International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 353
Case Study on “Budget and Schedule Overrun during the Construction
phase of Project”
Shubham S. Deshmukh1, Shubham D. Menkudle2
1Post Graduates students, Construction Management, MIT ADT University, MIT College of Management,
Pune -412201
2Post Graduates students, Construction Management, MIT ADT University, MIT College of Management,
Pune -412201
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Delay and budget overrun are inherent part of
most projects despite the much acquired knowledge inproject
management. It is important to note that physical and
economic scale of projects today is such that it is driven under
the platform of profit to the parent organization, and of
national interest (for government projects) by the degree of
success defined within the Iron triangle of cost, time, and
scope. It is therefore much appreciatedtolookatsomereasons
of delays and cost overrun in project and their mitigation
process, so as to increase the perception of project success. In
this industry it is well known that most construction projects
are exposed to time and cost overrun. Literatures of previous
studies were classified into two main parts which are factors
effecting: (1) Schedule overruns of project; (2) Budget
overrun. Most studies like these were revised which also
included the study of the factors mentioned above in many
countries The aim of this study is to evaluate factors
consequence time and cost overruns on construction projects
in India. The objectives of the study were concluded through
valid applications. The study clarified that “Lack of
maintenance of the equipment” “Poor procurement
programming of materials, Strikes, riots and other external
factors was the most critical factor that influence project
delay. The study illustrated that "delayin preliminaryhanding
over the site" “Low productivity of labour" wasoneofthemost
important factors that may lead to Budget overrun. Also it
clarified that contractor's delay of material delivery and
equipment has led to cost overrun. Thestudyalso clarifiedthat
prices inflation highly contributes to cost overrun.
Key Words: Budget Overrun, Schedule Overrun, Construction
Projects.
1. INTRODUCTION
In this construction industry, physical development can be
achieved, and that is truly the wheel of the national
economy. The increasing complexity of infrastructure
projects and the environment within which they are
constructed place greater and higher demands on
construction managers to deliver projects on time, within
the planned budget and with high quality. Infrastructure
plays an important role in the economic growth of our
country. Today, India is one of the leading outsourcing
centre in the world. Besides this,duetovariousissues,larger
number of infrastructure projects in India arebeingdelayed.
Delay and budget overrun are inherent part of mostprojects
despite the much acquired knowledge in project
management. It is important to note that physical and
economic scale of projects today is such that it is driven
under the platform of profit to the parent organization, and
of national interest (for government projects) by the degree
of success defined within the Iron triangle of cost, time, and
scope. It is therefore much appreciated to look at some
reasons of delays and cost overrun in project and their
mitigation process, so as to increase the perception of
project success.
Here we took the several projects as a case study
over which we can show how the budget and schedule
overrun during its construction phase of project and give
remedies to the same. The name of the project or place was
kept confidential as the company polices.
1.1 Indian Construction Sector
The successful execution of construction projects and
keeping them within estimated cost and prescribed
schedules depends upon methods that require sound
engineering judgment. But, because of the disapproval of
owners, contractors and consultants, however, many
projects struggle huge delays and therebyexceedinitial time
and cost estimates. This problem is more obvious in the
traditional contracts in which the contract is awarded to the
lowest bidding contractor. Although the construction
industry in our country has been suffered ever since last
decade, recent activities in the region with the restructuring
of economies and attracting foreigninvestmentareexpected
to yield a miraculous growth in the construction industry.
Therefore, cost-effectiveness and timeliness could improve
construction efficiency that would certainly contribute to
cost savings for the country. Effectiveness of cost and time
were linked with managing costandtime,whichinthisstudy
were approached via investigating timeandcostoverrunsof
construction projects in India. In the construction industry,
physical development can be achieved whichisthewheel of
the national economy. The more materials, engineering
labour, resources, equipment, and capital market exchange
are provided within the national economy, the higher is the
effect of the extent of self-confidence. The increasing
complexity of infrastructure projects and the surrounding
within which they are to be constructed place higher
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 354
demands on construction manager to deliver projects on
time in the planned budget and with high quality.
1.2 Schedule Overrun
Schedule Overrun occurs when a project’s time restrictionis
violated. In other words project doesn’t meet its expected
deadline as some of tasks from its Critical Path have been
delayed by the project team. Schedule Overrun makes the
Project Client not satisfied by performance of the team, as
the project has run out of its predefined timeframes, but the
desired project haven’t been handing over to the Client yet.
Schedule overrun may mean not only non-meeting of the
final due date of a project, but also missing to match
predefined project milestones while this project is still in
process, which may underlie further delay if not rectified as
appropriate.
1.3 Budget Overrun
A Budget overrun, also known as a cost increase,underrated
or cost overrun, involves unexpected costs incurred in
excess of budgeted amounts due to an underestimation of
the actual cost during budgeting. Budget overrun should be
distinguished from cost escalation, which is an anticipated
growth in a budgeted cost due to factors such as inflation.
Final Contract – Original Contract
Cost Overrun = Amount Amount
Original Contract
Amount
2. LITERATURE REVIEW
Vaibhav Y. Katre,Dr.D.M.Ghaitidak(2016),“Elements of
Cost and Schedule Overrun in Construction Projects”
They Studied the existing projects where the cost and time
overrun affects the project and make bad impact in market
by interviewing the project manager and related personal.
They analyze the fact and give suggestion to the project
related companies to improve managerial skills by
conducting training program and workshops and also
improve communication between project participants in
project phase.
T. Subramani, et al (2014), “Causes of Cost Overrun in
Construction” The industry plays a pivotal role in
developing the country’s infrastructure, a pre-requisite for
high levels of economic growth. Most construction projects
experience cost overrun and it put massive financial burden
on the client or owner. Therefore this research was carried
out to identify the causes leading to cost overrun in
construction projects. Desk study along with questionnaire
survey was used to identify the causes of cost overrun. A
total of 30 filled questionnaires were collected from clients,
consultants and contractors. From the analysis oftheresults
it was found that consensus of opinion exists between
respondents on the causes of cost overrun. The results
showed that, slow decision making, poor schedule
management, increase in material/machine prices, poor
contract management, poor design/ delay in providing
design, rework due to wrong work, problems in land
acquisition, wrong estimation/ estimation method,andlong
period between design and time of bidding/tendering are
the major causes of cost overrun.
Ram Singh (2009), “Delays and Cost Overruns in
Infrastructure Projects: An Enquiry into Extents, Causes
and Remedies”
Ram Singh say media reports abound on instances of
prolonged delays and excessive cost overruns in
infrastructure projects. Only a small number of projects get
delivered in time and within the budget. Examples of
successful project implementation, like construction of the
Delhi Metro Rail, are few and appear only far in between.
Indeed, the problem of time and cost overruns in India is
widespread and severe. Yet, very few empirical studiesexist
on the subject. Even rarer are the studies based on
completed projects. As a result, the extents as well as the
causes behind delays and cost overruns have remained
under researched. This study investigates the variousissues
related to delays and cost overruns in publically funded
infrastructure projects.
Sai Murali Krishna Reddy.Raya and S.S Bhanu Prakash
(2016), “Cost and Time Overrun in Indian Construction
Industry”
A lot of research and studies have been done to identify the
root cause of the time overrun and cost overrun in
construction projects which lead to the delay in the project
completion Time and cost are the lifelines of any and every
project. It is of supreme importance to study, analyze and
evaluate the common factors leading to these constraints
and suggest the best mitigation measures to overcome time
and cost overrun constraints. During the constructionphase
it is the prime responsibility of the project managers to
monitor cost and time and avoid the overruns of the both
cost and time. Due to these limitations, this paper discusses
the effective cost and time control overrun practices in
construction industry.
Ramanathan ChidambaramandNarayananSambuPotty
(2014), “Qualitative analysis of Time delay and Cost
overrun in Multiple Design and Build Projects”
Projects are more complicated involving huge contract
values, participants from multi-discipline, more specialized
works, tighter schedule, stringent quality standards, etc.
Ultimately, cost and time are the two key parameters that
plays significant role in a project success. The study focuses
on multiple Design and Build project which has complicated
risk and is governed by fixed contract sum (Lump sum). As
such, there is no such specific study to address this problem
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 355
faced in Malaysia constructionindustry.Qualitative research
was applied at three stages of projects for time delay and
two aspects for cost overrun. This paper presentsoneaspect
each for time delay and cost overrun.
3. Problem Statement and Objective
A. Problem Statement
1. Material Unavailability.
2. Design Errors
3. Scope Changes
4. Inappropriate and inadequate procurement
5. Lack of project leadership skills.
6. Communication problem between project participants
B. Objective
1. Analyses for rectifying the factors that significantly affect
budget overruns and schedule overrun.
2. To find out the impact of over-runs on the stakeholders.
3. To analyze how frequent of these causes occur.
4. To study how the factors of differenttypeshelpinincrease
budget overrun and schedule overrun in the construction
industry and make a mitigation plan for it.
5. Investigation of the reasons and the responsibilities for
cost overruns and schedule delays by collecting, reviewing,
processing and analyzing change order and contract
information data.
4. Methodology
1. Identifying the project which currently under Budget
overrun and schedule overrun, Data collection of current
ongoing projects by interviewing the project authorities and
contractors to find out the problem.
2. Find out the factor which influence the schedule and
Budget overrun
3. Study of all the documents which are related to the
projects like drawings, BOQ’s, Work orders, Budget sheet,
etc.
3. Suggest the remedies to the problem.
5. Case Study/Data Collection
Two Residential projectswasselectedforcasestudy
but the Name of project and Company are kept confidential
as per the company polices. So both the projects are under
construction phase in which one is the Premium Class
project and other is Economic Class Project. Both Projects
have different Cash flows and Different Specifications.These
Case Study analyses the main reason for Schedule overrun
and its direct impact on the Budget of the project. There are
many risk factors involves in construction phase of project.
With the help of Project In-charge of both projects we came
to know about the actual causes of schedule and budget
overrun.
Premium class project are having 1st quality high
cost related materials where Economy class projects having
middle class of material like in Flooring Premium class
project having Italian marble and in Economy class project
having Vitrified tiles. Such kind of specification makes
procurement more complex during construction phase. The
main reason for Schedule overrun and budget overrun was
explained by the in-charge suchasprocurement plans,scope
finalization period, customer changes, Raw material Non -
availability, Drawing finalization, Technical clearance, Co-
ordination with Contractors and stack holder of the projects
or supporting team, etc.
Table 5.1- Details of Project 1
Table 5.2- Details of Project 2
Comparison based on actual status of the project is given.
Both the project are having different site conditions, so it is
also to be take into consideration while planningtheproject.
Sr.
No
Name Details
1 Project Type Premium Class
2 Project Start Date 20 March 2017
3 Project Finish Date 20 April 2020
4 Actual Start Date 20 March 2017
5 Actual Finish Date as per
current Tracking Status
16 Sep 2020
6 Delay in Days 149 Days
7 Planned Cost at 100%
Project
Completion(Approx.)
228 Cr.
8 Actual Cost at 30% Project
Completion (Approx.)
69.5 Cr.
9 Expected Cost to be spend
(Approx.)
68 Cr
10 Increased Cost 1.5 Cr.
Sr.
No
Name Details
1 Project Type Economic Class
2 Project Start Date 1 June 2017
3 Project Finish Date 31 Dec 2019
4 Actual Start Date 1 June 2017
5 Actual Finish Date as per
current Tracking Status
25 March 2020
6 Delay in Days 85 Days
7 Planned Cost at 100%
Project
Completion(Approx.)
200 Cr.
8 Actual Cost at 60% Project
Completion (Approx.)
122 Cr.
9 Expected Cost to be spend
(Approx.)
120 Cr
10 Increased Cost 2 Cr.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 356
By Studying the BOQ’s related to various Activities,
it has been observed that BOQ which are made by the
Estimation Department of the company are having
approximate Quantities which are to be used for preparing
the budget of the project but when it comes to actual
measurement of the quantity to pass the Running account
bills, It shows increased amount of calculated amount in
BOQ’s, So It basically increase the Cost of the project.
Schedule which are made at initial stage of the
project are based on initial data but when it comes to actual
tracking of the project it shows delay in the progress due to
Predicted duration of the activity without referring
methodology of that activities and manpower also.
6. Study analysis/ Suggestion Given-
i. Make a Practical schedule considering Site
Condition, Climate Conditions, Holidays, Labour
Productivity and No. of contractors which are
working for finishing activities.
ii. Freeze the Scope of work
iii. Budget shall be created by considering extra items
which are involved later on stage of the project or
kept extra contingency percentage.
iv. Make Procurement Schedule at the initial sage of
the project so that it would meet the requirementof
project as per schedule and also keep the current
progress update of site.
v. Drawing Tracking schedule also need to maintain
for early delivery of “Good for construction”
Drawings on Site.
vi. 4 Month Rolling Plan shall be prepared and Track
on Monthly basis.
vii. Tender schedule shall be prepared as per Micro
Activity which are required to complete the project
including its lead period.
viii. Prepare the Cash flow report required for the next
Four month of the project for effective tracking on
Cash.
ix. Weekly Tracking/ Monitoring of the activity
required on site by planning team so that action to
be taken on critical activities before it get delayed.
7. Conclusion
Time and cost overrun have been a major recurring
problem in construction industry. Brief reasons for time
overruns as reported by various project implementing
agencies are delay in land acquisition, delay in equipment
erection, inadequate mobilization by the contractor,delayin
forest clearance, fund constraints, change in scope of work,
cancellation of tender, law & order problem, delay in supply
of equipment, slow progress of civil work, escalation in cost
Realizing the importance of subject, construction
delay not only results in time overrun but also in cost
overrun. There are various causes due to which project
suffers from these delays. As the project is running on many
number of factors & participant, these all are having
individual causes. But the importantparticipantslikeowner,
contractor, and consultant have more influence on project
performance. Hence the causes of these participants are
discussed which will helpful to improve the project delivery
in terms of time as well as cost efficient.
Study analysis or Suggestion which are given is
useful to reduce the Budget and schedule overrun during
construction phase of project.
REFERENCES
[1] Arvan, L. and Leite. (1990),'CostOverrunsinLong-Term
Project,' International Journal ofIndustrial Organization,
8(3), 443-67M. Young, The Technical Writer’s
Handbook. Mill Valley, CA: University Science, 1989.
[2] Ramanathan Chidambaram, and Narayanan Sambu
Potty(2014), “Qualitative analysis of Time delay and
Cost overrun in Multiple Design and Build Projects”
International Conference Data Mining, Civil and
Mechanical Engineering, Bali (Indonesia)
[3] T.Subramani, P S Sruthi , M.Kavitha(2014), “Causes of
Cost Overrun In Construction” 1 Professor & Dean,
Department of Civil Engineering, VMKV Engg. College,
Vinayaka Missions University, Salem,India 2PGStudent
of Construction Engineering and management,
Department of Civil Engineering, VMKV Engg.
College,Vinayaka Missions University, Salem, India 3
Managing Director, Priyanka Associates, Civil
Engineering Consultant and Valuers, Salem ISSN (e):
2250-3021, ISSN (p): 2278-8719 Vol. 04, Issue 06(June.
2014), ||V3|| PP 01-07
[4] Sai Murali Krishna Reddy.Raya and S.S Bhanu Prakash
(2016), “Cost and Time Overrun in Indian Construction
Industry” Industrial Science Research Journal,2(4),1-9.
[5] Vaibhav Y. Katre, Dr. D.M. Ghaitidak (2016), “Elements
of Cost and Schedule Overrun in Construction Projects”
e-ISSN: 2278-067X, p-ISSN: 2278-800X, www.ijerd.com
Volume 12, Issue 7 (July 2016), PP.64-68
[6] Ram Singh (2009), “Delays and Cost Overruns in
Infrastructure Projects: An Enquiry into Extents,Causes
and Remedies” Department of Economics Delhi School
of Economics University of Delhi
[7] N.Hamezah ,M.A.Khoiry,I . Arshad, N.M.Tawil and A.I.
Che Ani (2011)“Causes of construction Delay Theoretical
framework”

Mais conteúdo relacionado

Mais procurados

Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Associate Professor in VSB Coimbatore
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...IJERA Editor
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET Journal
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Charles Abraham Scheck
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )Engr_Emad Khan
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Journals
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsIRJET Journal
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET Journal
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectIRJET Journal
 

Mais procurados (19)

Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
 
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
A Study of Factors Caused for Time & Cost Overruns in Construction Project & ...
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
Time overruns
Time overrunsTime overruns
Time overruns
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
Risk management
Risk managementRisk management
Risk management
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
20320140503023
2032014050302320320140503023
20320140503023
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
IRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction ProjectsIRJET- Analysis of Cost Overrun in Construction Projects
IRJET- Analysis of Cost Overrun in Construction Projects
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 

Semelhante a IRJET- Case Study on Budget and Schedule Overrun During the Construction Phase of Project

Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET Journal
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfKarthikeyanP288430
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docxEbrahimJemal4
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET Journal
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...IRJET Journal
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...IRJET Journal
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...ijtsrd
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTIRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTIRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 

Semelhante a IRJET- Case Study on Budget and Schedule Overrun During the Construction Phase of Project (20)

Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx10.11648.j.jccee.20160101.13756.docx
10.11648.j.jccee.20160101.13756.docx
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 
Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...Investigating the Effectiveness of Construction Practices in Delayed Resident...
Investigating the Effectiveness of Construction Practices in Delayed Resident...
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 

Mais de IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

Mais de IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Último

Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 

Último (20)

POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 

IRJET- Case Study on Budget and Schedule Overrun During the Construction Phase of Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 353 Case Study on “Budget and Schedule Overrun during the Construction phase of Project” Shubham S. Deshmukh1, Shubham D. Menkudle2 1Post Graduates students, Construction Management, MIT ADT University, MIT College of Management, Pune -412201 2Post Graduates students, Construction Management, MIT ADT University, MIT College of Management, Pune -412201 ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Delay and budget overrun are inherent part of most projects despite the much acquired knowledge inproject management. It is important to note that physical and economic scale of projects today is such that it is driven under the platform of profit to the parent organization, and of national interest (for government projects) by the degree of success defined within the Iron triangle of cost, time, and scope. It is therefore much appreciatedtolookatsomereasons of delays and cost overrun in project and their mitigation process, so as to increase the perception of project success. In this industry it is well known that most construction projects are exposed to time and cost overrun. Literatures of previous studies were classified into two main parts which are factors effecting: (1) Schedule overruns of project; (2) Budget overrun. Most studies like these were revised which also included the study of the factors mentioned above in many countries The aim of this study is to evaluate factors consequence time and cost overruns on construction projects in India. The objectives of the study were concluded through valid applications. The study clarified that “Lack of maintenance of the equipment” “Poor procurement programming of materials, Strikes, riots and other external factors was the most critical factor that influence project delay. The study illustrated that "delayin preliminaryhanding over the site" “Low productivity of labour" wasoneofthemost important factors that may lead to Budget overrun. Also it clarified that contractor's delay of material delivery and equipment has led to cost overrun. Thestudyalso clarifiedthat prices inflation highly contributes to cost overrun. Key Words: Budget Overrun, Schedule Overrun, Construction Projects. 1. INTRODUCTION In this construction industry, physical development can be achieved, and that is truly the wheel of the national economy. The increasing complexity of infrastructure projects and the environment within which they are constructed place greater and higher demands on construction managers to deliver projects on time, within the planned budget and with high quality. Infrastructure plays an important role in the economic growth of our country. Today, India is one of the leading outsourcing centre in the world. Besides this,duetovariousissues,larger number of infrastructure projects in India arebeingdelayed. Delay and budget overrun are inherent part of mostprojects despite the much acquired knowledge in project management. It is important to note that physical and economic scale of projects today is such that it is driven under the platform of profit to the parent organization, and of national interest (for government projects) by the degree of success defined within the Iron triangle of cost, time, and scope. It is therefore much appreciated to look at some reasons of delays and cost overrun in project and their mitigation process, so as to increase the perception of project success. Here we took the several projects as a case study over which we can show how the budget and schedule overrun during its construction phase of project and give remedies to the same. The name of the project or place was kept confidential as the company polices. 1.1 Indian Construction Sector The successful execution of construction projects and keeping them within estimated cost and prescribed schedules depends upon methods that require sound engineering judgment. But, because of the disapproval of owners, contractors and consultants, however, many projects struggle huge delays and therebyexceedinitial time and cost estimates. This problem is more obvious in the traditional contracts in which the contract is awarded to the lowest bidding contractor. Although the construction industry in our country has been suffered ever since last decade, recent activities in the region with the restructuring of economies and attracting foreigninvestmentareexpected to yield a miraculous growth in the construction industry. Therefore, cost-effectiveness and timeliness could improve construction efficiency that would certainly contribute to cost savings for the country. Effectiveness of cost and time were linked with managing costandtime,whichinthisstudy were approached via investigating timeandcostoverrunsof construction projects in India. In the construction industry, physical development can be achieved whichisthewheel of the national economy. The more materials, engineering labour, resources, equipment, and capital market exchange are provided within the national economy, the higher is the effect of the extent of self-confidence. The increasing complexity of infrastructure projects and the surrounding within which they are to be constructed place higher
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 354 demands on construction manager to deliver projects on time in the planned budget and with high quality. 1.2 Schedule Overrun Schedule Overrun occurs when a project’s time restrictionis violated. In other words project doesn’t meet its expected deadline as some of tasks from its Critical Path have been delayed by the project team. Schedule Overrun makes the Project Client not satisfied by performance of the team, as the project has run out of its predefined timeframes, but the desired project haven’t been handing over to the Client yet. Schedule overrun may mean not only non-meeting of the final due date of a project, but also missing to match predefined project milestones while this project is still in process, which may underlie further delay if not rectified as appropriate. 1.3 Budget Overrun A Budget overrun, also known as a cost increase,underrated or cost overrun, involves unexpected costs incurred in excess of budgeted amounts due to an underestimation of the actual cost during budgeting. Budget overrun should be distinguished from cost escalation, which is an anticipated growth in a budgeted cost due to factors such as inflation. Final Contract – Original Contract Cost Overrun = Amount Amount Original Contract Amount 2. LITERATURE REVIEW Vaibhav Y. Katre,Dr.D.M.Ghaitidak(2016),“Elements of Cost and Schedule Overrun in Construction Projects” They Studied the existing projects where the cost and time overrun affects the project and make bad impact in market by interviewing the project manager and related personal. They analyze the fact and give suggestion to the project related companies to improve managerial skills by conducting training program and workshops and also improve communication between project participants in project phase. T. Subramani, et al (2014), “Causes of Cost Overrun in Construction” The industry plays a pivotal role in developing the country’s infrastructure, a pre-requisite for high levels of economic growth. Most construction projects experience cost overrun and it put massive financial burden on the client or owner. Therefore this research was carried out to identify the causes leading to cost overrun in construction projects. Desk study along with questionnaire survey was used to identify the causes of cost overrun. A total of 30 filled questionnaires were collected from clients, consultants and contractors. From the analysis oftheresults it was found that consensus of opinion exists between respondents on the causes of cost overrun. The results showed that, slow decision making, poor schedule management, increase in material/machine prices, poor contract management, poor design/ delay in providing design, rework due to wrong work, problems in land acquisition, wrong estimation/ estimation method,andlong period between design and time of bidding/tendering are the major causes of cost overrun. Ram Singh (2009), “Delays and Cost Overruns in Infrastructure Projects: An Enquiry into Extents, Causes and Remedies” Ram Singh say media reports abound on instances of prolonged delays and excessive cost overruns in infrastructure projects. Only a small number of projects get delivered in time and within the budget. Examples of successful project implementation, like construction of the Delhi Metro Rail, are few and appear only far in between. Indeed, the problem of time and cost overruns in India is widespread and severe. Yet, very few empirical studiesexist on the subject. Even rarer are the studies based on completed projects. As a result, the extents as well as the causes behind delays and cost overruns have remained under researched. This study investigates the variousissues related to delays and cost overruns in publically funded infrastructure projects. Sai Murali Krishna Reddy.Raya and S.S Bhanu Prakash (2016), “Cost and Time Overrun in Indian Construction Industry” A lot of research and studies have been done to identify the root cause of the time overrun and cost overrun in construction projects which lead to the delay in the project completion Time and cost are the lifelines of any and every project. It is of supreme importance to study, analyze and evaluate the common factors leading to these constraints and suggest the best mitigation measures to overcome time and cost overrun constraints. During the constructionphase it is the prime responsibility of the project managers to monitor cost and time and avoid the overruns of the both cost and time. Due to these limitations, this paper discusses the effective cost and time control overrun practices in construction industry. Ramanathan ChidambaramandNarayananSambuPotty (2014), “Qualitative analysis of Time delay and Cost overrun in Multiple Design and Build Projects” Projects are more complicated involving huge contract values, participants from multi-discipline, more specialized works, tighter schedule, stringent quality standards, etc. Ultimately, cost and time are the two key parameters that plays significant role in a project success. The study focuses on multiple Design and Build project which has complicated risk and is governed by fixed contract sum (Lump sum). As such, there is no such specific study to address this problem
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 355 faced in Malaysia constructionindustry.Qualitative research was applied at three stages of projects for time delay and two aspects for cost overrun. This paper presentsoneaspect each for time delay and cost overrun. 3. Problem Statement and Objective A. Problem Statement 1. Material Unavailability. 2. Design Errors 3. Scope Changes 4. Inappropriate and inadequate procurement 5. Lack of project leadership skills. 6. Communication problem between project participants B. Objective 1. Analyses for rectifying the factors that significantly affect budget overruns and schedule overrun. 2. To find out the impact of over-runs on the stakeholders. 3. To analyze how frequent of these causes occur. 4. To study how the factors of differenttypeshelpinincrease budget overrun and schedule overrun in the construction industry and make a mitigation plan for it. 5. Investigation of the reasons and the responsibilities for cost overruns and schedule delays by collecting, reviewing, processing and analyzing change order and contract information data. 4. Methodology 1. Identifying the project which currently under Budget overrun and schedule overrun, Data collection of current ongoing projects by interviewing the project authorities and contractors to find out the problem. 2. Find out the factor which influence the schedule and Budget overrun 3. Study of all the documents which are related to the projects like drawings, BOQ’s, Work orders, Budget sheet, etc. 3. Suggest the remedies to the problem. 5. Case Study/Data Collection Two Residential projectswasselectedforcasestudy but the Name of project and Company are kept confidential as per the company polices. So both the projects are under construction phase in which one is the Premium Class project and other is Economic Class Project. Both Projects have different Cash flows and Different Specifications.These Case Study analyses the main reason for Schedule overrun and its direct impact on the Budget of the project. There are many risk factors involves in construction phase of project. With the help of Project In-charge of both projects we came to know about the actual causes of schedule and budget overrun. Premium class project are having 1st quality high cost related materials where Economy class projects having middle class of material like in Flooring Premium class project having Italian marble and in Economy class project having Vitrified tiles. Such kind of specification makes procurement more complex during construction phase. The main reason for Schedule overrun and budget overrun was explained by the in-charge suchasprocurement plans,scope finalization period, customer changes, Raw material Non - availability, Drawing finalization, Technical clearance, Co- ordination with Contractors and stack holder of the projects or supporting team, etc. Table 5.1- Details of Project 1 Table 5.2- Details of Project 2 Comparison based on actual status of the project is given. Both the project are having different site conditions, so it is also to be take into consideration while planningtheproject. Sr. No Name Details 1 Project Type Premium Class 2 Project Start Date 20 March 2017 3 Project Finish Date 20 April 2020 4 Actual Start Date 20 March 2017 5 Actual Finish Date as per current Tracking Status 16 Sep 2020 6 Delay in Days 149 Days 7 Planned Cost at 100% Project Completion(Approx.) 228 Cr. 8 Actual Cost at 30% Project Completion (Approx.) 69.5 Cr. 9 Expected Cost to be spend (Approx.) 68 Cr 10 Increased Cost 1.5 Cr. Sr. No Name Details 1 Project Type Economic Class 2 Project Start Date 1 June 2017 3 Project Finish Date 31 Dec 2019 4 Actual Start Date 1 June 2017 5 Actual Finish Date as per current Tracking Status 25 March 2020 6 Delay in Days 85 Days 7 Planned Cost at 100% Project Completion(Approx.) 200 Cr. 8 Actual Cost at 60% Project Completion (Approx.) 122 Cr. 9 Expected Cost to be spend (Approx.) 120 Cr 10 Increased Cost 2 Cr.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 356 By Studying the BOQ’s related to various Activities, it has been observed that BOQ which are made by the Estimation Department of the company are having approximate Quantities which are to be used for preparing the budget of the project but when it comes to actual measurement of the quantity to pass the Running account bills, It shows increased amount of calculated amount in BOQ’s, So It basically increase the Cost of the project. Schedule which are made at initial stage of the project are based on initial data but when it comes to actual tracking of the project it shows delay in the progress due to Predicted duration of the activity without referring methodology of that activities and manpower also. 6. Study analysis/ Suggestion Given- i. Make a Practical schedule considering Site Condition, Climate Conditions, Holidays, Labour Productivity and No. of contractors which are working for finishing activities. ii. Freeze the Scope of work iii. Budget shall be created by considering extra items which are involved later on stage of the project or kept extra contingency percentage. iv. Make Procurement Schedule at the initial sage of the project so that it would meet the requirementof project as per schedule and also keep the current progress update of site. v. Drawing Tracking schedule also need to maintain for early delivery of “Good for construction” Drawings on Site. vi. 4 Month Rolling Plan shall be prepared and Track on Monthly basis. vii. Tender schedule shall be prepared as per Micro Activity which are required to complete the project including its lead period. viii. Prepare the Cash flow report required for the next Four month of the project for effective tracking on Cash. ix. Weekly Tracking/ Monitoring of the activity required on site by planning team so that action to be taken on critical activities before it get delayed. 7. Conclusion Time and cost overrun have been a major recurring problem in construction industry. Brief reasons for time overruns as reported by various project implementing agencies are delay in land acquisition, delay in equipment erection, inadequate mobilization by the contractor,delayin forest clearance, fund constraints, change in scope of work, cancellation of tender, law & order problem, delay in supply of equipment, slow progress of civil work, escalation in cost Realizing the importance of subject, construction delay not only results in time overrun but also in cost overrun. There are various causes due to which project suffers from these delays. As the project is running on many number of factors & participant, these all are having individual causes. But the importantparticipantslikeowner, contractor, and consultant have more influence on project performance. Hence the causes of these participants are discussed which will helpful to improve the project delivery in terms of time as well as cost efficient. Study analysis or Suggestion which are given is useful to reduce the Budget and schedule overrun during construction phase of project. REFERENCES [1] Arvan, L. and Leite. (1990),'CostOverrunsinLong-Term Project,' International Journal ofIndustrial Organization, 8(3), 443-67M. Young, The Technical Writer’s Handbook. Mill Valley, CA: University Science, 1989. [2] Ramanathan Chidambaram, and Narayanan Sambu Potty(2014), “Qualitative analysis of Time delay and Cost overrun in Multiple Design and Build Projects” International Conference Data Mining, Civil and Mechanical Engineering, Bali (Indonesia) [3] T.Subramani, P S Sruthi , M.Kavitha(2014), “Causes of Cost Overrun In Construction” 1 Professor & Dean, Department of Civil Engineering, VMKV Engg. College, Vinayaka Missions University, Salem,India 2PGStudent of Construction Engineering and management, Department of Civil Engineering, VMKV Engg. College,Vinayaka Missions University, Salem, India 3 Managing Director, Priyanka Associates, Civil Engineering Consultant and Valuers, Salem ISSN (e): 2250-3021, ISSN (p): 2278-8719 Vol. 04, Issue 06(June. 2014), ||V3|| PP 01-07 [4] Sai Murali Krishna Reddy.Raya and S.S Bhanu Prakash (2016), “Cost and Time Overrun in Indian Construction Industry” Industrial Science Research Journal,2(4),1-9. [5] Vaibhav Y. Katre, Dr. D.M. Ghaitidak (2016), “Elements of Cost and Schedule Overrun in Construction Projects” e-ISSN: 2278-067X, p-ISSN: 2278-800X, www.ijerd.com Volume 12, Issue 7 (July 2016), PP.64-68 [6] Ram Singh (2009), “Delays and Cost Overruns in Infrastructure Projects: An Enquiry into Extents,Causes and Remedies” Department of Economics Delhi School of Economics University of Delhi [7] N.Hamezah ,M.A.Khoiry,I . Arshad, N.M.Tawil and A.I. Che Ani (2011)“Causes of construction Delay Theoretical framework”