SlideShare uma empresa Scribd logo
1 de 2
Salford City College
Eccles Sixth Form Centre
BTec Level 3
Extended Diploma in Creative Media Production
Games Design
Final Major Project
Schedule
Review date: 06.02.13
Monday Tuesday Wednesday Thursday Friday Saturday Sunday
w/b 04.02.13 Task 1 - FMP Launch
Meeting
w/b 11.02.13 Half-Term
w/b 18.02.13 Book meeting slot
with project manager.
Begin secondary
research into existing
sandbox games
Begin primary
research in into
sandbox games
Review Schedule and
Production Log
w/b 25.02.13 Finish off all research
assignments in task 1
Begin Ideas generation
And set up blog
Complete Ideas
generation and update
blog with task 2 and 3
Review Schedule and
Production Log
w/b 04.03.13 Task 4: Pitch must
take place by this
week.
Finish Task 4 by this
point
Begin Pre-production Make a plan, including
budget and time, and
hold a pre-production
meeting.
Review Schedule and
Production Log
w/b 11.03.13 Task 5: Pre-production
must take place by
this week.
Begin creating building
assets, including
textures.
Continue plan, budget
and work out wages.
Plan and budget must
be finished by this
point.
Review Schedule and
Production Log
w/b 18.03.13 Investigate
appropriate colour
scheme.
Plan and budget must
be finished by this
point.
Begin to build basic
functionality using
unity.
Review Schedule and
Production Log
25.03.13 Easter Review Schedule and
Production Log
01.04.13 Easter Review Schedule and
Production Log
w/b 08.04.13 Create other assets,
e.g. characters.
Create other
environment assets.
Continue working on
functionality.
Review Schedule and
Production Log
w/b 15.04.13 Work on completing
functionality.
Keep working on
functionality
Keep working on
functionality
Review Schedule and
Production Log
w/b 22.04.13 Fix issues involving
controls with in the
built game
Review Schedule and
Production Log
w/b 29.04.13 Finish first ‘alpha
stage’ and test it.
Make siome changes
based on feedback
Review Schedule and
Production Log
w/b 06.05.13 Complete scoring
system for new game
mode.
Finish and Beta test Make appropriate
changes to the game.
Evaluation Review Schedule and
Production Log
w/b 13.05.13 Review Schedule and
Production Log
w/b 20.05.13 Task 8: Evaluation
should take place no
later than the
beginning of this
week.
DEADLINE

Mais conteúdo relacionado

Mais procurados

Final project schedule 10th april 2013
Final project schedule 10th april 2013Final project schedule 10th april 2013
Final project schedule 10th april 2013
Jason
 
Final project schedule 27th feb 2013
Final project schedule 27th feb 2013Final project schedule 27th feb 2013
Final project schedule 27th feb 2013
Jason
 
Final project schedule 24th april 2013
Final project schedule 24th april 2013Final project schedule 24th april 2013
Final project schedule 24th april 2013
Jason
 
Final project schedule 1st may 2013
Final project schedule 1st may 2013Final project schedule 1st may 2013
Final project schedule 1st may 2013
Jason
 
Fmp production log 24-05-13
Fmp production log 24-05-13Fmp production log 24-05-13
Fmp production log 24-05-13
jbiffaccforcoll
 
Final project schedule 10th april 2013
Final project schedule 10th april 2013Final project schedule 10th april 2013
Final project schedule 10th april 2013
Jason
 
Final project schedule 17th april 2013
Final project schedule 17th april 2013Final project schedule 17th april 2013
Final project schedule 17th april 2013
Jason
 
Final project schedule 3rd april 2013
Final project schedule 3rd april 2013Final project schedule 3rd april 2013
Final project schedule 3rd april 2013
Jason
 
Final project schedule 22nd may 2013
Final project schedule 22nd may 2013Final project schedule 22nd may 2013
Final project schedule 22nd may 2013
Jason
 
Final project schedule 15th may 2013
Final project schedule 15th may 2013Final project schedule 15th may 2013
Final project schedule 15th may 2013
Jason
 
Final project schedule 8th may 2013
Final project schedule 8th may 2013Final project schedule 8th may 2013
Final project schedule 8th may 2013
Jason
 
Fmp initial schedule_23_05_13
Fmp initial schedule_23_05_13Fmp initial schedule_23_05_13
Fmp initial schedule_23_05_13
KyleJFernley
 
2014 journalism final
2014 journalism final2014 journalism final
2014 journalism final
ptmediaweb
 
2014 senior journalism final
2014 senior journalism final2014 senior journalism final
2014 senior journalism final
ptmediaweb
 
Fmp production log_170314
Fmp production log_170314Fmp production log_170314
Fmp production log_170314
Rexeh1245
 
Production log
Production logProduction log
Production log
Rexeh1245
 

Mais procurados (18)

Final project schedule 10th april 2013
Final project schedule 10th april 2013Final project schedule 10th april 2013
Final project schedule 10th april 2013
 
Final project schedule 27th feb 2013
Final project schedule 27th feb 2013Final project schedule 27th feb 2013
Final project schedule 27th feb 2013
 
Final project schedule 24th april 2013
Final project schedule 24th april 2013Final project schedule 24th april 2013
Final project schedule 24th april 2013
 
Final project schedule 1st may 2013
Final project schedule 1st may 2013Final project schedule 1st may 2013
Final project schedule 1st may 2013
 
Fmp production log 24-05-13
Fmp production log 24-05-13Fmp production log 24-05-13
Fmp production log 24-05-13
 
Final project schedule 10th april 2013
Final project schedule 10th april 2013Final project schedule 10th april 2013
Final project schedule 10th april 2013
 
Final project schedule 17th april 2013
Final project schedule 17th april 2013Final project schedule 17th april 2013
Final project schedule 17th april 2013
 
Final project schedule 3rd april 2013
Final project schedule 3rd april 2013Final project schedule 3rd april 2013
Final project schedule 3rd april 2013
 
Final project schedule 22nd may 2013
Final project schedule 22nd may 2013Final project schedule 22nd may 2013
Final project schedule 22nd may 2013
 
Final project schedule 15th may 2013
Final project schedule 15th may 2013Final project schedule 15th may 2013
Final project schedule 15th may 2013
 
Final project schedule 8th may 2013
Final project schedule 8th may 2013Final project schedule 8th may 2013
Final project schedule 8th may 2013
 
Fmp initial schedule_23_05_13
Fmp initial schedule_23_05_13Fmp initial schedule_23_05_13
Fmp initial schedule_23_05_13
 
2014 journalism final
2014 journalism final2014 journalism final
2014 journalism final
 
ENGL 202 Online Project 1 Schedule
ENGL 202 Online Project 1 ScheduleENGL 202 Online Project 1 Schedule
ENGL 202 Online Project 1 Schedule
 
2014 senior journalism final
2014 senior journalism final2014 senior journalism final
2014 senior journalism final
 
Fmp production log_170314
Fmp production log_170314Fmp production log_170314
Fmp production log_170314
 
Project 2 Schedule ENGL 202 FA19 F2F
Project 2 Schedule ENGL 202 FA19 F2FProject 2 Schedule ENGL 202 FA19 F2F
Project 2 Schedule ENGL 202 FA19 F2F
 
Production log
Production logProduction log
Production log
 

Destaque

Sound file game maker instructions
Sound file game maker instructionsSound file game maker instructions
Sound file game maker instructions
Jason
 
Jack fletcher n3046174
Jack fletcher n3046174Jack fletcher n3046174
Jack fletcher n3046174
j45a45ck
 
Artistic styles used in computer games
Artistic styles used in computer gamesArtistic styles used in computer games
Artistic styles used in computer games
Jason
 
Task 3 – technical file
Task 3 – technical fileTask 3 – technical file
Task 3 – technical file
AkiTenshi
 
Design concepts and timeline pl
Design concepts and timeline plDesign concepts and timeline pl
Design concepts and timeline pl
AkiTenshi
 
Animation production log
Animation production logAnimation production log
Animation production log
AkiTenshi
 
Unit 78: Task 3 Technical file
Unit 78: Task 3 Technical fileUnit 78: Task 3 Technical file
Unit 78: Task 3 Technical file
ConnahTilley
 
Animation production log
Animation production logAnimation production log
Animation production log
AkiTenshi
 
Production log e6 26 october
Production log e6 26 octoberProduction log e6 26 october
Production log e6 26 october
Jason
 
Fmp production log_6th_mar_2013
Fmp production log_6th_mar_2013Fmp production log_6th_mar_2013
Fmp production log_6th_mar_2013
Jason
 
Uses of 3 d
Uses of 3 dUses of 3 d
Uses of 3 d
j45a45ck
 
The sims production log
The sims production logThe sims production log
The sims production log
j45a45ck
 
Artistic styles used in computer games
Artistic styles used in computer gamesArtistic styles used in computer games
Artistic styles used in computer games
Jason
 
Qa testing form - 2
Qa testing form - 2Qa testing form - 2
Qa testing form - 2
AkiTenshi
 
Fmp production log_08_05_2013
Fmp production log_08_05_2013Fmp production log_08_05_2013
Fmp production log_08_05_2013
j45a45ck
 

Destaque (20)

Sound file game maker instructions
Sound file game maker instructionsSound file game maker instructions
Sound file game maker instructions
 
Job roles
Job rolesJob roles
Job roles
 
Jack fletcher n3046174
Jack fletcher n3046174Jack fletcher n3046174
Jack fletcher n3046174
 
Artistic styles used in computer games
Artistic styles used in computer gamesArtistic styles used in computer games
Artistic styles used in computer games
 
Task 3 – technical file
Task 3 – technical fileTask 3 – technical file
Task 3 – technical file
 
Design concepts and timeline pl
Design concepts and timeline plDesign concepts and timeline pl
Design concepts and timeline pl
 
Jack Fletcher ICA1 'The Chair'
Jack Fletcher ICA1 'The Chair'Jack Fletcher ICA1 'The Chair'
Jack Fletcher ICA1 'The Chair'
 
Animation production log
Animation production logAnimation production log
Animation production log
 
Unit 78: Task 3 Technical file
Unit 78: Task 3 Technical fileUnit 78: Task 3 Technical file
Unit 78: Task 3 Technical file
 
Birds
BirdsBirds
Birds
 
Animation production log
Animation production logAnimation production log
Animation production log
 
Production log e6 26 october
Production log e6 26 octoberProduction log e6 26 october
Production log e6 26 october
 
Portfolio
PortfolioPortfolio
Portfolio
 
Fmp production log_6th_mar_2013
Fmp production log_6th_mar_2013Fmp production log_6th_mar_2013
Fmp production log_6th_mar_2013
 
Uses of 3 d
Uses of 3 dUses of 3 d
Uses of 3 d
 
The sims production log
The sims production logThe sims production log
The sims production log
 
Test
TestTest
Test
 
Artistic styles used in computer games
Artistic styles used in computer gamesArtistic styles used in computer games
Artistic styles used in computer games
 
Qa testing form - 2
Qa testing form - 2Qa testing form - 2
Qa testing form - 2
 
Fmp production log_08_05_2013
Fmp production log_08_05_2013Fmp production log_08_05_2013
Fmp production log_08_05_2013
 

Semelhante a Fmp schedule 08_05_2013

Fmp initial schedule_220513
Fmp initial schedule_220513Fmp initial schedule_220513
Fmp initial schedule_220513
Dom9533
 
Final FMP Schedule Complete
Final FMP Schedule CompleteFinal FMP Schedule Complete
Final FMP Schedule Complete
Cameron321
 
Initial schedule 210413
Initial schedule 210413Initial schedule 210413
Initial schedule 210413
hannahmorse
 
Ha4 initial schedule
Ha4 initial scheduleHa4 initial schedule
Ha4 initial schedule
BethMelia
 
Ha4 initial schedule_210413
Ha4 initial schedule_210413Ha4 initial schedule_210413
Ha4 initial schedule_210413
DenniHepburn96
 
Ha4 initial schedule_210413 pt4
Ha4 initial schedule_210413 pt4Ha4 initial schedule_210413 pt4
Ha4 initial schedule_210413 pt4
k_ishii_
 
Ha4 initial schedule_210413 pt5
Ha4 initial schedule_210413 pt5Ha4 initial schedule_210413 pt5
Ha4 initial schedule_210413 pt5
k_ishii_
 
Ha4 initial schedule week 6
Ha4 initial schedule week 6Ha4 initial schedule week 6
Ha4 initial schedule week 6
MattRogero
 
Ha4 initial schedule_210413 week 6
Ha4 initial schedule_210413 week 6Ha4 initial schedule_210413 week 6
Ha4 initial schedule_210413 week 6
MattRogero
 
Ha4 initial schedule_210413 pt2
Ha4 initial schedule_210413 pt2Ha4 initial schedule_210413 pt2
Ha4 initial schedule_210413 pt2
k_ishii_
 
Ha4 initial schedule_210413 pt2
Ha4 initial schedule_210413 pt2Ha4 initial schedule_210413 pt2
Ha4 initial schedule_210413 pt2
k_ishii_
 
Ha4 initial schedule_210413 pt3
Ha4 initial schedule_210413 pt3Ha4 initial schedule_210413 pt3
Ha4 initial schedule_210413 pt3
k_ishii_
 
Ha4 initial schedule_210413
Ha4 initial schedule_210413Ha4 initial schedule_210413
Ha4 initial schedule_210413
MattRogero
 
Ha4 initial schedule week 1
Ha4 initial schedule week 1Ha4 initial schedule week 1
Ha4 initial schedule week 1
MattRogero
 
Ha4 initial schedule_210413
Ha4 initial schedule_210413Ha4 initial schedule_210413
Ha4 initial schedule_210413
hannahmorse
 

Semelhante a Fmp schedule 08_05_2013 (20)

Fmp initial schedule_220513
Fmp initial schedule_220513Fmp initial schedule_220513
Fmp initial schedule_220513
 
Fmp schedule 01-05-13
Fmp schedule 01-05-13Fmp schedule 01-05-13
Fmp schedule 01-05-13
 
Final FMP Schedule Complete
Final FMP Schedule CompleteFinal FMP Schedule Complete
Final FMP Schedule Complete
 
Initial schedule 210413
Initial schedule 210413Initial schedule 210413
Initial schedule 210413
 
Ha4 initial schedule
Ha4 initial scheduleHa4 initial schedule
Ha4 initial schedule
 
Ha4 initial schedule_210413
Ha4 initial schedule_210413Ha4 initial schedule_210413
Ha4 initial schedule_210413
 
Ha4 initial schedule_210413 pt4
Ha4 initial schedule_210413 pt4Ha4 initial schedule_210413 pt4
Ha4 initial schedule_210413 pt4
 
Ha4 initial schedule_210413 pt5
Ha4 initial schedule_210413 pt5Ha4 initial schedule_210413 pt5
Ha4 initial schedule_210413 pt5
 
Ha4 initial schedule week 6
Ha4 initial schedule week 6Ha4 initial schedule week 6
Ha4 initial schedule week 6
 
Ha4 initial schedule_210413 week 6
Ha4 initial schedule_210413 week 6Ha4 initial schedule_210413 week 6
Ha4 initial schedule_210413 week 6
 
Ha4 initial schedule_210413 pt2
Ha4 initial schedule_210413 pt2Ha4 initial schedule_210413 pt2
Ha4 initial schedule_210413 pt2
 
Ha4 initial schedule_210413 pt2
Ha4 initial schedule_210413 pt2Ha4 initial schedule_210413 pt2
Ha4 initial schedule_210413 pt2
 
Ha4 initial schedule_210413 pt3
Ha4 initial schedule_210413 pt3Ha4 initial schedule_210413 pt3
Ha4 initial schedule_210413 pt3
 
Schedule 2
Schedule 2Schedule 2
Schedule 2
 
Schedule
ScheduleSchedule
Schedule
 
Ha4 initial schedule_210413
Ha4 initial schedule_210413Ha4 initial schedule_210413
Ha4 initial schedule_210413
 
Schedule 5
Schedule 5Schedule 5
Schedule 5
 
Ha4 initial schedule week 1
Ha4 initial schedule week 1Ha4 initial schedule week 1
Ha4 initial schedule week 1
 
Schedule 2
Schedule 2Schedule 2
Schedule 2
 
Ha4 initial schedule_210413
Ha4 initial schedule_210413Ha4 initial schedule_210413
Ha4 initial schedule_210413
 

Mais de j45a45ck

Gd02 ethical checklist
Gd02 ethical checklistGd02 ethical checklist
Gd02 ethical checklist
j45a45ck
 
Computers 09
Computers 09Computers 09
Computers 09
j45a45ck
 
Classrooms 09
Classrooms 09Classrooms 09
Classrooms 09
j45a45ck
 
Computer game graphics
Computer game graphicsComputer game graphics
Computer game graphics
j45a45ck
 
L3 gd ha6_robot_dreams_140212_01
L3 gd ha6_robot_dreams_140212_01L3 gd ha6_robot_dreams_140212_01
L3 gd ha6_robot_dreams_140212_01
j45a45ck
 
HA6 Schedule
HA6 ScheduleHA6 Schedule
HA6 Schedule
j45a45ck
 
Article plan
Article planArticle plan
Article plan
j45a45ck
 
Uses of 3D
Uses of 3DUses of 3D
Uses of 3D
j45a45ck
 
Sketch book
Sketch bookSketch book
Sketch book
j45a45ck
 
Design pack
Design packDesign pack
Design pack
j45a45ck
 
Layout Screenshots
Layout ScreenshotsLayout Screenshots
Layout Screenshots
j45a45ck
 
LRC screenshots
LRC screenshotsLRC screenshots
LRC screenshots
j45a45ck
 
Study area screenshots
Study area screenshotsStudy area screenshots
Study area screenshots
j45a45ck
 
Plans of areas to model
Plans of areas to modelPlans of areas to model
Plans of areas to model
j45a45ck
 
Light bot screenshots
Light bot screenshotsLight bot screenshots
Light bot screenshots
j45a45ck
 

Mais de j45a45ck (20)

Jack fletcher n3046174
Jack fletcher n3046174Jack fletcher n3046174
Jack fletcher n3046174
 
Gd02 ethical checklist
Gd02 ethical checklistGd02 ethical checklist
Gd02 ethical checklist
 
Computers 09
Computers 09Computers 09
Computers 09
 
Classrooms 09
Classrooms 09Classrooms 09
Classrooms 09
 
Plan
PlanPlan
Plan
 
Computer game graphics
Computer game graphicsComputer game graphics
Computer game graphics
 
Insects
InsectsInsects
Insects
 
Reptiles
ReptilesReptiles
Reptiles
 
L3 gd ha6_robot_dreams_140212_01
L3 gd ha6_robot_dreams_140212_01L3 gd ha6_robot_dreams_140212_01
L3 gd ha6_robot_dreams_140212_01
 
HA6 Schedule
HA6 ScheduleHA6 Schedule
HA6 Schedule
 
Article plan
Article planArticle plan
Article plan
 
Uses of 3D
Uses of 3DUses of 3D
Uses of 3D
 
Sketch book
Sketch bookSketch book
Sketch book
 
Final app
Final appFinal app
Final app
 
Design pack
Design packDesign pack
Design pack
 
Layout Screenshots
Layout ScreenshotsLayout Screenshots
Layout Screenshots
 
LRC screenshots
LRC screenshotsLRC screenshots
LRC screenshots
 
Study area screenshots
Study area screenshotsStudy area screenshots
Study area screenshots
 
Plans of areas to model
Plans of areas to modelPlans of areas to model
Plans of areas to model
 
Light bot screenshots
Light bot screenshotsLight bot screenshots
Light bot screenshots
 

Fmp schedule 08_05_2013

  • 1. Salford City College Eccles Sixth Form Centre BTec Level 3 Extended Diploma in Creative Media Production Games Design Final Major Project Schedule Review date: 06.02.13 Monday Tuesday Wednesday Thursday Friday Saturday Sunday w/b 04.02.13 Task 1 - FMP Launch Meeting w/b 11.02.13 Half-Term w/b 18.02.13 Book meeting slot with project manager. Begin secondary research into existing sandbox games Begin primary research in into sandbox games Review Schedule and Production Log w/b 25.02.13 Finish off all research assignments in task 1 Begin Ideas generation And set up blog Complete Ideas generation and update blog with task 2 and 3 Review Schedule and Production Log w/b 04.03.13 Task 4: Pitch must take place by this week. Finish Task 4 by this point Begin Pre-production Make a plan, including budget and time, and hold a pre-production meeting. Review Schedule and Production Log w/b 11.03.13 Task 5: Pre-production must take place by this week. Begin creating building assets, including textures. Continue plan, budget and work out wages. Plan and budget must be finished by this point. Review Schedule and Production Log w/b 18.03.13 Investigate appropriate colour scheme. Plan and budget must be finished by this point. Begin to build basic functionality using unity. Review Schedule and Production Log 25.03.13 Easter Review Schedule and Production Log 01.04.13 Easter Review Schedule and Production Log w/b 08.04.13 Create other assets, e.g. characters. Create other environment assets. Continue working on functionality. Review Schedule and Production Log w/b 15.04.13 Work on completing functionality. Keep working on functionality Keep working on functionality Review Schedule and Production Log w/b 22.04.13 Fix issues involving controls with in the built game Review Schedule and Production Log
  • 2. w/b 29.04.13 Finish first ‘alpha stage’ and test it. Make siome changes based on feedback Review Schedule and Production Log w/b 06.05.13 Complete scoring system for new game mode. Finish and Beta test Make appropriate changes to the game. Evaluation Review Schedule and Production Log w/b 13.05.13 Review Schedule and Production Log w/b 20.05.13 Task 8: Evaluation should take place no later than the beginning of this week. DEADLINE