
A Primer On Play: How to use Games for Learning and Results
 
Digital Learning Game Design: Lessons from the Trenches
Digital Learning Game Design: Lessons from the TrenchesDigital Learning Game Design: Lessons from the Trenches
Digital Learning Game Design: Lessons from the Trenches
 
Boston games forum universal design lessons - dave bisceglia
Boston games forum   universal design lessons - dave biscegliaBoston games forum   universal design lessons - dave bisceglia
Boston games forum universal design lessons - dave bisceglia
 
Play to Learn: Learning Games and Gamification that Get Results
Play to Learn: Learning Games and Gamification that Get ResultsPlay to Learn: Learning Games and Gamification that Get Results
Play to Learn: Learning Games and Gamification that Get Results
 
Creative Engineering 101
Creative Engineering 101Creative Engineering 101
Creative Engineering 101
 
Game Storming Overview- Big Design
Game Storming Overview- Big DesignGame Storming Overview- Big Design
Game Storming Overview- Big Design
 
Universal Design Lessons - Boston Games Forum
Universal Design Lessons - Boston Games ForumUniversal Design Lessons - Boston Games Forum
Universal Design Lessons - Boston Games Forum
 
LAFS SVI Level 3 - Game Design and Analysis
LAFS SVI Level 3 - Game Design and AnalysisLAFS SVI Level 3 - Game Design and Analysis
LAFS SVI Level 3 - Game Design and Analysis
 
Product Owner Challenge game
Product Owner Challenge game Product Owner Challenge game
Product Owner Challenge game
 
Being an Agile Tester
Being an Agile TesterBeing an Agile Tester
Being an Agile Tester
 
Global Game Jam Overview
Global Game Jam OverviewGlobal Game Jam Overview
Global Game Jam Overview
 
Gamification in Digital Marketing
Gamification in Digital MarketingGamification in Digital Marketing
Gamification in Digital Marketing
 
How to develop a game
How to develop a game How to develop a game
How to develop a game
 
Developing a serious game to evaluate and train group decision making skills
Developing a serious game to evaluate and train group decision making skills Developing a serious game to evaluate and train group decision making skills
Developing a serious game to evaluate and train group decision making skills
 
The-Stockless-Challenge-Participant-Briefing-Slides.pptx
The-Stockless-Challenge-Participant-Briefing-Slides.pptxThe-Stockless-Challenge-Participant-Briefing-Slides.pptx
The-Stockless-Challenge-Participant-Briefing-Slides.pptx
 
Play to Learn: Effective Learning Game Design
Play to Learn: Effective Learning Game DesignPlay to Learn: Effective Learning Game Design
Play to Learn: Effective Learning Game Design
 
Designing games with kodu_game_lab_v1
Designing games with kodu_game_lab_v1Designing games with kodu_game_lab_v1
Designing games with kodu_game_lab_v1
 
Continuous Improvement Tricks
Continuous Improvement TricksContinuous Improvement Tricks
Continuous Improvement Tricks
 
User Experience 6: Qualitative Methods, Playtesting and Interviews
User Experience 6: Qualitative Methods, Playtesting and InterviewsUser Experience 6: Qualitative Methods, Playtesting and Interviews
User Experience 6: Qualitative Methods, Playtesting and Interviews
 

Último

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Último (20)

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

Scrum simulation-with-lego-bricks-v2.0

  • 1. A Multi-Team, Full-Cycle, Product-Oriented Scrum Simulation with LEGO Bricks the Small & Medium Business Edition Can be adapted to teach other iteration-based Agile frameworks. Original paper published in Feb, 2009 Authored by Alexey Krivitsky Current version 2.0, Oct 2011 info@lego4scrum.com This work is distributed under a Creative Commons Attribution 3.0 Unported License 1
  • 2. PREFACE WHY A LEGO SIMULATION? ACKNOWLEDGEMENTS AND APPRECIATIONS CURRENT VARIATION LICENSING OF THIS WORK WEB COMMUNITY AND TRANSLATION PROJECT THE GAME DURATION, GROUP SIZE, MATERIALS ROLES Product Owner Scrum Masters Team Members Testers – Optional Role Allow No Observers WHAT TO OBSERVE Behaviors Communication Styles Broken Process STAGES OF THE GAME PRE-GAME: Organizing Teams PRE-GAME: Project Chartering PRE-GAME: Building the Backlog PRE-GAME: Estimating The fastest technique – swimlane sizing Planning poker with multiple teams GAME: Sprint Planning GAME: Sprinting GAME: Reviewing GAME: Release Cycle POST-GAME: Debriefing VARIATIONS Adding Fluctuations Enterprise Scrum Have your variation? Let us know THANK YOU! 2
  • 3. PREFACE WHY A LEGO SIMULATION? Over the last couple of years I have co-trained a dozen Scrum classes both certified and not. All of those classes had different simulation sessions, but I’ve always felt like there should be better ones. Below I am listing the features that a minimal game on Scrum should have, in my opinion. 1. OPEN BACKLOGS THAT TRIGGER IDEATING over DETAILED INSTRUCTIONS TO FOLLOW We want to start a game with an open backlog - an invitation for collaboration between a customer and teams. Backlogs can be prepared by trainers, but they should not be closed and precise like “do this, then do that.” This will sound like “good old” command and control. We want to teach and demonstrate a totally different kind of relationship between customers and teams. 2. MINDFUL PRODUCT DEVELOPMENT over A SERIES OF TASKS TO ACCOMPLISH We need to teach product development, not micromanagement on a task level. Hence, backlogs or instructions should not be composed of a series of tasks, rather they should be a vision of a product – a big thing teams are to build. 3. TEAMS COLLABORATING TOWARD COMMON SUCCESS over COMPETITION FOR SCORE The game should be scalable to suit classes of 20 people or more. Which, of course, will result in splitting the group into teams. This should be used as a chance to practice skills of inter-team collaboration. This needs to be done deliberately, as without specific instructions, it is natural for the teams to start competing. 4. USEFUL METRICS TO ASSESS BENEFITS OF AGILE over FIGURES THE TRAINERS ASKED TO COLLECT 3
  • 4. All metrics trainers ask participants to collect need to have an obvious benefit for the teams, as the games need to teach them to own their process. 5. CONTINUOUS IMPROVEMENTS over WINNING OR LOSING THE GAME WITH ONE TRY The game should be designed so that the teams get multiple tries at it. Each session generates lessons learned and helps them to figure out better processes. ACKNOWLEDGEMENTS AND APPRECIATIONS In early 2009 Mykola Gurov who helped me realize the potential of LEGOs as an “API”1 for product development simulations. Later that year, I created an early version of the game called “LEGO for extended SCRUM simulation” after discussing ideas with William Wake, Jurgen De Smet, Yves Hanoulle, and Xavier Quesada Allue. Since the first publication on Scrum Alliance website, I have received dozens of emails with appreciation for this work. Now I’d like to use this chance, in turn, to thank everyone who has contacted me to share their ideas and experiences with running the simulations: Gerry Kirk, Tim Yevgrashyn, Steve Rogalsky, Andriy Yevtushenko, Geoff Watts, Laurent Godé, Radu Davidescu, Martine Devos, Jo Newcombe Cook, Jakob Frandsen Martin Muntzing, Ola Ellnestam, Dusan Kocurek, Danny (Danko) Kovatch, Gustavo Quiroz, Jukka Lindström, Eduardo Bregaida, and Nathaniel Cadwell. Special thanks to Robin Dymond and Sergey Dmitriev for letting me run this game in their Certified Scrum Master classes. CURRENT VARIATION Since the first paper was published in 2009, dozens of trainers have tried this game. The current, improved, version of the simulation described in this paper reflects feedback and observations made. LICENSING OF THIS WORK 1Not sure what “API” means? Check out http://en.wikipedia.org/wiki/Application_programming_interface 4
  • 5. The current work is distributed under a Creative Commons Attribution 3.0 Unported License This license lets others distribute, remix, tweak, and build upon your work, even commercially, as long as they credit you for the original creation. This is the most accommodating of licenses offered. Recommended for maximum dissemination and use of licensed materials. WEB COMMUNITY AND TRANSLATION PROJECT We decided to create a place where people interested in teaching Scrum with LEGOs could come and collaborate. www.lego4scrum.com - Join the community, and help us spread the word. One of the ongoing projects of the community is to translate this paper into world languages. Check out the current status, and consider helping us out. We really appreciate your effort. THE GAME DURATION, GROUP SIZE, MATERIALS It is proven that the game can be adapted to fit the particular needs of trainers and serve different sizes of audience. A “standard” game is described below, but you are encouraged to adopt it to fit your particular needs. Timing: 100-120 minutes ● 100 minutes - when using fast team estimation techniques ● 120 minutes - when using planning poker or other estimation tools Group Size: 4-25 people ● Ideal is 2-3 teams of 4-6 people (gives 8-18 people) ● Can be extended with Scrum Masters LEGO Boxes: a LEGO box for a team of 4-6 people ● I use “Basic Brick Set #6177”2 ● It takes four boxes for 20 people Stationary: standard training package ● Stickers, flip chart paper sheets, markers ● Planning poker cards (or hand-made ones) 2 Visit the online LEGO store: http://shop.lego.com/en-US/LEGO-Basic-Bricks-Deluxe-6177 5
  • 6. Room Setup: a table for each team of 4-6 people ● Extra space (a table or a floor spot) for the integrated product is handy ROLES Product Owner As the trainer, I play the role of the Product Owner." The goal is to illustrate how Product Owners behave, what they typically expect and require, which team behaviors they appreciate and which they don't. Scrum Masters This game can be played without dedicated Scrum Masters. Sometimes I do have Scrum Masters in the game by inviting co-instructors. Another option would be to ask the team to select Scrum Masters. By having skillful facilitators playing Scrum Masters - who are constantly focused on the process, and a dedicated trainer - playing the business role, makes the game much more natural and an easy-going activity. Team Members Other students are team members. Testers – Optional Role You can have testers on the teams. Their main responsibility would be to help their teams document agreements on requirements and designs in order to perform acceptance testing. The downside, which I've experienced, is that rather than building LEGOs, the testers were observing quality. As the goal of such games is to learn by doing, I think it makes sense to encourage everyone to get engaged in the building process. Allow No Observers This game is so much fun playing that the observers will be losing more than they are gaining – my opinion. Otherwise, I’d love to hear good stories on this from you. WHAT TO OBSERVE Behaviors 6
  • 7. From my observations, certain behaviors people demonstrate in games are projections of working habits. And under stress people will tend to fall back to their natural behaviors. This game is deliberately designed to be stressful, so it might expose bad habits that could harm real Agile adoptions. My goal as a trainer is to point them out to the group and turn them into learning points and warnings to keep an eye on. Communication Styles Watch out for: “managers”, “dictators”, “loud voices,” and similar projections. This is a fruitful area for debriefing and topics for personal coaching. Broken Process Keep an eye on parts of the process the teams don’t do well. For example, during requirements discussion the teams might not ask as many clarifying questions as they need. Most likely they also have this issue, or will have this issue, in the particular area of a real project. Making this visible on debrief is one way of handling this. STAGES OF THE GAME The simulation has natural three parts: pre-game, game, and post-game or debrief. Pre-game ● Organizing teams ● Defining the Process ● Project chartering ● Building the Backlog ● Estimating Game ● Sprint Planning ● Sprinting ● Sprint Reviewing Post-game ● Debriefing PRE-GAME: Organizing Teams Will take 5 minutes. There is no reason why this activity cannot be a part of the game – a learning process. 7
  • 8. Striving to demonstrate self-organization in action I usually ask the team to self- organize in groups of 4-6 people and allocate working space This is a good warm-up activity since it might require moving tables around and cleaning them up. PRE-GAME: Project Chartering Will take 10 minutes. You are 5 minutes into the game now. As a trainer who is playing the Product Owner I need to communicate the following messages: 1. All teams will be building a single product – they are not competing, rather they work for the same vendor. 2. The product is a CITY with certain features. 3. The main building elements are LEGOs, though any other material can be used in addition. 4. I am the main decision maker of the product – it is my city. 5. I will be involved in the development process by being available to answer questions and provide feedback. Running this activity as collaborative chartering might be a good way. My goal is to make sure the teams practice Scrum by building “products” with LEGO bricks. Now the tricky question is how to combine the two roles: a Product Owner (who is not owning the process) and a class trainer (who has an interest in running it with Scrum). There are several ways I’ve tried doing this: 1. Changing hats – explain Scrum rules to the team I explicitly state whether I am currently a Product Owner or a trainer so that people are not confused. 2. Playing a newbie Product Owner – let the team sell you Scrum Most often I play a Product Owner who doesn’t know much about Agile or Scrum and after presenting my vision of a city I ask the team to help us design out the process that suits. Personally, I like this second approach more since it helps amplify learning from the class and let students practice articulating Agile values. PRE-GAME: Building the Backlog Will take 15 minutes. You are 15 minutes in the game now. 8
  • 9. Once you have sketched a charter and agreed on the process, it is the time to share the features of the city. I usually do this by showing the showing a team pre-prepared set of sticky notes hanging on a sheet of flip-chart paper. Usually it includes the following items: ● One storey building (several of these, one per sticky note) ● Two storey building (several) ● Shop ● School ● Church ● Hospital ● Kindergarten ● Bus stop ● Intersection (can be drawn) ● Park (can be drawn) ● River (can be drawn) ● Bridge Some of the items can be drawn on flip chart paper, and then the LEGOs are on top. Here you can get creative and build something more entertaining rather than a simple city. Once we’ve played this game with a start-up team, so we were building a “silicon village”. It obviously had some other items to be built, like a presentation hall with an iPad (presenting a screen), a bunch of open co-working areas in the city, a secure building for web servers, and a monument to a hero entrepreneur (a fancy monument on rails). That was fun! While presenting the backlog I briefly explain what I think each of the items may look like. And I try to postpone discussions until later. PRE-GAME: Estimating Will take up to 20 minutes. You are 30 minutes into the game now. Estimations. The hardest part, somehow. I may want to: 1. Drop estimates (as agile gurus would recommend) 2. Do it faster and simpler 9
  • 10. 3. Spend a bit of time on practicing planning poker RT @RonJeffries: "Every year there is new estimation technique. The real Agile approach would be to throw estimations out." - @agilemanager [YES!] Based on how much time we have I can decide to do the simplest technique or poker. The fastest technique – swimlane sizing I’ve learned this term from www.theagilepirate.net. Apparently, I do it in a less sophisticated manner. Check out a sketch below. Based on the triangulation concept3 and swimlane sizing4 we simply arrange columns to mark different story sizes (1 2 3 5 8 13 if you prefer Fibonacci - a little taste of science is always good), and ask students to drag stories to columns that represent story size. We do it in groups or altogether. This activity can also be run silently. Figure 1: Swimlanes for group estimations 3 Triangulation and other concepts of Agile estimating and planning, by Mike Cohn http:// www.mountaingoatsoftware.com/presentations/85-an-introduction-to-agile-estimating-and-planning 4 Swimlane Sizing – Complete & Fast Backlog Estimation http://theagilepirate.net/archives/109 10
  • 11. If a group is big enough that it cannot fit in front of the board, I ask each team to send a pair. When these pairs are done, the next come, until everyone got a chance to touch the board. Once done, I ask the group whether this is “good enough” to start with and whether they would like to do some real work now. Planning poker with multiple teams Running planning poker5 with multiple teams requires agreeing on sample size as a whole group, firstly. Agreeing on size is simple: pick up an item which is small and simple enough, but not trivial and assign it “2”. Usually everyone agrees to have all one-stored buildings as twos. Another approach to selecting sample stories to do t-shirt size estimates6 (XS, S, M, L, XL) and then mark all S-sized stories as “2” and continue with the poker. I’d like to share hints that help me make multi-team planning poker sessions work: ● Organize swimlanes wall (see sketches above) ● Ask teams to pull stories one by one for estimation. ● Ask teams to attach details to each story when they get clarifications from Product Owner (as it may be another team building the item). ● Actively encourage and appreciate team members asking clarifying questions which help define size. ● Once estimated, a story needs to be put on the wall, so that other teams can benefit from the new information. ● When done ask people to come up to the wall and make a sanity check with necessary changes (in my experience changes are rarely needed). If the teams do not know much about planning poker, it is worth doing a test run so that you can observe them using the technique correctly. I usually ask teams to guesstimate: “How much does a pint of Guinness cost in the U.K?” 5 Planning Poker is found by James Grening in 2002 and popularized by Mike Cohn: http://en.wikipedia.org/wiki/Planning_poker 6 T-shirt sizing http://blogs.msdn.com/b/oldnewthing/archive/2009/05/12/9605143.aspx 11
  • 12. This implies asking questions on points to be used, place and date of buying it – acts as a good warm-up for estimating stories. Interestingly, both techniques: swimlanes and planning poker provide the necessary precision for release planning as it has proven by hundreds of release burn-down charts. GAME: Sprint Planning You are 50 minutes into the game now. (And zero things are built! Does it prove enough that estimations are wasteful?) Now when the stories are estimated, you have to move them from the Swimlanes Wall back to the Backlog. Since we would like to make sprint planning highly visible, we are building a special Planning Wall that accumulates all teams’ plans for all sprints in the game. Figure 2: Multi-team Planning Wall, before planning sprint #1 12
  • 13. Figure 3: Multi-team Planning Wall, inside sprint #2 We time-box Sprint planning activity to three minutes asking teams to pull stories into their team’s sprint boxes. When all is done, we ask whether the teams are uncomfortable enough with their plans to give it a try! GAME: Sprinting Will take 7 minutes. We prefer 7-minutes sprints, as this time is quite enough to build several items with several people collaborating and without too much polishing it. To make sure students are stressed enough we show a big visible stopwatch from a notebook or an overhead projector: 13
  • 14. Figure 4: A stopwatch from www.online-stopwatch.com - timers of different forms, can be used offline. GAME: Reviewing Will take 5 minutes. When the time is up, I make sure students really stop building things and start demanding: “where is my city? ” As it has been observed, it is only after the second sprint teams start doing continuous deployments of stories to the demonstration environment (a flip chart paper). So in most cases after the first sprint, no one has ever thought on how to organize the demonstration. Sounds similar to the real life? I always got comments on debrief that I am playing the kindest Product Owner ever seen. Still, in most cases nothing is accepted after the first sprint, because after I am shown the buildings, I “come to realize”: ● I like symmetry. ● “All of the same color” actually meant “solid colors of buildings, but different for each.” ● Buildings are either too small, too big, or too diverse. ● Windows of different floors are not lined up. ● <make up your own reasoning> Unfinished items are brought back to the Backlog from the Planning Wall. Remaining work can be re-estimated, although we rarely update estimates. Once stories are accepted, the Release Burndown chart is updated by a PO, who makes a clear and loud announcement that the release has to be done in three sprints and now it looks like we will not be able to accomplish all stories. 14
  • 15. A few minutes can be spent on retrospecting on the topic of “how can we make it better the next sprint?”. GAME: Release Cycle Without too much time wasted on discussing failures of the first sprint, which is almost always a disaster, we jump back to Sprint Planning. I’ve learned it takes an average three sprints to build 80% of the backlog with anticipated quality, so the full cycle usually looks like this: 1. Sprint #1 a. Planning – 3 minutes b. Sprinting – 7 minutes c. Review – 5 minutes 2. Sprint #2 a. Planning – 3 minutes b. Sprinting – 7 minutes c. Review – 5 minutes 3. Sprint #3 a. Planning – 3 minutes b. Sprinting – 7 minutes c. Review – 5 minutes Subtotal: 45 minutes Since the preparations took us about 1 hour (from chartering to estimated backlog), sprints took 45 minutes, it will take about 15 minutes for debrief, the full game takes 120 minutes. Once practiced and with help from co-trainers, who play Scrum Master, it can be done a bit faster. POST-GAME: Debriefing It is probably wise to take a short break once the last sprint is reviewed and before jumping into debrief to calm down emotions and have a short rest (Did I tell you the game is designed to be exhaustive? Not only for the teams...) When gathered back in a circle, we run a facilitated discussion around the following open-ended questions: ● What did students observe? ● How did it feel being on a Scrum team? ● How did the short iterations go? 15
  • 16. ● How accurate were the estimations (provided the Release Burndown is there) ● What would we have done differently from the beginning, if we had another chance to play the game? ● What was the job of the Product Owner? ● How did it feel after the first sprint when almost all items required re-work? ● What did the Scrum Masters do? ● How will your strategy change, if you know the Product Owner is unavailable during sprints? ● How did inter-team communication go? Were there any dependencies? How were they resolved? ● What did students learn? VARIATIONS Adding Fluctuations Good friends of mine (Askhat Urazbaev and Nikita Filippov) have designed a similar game, which includes randomized fluctuations to the team size and complexity. Simply, after sprint planning is done and just before sprint start, the teams throw dice that either multiply story point estimates or make some team members gone “sick” for the sprint while the team will have to keep the sprint plan. The point this game makes is that team collaboration is essential for task balancing during sprints, as things might go differently than was planned. Enterprise Scrum I was able to scale the simulation with LEGOs to engage 100 students playing in 12 teams that were building 4 cities simultaneously. It requires quite a few tons of LEGOs but it seems to be a good way to demonstrate enterprise-level Scrum. This deserves another article to cover all rules and settings. Have your variation? Let us know We would like to hear your stories, your variation to the simulation – please join us at www.lego4scrum.com and email us your ideas at info@lego4scrum.com 16
  • 17. THANK YOU! Have playful projects! Alexey Krivitsky www.lego4scrum.com 17