DECLARATION BY STUDENT
I hereby declare that work entitled “Summer training project report”,
Submitted towards completion of vocational training after second year
of B.Tech (MECHANICAL) at PDPM-IIITDM JABALPUR
comprises of my original work
pursued under the supervision of guides at NTPC Sipat.
The results embodied in this report have not been submitted to any
other Institute or University for the fulfillment of any other curriculum.
Harshit Kumar Gupta
MECH ENGG.(4TH SEM)
PDPM-IIITDM JABALPUR
CERTIFICATE
This is to certify that Mr. Harshit Kumar Gupta Of PDPM
IIITDM JABALPUR has undergone vocational
training from 21-05-2012 to 18-06-2012 at NATIONAL
THERMAL POWER CORPORATION SIPAT (C.G.) in the
COAL HANDLING PLANT and has made the project
under my guidance.
Under the guidance of :-
Mr.M.C.Mitra
Sr.Supdt.(CHP/MM)
ACKNOWLEDGEMENT
“It is not possible to prepare a project report without the assistance and encouragement of other people.This
one is certainly no exception”
On the very outset of this report, I would like to extend my sincere and heartfelt obligation towards all the personages
who have helped me in this endeavor. Without there active guidance, help, cooperation and encouragement, I would
not have made head way in the project. First and foremost, I would like to express my sincere gratitude to my project
Guide Mr. M.C.Mitra.
I was privileged to experience a sustained enthusiastic and involved interest from his side .
I would also like to thank Mr. D.S.Patil, Mr. Sameer Ekka, Mr. A.K.Singh, who instead of their busy schedule, always
guided me in right direction to head and also helped me in understanding Coal Handling Plant.
Last but not the least, I would like to thank Mr. Pravin Patel, for the allotment in the C.H.P. Batch of Vocational
Trainees.
I would like to thank Employee Development Center for organizing and permitting the Vocational Training Program for
us.
Thanking You,
Harshit Kumar Gupta
POWER PLANT
FAMILRISATION
NTPC SIPAT
660MW X 3 , 500MW X 2
“Salient features of NTPC Sipat”
For the first time in the history of India, a thermal plant using Super Critical technology
is constructed. In addition to this a 765KV transmission system is used for the first
time in the country.
• The ultimate capacity of the plant was originally conceived as 3000MW. Thereafter,
Sipat project was reconfigured as follows:
• Thus the implementation of the project started in June 2007. It was to be completed
in two stages.
• Stage 1: 3*660 MW
• Stage 2: 2*500 MW
• The estimated cost for stage 1 was 7860.20 crores and for the stage 2 were 3785.18
crores. The coal source of this project is DIPKA Expansion project of SECL in Korba
(CG). Total coal linkage in the system is 15.04 million ton/year. The coal
transportation is carried on by MERRY GO ROUND system between the two projects.
This is to avoid transportation discrepancies and for the smooth functioning of the
plant.
• The water requirement for the plant is fulfilled from Hasdeo RBC, through 26 km
pipeline from Hardi Vishal.
• The beneficiary states are Chattisgarh, Gujarat, Madhya Pradesh, Maharashtra, goa,
Daman & Diu and Dadra & Nagar Haveli.|~|
A THERMAL POWER PLANT
MAINLY CONSISTS OF….
• 1.COAL HANDLING UNIT.
• 2.BOILER or STEAM GENERATOR UNIT.
• 3.TURBINE & ELECTRIC GENERATOR UNIT
• 4.CONDENSATION AND COOLING WATER
UNIT
• 5. ASH HANDLING PLANT
COAL
HANDLING
PLANT (CHP)
CHP MAINLY CONSISTS…
• TRACK HOOPER
• PADDLE FEEDER
• CONVEYER BELT
• MAGNETIC SEPRATOR
• CRUSHER HOUSE
• VGF
• TRANSFER POINTS
• STACKER
• STOCKYARD/COAL PILES
• The function of a CHP is to receive, process, store &
feed the Coal bunkers consistently over the entire
life of the Power plant.
• Coal is received from mines in the form of lumps, the
sizes varying from 100mm to 350mm,BOBR meaning
Bogie Open Bottom Rapid discharge unloaded in
TRACK HOOPERS .
(Here it comes mainly from DEEPIKA
MINES )BOBR
TRACK
HOOPER
PADDLE FEEDER
• Then this raw coal is scooped onto the
conveyer by use of PADDLE FEEDER
CONVEYER BELT…
• Now this conveyer belt moves forward and carries that
raw coal to CRUSHER HOUSE.
• In between there are equipment likes METAL
DETECTORS, SUSPENDED MAGNETS which
separates coal from METALS which is not desirable in
the production and Non-ferrous materials like stones,
shells, wood etc. are removed MANUALLY
• These belts are very strong and have steel cords inside.
• There are Normal conveyor Idlers , they are the
supporting rollers for the conveyor belt on which the coal
laden conveyor belt glides |~|
TYPICAL CONVEYER BELT…
CRUSHER HOUSE….
• Here coal received from track hoopers is fed to
VGF(Vibrating Gizzle Feeder) which allows 20(+) size
coal to go to crusher and not allow 20(-) coal to go to
crusher where there size is reduced to 20(-)
-Here we use Roller hammer type crusher .
- And there are 4 COUPLING motors located
over springs for rotating the rollers.
-Then all 20(-) coal is sent either to STOCK
YARD or to COAL BUNKERS
via appropriate TRANSFER POINTS
through CONVEYER BELT.
STACKER!!!! AND STOCK
YARD
• Coal stocks are made to meet needs in future
emergency situations.
• Stacking/ reclaiming of coal is done by bucket wheel
type stacker-cum-reclaimer moving on rails.
• The stacker-cum- reclaimer can stack coal on either
sides of the yard conveyer
• During stacking mode coal is fed from conveyors on
boom conveyor and while in reclaim mode,
boom conveyor discharges coal on the yard conveyor for
feeding coal to bunkers through conveyors and transfer
points.
• Note always water sprinklers are used to avoid fire in
COAL PILES
OPERATION OF STACKER…
• Luffing : This is vertical movement ,powered
generally by 2 hydraulic cylinders
• Traveling : The stacker moves on a rail track
enabling it to move around the stockyard as
required.
• Slewing: This is rotation of the stacker around its
central axis to align or place the stockpile where
required. This utilizes sun and planet gear type
gear box
A TYPICAL STACKER....
BOILER
OR
STEAM GENERATOR
IT MAINLY CONSISTS THESE
SYSTEMS…
• Fuel Preparation System
• Air & Flue Gas System
• Water & Steam System
• Fuel Firing System
• Deareation & Feed Pumping System
FUEL PREPRATION SYSTEM
MAINLY CONSISTS….
• TRIPPERS: This is mechanism for dropping coals from
conveyer to BUNKERS .These only allows calculated
amount of coal to be dropped in all bunkers
• COAL BUNKERS which stores coal mixture (20%
imported+ 80% Indian) and feeds this coal to
• BOWL MILLS/PULVERISER where 20(-) coal is further
crushed to powder form having 200 meshes in 1 sq inch
There is SEAL AIR FAN for sealing of mill from dust.
• PA FANS are used firstly to reduce moisture content,
secondly to heat it and lastly to transport powdered coal
to different corners of BOILER via 4 different pipes
.There are both COLD AIR DUT AND HOT AIR DUCT
TO MAINTAIN TEMP
AIR AND FLUE GAS SYSTEM
MAINLY CONSISTS ….
• FD fans provides sufficient air for combustion by taking
air from atmosphere and then heated by air
preheater(APH)
• ID fans induces negative pressure in BOILER by
drawing out combustible gases
• Flue gases generated by combustion contains quite imp
amount of heat which we utilise by sending it to
ECONOMISER and APH (to pre heat air) then cooled
flue gas is sent to ESP
• ESP (Electro Static Precipitator) where by corona
effect(cyclone separator) particles get precipitated over
electrode and flue gas escapes to atmosphere via
CHIMNEYS. Precipitate is sent to ASP(Ash Slurry
Pump) house
WATER AND STEAM SYSTEM
MAINLY CONSISTS ….
• Boiler Feed Water Pump(BFW PUMP)-which pumps
boiler feed water to ECONOMISER pressure.
• ECONOMISER –preheats BFW(all the sensible heating
of BFW is done here only)
• ****Then it goes to BOILER DRUM where saturated
steam get separated from mixed state steam by virtue of
cyclone steam separators and moisture content is again
circulated after mixing with BFW
• NOTE-* implies that this unit i.e BOILER DRUM is not
found in SUPER CRITICAL BOILERS(as there is no
region inside dome according to MODIFIED RANKINE
CYCLE . So here water is always circulated only once )
SUPER HEATERS…
• Then separated saturated steam is taken out from boiler
drum through series of nozzles and fed to series of
SUPER HEATERS.
• Firstly through DIV PANEL SH-which heats saturated
steam by about 40 degree by mode of convection
• Then this passes through PLATEN SH-which raises
temp further by next 70 degrees by mode of radiation
then it goes to FINAL SH via ATTEMPRATOR which
lowers the temp by spraying a fine stream of water(it is
done to control the temp )
• FINAL SH where remaining temp inc is picked up after
which it goes to HP turbine and get expanded
** All the superheaters used are basically CLOSED
HEATER
REHEATERS….
• Sole purpose of reheating is to devoid wet steam from
condenser which may result in EROSION OF BLADES
of turbine.
• After steam get expanded in HP turbine(upto IP say 345
degree and 45 bar) outlet steam is passed to
REHEATERS (after passing via another
ATTEMPRATOR) which heats up that steam
• LT REHEATER and HT REHEATER:where temp is
raised upto temp of inlet of HP turbine
FIRING SYSTEM MAINLY
INCLUDES…
• Powdered coal is transported by PA fans to
corners of BOILER by 4 diff pipes(having same
pressure) and is blown TANGENTIALLY(to
imaginary circle called FIRE-BALL) in furnace
from all corners leading to formation of fireball.
•
• Extra oxygen required for combustion is
provided by SECONDRY AIR
• Initially during LIGHTING UP of boiler we
first ignite coal by HFO and HLT and stop
them after initialization
• BURNER TILT MECHANISM:
DEAERATION AND FEED
PUMPING SYSTEM MAINLY
CONSISTS…
• DEAERATOR :whose main purpose is to remove air and
other gases from BFW (is mainly done otherwise they
may corrode different metals used in plant) and also to
preheat BFW . It is worth noticing that it is the only used
CLOSED TYPE HEATERS others are OPEN HEATER
• FEED PUMP: It mainly pumps BFW coming out of
deaerator to ECONOMISER pressure.
TURBINE
&
GENERATOR
• Sole purpose of turbine is to produce work by expanding
steam from very high pressure to low condenser
pressure.
• We mainly use three types of turbine here viz. 1 HP
turbine, 1 IP turbine and 2 LP turbine
• We are using different pressure turbines for reheating
purpose so that we can enhance overall efficiency of the
plant (or so that we can overcome problem of wet
steam)
• First superheated steam is allowed to expand in HPT to
some IP and then send back to boiler for reheating
purpose.
• Then this reheated steam is sent to IP turbine for
expanding where after it get expanded to some lower
pressure a BLEND steam is taken out and sent to FEED
WATER HEATER (FWH) for heating feed water (for
REGENERATION )
BASIC ASPECTS OF 500 MW
STEAM TURBINE….
GENERATOR…
• Shaft rotated at very high RPM by TURBINE is then
coupled to generator which converts rotating energy of
shafts into electrical energy.
• During this process there is large amount of heat
generation for which we require a special type of cooling
system.
• Hydrogen gas cooling, in an oil-sealed casing, is used
because it has the highest known heat transfer
coefficient of any gas and for its low viscosity which
reduces wind-age losses
• This system requires special handling during start-up,
with air in the chamber first displaced by carbon dioxide
before filling with hydrogen. This ensures that the highly
flammable hydrogen does not mix with oxygen in the air.
CONDENSATION
AND
COOLING WATER UNIT
CONDENSATION UNIT
MAINLY CONSIST OF…
• CONDENSER: which is a shell type heat exchanger in
which exhaust steam is cooled by running cooling water
(circulated through tubes) and inturn CW gets heated
and is send to COOLING TOWER for getting cooled
• Then this cooled water is extracted by CEP(Condensate
extraction pump) and heated by LPH and then to BFP
and then to HPH and then to ECONOMISER
COOLING WATER UNIT
MAINLY CONSIST OF…..
• During cooling of steam CW gets heated and
this is send to COOLING TOWERS for getting
cooled.
• Here hot CW is fed onto top of COOLING
TOWER and allowed to fall down
• Also perpendicular to direction of falling air is
allowed to blow which cools the water and gets
out from top of the tower
• Also since always some of the water losts in the
whole process either due to leakage or due to
evaporation so we supply extra water from
MAKE UP WATER PUMP
A typical COOLING TOWER
looks like…
ASH HANDLING PLANT ….
• Wherever coal is burned it is necessary to have an
efficient ash handling system, especially in a coal-fired
power station environment where large quantities of
pulverized fuel ash (PFA) are created
• The various systems involved in the ash handling system
are:
-Bottom ash handling system
-Fly ash handling system (both wet & dry)
-Slurry handling system from slurry pump house to ash dyke
-Ash water system
-Ash water recirculation system
• Basically, two types of ash are generated:
-Fly ash (approx 80%)
-Bottom ash (approx 20%)
• Ash collected in hoppers is grinded by grinders and
mixed with water and then sent to ash slurry house by
using jet pumps.
• Where it is collected in ASH PIT, from where it is
pumped to ASH POND.
• Here there is also an auxiliary pump which is used for
FLUSHING OFF blockages. |~|
• FLOW DIAGRAM OF AHP
Hopper
Clinker grinder
Scrapper
Conveyor
Overflow water
Trench
BA
Trans.
Pump
A
S
P
H
Ash
Dyke
A.S.
Pump

Mais conteúdo relacionado

Mais procurados

Ntpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardNtpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardI.E.T. lucknow
 
Power Plant Familiarization
Power Plant FamiliarizationPower Plant Familiarization
Power Plant FamiliarizationAanand Kumar
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)Rajan Kumar Choudhary
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC pptkirbadh
 
Thermal power plant
 Thermal power plant  Thermal power plant
Thermal power plant sagar20jain
 
VOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVIKASH BAGHEL
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant pptPrakash Jarotia
 
Ntpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanNtpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanBHANUKISHAN1
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationLekhraJ Meena
 
Kota Super Thermal Power Plant
Kota Super Thermal Power PlantKota Super Thermal Power Plant
Kota Super Thermal Power PlantHimanshu Dixit
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptEr. Aman Agrawal
 
A best ppt on kota super thermal power station
A best ppt on kota super thermal power stationA best ppt on kota super thermal power station
A best ppt on kota super thermal power stationNaveen Kumar
 
kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slidesDanveer Singh
 
thermal power plant at NTPC
thermal power plant at NTPCthermal power plant at NTPC
thermal power plant at NTPCricha khatri
 

Mais procurados (20)

Ntpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyardNtpc dadri thermal power plant & switchyard
Ntpc dadri thermal power plant & switchyard
 
Power Plant Familiarization
Power Plant FamiliarizationPower Plant Familiarization
Power Plant Familiarization
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
 
Summer training in NTPC ppt
Summer training in NTPC pptSummer training in NTPC ppt
Summer training in NTPC ppt
 
Thermal power plant
 Thermal power plant  Thermal power plant
Thermal power plant
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
VOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBA
 
NTPC Farakka
NTPC FarakkaNTPC Farakka
NTPC Farakka
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
Ntpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishanNtpc kahalgaon project by bhanu kishan
Ntpc kahalgaon project by bhanu kishan
 
A Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power StationA Presentation on Kota Super Thermal Power Station
A Presentation on Kota Super Thermal Power Station
 
Kota Super Thermal Power Plant
Kota Super Thermal Power PlantKota Super Thermal Power Plant
Kota Super Thermal Power Plant
 
kota Super Thermal Power Station training ppt
kota Super Thermal Power Station training pptkota Super Thermal Power Station training ppt
kota Super Thermal Power Station training ppt
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
A best ppt on kota super thermal power station
A best ppt on kota super thermal power stationA best ppt on kota super thermal power station
A best ppt on kota super thermal power station
 
kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slides
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling Plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
thermal power plant at NTPC
thermal power plant at NTPCthermal power plant at NTPC
thermal power plant at NTPC
 
Harsh ntpc
Harsh ntpcHarsh ntpc
Harsh ntpc
 

Destaque

Indian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~iIndian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~ihaxxo24
 
NTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORTNTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORTARVIND NEGI
 
Sipat thermal power plant
Sipat thermal power plantSipat thermal power plant
Sipat thermal power plantJinendra Ninama
 
comparative analysis on ntpc and nhpc
comparative analysis on ntpc and nhpccomparative analysis on ntpc and nhpc
comparative analysis on ntpc and nhpcAhMed Ŝĥãbÿ
 
CFA Challenge - Tata Power
CFA Challenge - Tata PowerCFA Challenge - Tata Power
CFA Challenge - Tata PowerPurav Sheth
 
NTPC SUMMER INTERNSHIP MBA FINANCE
NTPC SUMMER INTERNSHIP MBA FINANCENTPC SUMMER INTERNSHIP MBA FINANCE
NTPC SUMMER INTERNSHIP MBA FINANCENEHA GAUTAM
 
Power Plant Training Certificates
Power Plant Training CertificatesPower Plant Training Certificates
Power Plant Training Certificatesatavane
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
MPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training SeminarMPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training SeminarSuraj Talreja
 
THERMAL POWER PLANT PARALI
THERMAL POWER PLANT PARALITHERMAL POWER PLANT PARALI
THERMAL POWER PLANT PARALIMahendra Magre
 
Coal India Limited Report (Khagendradewangan.blogspot.in)
Coal India Limited Report (Khagendradewangan.blogspot.in)Coal India Limited Report (Khagendradewangan.blogspot.in)
Coal India Limited Report (Khagendradewangan.blogspot.in)KHAGENDRA KUMAR DEWANGAN
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavmukesh yadav
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantViren Patel
 
Small%20 arms%20factory%20final%20report
Small%20 arms%20factory%20final%20reportSmall%20 arms%20factory%20final%20report
Small%20 arms%20factory%20final%20reportPrakharBhasker
 
Nothern Coalfields Limited
Nothern Coalfields LimitedNothern Coalfields Limited
Nothern Coalfields LimitedAshz Mahajan
 

Destaque (20)

Ntpc.ppt
Ntpc.pptNtpc.ppt
Ntpc.ppt
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
 
Indian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~iIndian railways mechanical vocational training report 2 haxxo24 i~i
Indian railways mechanical vocational training report 2 haxxo24 i~i
 
NTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORTNTPC BADARPUR PROJECT REPORT
NTPC BADARPUR PROJECT REPORT
 
Sipat thermal power plant
Sipat thermal power plantSipat thermal power plant
Sipat thermal power plant
 
comparative analysis on ntpc and nhpc
comparative analysis on ntpc and nhpccomparative analysis on ntpc and nhpc
comparative analysis on ntpc and nhpc
 
CFA Challenge - Tata Power
CFA Challenge - Tata PowerCFA Challenge - Tata Power
CFA Challenge - Tata Power
 
NTPC SUMMER INTERNSHIP MBA FINANCE
NTPC SUMMER INTERNSHIP MBA FINANCENTPC SUMMER INTERNSHIP MBA FINANCE
NTPC SUMMER INTERNSHIP MBA FINANCE
 
Power Plant Training Certificates
Power Plant Training CertificatesPower Plant Training Certificates
Power Plant Training Certificates
 
Ntpc
NtpcNtpc
Ntpc
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
MPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training SeminarMPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training Seminar
 
Sumit coal
Sumit coalSumit coal
Sumit coal
 
THERMAL POWER PLANT PARALI
THERMAL POWER PLANT PARALITHERMAL POWER PLANT PARALI
THERMAL POWER PLANT PARALI
 
Coal India Limited Report (Khagendradewangan.blogspot.in)
Coal India Limited Report (Khagendradewangan.blogspot.in)Coal India Limited Report (Khagendradewangan.blogspot.in)
Coal India Limited Report (Khagendradewangan.blogspot.in)
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadav
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Small%20 arms%20factory%20final%20report
Small%20 arms%20factory%20final%20reportSmall%20 arms%20factory%20final%20report
Small%20 arms%20factory%20final%20report
 
Nothern Coalfields Limited
Nothern Coalfields LimitedNothern Coalfields Limited
Nothern Coalfields Limited
 
Internship Report
Internship ReportInternship Report
Internship Report
 

Semelhante a Ntpc (national thermal power corporation) sipat mechanical vocational training report 4 haxxo24 i~i

NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORTAnkur Pal
 
Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt nilesh choubey
 
Presentation sai,varun.
Presentation sai,varun.Presentation sai,varun.
Presentation sai,varun.Sai Kumar
 
Coal based power plant
Coal based power plantCoal based power plant
Coal based power plantGaurav Kaushik
 
Thermal power plant | Electrical Engineering | Notes | Source of Energy
Thermal power plant | Electrical Engineering | Notes | Source of EnergyThermal power plant | Electrical Engineering | Notes | Source of Energy
Thermal power plant | Electrical Engineering | Notes | Source of EnergyJayant Suthar
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantaman Singh
 
NTPC,Dadri Training presentation
NTPC,Dadri Training presentationNTPC,Dadri Training presentation
NTPC,Dadri Training presentationNitish Bhati
 
BK T. P. P. Vocational Training Report
BK T. P. P. Vocational Training ReportBK T. P. P. Vocational Training Report
BK T. P. P. Vocational Training Reportavijit1996
 
SUMMER TRAINING AT NTPC DADRI GAS SECTION
SUMMER TRAINING AT NTPC DADRI GAS SECTIONSUMMER TRAINING AT NTPC DADRI GAS SECTION
SUMMER TRAINING AT NTPC DADRI GAS SECTIONAMIT KUMAR
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plantRashmi Nimje
 
Ntpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaNtpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaPrakash Sharma
 
project report for vocational trainee
project report for vocational traineeproject report for vocational trainee
project report for vocational traineeSourav Jana
 
DG Cement Power Plants (Internship Report)
DG Cement Power Plants (Internship Report)DG Cement Power Plants (Internship Report)
DG Cement Power Plants (Internship Report)Haseeb Ahsan
 

Semelhante a Ntpc (national thermal power corporation) sipat mechanical vocational training report 4 haxxo24 i~i (20)

NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORT
 
Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt Summer training at NTPC Badarpur ppt
Summer training at NTPC Badarpur ppt
 
Industrial training
Industrial trainingIndustrial training
Industrial training
 
Presentation sai,varun.
Presentation sai,varun.Presentation sai,varun.
Presentation sai,varun.
 
Coal based power plant
Coal based power plantCoal based power plant
Coal based power plant
 
Richappt
RichapptRichappt
Richappt
 
Boilers
BoilersBoilers
Boilers
 
Thermal power plant | Electrical Engineering | Notes | Source of Energy
Thermal power plant | Electrical Engineering | Notes | Source of EnergyThermal power plant | Electrical Engineering | Notes | Source of Energy
Thermal power plant | Electrical Engineering | Notes | Source of Energy
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Steam plan
Steam planSteam plan
Steam plan
 
NTPC,Dadri Training presentation
NTPC,Dadri Training presentationNTPC,Dadri Training presentation
NTPC,Dadri Training presentation
 
BK T. P. P. Vocational Training Report
BK T. P. P. Vocational Training ReportBK T. P. P. Vocational Training Report
BK T. P. P. Vocational Training Report
 
SUMMER TRAINING AT NTPC DADRI GAS SECTION
SUMMER TRAINING AT NTPC DADRI GAS SECTIONSUMMER TRAINING AT NTPC DADRI GAS SECTION
SUMMER TRAINING AT NTPC DADRI GAS SECTION
 
Thermal power plants
Thermal power plantsThermal power plants
Thermal power plants
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plant
 
Ntpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharmaNtpc dadri ppt by pc sharma
Ntpc dadri ppt by pc sharma
 
Ntpc dadri ppt
Ntpc dadri pptNtpc dadri ppt
Ntpc dadri ppt
 
Ppt aman
Ppt amanPpt aman
Ppt aman
 
project report for vocational trainee
project report for vocational traineeproject report for vocational trainee
project report for vocational trainee
 
DG Cement Power Plants (Internship Report)
DG Cement Power Plants (Internship Report)DG Cement Power Plants (Internship Report)
DG Cement Power Plants (Internship Report)
 

Mais de haxxo24

Wagon project report mechanical vocational training presentation haxxo24 i~i
Wagon project report mechanical vocational training presentation haxxo24 i~iWagon project report mechanical vocational training presentation haxxo24 i~i
Wagon project report mechanical vocational training presentation haxxo24 i~ihaxxo24
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...haxxo24
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...haxxo24
 
South east central railway (secr) bilaspur mechanical vocational training pre...
South east central railway (secr) bilaspur mechanical vocational training pre...South east central railway (secr) bilaspur mechanical vocational training pre...
South east central railway (secr) bilaspur mechanical vocational training pre...haxxo24
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~ihaxxo24
 
Lanco amarkantak power ltd korba mechanical vocational training report 2 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 2 haxx...Lanco amarkantak power ltd korba mechanical vocational training report 2 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 2 haxx...haxxo24
 
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...haxxo24
 
Indian railways mechanical vocational training report 1 haxxo24 i~i
Indian railways mechanical vocational training report 1 haxxo24 i~iIndian railways mechanical vocational training report 1 haxxo24 i~i
Indian railways mechanical vocational training report 1 haxxo24 i~ihaxxo24
 
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...haxxo24
 
Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...haxxo24
 
Bharat aluminium company ltd. (balco) mechanical vocational training report h...
Bharat aluminium company ltd. (balco) mechanical vocational training report h...Bharat aluminium company ltd. (balco) mechanical vocational training report h...
Bharat aluminium company ltd. (balco) mechanical vocational training report h...haxxo24
 

Mais de haxxo24 (11)

Wagon project report mechanical vocational training presentation haxxo24 i~i
Wagon project report mechanical vocational training presentation haxxo24 i~iWagon project report mechanical vocational training presentation haxxo24 i~i
Wagon project report mechanical vocational training presentation haxxo24 i~i
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...
 
South east central railway (secr) bilaspur mechanical vocational training pre...
South east central railway (secr) bilaspur mechanical vocational training pre...South east central railway (secr) bilaspur mechanical vocational training pre...
South east central railway (secr) bilaspur mechanical vocational training pre...
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
 
Lanco amarkantak power ltd korba mechanical vocational training report 2 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 2 haxx...Lanco amarkantak power ltd korba mechanical vocational training report 2 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 2 haxx...
 
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...
Lanco amarkantak power ltd korba mechanical vocational training report 1 haxx...
 
Indian railways mechanical vocational training report 1 haxxo24 i~i
Indian railways mechanical vocational training report 1 haxxo24 i~iIndian railways mechanical vocational training report 1 haxxo24 i~i
Indian railways mechanical vocational training report 1 haxxo24 i~i
 
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
 
Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...Cseb (chhattisgarh state electricity board) korba east vocational training pr...
Cseb (chhattisgarh state electricity board) korba east vocational training pr...
 
Bharat aluminium company ltd. (balco) mechanical vocational training report h...
Bharat aluminium company ltd. (balco) mechanical vocational training report h...Bharat aluminium company ltd. (balco) mechanical vocational training report h...
Bharat aluminium company ltd. (balco) mechanical vocational training report h...
 

Último

Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxAmanpreet Kaur
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxAmita Gupta
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...christianmathematics
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxdhanalakshmis0310
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 

Último (20)

Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptx
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 

Ntpc (national thermal power corporation) sipat mechanical vocational training report 4 haxxo24 i~i

  • 1. DECLARATION BY STUDENT I hereby declare that work entitled “Summer training project report”, Submitted towards completion of vocational training after second year of B.Tech (MECHANICAL) at PDPM-IIITDM JABALPUR comprises of my original work pursued under the supervision of guides at NTPC Sipat. The results embodied in this report have not been submitted to any other Institute or University for the fulfillment of any other curriculum. Harshit Kumar Gupta MECH ENGG.(4TH SEM) PDPM-IIITDM JABALPUR
  • 2. CERTIFICATE This is to certify that Mr. Harshit Kumar Gupta Of PDPM IIITDM JABALPUR has undergone vocational training from 21-05-2012 to 18-06-2012 at NATIONAL THERMAL POWER CORPORATION SIPAT (C.G.) in the COAL HANDLING PLANT and has made the project under my guidance. Under the guidance of :- Mr.M.C.Mitra Sr.Supdt.(CHP/MM)
  • 3. ACKNOWLEDGEMENT “It is not possible to prepare a project report without the assistance and encouragement of other people.This one is certainly no exception” On the very outset of this report, I would like to extend my sincere and heartfelt obligation towards all the personages who have helped me in this endeavor. Without there active guidance, help, cooperation and encouragement, I would not have made head way in the project. First and foremost, I would like to express my sincere gratitude to my project Guide Mr. M.C.Mitra. I was privileged to experience a sustained enthusiastic and involved interest from his side . I would also like to thank Mr. D.S.Patil, Mr. Sameer Ekka, Mr. A.K.Singh, who instead of their busy schedule, always guided me in right direction to head and also helped me in understanding Coal Handling Plant. Last but not the least, I would like to thank Mr. Pravin Patel, for the allotment in the C.H.P. Batch of Vocational Trainees. I would like to thank Employee Development Center for organizing and permitting the Vocational Training Program for us. Thanking You, Harshit Kumar Gupta
  • 5. “Salient features of NTPC Sipat” For the first time in the history of India, a thermal plant using Super Critical technology is constructed. In addition to this a 765KV transmission system is used for the first time in the country. • The ultimate capacity of the plant was originally conceived as 3000MW. Thereafter, Sipat project was reconfigured as follows: • Thus the implementation of the project started in June 2007. It was to be completed in two stages. • Stage 1: 3*660 MW • Stage 2: 2*500 MW • The estimated cost for stage 1 was 7860.20 crores and for the stage 2 were 3785.18 crores. The coal source of this project is DIPKA Expansion project of SECL in Korba (CG). Total coal linkage in the system is 15.04 million ton/year. The coal transportation is carried on by MERRY GO ROUND system between the two projects. This is to avoid transportation discrepancies and for the smooth functioning of the plant. • The water requirement for the plant is fulfilled from Hasdeo RBC, through 26 km pipeline from Hardi Vishal. • The beneficiary states are Chattisgarh, Gujarat, Madhya Pradesh, Maharashtra, goa, Daman & Diu and Dadra & Nagar Haveli.|~|
  • 6.
  • 7. A THERMAL POWER PLANT MAINLY CONSISTS OF…. • 1.COAL HANDLING UNIT. • 2.BOILER or STEAM GENERATOR UNIT. • 3.TURBINE & ELECTRIC GENERATOR UNIT • 4.CONDENSATION AND COOLING WATER UNIT • 5. ASH HANDLING PLANT
  • 9.
  • 10. CHP MAINLY CONSISTS… • TRACK HOOPER • PADDLE FEEDER • CONVEYER BELT • MAGNETIC SEPRATOR • CRUSHER HOUSE • VGF • TRANSFER POINTS • STACKER • STOCKYARD/COAL PILES
  • 11. • The function of a CHP is to receive, process, store & feed the Coal bunkers consistently over the entire life of the Power plant. • Coal is received from mines in the form of lumps, the sizes varying from 100mm to 350mm,BOBR meaning Bogie Open Bottom Rapid discharge unloaded in TRACK HOOPERS . (Here it comes mainly from DEEPIKA MINES )BOBR TRACK HOOPER
  • 12. PADDLE FEEDER • Then this raw coal is scooped onto the conveyer by use of PADDLE FEEDER
  • 13. CONVEYER BELT… • Now this conveyer belt moves forward and carries that raw coal to CRUSHER HOUSE. • In between there are equipment likes METAL DETECTORS, SUSPENDED MAGNETS which separates coal from METALS which is not desirable in the production and Non-ferrous materials like stones, shells, wood etc. are removed MANUALLY • These belts are very strong and have steel cords inside. • There are Normal conveyor Idlers , they are the supporting rollers for the conveyor belt on which the coal laden conveyor belt glides |~|
  • 15. CRUSHER HOUSE…. • Here coal received from track hoopers is fed to VGF(Vibrating Gizzle Feeder) which allows 20(+) size coal to go to crusher and not allow 20(-) coal to go to crusher where there size is reduced to 20(-) -Here we use Roller hammer type crusher . - And there are 4 COUPLING motors located over springs for rotating the rollers. -Then all 20(-) coal is sent either to STOCK YARD or to COAL BUNKERS via appropriate TRANSFER POINTS through CONVEYER BELT.
  • 16. STACKER!!!! AND STOCK YARD • Coal stocks are made to meet needs in future emergency situations. • Stacking/ reclaiming of coal is done by bucket wheel type stacker-cum-reclaimer moving on rails. • The stacker-cum- reclaimer can stack coal on either sides of the yard conveyer • During stacking mode coal is fed from conveyors on boom conveyor and while in reclaim mode, boom conveyor discharges coal on the yard conveyor for feeding coal to bunkers through conveyors and transfer points. • Note always water sprinklers are used to avoid fire in COAL PILES
  • 17. OPERATION OF STACKER… • Luffing : This is vertical movement ,powered generally by 2 hydraulic cylinders • Traveling : The stacker moves on a rail track enabling it to move around the stockyard as required. • Slewing: This is rotation of the stacker around its central axis to align or place the stockpile where required. This utilizes sun and planet gear type gear box
  • 20. IT MAINLY CONSISTS THESE SYSTEMS… • Fuel Preparation System • Air & Flue Gas System • Water & Steam System • Fuel Firing System • Deareation & Feed Pumping System
  • 21. FUEL PREPRATION SYSTEM MAINLY CONSISTS…. • TRIPPERS: This is mechanism for dropping coals from conveyer to BUNKERS .These only allows calculated amount of coal to be dropped in all bunkers • COAL BUNKERS which stores coal mixture (20% imported+ 80% Indian) and feeds this coal to • BOWL MILLS/PULVERISER where 20(-) coal is further crushed to powder form having 200 meshes in 1 sq inch There is SEAL AIR FAN for sealing of mill from dust. • PA FANS are used firstly to reduce moisture content, secondly to heat it and lastly to transport powdered coal to different corners of BOILER via 4 different pipes .There are both COLD AIR DUT AND HOT AIR DUCT TO MAINTAIN TEMP
  • 22. AIR AND FLUE GAS SYSTEM MAINLY CONSISTS …. • FD fans provides sufficient air for combustion by taking air from atmosphere and then heated by air preheater(APH) • ID fans induces negative pressure in BOILER by drawing out combustible gases • Flue gases generated by combustion contains quite imp amount of heat which we utilise by sending it to ECONOMISER and APH (to pre heat air) then cooled flue gas is sent to ESP • ESP (Electro Static Precipitator) where by corona effect(cyclone separator) particles get precipitated over electrode and flue gas escapes to atmosphere via CHIMNEYS. Precipitate is sent to ASP(Ash Slurry Pump) house
  • 23. WATER AND STEAM SYSTEM MAINLY CONSISTS …. • Boiler Feed Water Pump(BFW PUMP)-which pumps boiler feed water to ECONOMISER pressure. • ECONOMISER –preheats BFW(all the sensible heating of BFW is done here only) • ****Then it goes to BOILER DRUM where saturated steam get separated from mixed state steam by virtue of cyclone steam separators and moisture content is again circulated after mixing with BFW • NOTE-* implies that this unit i.e BOILER DRUM is not found in SUPER CRITICAL BOILERS(as there is no region inside dome according to MODIFIED RANKINE CYCLE . So here water is always circulated only once )
  • 24.
  • 25. SUPER HEATERS… • Then separated saturated steam is taken out from boiler drum through series of nozzles and fed to series of SUPER HEATERS. • Firstly through DIV PANEL SH-which heats saturated steam by about 40 degree by mode of convection • Then this passes through PLATEN SH-which raises temp further by next 70 degrees by mode of radiation then it goes to FINAL SH via ATTEMPRATOR which lowers the temp by spraying a fine stream of water(it is done to control the temp ) • FINAL SH where remaining temp inc is picked up after which it goes to HP turbine and get expanded ** All the superheaters used are basically CLOSED HEATER
  • 26. REHEATERS…. • Sole purpose of reheating is to devoid wet steam from condenser which may result in EROSION OF BLADES of turbine. • After steam get expanded in HP turbine(upto IP say 345 degree and 45 bar) outlet steam is passed to REHEATERS (after passing via another ATTEMPRATOR) which heats up that steam • LT REHEATER and HT REHEATER:where temp is raised upto temp of inlet of HP turbine
  • 27.
  • 28. FIRING SYSTEM MAINLY INCLUDES… • Powdered coal is transported by PA fans to corners of BOILER by 4 diff pipes(having same pressure) and is blown TANGENTIALLY(to imaginary circle called FIRE-BALL) in furnace from all corners leading to formation of fireball. •
  • 29. • Extra oxygen required for combustion is provided by SECONDRY AIR • Initially during LIGHTING UP of boiler we first ignite coal by HFO and HLT and stop them after initialization • BURNER TILT MECHANISM:
  • 30. DEAERATION AND FEED PUMPING SYSTEM MAINLY CONSISTS… • DEAERATOR :whose main purpose is to remove air and other gases from BFW (is mainly done otherwise they may corrode different metals used in plant) and also to preheat BFW . It is worth noticing that it is the only used CLOSED TYPE HEATERS others are OPEN HEATER • FEED PUMP: It mainly pumps BFW coming out of deaerator to ECONOMISER pressure.
  • 31.
  • 33. • Sole purpose of turbine is to produce work by expanding steam from very high pressure to low condenser pressure. • We mainly use three types of turbine here viz. 1 HP turbine, 1 IP turbine and 2 LP turbine • We are using different pressure turbines for reheating purpose so that we can enhance overall efficiency of the plant (or so that we can overcome problem of wet steam) • First superheated steam is allowed to expand in HPT to some IP and then send back to boiler for reheating purpose. • Then this reheated steam is sent to IP turbine for expanding where after it get expanded to some lower pressure a BLEND steam is taken out and sent to FEED WATER HEATER (FWH) for heating feed water (for REGENERATION )
  • 34. BASIC ASPECTS OF 500 MW STEAM TURBINE….
  • 35.
  • 36.
  • 37. GENERATOR… • Shaft rotated at very high RPM by TURBINE is then coupled to generator which converts rotating energy of shafts into electrical energy. • During this process there is large amount of heat generation for which we require a special type of cooling system. • Hydrogen gas cooling, in an oil-sealed casing, is used because it has the highest known heat transfer coefficient of any gas and for its low viscosity which reduces wind-age losses • This system requires special handling during start-up, with air in the chamber first displaced by carbon dioxide before filling with hydrogen. This ensures that the highly flammable hydrogen does not mix with oxygen in the air.
  • 39. CONDENSATION UNIT MAINLY CONSIST OF… • CONDENSER: which is a shell type heat exchanger in which exhaust steam is cooled by running cooling water (circulated through tubes) and inturn CW gets heated and is send to COOLING TOWER for getting cooled • Then this cooled water is extracted by CEP(Condensate extraction pump) and heated by LPH and then to BFP and then to HPH and then to ECONOMISER
  • 40. COOLING WATER UNIT MAINLY CONSIST OF….. • During cooling of steam CW gets heated and this is send to COOLING TOWERS for getting cooled. • Here hot CW is fed onto top of COOLING TOWER and allowed to fall down • Also perpendicular to direction of falling air is allowed to blow which cools the water and gets out from top of the tower • Also since always some of the water losts in the whole process either due to leakage or due to evaporation so we supply extra water from MAKE UP WATER PUMP
  • 41.
  • 42. A typical COOLING TOWER looks like…
  • 43. ASH HANDLING PLANT …. • Wherever coal is burned it is necessary to have an efficient ash handling system, especially in a coal-fired power station environment where large quantities of pulverized fuel ash (PFA) are created • The various systems involved in the ash handling system are: -Bottom ash handling system -Fly ash handling system (both wet & dry) -Slurry handling system from slurry pump house to ash dyke -Ash water system -Ash water recirculation system • Basically, two types of ash are generated: -Fly ash (approx 80%) -Bottom ash (approx 20%)
  • 44. • Ash collected in hoppers is grinded by grinders and mixed with water and then sent to ash slurry house by using jet pumps. • Where it is collected in ASH PIT, from where it is pumped to ASH POND. • Here there is also an auxiliary pump which is used for FLUSHING OFF blockages. |~| • FLOW DIAGRAM OF AHP Hopper Clinker grinder Scrapper Conveyor Overflow water Trench BA Trans. Pump A S P H Ash Dyke A.S. Pump