Introduction
• This presentation is intended as supplemental
  information in support of the 9102 Standard for
  Aerospace First Article Inspection requirements.

• This material should be used in conjunction with the
  standard. The requirements cited in the standard
  always take precedent.




                                                         2
Requirements
 First Article Inspection Reports are to be recorded in
  English or in a language specified by the customer.

 AS/EN/SJAC9102 Revision A - Aerospace First Article
  Inspection Requirement

 8.2.4.2 First Article Inspection: The organization’s
  system shall provide a process for the inspection,
  verification, and documentation of a representative
  item from the first production run of a new part, or
  following any subsequent change that invalidates the
  previous first article inspection result.

    NOTE: USE (AS) (EN) (SJAC) 9102 with this
     tutorial for requirements



                                                           3
Requirements
 Additional Customer requirements if applicable

 AS/EN/SJAC9102 Rev A forms are to be completed in
  accordance with the Appendix A guide of the standard

 Note: If alternate forms are used, they must contain
  all “Required” and “Conditionally Required”
  information and have the same field reference
  numbers as AS/EN/SJAC9102 Rev A




                                                         4
Definition

FIRST ARTICLE INSPECTION (FAI):

A complete, independent, and documented physical and
functional inspection process to verify that prescribed
production methods have produced an acceptable item
as specified by engineering drawings, planning,
purchase order, engineering specifications, and/or
other applicable design documents.

Ref 9102 Rev A




                                                          5
Purpose
Provides objective evidence:

   that all engineering, design and specification
   requirements, including process and manufacturing
   validation, are correctly
       understood
       accounted for
       verified
       and recorded.

   of a consistent documentation requirement for
   aerospace components.




                                                       6
Evaluation Activities
• The organization should conduct the following
  activities in support of FAI;
  – Review documentation for the manufacturing
    process (e.g., routing sheets,
    manufacturing/quality plans, manufacturing work
    instructions, etc.) to make sure all operations are
    complete as planned.
  – Review referenced exhibits supporting the FAI
    (e.g., inspection data, test data, Acceptance Test
    Procedures, etc.) for completeness.
  – Review nonconformance documentation (if any),
    for completeness.
  – Review material certifications for compliance, as
    applicable.
Evaluation Activities
  – Verify that approved Special Process sources are
    used (as applicable), and that the manufacturing
    planning/routing document calls out the correct
    specification.
  – Verify that Key Characteristic requirements have
    been met, as applicable Verify part specific gages
    and/or tooling are qualified and traceable, as
    applicable.
  – Verify that every design characteristic requirement
    is accounted for, uniquely identified and has
    inspection results traceable to each unique
    identifier.
  – Note the company FAI procedure should address all
    evaluation activities
When should FAI be performed?
 Full FAI
    New part introduction
    New supplier or new location of manufacture
    Lapse in production for more than 2 years
    When required by the customer

 Partial (Delta) FAI
    Design change
    A change in the method of manufacture (e.g.
   Tooling, Processes, Machine, Location, Numerical
   Control Program, Sequence of Manufacture).




                                                      9
What does it apply to?
 All product defined by engineering drawings or model
 based definitions. Delete-issued by the Customer

 Assemblies- for those characteristics specified on the
 assembly level drawing only

 All levels of detail parts within assembly
    including castings and forgings

 Modified Standard, Electronic or COTS Items as “make
  from” with unique engineer modifications on drawing
    Only the modifications




                                                           10
What does it not apply to?
Standard Parts

Electronic Components

Commercial Off The Shelf (COTS) Items

                  No FAI required




                                         11
What is included?
 Verification of all design characteristics

 Material and Special Process Certifications

 Manufacturing Process Verification

 Nonconformance resolution




                                                12
Forms
The Following Forms comprise a First Article Inspection
Report (FAIR) full instructions in 9102 appendix A

   AS9102 A Form 1: Part Number Accountability shall be used
   to identify the part that is being first article inspected (FAI
   part) and associated sub-assemblies or detail parts.

   AS9102 A Form 2: Product Accountability – Raw Material,
   Specifications and Special Process(s), Functional Testing shall
   be used if any material, special processes or functional testing
   are defined as a design requirement.

   AS9102 A Form 3: Characteristic Accountability, Verification
   and Compatibility Evaluation shall be used to record an actual
   measurement or inspection/verification of the FAI part for
   every design characteristic on the drawing, including notes.
                                                                     13
AS9102 A Form 1 – Part Number Accountability
             1. Part Number                     2. Part Name                       3. Serial Number                 4. FAI Report Number



             5. Part Revision Level             6. Drawing Number                  7. Drawing revision level        8. Additional Changes




             9. Manufacturing Process            10. Organization Name             11. Supplier Code                12. P.O. Number
             Reference



             13. Detail FAI                     14.    Full FAI                    Baseline Part Number including revision level
                                                       Partial FAI
                   Assembly FAI                        Reason for Partial FAI:

              a)    if above part number is a detail part only, go to Field 19
              b)    if above part number is an assembly, go to the “INDEX” section below.
                    INDEX of part numbers or sub-assembly numbers required to make the assembly noted above.
             15. Part Number                    16. Part Name                      17. Part Serial Number            18. FAI Report Number




         YELLOW or LIGHT GREY fields – MANDATORY
                   information required.
          BLUE or DARK GREY fields – CONDITIONALLY
           REQUIRED. These fields must be completed
                 when information is available.
            WHITE fields – OPTIONAL information required
                           when available.
             1) Signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for
             disposition.

             2) Also indicate if the FAI is complete per Section 5.4:      FAI complete                     FAI not Complete
             19. Signature By                                                                                        20. Date

             21. Reviewed By                                                                                         22. Date

             23. Customer Approval                                                                                   24. Date

             Form 1, 9102 Rev A, Date: Oct 24, 2003

                                                                                                                                             14
AS/EN/SJAC9102 Rev A First Article Inspection
     AS9102 A Form 1 – Part Number Accountability
                                                                                                    Sheet 1 of _
            Form 1: Part Number Accountability
                 1. Part Number           2. Part Name         3. Serial Number                4. FAI Report Number



                 5. Part Revision Level   6. Drawing Number    7. Drawing revision level       8. Additional Changes

                            Box 1. Part Number of the FAI part.
                    Box 2. Name of the part as shown on the drawing.
                 9. Manufacturing Process 10. Organization Name 11. Supplier Code              12. P.O. Number
                 Reference           Box 3. Serial number of the                           FAI part.
                                                Box 4. The Report No.
                 13. Detail FAI           14. Full FAI         Baseline Part Number including revision level
 Box 5. The revision of                   the part
                                              Partial FAI  being first article inspected. Indicate if
                  Assembly FAI                therePartial FAI: revision.
                                               Reason for is no
Note: The latest revision (Box 7) does not always affect all parts contained on a drawing.
                a) if above part number is a detail part only, go to Field 19
        Box 6. ifThe drawing numbersection below.
                b) above part number is an assembly, go to the “INDEX” associated with the FAI part.
          (if different from numbers or sub-assembly numbers required to make the assembly noted above.
                    INDEX of part part number)
                 15. Part Number          16. Part Name        17. Part Serial Number          18. FAI Report Number
                 Box 7. Reference the revision engineering drawing.
     (if drawing number is different from part number)
     Box 8. Reference Design, Engineering or Manufacturing changes
      affecting the FAI part, not reflected by the current part/drawing15
                                revision level.                                                                        15
AS9102 A Form 1 – Part Number Accountability

         1. Part Number              2. Part Name               3. Serial Number            4. FAI Report Number



         5. Part Revision Level      6. Drawing Number          7. Drawing revision level   8. Additional Changes




         9. Manufacturing Process    10. Organization Name      11. Supplier Code           12. P.O. Number
         Reference


                  Box 9. Reference the internal works order.
         13. Detail FAI                14. Full FAI                       Baseline Part Number including revision level
      Box 10. Name of the organization performing the FAI .
                                             Partial FAI
         Assembly FAI 11. Reference the supplier vendor code.
              Box                            Reason for Partial FAI:
    Box if12.part number is a detail part only, go to Field 19
       a) above Reference the customer Purchase Order number.
       b) if above part number is an assembly, go to the “INDEX” section below.
                                 Box 13. Check as appropriate.
          INDEX of part numbers or sub-assembly numbers required to make the assembly noted above.
    BoxPart Number
      15. 14. Check asPart Name        16. appropriate. Part Serial Partial FAI Report Number
                                                                          17. For Number                  18. FAI provide the
    baseline drawing number, including issue status and the
             reason. i.e Change of manufacturing location,
    Non-Conformance, Process change, Design change etc.
                                                                                                                                16
AS9102 A Form 1 – Part Number Accountability

         1. Part Number                  2. Part Name                      3. Serial Number            4. FAI Report Number



         5. Part Revision Level          6. Drawing Number                 7. Drawing revision level   8. Additional Changes
               Boxes 15, 16, 17 and 18 – this section is only
                  required if the Part Number in Box 1. is an
                              Assembly with lower level parts.P.O. Number
         9. Manufacturing Process 10. Organization Name 11. Supplier Code 12.
         Reference
                  Box 15. Reference all lower level parts or
                   next level sub-assembly Part Number.
         13. Detail FAI             14. Full FAI  Baseline Part Number including revision level
      Box 16. Part                namePartial FAI
                                         as shown on the drawing/ parts                                                       list.
            Assembly FAI                        Reason for Partial FAI:

         a) if above part number is a detail part only, go to Field 19
         b) if above part number is an assembly, go to the “INDEX” section below.
              INDEX of part numbers or sub-assembly numbers required to make the assembly noted above.
         15. Part Number                 16. Part Name                     17. Part Serial Number      18. FAI Report Number


         Box 17. Reference the serial number of the part.
   Box 18. A reference number that identifies the FAI package.
                                                                                                                                      17
AS9102 A Form 1 – Part Number Accountability




                     Box 19. The name and signature of the
                         person who prepared the FAI.
                        Box 20. Date when the FAI was prepared.

                      Box 21. The name of the person who
                     reviewed or approved the FAI package.
                        Box 22. Date when the FAI was reviewed.
      1) Signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for
      disposition.

      2) Also indicate if the FAI is complete per Section 5.4:   FAI complete                  FAI not Complete
      19. Signature By                                                                                  20. Date

      21. Reviewed By                                                                                   22. Date

      23. Customer Approval                                                                             24. Date

      Form 1, 9102 Rev A, Date: Oct 24, 2003

                                  Box 23. Customer Approval.
                             Box 24. Date of Customer approval.

                                                                                                                                    18
AS9102 A Form 2 – Product
     Accountability
            1. Part Number           2 Part Name                      3. Serial Number                      4. FAI Report
                                                                                                               Number


            5. Material or Process   6. Specification   7. Code       8. Special Process   9. Customer      10. Certificate of
              Name                      Number                           Supplier Code       Approval           Conformance
                                                                                             Verification       number
                                                                                              (Yes/No/NA)




           Boxes 1 - 4 are repeated on all forms for
               convenience and traceability.




            11. Functional Test      12. Acceptance report number, if applicable
            Procedure Number




            13. Comments

            14. Prepared By                                                  15. Date

                                                                                                                                 19
AS9102 A Form 2 – Product
       Accountability

  1. Part Number           2 Part Name                  3. Serial Number                      4. FAI Report
                                                                                                 Number


  5. Material or Process   6. Specification   7. Code   8. Special Process   9. Customer      10. Certificate of
    Name                      Number                       Supplier Code       Approval           Conformance
                                                                               Verification       number
                                                                                (Yes/No/NA)



 Box 5. Enter the name of the material or process i.e. Aluminium
                     Alloy, Cadmium Plate etc.
Box 6. Enter the material or process specification number, class and
material form i.e. AMS4928 Bar (Include ‘make from’ materials, weld/
      braze filler materials, standard catalogue hardware etc).
                      Box 7. Reference any material code specified.
             Box 8. Reference Special Process Supplier Vendor code,
                                name & address.
  Box 9. Indicate if technical approval is required by the customer.
Box 10. Reference Certificate of Conformance number(s) e.g. Special
Process, Raw material & Mill certifications, Laboratory Reports etc.
                                                                                                                   20
AS9102 A Form 2 – Product
     Accountability




11. Functional Test     12. Acceptance report number, if applicable
Procedure Number




               Box 11. Reference the Functional Test procedure
                           as stated on the drawing.
                  Box 12. Reference the Functional Test report.
13. Comments

14. Prepared By                                                 15. Date


                            Box 13. Comments – As applicable.
          Box 14. The name of the person who prepared this form.

                      Box 15. Date when this form was completed.


                                                                           21
Ballooned Drawings
 A ballooned drawing is optional and considered an
  industry best practice to support Box 5 of Form 3
 Identify 100% of characteristics
 Balloon and number all dimensions
 Balloon and number all surface finish callouts
   Including exclusion and inclusion area callouts
 Balloon and number all material and hardness
  callouts
   Don’t forget the requirements identified in the title
    boxes at the bottom of the drawings.




                                                            22
BALLOONED                   Note 2

DRAWINGS                                      1




                                          2


                                              3

       8                                  4

             7                        5

                        6

Note: In this example not all characteristics ballooned
                                                      23
AS9102 A Form 3 – Characteristic Accountability,
   Verification and Compatibility Evaluation
1. Part Number                                                  2. Part Name                                             3. Serial Number        4. FAI Report


                  Characteristic Accountability                                Inspection / Test Results                                                         Optional
5.   6.        7. Characteristic 8.                             9.                        10.              11.         14.
Char Reference Designator        Requirement                    Results                   Designed         Non-        [Insert columns, etc., as required by
No.  Location                                                                             Tooling          Conformance Organization or Customer}
                                                                                                           Number




                            Boxes 1 - 4 are repeated on all forms for
                                convenience and traceability.




The signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition.
12. Prepared By                                                                                               13. Date




                                                                                                                                                                  24
AS9102 A Form 3 – Characteristic Accountability,
            Verification and Compatibility Evaluation
1. Part Number                                                  2. Part Name                                                3. Serial Number         4. FAI Report


                  Characteristic Accountability                                Inspection / Test Results                                                             Optio
5.   6.        7. Characteristic 8.                             9.                        10.              11.         14.
Char Reference Designator        Requirement                    Results                   Designed         Non-        {Insert columns, etc. as required by Organization
No.  Location                                                                             Tooling          Conformance or Customer}
                                                                                                           Number




               Box 5. Assign a unique number for each design
              Box 6. Reference the drawing zone
             Box 7. Reference any zoned characteristics i.e. Key
                                characteristic.
                (include Sheet No. and Zone).
            These are to be traceable Critical Characteristic, etc.
              Characteristics, Safety to each drawing requirement.




The signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition.
12. Prepared By                                                                                                  13. Date



                                                                                                                                                                     25
AS9102 A Form 3 – Characteristic Accountability,
            Verification and Compatibility Evaluation
1. Part Number                                                  2. Part Name                                             3. Serial Number      4. FAI Report


                  Characteristic Accountability                                Inspection / Test Results                                                             Opt
5.   6.        7. Characteristic 8.                             9.                        10.              11.         14.
Char Reference Designator        Requirement                    Results                   Designed         Non-        {Insert columns, etc. as required by Organization
No.  Location                                                                             Tooling          Conformance or Customer}
                                                                                                           Number




 Box 9.
    Indicate measurements specified for each designof specially
        Box 10. Record the tool identification number characteristic.
          Box 8. Indicate the obtained a media of inspection.
             designed tooling used as requirement for thenumber if any
                                                             design
  Box 11. Record non-conformance be features reference values.
        Multiple characteristics shall document with minimum and
                        i.e. Dimensional listed as individual
         characteristicRecord any addition information required.
               Box 14.
         maximum value of tolerance, foundaccountedSpecification
              design characteristicmust be non-conforming.
                 All drawing notes is Drawing notes, for.
                               requirements etc.
      Processes that require design verification must have statement of
     compliance recorded on the form i.e. Certification of Compliance –
                                state ‘Accept’.
    Laboratory reports or Certificate of test must show specific values for
                      requirements and actual results.
The signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition.
12. Prepared By                                                                                               13. Date


                                                                                                                                                                  26
AS9102 A Form 3 – Characteristic Accountability,
           Verification and Compatibility Evaluation
1. Part Number                                                  2. Part Name                                                 3. Serial Number      4. FAI Report


                  Characteristic Accountability                                Inspection / Test Results                                                             Optio
5.   6.        7. Characteristic 8.                             9.                          10.            11.          14.
Char Reference Designator        Requirement                    Results                     Designed       Non-        [Insert columns, etc., as required by Organization
No.  Location                                                                               Tooling        Conformance or Customer]
                                                                                                           Number




                          Box 12. Name of the person who prepared this form.

                                    Box 13. Date when this form was completed.



The signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition.
12. Prepared By                                                                                                   13. Date


                                                                                                                                                                     27
Forms Link


AS9102 A forms can be downloaded at:

    www.sae.org/aaqg/publications/as9102a-faq.htm

9102 FAQ Link

   www.sae.org/iaqg/publications/faq9102.htm




                                                    28
Most Common Reasons for FAI Rejection

 C of Cs do not accompany the FAI Report.
 Missing FAI Reports or Test Reports for sub-assemblies
 and/or fabricated detail parts.
 Variable data requirements from the engineering drawing
 are not provided with numerical results.
 Missing or wrong information provided.
 Missing special processor full address on AS9102 A Form
 2, box 8.
 Missing tolerances on AS9102 A Form 3, box 8.
 Customer flow down requirements not met.

                                                            29

Mais conteúdo relacionado

Mais procurados

Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01
BhimKunwar2
 
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPTPROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
Inter Alliance Werardt
 
Ppap training-presentation
Ppap training-presentationPpap training-presentation
Ppap training-presentation
Ranvijay Akela
 
Procedure identification and traceability
Procedure   identification and traceabilityProcedure   identification and traceability
Procedure identification and traceability
William Laride
 
ADVANCED PRODUCT QUALITY
ADVANCED PRODUCT QUALITYADVANCED PRODUCT QUALITY
ADVANCED PRODUCT QUALITY
anish malan
 

Mais procurados (20)

Apqp fundamentals
Apqp fundamentalsApqp fundamentals
Apqp fundamentals
 
Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01Ppap training-presentation-150311063239-conversion-gate01
Ppap training-presentation-150311063239-conversion-gate01
 
ISO/TS 16949:2009 to IATF 16949:2016
ISO/TS 16949:2009 to IATF 16949:2016ISO/TS 16949:2009 to IATF 16949:2016
ISO/TS 16949:2009 to IATF 16949:2016
 
APQP
APQP APQP
APQP
 
Production part approval process ppt 1
Production part approval process ppt 1Production part approval process ppt 1
Production part approval process ppt 1
 
PPT Presentation on IATF 16949 Documentation
PPT Presentation on IATF 16949 DocumentationPPT Presentation on IATF 16949 Documentation
PPT Presentation on IATF 16949 Documentation
 
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPTPROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
PROCESS FAILURE MODE EFFECTS ANALYSIS (PFMEA) PPT
 
Ppap training-presentation
Ppap training-presentationPpap training-presentation
Ppap training-presentation
 
Non confirming products
Non confirming productsNon confirming products
Non confirming products
 
Ppap training presentation
Ppap   training presentationPpap   training presentation
Ppap training presentation
 
IRIS Certification (ISO 22163:2017) Process
IRIS Certification (ISO 22163:2017) Process IRIS Certification (ISO 22163:2017) Process
IRIS Certification (ISO 22163:2017) Process
 
List of mandatory IATF 16949 documents
List of mandatory IATF 16949 documents List of mandatory IATF 16949 documents
List of mandatory IATF 16949 documents
 
Apqp
ApqpApqp
Apqp
 
Iso 9001:2015 internal auditor Course
Iso 9001:2015  internal auditor Course Iso 9001:2015  internal auditor Course
Iso 9001:2015 internal auditor Course
 
Apqp process flow
Apqp process flowApqp process flow
Apqp process flow
 
FMEA Introduction.ppt
FMEA Introduction.pptFMEA Introduction.ppt
FMEA Introduction.ppt
 
Procedure identification and traceability
Procedure   identification and traceabilityProcedure   identification and traceability
Procedure identification and traceability
 
Training ppt for control plan
Training ppt for control plan   Training ppt for control plan
Training ppt for control plan
 
ADVANCED PRODUCT QUALITY
ADVANCED PRODUCT QUALITYADVANCED PRODUCT QUALITY
ADVANCED PRODUCT QUALITY
 
PPAP 101: What You Should Know About PPAP
PPAP 101: What You Should Know About PPAPPPAP 101: What You Should Know About PPAP
PPAP 101: What You Should Know About PPAP
 

Destaque

1st Article Linked In
1st Article Linked In1st Article Linked In
1st Article Linked In
alspread
 
Eie 6 formas jurídicas, versión 97 2003
Eie 6 formas jurídicas, versión 97 2003Eie 6 formas jurídicas, versión 97 2003
Eie 6 formas jurídicas, versión 97 2003
Justetetament
 
Welding visual inspection
Welding visual inspectionWelding visual inspection
Welding visual inspection
businespartner
 
Secret cb vol_01
Secret cb vol_01Secret cb vol_01
Secret cb vol_01
dodgez99
 
التعليم المبرمج
التعليم المبرمجالتعليم المبرمج
التعليم المبرمج
rasha-24
 
Temel teknik resim
Temel teknik resimTemel teknik resim
Temel teknik resim
Erol Dizdar
 

Destaque (20)

1st Article Linked In
1st Article Linked In1st Article Linked In
1st Article Linked In
 
Guide to implement AS9100 Rev C
Guide to implement AS9100 Rev CGuide to implement AS9100 Rev C
Guide to implement AS9100 Rev C
 
TOOL LIFE TEST
TOOL LIFE TESTTOOL LIFE TEST
TOOL LIFE TEST
 
Excel formulas tf-jul1605
Excel formulas tf-jul1605Excel formulas tf-jul1605
Excel formulas tf-jul1605
 
DISCUS for FAI
DISCUS for FAIDISCUS for FAI
DISCUS for FAI
 
CQC: First Inspection: A Survival Guide
CQC: First Inspection: A Survival GuideCQC: First Inspection: A Survival Guide
CQC: First Inspection: A Survival Guide
 
Information about Cell and it's structure and protein synthesis
Information about Cell and it's structure and protein synthesisInformation about Cell and it's structure and protein synthesis
Information about Cell and it's structure and protein synthesis
 
Eie 6 formas jurídicas, versión 97 2003
Eie 6 formas jurídicas, versión 97 2003Eie 6 formas jurídicas, versión 97 2003
Eie 6 formas jurídicas, versión 97 2003
 
7 Tips to Avoid Poor Quality Production
7 Tips to Avoid Poor Quality Production7 Tips to Avoid Poor Quality Production
7 Tips to Avoid Poor Quality Production
 
Tool wear, tool life & machinability
Tool wear, tool life & machinabilityTool wear, tool life & machinability
Tool wear, tool life & machinability
 
Thermographic Nondestructive Testing (NDT)
Thermographic Nondestructive Testing (NDT)Thermographic Nondestructive Testing (NDT)
Thermographic Nondestructive Testing (NDT)
 
Pennsylvania Weatherization Quality Control Inspection Checklist
Pennsylvania Weatherization Quality Control Inspection ChecklistPennsylvania Weatherization Quality Control Inspection Checklist
Pennsylvania Weatherization Quality Control Inspection Checklist
 
Welding visual inspection
Welding visual inspectionWelding visual inspection
Welding visual inspection
 
APQP: Advanced Product/Project Quality Planning
APQP: Advanced Product/Project Quality PlanningAPQP: Advanced Product/Project Quality Planning
APQP: Advanced Product/Project Quality Planning
 
AS 9100:2016 and ISO 9001:2015 - Clause 9.3 Management Review : What's New?
AS 9100:2016 and ISO 9001:2015 - Clause 9.3 Management Review : What's New?AS 9100:2016 and ISO 9001:2015 - Clause 9.3 Management Review : What's New?
AS 9100:2016 and ISO 9001:2015 - Clause 9.3 Management Review : What's New?
 
08 cutting tool_ebook
08 cutting tool_ebook08 cutting tool_ebook
08 cutting tool_ebook
 
Secret cb vol_01
Secret cb vol_01Secret cb vol_01
Secret cb vol_01
 
Well oil seal catalog
Well oil seal catalogWell oil seal catalog
Well oil seal catalog
 
التعليم المبرمج
التعليم المبرمجالتعليم المبرمج
التعليم المبرمج
 
Temel teknik resim
Temel teknik resimTemel teknik resim
Temel teknik resim
 

Semelhante a FIRST ARTICLE INSPECTION

3 Sample Procedures
3 Sample Procedures3 Sample Procedures
3 Sample Procedures
Robert Klemm
 
IATF-Rules-5th-Edition_Sanctioned-Interpretations-Dec-2020.pdf
IATF-Rules-5th-Edition_Sanctioned-Interpretations-Dec-2020.pdfIATF-Rules-5th-Edition_Sanctioned-Interpretations-Dec-2020.pdf
IATF-Rules-5th-Edition_Sanctioned-Interpretations-Dec-2020.pdf
martinusteddy
 
Omnex sac may01
Omnex sac may01Omnex sac may01
Omnex sac may01
Omnex Inc.
 

Semelhante a FIRST ARTICLE INSPECTION (20)

AS9102B Overview.pptx
AS9102B Overview.pptxAS9102B Overview.pptx
AS9102B Overview.pptx
 
Jamco_FAI_Training_Materials_AS9102_Rev_B.pdf
Jamco_FAI_Training_Materials_AS9102_Rev_B.pdfJamco_FAI_Training_Materials_AS9102_Rev_B.pdf
Jamco_FAI_Training_Materials_AS9102_Rev_B.pdf
 
Copy of Basic Quality infromation for maufacturing sector.pdf
Copy of Basic Quality infromation for maufacturing sector.pdfCopy of Basic Quality infromation for maufacturing sector.pdf
Copy of Basic Quality infromation for maufacturing sector.pdf
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013
 
Api q1 6 a monogram-iso audit template- blank
Api q1 6 a monogram-iso audit template- blankApi q1 6 a monogram-iso audit template- blank
Api q1 6 a monogram-iso audit template- blank
 
3 Sample Procedures
3 Sample Procedures3 Sample Procedures
3 Sample Procedures
 
E9._Non-Conformity_Report_NCR.doc
E9._Non-Conformity_Report_NCR.docE9._Non-Conformity_Report_NCR.doc
E9._Non-Conformity_Report_NCR.doc
 
Basic Handover of Bill of Material(2).docx
Basic Handover of Bill of Material(2).docxBasic Handover of Bill of Material(2).docx
Basic Handover of Bill of Material(2).docx
 
Disposition of Defective Materials by Implementing Various Japanese Techniques
Disposition of Defective Materials by Implementing Various Japanese TechniquesDisposition of Defective Materials by Implementing Various Japanese Techniques
Disposition of Defective Materials by Implementing Various Japanese Techniques
 
Quality application
Quality applicationQuality application
Quality application
 
PROCUREMENT
PROCUREMENTPROCUREMENT
PROCUREMENT
 
Rollout
RolloutRollout
Rollout
 
IATF-Rules-5th-Edition_Sanctioned-Interpretations-Dec-2020.pdf
IATF-Rules-5th-Edition_Sanctioned-Interpretations-Dec-2020.pdfIATF-Rules-5th-Edition_Sanctioned-Interpretations-Dec-2020.pdf
IATF-Rules-5th-Edition_Sanctioned-Interpretations-Dec-2020.pdf
 
Ppaptr
PpaptrPpaptr
Ppaptr
 
AIAG_Production_Part_Approval_process_PP.pdf
AIAG_Production_Part_Approval_process_PP.pdfAIAG_Production_Part_Approval_process_PP.pdf
AIAG_Production_Part_Approval_process_PP.pdf
 
AIAG Production Part Approval Process PPAP 4Th Edition
AIAG Production Part Approval Process PPAP 4Th EditionAIAG Production Part Approval Process PPAP 4Th Edition
AIAG Production Part Approval Process PPAP 4Th Edition
 
FS for FICO
FS for FICOFS for FICO
FS for FICO
 
TSE FPA REQUIREMENT.pptx
TSE FPA REQUIREMENT.pptxTSE FPA REQUIREMENT.pptx
TSE FPA REQUIREMENT.pptx
 
Omnex sac may01
Omnex sac may01Omnex sac may01
Omnex sac may01
 
jabil-production-part-approval-process.pdf
jabil-production-part-approval-process.pdfjabil-production-part-approval-process.pdf
jabil-production-part-approval-process.pdf
 

Último

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 

Último (20)

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural ResourcesEnergy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
Energy Resources. ( B. Pharmacy, 1st Year, Sem-II) Natural Resources
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 

FIRST ARTICLE INSPECTION

  • 1. Guide for successful completion of First Article Inspection Reports Company Confidential Rev. Jan 2012 1
  • 2. Introduction • This presentation is intended as supplemental information in support of the 9102 Standard for Aerospace First Article Inspection requirements. • This material should be used in conjunction with the standard. The requirements cited in the standard always take precedent. 2
  • 3. Requirements  First Article Inspection Reports are to be recorded in English or in a language specified by the customer.  AS/EN/SJAC9102 Revision A - Aerospace First Article Inspection Requirement  8.2.4.2 First Article Inspection: The organization’s system shall provide a process for the inspection, verification, and documentation of a representative item from the first production run of a new part, or following any subsequent change that invalidates the previous first article inspection result.  NOTE: USE (AS) (EN) (SJAC) 9102 with this tutorial for requirements 3
  • 4. Requirements  Additional Customer requirements if applicable  AS/EN/SJAC9102 Rev A forms are to be completed in accordance with the Appendix A guide of the standard  Note: If alternate forms are used, they must contain all “Required” and “Conditionally Required” information and have the same field reference numbers as AS/EN/SJAC9102 Rev A 4
  • 5. Definition FIRST ARTICLE INSPECTION (FAI): A complete, independent, and documented physical and functional inspection process to verify that prescribed production methods have produced an acceptable item as specified by engineering drawings, planning, purchase order, engineering specifications, and/or other applicable design documents. Ref 9102 Rev A 5
  • 6. Purpose Provides objective evidence: that all engineering, design and specification requirements, including process and manufacturing validation, are correctly  understood  accounted for  verified  and recorded. of a consistent documentation requirement for aerospace components. 6
  • 7. Evaluation Activities • The organization should conduct the following activities in support of FAI; – Review documentation for the manufacturing process (e.g., routing sheets, manufacturing/quality plans, manufacturing work instructions, etc.) to make sure all operations are complete as planned. – Review referenced exhibits supporting the FAI (e.g., inspection data, test data, Acceptance Test Procedures, etc.) for completeness. – Review nonconformance documentation (if any), for completeness. – Review material certifications for compliance, as applicable.
  • 8. Evaluation Activities – Verify that approved Special Process sources are used (as applicable), and that the manufacturing planning/routing document calls out the correct specification. – Verify that Key Characteristic requirements have been met, as applicable Verify part specific gages and/or tooling are qualified and traceable, as applicable. – Verify that every design characteristic requirement is accounted for, uniquely identified and has inspection results traceable to each unique identifier. – Note the company FAI procedure should address all evaluation activities
  • 9. When should FAI be performed?  Full FAI  New part introduction  New supplier or new location of manufacture  Lapse in production for more than 2 years  When required by the customer  Partial (Delta) FAI  Design change  A change in the method of manufacture (e.g. Tooling, Processes, Machine, Location, Numerical Control Program, Sequence of Manufacture). 9
  • 10. What does it apply to?  All product defined by engineering drawings or model based definitions. Delete-issued by the Customer  Assemblies- for those characteristics specified on the assembly level drawing only  All levels of detail parts within assembly  including castings and forgings  Modified Standard, Electronic or COTS Items as “make from” with unique engineer modifications on drawing Only the modifications 10
  • 11. What does it not apply to? Standard Parts Electronic Components Commercial Off The Shelf (COTS) Items No FAI required 11
  • 12. What is included?  Verification of all design characteristics  Material and Special Process Certifications  Manufacturing Process Verification  Nonconformance resolution 12
  • 13. Forms The Following Forms comprise a First Article Inspection Report (FAIR) full instructions in 9102 appendix A AS9102 A Form 1: Part Number Accountability shall be used to identify the part that is being first article inspected (FAI part) and associated sub-assemblies or detail parts. AS9102 A Form 2: Product Accountability – Raw Material, Specifications and Special Process(s), Functional Testing shall be used if any material, special processes or functional testing are defined as a design requirement. AS9102 A Form 3: Characteristic Accountability, Verification and Compatibility Evaluation shall be used to record an actual measurement or inspection/verification of the FAI part for every design characteristic on the drawing, including notes. 13
  • 14. AS9102 A Form 1 – Part Number Accountability 1. Part Number 2. Part Name 3. Serial Number 4. FAI Report Number 5. Part Revision Level 6. Drawing Number 7. Drawing revision level 8. Additional Changes 9. Manufacturing Process 10. Organization Name 11. Supplier Code 12. P.O. Number Reference 13. Detail FAI 14. Full FAI Baseline Part Number including revision level Partial FAI Assembly FAI Reason for Partial FAI: a) if above part number is a detail part only, go to Field 19 b) if above part number is an assembly, go to the “INDEX” section below. INDEX of part numbers or sub-assembly numbers required to make the assembly noted above. 15. Part Number 16. Part Name 17. Part Serial Number 18. FAI Report Number YELLOW or LIGHT GREY fields – MANDATORY information required. BLUE or DARK GREY fields – CONDITIONALLY REQUIRED. These fields must be completed when information is available. WHITE fields – OPTIONAL information required when available. 1) Signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition. 2) Also indicate if the FAI is complete per Section 5.4: FAI complete FAI not Complete 19. Signature By 20. Date 21. Reviewed By 22. Date 23. Customer Approval 24. Date Form 1, 9102 Rev A, Date: Oct 24, 2003 14
  • 15. AS/EN/SJAC9102 Rev A First Article Inspection AS9102 A Form 1 – Part Number Accountability Sheet 1 of _ Form 1: Part Number Accountability 1. Part Number 2. Part Name 3. Serial Number 4. FAI Report Number 5. Part Revision Level 6. Drawing Number 7. Drawing revision level 8. Additional Changes Box 1. Part Number of the FAI part. Box 2. Name of the part as shown on the drawing. 9. Manufacturing Process 10. Organization Name 11. Supplier Code 12. P.O. Number Reference Box 3. Serial number of the FAI part. Box 4. The Report No. 13. Detail FAI 14. Full FAI Baseline Part Number including revision level Box 5. The revision of the part Partial FAI being first article inspected. Indicate if Assembly FAI therePartial FAI: revision. Reason for is no Note: The latest revision (Box 7) does not always affect all parts contained on a drawing. a) if above part number is a detail part only, go to Field 19 Box 6. ifThe drawing numbersection below. b) above part number is an assembly, go to the “INDEX” associated with the FAI part. (if different from numbers or sub-assembly numbers required to make the assembly noted above. INDEX of part part number) 15. Part Number 16. Part Name 17. Part Serial Number 18. FAI Report Number Box 7. Reference the revision engineering drawing. (if drawing number is different from part number) Box 8. Reference Design, Engineering or Manufacturing changes affecting the FAI part, not reflected by the current part/drawing15 revision level. 15
  • 16. AS9102 A Form 1 – Part Number Accountability 1. Part Number 2. Part Name 3. Serial Number 4. FAI Report Number 5. Part Revision Level 6. Drawing Number 7. Drawing revision level 8. Additional Changes 9. Manufacturing Process 10. Organization Name 11. Supplier Code 12. P.O. Number Reference Box 9. Reference the internal works order. 13. Detail FAI 14. Full FAI Baseline Part Number including revision level Box 10. Name of the organization performing the FAI . Partial FAI Assembly FAI 11. Reference the supplier vendor code. Box Reason for Partial FAI: Box if12.part number is a detail part only, go to Field 19 a) above Reference the customer Purchase Order number. b) if above part number is an assembly, go to the “INDEX” section below. Box 13. Check as appropriate. INDEX of part numbers or sub-assembly numbers required to make the assembly noted above. BoxPart Number 15. 14. Check asPart Name 16. appropriate. Part Serial Partial FAI Report Number 17. For Number 18. FAI provide the baseline drawing number, including issue status and the reason. i.e Change of manufacturing location, Non-Conformance, Process change, Design change etc. 16
  • 17. AS9102 A Form 1 – Part Number Accountability 1. Part Number 2. Part Name 3. Serial Number 4. FAI Report Number 5. Part Revision Level 6. Drawing Number 7. Drawing revision level 8. Additional Changes Boxes 15, 16, 17 and 18 – this section is only required if the Part Number in Box 1. is an Assembly with lower level parts.P.O. Number 9. Manufacturing Process 10. Organization Name 11. Supplier Code 12. Reference Box 15. Reference all lower level parts or next level sub-assembly Part Number. 13. Detail FAI 14. Full FAI Baseline Part Number including revision level Box 16. Part namePartial FAI as shown on the drawing/ parts list. Assembly FAI Reason for Partial FAI: a) if above part number is a detail part only, go to Field 19 b) if above part number is an assembly, go to the “INDEX” section below. INDEX of part numbers or sub-assembly numbers required to make the assembly noted above. 15. Part Number 16. Part Name 17. Part Serial Number 18. FAI Report Number Box 17. Reference the serial number of the part. Box 18. A reference number that identifies the FAI package. 17
  • 18. AS9102 A Form 1 – Part Number Accountability Box 19. The name and signature of the person who prepared the FAI. Box 20. Date when the FAI was prepared. Box 21. The name of the person who reviewed or approved the FAI package. Box 22. Date when the FAI was reviewed. 1) Signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition. 2) Also indicate if the FAI is complete per Section 5.4: FAI complete FAI not Complete 19. Signature By 20. Date 21. Reviewed By 22. Date 23. Customer Approval 24. Date Form 1, 9102 Rev A, Date: Oct 24, 2003 Box 23. Customer Approval. Box 24. Date of Customer approval. 18
  • 19. AS9102 A Form 2 – Product Accountability 1. Part Number 2 Part Name 3. Serial Number 4. FAI Report Number 5. Material or Process 6. Specification 7. Code 8. Special Process 9. Customer 10. Certificate of Name Number Supplier Code Approval Conformance Verification number (Yes/No/NA) Boxes 1 - 4 are repeated on all forms for convenience and traceability. 11. Functional Test 12. Acceptance report number, if applicable Procedure Number 13. Comments 14. Prepared By 15. Date 19
  • 20. AS9102 A Form 2 – Product Accountability 1. Part Number 2 Part Name 3. Serial Number 4. FAI Report Number 5. Material or Process 6. Specification 7. Code 8. Special Process 9. Customer 10. Certificate of Name Number Supplier Code Approval Conformance Verification number (Yes/No/NA) Box 5. Enter the name of the material or process i.e. Aluminium Alloy, Cadmium Plate etc. Box 6. Enter the material or process specification number, class and material form i.e. AMS4928 Bar (Include ‘make from’ materials, weld/ braze filler materials, standard catalogue hardware etc). Box 7. Reference any material code specified. Box 8. Reference Special Process Supplier Vendor code, name & address. Box 9. Indicate if technical approval is required by the customer. Box 10. Reference Certificate of Conformance number(s) e.g. Special Process, Raw material & Mill certifications, Laboratory Reports etc. 20
  • 21. AS9102 A Form 2 – Product Accountability 11. Functional Test 12. Acceptance report number, if applicable Procedure Number Box 11. Reference the Functional Test procedure as stated on the drawing. Box 12. Reference the Functional Test report. 13. Comments 14. Prepared By 15. Date Box 13. Comments – As applicable. Box 14. The name of the person who prepared this form. Box 15. Date when this form was completed. 21
  • 22. Ballooned Drawings  A ballooned drawing is optional and considered an industry best practice to support Box 5 of Form 3  Identify 100% of characteristics  Balloon and number all dimensions  Balloon and number all surface finish callouts  Including exclusion and inclusion area callouts  Balloon and number all material and hardness callouts  Don’t forget the requirements identified in the title boxes at the bottom of the drawings. 22
  • 23. BALLOONED Note 2 DRAWINGS 1 2 3 8 4 7 5 6 Note: In this example not all characteristics ballooned 23
  • 24. AS9102 A Form 3 – Characteristic Accountability, Verification and Compatibility Evaluation 1. Part Number 2. Part Name 3. Serial Number 4. FAI Report Characteristic Accountability Inspection / Test Results Optional 5. 6. 7. Characteristic 8. 9. 10. 11. 14. Char Reference Designator Requirement Results Designed Non- [Insert columns, etc., as required by No. Location Tooling Conformance Organization or Customer} Number Boxes 1 - 4 are repeated on all forms for convenience and traceability. The signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition. 12. Prepared By 13. Date 24
  • 25. AS9102 A Form 3 – Characteristic Accountability, Verification and Compatibility Evaluation 1. Part Number 2. Part Name 3. Serial Number 4. FAI Report Characteristic Accountability Inspection / Test Results Optio 5. 6. 7. Characteristic 8. 9. 10. 11. 14. Char Reference Designator Requirement Results Designed Non- {Insert columns, etc. as required by Organization No. Location Tooling Conformance or Customer} Number Box 5. Assign a unique number for each design Box 6. Reference the drawing zone Box 7. Reference any zoned characteristics i.e. Key characteristic. (include Sheet No. and Zone). These are to be traceable Critical Characteristic, etc. Characteristics, Safety to each drawing requirement. The signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition. 12. Prepared By 13. Date 25
  • 26. AS9102 A Form 3 – Characteristic Accountability, Verification and Compatibility Evaluation 1. Part Number 2. Part Name 3. Serial Number 4. FAI Report Characteristic Accountability Inspection / Test Results Opt 5. 6. 7. Characteristic 8. 9. 10. 11. 14. Char Reference Designator Requirement Results Designed Non- {Insert columns, etc. as required by Organization No. Location Tooling Conformance or Customer} Number Box 9. Indicate measurements specified for each designof specially Box 10. Record the tool identification number characteristic. Box 8. Indicate the obtained a media of inspection. designed tooling used as requirement for thenumber if any design Box 11. Record non-conformance be features reference values. Multiple characteristics shall document with minimum and i.e. Dimensional listed as individual characteristicRecord any addition information required. Box 14. maximum value of tolerance, foundaccountedSpecification design characteristicmust be non-conforming. All drawing notes is Drawing notes, for. requirements etc. Processes that require design verification must have statement of compliance recorded on the form i.e. Certification of Compliance – state ‘Accept’. Laboratory reports or Certificate of test must show specific values for requirements and actual results. The signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition. 12. Prepared By 13. Date 26
  • 27. AS9102 A Form 3 – Characteristic Accountability, Verification and Compatibility Evaluation 1. Part Number 2. Part Name 3. Serial Number 4. FAI Report Characteristic Accountability Inspection / Test Results Optio 5. 6. 7. Characteristic 8. 9. 10. 11. 14. Char Reference Designator Requirement Results Designed Non- [Insert columns, etc., as required by Organization No. Location Tooling Conformance or Customer] Number Box 12. Name of the person who prepared this form. Box 13. Date when this form was completed. The signature indicates that all characteristics are accounted for; meet drawing requirements or are properly documented for disposition. 12. Prepared By 13. Date 27
  • 28. Forms Link AS9102 A forms can be downloaded at: www.sae.org/aaqg/publications/as9102a-faq.htm 9102 FAQ Link www.sae.org/iaqg/publications/faq9102.htm 28
  • 29. Most Common Reasons for FAI Rejection C of Cs do not accompany the FAI Report. Missing FAI Reports or Test Reports for sub-assemblies and/or fabricated detail parts. Variable data requirements from the engineering drawing are not provided with numerical results. Missing or wrong information provided. Missing special processor full address on AS9102 A Form 2, box 8. Missing tolerances on AS9102 A Form 3, box 8. Customer flow down requirements not met. 29