exam questions

Exam Questions
1. Which of the following is NOT a type of project management office?
A.	
B.	
C.	
D.	

Directive
Value-driven
Supportive
Controlling

2. Which of the following is NOT a characteristic of a project?
A.	
B.	
C.	
D.	

Temporary
Strategic
Specific result
Progressively elaborated

3. An energy company is investing in a series of initiatives to look for alternative energy sources so that the
company can be competitive in 10 years. The initiatives are tracked and managed together because this goal
is vital to the success of the company. This is an example of:
A.	
B.	
C.	
D.	

A portfolio
A program
A project
A enterprise environmental factor

4. Which of the following is NOT a responsibility of a project manager?
A.	 Managing stakeholder expectations
B.	 Managing project constraints
C.	 Gathering product requirements
D.	 Sponsoring the project
5. Which of the following is NOT an interpersonal skill?
A.	
B.	
C.	
D.	

Motivation
Brainstorming
Team building
Coaching

32  Chapter 1
introduction to the pmp exam

Exam Questions
6. Which of the following is NOT true about interpersonal skills?
A.	
B.	
C.	
D.	

Coaching means helping your team to get more exercise.
Motivation means helping team members get what they want out of the project.
Influencing means sharing power with people to get something done.
Conflict management means finding positive solutions to conflicts during the project.

7. Which of the following is NOT true about portfolio management?
A.	 The portfolio manager judges the success of the portfolio by combining data from all of its programs and
projects.
B.	 A portfolio can contain projects and programs.
C.	 A portfolio is organized around a business goal.
D.	 A portfolio is always a group of programs.
8. You’re managing a project to remodel a kitchen. You use earned value calculations to figure out that
you’re going to run $500 over budget if your project continues at the current rate. Which of the following
core characteristics of a project manager are you using to find the problem?
A.	
B.	
C.	
D.	

Knowledge
Performance
Personal
None of the above

9. At the beginning of a project, a software team project manager is given a schedule with everyone’s
vacations on it. She realizes that because the software will be delivered to the QA team exactly when they
have overlapping vacations, there is a serious risk of quality problems, because there won’t be anyone to
test the software before it goes into production. What BEST describes the constraint this places on the
project?
A.	
B.	
C.	
D.	

Quality constraint
Time constraint
Resource constraint
Risk constraint

10. A project manager is having trouble with his project because one of his team members is not performing,
which is causing him to miss an important date he promised to a stakeholder. He discovers that the team
member knew about the project problem, but didn’t tell him because the team members are all afraid of his
bad temper. Which BEST describes how the project manager can avoid this situation in the future?
A.	
B.	
C.	
D.	

Increasing his knowledge of the PMBOK Guide
Measuring personal performance
Improving his personal skills
Managing stakeholder expectations

you are here 4  33
Answers

exam questions answers

Exam Questions
1. Answer: B

Although PMOs are usually value-driven, that’s not a valid type of PMO. The three types of PMOs are supportive,
controlling, and directive. Supportive PMOs provide templates and guidelines for running projects, controlling PMOs
audit projects to ensure adherence to processes and standards, and directive PMOs provide project managers to
manage projects.
2. Answer: B
A project doesn’t have to be strategic or critical. It only needs to be temporary, have a specific result, and be
progressively elaborated.

Look out for questions like this one
might tell you that a project should on the exam. Common sense
want to do it, but that’s not what be important for a company to
the question is asking.

3. Answer: A
Since the initiatives are being managed together because of a strategic business goal, you can tell that this is a
portfolio.
Portfolios are org

anized around
organized around a shared benefibusiness goals, and programs are
t in managing them together.

4. Answer: D
The sponsor is the person who pays for the project. The project manager doesn’t usually play that role.

5. Answer: B

In fact, you’ll learn more about its role in defining
project requirements in a couple of chapters.

Brainstorming is an activity that you do with other people, but it’s not an interpersonal skill that you need to hone to help
manage all of the stakeholders on your project.

6. Answer: A
Coaching is really about helping your team members to get better at what they do. Anything you do to challenge them
to develop their skills is coaching.

7. Answer: D
Since a portfolio can be a group of programs and projects, option D is the one that’s not true. It can be a group of
programs, but it doesn’t have to be.

34  Chapter 1
Answers

introduction to the pmp exam

Exam Questions
8. Answer: A

Your knowledge of earned value management techniques is how you can predict that the project will be
over budget. Knowing that could help you plan ahead to avoid further cost overruns. Minimally, it can help
you to reset expectations with your stakeholders so they have a better idea of what’s coming.

9. Answer: C
This is a resource constraint, because the project manager’s resources—in this case, the people who will
be testing the software—are not going to be available to her when she needs them. Yes, this will cause
problems with the quality, introduce risks, and cause schedule problems. But they’re not schedule, time, or
risk constraints, because there’s no outside limitation placed on the project quality, schedule, or risks. The
only outside limitation is the resource availability. If they were available, there wouldn’t be a problem!

10. Answer: C
The way that the project manager interacts with the people on his team interfered with his work getting
done. This is a good example of how a lack of personal skills can lead directly to major project problems
down the line, and it’s why this particular project manager needs to work on his personal skills.

The project manager’s temper
led to a disappointed stakeholder,
but that doesn’t mean that the
stakeholder’s expectations were
out of line. This was an avoidable
project problem, and better
personal skills would have fixed it.

You made it
through your
first chapter and
exam questions!
How’d it go?

you are here 4  35

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

Pmp exam q&a
Pmp exam q&aPmp exam q&a
Pmp exam q&a
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility exam
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes exam
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management exam
 
05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management exam
 
Pmp sample questions
Pmp sample questionsPmp sample questions
Pmp sample questions
 
Pmp2
Pmp2Pmp2
Pmp2
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
Pmp5
Pmp5Pmp5
Pmp5
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
Pmstudy exam 3
Pmstudy exam 3Pmstudy exam 3
Pmstudy exam 3
 
Full length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folksFull length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folks
 
09 pmp human resource management exam
09 pmp human resource  management exam09 pmp human resource  management exam
09 pmp human resource management exam
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle exam
 
Pmp test 01
Pmp test 01Pmp test 01
Pmp test 01
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 

Semelhante a Pmp1

Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkD10iT
 
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMajor Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMd. Masudur Rahman, PMP
 
Risk 1 actual test 7 (273 q)
Risk 1 actual test 7 (273 q)Risk 1 actual test 7 (273 q)
Risk 1 actual test 7 (273 q)Mohamed Saeed
 
Session 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM CertificationsSession 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM CertificationsSeshne Govender
 
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...Mr.Allah Dad Khan
 
9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development ProcessSattrix Software Solutions
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 

Semelhante a Pmp1 (20)

PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
PMP Certificate- introduction
PMP Certificate- introductionPMP Certificate- introduction
PMP Certificate- introduction
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Pmp Five Sample Questions
Pmp Five Sample QuestionsPmp Five Sample Questions
Pmp Five Sample Questions
 
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management FrameworkProject Management Professional (PMP) | Lesson 02 | Project Management Framework
Project Management Professional (PMP) | Lesson 02 | Project Management Framework
 
PMP® Sample Questions Set #2
PMP® Sample Questions Set #2PMP® Sample Questions Set #2
PMP® Sample Questions Set #2
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Major Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptxMajor Project Management Challenges and The Way Forward.pptx
Major Project Management Challenges and The Way Forward.pptx
 
Pmi rmp
Pmi rmpPmi rmp
Pmi rmp
 
Risk 1 actual test 7 (273 q)
Risk 1 actual test 7 (273 q)Risk 1 actual test 7 (273 q)
Risk 1 actual test 7 (273 q)
 
2
22
2
 
PMP Sample Questions Set 3
PMP Sample Questions Set 3PMP Sample Questions Set 3
PMP Sample Questions Set 3
 
Session 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM CertificationsSession 8 Everything You Should Know About PMP & CAPM Certifications
Session 8 Everything You Should Know About PMP & CAPM Certifications
 
PMP Exam Sample Questions 4
PMP Exam Sample Questions 4PMP Exam Sample Questions 4
PMP Exam Sample Questions 4
 
Free PMP Exam Q & A
Free PMP Exam Q & AFree PMP Exam Q & A
Free PMP Exam Q & A
 
PMP® Sample Questions 3
PMP® Sample Questions 3PMP® Sample Questions 3
PMP® Sample Questions 3
 
PMP® Sample Questions
PMP® Sample QuestionsPMP® Sample Questions
PMP® Sample Questions
 
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...28.Causes of project failure   A Lecture By Mr Allah Dad Khan Visiting Profes...
28.Causes of project failure A Lecture By Mr Allah Dad Khan Visiting Profes...
 
9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process9 Common Challenges in the Software Development Process
9 Common Challenges in the Software Development Process
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 

Mais de Jamil Faraj , PMP

Mais de Jamil Faraj , PMP (10)

Corona-virus PMP study plan
Corona-virus PMP study planCorona-virus PMP study plan
Corona-virus PMP study plan
 
PMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMPPMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMP
 
Jamil Faraj CV 2020
Jamil Faraj CV 2020Jamil Faraj CV 2020
Jamil Faraj CV 2020
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
دورة وظيفة العمر
دورة وظيفة العمردورة وظيفة العمر
دورة وظيفة العمر
 

Último

1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibitjbellavia9
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxAmanpreet Kaur
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 

Último (20)

1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 

Pmp1

  • 1. exam questions Exam Questions 1. Which of the following is NOT a type of project management office? A. B. C. D. Directive Value-driven Supportive Controlling 2. Which of the following is NOT a characteristic of a project? A. B. C. D. Temporary Strategic Specific result Progressively elaborated 3. An energy company is investing in a series of initiatives to look for alternative energy sources so that the company can be competitive in 10 years. The initiatives are tracked and managed together because this goal is vital to the success of the company. This is an example of: A. B. C. D. A portfolio A program A project A enterprise environmental factor 4. Which of the following is NOT a responsibility of a project manager? A. Managing stakeholder expectations B. Managing project constraints C. Gathering product requirements D. Sponsoring the project 5. Which of the following is NOT an interpersonal skill? A. B. C. D. Motivation Brainstorming Team building Coaching 32  Chapter 1
  • 2. introduction to the pmp exam Exam Questions 6. Which of the following is NOT true about interpersonal skills? A. B. C. D. Coaching means helping your team to get more exercise. Motivation means helping team members get what they want out of the project. Influencing means sharing power with people to get something done. Conflict management means finding positive solutions to conflicts during the project. 7. Which of the following is NOT true about portfolio management? A. The portfolio manager judges the success of the portfolio by combining data from all of its programs and projects. B. A portfolio can contain projects and programs. C. A portfolio is organized around a business goal. D. A portfolio is always a group of programs. 8. You’re managing a project to remodel a kitchen. You use earned value calculations to figure out that you’re going to run $500 over budget if your project continues at the current rate. Which of the following core characteristics of a project manager are you using to find the problem? A. B. C. D. Knowledge Performance Personal None of the above 9. At the beginning of a project, a software team project manager is given a schedule with everyone’s vacations on it. She realizes that because the software will be delivered to the QA team exactly when they have overlapping vacations, there is a serious risk of quality problems, because there won’t be anyone to test the software before it goes into production. What BEST describes the constraint this places on the project? A. B. C. D. Quality constraint Time constraint Resource constraint Risk constraint 10. A project manager is having trouble with his project because one of his team members is not performing, which is causing him to miss an important date he promised to a stakeholder. He discovers that the team member knew about the project problem, but didn’t tell him because the team members are all afraid of his bad temper. Which BEST describes how the project manager can avoid this situation in the future? A. B. C. D. Increasing his knowledge of the PMBOK Guide Measuring personal performance Improving his personal skills Managing stakeholder expectations you are here 4  33
  • 3. Answers exam questions answers Exam Questions 1. Answer: B Although PMOs are usually value-driven, that’s not a valid type of PMO. The three types of PMOs are supportive, controlling, and directive. Supportive PMOs provide templates and guidelines for running projects, controlling PMOs audit projects to ensure adherence to processes and standards, and directive PMOs provide project managers to manage projects. 2. Answer: B A project doesn’t have to be strategic or critical. It only needs to be temporary, have a specific result, and be progressively elaborated. Look out for questions like this one might tell you that a project should on the exam. Common sense want to do it, but that’s not what be important for a company to the question is asking. 3. Answer: A Since the initiatives are being managed together because of a strategic business goal, you can tell that this is a portfolio. Portfolios are org anized around organized around a shared benefibusiness goals, and programs are t in managing them together. 4. Answer: D The sponsor is the person who pays for the project. The project manager doesn’t usually play that role. 5. Answer: B In fact, you’ll learn more about its role in defining project requirements in a couple of chapters. Brainstorming is an activity that you do with other people, but it’s not an interpersonal skill that you need to hone to help manage all of the stakeholders on your project. 6. Answer: A Coaching is really about helping your team members to get better at what they do. Anything you do to challenge them to develop their skills is coaching. 7. Answer: D Since a portfolio can be a group of programs and projects, option D is the one that’s not true. It can be a group of programs, but it doesn’t have to be. 34  Chapter 1
  • 4. Answers introduction to the pmp exam Exam Questions 8. Answer: A Your knowledge of earned value management techniques is how you can predict that the project will be over budget. Knowing that could help you plan ahead to avoid further cost overruns. Minimally, it can help you to reset expectations with your stakeholders so they have a better idea of what’s coming. 9. Answer: C This is a resource constraint, because the project manager’s resources—in this case, the people who will be testing the software—are not going to be available to her when she needs them. Yes, this will cause problems with the quality, introduce risks, and cause schedule problems. But they’re not schedule, time, or risk constraints, because there’s no outside limitation placed on the project quality, schedule, or risks. The only outside limitation is the resource availability. If they were available, there wouldn’t be a problem! 10. Answer: C The way that the project manager interacts with the people on his team interfered with his work getting done. This is a good example of how a lack of personal skills can lead directly to major project problems down the line, and it’s why this particular project manager needs to work on his personal skills. The project manager’s temper led to a disappointed stakeholder, but that doesn’t mean that the stakeholder’s expectations were out of line. This was an avoidable project problem, and better personal skills would have fixed it. You made it through your first chapter and exam questions! How’d it go? you are here 4  35