Reflections on lessons learnt from failures in projects 11th November 2009, GlaxoSmithKline, Stevenage Dr. David Hancock BEngCEng MBA FRSA FIMMM RRP Chartered FCIPD
Agenda Some simple examples of failure What is Project Success? Odd one out? Problem Solving Problem Types Conclusions
Case Studies from my direct experience
Copenhagen Metro
Project Complexity - Systems
Project Complexity - Behavioural           was a specially-formed working co-operation between six engineering companies from Denmark, England, France, Italy and Austria. These are Carillion PLC (UK), SAE International (France), BachySoletanche (UK), STRABAG AG (Austria), NCC Danmark A/S (Denmark) and Astaldi (Italy).
Copenhagen Metro Islands Brygge (TBM)
Copenhagen MetroIslands Brygge
Copenhagen Metro HavnegadeShaft
6.7 billion DKK or 8.7 billion? (30% increase)2 billion DKK Claimed in 2000 still outstanding Annual Report 2001 Annual Report 2002 Annual Report 2003 Annual Report 2004 Annual Report 2005 Annual Report 2006 Annual Report 2008 Annual Report 2007
Understanding what is meant by project success is crucial
Heathrow Express Collapse Record fine after tunnel collapse  One of the worst civil engineering disasters for 25 years. Builder Balfour Beatty has been fined a record £1.2m for the collapse of a tunnel at Heathrow Airport, which put lives at risk and caused the cancellation of hundreds of flights.  The tunnel collapsed in the early hours of October 21, 1994. Fortunately no-one was in the tunnel at the time.  However, the court was told that the collapse could have crushed to death people using the nearby Piccadilly tube line and the judge hearing the case, Justice Peter Cresswell, said it was "luck more than judgment" that this did not happen.  Huge crater The collapse could have ended in real disaster. The engineering disaster caused a huge crater to appear between the airport's two main runways and caused damage to car parks and buildings. It took months to clear up the damage. The collapse occurred during the construction of a tunnel for the Heathrow Express Rail Link.  Balfour Beatty pleaded guilty to failing to ensure the safety of both its employees and members of the public. Austrian engineering firm Geoconsult, which was responsible for monitoring the progress of the Heathrow Express Link, was also fined £500,000. The judge ordered both companies to pay a further £100,00 each in costs.  Terrible disaster  Justice Cresswell said: "This was one of the worst civil engineering disasters in the United Kingdom in the last quarter of a century. The tunnels were being built below part of the world's busiest international airport and there was considerable potential for harm."  Both firms were found guilty of falling "seriously short" of the appropriate standards and reasonable steps, resulting in serious breaches of the Health and Safety Regulations.  Martin Thurgood, of the Health and Safety Executive, told the BBC: "This level of fine sends a clear message to the industry, whether (to) the client's designers, contractors or sub-contractors, that they do need to take full account of workers safety and public safety in the way in which they go about their business."  Balfour Beatty, based in Edinburgh, is one of the UK's largest building groups, and is part of the engineering group BICC. It said it deeply regretted the accident. The tunnel's collapse delayed the opening of the Heathrow Express by six months and caused long hold ups on part of the Jubilee line extension, where engineers were using similar building techniques.
13 Cambourne House Canteen & Welfare Units Heathrow Express collapse
Normal Accidents A normal accident typically involves interactions that are "not only unexpected, but are incomprehensible for some critical period of time." The people involved just don't figure out quickly enough what is really going wrong. A normal accident occurs in a complex system, one that has so many parts that it is likely that something is wrong with more than one of them at any given time. A well-designed complex system will include redundancy, so that each fault by itself does not prevent proper operation. However, unexpected interactions, especially with tight coupling, may lead to system failure.
Odd one out?
Millennium Wheel 2000 THE MILLENNIUM WHEEL received a further setback today as it was revealed that its opening may be pushed back to February. The delays stem from a problem discovered just before the wheel, or "BA London Eye" as the ad suits prefer to call it, was due to launch on New Year's Eve. Safety officials were concerned with a clutch attached to one of the passenger capsules. A further safety check has discovered that all the capsules' German made clutches are faulty and need replacing. Originally the operators of the wheel, British Airways, had planned to fully open at the end of January. Early rides which were reserved for the media, staff and prize-winners may now be postponed. Paid for rides, due to start at the beginning of February are also in doubt.  14-01-00
London Eye 2006 The London Eye is an observation wheel that completed construction in 1999 and opened to the public in March, 2000. As of June 2007, it is the largest observation wheel in the world, although there are larger ferris wheels, such as The Star of Nanchang, and a contender for the title in the Singapore Flyer due for completion in 2007. The London Eye has become the most popular paid for UK visitor attraction, visited by over 3.5 million people a year
Millennium Stadium Oct 2001 April 2001 £1 £100m The O'Rourke Construction Group of Essex has finalised details of its takeover of the construction arm of Laing Group for a nominal fee of £1.  O'Rourke was named as preferred bidder last April, when the division was expected to go for £100 million.  However, the price was dramatically reduced as spiralling losses on its fixed-price contracts such as the Cardiff Millennium Stadium came to light. Instead, Laing will take a £30 million disposal loss - the value of its net assets
Sydney Opera House (1960) The construction was estimated to take about five years at a cost of A$7 million. The government pressured Utzon into starting construction in 1959, two years ahead of the architect's proposed schedule. Unfortunately the roof shells were too heavy for the supporting columns that were already built, so these were demolished and rebuilt. These and several other setbacks led to delays and increasing cost overruns. In 1965, Australian Premier attempted to force Utzon reduce costs by withholding payments. In 1966 Utzon resigned and returned to his native Denmark taking the plans for the interior with him. The project was finally completed in 1973. Its total cost amounted to an astronomical A$102 million, almost 15 times the estimated budget. The design of the interior never matched the exterior.
Sydney Opera House (1990) In 1992, the Australian architects’ professional body, which was complicit in his sacking in 1966, awarded the architect a commemorative medal and an apology.  In 1994, research by architecture student Philip Nobis resulted in an exhibition that showed how the Opera House interiors would have looked had Utzon been allowed to complete the project. This clearly demonstrated that the unexciting interiors, inferior acoustics and other problems would not exist had the architect’s plans been implemented. In 1999 Utzon, although unable to travel, agreed to collaborate with Sydney architect Richard Johnson on this necessary work with his son Jan acting as a liaison On April 7, JørnUtzon, the architect who designed the Sydney Opera House, was awarded the 2003 Pritzker Architecture Prize Its events attract some two million visitors each year, making it one of the world's most popular cultural institutions and an icon for Sydney and Australia.
The Millenium Dome 2001 When historians of the future look back at Britain in 2000 the Dome will figure as a failure. There was that disastrous opening night, when the good and the great had to queue for hours in the cold at Stratford underground station. There were those ridiculous visitor forecasts, drawn up not on the basis of sound research but as the only way to make the books balance. There were too few managers with the right experience and too many meddling politicians, too many changes of mind and too little clarity of vision which is why the Dome ended up as an uncomfortable cross between a theme park and a museum. It was, in truth, far too ambitious. The politicians and the Millennium Commission wanted an exhibition which would encapsulate the very best of modern Britain, a beacon to the rest of the world, the most exciting and enjoyable experience available at the Millennium anywhere. We ended up with a striking upturned wok and the Body Zone, a modest success as an exhibition, a gargantuan financial and political failure - but a wonderful story for journalists
The O2 2007 A decade on...the Dome finally works. Tonight the Millennium Tent re-opens as the O2 Arena. What has happened inside the Tent is extraordinary, not least because it has been virtually covert. Since there is a roof already in place, construction of a vast 23,000 arena could not be achieved with conventional tower cranes. Instead, tools called stand-jacks were used to build from the ground up. The result is astonishing: if anything, the Tent filled with a building looks more frighteningly huge than it did empty. The arena was designed by HOK Sport, the American specialist architectural firm also responsible for the Emirates Stadium.
Problem Solving “Successful problem solving requires finding the right solution to the right problem. We fail more often because we solve the wrong problem than because we get the wrong solution to the right problem”.  Russell Ackoff, 1974
Problem Types  Tame Problems  Systems Complexity  Messes (Ackoff 1970)   Behavioural Complexity  Wicked Problems (Rittel & Weber 1973)  Wicked Messes (Roth & Senge 1996)
Time since beginning Problem Solving “TAME” Problems can be solved by linear or “waterfall” process Gather Data Analyse Data Problem Solution Formulate Solution Implement Solution
Systems Complexity Clusters of interrelated or interdependent  problems Messes (Ackoff 1970)
“MESSES”meet the following criteria: Organisational Complexity- clusters of interrelated or interdependent problems, or systems of problems. Messesare puzzles; rather than solving them we resolvetheir complexities. Cannot be solved in relative isolation from one another.
Behavioural Complexity Conflicting social ethics and beliefs ‘Wickedness’ (Rittel & Webber 1973)
“WICKED PROBLEMS”are characterised by: An evolving set of interlocking issues and constraints- no definitive statement of the problem (no understanding of the problem until the solution has been developed). Manystakeholders- the problem solving process is fundamentally social (getting the right answer is not as important as having stakeholders accept the solution). The constraints(resources, politics) change with time- stakeholders come and go, change their minds or change the rules. Since there is no definitive Problem there is no definitive Solution.
Problem Solution Time since beginning Wicked Problems “WICKED” Problems cannotbe solved by linear or “waterfall” process
Boston Matrix High Resolution is social/ political/ ethical/ moral/ behavioural Wicked Mess Wicked Behavioural Complexity Tame Mess Solution is Scientific Low High Low Dynamic Systems Complexity

Mais conteúdo relacionado

Mais procurados

Lesson 3
Lesson 3Lesson 3
Lesson 3
total
 
History of Mott MacDonald flyer_2016_lo
History of Mott MacDonald flyer_2016_loHistory of Mott MacDonald flyer_2016_lo
History of Mott MacDonald flyer_2016_lo
Paula Pontes
 
Led Architecture
Led ArchitectureLed Architecture
Led Architecture
Cenika
 
East Magazine Issue 2
East Magazine Issue 2East Magazine Issue 2
East Magazine Issue 2
MarkBradbury
 
Fresh Air Squares Mar 16
Fresh Air Squares Mar 16Fresh Air Squares Mar 16
Fresh Air Squares Mar 16
Shane Clarke
 

Mais procurados (19)

190922_Allies and Morrison_Artur Carulla_Shougang Forum
190922_Allies and Morrison_Artur Carulla_Shougang Forum190922_Allies and Morrison_Artur Carulla_Shougang Forum
190922_Allies and Morrison_Artur Carulla_Shougang Forum
 
Lesson 3
Lesson 3Lesson 3
Lesson 3
 
Cardiff Bay
Cardiff BayCardiff Bay
Cardiff Bay
 
10 maps that have made a difference
10 maps that have made a difference10 maps that have made a difference
10 maps that have made a difference
 
Lesson 3
Lesson 3Lesson 3
Lesson 3
 
Joe Montgomery. ULI
Joe Montgomery. ULIJoe Montgomery. ULI
Joe Montgomery. ULI
 
2012 London olympics
2012 London olympics2012 London olympics
2012 London olympics
 
History of Mott MacDonald flyer_2016_lo
History of Mott MacDonald flyer_2016_loHistory of Mott MacDonald flyer_2016_lo
History of Mott MacDonald flyer_2016_lo
 
Olympics update and quarterly economic report (international journalists) - J...
Olympics update and quarterly economic report (international journalists) - J...Olympics update and quarterly economic report (international journalists) - J...
Olympics update and quarterly economic report (international journalists) - J...
 
Led Architecture
Led ArchitectureLed Architecture
Led Architecture
 
Cardiff
CardiffCardiff
Cardiff
 
Erin, alfie, amelia, katie
Erin, alfie, amelia, katieErin, alfie, amelia, katie
Erin, alfie, amelia, katie
 
Transport & Regeneration
Transport & RegenerationTransport & Regeneration
Transport & Regeneration
 
London 2012 olympic games
London 2012 olympic gamesLondon 2012 olympic games
London 2012 olympic games
 
East Magazine Issue 2
East Magazine Issue 2East Magazine Issue 2
East Magazine Issue 2
 
Fresh Air Squares Mar 16
Fresh Air Squares Mar 16Fresh Air Squares Mar 16
Fresh Air Squares Mar 16
 
Nr idea workshop oxford april 2016 version1
Nr idea workshop oxford april 2016 version1Nr idea workshop oxford april 2016 version1
Nr idea workshop oxford april 2016 version1
 
Piccadilly circus
Piccadilly circusPiccadilly circus
Piccadilly circus
 
Fbe manchester energy event nov 2015
Fbe manchester energy event nov 2015Fbe manchester energy event nov 2015
Fbe manchester energy event nov 2015
 

Destaque (8)

Chefsintrodution VäRmdö Kommun
Chefsintrodution VäRmdö KommunChefsintrodution VäRmdö Kommun
Chefsintrodution VäRmdö Kommun
 
F1
F1F1
F1
 
Where next for the Enterprise Risk Manager
Where next for the Enterprise Risk ManagerWhere next for the Enterprise Risk Manager
Where next for the Enterprise Risk Manager
 
Proyecto Sena En Ingles 1
Proyecto Sena En Ingles 1Proyecto Sena En Ingles 1
Proyecto Sena En Ingles 1
 
Martin Fischer Online Resume
Martin Fischer Online ResumeMartin Fischer Online Resume
Martin Fischer Online Resume
 
Proyecto Sena En Ingles 011
Proyecto Sena En Ingles 011Proyecto Sena En Ingles 011
Proyecto Sena En Ingles 011
 
Genealogy on a Budget
Genealogy on a BudgetGenealogy on a Budget
Genealogy on a Budget
 
proyecto sena
proyecto senaproyecto sena
proyecto sena
 

Semelhante a Lessons learnt from projects

London eye. asís, marcos e y marcos n.
London eye.  asís, marcos e y marcos n.London eye.  asís, marcos e y marcos n.
London eye. asís, marcos e y marcos n.
rqi7
 
Cross-party letter regarding Earls Court Exhibition Centres
Cross-party letter regarding Earls Court Exhibition Centres Cross-party letter regarding Earls Court Exhibition Centres
Cross-party letter regarding Earls Court Exhibition Centres
CityHallLabour
 
Unit 1 Exam .docx
Unit 1 Exam                                                   .docxUnit 1 Exam                                                   .docx
Unit 1 Exam .docx
willcoxjanay
 

Semelhante a Lessons learnt from projects (20)

10 Construction projects that broke the bank!
10 Construction projects that broke the bank!10 Construction projects that broke the bank!
10 Construction projects that broke the bank!
 
London eye
London eyeLondon eye
London eye
 
C:\Fake Path\London Eye
C:\Fake Path\London EyeC:\Fake Path\London Eye
C:\Fake Path\London Eye
 
TurningPointA4-1107
TurningPointA4-1107TurningPointA4-1107
TurningPointA4-1107
 
Building Briefs – July 27th
Building Briefs – July 27thBuilding Briefs – July 27th
Building Briefs – July 27th
 
British Design Classics with embeded QR codes
British Design Classics with embeded QR codesBritish Design Classics with embeded QR codes
British Design Classics with embeded QR codes
 
London eye. asís, marcos e y marcos n.
London eye.  asís, marcos e y marcos n.London eye.  asís, marcos e y marcos n.
London eye. asís, marcos e y marcos n.
 
Concorde project
Concorde projectConcorde project
Concorde project
 
Cross-party letter regarding Earls Court Exhibition Centres
Cross-party letter regarding Earls Court Exhibition Centres Cross-party letter regarding Earls Court Exhibition Centres
Cross-party letter regarding Earls Court Exhibition Centres
 
Floating Alternative In The Thames Estuary
Floating Alternative In The Thames EstuaryFloating Alternative In The Thames Estuary
Floating Alternative In The Thames Estuary
 
The London Mayor’s 2020 Vision
The London Mayor’s 2020 VisionThe London Mayor’s 2020 Vision
The London Mayor’s 2020 Vision
 
London Docklands by Jenny M
London Docklands by Jenny MLondon Docklands by Jenny M
London Docklands by Jenny M
 
Zak World of Façades United Kingdom, 4th October London
Zak World of Façades United Kingdom, 4th October LondonZak World of Façades United Kingdom, 4th October London
Zak World of Façades United Kingdom, 4th October London
 
FLOAT INCORPORATED + MARIBE HORIZON 2020
FLOAT INCORPORATED + MARIBE HORIZON 2020FLOAT INCORPORATED + MARIBE HORIZON 2020
FLOAT INCORPORATED + MARIBE HORIZON 2020
 
How Aerospace Bristol was created, presentation
How Aerospace Bristol was created, presentationHow Aerospace Bristol was created, presentation
How Aerospace Bristol was created, presentation
 
The story of UK nuclear energy
The story of UK nuclear energyThe story of UK nuclear energy
The story of UK nuclear energy
 
Benefits of Buying a Property in East London.pdf
Benefits of Buying a Property in East London.pdfBenefits of Buying a Property in East London.pdf
Benefits of Buying a Property in East London.pdf
 
Benefits of Buying a Property in East London.pdf
Benefits of Buying a Property in East London.pdfBenefits of Buying a Property in East London.pdf
Benefits of Buying a Property in East London.pdf
 
Unit 1 Exam .docx
Unit 1 Exam                                                   .docxUnit 1 Exam                                                   .docx
Unit 1 Exam .docx
 
TRE July 2016 - Stirling
TRE July 2016 - StirlingTRE July 2016 - Stirling
TRE July 2016 - Stirling
 

Último

Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
allensay1
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
vineshkumarsajnani12
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
ZurliaSoop
 

Último (20)

Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al MizharAl Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
Al Mizhar Dubai Escorts +971561403006 Escorts Service In Al Mizhar
 
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book nowGUWAHATI 💋 Call Girl 9827461493 Call Girls in  Escort service book now
GUWAHATI 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Buy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail AccountsBuy gmail accounts.pdf buy Old Gmail Accounts
Buy gmail accounts.pdf buy Old Gmail Accounts
 
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service AvailableBerhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
Berhampur Call Girl Just Call 8084732287 Top Class Call Girl Service Available
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in PakistanChallenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
Challenges and Opportunities: A Qualitative Study on Tax Compliance in Pakistan
 
Arti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdfArti Languages Pre Seed Teaser Deck 2024.pdf
Arti Languages Pre Seed Teaser Deck 2024.pdf
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTSDurg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
Durg CALL GIRL ❤ 82729*64427❤ CALL GIRLS IN durg ESCORTS
 
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book nowKalyan Call Girl 98350*37198 Call Girls in Escort service book now
Kalyan Call Girl 98350*37198 Call Girls in Escort service book now
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGParadip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Paradip CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur CALL GIRL❤7091819311❤CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 

Lessons learnt from projects

  • 1. Reflections on lessons learnt from failures in projects 11th November 2009, GlaxoSmithKline, Stevenage Dr. David Hancock BEngCEng MBA FRSA FIMMM RRP Chartered FCIPD
  • 2. Agenda Some simple examples of failure What is Project Success? Odd one out? Problem Solving Problem Types Conclusions
  • 3. Case Studies from my direct experience
  • 6. Project Complexity - Behavioural was a specially-formed working co-operation between six engineering companies from Denmark, England, France, Italy and Austria. These are Carillion PLC (UK), SAE International (France), BachySoletanche (UK), STRABAG AG (Austria), NCC Danmark A/S (Denmark) and Astaldi (Italy).
  • 10. 6.7 billion DKK or 8.7 billion? (30% increase)2 billion DKK Claimed in 2000 still outstanding Annual Report 2001 Annual Report 2002 Annual Report 2003 Annual Report 2004 Annual Report 2005 Annual Report 2006 Annual Report 2008 Annual Report 2007
  • 11. Understanding what is meant by project success is crucial
  • 12. Heathrow Express Collapse Record fine after tunnel collapse One of the worst civil engineering disasters for 25 years. Builder Balfour Beatty has been fined a record £1.2m for the collapse of a tunnel at Heathrow Airport, which put lives at risk and caused the cancellation of hundreds of flights. The tunnel collapsed in the early hours of October 21, 1994. Fortunately no-one was in the tunnel at the time. However, the court was told that the collapse could have crushed to death people using the nearby Piccadilly tube line and the judge hearing the case, Justice Peter Cresswell, said it was "luck more than judgment" that this did not happen. Huge crater The collapse could have ended in real disaster. The engineering disaster caused a huge crater to appear between the airport's two main runways and caused damage to car parks and buildings. It took months to clear up the damage. The collapse occurred during the construction of a tunnel for the Heathrow Express Rail Link. Balfour Beatty pleaded guilty to failing to ensure the safety of both its employees and members of the public. Austrian engineering firm Geoconsult, which was responsible for monitoring the progress of the Heathrow Express Link, was also fined £500,000. The judge ordered both companies to pay a further £100,00 each in costs. Terrible disaster Justice Cresswell said: "This was one of the worst civil engineering disasters in the United Kingdom in the last quarter of a century. The tunnels were being built below part of the world's busiest international airport and there was considerable potential for harm." Both firms were found guilty of falling "seriously short" of the appropriate standards and reasonable steps, resulting in serious breaches of the Health and Safety Regulations. Martin Thurgood, of the Health and Safety Executive, told the BBC: "This level of fine sends a clear message to the industry, whether (to) the client's designers, contractors or sub-contractors, that they do need to take full account of workers safety and public safety in the way in which they go about their business." Balfour Beatty, based in Edinburgh, is one of the UK's largest building groups, and is part of the engineering group BICC. It said it deeply regretted the accident. The tunnel's collapse delayed the opening of the Heathrow Express by six months and caused long hold ups on part of the Jubilee line extension, where engineers were using similar building techniques.
  • 13. 13 Cambourne House Canteen & Welfare Units Heathrow Express collapse
  • 14. Normal Accidents A normal accident typically involves interactions that are "not only unexpected, but are incomprehensible for some critical period of time." The people involved just don't figure out quickly enough what is really going wrong. A normal accident occurs in a complex system, one that has so many parts that it is likely that something is wrong with more than one of them at any given time. A well-designed complex system will include redundancy, so that each fault by itself does not prevent proper operation. However, unexpected interactions, especially with tight coupling, may lead to system failure.
  • 16. Millennium Wheel 2000 THE MILLENNIUM WHEEL received a further setback today as it was revealed that its opening may be pushed back to February. The delays stem from a problem discovered just before the wheel, or "BA London Eye" as the ad suits prefer to call it, was due to launch on New Year's Eve. Safety officials were concerned with a clutch attached to one of the passenger capsules. A further safety check has discovered that all the capsules' German made clutches are faulty and need replacing. Originally the operators of the wheel, British Airways, had planned to fully open at the end of January. Early rides which were reserved for the media, staff and prize-winners may now be postponed. Paid for rides, due to start at the beginning of February are also in doubt. 14-01-00
  • 17. London Eye 2006 The London Eye is an observation wheel that completed construction in 1999 and opened to the public in March, 2000. As of June 2007, it is the largest observation wheel in the world, although there are larger ferris wheels, such as The Star of Nanchang, and a contender for the title in the Singapore Flyer due for completion in 2007. The London Eye has become the most popular paid for UK visitor attraction, visited by over 3.5 million people a year
  • 18. Millennium Stadium Oct 2001 April 2001 £1 £100m The O'Rourke Construction Group of Essex has finalised details of its takeover of the construction arm of Laing Group for a nominal fee of £1. O'Rourke was named as preferred bidder last April, when the division was expected to go for £100 million. However, the price was dramatically reduced as spiralling losses on its fixed-price contracts such as the Cardiff Millennium Stadium came to light. Instead, Laing will take a £30 million disposal loss - the value of its net assets
  • 19. Sydney Opera House (1960) The construction was estimated to take about five years at a cost of A$7 million. The government pressured Utzon into starting construction in 1959, two years ahead of the architect's proposed schedule. Unfortunately the roof shells were too heavy for the supporting columns that were already built, so these were demolished and rebuilt. These and several other setbacks led to delays and increasing cost overruns. In 1965, Australian Premier attempted to force Utzon reduce costs by withholding payments. In 1966 Utzon resigned and returned to his native Denmark taking the plans for the interior with him. The project was finally completed in 1973. Its total cost amounted to an astronomical A$102 million, almost 15 times the estimated budget. The design of the interior never matched the exterior.
  • 20. Sydney Opera House (1990) In 1992, the Australian architects’ professional body, which was complicit in his sacking in 1966, awarded the architect a commemorative medal and an apology. In 1994, research by architecture student Philip Nobis resulted in an exhibition that showed how the Opera House interiors would have looked had Utzon been allowed to complete the project. This clearly demonstrated that the unexciting interiors, inferior acoustics and other problems would not exist had the architect’s plans been implemented. In 1999 Utzon, although unable to travel, agreed to collaborate with Sydney architect Richard Johnson on this necessary work with his son Jan acting as a liaison On April 7, JørnUtzon, the architect who designed the Sydney Opera House, was awarded the 2003 Pritzker Architecture Prize Its events attract some two million visitors each year, making it one of the world's most popular cultural institutions and an icon for Sydney and Australia.
  • 21. The Millenium Dome 2001 When historians of the future look back at Britain in 2000 the Dome will figure as a failure. There was that disastrous opening night, when the good and the great had to queue for hours in the cold at Stratford underground station. There were those ridiculous visitor forecasts, drawn up not on the basis of sound research but as the only way to make the books balance. There were too few managers with the right experience and too many meddling politicians, too many changes of mind and too little clarity of vision which is why the Dome ended up as an uncomfortable cross between a theme park and a museum. It was, in truth, far too ambitious. The politicians and the Millennium Commission wanted an exhibition which would encapsulate the very best of modern Britain, a beacon to the rest of the world, the most exciting and enjoyable experience available at the Millennium anywhere. We ended up with a striking upturned wok and the Body Zone, a modest success as an exhibition, a gargantuan financial and political failure - but a wonderful story for journalists
  • 22. The O2 2007 A decade on...the Dome finally works. Tonight the Millennium Tent re-opens as the O2 Arena. What has happened inside the Tent is extraordinary, not least because it has been virtually covert. Since there is a roof already in place, construction of a vast 23,000 arena could not be achieved with conventional tower cranes. Instead, tools called stand-jacks were used to build from the ground up. The result is astonishing: if anything, the Tent filled with a building looks more frighteningly huge than it did empty. The arena was designed by HOK Sport, the American specialist architectural firm also responsible for the Emirates Stadium.
  • 23. Problem Solving “Successful problem solving requires finding the right solution to the right problem. We fail more often because we solve the wrong problem than because we get the wrong solution to the right problem”. Russell Ackoff, 1974
  • 24. Problem Types Tame Problems Systems Complexity Messes (Ackoff 1970) Behavioural Complexity Wicked Problems (Rittel & Weber 1973) Wicked Messes (Roth & Senge 1996)
  • 25. Time since beginning Problem Solving “TAME” Problems can be solved by linear or “waterfall” process Gather Data Analyse Data Problem Solution Formulate Solution Implement Solution
  • 26. Systems Complexity Clusters of interrelated or interdependent problems Messes (Ackoff 1970)
  • 27. “MESSES”meet the following criteria: Organisational Complexity- clusters of interrelated or interdependent problems, or systems of problems. Messesare puzzles; rather than solving them we resolvetheir complexities. Cannot be solved in relative isolation from one another.
  • 28. Behavioural Complexity Conflicting social ethics and beliefs ‘Wickedness’ (Rittel & Webber 1973)
  • 29. “WICKED PROBLEMS”are characterised by: An evolving set of interlocking issues and constraints- no definitive statement of the problem (no understanding of the problem until the solution has been developed). Manystakeholders- the problem solving process is fundamentally social (getting the right answer is not as important as having stakeholders accept the solution). The constraints(resources, politics) change with time- stakeholders come and go, change their minds or change the rules. Since there is no definitive Problem there is no definitive Solution.
  • 30. Problem Solution Time since beginning Wicked Problems “WICKED” Problems cannotbe solved by linear or “waterfall” process
  • 31. Boston Matrix High Resolution is social/ political/ ethical/ moral/ behavioural Wicked Mess Wicked Behavioural Complexity Tame Mess Solution is Scientific Low High Low Dynamic Systems Complexity
  • 32. Wicked Problem Solving Resolving “WICKED MESSES”is “SATISFICING” (H. Simon 1956) Because of the number of stakeholders, changing constraints and dynamics of the problem, there is no ideal solution-it is “as good as it gets” or “good enough” The Problem solving process ends when resource (time, money energy etc.) runs out! Therefore we need a different approach when handling project management with respect to problems which are not Tame
  • 33. Summary Conclusions During strategic & initial (design) stages of project you should expect a predominance of ‘wicked’problems and fewer technical and tame problems therefore communication and understanding is more complex and crucial. Need to define success at the beginning in both ‘hard’ and ‘soft’ terms. Dialogue and understanding (Communication) within workshops is key to managing behavioural risk on projects. Need to have the whole system represented during early decision making [holistic approach]. Present project management practices underplay behavioural and systemic aspects. The integration of project into business is often ignored
  • 34. “When all you have is a hammer,everything looks like a nail ”. - Japanese Proverb

Notas do Editor

  1. 1998Liva and Betty start their drilling work. They start from Islands Brygge and head towards Stadsgraven. In August the boring machines are lifted up and transferred to Havnegade, and during the autumn they continue on towards Strandlodsvej in East Amager. In Italy, production of the first train set begins. In all, 34 trains are produced for the Metro system.1999In May the first train set arrives at the Control and Maintenance Centre in Ørestad, and trial runs begin on a special test track there. On 10 December Liva breaks through to Strandslodsvej – Betty gets there five days later.2000Liva and Betty turn their drilling heads the other way. They are transferred to Havnegade and start drilling in the direction of Nørreport. Again it is Liva who is first to reach the goal in May – quickly followed by Betty, who gets there in mid June. On the elevated track in Ørestad they begin testing trains.2001The tunnel boring machines continue their work as far as FalkonerAllé in Frederiksberg and put the last ring in place in February. Train sets arrive from Italy in a steady stream, and in November trains are tested for the first time in the tunnel between Islands Brygge and Lergravsparken station.